1 UDK ALLOCATION OF PROJECT RESOURCES AND THE INADEQUACY OF THE TRADITIONAL PROCUREMENT SYSTEM P. D. Rwelamila, A. Ngowi Abstract Technology in the construction industry is becoming more complex and composite, and new practices are increasingly becoming transient and expedient. In thls environment the trahtional procurement system (TPS) has been criticised for being unable to cope with the complexity and the dynamic nature of the current industry in allocating project resources. Consequently new procurement processes are being introduced and utilised as the panacea in dealing with the objectives of the project economic system. Research to date has however focused on the techcal aspects of project procurement in a conservative way and little or no cognisance is taken of the related management issues addressing the appropriate way of allocating project resources. This paper argues that, for illost projects the problem is not the inability of the trahtional procurement system to meet the requirements of a demanding industry of managing the objectives of the project economic system, rather that the fault lies within the management of the "human aspect" within that system. The paper proposes that the trahtional procurement system needs to be applied utilising modem management approaches. The paper proposes that the use of Total Systems Intervention (TSI) would provide a framework within which an informed choice can be made as to the most appropriate methods in dealing with human behaviour as a relationship between ends and scarce means which have alternative uses in a construction project. P. D. Rwelamila, Department of Buildmg Sciences, Royal Institute of Technology, Stockholm, Sweden A. Ngowi, Department of Civil Engineering, University of Botswana, Gaborone, Botswana

2 Keywords: Management, procurement system, total systems intervention. Alociranje projektnih resursa i nepodobnost tradicionalnog sustava ugovaranja Saietak Tehnologija u gradevinarshu postaje sve kompleksnija i sloaenija, a novi postupci postaju sve kratkotrajniji i ~Cinkovitiji. U tom se okruziu kritizira tradicionalni sustav ugovaranja kao nesposoban da se nosi sa sloienoscu i dinamicnom prirodom u danainjem gradevinarstvu pri odredivanju mjesta projektnih resursa. Stoga se uvode i primijenjuju novi procesi ugovaranja kao univerzalni lijek za postizavanje ciljeva projektnog ekonomskog sustava. Istraiivanja su se, medutim, usredototila na tehnicke aspekte projektnog ugovaranja na konzenlativan natin, te se malo ili nikako ne pridaje znacaja srodnim pitanjima vodenja projekta kojim se traii odgovaraiuci nacin alociranja projektnih resursa. Rad tvrdi da za vecinu projekata, problem nije da tradicionalni sustav ugovaranja ne moie ispuniti potrebe zahtievne privrede koja podrazumijeva upravljanje ciljevima ekonomskog sustava projekta, nego je problem u upravljanju "ljudskog aspekta" u tom sustavu. Rad predlaie da tradicionalni sustav treba biti prinlijenjen srodnim upravljackim natinima. Takoder, predlaie se koristenje CSI (cjelokupna sustavska intervencija) koja bi dala kostur u kojem bi se ii~ormirana odluka mogla ostvariti u vezi njoj primjenjive nietode djelovanja sa ljudskim ponasanjem kao veza izmedu ciljeva i rijetkih natina dostignuka koje imaju razne uporabe u graditeljskom projektu. KljuZne rijezi: menadiment, sustav ugovaranja, totalna inverzija sustava 1 Introduction The project client's principal objectives (parameters) are cost, time, quality and utility. According to Rwelainila and Savile [l], these are referred to as client's objectives pyramid. Organizational structures of coilstruction projects must be established in order to manage these project parameters. Successes and failures related to a project organizational structure must be measured on the basis of these parameters. The project organizational structure, which is the collective action required to acquire the design, management, and installation inputs is referred to as a procurement system. Thts paper focuses on the traditional procurement system (TPS). According to documented evidence, tlus system has been in existence since 1870, when Cubitt in London in the United Kingdom first began to offer the services of a general contractor. Prior to that, building work tended to be procured as a series of direct contracts between the client and the trade contractors. This is the essence of what is today called construction management [2].

3 The essence of TPS is that construction work involving simcant architectural input, is undertaken with the client contracting and the architect as the principal design consultant. A separate contract is entered into between the client and the structurallcivil engineer. Later, a separate contract is entered into by the client and the contractor/builder. In other words, the designer designs, and the builder builds. In order to achieve this, the architect must co-ordmate all of the design input from the various technological design specialists, so that a single comprehensive set of documents can be put out to tender. In those projects involving mainly civil works, and where no architect is needed. the civil engineer is the consultant designer and only two contracls are undertaken, namely: between the client and the civil engineer; and, between the client and the contractor~builder. There has for some time ken a strong indication that construction projects sueer from inappropriately defined procurenlent systems [3]. Researchers and writers on construction management are increasingly stressing the need for procurement systems to be tailored to meet particular project needs (41 [5]. Wlule these views are a reflection of appropriate hnking i.e., an acknowledgement of changing technology in the construction industry, and clients requirements becoming more complex, composite and sophisticated, a number of performance studies on projects utilising the TPS have generally blamed the TPS itself, contendmg that it is out of date, inefficient, expensive and does not adequately reflect an appropriate relationship between the client and the contractor [61 [71 [S]. This paper seeks to present the argument that the TPS is basically used as a "default system". Furthermore, it shows that TPS has been used merely because consultants have failed to consider the issue of appropriateness. It argues against this approach which has resulted in an indirect acceptance of a situation that the TPS, as defined in conventions and standard documents wihn the industry, is meant to work precisely as defined. This paper proposes that the use of a modern management approach, namely : Total Systems Internention would provide the framework wihn which an informed choice can be made as to the most appropriate methods for addressing project procurement issues. Finally, conclusions are drawn, from wihn a management perqxcbve, as to the sigruficance of understandmg the role and basic framework of the traditional procurement system within the construction industry. 2 The TPS - in theory Accordmg to Hughes 121, the TPS should be used where : 1. The client has conunissioned, and taken responsibility for, the design of the works (Cl); 2. The design is complete at the time of selecting the contractor ((72): 3. Prime cost sums, including nominated sub-contracts, do not form the major proportion of the contract sum (C3); 4. The architect or engineer appointed by the client is adequately experienced to cope with the co-ordination of the design team, to lead the design effort, and to co-ordinate the interface between design and fabrication (C4); 5. The client wishes to use a quantity s~eyor/cost engineer to plan and control the finance of the project, in conjunction with the architect or engineer (C'5);

4 6. The client wishes the contractor selection process to be based upon the contractor's estimate of price and for the contractor to bear the risk of costs exceeding prices (C9; 7. The client wishes to reserve the right, via nomination, to select the subcontractors for certain parts of the work (but see (iii) above) (C7); 8. It is important that an acceptable negotiated fonn is used in order to ensure a fair and familiar distribution of risk (C8); and, 9. The client does not know what else to do, and the consultants do not raise the choice of procurement system as an issue (C9). Tlle above TPS project characteristics are referenced (Cl, C2 etc.) to facilitate cross referencing later. A combination of one or more of these proiect characteristics could occur on projects following the TPS. It may happen that a contract is let under circumstances which do not accord with those given, but it is suggested that such projects would be better served by the TPS in an adjusted version (hybrid versions of the TPS) or, by another procurement system outside of the TPS franlemrk. The TPS could be adjusted by adopting a process wluch employs a range of approaches (or systems nletaphors) in order to encourage creative thnking about the respective project and the inherent complex issues involved i.e., those which are not compatible with the basic framework of a typical TPS that project consultants have to confront. The process and logic of applying TSI to aid the TPS and other hybrid versions of TPS will be discussed after looking at the results of using TPS under those circumstances which are not in accordance with the typical basic framework, and that do not consider appropriate adjustments that could be implemented. 3 The TPS - in practice As indicated above, the TPS has been severely criticised for being out of date, inefficient, expensive and, for not adequately reflecting the appropriate relationship between the client and the contractor. In order to establish the reasons behind these claims, it is important to look at the performance of the TPS, or systems which are perceived to be the TPS, in terms of their ability to meet the client's brief The data has been drawn from research conducted in Botswana. Comparisons are made with sinilar trends and occurrences in the United Kingdom. Due to lack of space and bmvity, a few salient findings will be discussed. In order to look at the TPS. or other systems perceived to be the TPS, with respect to meeting the client's brief. the four feasible objectives of the client wluch primarily define that belief need to be addressed. These are: time, cost, quality and utility [l] [9] [lo]. Furthermore, that if a project is percei~ed by the client to have complied with the established standards set in the brief in terms of these four parameters, it can be argued that the procurement system utilised for the respective project has been successful.

5 3.1 Research studies Research puradigm: Two separate research projects were carried out in Botswana in order to address what was being referred to as 'the problems of using the traditional procurement system (TPS). These stuhes attempted lo address certain elements that are measurable within the TPS, in order to investigate if appropriate nxthods are used in selecting this procurement system. The aim was to establish from various builhng projects stakeholders the characteristics of their projects. This was necessary because an increasing number of participants in the Botswana construction industry were expressing great concern over the poor quality of builhngs. Most building projects in Botswana are purported to be procured using the TPS, hence poor quality of buildmgs was linked to the TPS Architects and quantity surveyors study A survey of Botswana architectural and quantity surveying firms was carried out via a medium of postal questionnaire. The research sample was drawn from a register of Botswana Institute of Development Professions (EIDP). All registered firms of architects and quantity surveyors were sent questionnaires. These amounted to 13 and 11 Jrn1.r ofarchitects and QuantiQ Suwt.yors respectivelv. The number of replies that were suitable for analysis amounted to: 10 (77%) and 8 (73%) architectural and quantiq suweyingjrms respectively. The TPS characteristics as inhcated in section 2 above were tabulated, and respondents opinions were sought regarhng the characteristics of their projects. The results of the survey are shown in Table 1. Table 1. Architect and quantity surveyors' opinions regarding the characteristics of their projects True More true Difficult More False than false to say false than true Arc Qs Arc Qs Arc Qs Arc Qs Arc Qs Project % % % % % % % % % % characteristics (Ref section 2)

6 As indcated in Table 1, the majority of archtect and quantity surveyor respondents are in agreement that characteristics (Cl), (C3), (C4), (C5), (C6), (C7) and (C9) represent common characteristics of most of their public building projects. The majority of architects (90%) and quantity surveyors (95%) are in agreement that characteristic C2 does not conform to most of their public buildng projects. Architects and quantity surveyors are in agreement over characteristic C8, they are of the opinion that it is false to say that an acceptable negotiated project contract fornl is normally used to ensure fair and familiar distribution of project risk. Architect and quanti& surveyor responrients are in agreement that the dominant procurement system in the Botswana public building sector is not what is generally purported to be. Although the TPSproject management structure and its respective standard forms of contract is used for most of the public building projects, these findings suggest that hybrid versions of the TPSare used in the BotLswana public building sector Twelve large building projects study Rwelamila [I I] surveyed twelve large building projects in Botswana where the TPS was said to be in use. It was found that delays in construction time had occurred on eighty percent (80%) of the projects, primarily due to late design. As indcated in section 2 above, the typical TPS is a system in which linear relationships exist between each of its key activities i.e., design is developed, bills of quantities and other descriptive documentation is prepared, a contractor is selected and construction is commenced, with a full set of worlung drawings and schedules. If tlus linear relationship is not possible, the TPS needs the application of the Total Systems Intervention approach in order to cope wth the sociological complexities inherent in tlus environment. Furthermore, it was established that-on those projects where information delays had ocmred, they were characterized by prime cost sums fonning major portions of the contracts sum (refer to C3 in section 2), by poor documentation, and a f&quent break-down in commun~cation between the partles involved. Whilst the procurement system used was said to be the TPS, it is clear that hybrid versions of TPS were, in reality, in use Implications of the surveys Both studes have demonstnted that the problems inherent in the Botswana construction industry are not necessarily the fault of the TPS, but conceivably the failure of the parties involved to fully understand the role of, and the typical basic framework of the TPS. The application of a modern management approach to problem-solving, namely: TSI, will aide in facilitating an understandmg of the TPS and the appropriate adjustment to be made for each particular project. 4 The application of TSI In order to highlight the application of TSI approach, a brief philosophical idealom underpinning TSI will be given. Secondly, an overview of the TSI approach will be given.

7 Lastly, comments will be made on its application to the TPS and hybrid versions of the TPS. 4.1 Introduction In an industry characterised by accelerating change, increasing uncertainty and growing complexity, it is apparent that these hybrid fornls of the TPS as discussed in the above surveys, are used without due consideration to their implications in managing the primary project parameters. The approach of using hybrid forms of the TPS without changing the tradtional management structure and its respective contractual arrangements has neglected to take cognisance of the project dyilamics. Furthermore, the approach has left crucial human-related management issues unanswered [l 1 ] [ 171 [ 181. It is contented by Flood [19], that the management of project parameters can be improved via an effective approach to management that assumes the organisational structure is that of a sociccultural system i.e., the aspect of culture is included within the management scenario of the hybrid TPS. The socic-cultural perception of the project organisation, is underpinned by the philosophy of idealogy of critical systerns thinking. Critical systems thlnking has developed as a direct result of the criticisms levelled at the earlier systems approaches [20]. The philosophical idealogy of critical systems thinking is defined by the three commitments, namely: to critique (constant questioning of the practice of all procurement systems), to emancipation (recognition of project personnel with the project organisation and their potential for full development via free and equal participation in the management of the project), and to plzlralisrn (a realisation that all procurement systems have a contribution to make. and that no single procurement system is suecient to address the full range of probleinatic situations facing various building projects) [20]. This innovative way of thlnking encourages a change in one's perception of the global environment as a whole, and hence the project procurement system, and provides the philosophical underpinning for a new approach to planning, designing, and "problem solving" [21]. The approach is that of Total Systems Intervention (TSI), a brief overview of which is presented hereunder. 4.2 Total systems intervention (TSI) There are three phases of TSI, namely: creativity, choice and impleinentation Creativity The creativity phase requires the use of systems metaphors that focus attention on Merent aspects of the project organisation's functioning in order to encourage project managers to thmk creatively about the project through the procurement system The intention is that at the end of the creativity phase a dominant metaphor will emerge which highlights the main concerns and interests of the procurement system and provides the basis for a choice of an appropriate intervention methodology.

8 4.2.2 Choice The choice phase requires that an appropriate systems-based intervention methodology that suits the characteristics of the organisation's situation (established during the creativity phase), be chosen. Flood and Jackson [2 11 propose a two-dimensional framework that is aimed at aiding this decision-inalung process. The first dimension refers to the co~nplexity of the system that constitutes the problem situation i.e., simple and complex systems. The second dimension pertains to the relationship between the individuals or parties who stand to gainnose from a systems involvement i.e.. unitary, pluralist or coercive. Table 2 depicts a summary of the appropriate systems inethodology within each of the problem contexts and the underlying metaphor that is established during the creativity phase. The outcome of the choice phase is that a donunant systems methodology will be chosen. Table 2 Systems methodologies related to systems metaphors and problem contexts [2 11 Systems Methodology (Examples) Systems Dynamics Viable Systems Diagnosis Strategic Assumption Surfacing and Testing (SAST) Interactive Planning Soft Systems Methodology (SSM) Critical System Heuristic Assuinptionsl Problem Contexts S-u C-u S -P C - P C-P S-Co Undelying Metaphors Machne, Team Organism, Brain, Team Machine, Coalition, Culture Brain, Coalition, Culture Organism, Coalition, Culture Machinel Organism, Prison Note : S is simple, C is complex, U is unitary, P is pluralist, Co is coercive Implementation The implementation phase's task is to employ a particular systems methodology in order to transform the dominant vision of the project andlor the procurement system (the TPS or hybrid

9 versions of TPS), its structure and the general orientation adopted towards concerns and problems, into specific proposals for change. The aim of tlus phase is to bring about coordinated change in those aspects of the project and/or the procurement system currently fundamental to its effective and efficient functioning The application of TSI Creativify - The establishment of the appropriate systems metaphor to be utilised is solely dependent on what aspects of the organisation within the procurement system you are wishing to highlight. For example : If you are wishing to establish the participants to the procurement system, and their perceptions of each other and the procurement system itself, then the adoption of the culture metaphor is seen to be the most appropriate under these circumstances. Choice - According to Table 2, the adoption of the culture metaphor allows you the choice of three methodologies, namely: SAST, Interactive Planning, and SSM. In order to narrow the options down, the solution would be to analyse the problem contexts and the other underlying systems nietaphors wihn those system methodologies and choose the nlethodology that best suits the requirements for the analysis of a particular project. Implementation - This last stage would involve the use of the chosen system's methodology to modify/adjust the procurement system so as to meet the requirements of a pmcular project. 5 Conclusions This paper is not trying to glorify the TPS or its hybrid versions as universal systems which are appropriate for all types of projects. It is arguing from the premise that what has been referred to as the TPS shortfalls are not necessarily true, because certain basic considerations (Section 2 : [2] and intrinsic hu~nanisticl systemic/ management factors have been neglected by project managers/client representatives in applying the hybrid versions of the TPS. It must be acknowledged from the outgoing arguments that. generally, the TPS is often used as a "default procurement system" i.e., it is used merely because consultants have failed to consider the issue of its appropriateness. Hybrid versions of the TPS by which clients procure buildings/other structures, and contractor's sell their services, have occurred in recent years, largely because of the dnve for value for money. At much the sanle time, project parameters standards (quality, tine, cost and utility) have begun to decline and it seems apparent to suggest that one of the main reasons for hs is the fact that the TPS hybrid versions have been used without appropriate consideration to the implications these versions may or may not have on the overall performance of a project. In order to address the implications of these hybrid versions of the TPS, a new approach to planning, designing, "problem solving" and evaluation needs to be adopted. In examining the complexities inherent in the traditional procurement system and its hybrid versions, the Total Systems Intervention (TSI) approach may be seen to be an appropriate intervention

10 methodology for the greater attainment of sliared meaning between the parties involved in the specific procurement system, to suit the particular requirements of a particular project. Lastly, the TSI approach serves to provide insight into those issues inherent in the construction industry in Botswana and most english spenlung conlmonwealth countries, and niore specifically, the Tradtional Procurement System and it various hybrid versions. 6 References 1. Rwelamila, P.D. and Savile, P.W. (1994) Hybrid value engineering: the challenge of construction project management in the 1990s. International Journal of Project Management, Vol. 12. No. 3. pp Hughes W.P. (1991) An analysis of construction management contracts. Technical Infornration Service No. 135, C.I.O.B. 3. Carpenter, J.B.G. (1981) The UK System of Construction Procurement and What is Wrong: How to Improve. Paper to the R.I.C.S. Quantity Surveyor's 12th Triennial Conference, April, London, United Kingdom. 4. Walker, A. (1984) Construction Project Management. Granada, London, United Kingdom. 5. Rwelamila, P.D. and Wiseman, G.T. (1995) Concrete quality management: a research study of the general contractor in South Africa, Construction and Building Materials, Vol. 9, No. 3. pp Construction News (1986) BPF contract: The professionals' verdict. Construction News, October, pp Dawson, H. (1988) A client's viewpoint. Chartered Quantity Surveyor, November, pp Chartered Quantity Surveyor (1989) Talking about design and build. Chartered Quantity Surveyor, February, United Kingdom. 9. Sidwell, A.C. (1982) A Critical Study of Project Team and Organisational Forms within the Building Process. Unpublished Ph.D. Thesis, University of Aston, Birmingham, United Kingdom. 10. Morris, P.W.G. and Hough, G.H. (1986) Preconditions of success and failure in nrajor projects. Major Projects Association Technical Paper No.3, September, United Kingdom. 11. Rwelarnila, P.D. (1992) The Factors Affecting Productivity in the Botswa~ia Construction industry - the case of Gaborone. Botswana Jo.urna1 of Technology, No. 1, pp Franks, J. (1990) Building Procurement System. Second edition. C.I.O.B., Ascot, United Kingdom. 13. Hindle, R.D. (1991) Deteriorating quality standards of new housing in the Western Cape. S A Builder, September, pp

11 14. Flanagan, R. and Norman, G. (1989) Pricing Policy, in The Management of Construction Firms (Eds. P.M. Hillebrandt and J. Cannon). Macmillan, London, United Kingdom. 15. Alnian, M.G. (1989) Barriers to Quality in South African Building. MBA Research report, Graduate School of Business, University of Cape Town,South Africa. 16. Ball, M. (1988) Rebuilding Construction : Economic Change and the British Construction Industry. Routledge, London, United Kingdom. 17. Gharajedaghi. J. (1985) Towards a Systems Theory of Organization. Intersysterns Publications, United States of America. 18. Van Donk. D.P. and Sanders, G. (1993) Organisational culture as a missing link in quality management. International Journal of Quality and Reliability Management, Vol.10, No.5, pp Flood, R.L. (1993) Beyond TQM. John Wiley & Sons, Chichester. 20. Schecter, D. (1991) Critical systems thinking in the 1980's : A connective summary, in Critical Systems Thinking : Directed Readings (Eds. R.L.Flood and M.C. Jackson). John Wiley & Sons, Chichester, pp Flood, R.L. and Jackson, M.C. (1991) Creative Problem Solving : Total Systems Intervention. John Wiley & Sons, Chichester. Note: P D Rwelamila is a visiting Research Fellow to the Department of Building Sciences at the Royal Institute of Technology and is currently on sabbatical leave from the Department of Construction Economics and Management. University os Cape Town.

Introduction. Project Management in New Zealand

Introduction. Project Management in New Zealand AN ANALYSIS OF THE USE OF INFORMATION TECHNOLOGY FOR PROJECT MANAGEMENT IN THE NEW ZEALAND CONSTRUCTION INDUSTRY Dr Suzanne Wilkinson, Senior Lecturer, Department of Civil and Resource Engineering The

More information

PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS

PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS PERCEPTIONS OF TIME, COST AND QUALITY MANAGEMENT ON BUILDING PROJECTS Professor P.A. Bowen and Associate Professor K.S. Cattel, University of Cape Town K.A. Hall, The University of New South Wales Associate

More information

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012. RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as

More information

Check. They re Chartered. Chartered Project Managers

Check. They re Chartered. Chartered Project Managers Check. They re Chartered. Chartered Project Managers The Society of Chartered Surveyors Ireland is the leading organisation of its kind in Ireland for professionals working in the property, land and construction

More information

THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy

THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM. Mr C. A. F. Sweet The South Institute of Mining and Metallurgy THE RELATIONSHIP BETWEEN THE CLIENT, CLIENTS PROJECT TEAM AND THE EPCM PROJECT TEAM Mr C. A. F. Sweet The South Institute of Mining and Metallurgy The inter-relationship between these parties and the effect

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

CONTRACTOR DEVELOPMENT MODELS THAT MEET THE CHALLENGES OF GLOBALISATION - A CASE FOR DEVELOPING MANAGEMENT CAPABILITY OF LOCAL CONTRACTORS

CONTRACTOR DEVELOPMENT MODELS THAT MEET THE CHALLENGES OF GLOBALISATION - A CASE FOR DEVELOPING MANAGEMENT CAPABILITY OF LOCAL CONTRACTORS CONTRACTOR DEVELOPMENT MODELS THAT MEET THE CHALLENGES OF GLOBALISATION - A CASE FOR DEVELOPING MANAGEMENT CAPABILITY OF LOCAL CONTRACTORS W.S. DLUNGWANA CSIR Division of Building and Construction Technology,

More information

Nottingham Trent University Course Specification

Nottingham Trent University Course Specification Nottingham Trent University Course Specification 1. 2. 3. 4. 5. Basic Course Information Awarding Institution: School/Campus: Final Award, Course Title and Modes of Study: Normal Duration: UCAS Code: Nottingham

More information

CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT

CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT CRITICAL SUCCESS FACTORS OF PROJECT MANAGEMENT SHAMIL NAOUM and DANIEL FONG Department of Property, Surveying and Construction, London South Bank University, 103 Borough Road, London, UK, SE1 0AA. naoums@lsbu.ac.uk

More information

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department

More information

PUBLIC WORKS CONCESSIONS AND SERVICE CONCESSIONS ANNUAL REPORT - 2011 - ITALY. (June 2011) Prof. Francesco GOISIS

PUBLIC WORKS CONCESSIONS AND SERVICE CONCESSIONS ANNUAL REPORT - 2011 - ITALY. (June 2011) Prof. Francesco GOISIS PUBLIC WORKS CONCESSIONS AND SERVICE CONCESSIONS ANNUAL REPORT - 2011 - ITALY (June 2011) Prof. Francesco GOISIS INDEX 1. THE CONCEPT OF CONCESSION AND HOW TO DISTINGUISH IT FROM THE CONCEPT OF PUBLIC

More information

Prescription of qualifications: ARB Criteria at Parts 1, 2 and 3

Prescription of qualifications: ARB Criteria at Parts 1, 2 and 3 Prescription of qualifications: ARB Criteria at Parts 1, 2 and 3 Architects Registration Board 8 Weymouth Street London W1W 5BU Telephone 020 7580 5861 Facsimile 020 7436 5269 www.arb.org.uk Approved:

More information

School of Computing and Technology

School of Computing and Technology School of Computing and Technology We offer employmentfocused education and research in computing, the built environment and engineering, giving our students industry-relevant skills and knowledge. Applied

More information

Project manager services

Project manager services Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism

More information

New product development within ABC Electronics

New product development within ABC Electronics New product development within ABC Electronics ABC Electronics is involved in design and manufacture of products for the IT industry; it has core technical expertise in acoustics, electronics design and

More information

The S 3 (Strategy-Service-Support) Framework for Business Process Modelling

The S 3 (Strategy-Service-Support) Framework for Business Process Modelling The S 3 (Strategy-Service-Support) Framework for Business Process Modelling P. Loucopoulos Department of Computation University of Manchester Institute of Science & Technology P.O. Box 88, Manchester,

More information

Guaranteed Maximum Price contracts in Western Australia

Guaranteed Maximum Price contracts in Western Australia Guaranteed Maximum Price contracts in Western Australia P. R. Davis 1, D. Stevenson 2 1 Curtin University of Technology Perth WA 2 Project Director INCOLL - Project Management Consultants Corresponding

More information

Quality Management Subcontractor QM Guide-Section Two

Quality Management Subcontractor QM Guide-Section Two SECTION TWO QUALITY MANAGEMENT SYSTEMS Version No 1. PREFACE This document has been developed to assist subcontractors to meet Monaco Hickeys (MHPL) Quality Management (QM) requirements whilst working

More information

DETERMINANTS OF PROJECT MANAGEMENT SUCCESS

DETERMINANTS OF PROJECT MANAGEMENT SUCCESS DETERMINANTS OF PROJECT MANAGEMENT SUCCESS Gary Walker, Dr Shamil Naoum and Professor Rod Howes South Bank University, School of Construction, London. SW8 2JZ One of the features of the construction industry

More information

EMPLOYING QUINQUENNIAL ARCHITECTS/SURVEYORS AND OTHER

EMPLOYING QUINQUENNIAL ARCHITECTS/SURVEYORS AND OTHER EMPLOYING QUINQUENNIAL ARCHITECTS/SURVEYORS AND OTHER 5 PROFESSIONAL ADVISORS GUIDANCE SHEET It is important for every church to have a good working relationship with its QI architect/surveyor as well

More information

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution

More information

INNOVATION AND STRATEGIC PLANNING AS KEY ELEMENTS TO ENTREPRENEURIAL SUCCESS

INNOVATION AND STRATEGIC PLANNING AS KEY ELEMENTS TO ENTREPRENEURIAL SUCCESS INNOVATION AND STRATEGIC PLANNING AS KEY ELEMENTS TO ENTREPRENEURIAL SUCCESS JOY JOLLY MUTAGA IENMJOURNAL DEPARTMENT OF BUSINESS MANAGEMENT UNIVERSITY OF PRETORIA Abstract: This study investigates the

More information

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement Government of the Kingdom of Lesotho Ministry of Public Works and Transport Project Employer Contractor Contract Date Contract No Principal Building Agreement MINISTRY OF PUBLIC WORKS & TRANSPORT BUILDING

More information

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy. Senior Project Manager Job Description Reference: 102014/51 Job Title: Senior Project Manager Purpose of Role: The University is committed to providing an environment conducive to high quality teaching

More information

Procurement Systems and Project Organisation Model for Low Cost Housing

Procurement Systems and Project Organisation Model for Low Cost Housing Procurement Systems and Project Organisation Model for Low Cost Housing Murtala A. OLADAPO, Nigeria Key words: Procurement systems, project organisation, sustainable, low-cost housing. ABSTRACT Procurement

More information

STAGE 1 COMPETENCY STANDARD FOR PROFESSIONAL ENGINEER

STAGE 1 COMPETENCY STANDARD FOR PROFESSIONAL ENGINEER STAGE 1 STANDARD FOR PROFESSIONAL ENGINEER ROLE DESCRIPTION - THE MATURE, PROFESSIONAL ENGINEER The following characterises the senior practice role that the mature, Professional Engineer may be expected

More information

The application of lean production to project management

The application of lean production to project management The application of lean production to project management Michael Horman & Russell Kenley m.horman@architecture.unimelb.edu.au kenley@arbld.unimelb.edu.au Faculty of Architecture, Building and Planning

More information

How To Design A Project

How To Design A Project Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project

More information

What is effective Design Management?

What is effective Design Management? What is effective Design Management? Design Management is becoming increasingly recognised as critical to the success of complex construction projects. However, the role of the Design Manager is poorly

More information

SAQA LOGO: QUALIFICATION TITLE Bachelors Degree in Quantity Surveying (NQF level 7) based on Unit Standards. LEVEL: NQF level 7 CREDITS: 360 FIELD:

SAQA LOGO: QUALIFICATION TITLE Bachelors Degree in Quantity Surveying (NQF level 7) based on Unit Standards. LEVEL: NQF level 7 CREDITS: 360 FIELD: QUALIFICATION TITLE Bachelors Degree in Quantity Surveying (NQF level ) based on Unit Standards SAQA LOGO: LEVEL: NQF level CREDITS: 360 FIELD: NSB 12: Physical Planning and Construction SUB-FIELD: Physical

More information

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE

More information

A SYSTEMS MODEL OF PROJECT MANAGEMENT

A SYSTEMS MODEL OF PROJECT MANAGEMENT A SYSTEMS MODEL OF PROJECT MANAGEMENT Richard Brian Barber Research Student School of Civil Engineering Australian Defence Force Academy Canberra ACT Australia 2600 barberrb@bigpond.net.au INTRODUCTION

More information

The Client and the Architect

The Client and the Architect The Client and the Architect Giving the client more than they ever dreamt of within budget and on time? Design & Quality Quality, above all, is about care, people, passion, consistency, eyeball contact

More information

Contract Management. Brief 22. Public Procurement. September 2011

Contract Management. Brief 22. Public Procurement. September 2011 Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This

More information

The South African Council for the Project and Construction Management Professions (SACPCMP)

The South African Council for the Project and Construction Management Professions (SACPCMP) The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act

More information

Effects of Project Management on the Performance of a Construction Firm in Nigeria

Effects of Project Management on the Performance of a Construction Firm in Nigeria Effects of Project Management on the Performance of a Construction Firm in Nigeria Irefin, Isaac Adeyemi, PhD African Institute for Science Policy and Innovation Obafemi Awolowo University Ile-Ife, Nigeria

More information

A comparison of supply chain risk perceptions in Original Equipment Manufacturers and Tier One suppliers: A case-study in the aerospace industry.

A comparison of supply chain risk perceptions in Original Equipment Manufacturers and Tier One suppliers: A case-study in the aerospace industry. 011-0290 A comparison of supply chain risk perceptions in Original Equipment Manufacturers and Tier One suppliers: A case-study in the aerospace industry. Naomi Brookes Amrik Singh Aston Business School

More information

THE EDUCATION FRAMEWORK FOR MASTERS DEGREE PROGRAMMES

THE EDUCATION FRAMEWORK FOR MASTERS DEGREE PROGRAMMES THE EDUCATION FRAMEWORK FOR MASTERS DEGREE PROGRAMMES SECTION 1 General Information about the CIOB INDEX REFERENCE SUBJECT PAGE REFERENCE Section 1 General Information about the CIOB Page 3 1.1 About the

More information

Programs, standalone & component projects, and perceptions of scope of project management applicability

Programs, standalone & component projects, and perceptions of scope of project management applicability Programs, Standalone & Component Programs, standalone & component projects, and perceptions of scope of project management applicability By Alan Stretton ABSTRACT This paper first discusses initiation

More information

Measuring, Estimating and Tendering Processes in Construction and the Built Environment

Measuring, Estimating and Tendering Processes in Construction and the Built Environment Unit 9: Measuring, Estimating and Tendering Processes in Construction and the Built Environment Unit code: QCF Level 3: Credit value: 10 Guided learning hours: 60 Aim and purpose F/600/0223 BTEC Nationals

More information

EMPLOYABILITY AND THE UNDERGRADUATE BUILDING SURVEYING PROGRAMME AT THE UNIVERSITY OF SALFORD

EMPLOYABILITY AND THE UNDERGRADUATE BUILDING SURVEYING PROGRAMME AT THE UNIVERSITY OF SALFORD EMPLOYABILITY AND THE UNDERGRADUATE BUILDING SURVEYING PROGRAMME AT THE UNIVERSITY OF SALFORD Andy Bowden, University of Salford, School of Construction & Property Management. BACKGROUND This reflective

More information

This research was funded by the Cooperative Research Centre for Construction Innovation, part of the Australian Government's CRC Program.

This research was funded by the Cooperative Research Centre for Construction Innovation, part of the Australian Government's CRC Program. Relational Contracting, Culture and Globalisation Professor Steve Rowlinson Department of Real Estate and Construction, The University of Hong Kong, Hong Kong, steverowlinson@hku.hk Fiona Y.K. Cheung Researcher,

More information

MSc in Construction Management (Cycle 2, level 4)

MSc in Construction Management (Cycle 2, level 4) (Cycle 2, level 4) is a 2 year full-time graduate study program of 120 ECTS credits (4 semesters, 30 ECTS each semester). Students generally take 90 ECTS in specialized courses and a 30 ECTS thesis. In

More information

Before : THE HONOURABLE MR JUSTICE COULSON - - - - - - - - - - - - - - - - - - - - - Between : PANTELLI ASSOCIATES LIMITED.

Before : THE HONOURABLE MR JUSTICE COULSON - - - - - - - - - - - - - - - - - - - - - Between : PANTELLI ASSOCIATES LIMITED. Neutral Citation Number: [2010] EWHC 3189 (TCC) IN THE HIGH COURT OF JUSTICE QUEEN'S BENCH DIVISION TECHNOLOGY AND CONSTRUCTION COURT Case No: HT-10-332 Royal Courts of Justice Strand, London, WC2A 2LL

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

The Role of Building Construction Project Team Members In Building Projects Delivery

The Role of Building Construction Project Team Members In Building Projects Delivery IOSR Journal of Business and Management (IOSR-JBM) e-issn: 2278-487X, p-issn: 2319-7668. Volume 14, Issue 1 (Sep. - Oct. 2013), PP 30-34 The Role of Building Construction Project Team Members In Building

More information

Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries

Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries Effective Front-End Project Management A Key Element in Achieving Project Success in Developing Countries O O FANIRAN School of Civil and Environmental Engineering The University of New South Wales Sydney

More information

DEFECT EXCLUSIONS IN CONTRACT WORK POLICIES

DEFECT EXCLUSIONS IN CONTRACT WORK POLICIES WHITEPAPER May 2014 www.beroeinc.com DEFECT EXCLUSIONS IN CONTRACT WORK POLICIES The need for risk balance and transfer of risk in highly invested construction projects has resulted in the fast growth

More information

Module 1: Introduction to Industrial Energy Management

Module 1: Introduction to Industrial Energy Management Module 1: Introduction to Industrial Energy Management Organisations that successfully manage energy have business processes to plan, monitor, and control energy use, just as they do for other corporate

More information

Case study as a research strategy: Investigating extreme weather resilience of construction SMEs in the UK

Case study as a research strategy: Investigating extreme weather resilience of construction SMEs in the UK Case study as a research strategy: Investigating extreme weather resilience of construction SMEs in the UK Gayan Wedawatta School of the Built Environment, the University of Salford, UK g.s.d.wedawatta@edu.salford.ac.uk

More information

KEYWORDS: Co-design, design games, distributed design processes, network theories, relationship management

KEYWORDS: Co-design, design games, distributed design processes, network theories, relationship management Co-Creation in Distributed Value Creation Systems and Networks (blank line) Anne Louise Bang Kolding School of Design, Kolding, Denmark alb@dskd.dk (blank line) Poul Rind Christensen Kolding School of

More information

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT

RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) RISK MANAGEMENT JUST A PART OF PROJECT MANAGEMENT RISK MANAGEMENT OVERVIEW - APM Project Pathway (Draft) Risk should be defined as An uncertain event that, should it occur, would have an effect (positive or negative) on the project or business objectives.

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

The Open University s repository of research publications and other research outputs

The Open University s repository of research publications and other research outputs Open Research Online The Open University s repository of research publications and other research outputs From professional to PhD student: challenges of status transition Journal Article How to cite:

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

Human Resources Management Philosophy JAGODA MRZYGŁOCKA-CHOJNACKA PHD 1

Human Resources Management Philosophy JAGODA MRZYGŁOCKA-CHOJNACKA PHD 1 Human Resources Management Philosophy JAGODA MRZYGŁOCKA-CHOJNACKA PHD 1 Human Resources Management Philosophy The HR Management Philosophy is not mainly about Human Resources Function. It is more about

More information

On the attributes of a critical literature review. Saunders, Mark N. K. 1 & Rojon, Céline 2. United Kingdom.

On the attributes of a critical literature review. Saunders, Mark N. K. 1 & Rojon, Céline 2. United Kingdom. On the attributes of a critical literature review Saunders, Mark N. K. 1 & Rojon, Céline 2 1 School of Management, University of Surrey, Guildford, GU2 7XH, United Kingdom; 2 Department of Psychology &

More information

Analysing the types of procurement used in the UK: a comparison of two data sets.

Analysing the types of procurement used in the UK: a comparison of two data sets. Analysing the types of procurement used in the UK: a comparison of two data sets. 5,094 words Stephen Gruneberg, School of Construction Management and Engineering, University of Reading, Whiteknights,

More information

BUILDING CONSTRUCTION PRIMARY TASK MODELS

BUILDING CONSTRUCTION PRIMARY TASK MODELS Construction Informatics Digital Library http://itc.scix.net/ paper w78-1996-319.content BUILDING CONSTRUCTION PRIMARY TASK MODELS Kangari R. and Sadri S. ABSTRACT: This paper provides a foundation for

More information

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7.

What's Wrong with Project Management? Introduction. Welcome to the November 2009 INSIGHTS published by acumen7. Welcome to the November 2009 INSIGHTS published by acumen7. The purpose of this newsletter is to bring you new perspectives on key subjects to stimulate your own thoughts and ideas. In each edition (which

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Overview COSCSMO10. Implement, monitor and control strategic procurement systems in construction management

Overview COSCSMO10. Implement, monitor and control strategic procurement systems in construction management Overview This standard is about agreeing and implementing with stakeholders what systems are most effective for managing the project. The systems identified will need to be prioritised and formalised if

More information

A Soft Approach to Solving Hard Problems in Construction Project Management

A Soft Approach to Solving Hard Problems in Construction Project Management Second International Conference on Construction in the 21 st Century (CITC-II) Sustainability and Innovation in Management and Technology 10-12 December, 2003, Hong Kong A Soft Approach to Solving Hard

More information

Proceedings of the 34th Hawaii International Conference on System Sciences - 2001

Proceedings of the 34th Hawaii International Conference on System Sciences - 2001 Aligning Business and Information Technology through the Balanced Scorecard at a Major Canadian Financial Group: its Status Measured with an IT BSC Maturity Model Wim Van Grembergen University of Antwerp

More information

Dental Contractor Loss Analysis Exercise

Dental Contractor Loss Analysis Exercise Dental Contractor Loss Analysis Exercise A report summarising the results of a loss analysis exercise aimed at measuring the prevalence of suspected fraud in contractor claims within NHS dental services.

More information

RICHARD HAMILTON MORRIS

RICHARD HAMILTON MORRIS RICHARD HAMILTON MORRIS D I P A R B F C I A R B M A C O S T E M A P M A C I O B SUMMARY OF QUALIFICATIONS PROFESSIONAL EXPERIENCE CEM Diploma in Arbitration Fellow of the Chartered Institute of Arbitrators

More information

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a

More information

Coaching and mentoring - The role of experience and sector knowledge

Coaching and mentoring - The role of experience and sector knowledge Page 10 Coaching and mentoring - The role of experience and sector knowledge Jonathan Passmore, OPM, 252b Gray s Inn Road, London WC1X 8XG Email contact: jonathancpassmore@yahoo.co.uk Abstract This article

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

Managing new relationships: design sensibilities, the new information and communication technologies and schools 1.

Managing new relationships: design sensibilities, the new information and communication technologies and schools 1. Managing new relationships: design sensibilities, the new information and communication technologies and schools 1. Chris Bigum Central Queensland University On- Line Paper & Copyright This draft paper

More information

Royal Institute of British Architects. Procurement policy. Building teams achieving value

Royal Institute of British Architects. Procurement policy. Building teams achieving value Royal Institute of British Architects Procurement policy Building teams achieving value November 2001 RIBA Procurement Policy The RIBA is committed to construction procurement that: R provides the best

More information

Employee Health and Well being in the NHS: A Trust Level Analysis

Employee Health and Well being in the NHS: A Trust Level Analysis Employee Health and Well being in the NHS: A Trust Level Analysis Anna Topakas Lul Admasachew Jeremy Dawson Aston Business School, Aston University Contents Executive Summary...2 1. Background...3 2. Methods...4

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

Project Management Professional. Group BUSINESS PLAN 2013 2015

Project Management Professional. Group BUSINESS PLAN 2013 2015 Project Management Professional Group BUSINESS PLAN 2013 2015 In construction many projects do not meet their required performance standards or are delivered late and over budget. These issues can be directly

More information

Evaluating the effects of communication in construction project delivery in Nigeria

Evaluating the effects of communication in construction project delivery in Nigeria Global Journal of Environmental Science and Technology: ISSN-2360-7955, Vol. 2(5): pp 048-054, June, 2014. Copyright 2014 Spring Journals Full Length Research Paper Evaluating the effects of communication

More information

Policy Statement 16/2006. Acute and Multidisciplinary Working

Policy Statement 16/2006. Acute and Multidisciplinary Working RCN Policy Unit Policy Statement 16/2006 Acute and Multidisciplinary Working The Royal College of Nursing of the United Kingdom and the Royal College of Physicians (London) September 2006 Royal College

More information

MSc Project Management

MSc Project Management School of Construction Management and Engineering MSc Project Management Developing tomorrow s project leaders in construction Postgraduate Programme information What is Project Management? Project management

More information

CLIENT / PROJECT MANAGER AGREEMENT

CLIENT / PROJECT MANAGER AGREEMENT Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT

More information

PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY

PROJECT RISK MANAGEMENT IN THE QUEENSLAND ENGINEERING CONSTRUCTION INDUSTRY: A SURVEY Lyons, Terry and Skitmore, Martin (2004) Project risk management in the Queensland engineering construction industry: a survey. International Journal of Project Management 22(1):pp. 51-61. Copyright 2004

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria

Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria Whole Life Costing and Cost Management Framework for Construction Projects in Nigeria H. Onukwube Senior Lecturer, Department of Building, University of Lagos, Akoka, Yaba, Lagos. Nigeria. Email: onukwube12345678@yahoo.com

More information

School Construction Projects

School Construction Projects The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect

More information

How To Become A Construction Worker In Nsw

How To Become A Construction Worker In Nsw 2012 Salary Survey - Results NSW Building and Construction Industry Contents Foreword 1 Survey Partners 2 Section A General Questions on Company Operations 3 Section B Questions on Salary Package levels

More information

Pearson Education Limited 2003

Pearson Education Limited 2003 156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

CURRICULUM for Diploma of Technology in Project Management

CURRICULUM for Diploma of Technology in Project Management CURRICULUM for Diploma of Technology in Project Management Revised 1 April 2011 Table of contents 1. Introduction 2. The purpose of the programme 3. Programme duration 4. Programme title 5. Admission requirements

More information

OUTLINE SCOPE OF SERVICES FOR THE ROLE OF INFORMATION MANAGMENT

OUTLINE SCOPE OF SERVICES FOR THE ROLE OF INFORMATION MANAGMENT OUTLINE SCOPE OF SERVICES FOR THE ROLE OF INFORMATION MANAGMENT first edition 2013 The CIC acknowledges the technical input and leadership provided by the BIM Task Group in support of the production of

More information

Draft guidelines and measures to improve ICT procurement. Survey results

Draft guidelines and measures to improve ICT procurement. Survey results Draft guidelines and measures to improve ICT procurement Survey results Europe Economics Chancery House 53-64 Chancery Lane London WC2A 1QU Tel: (+44) (0) 20 7831 4717 Fax: (+44) (0) 20 7831 4515 www.europe-economics.com

More information

Guide to Reviewing Contract Documentation

Guide to Reviewing Contract Documentation Guide to Reviewing Contract Documentation Introduction In order to help members address the issues associated with the review of contracts The Royal Institute of British Architects (RIBA), in association

More information

PEER REVIEW HISTORY ARTICLE DETAILS VERSION 1 - REVIEW

PEER REVIEW HISTORY ARTICLE DETAILS VERSION 1 - REVIEW PEER REVIEW HISTORY BMJ Open publishes all reviews undertaken for accepted manuscripts. Reviewers are asked to complete a checklist review form (http://bmjopen.bmj.com/site/about/resources/checklist.pdf)

More information

326 H. I. JIMOH. Aims and Objectives of the Study

326 H. I. JIMOH. Aims and Objectives of the Study Kamla-Raj 2008 J. Hum. Ecol., 23(4): 325-329 (2008) Drainage Problems in a Tropical Environment: Perspectives on Urban Quality Management H. I. Jimoh Department of Geography, University of Ilorin, Ilorin,

More information

DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM

DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM DEVELOPMENT OF CONSTRUCTION BEST PRACTICE EXPERT SYSTEM Joanna Poon, Keith Potts and Patricia Cooper School of Engineering and the Built Environment University of Wolverhampton Wolverhampton WV1 1SB UK

More information

Extending Unfair Contract Term Protections to Small Businesses. SUBMISSION by the OFFICE OF THE AUSTRALIAN SMALL BUSINESS COMMISSIONER

Extending Unfair Contract Term Protections to Small Businesses. SUBMISSION by the OFFICE OF THE AUSTRALIAN SMALL BUSINESS COMMISSIONER Extending Unfair Contract Term Protections to Small Businesses SUBMISSION by the OFFICE OF THE AUSTRALIAN SMALL BUSINESS COMMISSIONER AUGUST 2014 We are writing to provide some observations on the small

More information

Construction Technology and Design in Construction and Civil Engineering

Construction Technology and Design in Construction and Civil Engineering Unit 5: Construction Technology and Design in Construction and Civil Engineering Unit code: QCF Level 3: Credit value: 10 Guided learning hours: 60 Aim and purpose T/600/0283 BTEC Nationals The aim of

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

TOTAL QUALITY MANAGEMENT ADOPTION BY PROCESS ENGINEERING DESIGN FIRMS IN SOUTH AFRICA

TOTAL QUALITY MANAGEMENT ADOPTION BY PROCESS ENGINEERING DESIGN FIRMS IN SOUTH AFRICA TOTAL QUALITY MANAGEMENT ADOPTION BY PROCESS ENGINEERING DESIGN FIRMS IN SOUTH AFRICA ABSTRACT L. NJENGE University of Johannesburg, Faculty of Engineering and Built Environment University of Johannesburg,

More information