CMS Expedited Life Cycle (XLC) Process: Executive Overview
|
|
- Emmeline Fleming
- 8 years ago
- Views:
Transcription
1 Department of Health and Human Services Centers for Medicare & Medicaid Services CMS Expedited Life Cycle (XLC) Process: Executive Overview Version 2.11 August 28, 2014
2 The Centers for Medicare & Medicaid Services (CMS) Expedited Life Cycle (XLC) model offers a simplified information technology (IT) oversight framework to help CMS IT Project Managers, Business Owners, critical partners, and other stakeholders establish necessary reviews/artifacts for IT project oversight based on risk level. The XLC includes three tailored options to accommodate IT projects of varying complexity. The primary purpose of these XLC options is to balance speed and oversight in a manner appropriate to the complexity and risk associated with a particular IT project. High-Level Process Overview An IT project begins at the definition stage, before it can be reviewed and approved. Once approved, the project team executes a development life cycle with involvement from appropriate stakeholders. This ongoing involvement includes the participation of the project team, governance boards, Business Owners, CMS Office of Information Services (OIS), and leadership. The following figure depicts the five key, high-level activities associated with the development life cycle of a typical IT project. Figure 1: High-Level XLC Process As shown in the next figure, each high-level activity has specific tasks and stakeholders: XLC Executive Overview 1
3 Activity 1: Staff Work The project team defines the idea and creates the preliminary set of documentation, starting with the IT Intake Request Form. This documentation articulates the business need, scope, and highlevel architecture. Activity 2: Reviews Activity 2 involves a Business Architecture and Technology Solutions (BATS) Board review to institutionalize governance of the shared services approach through initial needs assessments and architecture reviews. This constitutes the first XLC review, the Architecture Review (AR). The BATS Board may delegate the AR to the Technical Review Board (TRB). Activity 3: Project Approval An approval from the BATS Board kicks off Activity 3, which culminates with an IT Investment Review Board (ITIRB) review that focuses on strategic, enterprise-level shared solutions. This constitutes the second XLC review, the Investment Selection Review (ISR). Activity 4: Project Execution The ITIRB approval marks the start of Activity 4, which constitutes the project execution and any reviews appropriate for that project, depending on the complexity level of that project. Activity 5: Ongoing Performance Monitoring & Measurement Activity 5 is the ongoing performance monitoring throughout the process. Figure 2: Process Flow of the Five Activities XLC Executive Overview 2
4 System Development CMS Expedited Life Cycle (XLC) Options The XLC model provides a streamlined approach to project oversight and execution. XLC is a tailored approach to project execution and governance based on project risk. This model promotes agility, effective project review, and establishing appropriate oversight earlier in the process. The following figure depicts the CMS Expedited Life Cycle model with these five key phases: Initiation, Concept, and Planning Requirements Analysis and Design Development and Test Implementation Operations & Maintenance and Disposition Project risk is assessed and a Complexity Level of 1, 2, or 3 is assigned. The XLC varies the number of reviews depending on the project s risk, as shown in the following figure. Figure 3: CMS Expedited Life Cycle XLC Executive Overview 3
5 Each Complexity Level includes two types of reviews: Governance Board Reviews: Conducted by CMS governance bodies and including relevant stakeholders. Integrated Project Team (IPT)/Independent Assessment Team (IAT) Reviews: Conducted by the IPT/IAT with relevant stakeholders. The IPT may engage members of the governance boards for these reviews. A Project Process Agreement (PPA) establishes a common understanding between all stakeholders on which reviews will be conducted, which artifacts are appropriate, and which tests will be performed. System Development Options The XLC provides Business Owners and IT Project Managers the option to pick one of three tailored XLC oversight options to manage project risk and complexity. This approach offers stakeholders the ability to establish appropriate rigor and oversight. The following definitions and decision criteria are used as a starting point to determine the level of complexity associated with a project as well as the appropriate system development XLC option for that project. Complexity Level 1 Projects: Applies to minor changes to existing services, systems, and/or environments that do not affect the state of any security controls or requirements. Complexity Level 2 Projects: Applies to an isolated, minor, or incremental change with minimal impact to existing systems that does not significantly affect the state of any security controls or requirements. Complexity Level 3 Projects: Applies to a new, one-of-a-kind design and development effort to support an enterprise, center, or department-specific IT solution or a project for a system that has or will have significant security and risk implications. This could be an initial, major development, modernization, or enhancement effort and requires project teams to document detailed requirements, design, and technical solution specifications. Expectations and Risk Considerations The XLC provides the flexibility to fast-track projects and alleviates any delays due to gate review scheduling constraints. The IPT can conduct non-governance board reviews internally within the project. When planning project activities and applicable life cycle processes and while preparing the PPA, it is important to consider the risk of forgoing a review and plan appropriate mitigation strategies to ensure project success. More details about each artifact, stage gate reviews, and potential risks of not having a review altogether are provided in the CMS Expedited Life Cycle Process: Detailed Description document. Governance for the CMS Expedited Life Cycle Several CMS governance bodies review and provide important feedback to projects. CMS is currently streamlining the governance bodies and functions to ensure clear roles, responsibilities, and project guidance. Each governance body s involvement is being assessed to ensure that the appropriate level of oversight is provided in each review by the right group. XLC Executive Overview 4
6 XLC Support for Multiple Development Methodologies The CMS XLC model is methodology-agnostic, meaning that the XLC model supports all forms of development methodologies. XLC governance reviews will thus accommodate the use of Agile and other iterative methodologies. Project Managers are encouraged to conduct IPT and IAT reviews iteratively during the project s life cycle. XLC Drives Streamlined IT Development The CMS XLC model provides Business Owners, Project Managers, and other stakeholders with guidance on selecting the appropriate XLC option. This selection will then influence an IT project s overall governance, oversight processes, documentation requirements, and schedule. The XLC ensures a streamlined approach to project life cycle processes and a flexible approach to project execution, increasing predictability and efficiency. XLC Executive Overview 5
CMS Expedited Life Cycle Process: Detailed Description
Department of Health and Human Services Centers for Medicare & Medicaid Services CMS Expedited Life Cycle Process: Detailed Description Version 3.3 November 21, 2014 Record of Changes # Date Reference
More informationCMS XLC Guidelines for Agile Projects
Centers for Medicare & Medicaid Services CMS XLC Guidelines for Agile Projects v 1.0 09/03/2014 Record of Changes Version Date Author/Owner Description of Change 1.0 09/03/2014 XLC Steering Committee Formal
More informationEnterprise Performance Life Cycle Framework
United States Department of Health & Human Services Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services (HHS)
More informationU.S. Department of Education Federal Student Aid
U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Stage Gate Review Process Description Version 1.3 06/30/2015 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Lifecycle
More informationEstablishment Review Process
Establishment Review Process DEPARTMENT OF HEALTH AND HUMAN SERVICES CENTERS for MEDICARE & MEDICAID SERVICES Center for Consumer Information and Insurance Oversight Health Insurance Exchange System-Wide
More informationU.S. Department of Education Federal Student Aid
U.S. Department of Education Federal Student Aid Lifecycle Management Methodology Version 1.3 06/30/15 Final DOCUMENT NUMBER: FSA_TOQA_PROC_STGRW.NA_001 Update History Lifecycle Management Methodology
More informationEnhanced Funding Requirements: Seven Conditions and Standards
Department of Health and Human Services Centers for Medicare & Medicaid Services Enhanced Funding Requirements: Seven Conditions and Standards Medicaid IT Supplement (MITS-11-01-v1.0) Version 1.0 April
More informationCMS SYSTEM SECURITY PLAN (SSP) PROCEDURE
Chief Information Officer Office of Information Services Centers for Medicare & Medicaid Services CMS SYSTEM SECURITY PLAN (SSP) PROCEDURE August 31, 2010 Version 1.1 - FINAL Summary of Changes in SSP
More informationAutomated Software Testing Economics: A White Paper
Automated Software Testing Economics: A White Paper Contents Automated Software Testing Economics 1 Automated Software Testing Case Study 2 Benefits of Automated Software Testing 4 About Master Key Consulting
More informationCMS Testing Framework Overview
Department of Health and Human Services Centers for Medicare & Medicaid Services Office of Information Services CMS Framework Overview Version 1.1 May 18, 2011 Table of Contents 1. Introduction... 1 1.1
More informationAgile Project Management By Mark C. Layton
Agile Project Management By Mark C. Layton Agile project management focuses on continuous improvement, scope flexibility, team input, and delivering essential quality products. Agile project management
More informationHHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
More informationIntroduction to OpenUP (Open Unified Process)
Introduction to OpenUP (Open Unified Process) Different projects have different process needs. Typical factors dictate the needs for a more formal or agile process, such as team size and location, architecture
More informationPPM V2.0 Frequently Asked Questions (FAQs) U.S. Department of Housing and Urban Development
PPM V2.0 Frequently Asked Questions (FAQs) U.S. Department of Housing and Urban Development December 2015 1. Getting Started with PPM Life Cycle 2. PPM Life Cycle Process 3. PPM V2.0 and Project Types
More informationIntroducing Agility into a Phase Gate Process
B E S T P R A C T I C E S W H I T E P A P E R Introducing Agility into a Phase Gate Process Jenny Stuart, Vice President of Consulting, Construx Software Version 1.1, June 2011 Contributors Earl Beede,
More informationTable of Contents. CHAPTER 1 Web-Based Systems 1. CHAPTER 2 Web Engineering 12. CHAPTER 3 A Web Engineering Process 24
Table of Contents CHAPTER 1 Web-Based Systems 1 The Web 1 Web Applications 2 Let s Introduce a Case Study 3 Are WebApps Really Computer Software? 4 Are the Attributes of WebApps Different from the Attributes
More informationGuide to Enterprise Life Cycle Processes, Artifacts, and Reviews
Department of Health and Human Services Centers for Medicare & Medicaid Services Center for Consumer Information and Insurance Oversight Guide to Enterprise Life Cycle Processes, Artifacts, and Reviews
More informationSoftware Development Life Cycle (SDLC)
Software Development Life Cycle (SDLC) Supriyo Bhattacharjee MOF Capability Maturity Model (CMM) A bench-mark for measuring the maturity of an organization s software process CMM defines 5 levels of process
More informationSecond Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract This second Amendment to Contract Number is effective as of December 12, 2011, between the Iowa Department
More informationTraditional requirements
What do we do now? Traditional requirements Reams of paper Detailed requirements documented upfront Documentation of so many requirements that they had to be identified as mandatory or desirable Customers
More informationUnited States Department of Health & Human Services Enterprise Architecture Program Management Office. HHS Enterprise Architecture Governance Plan
United States Department of Health & Human Services Enterprise Architecture Program Management Office HHS Enterprise Architecture Governance Plan Version 3.0 February 2007 Approvals The Health and Human
More informationNational Information Exchange Model. Human Services Domain Charter
National Information Exchange Model Human Services Domain Charter June 15, 2012 Document Change Control Page No. Approver Date Description 1 D. Jenkins 01/31/2012 First draft completed and delivered to
More informationPicasso Recommendation
Picasso Recommendation Mission The School of Dentistry for the University at Buffalo (UB) uses a custom application called Picasso to manage their clinic operations. Developed by two engineers in 1997,
More informationINFORMATION TECHNOLOGY PROJECT EXECUTION MODEL GUIDE FOR SMALL AND MEDIUM PROJECTS
NOT MEASUREMENT SENSITIVE DOE G 415.1-2 INFORMATION TECHNOLOGY PROJECT EXECUTION MODEL GUIDE FOR SMALL AND MEDIUM PROJECTS [This Guide describes acceptable, but not mandatory means for complying with requirements.
More informationMedicaid and CHIP FAQs: Implementing Hospital Presumptive Eligibility Programs January 2014
DEPARTMENT OF HEALTH & HUMAN SERVICES Centers for Medicare & Medicaid Services 7500 Security Boulevard, Mail Stop S2-26-12 Baltimore, Maryland 21244-1850 Overview Medicaid and CHIP FAQs: Implementing Hospital
More informationProcess Methodology. Wegmans Deli Kiosk. for. Version 1.0. Prepared by DELI-cious Developers. Rochester Institute of Technology
Process Methodology for Wegmans Deli Kiosk Version 1.0 Prepared by DELI-cious Developers Rochester Institute of Technology September 15, 2013 1 Table of Contents 1. Process... 3 1.1 Choice... 3 1.2 Description...
More informationSystems Development Life Cycle (SDLC)
DEPARTMENT OF BUDGET & MANAGEMENT (SDLC) Volume 1 Introduction to the SDLC August 2006 Table of Contents Introduction... 3 Overview... 4 Page 2 of 17 INTRODUCTION 1.0 STRUCTURE The SDLC Manual consists
More informationProject Management Office Best Practices
Project Management Office Best Practices Agenda Maturity Models (Industry & PMO) PMO Areas of Expertise (Scale & Scope) Project Management Office Process Model Project Management Framework PMO Implementation
More informationCOMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF HEALTH AND HUMAN SERVICES
COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF HEALTH AND HUMAN SERVICES The Office of Information Technology Project Methodology and Lifecycle Guide Version 4.4 Last Updated: November 15, 2011 CE M
More informationREVIEW ON THE EFFECTIVENESS OF AGILE UNIFIED PROCESS IN SOFTWARE DEVELOPMENT WITH VAGUE SYSTEM REQUIREMENTS
REVIEW ON THE EFFECTIVENESS OF AGILE UNIFIED PROCESS IN SOFTWARE DEVELOPMENT WITH VAGUE SYSTEM REQUIREMENTS Lisana Universitas Surabaya (UBAYA), Raya Kalirungkut, Surabaya, Indonesia E-Mail: lisana@ubaya.ac.id
More informationGuidance for Exchange and Medicaid Information Technology (IT) Systems
Department of Health and Human Services Centers for Medicare & Medicaid Services Guidance for Exchange and Medicaid Information Technology (IT) Systems Version 2.0 May, 2011 Table of Contents 1. Introduction...
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationCMS Policy for Configuration Management
Chief Information Officer Centers for Medicare & Medicaid Services CMS Policy for Configuration April 2012 Document Number: CMS-CIO-POL-MGT01-01 TABLE OF CONTENTS 1. PURPOSE...1 2. BACKGROUND...1 3. CONFIGURATION
More informationFINAL Version 1.0 June 25, 2014
CENTERS for MEDICARE & MEDICAID SERVICES Enterprise Information Security Group 7500 Security Boulevard Baltimore, Maryland 21244-1850 Risk Management Handbook Volume III Standard 7.2 FINAL Version 1.0
More informationCMS NEWS. October, 25, 2012 (202) 690-6145
DEPARTMENT OF HEALTH & HUMAN SERVICES Centers for Medicare & Medicaid Services Room 352-G 200 Independence Avenue, SW Washington, DC 20201 CMS NEWS FOR IMMEDIATE RELEASE Contact: CMS Media Relations October,
More informationClassical Software Life Cycle Models
Classical Software Life Cycle Models SWEN 301 Trimester 1, 2015 Lecturer: Dr Hui Ma Engineering and Computer Science Lecture slides make use of material provided on the textbook's companion website Motivation
More informationVermont Enterprise Architecture Framework (VEAF) Master Data Management (MDM) Abridged Strategy Level 0
Vermont Enterprise Architecture Framework (VEAF) Master Data Management (MDM) Abridged Strategy Level 0 EA APPROVALS EA Approving Authority: Revision
More informationCMS Policy for Information Technology (IT) Investment Management & Governance
Chief Information Officer Office of Information Services Centers for Medicare & Medicaid Services CMS Policy for Information Technology (IT) Investment Management & Governance May 17, 2007 Document Number:
More informationQuality assurance in an Agile delivery method
Quality assurance in an Agile delivery method Guy Nelson (Quality Manager, Fidelity International) Barbara Roberts (Accredited DSDM Consultant) April 2006 Agenda The Challenges to Quality Assurance CMMi
More informationFinal Version 1.0 November 8, 2012
CENTERS for MEDICARE & MEDICAID SERVICES Enterprise Information Security Group 7500 Security Boulevard Baltimore, Maryland 21244-1850 Volume I Chapter 1 Final Version 1.0 November 8, 2012 Document Number:
More informationWhitepaper. Agile Methodology: An Airline Business Case YOUR SUCCESS IS OUR FOCUS. Published on: Jun-09 Author: Ramesh & Lakshmi Narasimhan
YOUR SUCCESS IS OUR FOCUS Whitepaper Published on: Jun-09 Author: Ramesh & Lakshmi Narasimhan 2009 Hexaware Technologies. All rights reserved. Table of Contents 1. Introduction 2. Subject Clarity 3. Agile
More informationSoftware Development Methodologies
Software Development Methodologies Lecturer: Raman Ramsin Lecture 12 Agile Methodologies: Crystal 1 Crystal Introduced by Cockburn as a family of methodologies in 1998. New members of the family were defined
More informationBiometrics Enterprise Architecture Project Management Plan (BMEA PMP)
Biometrics Enterprise Architecture Project Management Plan (BMEA PMP) Version 1.0 Prepared by: Date: November 24, 2008 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0 Responsible
More informationSoftware Development Methodologies
Software Development Methodologies Lecturer: Raman Ramsin Lecture 15 Agile Methodologies: AUP 1 Agile Unified Process (AUP) Proposed by Ambler as a simplified version of the Rational Unified Process (RUP).
More informationNASCIO EA Development Tool-Kit Solution Architecture. Version 3.0
NASCIO EA Development Tool-Kit Solution Architecture Version 3.0 October 2004 TABLE OF CONTENTS SOLUTION ARCHITECTURE...1 Introduction...1 Benefits...3 Link to Implementation Planning...4 Definitions...5
More informationDecember 5, 2014. Submitted Electronically
December 5, 2014 Submitted Electronically Ms. Nancy J. Griswold Chief Administrative Law Judge Office of Medicare Hearings and Appeals U.S. Department of Health and Human Services 1700 N. Moore Street
More informationCSE 435 Software Engineering. Sept 16, 2015
CSE 435 Software Engineering Sept 16, 2015 2.1 The Meaning of Process A process: a series of steps involving activities, constraints, and resources that produce an intended output of some kind A process
More informationDrupal Services Program Charter
Prepared by Christina Konstantinidou, ITS Last Edited January 3, 2014 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Drupal Services Program Charter Executive Summary The
More informationuser Experience Designing an Affordable Care Act Enrollment Project Overview
Designing a First-Class User Experience for Affordable Care Act Enrollment Project Overview February 2012 Project Objectives 1. Develop first-class user experience (UX) design for health insurance exchanges
More informationNYU. Business Solution Engineering Project Sample Application XXX
NYU Business Solution Engineering Project Sample Application XXX Great things are not done by impulse, but by a series of small things brought together. Vincent Van Gogh Authors: xxx Version Number: 1.0
More informationBasic Unified Process: A Process for Small and Agile Projects
Basic Unified Process: A Process for Small and Agile Projects Ricardo Balduino - Rational Unified Process Content Developer, IBM Introduction Small projects have different process needs than larger projects.
More informationOptimizing Your Software Process
Optimizing Your Software Process Top 5 Software Development Process Challenges Executive Summar ry A process framework is a combination of project management, technical practices, and supporting tools.
More informationCalifornia Enterprise Architecture Framework
Version 2.0 August 01, 2013 This Page is Intentionally Left Blank Version 2.0 ii August 01, 2013 TABLE OF CONTENTS 1 Executive Summary... 1 1.1 What is Enterprise Architecture?... 1 1.2 Why do we need
More informationDELIVERING SOFTWARE WITH AGILITY, WITHOUT AGILE FIVE REAL-WORLD LESSONS
Table of Contents SUMMARY AND CONTEXT... i UNIQUE CHALLENGES OF LARGE ORGANIZATIONS... 1 BECOMING AGILE (NOT AGILE)... 3 Lesson #1: It s the people, not the process... 3 Lesson #2: Partner developers with
More informationAugust 26, 2013 (202) 690-6145. CMS and New York Partner to Coordinate Care for Medicare-Medicaid Enrollees
DEPARTMENT OF HEALTH & HUMAN SERVICES Centers for Medicare & Medicaid Services Room 352-G 200 Independence Avenue, SW Washington, DC 20201 FACT SHEET FOR IMMEDIATE RELEASE Contact: CMS Media Relations
More informationEnterprise Content Management (ECM)
Business Assessment: A Quick-Reference Summary Intro to MIKE2 methodology and phase 1 The methodology that will be used throughout the specialist track is based on the MIKE2 methodology. MIKE stands for
More informationFinancial Management 101
Financial Management 101 DEPARTMENT OF HEALTH AND HUMAN SERVICES CENTERS for MEDICARE & MEDICAID SERVICES Center for Consumer Information and Insurance Oversight State Exchange Grantee Meeting The material
More informationSupporting Workflow Overview. CSC532 Fall06
Supporting Workflow Overview CSC532 Fall06 Objectives: Supporting Workflows Define the supporting workflows Understand how to apply the supporting workflows Understand the activities necessary to configure
More informationAgile Testing. What Students Learn
Agile Testing Transition sound traditional test practices into an Agile development environment. By using a step-by-step approach, this course documents how to transition from traditional test practices
More informationUS Department of Education Federal Student Aid Integration Leadership Support Contractor January 25, 2007
US Department of Education Federal Student Aid Integration Leadership Support Contractor January 25, 2007 Task 18 - Enterprise Data Management 18.002 Enterprise Data Management Concept of Operations i
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More informationMINNESOTA HEALTH INSURANCE EXCHANGE PERFORMANCE PROGRESS REPORT
MINNESOTA HEALTH INSURANCE EXCHANGE PERFORMANCE PROGRESS REPORT Submitted to CCIIO September, 2012 Core Area: Legal Authority and Governance Hire full-time staff within the Department of Commerce dedicated
More informationwww.pwc.com Scale agile throughout the enterprise A PwC point of view
www.pwc.com Scale agile throughout the enterprise A PwC point of view December 2013 Overview Today it s rare to speak with a company that is not adopting some form of agile development practice. However,
More informationProduction Readiness Review (PRR) Process Description
Production Readiness Review (PRR) Process Description Version 13.0 Final 7/31/2013 Document Identifier: FSA_TOQA_PROC_RLS.PRR_001 Document Version Control Document Version Control Version Date Description
More informationQuality Assurance in an Agile Environment
Quality Assurance in an Agile Environment 1 Discussion Topic The Agile Movement Transition of QA practice and methods to Agile from Traditional Scrum and QA Recap Open Discussion www.emids.com 2 What is
More informationSoftware Development Process
Software Development Process A software development process, also known as software development lifecycle, is a structure imposed on the development of a software product. Similar terms include software
More informationHow To Write Software
Overview of Software Engineering Principles 1 Software Engineering in a Nutshell Development of software systems whose size/ complexity warrants a team or teams of engineers multi-person construction of
More informationIntegrating PRINCE2 and Scrum for successful new product development
1 Goal Professional Services Pty Ltd 2 Renewtek Pty Ltd Integrating PRINCE2 and Scrum for successful new product development Rankins G J 1 and Kearns M 2 This paper was presented at the Australian Institute
More informationA Capability Maturity Model (CMM)
Software Development Life Cycle (SDLC) and Development Methods There are some enterprises in which a careful disorderliness is the true method. Herman Melville Capability Maturity Model (CMM) A Capability
More informationAgile Project Management A Primer. Brian Stewart AVU ACEP Nairobi 17 th 2013
Agile Project Management A Primer Brian Stewart AVU ACEP Nairobi 17 th 2013 http://www.coleyconsulting.co.uk/images/waterfall-model.gif Problems with waterfall model Over-planning Insufficient Communication
More informationFive best practices for deploying a successful service-oriented architecture
IBM Global Services April 2008 Five best practices for deploying a successful service-oriented architecture Leveraging lessons learned from the IBM Academy of Technology Executive Summary Today s innovative
More informationBy O livia K a sik a nd O ma r Silve r
By O livia K a sik a nd O ma r Silve r A long-standing business standard for software development, the Waterfall method, assumes that project steps can be completed sequentially and all costs, benefits,
More informationPositive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
More informationBridging the IT Business Gap The Role of an Enterprise Architect
Whitepaper Bridging the IT Business Gap The Role of an Enterprise Architect Today s enterprises understand the value that Information Technology (IT) can bring to their business. IT supports day-to-day
More informationRapid Development & Software Project Survival Guide Steve McConnell Dave Root (Developed with Mel Rosso-Llopart)
Lifecycle Planning Rapid Development & Software Project Survival Guide Steve McConnell Dave Root (Developed with Mel Rosso-Llopart) Version 1.4 David Root, 2005, all rights reserved 1 Topics Who am I to
More informationCANOPYv100. Portfolio, Program and Project Management Suite Project Assistant Program Coordinator Portfolio Administrator
TM CANOPYv100 Portfolio, Program and Project Management Suite Project Assistant Collaboration Consolidation Clarity Program Coordinator Portfolio Administrator CANOPYv100 Portfolio, Program and Project
More informationIT Solutions Life Cycle Management. Pension Benefit Guaranty Corporation Dated: November 1, 2012 v1.2
IT Solutions Life Cycle Pension Benefit Guaranty Corporation Dated: November 1, 2012 v1.2 IT Solutions Life Cycle Pension Benefit Guaranty Corporation ITSLCM External Processes IT Standards (S) & Guidance
More informationConcept of Operations for Line of Business Initiatives
Concept of Operations for Line of Business Initiatives Version 1.0 Office of E-Gov and IT, OMB March 2006 Table of Contents FOREWORD...2 1 OBJECTIVES OF THE LINES OF BUSINESS CONCEPT OF OPERATIONS...3
More informationTerrace Consulting Services
Terrace Consulting Services Overview: Every project will require some degree of Planning before Implementation can begin. Analysis and Planning are essential in order to confirm requirements, define the
More informationInformation and Infrastructure Viewpoints
National Human Services Interoperability Architecture (NHSIA) NHSIA Webinar Series Overview Key Concepts Capability & Business Viewpoints Information & Infrastructure Viewpoints Systems Viewpoint and Wrap-Up
More informationValue to the Mission. FEA Practice Guidance. Federal Enterprise Architecture Program Management Office, OMB
Value to the Mission FEA Practice Guidance Federal Enterprise Program Management Office, OMB November 2007 FEA Practice Guidance Table of Contents Section 1: Overview...1-1 About the FEA Practice Guidance...
More informationFinancial Services Commission Authorisations Workshop
Financial Services Commission Authorisations Workshop 2015 Our Vision and Mission Vision To be recognised by our stakeholders as a model international financial services regulator. Mission To provide financial
More informationState of Minnesota IT Governance Framework
State of Minnesota IT Governance Framework June 2012 Table of Contents Table of Contents... 2 Introduction... 4 IT Governance Overview... 4 Process for Developing the New Framework... 4 Management of the
More informationChallenging ALM: What really matters when picking tools? Share this Ebook
Challenging ALM: What really matters when picking tools? Beyond features, performance and price. It is a given: software teams must rapidly respond to change to keep pace. Or risk the software they create
More informationNuclear Regulatory Commission Computer Security Office CSO Office Instruction
Nuclear Regulatory Commission Computer Security Office CSO Office Instruction Office Instruction: Office Instruction Title: CSO-PLAN-0100 Enterprise Risk Management Program Plan Revision Number: 1.0 Effective
More informationInformation Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
More informationUrgent Business Needs Strategy
Washington State Office of Financial Management Roadmap for Financial and Administrative Policies, Processes, and Systems Urgent Business Needs Strategy May 2005 070605-14.56 DISCUSSION DRAFT Roadmap for
More information1.0 Purpose. 2.0 Roles and Responsibilities. Management System Description: Project Management. Management System Owner: Lorie Howard
Management System Description: Project Management Management System Owner: Lorie Howard Point of Contact: Lorie Howard EMCBC Home Page Issue Date: Revision: 1 1.0 Purpose The purpose of the Office of Environmental
More informationProject Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development
Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software
More informationThe following is intended to outline our general product direction. It is intended for informational purposes only, and may not be incorporated into
The following is intended to outline our general product direction. It is intended for informational purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any
More informationDocumentation Management Portal Implementation Statement of Work
Documentation Management Portal Implementation Statement of Work Prepared For: State of Michigan Department of Community Health 400 South Pine Street Lansing, Michigan 48909 Prepared By: CNSI 6465 Millennium
More informationBalancing the Outsourcing Equation
Whitepaper Balancing the Outsourcing Equation A Blueprint on how to obtain the benefits of outsourcing without the risks. 2013 Blueprint Software Systems Inc. All rights reserved Executive Summary This
More information22 nd -24 th July 2015
22 nd -24 th July 2015 B-19 Country Club, Uccle, Brussels Funded by the Seventh Framework Programme of the European Union Overview Inception Phase Key Goals Inception Reporting Requirements Key Goals Purpose
More informationHow To Understand The Role Of Enterprise Architecture In The Context Of Organizational Strategy
Enterprise Architecture in the Context of Organizational Strategy Sundararajan Vaidyanathan Senior Enterprise Architect, Unisys Introduction The Presidential Management Agenda (PMA) 1 is geared towards
More informationPrivacy Requirements Definition and Testing in the Healthcare Environment
Definition and Testing in the Healthcare Environment Julie S. McEwen, CIPM, CIPP/G/IT/US, CISSP, PMP Julie Snyder, CIPM, CIPP/G/US Approved for Public Release. Distribution Unlimited. 13-2766 2013 The
More informationSection 7 RFP reference: 7.2.7 Quality Assurance, Page 64
Section 1 Transmittal Letter Section 2 Introduction (Executive Summary) Section 3 Summary of the Bidder s Understanding of the Project Scope Section 4 Bidder s Products, Methodology, and Approach to the
More informationPROTIVITI FLASH REPORT
PROTIVITI FLASH REPORT Cybersecurity Framework: Where Do We Go From Here? February 25, 2014 Just over a year ago, President Barack Obama signed an Executive Order (EO) calling for increased cybersecurity
More informationAgile Development Overview
Presented by Jennifer Bleen, PMP Project Services Practice of Cardinal Solutions Group, Inc. Contact: Agile Manifesto We are uncovering better ways of developing software by doing it and helping others
More informationIT Project Governance Manual Version 1.1
IT Project Governance Manual Version 1.1 A Mandatory Reference for ADS Chapter 577 New Reference: 04/13/2010 Responsible Office: CIO File Name: 577mak_041310 UNITED STATES AGENCY FOR IT Project Goverance
More informationNightOwlDiscovery. EnCase Enterprise/ ediscovery Strategic Consulting Services
EnCase Enterprise/ ediscovery Strategic Consulting EnCase customers now have a trusted expert advisor to meet their discovery goals. NightOwl Discovery offers complete support for the EnCase Enterprise
More information