1 DCAA New Tactics in Obtaining Contractor Internal audit reports By Todd Bishop and David Eck, CPA In August 2012, the Defense Contract Audit Agency (DCAA) issued updates to its policy guidance and the Contract Audit Manual associated with audits of Contractor Business Systems. Permeating these updates is the DCAA long established belief that contractor internal audit reports are a necessity to the delivery of a satisfactory audit. Although the courts have found internal audit reports are not a necessity, some individuals within the Agency continue to pressure contractors to cooperate or threaten submit or face the wrath. A recent GAO report added significant support to the DCAA position. Contractors respond to the DCAA requests in a wide variety of ways. At one extreme a company may provide entire internal audit report including workpapers and at the other extreme are contractors that deny access entirely. This is clearly spelled out in the Government Accountability Office s (GAO) report (GAO-12-88) dated December 8, 2011 entitled Defense Contract Audits-Actions Needed to Improve DCAA s Access to and Use of Defense Company Audit Reports. In this report, the GAO recommended that:... DCAA take steps to facilitate access to internal audits and assess periodically whether other actions are needed. DOD generally agreed to implement GAO s recommendations but expressed skepticism that this alone would fully ensure access to internal audits. What the GAO Found The GAO concluded that DCAA is not making full use of defense company internal audit reports to help accomplish its contract audit mission. The GAO believes that DCAA access to relevant internal audit reports is required for DCAA to meet the Generally Accepted Government Auditing Standards (GAGAS) requirements for assessing internal controls and the information is relevant to DCAA audit planning and risk assessment. The GAO believes that internal audit reports include information on defense contractor internal controls and business systems used to manage defense contracts that DCAA is responsible for auditing and contain information and analysis that DCAA could find useful as it conducts its own audit work. The GAO recommends that DCAA increase its access to and use of defense company internal audit reports.
2 The GAO reviewed 1,125 internal audits at seven large defense contractors during the period and found that the contractors generally complied with recognized professional standards (i.e., Institute of Internal Audit Standards) for organizing their internal audit departments and performing internal audits. Of the 1,125 internal audits reviewed, GAO determined that 520 audits relate to defense contracts and DCAA s contract audit mission. Of the 520 audits, DCAA only requested 115 internal audit reports. DCAA provided several reasons for not requesting other internal audit reports, including: Access to contractor audit information was not critical to the audit work being performed. DCAA had difficulty in determining which internal audit reports were relevant to DCAA s audit work (e.g., title of the audit report was not descriptive enough). Decrease in the number of DCAA audits performed over the last few years. Contractor requires DCAA to link the request for internal audits to an ongoing DCAA audit of a particular contract or proposal. DCAA Policy Memorandum In response to GAO s report and recommendations, DCAA issued an August 14, 2012 Policy Memorandum and made updates to the DCAA Contract Audit Manual (DCAM) to provide direction to the DCAA auditors for requesting and monitoring requests for contractors internal audit reports. The Policy Memorandum requires the DCAA Contract Audit Coordinator (CAC) offices and Field Audit Offices (FAOs) at major contractor locations to establish a process and a central point of contact to obtain and monitor DCAA s access to and use of internal audits. DCAM was updated to require the central point of contact to: Coordinate with the contractor and obtain a semi-annual summary level listing of all internal audit reports issued. The summary document will contain sufficient descriptions to ascertain whether the internal audit may affect Government contracts. Review the summary list of internal audits. If the summary is not adequate to determine which internal audits may affect Government contracts, coordinate with the contractor to obtain the information necessary. Provide the summary list to the CAC Network or the FAO s audit teams responsible for audits of the contractor. Send a request to the contractor for copies of reports and/or working papers considered pertinent by the auditors and provide the auditors copies of the information obtained from the contractor. Implement a process to track auditor s requests for internal audit reports and the contractor s response to the requests.
3 Provide DCAA Headquarters a semi-annual summary of all requests for internal audit reports, the contractor s response to each request and the audit assignment for which access to the internal audit report was requested. The guidance states that for non major contractors, a formal tracking process or a central point of contact is not mandatory, but notes that internal audit reports can still be useful in the performance of audits at these contractors. DCAA does acknowledge, as outlined in the GAO report, that the Agency cannot request unlimited access to all internal company materials, but should have access to materials relevant to its audit responsibilities. Contractors that fail to comply will face the Access to Record Procedures of the DCAA. These procedures may lead to a subpoena of the reports, if access is ultimately denied by the contractor and possibly to the next test case for DCAA and access to records in the courts. DCAA Authority to Access DCAA s use of its access authority was addressed in two court decisions issued in 1988, commonly referred to as Newport News I and Newport News II. The courts held that DCAA does not have unlimited power to demand access to all internal company documents, but they also held that DCAA may demand access to materials relevant to its audit responsibilities. The court further held that DCAA statutory subpoena power could not be used to access internal audits not tied to a specific contract or proposal. The Director of DCAA has not issued any subpoenas to obtain internal audits since 1988, primarily because DCAA cannot link any denial of internal audit reports to a specific contract or proposal. In the DCAA s first annual report to Congress issued in March 2012, the DCAA states that amendments to laws are required to give DCAA a much broader access to the types of records needed to accomplish the Agency s mission. If companies have a policy to release internal audit reports to DCAA, they should, at a minimum, require the auditor to identify the nexus between their request and a specific contract or proposal. Most contractors that have provided DCAA access say they receive no feedback from DCAA on the results of the evaluations of the audits and the extent of reliance. In fact, contractors believe that DCAA too often uses the reports for the sake of obtaining audit leads increasing DCAA audit work, where the procedural intent is alleged to rely on the internal audit work to reduce the quantity of DCAA s limited resources necessary to accomplish audit objectives.
4 One chief financial executive at a top five defense contractor commented: I used to provide DCAA with unrestricted access to internal audit reports and working papers, but when they started to misuse this information as audit leads to increase audit scope, I pulled back on the access. If DCAA is provided access to relevant internal audit information, contractors should require that the auditor provide timely feedback on their evaluations of this information and extent of reliance. The Internal Audit Access Road Ahead Contractors should expect a continued increase in the number of DCAA requests for internal audit reports. In anticipation of these requests, contractors should ensure they have adequate policies and procedures on describing the company s process for providing or not providing DCAA access to these reports, including: Identifying and segregating those reports that relate to DCAA s audit mission. Requiring DCAA to provide a link between requests for internal audit reports to specific contracts and proposals. Describing what access to internal audit reports and related working papers will be provided to DCAA (complete copies, executive summaries, review only with no copies provided, etc.). Requiring DCAA to provide timely feedback on its evaluations and use of internal audit reports. What is evident is more DCAA requests will be made and the subsequent scrutiny of internal audit reports and workpapers will certainly create future issues and challenges. For those contractors that deny access or provide limited access, it is likely that DCAA will follow its Denial of Access to Records process whereby up to four letters may be issued stating that the contractor has denied access to pertinent contract records which could lead to a DCAA subpoena for the requested documents. Additionally, these denials will likely erode well defined relationships with contracting officers at all levels and result in withholdings under the business systems rule. In the end, contractors should prepare for either providing internal audit reports at some level or develop a well defined legal position in anticipation of litigation. With the support of the GAO report and significant political pressure lobbying for Congress to provide DCAA broader statutory authority regarding access only time will tell if rational heads will prevail and contractors will be allowed to run their businesses
5 without threats. Time will also tell if contractors need to brace for additional barriers to success in an industry where the pendulum currently favoring auditors running the show with little getting done. If you have any questions or need assistance, please contact your Government Contracting Consultant or Todd Bishop at or David Eck at David Eck has more than 31 years experience working in the government accounting field. He has extensive knowledge and experience in all aspects of government laws and regulations, including the Federal Acquisition Regulations, individual agency supplements to the FAR, the Truth in Negotiations Act, the Cost Accounting Standards and the Office of Management and Budget (OMB) Circulars. David worked with the Defense Contract Audit Agency (DCAA) for more than 30 years and was responsible for the development and implementation of DCAA s contract audit policy, including the Contract Audit Manual and standard audit programs. Todd Bishop has more than 20 years of experience helping companies identify and resolve issues associated with cost accounting, financial management systems, requests for equitable adjustments and claims. Todd s work includes helping clients understand the requirements associated with compliance with Federal business system requirements, developing and implementing pricing strategies, indirect cost allocation solutions, developing accounting, estimating, procurement, project management and integrated system requirements for clients in various industries. About the Dixon Hughes Goodman LLP Government Contracting Industry Group: With more than 1,700 people in 11 states, Dixon Hughes Goodman is the largest certified public accounting firm based in the Southern U.S. and the 14th largest in the nation. Our Government Contracting Services Group is active in government contracting associations, keeps up to date with the effects of policies on the local and national levels and provides proactive advice to our clients. In addition, we actively monitor the Federal Acquisition Regulations (FAR), the Cost Accounting Standards (CAS) agenda, as well as changes to the Small Business Administration (SBA). Visit for more information
INSTRUCTION NUMBER 7640.02 August 22, 2008
Department of Defense INSTRUCTION NUMBER 7640.02 August 22, 2008 IG DoD SUBJECT: Policy for Follow-up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This Instruction: a. Reissues DoD
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 7640.02 April 15, 2015 IG DoD SUBJECT: Policy for Follow-Up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This instruction reissues DoD Instruction
GAO DEFENSE CONTRACT AUDITS. Actions Needed to Improve DCAA's Access to and Use of Defense Company Internal Audit Reports
GAO United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate December 2011 DEFENSE CONTRACT AUDITS Actions Needed to Improve DCAA's Access to and Use of Defense
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security
MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit
Focus. FEATURE COMMENT: DCAA Access To Information What You Need To Know And Strategies For Protecting Your Business
Reprinted from The Government Contractor, with permission of Thomson Reuters. Copyright 2014. Further use without the permission of West is prohibited. For further information about this publication, please
Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013
Report No. DODIG-2014-109 Inspector General U.S. Department of Defense SEPTEMBER 8, 2014 Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013 INTEGRITY EFFICIENCY ACCOUNTABILITY
Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers
Curtis Matthews, Managing Partner Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers Findley Gillespie, Senior Manager May 18, 2011 1 The material appearing in this presentation
Hotline Complaint Regarding the Defense Contract Audit Agency Examination of a Contractor s Subcontract Costs
Inspector General U.S. Department of Defense Report No. DODIG-2015-061 DECEMBER 23, 2014 Hotline Complaint Regarding the Defense Contract Audit Agency Examination of a Contractor s Subcontract Costs INTEGRITY
Strategies for Achieving Successful Audit Outcomes. Presented by: Noah Leiden, CPA Partner Patrick J. Fitzgerald, CPA Director
Strategies for Achieving Successful Audit Outcomes Presented by: Noah Leiden, CPA Partner Patrick J. Fitzgerald, CPA Director Agenda What is Success? Understanding and Impacting the Audit Process Strategies
You've successfully subscribed to this feed! Updated content can be viewed in Internet Explorer and other programs that use the Common Feed List.
Page 1 of 5 You've successfully subscribed to this feed! Updated content can be viewed in Internet Explorer and other programs that use the Common Feed List. View my feeds DCAA News Thursday, May 28, 2009,
Incurred Cost Submissions - It's Not Too Early!
Incurred Cost Submissions - It's Not Too Early! March 28, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP Agenda Treat Incurred Cost Submissions like a Project Why an Incurred Cost Submission?
DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member
DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member Agenda State of the Agencies DCAA/DCMA What does GAO have to say? What does DOD IG have to
Department of Defense MANUAL
Department of Defense MANUAL NUMBER 7600.07 August 3, 2015 IG DoD SUBJECT: DoD Audit Manual References: See Enclosure 1 1. PURPOSE. This manual: a. Reissues DoD 7600.07-M (Reference (a)) in accordance
1 1 1 2 2 2 2 3 3 3 3 3 4 4 4 4 5 back
Introduction Bid Protest Business Systems Design, Evalution and Validation Contractor Accounting & Compliance Risk Assessments Contractor Purchasing System Review (CPSR) Cost Accounting Standards (CAS)
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION
TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Internal Revenue Service September 14, 2010 Reference Number: 2010-10-115 This report has cleared the Treasury Inspector General for Tax Administration
Master Document Audit Program. Activity Code 19409 Compliance Audit CAS 409 Version 5.16, dated November 2015 B-1 Planning Considerations
Activity Code 19409 Compliance Audit CAS 409 B-1 Planning Considerations Audit Specific Independence Determination Members of the audit team and internal specialists consulting on this audit must complete
Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies
Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY
CHAPTER 8. Table of Contents
July 29, 2015 8(1) Paragraph CHAPTER 8 Table of Contents 8-000 Cost Accounting Standards Page 8-001 Scope of Chapter... 801 8-100 Section 1 --- Overview - Cost Accounting Standards Board (CASB) Rules and
The Changing Government Contractor Environment
The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.
DCAA and the Small Business Innovative Research (SBIR) Program
Defense Contract Audit Agency (DCAA) DCAA and the Small Business Innovative Research (SBIR) Program Judice Smith and Chang Ford DCAA/Financial Liaison Advisors NAVAIR 2010 Small Business Aviation Technology
DCAA Contract Audit Manual
D(1) APPENDIX D Table of Contents Paragraph Page D-000 Technical Specialist Assistance D-001 Scope... D1 D-100 Section 1 --- Deciding Whether Technical Specialist Assistance is Needed D-101 General...
Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions
Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions Nicole Mitchell, CPA Donna Dominguez Aronson LLC May 1, 2013 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland
QUALITY CONTROL REVIEW REPORT
IG-02-007 QUALITY CONTROL REVIEW REPORT ERNST & YOUNG LLP AND DEFENSE CONTRACT AUDIT AGENCY AUDIT OF SOUTHWEST RESEARCH INSTITUTE, FISCAL YEAR ENDED SEPTEMBER 24, 1999 January 23, 2002 OFFICE OF INSPECTOR
Master Document Audit Program. Activity Code 19404 Compliance Audit CAS 404 Version 5.15, dated November 2015 B-1 Planning Considerations
Activity Code 19404 Compliance Audit CAS 404 B-1 Planning Considerations Audit Specific Independence Determination Members of the audit team and internal specialists consulting on this audit must complete
July 6, 2015 11(1) CHAPTER 11
July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---
How to Establish an SBIR Accounting System that Can Withstand a Government Audit
In cooperation with Connecticut Innovations 4/16/14 How to Establish an SBIR Accounting System that Can Withstand a Government Audit Edward G. Jameson, CPA Managing Partner Jameson & Company, CPAs www.jamesoncpa.com
REVIEW OF NASA S INTERNAL CONTROLS FOR AWARDS WITH SMALL BUSINESSES
FEBRUARY 28, 2013 AUDIT REPORT OFFICE OF AUDITS REVIEW OF NASA S INTERNAL CONTROLS FOR AWARDS WITH SMALL BUSINESSES OFFICE OF INSPECTOR GENERAL National Aeronautics and Space Administration REPORT NO.
How To Audit A Government Contractor
Activity Code 17740 Version 6.11, dated November 2015 B-1 Planning Considerations Preaward Survey of Prospective Contractor Accounting System Audit Specific Independence Determination Members of the audit
Department of Defense DIRECTIVE
Department of Defense DIRECTIVE NUMBER 5400.11 October 29, 2014 DCMO SUBJECT: DoD Privacy Program References: See Enclosure 1 1. PURPOSE. This directive: a. Reissues DoD Directive (DoDD) 5400.11 (Reference
IDEA PAPER 95-A %JANJO 5`1995' B TITLE. AUTHOR. :.a EFANIE B. DUNCAN PROFESSIONAL MILITARY COMPTROLLER SCHOOL DEFINING RESPONSIBILITY IN MAINTAINING
PROFESSIONAL MILITARY COMPTROLLER SCHOOL IDEA PAPER TITLE DEFINING RESPONSIBILITY IN MAINTAINING FINANCIAL ACCOUNTING SYSTEMS AUTHOR. :.a EFANIE B. DUNCAN r Class T7 95-A %JANJO 5`1995' B COLLEGE FOR PROFESSIONAL
POST-GOVERNMENT EMPLOYMENT ADVICE OPINION REQUEST
POST-GOVERNMENT EMPLOYMENT ADVICE OPINION REQUEST (Read Privacy Act Statement on the last page before completing form.) REPORT CONTROL SYMBOL DD-GC(AR)2412 OMB No. 0704-0467 OMB approval expires Jun 30,
Defense Logistics Agency INSTRUCTION
Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned
Sage TimeSheet. Defending the Contractor Ensuring DCAA Compliance With Time and Expense Software
Sage TimeSheet Defending the Contractor Ensuring DCAA Compliance With Time and Expense Software Contents Introduction: Executive Summary.............................. 3 History and Mission of the DCAA..............................
GAO DCAA AUDITS. Allegations That Certain Audits at Three Locations Did Not Meet Professional Standards Were Substantiated
GAO United States Government Accountability Office Report to Congressional Addressees July 2008 DCAA AUDITS Allegations That Certain Audits at Three Locations Did Not Meet Professional Standards Were Substantiated
How to Establish an SBIR Accounting System that Can Withstand a Government Audit
In cooperation with Connecticut Innovations 2/27/14 How to Establish an SBIR Accounting System that Can Withstand a Government Audit Edward G. Jameson, CPA Managing Partner Jameson & Company, CPAs www.jamesoncpa.com
As the Defense Contract Audit Agency slowly
Reprinted from Government Contract Costs, Pricing & Accounting Report, with permission of Thomson Reuters. Further use without the permission of West is prohibited. For further information about this publication
DoD Methodologies to Identify Improper Payments in the Military Health Benefits and Commercial Pay Programs Need Improvement
Report No. DODIG-2015-068 I nspec tor Ge ne ral U.S. Department of Defense JA N UA RY 1 4, 2 0 1 5 DoD Methodologies to Identify Improper Payments in the Military Health Benefits and Commercial Pay Programs
Peckar & Abramson. A Professional Corporation Attorneys & Counselors at Law
A Professional Corporation Attorneys & Counselors at Law EXPANSION OF FEDERAL GOVERNMENT AUDIT POWERS AND PROGRAMS: WHAT TO DO WHEN THE AUDITORS ARRIVE Our earlier s described initiatives by the federal
Defending the Contractor: Ensuring DCAA Compliance with Time and Expense Software
Defending the Contractor: Ensuring DCAA Compliance with Time and Expense Software The Premier Sage Software Business Solutions Provider National Presence, Local Touch 1.800.425.9843 www.blytheco.com TABLE
DCAA Initiatives/Current Issues
Defense Contract Audit Agency DCAA Initiatives/Current Issues Maryland Association of CPAs 2010 Government Contractors' Conference September 21, 2010 Kenneth J. Saccoccia Assistant Director Policy and
Presenting the Numbers: Accounting Systems for Government Contractors
Presenting the Numbers: Accounting Systems for Government Contractors William D. Craven, CPA Senior Cost/Price Analyst CH2M HILL Plateau Remediation Company William D. Craven, CPA, CMA, CIA Cost/Price
What Exactly is an Acceptable Accounting System?
What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible
MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES
MEMORANDUM FOR THE HEADS OF DEPARTMENTS AND AGENCIES FROM: SUBJECT: Peter R. Orszag Director Managing the Multi-Sector Workforce Federal agencies use both federal employees and private sector contractors
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM
Master Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations
Activity Code 11070 Version 1.5, dated September 2015 B-01 Planning Considerations Accounting System Audit Audit Specific Independence Determination Members of the audit team and internal specialists consulting
Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update
Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update Baker Tilly Beers & Cutler, PLLC, is a wholly-owned subsidiary of Baker Tilly Virchow Krause, LLP. 2015 Baker Tilly Beers
Defense Contract Audit Agency NAVAIR Small Business Aviation Technology Conference
Defense Contract Audit Agency NAVAIR Small Business Aviation Technology Conference November 29-30, 2006 t Defense Contract Audit Agency Established in 1965 Separate Agency of the Department of Defense
Are You Looking to Sell Your Products & Services to the US Government? Overview
Are You Looking to Sell Your Products & Services to the US Government? What You Need to Know About Accounting, Compliance, and Reporting! 1 FICPA Overview The US Government is the largest consumer of goods
Understanding Unallowable Cost so You Don t Pay the Price
Understanding Unallowable Cost so You Don t Pay the Price Identification and Definition of Unallowable Costs per CAS and FAR An unallowable cost is one that: Under the provisions of any pertinent law,
Master Document Audit Program. Business System Deficiency Report Assignment. Version No. 1.3, dated June 2014 B-1 Planning Considerations
Activity Code 11090 B-1 Planning Considerations Business System Deficiency Report Assignment Audit Specific Independence Determination Members of the audit team and internal specialists consulting on this
October 15, 2015 1(1) CHAPTER 1. Table of Contents
October 15, 2015 1(1) CHAPTER 1 Table of Contents Paragraph Page 1-000 Introduction To Contract Audit 1-001 Scope of Chapter... 101 1-100 Section 1 --- Establishment and Responsibilities of DCAA 1-101
DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence
DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of
Department of Defense INSTRUCTION. DoD and Department of Veterans Affairs (VA) Health Care Resource Sharing Program
Department of Defense INSTRUCTION NUMBER 6010.23 January 23, 2012 Incorporating Change 1, Effective October 3, 2013 USD(P&R) SUBJECT: DoD and Department of Veterans Affairs (VA) Health Care Resource Sharing
This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance
This document has been archived. The Why and When list at the AAPD Archive identifies why the document has been archived and where current guidance may be found. Internal users may also access the OAA
Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT
Attachment II FLOW-DOWN CLAUSES APPLICABLE TO PURCHASE ORDERS INVOLVING FUNDS FROM A FEDERAL GOVERNMENT CONTRACT OR GRANT If the Order involves funds from a Federal government contract or funds from a
Procurement Reform - Documentation Requirements for Non-Profit Recipients
Mandatory Reference: N/A Supplementary Reference: 303 File: 30359s1 Procurement Reform - Documentation Requirements for Non-Profit Recipients To assist in meeting Agency streamlining goals, the collection
Small Business Contracting at Marine Corps Systems Command Needs Improvement
Inspector General U.S. Department of Defense Report No. DODIG-2016-019 NOVEMBER 10, 2015 Small Business Contracting at Marine Corps Systems Command Needs Improvement INTEGRITY EFFICIENCY ACCOUNTABILITY
DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process
Inspector General U.S. Department of Defense Report No. DODIG-2015-045 DECEMBER 4, 2014 DoD Cloud Computing Strategy Needs Implementation Plan and Detailed Waiver Process INTEGRITY EFFICIENCY ACCOUNTABILITY
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 8910.01 May 19, 2014 DoD CIO SUBJECT: Information Collection and Reporting References: See Enclosure 1 1. PURPOSE. This instruction: a. Reissues DoD Instruction
CHAPTER 3 FINANCIAL MANAGEMENT SYSTEMS: POLICY, ROLES AND RESPONSIBILITIES FOR CONFORMANCE, EVALUATION, AND REPORTING
CHAPTER 3 FINANCIAL MANAGEMENT SYSTEMS: POLICY, ROLES AND RESPONSIBILITIES FOR CONFORMANCE, EVALUATION, AND REPORTING 0301. GENERAL. By statute the head of a Federal agency is responsible for establishing
UNIT 34: COST ACCOUNTING STANDARDS
UNIT CERTIFICATION Statement of Completion has satisfactorily completed training in the duty of this Unit under the conditions described below and in accordance with the overall standard(s) for this Unit.
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63)
Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Pat Fitzgerald Director Defense Contract Audit Agency The views expressed in this presentation
Report No. D-2011-6-008
Hotline Review June 28, 2011 Hotline Complaint Regarding a Defense Contract Audit Agency Employee Conducting Private For-Profit Tax Business Activity on Government Time and Using Government Equipment Report
Ensure Compliance For Government Contractors
Ensure Compliance For Government Contractors Topics Overview NeoSystems Corp 2009-2012 ENSURE COMPLIANCE FOR GOVERNMENT CONTRACTORS TABLE OF CONTENTS V15C Learning Objectives... 4 Introduction... 5 Government
Five-Year Strategic Plan
U.S. Department of Education Office of Inspector General Five-Year Strategic Plan Fiscal Years 2014 2018 Promoting the efficiency, effectiveness, and integrity of the Department s programs and operations
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 5100.64 March 30, 2006 Certified Current as of December 3, 2010 GC, DoD SUBJECT: DoD Foreign Tax Relief Program References: (a) DoD Directive 5100.64, "DoD Foreign
GAO. Standards for Internal Control in the Federal Government. Internal Control. United States General Accounting Office.
GAO United States General Accounting Office Internal Control November 1999 Standards for Internal Control in the Federal Government GAO/AIMD-00-21.3.1 Foreword Federal policymakers and program managers
Are you in Compliance with the Financial Rules for 8(a) Companies?
Are you in Compliance with the Financial Rules for 8(a) Companies? Sales Less than $1M Withdrawals exceeding $250,000 are considered excessive. Compiled financial statements are required within 90 days
DCAA Guidelines. How the SBIR firm can work effectively with the Defense Contract Audit Agency
DCAA Guidelines How the SBIR firm can work effectively with the Defense Contract Audit Agency Today s Presenters OUTLINE Presenter Introduction DCAA & DCMA DCAA Overview Types of DCAA Audits What it takes
PAC 730.3.B.03/2012-07 April 24, 2014 14-PAC-005(R) MEMORANDUM FOR REGIONAL DIRECTORS, DCAA HEADS OF PRINCIPAL STAFF ELEMENTS, HQ, DCAA
DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PAC 730.3.B.03/2012-07 April 24, 2014 14-PAC-005(R) MEMORANDUM FOR
A. This Directive applies throughout DHS, unless exempted by statutory authority.
I. Purpose Department of Homeland Security DHS Directives System Directive Number: 103-02 Revision Number: 00 Issue Date: 6/19/2014 ENTERPRISE ARCHITECTURE MANAGEMENT This Directive establishes the Department
Department of Defense INSTRUCTION
Department of Defense INSTRUCTION NUMBER 3204.01 August 20, 2014 USD(AT&L) SUBJECT: DoD Policy for Oversight of Independent Research and Development (IR&D) References: See Enclosure 1 1. PURPOSE. This
GAO. Government Auditing Standards. 2011 Revision. By the Comptroller General of the United States. United States Government Accountability Office
GAO United States Government Accountability Office By the Comptroller General of the United States December 2011 Government Auditing Standards 2011 Revision GAO-12-331G GAO United States Government Accountability
Controls Over EPA s Compass Financial System Need to Be Improved
U.S. ENVIRONMENTAL PROTECTION AGENCY OFFICE OF INSPECTOR GENERAL Controls Over EPA s Compass Financial System Need to Be Improved Report No. 13-P-0359 August 23, 2013 Scan this mobile code to learn more
Master Document Audit Program
Activity Code 11510 B-1 Planning Considerations Information Technology General System Controls Audit Specific Independence Determination Members of the audit team and internal specialists consulting on
DoD Financial Management Regulation Volume 12, Chapter 5 September 1996 CHAPTER 5 GRANTS AND COOPERATIVE AGREEMENTS
CHAPTER 5 GRANTS AND COOPERATIVE AGREEMENTS 0501 OVERVIEW 050101. Purpose. This chapter prescribes the guidance to be followed by DoD Components to account for and control grants and cooperative agreements.
GOVERNMENT CONTRACT COSTS, PRICING & ACCOUNTING REPORT
Reprinted with permission from Government Contract Costs, Pricing & Accounting Report, Volume 10, Issue 2, K2015 Thomson Reuters. Further reproduction without permission of the publisher is prohibited.
DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule
DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group