Project Scheduling by Critical Path Method (CPM)
|
|
|
- Annis Brenda Day
- 9 years ago
- Views:
Transcription
1 12.1 Project Scheduling by Critical Path Method (CPM) Katta G. Murty Lecture slides CPM is application of DP to problems in Construction (project) Management. Many large construction projects going on around world. The recently completed Hong Kong Airport (Chek Lap Kok) and associated rail and bridge work, > US$10Billion The more than US $ 1 billion Shanghai World Financial Center (95 floors, 460 meters tall, 3.5 million feet 2, expected to be world s tallest building when completed). CPM is a method for planning, scheduling, and controlling such projects. 176
2 Basic Steps in CPM 1 Decompose project into Individual Jobs or Activities. 2DeterminePrecedence Relationships among jobs. They come from technological constraints. For example: Suspension bridge road units cannot be lifted into place until pillars are prepared. Painting the walls cannot be started until erecting walls completed. 3DrawtheArrow Diagram,orAOA Diagram,orProject Network representing precedence relationships. 4 Estimate job durations. 5 Use CPM to schedule activities over time to minimize project duration (DP used here). 6Inoperation,ifanyjobdelayed,useCPMtoreviseschedule for remaining jobs. 177
3 Precedence Relationships Predecessor Ancestor Successor Descendent Immediate Predecessor Immediate Successor or or Job 1 is a Predecessor or Ancestor of job 2 if job 2 cannot be started until job 1 completed. In above job 2 is a Successor or descendent of job 1. If job 1 is a predecessor of job 2, and no other job is a predecessor to job 2 and successor to job 1; job 1 is an Immediate Predecessor of job 2 If job 1 is an immediate predecessor of job 2, then job 2 is an Immediate Successor of job 1. A job may have many immediate predecessors, and many immediate successors. It can only be started after all its immediate predecessors have been completed. 178
4 Transitivity Job 1 predecessor of job 2, and job 2 predecessor of job 3 job 1 predecessor of job 3. This property called Transitivity. Given immediate predecessors of a job, we can obtain all its predecessors by transitivity. Precedence relationships define a Partial Ordering among jobs. If transitivity establishes that a job is a predecessor of itself, there is an Inconsistency in the data that should be corrected. If a distant predecessor of a job is shown as an immediate predecessor, there is Redundancy in the predecessor data, which should be corrected. 179
5 Example: Constructing an Office Bldg. Job IPs Duration 1. Site selection & purchase Architectural plans (AP) Revisions to AP Arrange Financing Construct outer frame Plans for interior Order furnishings (desks, etc.) Order Computer equipment Computer Network Design Interior Construction Instal computer equipment Move-In 5 Days 180
6 Construct single family home Job IPs Duration 0. Purchase site Prepare blueprint Excavation Foundations & Basement walls Frame Electrical wiring Insulate Roofing Ductwork & Plumbing Drywall installation 5, 7, Instal siding Exterior painting Interior painting Carpeting Instal interior fixtures Instal Exterior fixtures Move-in 14, 15 1 weeks 181
7 Hydroelectric Power Station Building Project No. Job IPs Duration 1. Site Ecological survey Get EPA approval Economic feasibility study Prel. design and cost est Project approval 2, Call quotations for elec equip. (turbines, generators,...) 7. Select suppliers for elec. equip Final design Select construction contractors Arrange materials supply 8, Dam building Power station building Power lines erection 7, Elec. equip. installation 7, Build up reservoir water level Commission the generators 14, Start supplying power 13, months 182
8 Project Networks 2 ways to represent predecessor relationships in network form. AON (Activity On Node) network easy to draw, not very useful. We discuss Activity On Arc (AOA) diagram or Arrow diagram. Here, jobs correspond to arcs. Each node corresponds to an Event, jobs corresponding to all arcs incident into it, and all their predecessors, have been completed. To portray predecessor relationships correctly in arrow diagram, sometimes necessary to introduce Dummy arcs corresponding to Dummy jobs (which always have 0 duration). 183
9 PROPERTIES SATISFIED BY ARROW DIAGRAM: 1 If job 1 is a predecessor of job 2, there will be a directed path in arrow diagram from the head node of job 1 to the tail node of job 2 (i.e. predecessor relationship represented through directed paths). 2 If job 1 is an immediate predecessor of job 2, Either head node of job 1 is tail node of job 2 Or there is a directed path from head node of job 1 to the tail node of job 2 consisting of dummy arcs only. 184
10 Need For Dummy Arcs Dummy arcs necessary whenever there is a subset of jobs A that have some but not all IPs in common. In this case we let arcs corresponding to common IPs of jobs in A to have same head node, and then add dummy arcs from that node to the tail nodes of arcs corresponding to jobs in A. Example Job IPs e 1 e 2 e 3 e 4 e 5 e 4 e 6 e 1, e 2, e 5 e 7 e 2, e 3, e 5 185
11 To avoid confusion, we follow convention that there should be no parallel arcs. So, if there are several jobs with same set of IPs, and same set of immediate successors, we represent them using dummy arcs. How to Draw Arrow Diagram? Put a Start node representing event of commencing project. Represent each job with no predecessor by an arc incident out of this start node. Same way, at end, represent all jobs with no successors by arcs incident into a single final node Finish Node representing event of project completion. If a job b has a single IP a, thenb can be represented by an arc incident out of the head node of a. If a job b has more than one IP, let p 1,...,p r be the head nodes of IPs of job b: either represent b by an arc incident out of one of the nodes 186
12 p 1,...,p r,sayp 1, and include dummy arcs from p 2,...,p r into p 1. or represent b by an arc incident out of a new node Q and include dummy arcs (p 1,Q),...,(p r,q). If some jobs have identical sets of immediate successors, make theheadnodeofarcsrepresentingthemthesame. If several jobs have some common IPs, represent these common IPs by arcs with the same head node, and include dummy arcs coming out of this node as necessary. Check: Precedence relationships not implied by original data not introduced. Precedence relationships implied by original data not omitted. See if no. of nodes & no. of dummy nodes can be reduced. For example, if there is a node with a single arc (which is a dummy arc) incident at it, then the 2 nodes on this dummy arc can be merged, and that dummy arc eliminated. 187
13 Since no job can be its own predecessor, project network cannot contain any directed cycles, so project network must be an acyclic network. Acyclic Networks A directed network that contains no circuits (directed cycles): A circuit or directed cycle A cycle that is not a circuit. Theorem: A Directed network acyclic iff nodes can be numbered s. th. on each arc number of tail < number of head Such numbering of nodes called acyclic numbering or topological ordering. 188
14 How to check if network acyclic, & find acyclic numbering of its nodes? 1. Number all nodes with no arcs incident into them, serially beginning with 1. Strike off all these nodes & arcs incident at them. 2. Now continue numbering all nodes with no arcs that are not struck off, incident into them, serially. Strike off all newly numbered nodes & arcs incident at them. 3. Repeat Step 2 until either: all nodes numbered (in this case network acyclic, you have acyclic numbering, terminate) or some unnumbered nodes, but every one has an arc that is not struck off, incident into it (in this case, network not acyclic, terminate). 189
15 Examples 190
16 Project Scheduling Find acyclic numbering of nodes in project network. Node 1 = start node, node n = finish node. To lay out jobs on time axis to minimize project duration. To answer questions like: Start time = 0. How soon can project be completed? How early would event corresp. to each node materialize? What is earliest time at which each job can be started (called Early Start Time of Job)? Foreachjob,whatislatesttimeatwhichitcanbestarted, without delaying project completion? Etc. 191
17 The Data For each arc (i, j) in the project network: t ij = Duration of job represented by arc (i, j) =Lengthofarc(i, j) Earliest Event Times Define: t i = Length of longest chain from node 1 to i. Clearly t i = earliest time at which event corresponding to node i can materialize. t n = length of longest chain from start node 1 to finish node n = Minimum Project Duration. A longest chain from node 1 to node n is called a Critical Path. There may be several critical paths. Arcs on critical paths called Critical arcs, theyrepresent Critical jobs. To complete project in min. time, every critical job should be started at earliest time. Any delay in a critical job delays project 192
18 completion. Jobs not on any critical path called Slack jobs. Early start time of job (i, j) =t i Early Finish Time of job (i, j) =t i + t ij. Forward pass DP Algorithm to find Early Start Times t i s Data Structures The Forward label on node i will be (L i,t i )wherel i called Predecessor Index of node i, is the previous node to i on a longest chain from 1 to i. Boundary Conditions: t 1 = 0. Forward label node 1 with (, 0). This label indicates it is Origin node. In this pass nodes labeled in the order 1 to n. The recurrence eq. for node r is: t r =max{t i + t ir : i s. th. (i, r) isanarc} L r in the label for node r is the i that attains the maximum in 193
19 the above eq. The longest path from node 1 to i can be traced using the predecessor indices backwards beginning with node i. The longest path from 1 to n is one critical path. To find all critical jobs & Latest Start Times: The forward pass gives only one critical path. To find all critical arcs, we define: µ i = Latest point of time at which the event corresponding to node i has to materialize for the project to finish in minimum duration. µ n = t n (Boundary Condition) µ i = µ n length of the longest chain from node i to node n. 194
20 The Backward Pass This pass determines the µ i by DP. They are determined in the order i = n, n 1,...,2, 1. µ n = t n Boundary condition. µ i =min{µ j t ij : j s. th. (i, j) isanarc} The Late Finish of job (i, j) =µ j The Late Staret of job (i, j) =µ j t ij The Total Slack of job (i, j) = Late start - early start = µ j t ij t i. Job (i, j) is critical iff its total slack = 0. HOMEWORK PROBLEMS: 1.Draw the arrow diagram and determine the early and late start and finish times of the various jobs in the following projects (A. Kanda and N. Singh [1988]). 195
21 Project: Setting Up a Fossil Fuel Power Plant No. Job IPs Job duration (months) 1. Land acquisition 6 2. Identi. trained personnel Land dev. & infrastructure Control room eng Lag in turbine civil works Delivery of TG Delivery of boiler Joining time for personnel Boiler prel. civil works Control room civil works TG civil works Training Boiler final civil works Erection of control room Erection of TG 6, Boiler erection 7, Hydraulic test Boiler light up 14, Box up of turbine Steam blowing, safety 18, valve floating 21. Turbine rolling Trial run Synchronization 22 1 IP = Immediate predecessors 2. Draw an arrow diagram for each of the following projects. Prepare a schedule for the various jobs in each project to complete it in minimum time. (R. Visweswara Rao). (a) Sewer and Waste System Design for a Power Plant No. Activity IPs Duration (days) 1. Collection system 40 outline 2.. Final design & 1 30 approval 3. Issue construction 2 30 drawings 4. Get sewer pipe & manholes 5. Fabricate & ship 3, Treat. system 70 drawings & approval 7. Issue treat. system 6 30 construction drawings 8. Award contract Final construction 8, IP = Immediate predecessors 196
22 (b) Data Process and Collection System Design for a Power Plant No. Activity IPs Duration (days) 1. Prel. Syst. 40 description 2. Develop specs Client approval 2 50 &placeorder contd. Data Process and Collection System Design contd. No. Activity IPs Duration (days) 4. Develop I/O 2 60 summary 5. Develop alarm 4 40 list 6. Develop log 3, 5 40 formats 7. Software def Hardware 3 35 requirements 9. Finalize I/O 5, 6 60 summary 10. Anal. performance 9 70 calculation 11. Auto. turbine 9 60 startup anal. 12. Boiler guides anal Fabricate & ship 10, 11, Software preparation 7, 10, Install & check 13, Termination & 9 30 wiring lists 17. Schematic wiring lists 18. Pulling & term. 15, of cables 19. Operational test First firing 19 1 IP = Immediate predecessors 197
23 (c) Electrical Auxiliary System Design for a Nuclear Plant No. Activity IPs Duration (days) 1. Aux. load list switchgear load ident kv & 480 v. switchgear 1 45 load ident. 4. Vital AC load determination 5. DC load determ Voltage drop study Diesel gen. sizing Inventer sizing Battery sizing 5, DC fault study Prel. AC fault 6, 7 20 current study 12. Power transformer 2, sizing 13. Composite oneline 2,3 72 diagram 14. Safety (class 1E) system design 15. Non-class 1E system design 16. Relaying oneline & metering dia line diagram 14, 15, Synchronizing & phasing diagrams 19. Client review 10, Equipment purchase & installation 198
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Precedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
ANALYSIS OF PROJECT PLANNING USING CPM AND PERT
ANALYSIS OF PROJECT PLANNING USING CPM AND PERT Rogelio Acuña Spring 2010 In Partial Fulfillment of Math 4395-Senior Project Department of Computer and Mathematical Sciences Faculty Advisor: Dr. Timothy
Scheduling Best Practices
In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
22 Project Management with PERT/CPM
hil61217_ch22.qxd /29/0 05:58 PM Page 22-1 22 C H A P T E R Project Management with PERT/CPM One of the most challenging jobs that any manager can take on is the management of a large-scale project that
Critical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Network analysis and building construction: Implications for timing and costing of activities
Journal of Civil Engineering and Construction Technology Vol. 2(5), pp. 90-100, May 2011 Available online at http://www.academicjournals.org/jcect ISSN 2141-2634 2011 Academic Journals Full Length Research
MECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Winter : Lecture # Project Time Management Homework Discussion Homework
Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) Applications
Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) Applications Two simple, yet interesting and important applications of partial ordering relations are the PERT and CPM techniques
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
B. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
Project Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Building Permit Application
Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER
2.8 An application of Dynamic Programming to machine renewal
ex-.6-. Foundations of Operations Research Prof. E. Amaldi.6 Shortest paths with nonnegative costs Given the following graph, find a set of shortest paths from node to all the other nodes, using Dijkstra
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule
763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Primavera P6 Exercise Worksheet
Primavera P6 Exercise Worksheet P6 Exercise Worksheet Preparing for the Exercises Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use
Software Engineering. Pert and Gantt exercises. Lecturer: Giuseppe Santucci
Software Engineering Pert and Gantt exercises Lecturer: Giuseppe Santucci Degree of freedom! I.3a 3 3 I. I. 3 I.3b I.3c I.4 Exercise s goals. Draw a PERT network (AON) representing a project s characteristics.
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION
SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
Leaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room
QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
Water Leak 1: Intrusion Policy
Water Leak 1: Intrusion Policy {Non-Casualty) 1. Determine Source of Leak Roof Leak- 11 See roof leak" Pressured Pipe leak- 11 See pressured pipe leak" Water Intrusion- See 11 see Water Intrusion leak"
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.
Planning & Scheduling CSTM 462 Managing a project through time and resources. The need for proper planning and scheduling. Project Management Objectives 1. Eliminate or reduce project RISK. 2. Obtain a
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Lecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
Building Condition Assessment Report
Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.
PERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION
Arizona Health Care Association DISASTER PLANNING AND EMERGENCY MANAGEMENT GUIDE POST INCIDENT DAMAGE ASSESSMENT CHECKLIST
It is essential to perform a Basic Damage Assessment (BDA) following an adverse event to help ensure the safety of building occupants as well as prevent additional losses from occurring. This checklist
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
ME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
APEC CAPABILITIES PROJECT MANAGEMENT / SUPPORT
PROJECT MANAGEMENT / SUPPORT Capital Cost Savings Construction Monitoring and Assistance In-Plant Production Assistance In-Plant Maintenance Assistance Procurement Assistance Project Cost Estimating o
BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis
Modeling Page 1 To BPEL or not to BPEL? 5:56 PM To BPEL or not to BPEL? BPEL disadvantage: more time to product BPEL advantage: better reusability, analysis Modeling Page 2 A tale of two strategies 5:57
PROGRAMMING TECHNIQUES. Chapter 5(Part 2)
PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate
CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING
CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can
Notes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
Application Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
7. PROJECT MANAGEMENT
7. PROJECT MANAGEMENT Syllabus Definition and scope of project, Technical design, Financing, Contracting, Implementation and performance monitoring. Implementation plan for top management, Planning Budget,
Guidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals
Presentation to Senate Select Committee on Government Facilities: Deferred Maintenance for State Supported Living Centers and State Hospitals Les Butler Associate Commissioner for Business and Regional
Section D..General Auto Electrical Corporation
43 Section D..General Auto Electrical Corporation 1. LED Based Signal unit GAEC manufacture LED based signaling system for use in electrified and non electrified sections of Indian railways. The exceptional
HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number: 300-004
HOWARD UNIVERSITY Policy Number: 300-004 Policy Title: ASSET CAPITALIZATION Responsible Officer: Chief Financial Officer Responsible Offices: Office of the Controller, Departments of Strategic Sourcing
Submit shop drawings for equipment provided under this section Shop drawings shall indicate:
Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,
..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...
..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... TIME MARK CORPORATION 11440 EAST PINE STREET TULSA, OK 74116 USA tel 918 438-1220 fax 918 437-7584 www.time-mark.com
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
Chapter 11: PERT for Project Planning and Scheduling
Chapter 11: PERT for Project Planning and Scheduling PERT, the Project Evaluation and Review Technique, is a network-based aid for planning and scheduling the many interrelated tasks in a large and complex
SCHEDULING AND PROJECT MANAGEMENT
SCHEDULING AND PROJECT MANAGEMENT Chapter Survey Scheduling Process Scheduling Methods Scheduling and cash management Who is the Project Manager Project Supervisory Team Project Life Cycle Tracking the
ST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Almost everyone in the planning and scheduling profession
PS.02 The Great Negative Lag Debate Mr. Edward E. Douglas III CCC PSP, Mr. Timothy T. Calvey PE PSP, Mr. Donald F. McDonald Jr. PE CCE PSP, and Mr. Ronald M. Winter PSP Almost everyone in the planning
Software Engineering. Dilbert on Project Planning. Overview CS / COE 1530. Reading: chapter 3 in textbook Requirements documents due 9/20
Software Engineering CS / COE 1530 Lecture 4 Project Management Dilbert on Project Planning Overview Reading: chapter 3 in textbook Requirements documents due 9/20 1 Tracking project progress Do you understand
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
Power Plant Electrical Distribution Systems
PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com
Project Scheduling. Introduction
Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Unit 1: Project Planning and Scheduling
Unit : Project Planning and Scheduling Objective Ð To provide a brief introduction to project planning and scheduling. The critical area where project management meets system development. ackground Most
Software Project Management Part 2: Work Breakdown Structures
Software Project Management Part 2: Work Breakdown Structures Introduction into Software Engineering Lecture 20 Bernd Bruegge Applied Software Engineering Technische Universitaet Muenchen 1 Where are we?
APPLICATION FOR NEW CONSTRUCTION
CITY OF ELKINS 401 DAVIS AVE ELKINS WV 26241 Date Pd: Receipt #: Session #: PHIL ISNER BLDG INSPECTOR / CODE ENFORCEMENT OFFICER 304-636-1414 Ext 1431 APP. DATE APPLICATION FOR NEW CONSTRUCTION APPLICANT
American Safety Insurance Company
American Safety Insurance Company General Liability Program A- Rated (Non-Admitted) Table of Contents Page 2 Page 3 Page 4 5 Underwriting Guidelines and Coverages Prohibited Classes Underwriting Classification
Certificate of Registration
Certificate of Registration This is to certify that Clancy Docwra Limited Supplier Number: 061973 are now fully registered as a supplier on UVDB for the following products/services 1.4.25 Communication
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education
OPEN ACCESS Engineering Leaders Conference 2014 Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education M.O. Daramola
Hitachi s Involvement in Nuclear Power Plant Construction in Japan
Hitachi s Involvement in Nuclear Power Plant Construction in Japan 48 Hitachi s Involvement in Nuclear Power Plant Construction in Japan Naoki Kajiyama Kenji Hamamura Koichi Murayama OVERVIEW: To protect
Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org
Planning and Managing Software Projects 2011-12 Class 9 Scheduling Fundamentals, Techniques, Optimization Emanuele Della Valle, Lecturer: Dario Cerizza http://emanueledellavalle.org Credits 2 This slides
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS
33 CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 4.1 BASICS OF LINEAR SCHEDULING The LSM is a graphical technique in which the locations or the length of the linear project is indicated
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
MONTHLY MONITORING REPORT. World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York
MONTHLY MONITORING REPORT World Trade Center Port Authority Trans-Hudson Terminal PORT AUTHORITY OF NEW YORK AND NEW JERSEY New York, New York January 2014 PMOC Contract Number: DTFT60-09-D-00008 Task
AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA)
AT&T Internet Data Center Site Specification Washington-DC Area (Ashburn, VA) Site Biography Market Area: Washington, DC Area Location: Ashburn, VA 20147-6011 Address: All deliveries should be sent to
A&E A&E. ProSurance TM. Application Form INSURANCE FOR ARCHITECTS & ENGINEERS
A&E INSURANCE FOR ARCHITECTS & ENGINEERS ProSurance TM A&E Application Form This is an application for an errors and omissions package policy designed specifically for architects and engineers. As well
