1 PUB (WRN) CCTV Inspection Requirements for Sewers and Manholes 1. PUB WRN Planning Division shall provide to QP the PUB s Geographic Information System (GIS) sewer IDs, the length of sewer(s), manhole IDs, the depth of manhole(s) and the year of commission of the sewer(s) and manhole(s). These IDs must be included in the CCTV inspection reports, JPEG photographs and MPEG/AVI videos. 2. For all CCTV inspections, both sewers and the adjoining manholes must be inspected and their condition assessment documented per the CCTV Inspection Requirements prescribed in this document in particular the submissions formats shown in Appendix A and B. Submissions which are not in accordance with the format will be deemed as non-compliant, incomplete and will be rejected. 3. All description of defects, findings and abnormalities shall be in full. Defects classification shall be in accordance with the WRc/WAA "Manual of Sewer Condition Classification" 4 th Edition or prevalent edition. Photographic evidence of each defect must be taken and included in the CCTV Inspection Report. Guidance notes on WRc defect classification is provided in Appendix C. Please refer for the complete WRc/WAA manual. 4. From 1 Jan 213, PUB only accepts CCTV inspection and reports from PUB Registered CCTV contractors. The list of latest PUB registered CCTV contractors is available in our website, 5. Prior to CCTV inspection, hydraulic cleaning of sewer(s) and manhole(s) must be carried out to assess their condition with an unobstructed view of their surfaces. 6. CCTV inspection of all sewers must cover the entire pipe length and should be carried out during low flow period (ideally water level should be less than 3% of the pipe diameter) for adequate viewing of the sewer condition. 7. If sewer is found be unable to be inspected due to surcharge condition even after the hydraulic cleaning. QP shall consult PUB (WRN), Network Management Branch for assistance. QP may contact the PUB (WRN), Network Management Branch via the PUB ONE Hotline at CCTV Inspection Video Recording for sewer(s) and manhole(s) 8. The positioning of the CCTV camera lens shall be in a stable condition and above the liquid flow line near the central axis of the sewer(s) and manhole(s). The speed of the CCTV unit in the sewer(s) and manhole(s) shall be limited to.2 m/s to enable all details to be extracted from the video recording. 9. QP shall ensure that all CCTV videos recording shall be of high quality recording and in a stable condition. During televising, the illumination must be adequate to provide an accurate and clear record of the entire sewer s and manhole s internal condition. As a minimum, the quality of the photos and video should be equivalent to the photos shown in Appendix A and B. 1. All documents including recordings should be submitted in DVD discs and no tape media will be accepted. 1-6 Ver 2. (Dec12)

2 11. Submission format of video and photos should be in MPEG/AVI and JPEG format respectively. 12. Each individual entire length pipe between manhole to manhole must be included in a single MPEG/AVI video file, except if a reverse set up is required due to an obstruction, in which case the reverse inspection shall be contained in a separate file. 13. Each individual manhole must be included in a separate MPEG/AVI video file. 14. At the start of each pipe length being inspected, the length of pipeline from zero chainage up to the cable calibration point shall be recorded and reported in order to obtain a full record of the pipe length. The meter reading entered on to the data display at the cable calibration point must allow for the distance from the start of the survey/inspection to the cable calibration point such that the chainage at the start of the survey is zero. The running footage display shall be consistence with the actual distance of the pipe from the start of the pipe length. (i) At the start of each sewer pipe length, a data generator shall electronically generate and clearly display on the viewing monitor and video recording a record of data in alphanumeric form containing the following minimum information: Project Reference Number Type of Survey: Pre-Con / Post Con / Before DLP / End DLP Sewer GIS ID Upstream and downstream manhole GIS IDs Sewer pipe diameter Sewer pipe material Direction of unit travel Road name/location Date and time of survey CCTV company name Upstream and downstream (or from and to ) manhole GIS numbers of inspected pipe segment Automatic update of the unit's chainage position in the pipeline from adjusted zero The text should be clearly displayed on a contrasting background for approximately 15 seconds. If the CCTV inspection is being performed on consecutive pipe segments with the same setup, this text information must be provided at the start of each pipe segment and the separate pipe segment will have to be saved in separate MPEG/AVI video file. (ii) During CCTV inspection, the running screen must include the following information. The display of this information must in no way obscure the central focus of the pipe being inspected. 2-6 Ver 2. (Dec12)

3 Project Reference Number Type of Survey: Pre-Con / Post Con / Before DLP / End DLP Sewer GIS ID Upstream and downstream manhole GIS IDs Sewer pipe diameter Sewer pipe material Direction of unit travel Road name/location Date and time of survey Upstream and downstream (or from and to ) manhole GIS numbers of inspected pipe segment Running footage (distance travelled) (iii) At the end of CCTV inspection of the inspected pipe segment, the ending screen text should indicate: Project Reference Number Type of Survey: Pre-Con / Post Con / Before DLP / End DLP Sewer GIS ID Upstream and downstream manhole GIS IDs Sewer pipe diameter Sewer pipe material Direction of unit travel Road name/location Date and time of survey Upstream and downstream (or from and to ) manhole GIS numbers of inspected pipe segment Ending footage The text should be clearly displayed on a contrasting background for approximately 15 seconds. 15. The video shall be free of all electrical interference and excessive background noise. Digital video recording playback shall be at the same speed that it was recorded. 16. The CCTV survey inspection shall include: (i) (ii) Preparation Prior to Inspection. Pipelines/manholes/inspection chambers to be inspected shall be hydraulically cleaned to assess their conditions with an unobstructed view of their surfaces over the complete pipe length. The pipelines and manholes shall be cleaned to enable existing cracks and corrosion to be clearly recorded on video printouts. Sequence of CCTV Inspection. After cleaning, both the sewers and the adjoining the adjoining manhole shall be visually inspected by means of CCTV camera system. The inspection will be done one manhole-to-manhole pipe section at a time. Each series of runs shall be recorded on a separate file. (iii) Direction of CCTV. The direction of unit travel shall be in the direction of flow in the pipe unless access to the upstream manhole is not possible or the unit cannot pass through the pipe from the end-to-end in the direction of flow, in which case a reverse setup will be allowed. In this case, this shall highlight the 3-6 Ver 2. (Dec12)

4 detailed issue in the CCTV inspection report. (iv) (v) Manhole condition assessment. CCTV inspection shall be carried out to all the manholes adjoining to the inspected sewers. All observations and findings shall be highlighted on the separate Manhole Inspection Report. Manhole inspection shall include (but not limited to) the following structural defects:- (1) Damage manhole frames and/or covers (including rocking manholes) (2) Signs of inflow/infiltration/exfiltration from the manhole walls (3) Damage benching QP shall re-clean and re-cctv survey inspection the sewerage pipe if the view of the televised sewer(s) and manhole(s) is obstructed and/or not clear. (vi) Camera Selection Sewerage pipes of sizes up to 45mm (inclusive) shall require CCTV unit with pan and tilt facilities. For sewer(s) more than 45mm diameter, CCTV unit with pan, tilt and zoom facilities shall be used to allow clear interpretation of all defects and its severity. Documents to be submitted to PUB(WRN) and submission Format 17. Upon the completion of each and every required survey inspection work, the results obtained from the CCTV survey of the sewer line(s) and the adjoining manhole(s) are to be incorporated into the CCTV Inspection Report. 18. QP shall submit all the following items to the PUB (WRN), Network Management Branch: (i) Hardcopy of computer generated (not hand-written) CCTV Survey Inspection Report on condition of each sewer segment inspected between manholes shall be reported in accordance with the sample format (shown in Appendix A). This report shall contain an overall plan of the pipeline(s) and manhole(s) inspected during the period, structural assessment and a summary of the findings. The sewer report shall be labelled as: Sewer GIS ID-mmddyy-C-Project Ref no.- PreCon / Post Con / Before DLP / End DLP Naming Convention Sewer GIS ID Mmddyy C Project Ref no. Pre-Con / Post Con / Before DLP / End DLP Description Sewer GIS ID being inspected Date of CCTV inspection CCTV inspection Project reference number Select the type of survey (ii) Hardcopy of computer generated CCTV Survey Inspection Report on condition of each manhole inspected shall be reported in accordance with the sample format (shown in Appendix B). This report shall contain an overall plan of the manhole inspected during the period, structural assessment and a summary of the findings. 4-6 Ver 2. (Dec12)

5 The manhole report shall be labelled as: Manhole GIS ID-mmddyy-C-Project Ref no.- Pre-Con / Post Con / Before DLP / End DLP Naming Convention Manhole GIS ID Mmddyy C Project Ref no. Pre-Con / Post Con / Before DLP / End DLP Description Manhole GIS ID being inspected Date of CCTV inspection CCTV inspection Project reference number Select the type of survey (iii) A DVD disc containing the softcopy of CCTV survey inspection reports (in PDF format) and CCTV videos. The top face of the DVD media shall be labelled-printed (Sewer GIS IDs-mmddyy-streetname-Project Ref no.-pre-con / Post Con / Before DLP / End DLP). Each sewer and manhole shall be saved in the respective individual folders. The naming convention for each folder (sewer and manhole) and the corresponding CCTV survey inspection report and video is shown below: (a) Each sewer segment should be saved in individual folder. Naming convention is as follows: Sewer Folder (Folder Name: Sewer GIS ID-mmddyy-C-Project Ref no.) (i) A PDF softcopy of the CCTV Inspection Report of the sewer segment. Save CCTV report as: Sewer GIS ID-mmddyy-C-Project Ref no.-pre-con / Post Con / Before DLP / End DLP.pdf (ii) Sewer CCTV survey video in MPEG/AVI format Save as: Sewer GIS ID-mmddyy-C-Project Ref no.-pre-con / Post Con / Before DLP / End DLP.mpeg or avi (b) Each manhole should be saved in individual folder. Naming convention is as follows: Manhole Folder (Folder Name: Manhole GIS ID-mmddyy- Project Ref no.) (i) A PDF softcopy the CCTV Inspection Report of the manhole inspected. Save CCTV report as: Manhole GIS ID-mmddyy-Project Ref no.-pre-con / Post Con / Before DLP / End DLP.pdf (ii) Manhole CCTV survey video in MPEG/AVI format Save as: Manhole GIS ID-mmddyy-Project Ref no.-pre-con / Post Con / Before DLP / End DLP.mpeg or avi 19. Any errors in recording, CCTV imagery, unclear video printouts and/or error in interpretation of the sewer(s) and/or manhole(s) defect, shall be rejected. CCTV SURVEY - VIDEO PRINTOUTS FOR HARDCOPY REPORT SUBMISSIONS 2. QP shall ensure that all video printouts shall be of high quality colour video printing and must clearly shows details and accurately reflect what is displayed from the 5-6 Ver 2. (Dec12)

6 monitor. The minimum size of the video prints shall be 1mm x 75mm. The photographic evidence (Video prints) of defects and abnormalities must be included in the CCTV Inspection Report. 21. Video prints shall be taken in the event of the following observation and findings: (i) (ii) (iii) (iv) Photographic evidence (video prints) shall be taken for all suspected defects. That is sewer pipes fractures, broken, collapse, deformation, displaced, sunken, pipes with sever joint displacement and abnormalities, sewer Liners suffering from peeling, deformation, bulging, broken, collapse etc and abnormalities, lateral openings where there is accumulation of debris at particular localized spots etc that the CCTV specialist comes across during the CCTV assessment. Where video prints are not otherwise required for a generally well maintained sewer (i.e. no evidence of defects or abnormalities etc) then video prints shall be taken for every and successive 15m interval of a sewer segment inspected, a general condition video print shall be taken (allows one to determine the changes of sediments level etc over the entire length of sewer inspected). To illustrate degree of mortar loss, size of a crack or facture, size of a void or any other quantifiable defect and a suitable metric scale shall be included in the clearly focus video printout. Where a video printout is taken to illustrate a specific defect, it shall occupy the central part of the video printout and be clearly in focus and accurately reflect the defect. QP shall ensure that all submissions of all videos and photographs are of good clarity. All defects including obstructions and abnormalities on junctions, connections, manholes and pipeline. Where a defect is continuous or repeated, the video printouts shall be taken at the beginning of the defect and at not less than 5m intervals thereafter. 22. If not clearly shown in the CCTV report submission, the PUB (WRN) may instruct the QP to provide additional CCTV video printouts at locations of defects and other locations of significant interest, the number of which is expected to be minimal. 23. QP shall ensure all printed video printouts shall be clearly identified and systematically annotated in relation to the following: (i) Sewer and manhole GIS IDs (ii) Date & Time of the inspection (iii) Chainage defect (iv) Type of Defect (v) Defect code The annotation shall be clearly visible and in contrast to its background, shall have a figure size no greater than 5mm, and be type printed. The annotation shall be positioned so as not to interfere with the subject of the video printout. 6-6 Ver 2. (Dec12)

7 Table of Contents Profile Report 1 Inspection: Sewer 1981 Legend of Classification 2 Section: 1 3

8 Project Reference No.: A Pre-Con / Main sections No. Upstream MH Downstream MH Date Road DVD No. Material SIP Length CCTV Length /5/29 Dalvey Estate 559 Vitrified clay m 75.9 Pipe size: 3 = 75.9 m (75.9 m) All sections = 75.9 m (75.9 m) CCTV - Dalvey Estate // Page: 1

9 Project Reference No.: A Defect Grade Description / Inspection: Sewer ID : No Structural Defects Pre-Con Acceptable Structural Condition 2: Circumfrential crack, Moderate joint defects, Spalling slight, Wear slight Minor collapse risk in short term but potential for further deterioration 3: Fractures with deformation up tp 5%, Longitudinal cracking or mulitlpe cracking, Minor loss of level, More severe joint defects, Spalling medium, Wear medium! Collapse unlikely in near future but future deterioration likely! 4: Broken, Deformation up to 1% and broken,, Fractured with deformation 5-1%, Multiple fractures, Serious loss of level, spalling large, wear large!! Collapse likely in foreseeable future!! 5: Already collapsed, Deformation over 1% and broken, Extensive areas of fabric missing, Fractured with deformation over 1%!!! Collapsed or collapse imminent!!! CCTV - Dalvey Estate // Page: 2

10 Sewer CCTV Inspection Report / Inspection: Sewer ID 1981 Survey Date : Type of Survey: Year Commissioned : Sewer GIS-ID : Operator : Team Supervisor : 5/5/29 Pre-Con G. Karthikeyan G. Karthikeyan Start Time : Weather : Camera : Full Segment CCTV : Cleaned : WRC Certified : 14:24: Dry IBAK Argus 5 Yes Yes Jhon Feliciano Road : Dalvey Estate Project Reference No : A US MH GIS-ID : Place : Bukit Timah DS MH GIS-ID: Location Details: Near Block No. 28 SIP Length : Location Code: Road CCTV Length : Grease Found (N/M/H) : Nil Purpose : Direction of Survey : Downstream Pipe Size (mm): Water Level (US) : 1% Pipe Material : Water Level (DS) : 1% Lining : Comment : m 75.9 m To assess pipe condition 3 mm Vitrified clay N/A CCTV inspection found the entire sewer pipeline is structurally sound and has no defect. 1:378 Position Code Observation Video Photo Grade Depth: 5.3 / Cover level: N ST Start of survey, downstream direction : V1P1-C.jpg.1 GP General photograph reference 2 : V1P2-C.jpg 4.7 GP General photograph reference 3 1: V1P3-C.jpg 9.8 GP General photograph reference 4 2: V1P4-C.jpg 15.8 GP General photograph reference 5 4: V1P5-C.jpg 19.9 GP General photograph reference 6 4: V1P6-C.jpg 25. GP General photograph reference 7 5: V1P7-C.jpg 3.8 GP General photograph reference 8 6: V1P8-C.jpg 36.1 GP General photograph reference 9 7: V1P9-C.jpg 4.9 GP General photograph reference 1 7: V1P1-C.jp g 45.1 GP General photograph reference 11 8: V1P11-C.jp g CCTV - Dalvey Estate // Page: 3

11 Inspection Report / Inspection: Sewer ID 1981 Date : Type of Survey: Year Commissioned : Sewer GIS-ID : Operator : Team Supervisor : 5/5/29 Pre-Con G. Karthikeyan G. Karthikeyan Start Time : Weather : Camera : Full Segment CCTV : Cleaned : WRC Certified : 14:24: Dry IBAK Argus 5 Yes Yes Jhon Feliciano 1:378 Position Code Observation Video Photo Grade 5.1 GP General photograph reference 12 8: V1P12-C.jp g 55.2 GP General photograph reference 13 9: V1P13-C.jp g 6.3 GP General photograph reference 14 1: V1P14-C.jp g 65.3 GP General photograph reference 15 1: V1P15-C.jp g 7.3 GP General photograph reference 16 11: V1P16-C.jp g 75. GP General photograph reference 17 13: V1P17-C.jp g FH Finish Survey 15: V1P18-C.jp Depth: 5.6 / Cover level: P g STR no def STR peak STR mean STR total STR grade SER no def SER peak SER mean SER total SER grade 1 1 CCTV - Dalvey Estate // Page: 4

12 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P1-C.jpg m, Start of survey, downstream direction Photo: P2-C.jpg.1m, General photograph reference 2 CCTV - Dalvey Estate // Page: 5

13 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P3-C.jpg 4.7m, General photograph reference 3 Photo: P4-C.jpg 9.8m, General photograph reference 4 CCTV - Dalvey Estate // Page: 6

14 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 2. IBAK Argus 5 G. Karthikeyan Photo: P5-C.jpg 15.8m, General photograph reference 5 Photo: P6-C.jpg 19.9m, General photograph reference 6 CCTV - Dalvey Estate // Page: 7

15 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P7-C.jpg 25m, General photograph reference 7 Photo: P8-C.jpg 3.8m, General photograph reference 8 CCTV - Dalvey Estate // Page: 8

16 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P9-C.jpg 36.1m, General photograph reference 9 Photo: P1-C.jpg 4.9m, General photograph reference 1 CCTV - Dalvey Estate // Page: 9

17 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P11-C.jpg 45.1m, General photograph reference 11 Photo: P12-C.jpg 5.1m, General photograph reference 12 CCTV - Dalvey Estate // Page: 1

18 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P13-C.jpg 55.2m, General photograph reference 13 Photo: P14-C.jpg 6.3m, General photograph reference 14 CCTV - Dalvey Estate // Page: 11

19 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P15-C.jpg 65.3m, General photograph reference 15 Photo: P16-C.jpg 7.3m, General photograph reference 16 CCTV - Dalvey Estate // Page: 12

20 Inspection pictures / Inspection: Sewer ID 1981 Place : Road : Date : Camera : Operator : Bukit Timah Dalvey Estate 5/5/29 IBAK Argus 5 G. Karthikeyan Photo: P17-C.jpg 75m, General photograph reference 17 Photo: P18-C.jpg 75.9m, Finish Survey CCTV - Dalvey Estate // Page: 13

21 Manhole Report / Inspection: Manhole ID Survey Date : Type of Survey : Weather : Manhole GIS-ID: Operator. : Team Supervisor : 4/13/29 Pre-Con Dry Andrew Chan Start Time : Yr. Commission: Camera : WRc Certified : Cleaned: 16:: 1968 IBAK Orion Street : Tampines Ind Ave. 5 Chamber Size: 195 Cover Size : Road : Tampines Material: Concrete Material : loc. Details : Outside the factory Shape: circular Shape : Location Code: Turf Cover Good Condition Frame Good Condition : Water Level : 2% SIP Depth : Channel Level : Yes CCTV Depth : Remarks : Yes Yes Cast Iron Double Triangular CCTV inspection found the entire manhole shaft, benchings and inverts including manhole cover and frame are in good condition. No. OP Pos Observation NO_Cl NO_Cl NO_Q Grade Remark ass1 ass2 uant1 1 GP. General Photograph, Manhole Surrounding Location 1 Good condition 2 GP. General Photograph, Manhole Cover 1 Good condition 3 GP. General Photograph, Shaft & Frame 1 Good condition 4 GP.2 General Photograph, Chamber Well 1 Good condition 5 GP 2.2 General Photograph, Chamber Well 1 Good condition 6 GP 4.1 General Photograph, Backdrop 1 Good condition 7 GP 5. General Photograph, Manhole Benching 1 Good condition 8 GP 5.8 General Photograph, Outgoing pipe 9 GP 5.8 General Photograph, Manhole Invert 1 GP 5.8 General Photograph, Incoming pipe 1 Good condition 1 Good condition 1 Good condition Coverplates No. Type Cover Shape Material Breadth/Widt Ground Invert Class MH-ID h [mm]/width Level Level 1 Heavy Duty Double Triangular Cast iron In- No. /outlets o' clock Type Shape Diameter/W Depth Material From MH To MH Water Level Channel Observation idth (mm)/wto invert 1 12 in circular Concrete % No Defect 2 6 out circular Concrete % No Defect Tampines Ind Ave5-C // Page: 1

22 Appendix B Manhole Pictures / Inspection: Manhole ID Survey Date : 4/13/29 Start Time : 16:: Type of Survey : Pre-Con Yr. Commission: 1968 Weather : Dry Camera : IBAK Orion Manhole GIS-ID : WRc Certified : Andrew Chan MH Photo: P1-C.JPG General Photograph, Manhole Surrounding Location MH Photo: P2-C.JPG General Photograph, Manhole Cover Tampines Ind Ave5-C // Page: 2 Operator : Andrew Chan Team Supervisor : Andrew Chan Cleaned : Yes

23 Manhole Pictures / Inspection: Manhole ID Survey Date : Job Number : Weather : Manhole GIS-ID : Operator : Team Supervisor : 4/13/ /EM3 Dry Andrew Chan Start Time : Yr. Commission: Camera : WRc Certified : Cleaned : 16:3: 1968 Andrew Chan Yes Photo: P3-C.JPG General Photograph, Shaft & Frame Photo: P4-C.JPG General Photograph, Chamber Wall Tampines Ind Ave5-C // Page: 3

24 Manhole Pictures / Inspection: Manhole ID Survey Date : Type of Survey : Weather : Manhole GIS-ID : Operator : Team Supervisor : 4/13/29 Pre-Con Dry Andrew Chan Start Time : Yr. Commission: Camera : WRc Certified : Cleaned : 16:: 1968 Andrew Chan Yes Photo: P5-C.JPG General Photograph, Chamber Wall Photo: P6-C.JPG General Photograph, backdrop Tampines Ind Ave5-C // Page: 4

25 Manhole Pictures / Inspection: Manhole ID Survey Date : Type of Survey : Weather : Manhole GIS-ID : Operator : Team Supervisor : 4/13/29 Dry Andrew Chan Start Time : Yr. Commission: Camera : WRc Certified : Cleaned : 16:: 1968 Andrew Chan Yes Photo: P7-C.JPG General Photograph, Manhole Benching Photo: P8-C.JPG General Photograph, Outgoing pipe Tampines Ind Ave5-C // Page: 5

26 Manhole Pictures / Inspection: Manhole ID Survey Date : Type of Survey : Weather : Manhole GIS-ID : Operator : Team Supervisor : 4/13/29 Pre-Con Dry Andrew Chan Start Time : Yr. Commission: Camera : WRc Certified : Cleaned : 16:: 1968 Yes Photo: P9-C.JPG General Photograph, Manhole Invert Photo: P1-C.JPG General Photograph, Incoming pipe Tampines Ind Ave5-C // Page: 6

27 Appendix C - Pg 1/5 GRADING OF INTERNAL CONDITION OF PIPE GRADE INTERNAL CONDITION TYPICAL DEFECT DESCRIPTIONS 5 Already collapsed Deformation >1% and broken Extensive areas of fabric missing Fracture with deformation >1% 4 Broken Deformation up to 1% and broken Fracture with deformation 5-1% Multiple fracture Serious loss of level Spalling large Wear large 3 Fracture with deformation <5% Longitudinal cracking or multiple cracking Minor loss of level More severe joint defects, I.e. open joint (large) or joint displaced (large) Spalling medium Wear medium 2 Circumferential crack Moderate joint defects, I.e. open joint (medium) or joint displaced (medium) Spalling slight Wear slight No structural defects 1 Grade Implication 5 Collapsed or collapse imminent 4 Collapse likely in foreseeable future 3 Collapse unlikely in near future but further deterioration likely 2 Minimum collapse risk in short term but potential for further deterioration 1 Acceptable structural condition The worst defect along the individual sewer length is used to give a single condition grade for that particular sewer length, i.e. the grade for the sewer length is based on the highest internal condition grade along the sewer length.

28 Appendix C - Pg 2/5 STANDARD CCTV CODING FORM CONDITION CODES, WRC NB. Any code with a J at the end ie CCJ refers to a defect that occurs within the area of a joint in the pipe. TYPE CODE DESCRIPTION PIPE CL CRACKED - LONGITUDINAL CC CRACKED - CIRCUMFERENTIAL CM CRACKED - MULTIPLE FL FRACTURE - LONGITUDINAL FC FRACTURE - CICUMFERENTIAL FM FRACTURE - MULTIPLE B BREAK D DEFORMED X COLLAPSED JDS JOINT DISPLACED - SLIGHT JDM JOINT DISPLACED - MEDIUM JDL JOINT DISPLACED - LARGE OJS OPEN JOINT - SLIGHT OJM OPEN JOINT - MEDIUM OJL OPEN JOINT - LARGE SS SURFACE DAMAGE - SPALLING SW SURFACE DAMAGE WEAR BRICK MS MORTAR MISSING - SURFACE MM MORTAR MISSING - MEDIUM MT MORTAR MISSING - TOTAL DB DISPLACED BRICK MB MISSING BRICKS DV DEFORMED VERTICALLY DH DEFORMED HORIZONTALLY DI DROPPED INVERT SERVICE RF ROOTS - FINE CONDITION RM ROOTS - MASS RT ROOTS - TAP IS INFILTRATION - SEEPER ID INFILTRATION - DRIPPER IR INFILTRATION - RUNNER IG INFILTRATION - GUSHER EH ENCRUSTATION - HEAVY EM ENCRUSTATION - MEDIUM EL ENCRUSTATION - LIGHT ESH SCALE - HEAVY ESM SCALE - MEDIUM ESL SCALE - LIGHT DE DEBRIS DES DEBRIS - SILT DEG DEBRIS - GREASE OB OBSTRUCTION WL WATER LEVEL LL LINE OF SEWER DEVIATES LEFT LR LINE OF SEWER DEVIATES RIGHT LU LINE OF SEWER DEVIATES UP LD LINE OF SEWER DEVIATES DOWN

29 Appendix C - Pg 3/5 STANDARD CCTV CODING FORM CONDITION CODES, WRC (Continued) TYPE CODE DESCRIPTION CONSTRUCTION JN JUNCTION X DEFECTIVE JUNCTION CN CONNECTION CNI CONNECTION INTRUDING CX DEFECTIVE CONNECTION CXI DEFECTIVE CONNECTION INTRUDING MH MANHOLE MISCELLANEOUS ST START OF SEWER SURVEY LENGTH FH FINISH OF SEWER SURVEY LENGTH SA SURVEY ABANDONED DC DIMENSION OF SEWER CHANGES LC SEWER LINING CHANGES MC MATERIAL CHANGE SC SHAPE CHANGE PC PIPE LENGTH CHANGE V VERMIN (RATS OR MICE) GP GENERAL PHOTOGRAPH CU CAMERA UNDER WATER LL LINE OF SEWER DEVIATES LEFT LR LINE OF SEWER DEVIATES RIGHT LU LINE OF SEWER DEVIATES UP LD LINE OF SEWER DEVIATES DOWN CONSTRUCTION JN JUNCTION FEATURE JX DEFECTIVE JUNCTION CN CONNECTION CNI CONNECTION INTRUDING CX DEFECTIVE CONNECTION CXI DEFECTIVE CONNECTION INTRUDING MH MANHOLE

30 Appendix C - Pg 4/5 STANDARD CCTV CODING FORM GENERAL - HEADER FIELDS NAME CODE DESCRIPTION PIPING USE D Downstream U Upstream PIPING SHAPE A Arched B Barrel C Circular E Egg Shaped H Horseshoe O Oval R Rectangular S Square T Trapezoidal U U-shaped with flat top X Other PIPING MATERIAL AK Alkathene AC Asbestos Cement BR Brick CI Cast Iron SI Spun Iron CO Concrete CSB Concrete Segments Bolted CSU Concrete Segments Unbolted CC Concrete Box Culvert DI Ductile Iron GRC Glass Reinforced Cement GRP Glass Reinforced Plastic PSC Plastic/Steel Composite PVC Polyvinyl chloride PE Polyethelene RC Reinforced Concrete RPM Reinforced Plastic Matrix ST Steel VC Vitrified Clay PP Polypropolene PF Pitch Fibre MAC Masonry in random courses XXX Other ZZZ Not Known PIPING LINING SSW Steel Reinforced Spiral Wound PVC GRP Glassfiber Reinforced Plastic EPX Epoxy Resin POL Polyester Resin XXX Other ZZZ Not Known

31 Appendix C - Pg 5/5 STANDARD CCTV CODING FORM GENERAL - HEADER FIELDS (Continued) NAME CODE DESCRIPTION PURPOSE A Adhoc inspection - related to structural or service condition defects B Adhoc inspection - related to blockage D Pre-Condition Existing Sewer inspection E Post-Condition Existing Sewer inspection F Before DLP - New Sewer inspection G End DLP - New Sewer inspection H Scheduled planning - inspection I Associated with future capital scheme J Resurvey for any reason X Other WEATHER 1 Dry 2 Heavy Rain 3 Light Rain 4 Showers LOCATION A On Road - General B On Road - Junction C On Road Expressway/Highway D Inside building/covered car-park E Footpath/Pavement F Fields/Turf G Gardens/Backyard (within private property) H Kitchen (within private property) I Inside heavy vegetation

Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers

Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers These guidelines outline inspection, reporting and acceptance requirements for newly constructed rigid and flexible

More information

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High

More information

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing CCTV INSPECTION OF SEWER LINES PART 1 GENERAL 1.1 SECTION INCLUDES A. CCTV Inspections 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02731 Sanitary Gravity Sewer Line Testing

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

Manhole Assessment. Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP)

Manhole Assessment. Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP) Manhole Assessment Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP) Ted DeBoda, PE NASSCO Executive Director Outline NASSCO Defects and Observations

More information

CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) 1. Scope of Work SS7-1

CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) 1. Scope of Work SS7-1 CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) INDEX PAGE 1. Scope of Work SS7-1 2. Contractor Certification SS7-1 3. Flushing

More information

STANDARD OPERATING INSTRUCTION SOI-GVW-198 CCTV Inspection of Sewerage Reticulation Works 1 PURPOSE 2 REFERENCES 3 DEFINITIONS

STANDARD OPERATING INSTRUCTION SOI-GVW-198 CCTV Inspection of Sewerage Reticulation Works 1 PURPOSE 2 REFERENCES 3 DEFINITIONS 1 PURPOSE The purpose of this SOI is to provide instruction and guidance for closed circuit television survey (CCTV) inspection, which the Corporation requires to be undertaken by the constructor as part

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, insurance, accessories, tools, transportation, supplies,

More information

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development

Greater Dublin Strategic Drainage Study Regional Drainage Policies - Volume 2 New Development 7 SPECIFICATIONS There is currently no Irish specification for construction of drainage works, or water supply works. There are several publications that give guidance on drainage works, such as the Building

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

IS THAT LINER THICK ENOUGH?

IS THAT LINER THICK ENOUGH? IS THAT LINER THICK ENOUGH? Philip McFarlane, Opus International Consultants Ltd ABSTRACT The amount of pipeline rehabilitation being undertaken in New Zealand is increasing each year. Larger diameter

More information

SECTION 724 PIPE CULVERTS

SECTION 724 PIPE CULVERTS SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

Using Frequent Sewer Inspection to Prioritize Asset Management. May 1, 2014. John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E.

Using Frequent Sewer Inspection to Prioritize Asset Management. May 1, 2014. John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E. Using Frequent Sewer Inspection to Prioritize Asset Management May 1, 2014 John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E. Agenda Rationale and Goals for Sewer Re-inspection How and why

More information

Module 3: Sewer Material Lecture 3: Sewer Material

Module 3: Sewer Material Lecture 3: Sewer Material Module 3: Sewer Material Lecture 3: Sewer Material [NPTEL, IIT Kharagpur, Prof. M.M.Ghangrekar, Department of Civil Engineering Page 1 3.0 SEWER MATERIAL 3.1 Important Factors Considered for Selecting

More information

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS PURPOSE AND SCOPE This document provides information and sets forth standards for sewer lateral closed

More information

We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year

We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year Reactive CCTV Surveys Lining & Patch Reactive London Drainage

More information

Guidelines for As-Built CCTV Inspections of Lined/Rehabilitated Pipe

Guidelines for As-Built CCTV Inspections of Lined/Rehabilitated Pipe Guidelines for As-Built CCTV Inspections of Lined/Rehabilitated Pipe P r e p a r e d B y : P r o j e c t M a x L i m i t e d 8 / 1 1 / 2 0 1 3 Supplementary Document to the CCC Specification CCTV for Christchurch

More information

REPAIRS TO DAMAGED SEWERS

REPAIRS TO DAMAGED SEWERS REPAIRS TO DAMAGED SEWERS A digout is the replacement of sewer or storm water pipes that are either broken or blocked due to tree roots, ground movement or ageing of pipes. When the use of high-pressure

More information

Module 3 : Sewer Material. Lecture 3 : Sewer Material

Module 3 : Sewer Material. Lecture 3 : Sewer Material 1 P age Module 3 : Sewer Material Lecture 3 : Sewer Material 2 P age 3.1 Important Factors Considered for Selecting Material for Sewer Following factors should be considered before selecting material for

More information

See Appendix A for additional information, or contact ASTM directly.

See Appendix A for additional information, or contact ASTM directly. DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion

More information

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology 2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)

More information

Sewer System Inspection: Techniques and Resources. Presented by: Doug Severson

Sewer System Inspection: Techniques and Resources. Presented by: Doug Severson Sewer System Inspection: Techniques and Resources Presented by: Doug Severson Sewer Inspection Why should you inspect a sewer system? Preserve critical assets Confirm system integrity Peace of mind Disaster

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

Reticulation sewers in basements Technical guidelines

Reticulation sewers in basements Technical guidelines Reticulation sewers in basements Technical guidelines Overview What These guidelines explain our technical requirements for laying sewers in building basements. The scope of the guide is restricted to

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

Interactive Decision Tree Automates Sewer Rehabilitation Planning

Interactive Decision Tree Automates Sewer Rehabilitation Planning Interactive Decision Tree Automates Sewer Rehabilitation Planning IWPCA Annual Conference June 5, 2008 Rodney Moeller, P.E., John Schroeder, P.E. BCEE, C. Timothy Fallara, P.E. & Mel Meng, P.E. Agenda

More information

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223 STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified

More information

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542 1.0 INTENT REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES 1.01 It is the intent of this specification to provide for the reconstruction of pipelines and conduits by the installation of a resin-impregnated

More information

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC

REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS. Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC REVIEW OF TRENCHLESS TECHNIQUES FOR THE REHABILITATION OF SEWERS Gerhard (Gerry) P. Muenchmeyer, P.E. Muenchmeyer Associates, LLC What is really out there? DO YOU DIG IT? INDUSTRY CONCERNS UNEXPECTED DEVELOPMENTS

More information

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk ALL YOUR NEEDS Tel: 01384 482228 www.midlanddrainage.co.uk Welcome to Midland Drainage Services Midland Drainage Services is a family owned and operated Drainage Company, based in the West Midlands and

More information

SPR PE Steel Reinforced Liner

SPR PE Steel Reinforced Liner ENGINEERED SOLUTIONS SPR PE Steel Reinforced Liner Reline Done Right Contech is your single source for rehabilitation of sanitary & storm sewers, culverts and bridges. Contech Engineered Solutions has

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013

VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 VIDEO INSPECTION AND LASER PROFILING IN FLORIDA AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 PIPE INSPECTION Over the last 5 years, the Department has spent approximately 175 million dollars

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets *Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; [email protected] Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes

More information

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL

More information

Guide to working on Public Sewers

Guide to working on Public Sewers Guide to working on Public Sewers affected by Building Works Introduction Severn Trent Water Ltd requires the work to be done in order to protect the public sewer and minimise the risk of us having to

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

Section 4. Sewer Testing

Section 4. Sewer Testing Section 4 Sewer Testing 4.1 General Sewers and ancillary works shall be tested and inspected for watertightness to prevent infiltration and exfiltration and to ensure the pipes are laid correctly according

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced

More information

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 EPA New England Water Infrastructure Outreach provides tools,

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

Pipeline Replacement using Relining

Pipeline Replacement using Relining Pipeline Replacement using Relining Mark Heathcote, March 2006 Relining of old pipeline systems is becoming an increasingly attractive option to asset owners and operators as an effective alternative to

More information

Culvert Repair, Materials, and Structural Design 4.4-1

Culvert Repair, Materials, and Structural Design 4.4-1 Culvert Repair, Materials, and Structural Design 4.4-1 4.4 Culvert Materials 4.4.1 General Culverts are primarily made with reinforced concrete, corrugated metal, and more recently, solidwall, profile

More information

www.pawsd.org Pagosa springs, Colorado 81157

www.pawsd.org Pagosa springs, Colorado 81157 Michael Church, President/Chairman Glenn Walsh, Vice President Gordon Mclver, Secretary Paul HansEn, Treasurer Blake Brueckner SCOPE OF WORK Pagosa Water and Sanitation District (PAWSD) is a quasi-municipal

More information

APPENDIX K PIPE INSPECTION

APPENDIX K PIPE INSPECTION APPENDIX K PIPE INSPECTION **Virginia Test Method 123** Post Installation Inspection of Buried Storm Drain Pipe and Pipe Culverts June 25, 2010 SCOPE For all roadway projects that are constructed by private

More information

Structural Pipe Lining Technology

Structural Pipe Lining Technology Structural Pipe Lining Technology ABOUT US Nu Flow install innovative technologies to rehabilitate failing or deteriorating piping systems. These technologies are non-invasive, in-situ, and offer a greener

More information

PRE INSTALLATION MANUAL

PRE INSTALLATION MANUAL REINFORCED CONCRETE PIPE PRE INSTALLATION INSPECTION & REPAIR MANUAL Kentucky Transportation Cabinet Kentucky Department of Highways Division of Materials 1227 Wilkinson Boulevard Frankfort, KY 40601 (502)

More information

VIDEO INSPECTION AND LASER DEFLECTION TESTING FOR POST CONSTRUCTION QC/QA SPECIFICATIONS AND MAINTENANCE INSPECTIONS

VIDEO INSPECTION AND LASER DEFLECTION TESTING FOR POST CONSTRUCTION QC/QA SPECIFICATIONS AND MAINTENANCE INSPECTIONS VIDEO INSPECTION AND LASER DEFLECTION TESTING FOR POST CONSTRUCTION QC/QA SPECIFICATIONS AND MAINTENANCE INSPECTIONS BY JOHN FLECKENSTEIN PIPELINE AND DRAINAGE CONSULTANTS INTRODUCTION History Of Post

More information

PRODUCT CATALOGUE. for. SMARTPHONE / WEBSITE / DIGITAL EDITION / BOOK / ipad / GPS

PRODUCT CATALOGUE. for. SMARTPHONE / WEBSITE / DIGITAL EDITION / BOOK / ipad / GPS PRODUCT CATALOGUE for This product catalogue has been downloaded from COSSD.com. Listed products/services and their descriptions are shown as supplied by the title company COSSD does not guarantee the

More information

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials

More information

CHAPTER 11 STORM DRAINAGE

CHAPTER 11 STORM DRAINAGE CHAPTER 11 STORM DRAINAGE SECTION 11 GENERAL 11.1 Scope. The provisions of this chapter shall govern the materials, design, construction and installation of storm drainage. 11.2 Where required. All roofs,

More information

Upstream Manhole Number 96746 55.9. Dry. Circumferential Location. Image Ref. At / From. Joint

Upstream Manhole Number 96746 55.9. Dry. Circumferential Location. Image Ref. At / From. Joint Surveyors name P/O No. U-71-1168 System Owner COA Pipeline Segment Reference 936 1614 Shape Circular H Rim to Invert RCP Sewer Category Grade to Invert Ln. Method Pre-Cleaning No PreCleaning Group/ Descriptor.

More information

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING 1.0 GENERAL 1.1 Scope 2.0 PRODUCTS 1.1.1 The work shall consist of testing wastewater and/or storm mains to ensure construction conforms to the proper line, grade, cross section and performance. 2.1 The

More information

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200 STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

SECTION 02733 CLEANING AND TELEVISION INSPECTION

SECTION 02733 CLEANING AND TELEVISION INSPECTION SECTION 02733 CLEANING AND PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Cleaning the sewer line to remove debris, solids, roots, sand, pieces of broken pipe, bricks, grease, and grit from sewer line and

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan and Condition Assessment Plan 4.1 Introduction 4.1.1 Purpose This addresses the requirements of Section IV.A. of the EPA Order. The plan documents the progress that each agency has made to date regarding

More information

INDEX. Sec. No. Items Page Nos.

INDEX. Sec. No. Items Page Nos. INDEX Sec. No. Items Page Nos. 1. Types of Pipe............... MSSP- 2 2. Concrete Pipe............... MSSP- 2 thru MSSP-3 3. ABS and PVC Truss Pipe............... MSSP- 3 4. ABS and PVC Solid Wall Pipe...............

More information

Sewerage Operation and Maintenance. Tokyo Metropolitan Government Bureau of Sewerage Facilities Management Division, Pipeline Management Section

Sewerage Operation and Maintenance. Tokyo Metropolitan Government Bureau of Sewerage Facilities Management Division, Pipeline Management Section Sewerage Operation and Maintenance Tokyo Metropolitan Government Bureau of Sewerage Facilities Management Division, Pipeline Management Section About the sewer system facilities About the operation and

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

SA Pipe Relining is dedicated to finding simple, non intrusive

SA Pipe Relining is dedicated to finding simple, non intrusive SA Pipe Relining is dedicated to finding simple, non intrusive solutions to complex problems using latest technologies and methodical work practises in an environmentally friendly and cost effective manner.

More information

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

DRAINAGE PIPE REPAIR & RELINING SOLUTIONS

DRAINAGE PIPE REPAIR & RELINING SOLUTIONS DRAINAGE PIPE REPAIR & RELINING SOLUTIONS Our technology Nuflow are the specialists in trenchless pipe relining, providing a structural repair. We provide a simple, practical, cost effective solution to

More information

INSTALLATION OF INSITUFORM LINER

INSTALLATION OF INSITUFORM LINER PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

Infrastructure Condition Assessment and Certification Programs (PACPMACP/LACP)

Infrastructure Condition Assessment and Certification Programs (PACPMACP/LACP) Infrastructure Condition Assessment and Certification Programs (PACPMACP/LACP) By Marilyn Shepard, NASSCO Master Trainer 2012 and 2013 Trainer of the Year 1 Module Overview Introduction to NASSCO Background,

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION

APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION North American Society for Trenchless Technology (NASTT) NO-DIG 2005 Orlando, Florida April 24-27, 2005 APPLICATION OF GLASS-REINFORCED PLASTIC TO SEWER REHABILITATION Lynn Osborn 1 1 ArmourGRiP Product

More information

VDOT 2001 Road and Bridge Standards Section 100 - Drainage Items

VDOT 2001 Road and Bridge Standards Section 100 - Drainage Items VDOT 2001 Road and Bridge s Page Title EW-1 EW-1A 101.01 Endwall for Pipe Culverts 12" - 36" Circular and 23" X 14" - 53" X 34" Elliptical Pipes EW-1PC EW-1APC 101.02 Precast Endwall for Pipe Culverts

More information

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District

Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Coast Trunk Sewer Rehabilitation Project for the Orange County Sanitation District Paul F. Wilson 1 and Robert J. Warren 2 1 1525 Faraday Ave, Suite 290, Carlsbad, California, USA 92008; e-mail: [email protected].

More information