1 Page: 1 of PROGRAM OBJECTIVE The purpose of this procedure is to define the responsibilities, methods, procedures and training required to safely and effectively remove or clean mold-contaminated building materials and contents. 2.0 SCOPE This program covers buildings owned or operated by the University of Pennsylvania. 3.0 DEFINITIONS 3.1 Approved Contractor A contractor who has been approved by EHRS & Facilities Services to perform mold remediation work. 3.2 Flame Resistant Polyethylene Sheeting Six mil flame resistant polyethylene sheeting meeting NFPA Level I Mold Remediation Project Projects requiring the remediation of less than ten square feet of mold-contaminated materials. Typically completed by trained Facilities Services personnel. EHRS notification is optional. 3.4 Level II Mold Remediation Project Projects involving remediation of greater than ten feet of mold-contaminated materials. Shall be completed by an approved contractor. EHRS notification is required. 3.5 Mold-Contaminated Materials - Materials determined to be mold-contaminated through visual and/or olfactory inspection or other sampling methods. 3.6 Post-Remediation Verification A post-remediation inspection performed by EHRS industrial hygienists or by industrial hygiene consultants selected by EHRS. The inspection may include visual inspection, olfactory detection or sampling as deemed appropriate. The purpose of the inspection is to verify that the remediation has been properly executed and that the area has been restored to what would be considered a normal indoor environment fungal ecology. 3.7 Trained Individual An individual who has completed EHRS mold remediation training. 4.0 RESPONSIBILITIES 4.1 Environmental Health and Radiation Safety (EHRS) Shall evaluate suspected areas of mold contamination and assess appropriate University response.
2 Page: 2 of Shall in conjunction with Facilities Services identify the underlying causes of mold contamination and identify responses to prevent recurrence Shall perform or coordinate mold remediation project oversight for level II projects Shall provide or coordinate appropriate training to Facilities Services staff that perform mold remediation Shall perform periodic reviews of the overall effectiveness of the Mold Remediation Procedures and update as required Shall maintain all sampling, training and post-remediation verification documentation. 4.4 Facilities Services Shall notify EHRS of mold growth in excess of ten square feet and other nonroutine water releases Shall perform mold remediation as outlined in this procedure Shall work in conjunction with EHRS to pre-qualify remediation contractors for level II projects Shall attend appropriate training and follow remediation work practices as outlined in the training and this procedure. 5.0 GENERAL INFORMATION 5.1 General Rules 6.0 PROCEDURE Only non-porous (e.g., metals, glass, and hard plastics) and semi-porous (e.g., wood, and concrete) materials that are structurally sound can be cleaned and reused. Cleaning should be completed using an appropriate cleaning agent. All materials that will be reused should be dry and visibly free from mold Porous materials such as ceiling tiles, insulation, and gypsum board may not be cleaned and should be removed and discarded as described in this procedure The use of gaseous, vapor-phase or aerosolized biocides or odor suppressants for remedial purposes is not permitted without specific approval from EHRS.
3 Page: 3 of Level I: Limited Areas of Mold Contamination (10 square feet or less of moldcontaminated materials) EHRS notification is optional Trained Facilities Services personnel may conduct remediation Personal protective equipment including at minimum, gloves and eye protection shall be worn Building occupants should be temporarily relocated during the remediation project Containment of the remediation area is not required. A polyethylene drop cloth should be installed in the immediate area of the remediation activity Contaminated materials that cannot be cleaned should be removed from the building in a sealed plastic bag or wrapped and sealed in polyethylene sheeting and disposed of. There are no special requirements for the disposal of moldy materials Hidden mold If additional mold contamination is discovered during the remediation project, contact EHRS to have the project reevaluated At the completion of the remediation project, all surfaces, including carpeting, in the vicinity of the remediation area shall be HEPA vacuumed. Additionally, nonporous surfaces shall be damp wiped and the floors mopped with the appropriate cleaning agent All areas should be left dry and visibly free from contamination and dust/debris. 6.2 Level II: Mid to Large Areas (greater than 10 square feet of mold-contaminated materials) EHRS must be notified of the intent to remediate as soon as possible Remediation shall be completed by an approved contractor selected by Facilities Services/EHRS. Remediation work practices shall be consistent with nationally accepted standards such as IICRC S500-Standard and Reference Guide for Professional Water Damage Restoration and IICRC S520-Standard and Reference Guide for Professional Mold Remediation Contractor is required to submit a work plan detailing methods and procedures used to complete the remediation project to EHRS for approval at least two working days in advance of the project.
4 Page: 4 of TRAINING EHRS shall review the work plan, request changes if necessary, and give the contractor permission to proceed EHRS shall perform project oversight to include periodic inspections to ensure that the project is completed in compliance with the work plan and complete post-remediation verification EHRS shall provide a written post-remediation verification report to Facilities Services and the occupants of the remediation area. 7.1 All personnel involved with mold remediation shall receive training consistent with their duties. Employees will receive training in order to acquire the understanding, knowledge and skills necessary for the safe performance of the duties assigned under this program. 7.2 Training shall be provided to each affected employee: Before the employee is first assigned duties Whenever the employer has reason to believe that there are deviations from the mold remediation procedures or that there are inadequacies in the employee's knowledge or use of these procedures The training shall establish employee proficiency in the duties required and shall introduce new or revised procedures, as necessary, for compliance. 7.3 Training content shall include: 8.0 DOCUMENTATION OSHA Hazard Communication Standard (29CFR ) Methods & Procedures for mold remediation to include: Isolation of HVAC systems Installation of isolation barriers and protection of non-contaminated materials within the remediation area Remediation, cleaning and disposal of mold-contaminated materials Final cleaning of remediation area Personal protective equipment including OSHA Respiratory Protection Standard (29 CFR ). 8.1 Training documentation shall be kept for all affected employees. Training rosters shall indicate the employee s name, date, and the instructor who performed the training.
5 Page: 5 of 5 EHRS shall maintain all training rosters and a copy of the training outline. The most current training record shall be kept for each affected employee. 8.2 EHRS shall maintain copies of all work plans. 8.3 EHRS shall maintain all sampling data. 8.4 EHRS shall maintain all post-remediation sampling reports. 9.0 REFERENCES 9.1 Institute of Inspection Cleaning and Restoration Certification - IICRC S500 Standard and Reference Guide for Professional Water Damage Restoration. 9.2 Institute of Inspection Cleaning and Restoration Certification IICRC S520 Standard and Reference Guide for Professional Mold Remediation. 9.3 Centers for Disease Control and Prevention Facts About Mold and Dampness US Environmental Protection Agency Mold and Dampness American Industrial Hygiene Association Facts About Mold involved/volunteergroups/documents/biosafetyvg- FactsAbout%20MoldDecember2011.pdf
Guidelines for Mold Remediation (Removal)
Guidelines for Mold Remediation (Removal) Indoor mold growth, water damage, or musty odors should be addressed quickly. Removing mold growth and correcting the underlying cause of water accumulation can
STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION
West Virginia University Environmental Health and Safety STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION Origination Date August 2013. Contents Purpose:... 2 Job Scope... 2 Definitions... 2 Roles/Responsibilities:...
DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE
1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to
Mold Management Plan Operations & Maintenance
Document #: SAFETY_015 Revision Date: October 4, 2010 Mold Management Plan Operations & Maintenance Developed by: Environmental Health & Safety Approved by: Associate VP of Facilities & Campus Services
UNIVERSITY OF TOLEDO
UNIVERSITY OF TOLEDO SUBJECT: MOLD PREVENTION AND REMEDIATION Procedure No: HM-08-035 PROCEDURE STATEMENT All indoor areas on campus are expected to present no immediate threat to the health and well-being
NORMI Professional Guidance for DIY Projects
NORMI Professional Guidance for DIY Projects In general, a well-trained and experienced indoor mold remediation professional (CMR) should be consulted when performing remediation. You may find a NORMI
Mold Response and Remediation Plan
1.0 Policy Statement The University of New Haven has developed a mold response and remediation plan in accordance with best practices set forth by the Environmental Protection Agency (EPA), Occupational
Mold Prevention and Remediation Program
Mold Prevention and Remediation Program TABLE OF CONTENTS INTRODUCTION... 3 Objective... 3 Applicability... 3 Responsibilities... 3 Program Enforcement... 5 HAZARD ASSESSMENT... 6 Visual Inspection...
MOLD RESPONSE AND REMEDIATION PLAN
MOLD RESPONSE AND REMEDIATION PLAN Prepared By: Triumvirate Environmental Developed: April 2011 Last Revised: March 2015 Program Approval Associate Vice President of Public Safety & Administrative Services
Army Facilities Management Information Document on Mold Remediation Issues
Army Facilities Management Information Document on Mold Remediation Issues TG 277 FEBRUARY 2002 NOTICE This publication is essential and current. An administrative review has been performed by the proponent
Excerpts from EPA s Mold Remediation in Schools and Commercial Buildings
www.epa.gov/mold/mold_remediation.html Compiled by SUNY Office for Capital Facilities, May 2014 Page 1 Compiled by SUNY Office for Capital Facilities, May 2014 Page 2 Compiled by SUNY Office for Capital
MOLD REMEDIATION KEY STEPS
MOLD REMEDIATION KEY STEPS The EPA has developed the following guidelines for mold remediation managers. These guidelines are generally helpful, but we believe an expert in the industry should be consulted
Response to Water Intrusion and Mold/Microbial Growth
I. Rationale Sufficient scientific evidence exists to conclude that there is an association between the presence of mold or other agents found in damp indoor environments and various health symptoms. Health
APPENDIX B. EPA s Investigating, Evaluating, and Remediating Moisture and Mold Problems (see EPA website for complete details)
APPENDIX B. EPA s Investigating, Evaluating, and Remediating Moisture and Mold Problems (see EPA website for complete details) Table 1: Water Damage - Cleanup and Mold Prevention Table 1 presents strategies
City of Philadelphia Mold Remediation, Water Damage and Use of Biocides
City of Philadelphia Mold Remediation, Water Damage and Use of s This document provides direction for remediation of building materials in City facilities with potential, visible or laboratory verified
Queen's University Environmental Health & Safety. 1.0 Introduction
1 Introduction The were developed by the Department of Environmental Health & Safety in accordance with the University s Policy Statement on Health and Safety and to ensure compliance with the Ontario
Mold and Mildew Mold and mildew can be detected by sight, smell and touch.
Mold and Mildew Mold and mildew can be detected by sight, smell and touch. Molds are usually black (not unlike the molds that grow in showers and between grout), green or tan in color, but can be in various
CITY OF LOS ANGELES GUIDELINES FOR ASSESSMENT AND REMEDIATION OF MOLD
CITY OF LOS ANGELES GUIDELINES FOR ASSESSMENT AND REMEDIATION OF MOLD The information contained within this manual has been compiled from the following reference sources: The Environmental Protection Agency
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials
Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place
March 2007. Get The Mold Out: Mold Clean-Up Guidance for Residences. Introduction
March 2007 Connecticut Department of Public Health Environmental Health Section Environmental & Occupational Health Assessment Program 410 Capitol Avenue MS # 11EOH, PO Box 340308 Hartford, CT 06134-0308
Industrial Hygiene/ Preventive Medicine Mold Assessment Guide
Industrial Hygiene/ Preventive Medicine Mold Assessment Guide TG 278 February 2002 NOTICE This publication is essential and current. An administrative review has been performed by the proponent office
ASBESTOS SCIENCE TECHNOLOGIES, INC.
ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - [email protected] Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report
University of Nevada, Reno Facilities Services Department STANDARD OPERATING PROCEDURE. Facilities Maintenance Services
University of Nevada, Reno Facilities Services Department STANDARD OPERATING PROCEDURE Facilities Maintenance Services Indoor Flood Cleanup and Mold Prevention DATE: 6/24/15 REVISED: PURPOSE This University
Old Dominion University Mold Management Plan
OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY 5255 Hampton Blvd. Spong Hall, suite 2501 Norfolk, Virginia 23529 Phone: (757) 683-4495 Fax: (757) 683-6025 Occupational Safety & Health Environmental Health Laboratory
University of Vermont
University of Vermont Department of Physical Plant Burlington, Vermont WATER INTRUSION GUIDELINES In accordance with: IIRC S500 IIRC S520 EPA Document 402-K-01-001 REVISED AND DISTRIBUTED BY: THE UNIVERSITY
Indoor Flood Cleanup and Mold Remediation Standard Operating Procedure (SOP)
Indoor Flood Cleanup and Mold Remediation Standard Operating Procedure (SOP) 1.0 Purpose The purpose of this SOP is to outline proper methods for cleanup and disposal following an indoor water release
MOLD REMEDIATION Kathleen Parrott, Ph.D. Professor of Housing, Virginia Tech
MOLD REMEDIATION Kathleen Parrott, Ph.D. Professor of Housing, Virginia Tech Virginia Cooperative Extension has three publications to help you deal with mold in your home: Mold Basics: What is mold? How
Stachybotrys chartarum a mold that may be found in water-damaged homes
Stachybotrys chartarum a mold that may be found in water-damaged homes November 2000 Environmental Health Investigations Branch California Department of Health Services Stachybotrys chartarum ecology Stachybotrys
Get The Mold Out: Mold Clean-Up Guidance for Residences. Introduction
Connec cut Department of Public Health Environmental & Occupa onal Health Assessment Program Environmental Health Sec on 410 Capitol Avenue, MS # 11EOH, PO Box 340308 Har ord, CT 06134-0308 Telephone:
WATER DAMAGE INVESTIGATION. Massachusetts Gaming Commission 101 Federal Street Boston, Massachusetts
WATER DAMAGE INVESTIGATION Massachusetts Gaming Commission 101 Federal Street Boston, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental Health Indoor Air Quality
University of Pittsburgh Safety Manual. EH&S Guideline Number: 01-007 ASBESTOS
Page 1 of 5 The inhalation of asbestos fibers in excess amounts can lead to chronic lung disease. Our knowledge of these health effects comes from studies of workers exposed routinely to high concentrations
An Informational Pamphlet. 416 South East Street Lebanon, OH 45036
An Informational Pamphlet 416 South East Street Lebanon, OH 45036 What is Mold? Mold is a type of fungus that is present in our natural environment. Mold spores, which are tiny microscopic seeds, can
Restoring your Property: How to be prepared for Rapid Response to Flood Damage
Restoring your Property: How to be prepared for Rapid Response to Flood Damage After a flood, the restoration process can be long and complex, particularly for large commercial properties. Failure to apply
Regulations & Guidelines
Regulations & Guidelines Short History of Mold Standards Leviticus 13: 47-50, 14: 39-47 Initial assessment by priest; follow-up visit in 7 days If mold spreads to walls, tear out contaminated stones and
INDOOR WATER INTRUSION (INDOOR WATER LINE BREAKS) Region 8 Sustainability & Environmental Management System
1.0 Purpose & Scope The purpose of this procedure is to provide a standardized approach to handle the unwanted entry of water, known as water incursions or intrusions into an indoor environment. This procedure
WATER DAMAGE INVESTIGATION. Massachusetts Department of Public Utilities 1 South Station Boston, Massachusetts
WATER DAMAGE INVESTIGATION Massachusetts Department of Public Utilities 1 South Station Boston, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental Health Indoor
MOLD INSPECTION REPORT. UCD Anschutz Medical Campus Building 402 12474 E. 19 th Ave. Aurora, CO 80045
MOLD INSPECTION REPORT For the Subject Property: UCD Anschutz Medical Campus Building 402 12474 E. 19 th Ave. Aurora, CO 80045 Report Date: August 7, 2015 Inspection/Testing Date: August 1, 2015 SET Project:
Mold Investigation Summary Report
Gold Health and Safety Consulting, Inc. 4001 Inglewood Ave., Suite 101-292, Redondo Beach, CA 90278 (310) 219-1955 (310) 219-1934 - Fax SUBJECT PROPERTY LOCATED AT: 4405 Tomorrowland Ave., Disneyland,
CLEANING CONTENTS FROM MOLD-CONTAMINATED ENVIRONMENTS
Information Series #200, September, 2004 CLEANING CONTENTS FROM MOLD-CONTAMINATED ENVIRONMENTS Mold growth and associated contamination in buildings continues to garner public attention. While the insurance
UI Procedures for Asbestos Management
UI Procedures for Asbestos Management The University of Iowa Rev.12/12/2012 These procedures apply to employees and contractors involving the identification, work on, removal, or repair of asbestos-containing
Remediation of Mold and Bacteria from Clean, Gray and Black Water Contamination in Buildings
LOSS CONTROL REFERENCE NOTE : from Liberty Mutual Insurance Remediation of Mold and Bacteria from Clean, Gray and Black Water Contamination in Buildings HIGHLIGHTS: Provides guidelines for remediating
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material
Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace
The National Institutes of Heath
The National Institutes of Heath Moisture and Mold Remediation Standard Operating Procedures August 2014 Technical Assistance Branch Division of Occupational Health and Safety, ORS I. Overview Introduction
Mold Remediation in Occupied Homes
building science.com 2008 Building Science Press All rights of reproduction in any form reserved. Mold Remediation in Occupied Homes Research Report - 0210 January-2002 Joseph Lstiburek, Terry Brennan
Clean Water: Supply side potable water, not wastewater. Gray Water/Sewage: Wastewater originating from a drain (sink, toilet, urinal).
Procedures for Emergency Responses to Flooding and Building Water Intrusion PURPOSE: To establish uniform, sanitary, and systematic procedures for responding to flooding and water intrusion emergencies.
Got Mold? Frequently Asked Questions About Mold
Office of Environmental Health & Safety Got Mold? Frequently Asked Questions About Mold What are molds? With more than 100,000 species in the world, it is no wonder molds can be found everywhere. Neither
Guidelines for Cleaning Staff on Managing Mould Growth in State Buildings
Guidelines for Cleaning Staff on Managing Mould Growth in State Buildings Prepared by the State Claims Agency 2 Index 1. Background 2. What are moulds? 3. What are the possible health effects? 4. How do
Procedures for Gray or Black Water Remediation from Flooding Contamination in Buildings
LOSS CONTROL REFERENCE NOTE : from Liberty Mutual Insurance Procedures for Gray or Black Water Remediation from Flooding Contamination in Buildings HIGHLIGHTS: Gray water or black water from flooding may
Mold Remediation in Schools and Commercial Buildings
EPA 402-K-01-001 September 2008 www.epa.gov/mold Mold Remediation in Schools and Commercial Buildings Indoor Air Quality (IAQ) Acknowledgements This document was prepared by the Indoor Environments Division
Water should be removed as soon as possible once the safety of the structure has been verified.
FACT SHEET Posted October 18 2005 Check List for Infection Control Concerns when Reopening Healthcare Facilities Closed due to Extensive Water and Wind Damage Prior to opening a healthcare facility that
IUB Water Damage Restoration Guideline
IUB Water Damage Restoration Guideline Purpose The IUB Water Damage Restoration guideline was developed to ensure that all water intrusions are handled in a professional manner which includes the latest
Water Incursion Standard Operating Procedure
Water Incursion Standard Operating Procedure Purpose: To provide a standardized procedure in the event of water incursion into any Penn State University facility. References: A Brief Guide to Mold, Moisture
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate
WATER INFILTRATION INTO BUILDINGS: Part 1: Mold in Buildings General Information
WATER INFILTRATION INTO BUILDINGS: Part 1: Mold in Buildings General Information Part 2: Guidelines for Managing Water Infiltration into Buildings Roles & Responsibilities Part 3: Guidelines for Facilities
CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program
CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program Guidance Concerning Remediation and Prevention of Mold Growth and Water Damage in Public Schools/Buildings to Maintain Air
Please note that this document presents recommendations on mold remediation. EPA does not regulate mold or mold spores in indoor air.
Mold Remediation in Schools and Commercial Buildings Acknowledgements This document was prepared by the Indoor Environments Division (IED) of the U.S. Environmental Protection Agency. IED would like to
Re: Addendum to Preliminary Water Damage Report, Mendocino Public Health Branch, 1120 South Dora Street, Ukiah, CA
IAS 960 Ms. Kristin McMenomey Risk Manager County of Mendocino 841 Low Gap Road Ukiah, CA 95482 Re: Addendum to Preliminary Water Damage Report, Mendocino Public Health Branch, 1120 South Dora Street,
ASBESTOS MANAGEMENT PROGRAM
ASBESTOS MANAGEMENT PROGRAM September 2015 Asbestos Management Program Table of Contents I. Purpose II. III. IV. Definitions Identification of Asbestos Asbestos Sampling V. Notification and Labeling VI.
Commonwealth of Kentucky Cabinet for Health and Family Services Department for Public Health Division of Public Health Protection and Safety
June 2, 2004 Commonwealth of Kentucky Cabinet for Health and Family Services Department for Public Health Division of Public Health Protection and Safety 275 East Main Street HS1EB Frankfort, KY 40621
NYU Safety Policy Manual
NYU Safety Policy Manual Page 1 of 6 Subject: Mold Prevention, Assessment, and Remediation Program Policy No. 167 ISSUE DATE REPLACES ORIGINATOR APPLICATION NYU Washington Square Campus PURPOSE The purpose
Mold Remediation Practices
Lorman Educational Services Mold Remediation Practices Presented by: A. James Partridge, PE James Partridge Consulting, LLC 925 South Adams Road Birmingham MI 48009-7039 248.645.1465 voice 248.645.1590
MOLDS & REMEDIATION TIPS
MOLDS & REMEDIATION TIPS Table of Contents Introduction... 3 Prevention... 4 Investigating, Evaluating & Remediating Moisture and Mold Problems... 4 Contents... 4 Cleanup Methods... 4 Personal Protective
Mold Basics. Why is mold growing in my home?
Mold Basics The key to mold control is moisture control. If mold is a problem in your home, you should clean up the mold promptly and fix the water problem. It is important to dry water-damaged areas and
Safety Policy Manual Policy No. 112
Policy: Mold Prevention, Assessment and Remediation Program Page 1 of 9 APPLICATION NYU Langone Medical Center (NYULMC) POLICY SUMMARY NYULMC is committed to protecting employees, patients, and visitors
New Protocol for the Assessment and Remediation of Indoor Mold Growth
New Protocol for the Assessment and Remediation of Indoor Mold Growth Ed Light 1,*, Roger Gay 1 and James Bailey 1 1 Building Dynamics, LLC, Ashton MD (USA) *Corresponding email: [email protected]
NADCA GENERAL SPECIFICATIONS FOR THE CLEANING OF COMMERCIAL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS
NADCA GENERAL SPECIFICATIONS FOR THE CLEANING OF COMMERCIAL HEATING, VENTILATING AND AIR CONDITIONING SYSTEMS National Air Duct Cleaners Association 1518 K Street, N.W. Suite 503 Washington, DC 20005 (202)
SECTION 23 01 30.51 HVAC AIR-DISTRIBUTION SYSTEM CLEANING
SECTION 23 01 30.51 HVAC AIR-DISTRIBUTION PART 1 - GENERAL 1.1 SUMMARY A. Section includes cleaning of interior surfaces of HVAC equipment. The HVAC equipment cleaning work includes the following: 1. Air
CERTIFIED LEAD-BASED PAINT RENOVATION CONTRACTOR. License Requirements & Work Practice Standards
CERTIFIED LEAD-BASED PAINT RENOVATION CONTRACTOR License Requirements & Work Practice Standards License Required By April 22, 2010, construction contractors that perform renovation on certain older buildings
Mould Mould A Basic Guide
Mould A Basic Guide Summary Mould is a fact of life. Moulds will grow practically everywhere people live and work. Mould is recognized as an occupational hazard for indoor workers as well as outdoor workers
ENVIRONMENTAL HEALTH CONSULTANTS
Ti Forensic Analytical ENVIRONMENTAL HEALTH CONSULTANTS Mold Investigation Report Findings of Initial Assessment Emerson Elementary School 2800 Forest Avenue Berkeley, CA July 18, 2013 Prepared for: Kevin
Radford University. Indoor Air Quality Management Plan
Radford University Indoor Air Quality Management Plan Spring 2015 Introduction Concerns with Indoor Air Quality (IAQ) have increased since energy conservation measures were instituted in office buildings
Mold. Clean Up, Removal, Safety Concerns
Mold & Clean Up, Removal, Safety Concerns What is Mold? What are the Symptoms? Should I be concerned? What is Toxic Mold? Molds are fungi that can be found both indoors and outdoors. It s not know how
Nick s Inspection Services
Nick s Inspection Services 909 Shorthorn Grain Valley Mo. 64029 Phone: 816-355-0368 Cell: 816-225-5783 Email: [email protected] Building Inspection Report and Protocol Inspection Date: 08-20-14
MOLD FAQs. 1. What is mold and where does it live? 2. How can mold affect my health?
MOLD FAQs 1. What is mold and where does it live? Molds are microscopic fungi that are part of the natural environment. They can grow almost anywhere (inside and out), but live especially in the soil outside.
Mold Questions and Answers Questions and Answers on Stachybotrys chartarum and other molds
Questions and Answers on Stachybotrys chartarum and other molds Questions and Answers 1. I heard about "toxic molds" that grow in homes and other buildings. Should I be concerned about a serious health
Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High
Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High School District Industry Standards Damage Assessments
Asbestos Work Permit Procedures
These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,
Controlling Condensation On CWP Insulation BY ED LIGHT, MEMBER ASHRAE; JAMES BAILEY, P.E., MEMBER ASHRAE; AND ROGER GAY
This article was published in ASHRAE Journal, Decemeber 2014. Copyright 2014 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without
Lead Exposure Management Plan
Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project
Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations
WATER DAMAGE/MOLD INVESTIGATION. Massachusetts Department of Developmental Services 68 North Main Street Carver, Massachusetts
WATER DAMAGE/MOLD INVESTIGATION Massachusetts Department of Developmental Services 68 North Main Street Carver, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental
WATER DAMAGE INVESTIGATION. Massachusetts Department of Children and Families 33 East Merrimack Street Lowell, Massachusetts
WATER DAMAGE INVESTIGATION Massachusetts Department of Children and Families 33 East Merrimack Street Lowell, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental
FACILITIES ENVIRONMENTAL TECHNICAL UNIT SPECIAL CONSTRUCTION WATER INTRUSION AND MOLD REMEDIATION PROCEDURE
Los Angeles Unified School District Facilities Services Division FACILITIES ENVIRONMENTAL TECHNICAL UNIT SPECIAL CONSTRUCTION WATER INTRUSION AND MOLD REMEDIATION PROCEDURE FACILITIES ENVIRONMENTAL TECHNICAL
ASBESTOS MANAGEMENT PLAN
ASBESTOS MANAGEMENT PLAN SAN JOSE STATE UNIVERSITY Environmental Health & Occupational Safety Asbestos Management Plan 1.0 Introduction 2.0 Policy 3.0 Responsibilities 4.0 Contract Administration 5.0 In-House
Managing Water Infiltration into Buildings. Water Damage Check List
Managing Water Infiltration into Buildings A Systematized Approach for Remediating Water Problems in Buildings due to Floods, Roof Leaks, Potable Water Leaks, Sewage Backup, Steam Leaks and Groundwater
By Gary Rosen, Ph.D., Certified Mold Free, Corp.
Texas Mold Licensing Laws: Training Requirements By Gary Rosen, Ph.D., Certified Mold Free, Corp. What prompted the Texas Legislature to regulate the mold industry? Which factors shaped the training requirements
BUREAU OF ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program
BUREAU OF ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program Use of Moisture Measuring Devices in Evaluating Water Damage in Buildings July 2007 The evaluation of mold colonization of building
Mold. Guidelines for New Jersey Residents. Understanding Mold Investigations & Remediation
Mold Guidelines for New Jersey Residents Understanding Mold Investigations & Remediation What Services Should I Ask For? What Are Important Inspection Procedures? Is Mold Sampling Helpful? What Information
- WATER DAMAGE RESTORATION -
- WATER DAMAGE RESTORATION - PROTOCOL FOR BIO-REVEAL SAMPLING OF CONDITION 1, 2 AND 3 MOLD & FUNGI CONTAMINATION Statement of Use The Bio-reveal Ultrasnap ATP swabs and the Bio-reveal Systemsure Plus luminometer
Preventing Long-Term Damage from Water Infiltration/Flooding in School Buildings
Preventing Long-Term Damage from Water Infiltration/Flooding in School Buildings A systematized approach for remediating water problems in buildings because of floods, roof leaks, potable water leaks,
WATER DAMAGE/MOLD INVESTIGATION. Massachusetts Department of Transitional Assistance 160 W. Rodney French Blvd New Bedford, Massachusetts
WATER DAMAGE/MOLD INVESTIGATION Massachusetts Department of Transitional Assistance 160 W. Rodney French Blvd New Bedford, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of
LEGAL REVIEW & UPDATE
LEGAL REVIEW & UPDATE There are lots of laws and regulations designed to protect workers, the general public, and the environment. However, not everyone follows the laws. Many people deliberately break