Change Management Plan (CMP)

Size: px
Start display at page:

Download "Change Management Plan (CMP)"

Transcription

1 Change Management Plan (CMP) i

2 Version/Change Record Revision Date Description ii

3 Table of Contents 1.0 Introduction Purpose Plan Scope Document Overview Referenced Documents Plans Work Products, Documents, and Records Roles and Responsibilities Engineering Review Board (ERB) Program Integration Team (PIT) Change Control Board (CCB) Configuration Management Customer Change Management Process and Procedures CR Submit CR ERB decision CR ERB Review CR PIT Review CR CCB Review CR ECR CR Customer Review CR Engineer Resolution CR Change Closure Metrics Number of unplanned outages related to changes number of unauthorized changes Backlog of change requests average time to implement changes Process Best Practice Guidance Notes on What Makes a Good change request Notes Glossary Acronyms List of Figures Figure 1.1 Overview of Change Management Decision Process... 6 Figure 3.1. Change Management Process... Error! Bookmark not defined. iii

4 List of Tables Table 1-1. Referenced Procedures... 7 Table 2-1. Change Management Resources... Error! Bookmark not defined. Table 2-2. Stakeholders and Responsibility/Authority... 8 Table 2-4. Engineering Review Board Membership... 9 Table 2-5. PIT Membership Table 2-6. Change Control Board Membership Table 3-1. Change Classes iv

5 1.0 INTRODUCTION This document provides the plan for managing changes to Configuration Items (CIs) for the program. From this point forward, any type of change to any CI, whether it is to the infrastructure, applications or documentation, will simply be referred as a change to the baseline. 1.1 PURPOSE The purpose of this Change Management Plan (CMP) is to define how changes to CIs are requested, evaluated, adjudicated, documented and incorporated. As the design evolves from one configuration to the next, changes must be recorded and documented in terms of their possible impact on the initial system requirements. Key Plan Objectives Establish an efficient methodology for requesting, evaluating, and adjudicating proposed changes to CIs. Establish reasonable controls for affecting changes to CIs. Define the roles and responsibilities of the parties involved in requesting, adjudicating, and implementing changes to CIs. Create an audit trail of all changes to CIs. 1.2 PLAN SCOPE The effort specifically addressed by this plan encompasses all of the change management activities to be undertaken by the program team, including its leadership and subcontractors (where applicable), to manage the program CIs and adherence to customer requirements. The CMP controls the changes to all CIs on the program. As shown in Figure 1.1, for a change to be approved, the first decision is whether the change is major enough to warrant sending it to the Engineering Review Board (ERB). If the change being requested is determined to be of minor impact, and therefore not in need of ERB approval, the change can be approved at this stage. If the decision is made to send it to the ERB, the CMP requires the change request to pass through as many as four different decision points before approval. The decisions points are the Engineering Review board (ERB), the Program Integration Team (PIT) for Class 1 changes, the Change Control Board (CCB) and the customer. All participants play a vital role in the change management process. This plan may be updated due to changes in the contract, customer direction, program scope, or requirements. Plans and processes are reviewed for update as needed and revised as required, to ensure consistency with customer requirements. More frequent reviews and updates are performed as necessary to ensure plans are current and useful. 5

6 Figure 1.1 Overview of the Change Management Approval Process 6

7 1.3 DOCUMENT OVERVIEW Section 1.0: Describes the scope and content of this plan and its relationship to other program plans and processes. Most of Section 1 will be defined in the Management Plan. Section 2.2.0: References the plans and stakeholders for performing change request/approval activities. Section 0: Describes the Change Management Process Section 4.0: Details the metrics used to monitor the Change Management Process Section 4.0: Describes best practices for generating CRs and ECRs Section 6.0: Provides direction to the glossary and list of acronyms used in this plan 1.4 REFERENCED DOCUMENTS The documents listed in this section form a part of this plan to the extent specified herein. In the event of conflict between the documents referenced herein and the contents of this plan, as defined by approved waivers and deviations, the contents of this plan, upon final approval, are considered the superseding authority. For all other conflicts, higher level manuals or plans are considered the superseding authority, until the conflict is resolved. The latest versions of these documents are assumed to be applicable unless otherwise specified by including the specific version. Refer to the Master Document List for the latest revision and date REFERENCED PRCEEDURES The following procedures are specifically referred to in this document. Table 1-1. Referenced Procedures Incident Management Problem Management Capacity Management Availability Management Configuration Management Title 7

8 2.0 PLANS This section defines the plans for performing change management activities. 2.1 WORK PRODUCTS, DOCUMENTS, AND RECORDS All program work products, documents and records to be placed under Configuration Management (CM) control, including the appropriate levels of control, are defined in the CMP. 2.2 ROLES AND RESPONSIBILITIES Stakeholders specific to change management are identified in Table 2-1. Table 2-1. Stakeholders and Responsibility/Authority Stakeholder Chief Engineer Project Manager Change Manager Change Coordinator Change Builder Configuration Manager Customer Change Request Responsibility/Authority Member of the ERB and CCB Ensures that changes to CIs are controlled, managed, and documented Reviews Change Requests (CR)for impact Manages schedule of changes to technical infrastructure Member of the ERB and CCB Manages the change review/approval process Reviews the risk & impact analysis Member of the ERB and CCB Advises the ERB and CCB on perspective of their respective teams Manages the change process, including risk and impact assessment Documents all changes to CIs in Remedy Responsible for updating the CIs Prepares change implementation plans Responsible for implementing approved changes Monitors the progress of changes Member of the ERB and CCB Technical subject matter expert Responsible for implementing and testing changes Member of the CCB Ensures compliance with the CMP Maintains change management tools and processes Acts as CCB Secretariat Maintains status accounting records Updates CIs upon change approval Accepts/rejects the Engineering Change Request (ECR) through their change board Has final approval authority on customer changes after baseline approval 8

9 2.3 ENGINEERING REVIEW BOARD (ERB) The ERB is a critical part of the change management process. The ERB membership is shown in Table 2-2. Its main responsibility is to ensure compliance to the functional requirements, as well as CIs by reviewing, analyzing, and recommending approval/disapproval of proposed technical solutions for modifications and risk mitigation activities. The ERB ensures a thorough integrated technical review of requirements and recommended corrective actions has occurred. The ERB may meet formally or review/approve the proposed change electronically. The ERB Chair determines the appropriate review method. The standard review time for both electronic and formal reviews is 5 business days unless otherwise directed by the ERB Chair. Upon ERB decision to proceed with an engineering change, the change is reviewed by the PIT (if the change impacts cost, schedule, performance, or presents a risk) and then by the CCB, or it goes straight to the CCB (if there is no impact to cost, schedule, or performance). Table 2-2. Engineering Review Board Membership Board Member Responsibility Authority Chief Engineer Chairs and facilitates ERB Directs ERB activities Authorizes changes to CIs that do not affect program cost, schedule, and/or risk Change Manager Change Coordinator(s) Change Builder(s) ERB Secretariat Security Manager Plans and schedules change requests Represent respective team(s) Provide technical input Acts as ERB Secretariat Assesses security impact of the change Reviews the change request for completeness and adequacy Assess risk and impact Routes the change request for approval based on the change class, priority, risk and impact Plans, prepares and supports delivery to the CCB of all proposed Class 2 changes Advises ERB on the system impact of the change from perspective of respective team Act as an information resource Ensures compliance with the change management process Keeps minutes Develops and maintains schedule/timeline Advises ERB on the security impact of the change 9

10 2.4 PROGRAM INTEGRATION TEAM (PIT) The PIT plans, prepares and supports delivery to the CCB of all proposed Class 1 changes (i.e., changes that impact cost, schedule or performance). PIT membership is shown in Table 2-3. Table 2-3. PIT Membership Position Responsibility Authority PIT Chair Daily program performance management Program integration Risk management Executability of program baseline Quality management system Configuration/change management Planning and scheduling Make day-to-day operational decisions within constraints of contracted commitment and customer expectations Act in absence of Program Manager (PM) Implement and enforce integrity of program processes Integrated Development Provide integrated Environment (IDE) assessment of program Cost/schedule/performance executability to PM reviews Prime Contracts Manager Subcontracts Manager Business Manager Interface with customer contracts team Contract management Execution of subcontracts Subcontract management Teaming agreements/work share Proposal estimating/pricing Business case analysis Commit enterprise to support new and/or revised contracts using enterprise processes as requested by PM Commit enterprise to support new or revised subcontracts using enterprise processes as requested by PM Commit enterprise to support new and/or revised contracts using enterprise processes as requested by PM 2.5 CHANGE CONTROL BOARD (CCB) The CCB governs all of the programs CIs. The CCB responsibilities include: Evaluate the scope of the change request and involve relevant functional teams in the technical evaluation Evaluate the request for risks and consequent impacts on cost, schedule, and performance Evaluate the request for program-wide impacts from the Chief Engineer 10

11 Accept the change as a valid modification to the applicable CIs Assign the change to a Change Coordinator Determine the time frame of the change delivery Generate the Engineering Change Request (ECR) to be submitted to the customer Document the change and update the configuration status accounting Interface with the customer to ensure that the CIs are internally consistent and executable The core members of the CCB are shown in Table 2-4. Representatives associated with other program support operations, such as Business Administration, Contracts and Quality Assurance (QA), support the CCB as required. CCB members review the disposition of proposed ERB accepted changes, and determine the total impact of the change. Table 2-4. Change Control Board Membership Board Member Responsibility Authority Change Manager Chairs CCB Directs CCB activities Authorizes expenditure of program resources Chief Engineer Business Manager PIT Lead Configuration Manager Change Coordinator(s) Change Builder(s) Security Manager Represents engineering Represents NGC enterprise and business operations interests Facilitates CCB Represents PIT Act as CCB Secretariat Represent respective team(s) Provide technical input Assesses security impact of the change Advises PM on NGC technical perspective, customer perspective, and integrity of product baseline Advises PM on NGC enterprise perspective Implements PM direction on contract matters Advises PM on integrity (executability) of program baseline Keeps minutes Develops and maintains schedule/timeline Advises CCB on the system impact of the change from perspective of respective team Prepares and share change implementation plans with CCB Act as an information resource Advises CCB on the security impact of the change 11

12 Table 2-4. Change Control Board Membership Board Member Responsibility Authority Customer Insight as a consultative member and approver of ECRs Advises PM on customer perspective Approves ECRs 2.6 CONFIGURATION MANAGEMENT Configuration Management provides integral control functions in support of the technical baseline management process. Configuration Management includes the process of managing requirements and physical configurations and the documents, data, and other records that identify those configurations. Configuration Management responsibilities in the change management process include: Ensure compliance with the change management process Maintain change management tools and processes Act as CCB Secretariat Maintain status accounting records Update baseline upon change approval 2.7 CUSTOMER The customer has insight into the change management process as a consultative member and ECR approver of the CCB. All Class I changes to an approved baseline are handled through the ECR process. (See class definitions Table 3-1.) Refer to Configuration Management Process overview below. Once an ECR has been created, the change is forwarded to the customer and is approved or rejected through their change board. They are the final approval authority on changes after baseline approval. 12

13 3.0 CHANGE MANAGEMENT PROCESS AND PROCEDURES This section describes the Change Management Process, shown in Error! Reference source not found., to request, evaluate, and adjudicate proposed Change Requests (CRs) to the technical and non-technical baselines. 3.1 CR SUBMIT Anyone may identify a CR. Whomever identifies the change is responsible for entering the CR (or changing the incident to a CR). The request can be a result of management direction, customer direction, changes in the contract, etc. A CR can be made for any controlled program baseline such as design, requirements, schedule, documentation, etc. The request, along with all pertinent information, is entered into the Remedy OnDemand Change Management database. In this manner, all of the details of the CR can be accessed and reviewed by the ERB members during the ERB. 3.2 CR ERB DECISION Once a change is entered into Remedy, the Project Manager and Change Manager will receive and notification. The two will review the CR and determine whether it will have a major or minor impact to the systems and the CIs. If the impact is minor, they will initiate an immediate change in the Remedy system. If the impact is major, they will move it to ERB, changing the status in Remedy to reflect their decision. 3.3 CR ERB REVIEW The ERB chair will receive notification when a CR is submitted to the Remedy database and indicate a major change. The ERB chair will determine if and when formal meetings will be scheduled to address any CRs. The ERB has the initial authority to approve or reject all requests. All CRs and ECRs are reviewed in Remedy. They can be viewed in order of highest to lowest priority if more than one is up for review. A CR may be sent back to the submitter for more details, rejected, or approved. If approved, the ERB determines the Class of the change. See Table 3-1 for Change Classes. Class I Changes go to the PIT for analysis. Class II changes go straight to the CCB for review. Table 3-1. Change Classes Change Class Class I Criteria Any impact to cost, schedule, product performance, the customer, and/or that may increase program risk. Specifically: Affect system, maintenance, or other incremental cost elements May push program scheduling or milestones outside tolerances Impact on form, fit, or function of a CI, particularly interface and compatibility characteristics Introduce significant and measurable Approval Authority CCB final approval Authority ERB reviews and approves all submitted changes prior to escalation to CCB PIT if the change affects cost, 13

14 Table 3-1. Change Classes Change Class Class II Criteria change in the operational or performance characteristics of the capability, including reliability and logistic supportability or processes Require retrofit action Have safety or security implications (including safety-critical software issues) Require amendment to delivered operational or maintenance documentation Require operator or maintainer training if accepted Affect guarantees or warranties on deliverables Impact to any customer expectation where we are exceeding and now can only meet, or exceed by a lesser amount Any change to a CI that is not Class I (does not impact cost, schedule, product performance, the customer, and/or increase program risk) Example: Documentation amendments to correct errors or update version/edition numbers Example: Any proposal to substitute a component with one that is built to the same Build Standard Example: Manufacturer-imposed changes to the internals of a spare that do not affect the item s functional or physical performance or substitution of technical components built to the same Build Approval Authority schedule or performance, the PIT will provide data for analysis ERB reviews and approves all submitted changes 3.4 CR PIT REVIEW The PIT chair receives an notification when a new CR is assigned for review. The PIT members review the proposed change, perform an analysis, and disposition the CR in Remedy to include the PITs recommendation. The PIT has the authority to approve or overturn and reject any ERB-approved CR. A CR may be sent back to the submitter for more details, rejected, or approved. If the change is accepted, the PIT determines if the change will impact the customer. If it does not, the change package/briefing, working with the Change Coordinator(s), is updated and the CR is sent to the CCB for review. If the CR does impact the customer, 14

15 the PIT will create an ECR (in Remedy), update the package/briefing, and the ECR will be sent to the CCB for review. 3.5 CR CCB REVIEW The CCB chair will receive an notification that there is a CR that needs to be reviewed. The CCB has final authority to approve or overturn and reject any ERB or PITapproved CR/ECR. A CR may be sent back to the submitter for more details, rejected, or approved. If a CR or ECR is rejected by the CCB, a determination will be made for inclusion in the Unapproved Change List for future opportunity monitoring. 3.6 CR If a CR is approved, and there is no impact to the customer, the Change Coordinator is notified to make the change to the CI. 3.7 ECR If an ECR is approved, the Change Coordinator is notified to create a formal ECR from the ECR record in the Remedy database for submission to the customer. 3.8 CR CUSTOMER REVIEW The customer receives and reviews the formal ECR. If rejected, the change is closed. The CCB will consider if the change will be included in the Unapproved Change List for future opportunity monitoring. If accepted, the CCB notifies the NGC team (item owner, and scheduler, and/or Business Manager, as applicable) to proceed with the approved change. The Change Coordinator implements the change, updates the CIs and the Configuration Manager updates the baseline. 3.9 CR ENGINEER RESOLUTION When a CR/ECR is assigned to someone to make the change or resolve the problem, an is sent notifying them of their assignment. When completed, the assignee reports the completion of the change, or resolution of the problem, in Remedy CR CHANGE CLOSURE CR When a CR is approved by the CCB, an is sent to the assignee to complete the change. The assignee processes the change and submits to the Configuration Manager to update the baseline. The Configuration Manager will close the CR once the change has been received and the item is back under CM control. Note: Only the Configuration Manager can close a CCB approved CR. ECR When an ECR is approved by the CCB, it is assigned to the appropriate Functional Lead to process a formal ECR for delivery to the customer. 1. The assignee generates the formal ECR and submits it to the Configuration Manager for delivery. 2. The Configuration Manager delivers the Formal ECR to the customer and then awaits acceptance/rejection of the ECR. 15

16 3. Upon approval, the ECR is assigned for completion of the change. 4. The assignee processes the change and submits it to the Configuration Manager for to update the baseline. The Configuration Manager will close the ECR once the change has been received and the item is back under CM control. 16

17 4.0 METRICS The primary objective of Change Management is to enable beneficial changes to be made with a minimum of disruption to IT services. The metrics recommended here are deemed to be effective in identifying procedures that lead to efficient, accurate, controlled and prompt handling of changes. 4.1 NUMBER OF UNPLANNED OUTAGES RELATED TO CHANGES Changes may very well involve a planned system outage to implement, but should not result in unplanned outages. This number should be very low over any time period and ideally zero. And number other than zero should initiate an evaluation into the efficacy of the procedures used to evaluate changes in the test environment. 4.2 NUMBER OF UNAUTHORIZED CHANGES The number of unauthorized changes in a properly-operating CM system is zero. This is the number expect over any time period. Any number other that zero should trigger an investigation into the cause. 4.3 BACKLOG OF CHANGE REQUESTS As the system matures, the backlog of CRs in Remedy is expected to decline. Should there be a material increase in the backlog of CRs in Remedy over some time period, a root cause analysis should be performed to understand why. 4.4 AVERAGE TIME TO IMPLEMENT CHANGES As the system support staff gains experience implementing changes on the system over time, there should be a decrease, if even slightly, in the average time to implement changes to the system. Should there be a material increase in the average time to implement changes, a satisfactory explanation should be ascertained, and additional personnel training may be necessary. 17

18 5.0 PROCESS BEST PRACTICE GUIDANCE In practice, it may prove advisable to by-pass certain aspects of the defined process. This is allowable so long as the intent of the process is maintained, which is to control and document product changes and problems/defects. The ERB or CCB must approve such actions. As they are determined, these allowable expediencies will be documented here. The intent of this section is to allow program staff to follow the process, while not being held back due to time constraints on the program. The intent is NOT to allow the process to be circumvented. 5.1 NOTES ON WHAT MAKES A GOOD CHANGE REQUEST The following are notes to help authors and engineers adhere to good CR practice. SUBMIT All applicable CR definition fields should be filled in by the submitter. The Short Title should be a brief descriptive name evoking the basic nature of the change/problem. Leave the details for the Description field. The Description should describe the change being requested or observed behavior that indicated there was a problem, and what was expected. For problems, be aware that the submitter, analysis assignee, and resolution assignee may be different people, possibly separated in both space and time. A good description is key to valuable troubleshooting. The steps to re-create the observation should detail the process necessary (test setup and steps if applicable) to reproduce the observed behavior. The Priority should be suggested. REVIEW The ERB/CCB may choose to expedite a CR/ECR through the process by advancing it to an appropriate state. The ERB/CCB should maintain notes in the Comments field describing such decisions. PROBLEM ANALYSIS All applicable CR analysis fields should be filled in by the analysis assignee. The Comments field should describe the nature of the error discovered by troubleshooting the described problem. The assignee should execute the procedure detailed in the Steps to Re-create. If either the Detail Description or the Steps to Re-create are inadequate to allow re-creation of the problem, the assignee should endeavor to elicit the information from the CR author, or have the ERB/CCB return the PCR to the author for enhancement. Every time the CR is analyzed (assuming Failed Regression), the analysis is appended to the Analysis field. Never delete previous data. The Time to Complete Analysis field should include the number of minutes it took to perform the analysis. Increment the value each time the PCR is analyzed. Never delete previous data. 18

19 The Impacts field should describe how the PCR will impact the program, whether it is cost, schedule, etc. RESOLUTION All applicable CR fields should be filled in by the Resolution Assignee. The Comments field should detail what the actual fix was. Each time the CR is fixed (assuming Failed Regression), the resolution is appended to the Comments field. Never delete previous data. The Time to Correct time should include the number of minutes it took to implement the fix, including testing. Increment the value each time the PCR is fixed. Never delete previous data. TEST All applicable CR fields should be filled in by test personnel. The Name Tester field should contain the name of the tester who performed the System Test. The Actual Time to Complete Testing should indicate the number of minutes it took to test the CR. Never delete previous data. The Version Fix Verified field indicates in which version the fix was tested. Any new observations about the CR should be included in Comments. Assignees should review the Comments when a CR is returned after a Failed Regression. 19

20 6.0 NOTES This section defines terms and acronyms typically used across the program. 6.1 GLOSSARY All glossary terms are defined and managed in the Master Glossary of Terms. 6.2 ACRONYMS All acronyms are defined and managed in the Master Acronym List. 20

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon

ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon Executive Summary: This document is seven pages. Page one is informational/background only. What follows over the next six pages are

More information

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK Office of Safety and Mission Assurance NASA-GB-9503 SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK AUGUST 1995 National Aeronautics and Space Administration Washington, D.C. 20546 PREFACE The growth in cost

More information

CMS Policy for Configuration Management

CMS Policy for Configuration Management Chief Information Officer Centers for Medicare & Medicaid Services CMS Policy for Configuration April 2012 Document Number: CMS-CIO-POL-MGT01-01 TABLE OF CONTENTS 1. PURPOSE...1 2. BACKGROUND...1 3. CONFIGURATION

More information

ITSM Process Description

ITSM Process Description ITSM Process Description Office of Information Technology Incident Management 1 Table of Contents Table of Contents 1. Introduction 2. Incident Management Goals, Objectives, CSFs and KPIs 3. Incident Management

More information

Change Management Process. June 1, 2011 Version 2.7

Change Management Process. June 1, 2011 Version 2.7 Change Management Process June 1, 2011 Version 2.7 Contents Document Control... 3 Overview... 4 Definition of a Change... 5 Description... 5 Objectives... 5 Key Terms & Definitions... 6 Change Management

More information

CHAPTER 7 Software Configuration Management

CHAPTER 7 Software Configuration Management CHAPTER 7 Software Configuration Management ACRONYMS CCB CM FCA MTBF PCA SCCB SCI SCM SCMP SCR SCSA SEI/CMMI SQA SRS USNRC INTRODUCTION Configuration Control Board Configuration Management Functional Configuration

More information

Change Management Process Guide

Change Management Process Guide XXXXX (XX) IT Operational Process Change Management Process Guide XXXXX Information Technology Preface The purpose of this document is to outline the procedures that govern the Change Management process

More information

Software Configuration Management Plan

Software Configuration Management Plan For Database Applications Document ID: Version: 2.0c Planning Installation & Acceptance Integration & Test Requirements Definition Design Development 1 / 22 Copyright 2000-2005 Digital Publications LLC.

More information

Draft Copy. Change Management. Release Date: March 18, 2012. Prepared by: Thomas Bronack

Draft Copy. Change Management. Release Date: March 18, 2012. Prepared by: Thomas Bronack Draft Copy Change Management Release Date: March 18, 2012 Prepared by: Thomas Bronack Section Table of Contents 10. CHANGE MANAGEMENT... 5 10.1. INTRODUCTION TO CHANGE MANAGEMENT... 5 10.1.1. PURPOSE OF

More information

Software and Hardware Configuration Management

Software and Hardware Configuration Management DOWNLOADED AND/OR HARD COPY UNCONTROLLED Verify that this is the correct version before use. AUTHORITY DATE Jeffrey Northey (original signature on file) IMS Manager 07/09/2014 Doug Dorrer (original signature

More information

hi Information Technologies Change Management Standard

hi Information Technologies Change Management Standard hi Information Technologies Change Management Standard Classification Service Delivery Standard # SVD-002 Approval Authority Chief Information Officer Implementation Authority Director, Service Delivery

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

Columbia College Process for Change Management Page 1 of 7

Columbia College Process for Change Management Page 1 of 7 Page 1 of 7 Executive Summary Columbia College's Process for Change Management is designed to provide an orderly and documented method in which changes to the College's computing environment are requested

More information

The purpose of this document is to define the Change Management policies for use across UIT.

The purpose of this document is to define the Change Management policies for use across UIT. UNIVERSITY OF UTAH - IT OPERATIONS POLICY UIT CHANGE MANAGEMENT POLICY Chapter or Section: Information Technology ID SOP-CNFM.001 UIT Configuration Management Policy Rev Date Author Change 4.4 9/29/11

More information

D R A F T. Resource Ordering and Status System (ROSS) Software Configuration Management Guidelines

D R A F T. Resource Ordering and Status System (ROSS) Software Configuration Management Guidelines TO #GA81 Resource Ordering and Status System (ROSS) D R A F T Resource Ordering and Status System (ROSS) Software Configuration Management Guidelines June 28, 2000 Version 1.1 Contract: GS-35F-4863G Delivery

More information

Project QA and Collaboration Plan for <project name>

Project QA and Collaboration Plan for <project name> Note: Text displayed in blue italics is included to provide guidance to the author and should be deleted or hidden before publishing the document. This template can be used at it is, or to complete and

More information

Process Description Change Management

Process Description Change Management Process Description Change Management Version 4.1 April, 2013 Document Change Control Version # Date of Issue Author(s) Brief Description 1.0 3/8/13 J.Worthington Initial Draft 2.0 3/25/13 J.Worthington

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

TechExcel. ITIL Process Guide. Sample Project for Incident Management, Change Management, and Problem Management. Certified

TechExcel. ITIL Process Guide. Sample Project for Incident Management, Change Management, and Problem Management. Certified TechExcel ITIL Process Guide Sample Project for Incident Management, Management, and Problem Management. Certified Incident Management Red Arrows indicate that the transition is done automatically using

More information

How To Manage Change Management At Uni

How To Manage Change Management At Uni Change Management Process VERSION 1.0 Version Date: 1 May 2006 Table of Revisions REVISION NUMBER DESCRIPTION OF CHANGES (PARAGRAPH AND OR SECTION NUMBERS FOR REVISION TRACKING) DATE OF CHANGE REVIEWED

More information

PHASE 9: OPERATIONS AND MAINTENANCE PHASE

PHASE 9: OPERATIONS AND MAINTENANCE PHASE PHASE 9: OPERATIONS AND MAINTENANCE PHASE During the Operations and Maintenance Phase, the information system s availability and performance in executing the work for which it was designed is maintained.

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

Infasme Support. Incident Management Process. [Version 1.0]

Infasme Support. Incident Management Process. [Version 1.0] Infasme Support Incident Management Process [Version 1.0] Table of Contents About this document... 1 Who should use this document?... 1 Summary of changes... 1 Chapter 1. Incident Process... 3 1.1. Primary

More information

HP Change Configuration and Release Management (CCRM) Solution

HP Change Configuration and Release Management (CCRM) Solution HP Change Configuration and Release Management (CCRM) Solution HP Service Manager, HP Release Control, and HP Universal CMDB For the Windows Operating System Software Version: 9.30 Concept Guide Document

More information

APPENDIX E TO DIR CONTRACT NO. DIR-TSO-2567 SOFTWARE MAINTENANCE AGREEMENT

APPENDIX E TO DIR CONTRACT NO. DIR-TSO-2567 SOFTWARE MAINTENANCE AGREEMENT APPENDIX E TO DIR CONTRACT NO. DIR-TSO-2567 SOFTWARE MAINTENANCE AGREEMENT This is a Software Maintenance Agreement ( Agreement ) dated as of, (the Effective Date ) by and between ( Customer ) having a

More information

Service Transition. ITIL is a registered trade mark of AXELOS Limited.. The Swirl logo is a trade mark of AXELOS Limited.. 1

Service Transition. ITIL is a registered trade mark of AXELOS Limited.. The Swirl logo is a trade mark of AXELOS Limited.. 1 Service Transition ITIL is a registered trade mark of AXELOS Limited.. The Swirl logo is a trade mark of AXELOS Limited.. 1 Lesson Objectives Service Transition - Introduction - Purpose and Objectives

More information

IT CHANGE MANAGEMENT POLICY

IT CHANGE MANAGEMENT POLICY IT CHANGE MANAGEMENT POLICY PURPOSE The purpose of the IT Change Management Policy is to manage changes in a planned and predictable manner in order to assign resources, assess risk and minimize any potential

More information

Introduction... 4. Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4. RFC Procedures... 5

Introduction... 4. Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4. RFC Procedures... 5 Remedy Change Management Version 3.0 Modified: 10/27/2015 Table of Contents Introduction... 4 Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4 RFC Procedures... 5 Process Flow

More information

Problem Management Fermilab Process and Procedure

Problem Management Fermilab Process and Procedure Management Fermilab Process and Procedure Prepared for: Fermi National Laboratory June 12, 2009 Page 1 of 42 GENERAL Description Purpose Applicable to Supersedes This document establishes a Management

More information

HP Service Manager. Process Designer Content Pack 9.30.1. Processes and Best Practices Guide

HP Service Manager. Process Designer Content Pack 9.30.1. Processes and Best Practices Guide HP Service Manager Process Designer Content Pack 9.30.1 Processes and Best Practices Guide Document Release Date: June, 2012 Software Release Date: June, 2012 1 Legal Notices Warranty The only warranties

More information

MWA Project. Configuration Management Plan

MWA Project. Configuration Management Plan Document No.: 46-01002 Revision: 0004 Date: 22-Oct-2009 MWA Project Configuration Management Plan MWA Project MWA Consortium Copyright 2009, MWA Consortium. All Rights Reserved. Control Status Document

More information

Old Phase Description New Phase Description

Old Phase Description New Phase Description Prologue This amendment of The FAA and Industry Guide to Product Certification (CPI Guide) incorporates changes based on lessons learned and supports the broader use of this guide by providing additional

More information

MWA Project. Configuration Management Plan

MWA Project. Configuration Management Plan Document No.: MWA-XXX-XXX Revision: 0002 Date: 07-OCT-2009 MWA Project Configuration Management Plan MWA Project MWA Consortium Copyright 2009, MWA Consortium. All Rights Reserved. Control Status Document

More information

Cisco Change Management: Best Practices White Paper

Cisco Change Management: Best Practices White Paper Table of Contents Change Management: Best Practices White Paper...1 Introduction...1 Critical Steps for Creating a Change Management Process...1 Planning for Change...1 Managing Change...1 High Level Process

More information

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)

Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial

More information

CONFIGURATION MANAGEMENT PLAN

CONFIGURATION MANAGEMENT PLAN CONFIGURATION MANAGEMENT PLAN Integrated Procurement System U.S. Election Commission i CONFIGURATION MANAGEMENT PLAN TABLE OF CONTENTS Page # 1.0 CONFIGURATION CONTROL...3 1.1 Change Control Board (CCB)...3

More information

Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience

Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience Management Model (CERT-RMM), both developed at Carnegie

More information

Cisco Network Optimization Service

Cisco Network Optimization Service Service Data Sheet Cisco Network Optimization Service Optimize your network for borderless business evolution and innovation using Cisco expertise and leading practices. New Expanded Smart Analytics Offerings

More information

The Newcastle upon Tyne Hospitals NHS Foundation Trust. IT Change Management Policy and Process

The Newcastle upon Tyne Hospitals NHS Foundation Trust. IT Change Management Policy and Process The Newcastle upon Tyne Hospitals NHS Foundation Trust Version No.: 2.0 Effective From: 16 July 2015 Expiry Date: 16 July 2018 Date Ratified: 5 June 2015 Ratified By: Director of IT 1 Introduction IT Change

More information

U.S. Department of Education Federal Student Aid

U.S. Department of Education Federal Student Aid U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle

More information

Baseline Change Control Procedure

Baseline Change Control Procedure Earned Value Management System (EVMS) Implementing Procedures Baseline Change Control Procedure EVMS-P-7 Revision 0 - October, 2006 Change Log Earned Value Management System Procedure Change Log Revision

More information

[name of project] Service Level Agreement

[name of project] Service Level Agreement [name of project] Service Level Agreement Policies and Procedures Posting: Nov.2008 Rev# xxx CIO Sign-Off: Approved and Reviewed By: Date: Document ID: SLA Revision 001 Authors: Disclaimer: Document sign-off

More information

SCHEDULE 3. Milestones and Deliverables. Redacted Version

SCHEDULE 3. Milestones and Deliverables. Redacted Version SCHEDULE 3 Milestones and Deliverables Redacted Version This Schedule 3 sets out the Service Provider s obligations in respect of the milestones and deliverables relating to the implementation and operation

More information

Change Management Process Document

Change Management Process Document Draft August 16, 2009 Version 4.0 (use of CMDB) Important: 1. This is a living document. 2. There will be a review of this document, with potential updates, three to six months following the approval and

More information

Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201

Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 PURCHASE ORDER ATTACHMENT Q-201A Software Quality Subcontractor Survey Questionnaire INSTRUCTIONS FOR PURCHASE ORDER ATTACHMENT Q-201 1. A qualified employee shall be selected by the Software Quality Manager

More information

EXIN IT Service Management Foundation based on ISO/IEC 20000

EXIN IT Service Management Foundation based on ISO/IEC 20000 Sample Exam EXIN IT Service Management Foundation Edition October 2013 Copyright 2013 EXIN All rights reserved. No part of this publication may be published, reproduced, copied or stored in a data processing

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

Christine M. Frye, CIPP/US, CIPM, Chief Privacy Officer, Bank of America

Christine M. Frye, CIPP/US, CIPM, Chief Privacy Officer, Bank of America Christine M. Frye, CIPP/US, CIPM, Chief Privacy Officer, Bank of America Dana Simberkoff, JD, CIPP/US, Vice President, Risk Management and Compliance, AvePoint The Landscape Prevention and Response Planning

More information

Reaching CMM Levels 2 and 3 with the Rational Unified Process

Reaching CMM Levels 2 and 3 with the Rational Unified Process Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP174 Table of Contents INTRODUCTION... 1 LEVEL-2, REPEATABLE... 3 Requirements Management... 3 Software Project

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

CHANGE MANAGEMENT POLICY

CHANGE MANAGEMENT POLICY DEPARTMENT OF TECHNOLOGY (DTECH) CHANGE MANAGEMENT POLICY Revised: 10/20/14 799 G Street, Sacramento, CA 95814 Table of Contents Introduction... 3 Definition of Change... 3 Definition of Change... 3 Objectives...

More information

Change Management Best Practices for ERP Applications, An Internal Auditor's Perspective. Jeffrey T. Hare, CPA CISA CIA ERP Risk Advisors

Change Management Best Practices for ERP Applications, An Internal Auditor's Perspective. Jeffrey T. Hare, CPA CISA CIA ERP Risk Advisors Change Management Best Practices for ERP Applications, An Internal Auditor's Perspective Jeffrey T. Hare, CPA CISA CIA ERP Risk Advisors Webinar Logistics Hide and unhide the Webinar control panel by clicking

More information

ITSM Reporting Services. Enterprise Service Management. Monthly Metric Report

ITSM Reporting Services. Enterprise Service Management. Monthly Metric Report ITSM Reporting Services Monthly Metric Report October 2011 Contents Introduction 3 Background 3 Purpose 3 Scope 3 AI6 Manage Change 4 Number of Changes Logged 4 Number of Emergency Changes Logged 4 Percentage

More information

Page 1 of 8. Any change, which meets the following criteria, will be managed using IM/IT Change Management Process.

Page 1 of 8. Any change, which meets the following criteria, will be managed using IM/IT Change Management Process. Page 1 of 8 1. Introduction This policy describes the Authority s Information Management/Information Technology (IM/IT) change management procedures. IM/IT manages changes to applications, infrastructure

More information

Contract No. E22PS02. PROJECT CONFIGURATION MANAGEMENT PLAN (CMP) for PRELIMINARY ENGINEERING AND DESIGN/BUILD PROCUREMENT

Contract No. E22PS02. PROJECT CONFIGURATION MANAGEMENT PLAN (CMP) for PRELIMINARY ENGINEERING AND DESIGN/BUILD PROCUREMENT Contract No. E22PS02 PROJECT CONFIGURATION MANAGEMENT PLAN (CMP) for PRELIMINARY ENGINEERING AND DESIGN/BUILD PROCUREMENT Revision 0.0 May 18, 2011 Prepared By: Robert E. Cone Engineering Manager Date

More information

Service Offering: Outsourced IdM Administrator Service

Service Offering: Outsourced IdM Administrator Service Service Offering: Outsourced IdM Administrator Service 2014 Hitachi ID Systems, Inc. All rights reserved. Contents 1 Introduction 1 2 The Outsourced IdM Administrator Service 2 2.1 Hitachi ID Systems and

More information

Change Management Communications Plan. March 13, 2003

Change Management Communications Plan. March 13, 2003 March 13, 2003 TABLE OF CONTENTS 1. PURPOSE... 1 2. ISSUE DEFINITION... 1 3. ROOT CAUSE ANALYSIS... 3 4. ACTIONS... 4 A. NEW EDITS FOR EXISTING BUSINESS RULES (ORDER AND PRE-ORDER)... 4 B. MODIFICATIONS

More information

Engineering Procedure

Engineering Procedure Engineering Procedure Design Owner: EPD 0014 MANAGING CONFIGURATION CHANGE Manager, Engineering Standards and Configuration Version 2.1 Issued February 2010 Approved Jagath Peiris Authorised Jim Modrouvanos

More information

CONFIGURATION COMMITTEE. Terms of Reference

CONFIGURATION COMMITTEE. Terms of Reference SWBTB (8/13) 166 (g) CONFIGURATION COMMITTEE Terms of Reference 1. CONSTITUTION 1.1 The Board hereby resolves to establish a Committee of the Board to be known as the Configuration Committee (The Committee).

More information

Change Submitter: The person or business requesting or filing the Request For Change (RFC) notice.

Change Submitter: The person or business requesting or filing the Request For Change (RFC) notice. ROLES, RESPONSIBILITIES, PROCEDUREs Change Submitter: The person or business requesting or filing the Request For Change (RFC) notice. IT Operations Change Manager: The steward of the Change Management

More information

Operational Change Control Best Practices

Operational Change Control Best Practices The PROJECT PERFECT White Paper Collection The Project Perfect White Paper Collection Operational Change Control Best Practices Byron Love, MBA, PMP, CEC, IT Project+, MCDBA Internosis, Inc Executive Summary

More information

I S O I E C 2 7 0 0 2 2 0 1 3 I N F O R M A T I O N S E C U R I T Y A U D I T T O O L

I S O I E C 2 7 0 0 2 2 0 1 3 I N F O R M A T I O N S E C U R I T Y A U D I T T O O L 15.1 ESTABLISH SECURITY AGREEMENTS WITH SUPPLIERS 15.1.1 EXPECT SUPPLIERS TO COMPLY WITH RISK MITIGATION AGREEMENTS Do you clarify the information security risks that exist whenever your suppliers have

More information

CM00 Change Management High Level

CM00 Change Management High Level CM00 Change Management High Level CM01 Create Change CM09 Assess and Execute Emergency / CM03 Approve Change CM05 Implement Change CM02 Assess And Schedule Change CM07 Review Change CM04 Communicate Scheduled

More information

CA Service Desk Manager

CA Service Desk Manager PRODUCT BRIEF: CA SERVICE DESK MANAGER CA Service Desk Manager CA SERVICE DESK MANAGER IS A VERSATILE, COMPREHENSIVE IT SUPPORT SOLUTION THAT HELPS YOU BUILD SUPERIOR INCIDENT AND PROBLEM MANAGEMENT PROCESSES

More information

WHITEPAPER Complying with HIPAA LogRhythm and HIPAA Compliance

WHITEPAPER Complying with HIPAA LogRhythm and HIPAA Compliance WHITEPAPER Complying with HIPAA LogRhythm and HIPAA Compliance Complying With HIPAA The Department of Health and Human Services (HHS) enacted the Health Insurance Portability and Accountability Act of

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

Centrify Server Suite Health Check

Centrify Server Suite Health Check CENTRIFY OPERATIONS HEALTH CHECK OVERVIEW Centrify Server Suite Health Check Summary Have you ever wondered if your organization is using Centrify s solution to the fullest potential? At Centrify, we take

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

ORACLE IT SERVICE MANAGEMENT SUITE

ORACLE IT SERVICE MANAGEMENT SUITE ORACLE IT SERVICE MANAGEMENT SUITE ITIL COMPATIBLE PINKVERIFY ORACLE IT SERVICE MANAGEMENT SUITE HAS BEEN CERTIFIED BY PINK ELEPHANT THROUGH THE PINKVERIFY PROCESS TO BE ITIL COMPATIBLE IN SIX PROCESS

More information

OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL. PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6.

OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL. PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6. OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6.6 STATUS FINAL Approvals The undersigned have approved the release of Version 6.6

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

074-8432-552 Page 1 of 7 Effective Date: 12/18/03 Software Supplier Process Requirements

074-8432-552 Page 1 of 7 Effective Date: 12/18/03 Software Supplier Process Requirements Page 1 of 7 Software Supplier Process Requirements 1.0 QUALITY SYSTEM FRAMEWORK 1.1 QUALITY POLICY The Seller shall document and implement a quality program in the form of Quality manual or detailed Quality

More information

Manage Deliverables - Construction Step 6. July 12, 2012

Manage Deliverables - Construction Step 6. July 12, 2012 Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

S1200 Technical Support Service Overview

S1200 Technical Support Service Overview S1200 Technical Support Service Overview Nic Chalk March 2015 V1.13 The information contained herein is believed to be accurate at the time of publication, but updates may be posted periodically and without

More information

Tait Support Agreement. Assured network communications. Service Description

Tait Support Agreement. Assured network communications. Service Description Tait Support Agreement Assured network communications Service Description CONTACT INFORMATION Tait Communications Corporate Head Office Tait Limited P.O. Box 1645 Christchurch New Zealand For addresses

More information

Defect Tracking Best Practices

Defect Tracking Best Practices Defect Tracking Best Practices Abstract: Whether an organization is developing a new system or maintaining an existing system, implementing best practices in the defect tracking and management processes

More information

CA Nimsoft Service Desk

CA Nimsoft Service Desk CA Nimsoft Service Desk Rapid Workflow Implementation Guide 7.13.7 Legal Notices Copyright 2013, CA. All rights reserved. Warranty The material contained in this document is provided "as is," and is subject

More information

SERVICE EXCELLENCE SUITE

SERVICE EXCELLENCE SUITE USERS GUIDE Release Management Service Management and ServiceNow SERVICE EXCELLENCE SUITE Table of Contents Introduction... 3 Overview, Objectives, and Current Scope... 4 Overview... 4 Objectives... 4

More information

<Project Name> Configuration Management Plan

<Project Name> Configuration Management Plan Version [Note: The following template is provided for use with the Rational Unified Process. Text enclosed in square brackets and displayed in blue italics (style=infoblue) is included

More information

Change Management Policy

Change Management Policy Change Management Policy Change management refers to a formal process for making changes to IT services. The goal of change management is to increase awareness and understanding of proposed changes across

More information

MKS Integrity & CMMI. July, 2007

MKS Integrity & CMMI. July, 2007 & CMMI July, 2007 Why the drive for CMMI? Missed commitments Spiralling costs Late delivery to the market Last minute crunches Inadequate management visibility Too many surprises Quality problems Customer

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

Configuration Management Self Assessment Checklist

Configuration Management Self Assessment Checklist Configuration Management Self Assessment Checklist Introduction: The purpose of this Configuration Management (CM) Self- Assessment Checklist is to ensure that the Organization correctly understands the

More information

INCIDENT MANAGEMENT & REQUEST FULFILLMENT PROCESSES. Process Owner: Service Desk Manager. Version: v2.0. November 2014 Page 0

INCIDENT MANAGEMENT & REQUEST FULFILLMENT PROCESSES. Process Owner: Service Desk Manager. Version: v2.0. November 2014 Page 0 INCIDENT MANAGEMENT & REQUEST FULFILLMENT PROCESSES Process Owner: Service Desk Manager Version: v2.0 November 2014 Page 0 Document Revision History Revision Description Date Approved by Number V1.0 Initial

More information

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

IT Baseline Management Policy. Table of Contents

IT Baseline Management Policy. Table of Contents Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...

More information

The Configuration Management process area involves the following:

The Configuration Management process area involves the following: CONFIGURATION MANAGEMENT A Support Process Area at Maturity Level 2 Purpose The purpose of is to establish and maintain the integrity of work products using configuration identification, configuration

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

CHG-11-G-001 Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 N/A. Edition workflows and process integrations?

CHG-11-G-001 Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 N/A. Edition workflows and process integrations? Purpose: [C]ontrol the lifecycle of all changes, enabling beneficial changes to be made with minimum disruption to IT services. (ST 4.2.1) Activities include: Assessing the impact of business change on

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

Standards for the Professional Practice of Internal Auditing

Standards for the Professional Practice of Internal Auditing Standards for the Professional Practice of Internal Auditing THE INSTITUTE OF INTERNAL AUDITORS 247 Maitland Avenue Altamonte Springs, Florida 32701-4201 Copyright c 2001 by The Institute of Internal Auditors,

More information