1 Incurred Cost Submissions - It's Not Too Early! March 28, 2013 David Eck and Todd W. Bishop Dixon Hughes Goodman LLP

2 Agenda Treat Incurred Cost Submissions like a Project Why an Incurred Cost Submission? Current requirements for the Incurred Cost Submission DCAA s current checklist for ICS adequacy Some common mistakes causing ICS to be returned as inadequate Allowability Issues of the Day GAO s recent audit report outlining DCAA s significant backlog and DCAA s proposed action plan The Statute of Limitations and the potential impact of recent court decisions on older, unaudited submissions Penalties 2

3 Treat ICS Like a Project Establish a Project Plan for the preparation of your ICS Identification of Milestone projects (i.e., each ICS Schedule) Identification of key parts of each ICS Schedule and responsible parties Milestone dates (beginning and end) for reviewing and completing each project/schedule, and for final review and submission of the ICS Purpose of this webinar is to help you get started in preparing your ICS, or help in the review process Please contact us on detailed questions you may have on Schedules or any other aspects of the ICS 3

4 Why an Incurred Cost Submission? Federal Acquisition Regulation (FAR) (d), allowable cost and payment Annual rates and bases shall be established based on FAR 42.7 Shall submit an adequate Rate Proposal within 6 months of FYE Clause ((d)(2)(iii)) includes list of schedules to meet adequacy FAR 42.7, Indirect Cost Rates Provides CO with procedures to settle final indirect rates Prescribes final vouchering process (within 120 days of final rates) Includes Quick Close-out (FAR ) FAR , Payments under Time-and-Materials and Labor-Hour Contracts Labor is excluded from ICS requirement (Hours and Labor Rates) Defines material costs (travel, ODCs, materials, subcontracts, indirect) Pass through costs defined by costs accounting practices 4

5 Current Requirements Must be adequate based on DCAA checklist or civilian agency requirements!! Subcontractors where you are the Prime (Schedule J) Review each of your subcontract documents to ensure subcontract type Determine if your subs are required to submit ICS (Type and Materiality) Utilize Quick Close-out procedures (FAR ) Cost Type subcontracts ensure your SubK Admin P&Ps are adequate Subcontractors where you are the Sub Be prepared for Prime to request an ICS (T&M, Cost Type SubK) If immaterial, request Quick close-out process Ensure that supporting financial data and documentation is readily available Indirect Rate True-ups/Adjusting Vouchers See DCAA Adequacy Checklist for specific details 5

6 The Adequacy Checklist

7 Examples Proposal Adequacy Checklist Questions Ensure all claimed pools, bases, and rates are shown, including COM (Schedule A) Verify the contractor has included explanatory notes for any adjustments from G&A Expenses booked per G/L to claimed costs (Schedule B) Ensure a cost schedule is provided for each overhead pool (Schedule C) Ensure a cost schedule is provided for each intermediary cost pool (Schedule D) Ensure that an explanation of each allocation base is included (Schedule E)

8 Examples Proposal Adequacy Checklist Questions Ensure the contractor calculated a separate COM rate (if applicable) for each final indirect pool (Schedule F) Verify the contractor included explanatory notes for any adjustments from direct costs and indirect costs booked per G/L to claimed costs (Schedule G) Ensure all flexibly priced contracts and subcontracts, including commercial T&M, are listed by contract and subtotaled by contract type. FFP and other commercial contracts may be shown on one summary line each (Schedule H)

9 Examples Proposal Adequacy Checklist Questions Verify cost detail is in the same level used for billing costs, comparisons of billed and claimed costs have been made and that any overpayments have been identified and include explanations on notifications to the government (Schedule I) Ensure the auditable subcontract schedule includes all types of subcontracts (e.g., cost-type, T&M/LH, IDIQ, with a variable element and FPI) and intercompany costs claimed by the contractor on flexibly prices contracts and/or upper-tier subcontracts (Schedule J)

10 Examples Proposal Adequacy Checklist Questions Ensure T&M contract cost information is presented by cost element, with labor presented by labor category, showing contract labor rates, not actual labor rates (Schedule K) Verify reconciliation of total payroll per IRS Form 941 to labor costs distribution (Schedule L) Ensure completion of the list of decisions, agreements, approvals, and accounting/organization changes that may impact claimed costs negative responses are required (Schedule M)

11 Examples Proposal Adequacy Checklist Questions Verify that the Certificate of Final Indirect Costs is signed by an individual of the contractor s organization at a level no lower that a vice president or chief financial officer of the business segment of the contractor that submits the proposal (Schedule N) Verify the contractors has accurately identified physically complete contracts that are already closed or ready to close (Schedule O)

12 Common Mistakes Driving Inadequacies Reconciliation of Disclosure Statement, Accounting Description and Forward Pricing Rate Submission to ICS to verify all rates have been included (especially intermediate pools) and direct costs are at the right level Appropriate T&M/LH/LOE contracts have been included on Schedule H of costs by contract and subcontract Overpayments/underpayments identified on Schedule I on billed and claimed costs have not been identified, of explanations have not been provided for payment identified payment variances

13 Common Mistakes Driving Inadequacies All auditable subcontracts (e.g., T&M/LH and FPI) have not been identified on Schedule J and reconciled to purchasing department information Contract/subcontract briefs are not adequate (especially identification of contract billing instructions) On T&M/LH contracts, employees appear to be billed in labor categories where they do not have the appropriate qualifications per the contract, and explanations have not been provided (e.g., resumes have not been updated, CO provided a waiver, etc)

14 Common Mistakes Driving Inadequacies Appropriate reconciliations of claimed direct and indirect costs to the G/L have not been performed, or if performed, differences have not been adequately explained Adequate reconciliations of total payroll per IRS submissions to labor cost distributions have not been included in ICS DCAM only requires a reconciliation to payroll totals if labor system is adequate ICS does not include a Schedule of Cumulative Allowable Costs by Contract

15 Common Mistakes Driving Inadequacies For identified unallowable costs, ICS does not include any directly associated costs Certificate of Final Indirect Rates has not been signed by a business segment VP or higher

16 Allowability Issues of the Day Executive Compensation (FAR ) Compensation reasonable reviews conducted by DCAA, especially Mid-Atlantic Region (FAR ); DHG has issued 2 articles: DCAA Compensation Reviews Court Finds They are based on Fatal Statistical Flaws 2/7/12 DCAA Compensation Reviews Court Finds Again They are Flawed 9/25/12 Incomplete supporting data for purchases and subcontracts, especially cost/price analyses (FAR )

17 Allowability Issues of the Day Professional and Consultant Costs (FAR ) Travel Costs (FAR ) Unreasonable Health Benefits, with emphasis on ineligible dependents Unexplained reconciliation issues

18 Executive Compensation 2012 Authorization Act ( 803) extended reimbursement cap to all employees rather than top 5, starting January 1, 2012 Exemption to scientists/engineers when necessary to ensure DOD access to needed skills Executive caps 2011: $763,029 (applies to all future years until revised) 2010: $693, : $684, : $612,196 Applies to DOD, Coast Guard and NASA contracts

19 ICS Audit Backlog and Plan Forward December 2012 GAO Report (GAO ) Assessed DCAA plan for 25,000 audit Backlog (Dates back to 1996) Timely contract closeout dependent upon audits Plan Forward Developed sampling plan in Coordination with DCMA Will use , Contracting officer determination procedure, for ICS not audited

20 Contract Closeout Process Figure 1: DOD Contract Closeout Process Interactive Graphic To highlight firm-fixed-price closeout process, roll mouse over legend. Click on blue box to go to figure 2, DCAA s incurred cost audit process. Contract is physically complete/ goods and services received Contracting officer performs pre-closeout administrative tasks a Payment differences reconciled and excess funds deobligated Final payment made Contract closed when contracting officer signs contract completion statement Indirect cost rates settled with DCAA recommendations Indirect cost rates for all relevant years applied to contract Final invoice submitted and reviewed Firm-fixed-price Flexibly priced Source: GAO analysis of federal and DOD regulations and guidance. a Certain low-dollar, fixed-price contracts are closed using a more simplified process.

21 DCAA s Risk based Initiative Creating DCAA s Sampling Pool (Data from March 14, 2013 DCAA Presentation American Bar Associations-Section of Public Contract Law Conference)

22 How Does DCAA Develop Sampling Pool? Most Importantly, an Adequate ICS DCAA Determines Adequacy Using its Checklist (available on DCAA website) Total Value of Incurred Cost Proposal Four Different Ranges Over $250M Then Expect an Audit Most recent audited ICS questioned costs Classified as Significant Meet the Above Criteria, Then Join the Sampling Pool as Low Risk

23 How Many Proposals Will DCAA Sample? (Data from March 14, 2013 DCAA Presentation American Bar Associations-Section of Public Contract Law Conference)

24 DCAA Backlog Sampling Criteria Exceptions If $1M or less and submitted Prior to then Excluded from Sampling Pool 100% Greater Than $250M will be audited All Proposals Greater than $100M will be audited once every three years Four Different Ranges Low Risk Not Sampled, Contracting Officer Negotiation/Determination DCMA Class Deviation Memorandum through Sept. 2013

25 Contractor Actions Regarding Backlog Evaluate your most recent negotiated Audited Rates and Amounts Questioned Do you fit the Sampling Criteria? Communicate with cognizant CO s/aco s regarding this process Are CO/ACO s are even aware of the process? Recommend Quick Closeout Procedures (FAR ) as they might be applicable regardless of Sampling Criteria

26 Statute of Limitations on ICS DHG issued article on 3/19/2013 entitled When Does the Clock Start Ticking? In 1994, Federal Acquisition Streamlining Act (FASA) established a six-year Statute of Limitations for claims Recent Court Cases demonstrate the Statute of Limitations is being tested at phases throughout the contract life cycle Each of these cases deal with cost claims and some directly relate to ICS One testing ground still to be proven either way is the applicability of the Statute of Limitations to the eventual audits of the ICS

27 Statute of Limitations on ICS Some companies have taken bold steps on unaudited ICS over 6 years old, such as: Notify DCAA they have 30 days to take what ever action on the old ICS, and then records will be destroyed Refused DCAA access to records on ICS, saying the ICS are no longer subject to audit Consult with your legal and other advisors before taking bold steps

28 Penalties Expressly Unallowable Costs ACO Assessment (FAR ) Unallowable Costs Under $10K, Mandatory Waiver (Far , FAR ) Thomas Assoc., Inc., ASBCA No , May 17, 2011, 11-1 BCA 34,764

29 ICS Audit Process - Before and After BEFORE AFTER 29

30 Questions? 30

31 Contacts David Eck, CPA Director, Government Contracting 1410 Spring Hill Rd., Suite 500 Tysons, VA Todd Bishop Director, Government Contracting 1410 Spring Hill Rd., Suite 500 Tysons, VA

DEFENSE CONTRACT AUDIT AGENCY GUIDE FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL

DEFENSE CONTRACT AUDIT AGENCY GUIDE FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL Instructions: This form should be completed for each proposal submission and maintained in the permanent file. Adequacy reviews of contractor incurred cost proposals include verification for completeness

More information

DEFENSE CONTRACT AUDIT AGENCY CHECKLIST FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL

DEFENSE CONTRACT AUDIT AGENCY CHECKLIST FOR DETERMINING ADEQUACY OF CONTRACTOR INCURRED COST PROPOSAL Instructions: This form should be completed for each proposal submission and maintained in the permanent file. Adequacy reviews of contractor incurred cost proposals include an assessment for completeness

More information

FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013)

FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) FAR UPDATE 52.216-7, Allowable Cost and Payment (Jun 2013) "It's never too early to prepare for your incurred cost submission (A webinar sponsored by Pleasant Valley Business Solutions) 1 Objective Know

More information

Cracking the ICE: Ensuring a Compliant Incurred Cost Submission. Carlos Alvarado, VP, FP&A

Cracking the ICE: Ensuring a Compliant Incurred Cost Submission. Carlos Alvarado, VP, FP&A Cracking the ICE: Ensuring a Compliant Incurred Cost Submission Carlos Alvarado, VP, FP&A Agenda Introduction Incurred Cost Proposal ICE Model Leveraging Reporting Applications Inadequacy Letters Q&A 2

More information

Incurred Cost Submissions

Incurred Cost Submissions Incurred Cost Submissions Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily the

More information

Monitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations

Monitoring Subcontracts. The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Monitoring Subcontracts The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Subcontracts What should a contractor know about subcontracting:

More information

Incurred Cost Submissions. John S. Sroka, CPA Acquisition Cost/Price Analyst

Incurred Cost Submissions. John S. Sroka, CPA Acquisition Cost/Price Analyst Incurred Cost Submissions John S. Sroka, CPA Acquisition Cost/Price Analyst Incurred Cost Proposals Allowable cost and payment clause requires the submission (FAR 52.216-7) Requires a signed certification

More information

DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System

DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System Breakout Session A Alfred J. Massey, Western Region, Special Programs Manager,

More information

Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions

Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions Time s Up: DCAA s Renewed Focus on Incurred Cost Submissions Nicole Mitchell, CPA Donna Dominguez Aronson LLC May 1, 2013 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland

More information

Submitting a Quality Report. Presented by Laura Davis, Strategic Consulting Solutions, Inc.

Submitting a Quality Report. Presented by Laura Davis, Strategic Consulting Solutions, Inc. Submitting a Quality Report Presented by Laura Davis, Strategic Consulting Solutions, Inc. Started in 2004 Based in Oak Ridge, TN Offices in Charleston, SC & Fayetteville, NC Focus on Government Contracting

More information

July 6, 2015 11(1) CHAPTER 11

July 6, 2015 11(1) CHAPTER 11 July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---

More information

If you require a copy of this presentation, please provide your contact information to either Christopher Weir or Bob Eyer and we will be sure to

If you require a copy of this presentation, please provide your contact information to either Christopher Weir or Bob Eyer and we will be sure to How do I survive an audit of an incurred cost submission? If you require a copy of this presentation, please provide your contact information to either Christopher Weir or Bob Eyer and we will be sure

More information

As the Defense Contract Audit Agency slowly

As the Defense Contract Audit Agency slowly Reprinted from Government Contract Costs, Pricing & Accounting Report, with permission of Thomson Reuters. Further use without the permission of West is prohibited. For further information about this publication

More information

Accounting System Requirements

Accounting System Requirements Accounting System Requirements Further information is available in the Information for Contractors Manual under Enclosure 2 The views expressed in this presentation are DCAA's views and not necessarily

More information

DCAA Audit R 4 Rights to Records, Requirements & Remedies

DCAA Audit R 4 Rights to Records, Requirements & Remedies San Diego Chapters Present DCAA Audit R 4 Rights to Records, Requirements & Remedies A Seminar with Panel Discussion and Audience Participation February 18, 2009 This Morning s Agenda 8:30 Introduction

More information

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group

More information

Pre-Award Accounting Systems

Pre-Award Accounting Systems Pre-Award Accounting Systems 2013 National SBIR Conference Christopher Andrezze, CPA Special Assistant to the Deputy Director May 16, 2013 The views expressed in this presentation are DCAA's views and

More information

The Cost Accounting Standards and Consequences of Noncompliance

The Cost Accounting Standards and Consequences of Noncompliance The Cost Accounting Standards and Consequences of Noncompliance Breakout Session E05 Greg Bingham, Vice President, The Kenrich Group LLC Mike LaCorte, Principal, The Kenrich Group LLC Tuesday, December

More information

The Changing Government Contractor Environment

The Changing Government Contractor Environment The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.

More information

DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219

DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 DEFENSE CONTRACT AUDIT AGENCY DEPARTMENT OF DEFENSE 8725 JOHN J. KINGMAN ROAD, SUITE 2135 FORT BELVOIR, VA 22060-6219 IN REPLY REFER TO PSP 730.8.B.1/2010-003 February 18, 2011 11-PSP-003(R) MEMORANDUM

More information

DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence

DCAA Our Role. Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE. Page 1. DCAA 1965-2015: Celebrating 50 Years of Excellence DCAA Our Role Laura Cloyd-Hall, CPA, MBA John D. Mollohan II, CPA, CFE DCAA 1965-2015: Celebrating 50 Years of Excellence Page 1 Topics About DCAA Typical DCAA Audits for Small Businesses Basic Roles of

More information

Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP)

Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP) Government Contract Accounting Are You DCAA Compliant? Procurement Technical Assistance Program (PTAP) NH Presentation October 20, 2010 Presented by: Fred Kline, MBA, CPA Tom Martin MBA, CPA Malcolm Young,

More information

Current Initiatives May 2015

Current Initiatives May 2015 DHG 20 th Annual Government Contracting Update Current Initiatives May 2015 Mr. Ken Saccoccia Deputy Director Page 1 One Agency One Mission DCAA Overview Priorities and Better Buying Power Small Business

More information

INCURRED COST ELECTRONICALLY (ICE) MANUAL

INCURRED COST ELECTRONICALLY (ICE) MANUAL INCURRED COST ELECTRONICALLY (ICE) MANUAL TABLE OF CONTENTS VERSION 2.0.1c A. INTRODUCTION 1. Purpose 2. Benefits of Using ICE 3. Hardware/Software Requirements B. ICE SOFTWARE APPLICATIONS PACKAGE 1.

More information

Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012

Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012 1 Panelists Robert A. ( Rob ) Burton, Partner, Venable LLP A 30-year veteran

More information

CHAPTER 8. Table of Contents

CHAPTER 8. Table of Contents July 29, 2015 8(1) Paragraph CHAPTER 8 Table of Contents 8-000 Cost Accounting Standards Page 8-001 Scope of Chapter... 801 8-100 Section 1 --- Overview - Cost Accounting Standards Board (CASB) Rules and

More information

INSTRUCTION NUMBER 7640.02 August 22, 2008

INSTRUCTION NUMBER 7640.02 August 22, 2008 Department of Defense INSTRUCTION NUMBER 7640.02 August 22, 2008 IG DoD SUBJECT: Policy for Follow-up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This Instruction: a. Reissues DoD

More information

January 2004 6(1) CHAPTER 6. Table of Contents

January 2004 6(1) CHAPTER 6. Table of Contents January 2004 6(1) Paragraph CHAPTER 6 Table of Contents 6-000 Incurred Costs Audit Procedures Page 6-001 Scope of Chapter... 601 6-100 Section 1 --- Introduction to Incurred Cost Audit Objectives 6-101

More information

What Exactly is an Acceptable Accounting System?

What Exactly is an Acceptable Accounting System? What Exactly is an Acceptable Accounting System? Kristen Soles, CPA Member Stephanie Widzinski, CPA Senior Manager September 27, 2012 Agenda Review DFARS Business System Rule What Agency is Responsible

More information

Basic Financial Requirements for Government Contracting

Basic Financial Requirements for Government Contracting Basic Financial Requirements for Government Contracting 2014 National SBIR/STTR Conference The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations

More information

Business Systems: Update on Proposed Rules

Business Systems: Update on Proposed Rules Business Systems: Update on Proposed Rules Presented By: Mark Burroughs, Partner Topics Review of Business System requirements Observations on areas of focus by the government Enforcement of significant

More information

NCMA MEETING PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011

NCMA MEETING PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011 NCMA MEETING 1 PREPARING FOR A DCAA PRICE PROPOSAL AUDIT JUNE 8, 2011 Denise M. Hunt DCAA LM Mt. Laurel Resident Office Forward Pricing Technical Specialist DCAA OVERVIEW AND PRICE PROPOSAL AUDIT PROCESS

More information

Department of Defense INSTRUCTION

Department of Defense INSTRUCTION Department of Defense INSTRUCTION NUMBER 7640.02 April 15, 2015 IG DoD SUBJECT: Policy for Follow-Up on Contract Audit Reports References: See Enclosure 1 1. PURPOSE. This instruction reissues DoD Instruction

More information

DOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks

DOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks DOD's Business Systems Rule: The Challenge Measuring Government Contractor Compliance Against Subjective Criteria and Perceived Risks Breakout Session #: B04 Presented by: Michael E. Steen, CPA Date: July

More information

Review of Consultant/Professional Services Cost Accounts

Review of Consultant/Professional Services Cost Accounts Review of Consultant/Professional Services Cost Accounts 1 Table of Contents Risk Assessment Research and Planning Entrance Conference Preliminary Analytical Procedures Results from Preliminary Analytical

More information

DCAA Guidelines. How the SBIR firm can work effectively with the Defense Contract Audit Agency

DCAA Guidelines. How the SBIR firm can work effectively with the Defense Contract Audit Agency DCAA Guidelines How the SBIR firm can work effectively with the Defense Contract Audit Agency Today s Presenters OUTLINE Presenter Introduction DCAA & DCMA DCAA Overview Types of DCAA Audits What it takes

More information

Presenting the Numbers: Accounting Systems for Government Contractors

Presenting the Numbers: Accounting Systems for Government Contractors Presenting the Numbers: Accounting Systems for Government Contractors William D. Craven, CPA Senior Cost/Price Analyst CH2M HILL Plateau Remediation Company William D. Craven, CPA, CMA, CIA Cost/Price

More information

Audit Expectations for Small Businesses

Audit Expectations for Small Businesses Audit Expectations for Small Businesses DEFENSE CONTRACT CONSULTING Joseph A. Dalton, CGFM/CFE/CAP Over 31 Years -Supervisory/Auditor Service- DCAA Retired Captain, U. S. Naval Reserve 1996 BUSINESS NO.

More information

Certificate of Accounting, Billing and Property System Adequacy

Certificate of Accounting, Billing and Property System Adequacy Certificate of Accounting, Billing and Property System Adequacy This certifies that, to the best of my knowledge and belief, Contractor s Accounting, Billing and/or Property System and related internal

More information

September 16, 2015 6(1) CHAPTER 6

September 16, 2015 6(1) CHAPTER 6 September 16, 2015 6(1) CHAPTER 6 Paragraph Table of Contents 6-000 Incurred Costs Audit Procedures Page 6-001 Scope of Chapter... 601 6-100 Section 1 --- Introduction to Incurred Cost Audit Objectives

More information

Managing Cost Type Contracts

Managing Cost Type Contracts Managing Cost Type Contracts October 9, 2013 By: Tom Marcinko Donna Dominguez 2013 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200 P 301.231.7630 F www.aronsonllc.com

More information

CHAPTER 6. 6-000 Incurred Cost Proposals

CHAPTER 6. 6-000 Incurred Cost Proposals January 2005 6-1 6-101 CHAPTER 6 6-000 Incurred Cost Proposals 6-101 Introduction a. This chapter covers submission of incurred cost proposals. These would include the various indirect overhead and General

More information

DCAA New Tactics in Obtaining Contractor Internal audit reports

DCAA New Tactics in Obtaining Contractor Internal audit reports DCAA New Tactics in Obtaining Contractor Internal audit reports By Todd Bishop and David Eck, CPA In August 2012, the Defense Contract Audit Agency (DCAA) issued updates to its policy guidance and the

More information

Accounting System Requirements

Accounting System Requirements Basic Financial Requirements for Government Contracting The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Accounting System Requirements

More information

31402 Federal Register / Vol. 76, No. 104 / Tuesday, May 31, 2011 / Rules and Regulations

31402 Federal Register / Vol. 76, No. 104 / Tuesday, May 31, 2011 / Rules and Regulations 31402 Federal Register / Vol. 76, No. 104 / Tuesday, May 31, 2011 / Rules and Regulations (iv) Best management practices for energy-efficient management of servers and Federal data centers. PART 52 SOLICITATION

More information

Preaward and Post Award Accounting System Audits. November 17, 2011 Pikes Peak NCMA Roland Wick

Preaward and Post Award Accounting System Audits. November 17, 2011 Pikes Peak NCMA Roland Wick Preaward and Post Award Accounting System Audits November 17, 2011 Pikes Peak NCMA Roland Wick OVERVIEW This presentation will provide: 1. The basic criteria for the Preaward and Post Award accounting

More information

Post Award Accounting System Audit at Nonmajor Contractors

Post Award Accounting System Audit at Nonmajor Contractors Activity Code 17741 Version 3.1, dated November 2015 B-01 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors Audit Specific Independence Determination Members of the audit

More information

Understanding the Rate Cycle. Presented By: Rich Wilkinson, VP Client Services

Understanding the Rate Cycle. Presented By: Rich Wilkinson, VP Client Services Understanding the Rate Cycle Presented By: Rich Wilkinson, VP Client Services The Rate Cycle and Related Trivia Basics of Indirect Rates The Traditional Structures Developing Rates Prospective Rate Submissions

More information

How to Survive a DCAA Audit

How to Survive a DCAA Audit How to Survive a DCAA Audit www.paulgunn.com 1 How to Survive a DCAA Audit - Overview Areas of interest and expectations of a typical audit: 1. Introduction o 2. The DCAA and Types of audits 3. Preparing

More information

Objectives of the Incurred Cost Audit

Objectives of the Incurred Cost Audit 36 Contract Management March 2011 Government contractors who incur costs on behalf of the government via contracts, grants, loans, or other contract vehicles are subject to incurred cost audits by the

More information

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012

Federal Regulatory Compliance Best Practices Washington Technology Webcast. September 27, 2012 Federal Regulatory Compliance Best Practices Washington Technology Webcast September 27, 2012 Agenda Topic Minutes Regulatory compliance overview 5 Major areas of financial compliance risk 15 Best practices

More information

Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012

Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012 Is Your Accounting System Making the Grade? Attributes of an Acceptable Accounting System April 26, 2012 2012 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200

More information

Uncompensated Overtime

Uncompensated Overtime Uncompensated Overtime 1 Table of Contents Risk Assessment Research and Planning Risk Assessment Labor System Entrance Conference Preliminary Analytical Procedures Audit Team Brainstorming for Fraud Risk

More information

Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013

Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013 Report No. DODIG-2014-109 Inspector General U.S. Department of Defense SEPTEMBER 8, 2014 Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013 INTEGRITY EFFICIENCY ACCOUNTABILITY

More information

Surviving a DCAA. Audit. Nicole Mitchell, CPA Director Aronson LLC. March 29, 2011

Surviving a DCAA. Audit. Nicole Mitchell, CPA Director Aronson LLC. March 29, 2011 Surviving a DCAA Incurred Cost Submission Audit Nicole Mitchell, CPA Director Aronson LLC March 29, 2011 2011 All Rights Reserved 805 King Farm Boulevard Suite 300 Rockville, Maryland 20850 301.231.6200

More information

Audit Issues In Government Subcontracting

Audit Issues In Government Subcontracting Audit Issues In Government Subcontracting Breakout Session E Brent A. Calhoon, CPA, Partner, Baker Tilly Virchow Krause, LLP Janie L. Maddox, CPCM, Fellow, Thursday, March 27 1:30pm 2:45pm Agenda 1. Introductions

More information

Government Contractor Business Systems and Overview of System Assessments

Government Contractor Business Systems and Overview of System Assessments Government Contractor Business Systems and Overview of System Assessments Agenda Overview of business systems rules and environment today 3 rd party assessments Practical solutions Contractor perspective

More information

CAS. Combined Air Support Cost Accounting Standards. Cost Impact Statements

CAS. Combined Air Support Cost Accounting Standards. Cost Impact Statements CAS Combined Air Support Cost Accounting Standards Cost Impact Statements Cost Impact Statements Presenter: Anthony J. Nicolella References 48 CFR 9903 CON 252 Fundamentals of CAS FAR Parts 30, 31 and

More information

WHAT MAKES AN ACCOUNTING SYSTEM COMPLIANT

WHAT MAKES AN ACCOUNTING SYSTEM COMPLIANT WHAT MAKES AN ACCOUNTING SYSTEM COMPLIANT Presented by: Laura Davis OVERVIEW Why Do I Need a Compliant Accounting System Auditor s Judgment Definitions Key Components Audits How to be prepared for an audit

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing

More information

GOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND

GOVERNMENT CONTRACTING MICROSOFT DYNAMICS AX AND GOVERNMENT CONTRACTING AND MICROSOFT DYNAMICS AX White paper on Government Contracting requirements and considerations in planning for a Dynamics AX implementation. 1 Government Contracting and Microsoft

More information

CHAPTER 2. 2-000 Preaward Surveys of Prospective Contractor Accounting Systems

CHAPTER 2. 2-000 Preaward Surveys of Prospective Contractor Accounting Systems CHAPTER 2 2-000 Preaward Surveys of Prospective Contractor Accounting Systems 2-101 Preaward Survey Overview A preaward survey is an evaluation, usually made by the cognizant contract administration office,

More information

U.S.Government. Contracts. Understanding and. Managing Receivables on U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A

U.S.Government. Contracts. Understanding and. Managing Receivables on U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A U$A Understanding and Managing Receivables on U.S.Government Contracts B Y R OGER C. GRAHAM, JR., CPA, PH.D., AND G ERALD R. CHROBUCK, CPA MANAGEMENT accounting quarterly 3 IT IS COMMON FOR GOVERNMENT CONTRACTORS

More information

Ensure Compliance For Government Contractors

Ensure Compliance For Government Contractors Ensure Compliance For Government Contractors Topics Overview NeoSystems Corp 2009-2012 ENSURE COMPLIANCE FOR GOVERNMENT CONTRACTORS TABLE OF CONTENTS V15C Learning Objectives... 4 Introduction... 5 Government

More information

Are You Looking to Sell Your Products & Services to the US Government? Overview

Are You Looking to Sell Your Products & Services to the US Government? Overview Are You Looking to Sell Your Products & Services to the US Government? What You Need to Know About Accounting, Compliance, and Reporting! 1 FICPA Overview The US Government is the largest consumer of goods

More information

DCAA and the Small Business Innovative Research (SBIR) Program

DCAA and the Small Business Innovative Research (SBIR) Program Defense Contract Audit Agency (DCAA) DCAA and the Small Business Innovative Research (SBIR) Program Judice Smith and Chang Ford DCAA/Financial Liaison Advisors NAVAIR 2010 Small Business Aviation Technology

More information

DEFENSE CONTRACT AUDIT AGENCY

DEFENSE CONTRACT AUDIT AGENCY DEFENSE CONTRACT AUDIT AGENCY Fundamental Building Blocks for an Acceptable Accounting System Presented by Sue Reynaga DCAA Branch Manager San Diego Branch Office August 24, 2011 Report Documentation Page

More information

Time-and-Materials and Labor-Hour Contracts The New Policies

Time-and-Materials and Labor-Hour Contracts The New Policies Time-and-Materials and Labor-Hour Contracts The New Policies Overview: Time-and-materials and labor-hour (T&M/LH) contracts are the least preferred contract types, but they may play an important role in

More information

DCAA Current Trends and Practices. SCS GovCon Seminar October 24, 2013

DCAA Current Trends and Practices. SCS GovCon Seminar October 24, 2013 DCAA Current Trends and Practices SCS GovCon Seminar October 24, 2013 What s Hot 2 Incurred Cost Submissions Requirements Common Deficiencies Closer Cost Scrutiny Travel Costs Restructuring Costs Consultant

More information

How to Survive a DCAA Pre-Award Audit

How to Survive a DCAA Pre-Award Audit How to Survive a DCAA Pre-Award Audit February 27, 13 Presented by: Paul H. Calabrese Senior Manager 301-214-4137 pcalab@rubino.com Bio http://www.rubino.com/company/staff/11- paul_h_calabrese/view LinkedIn

More information

DEFENSE CONTRACT AUDIT AGENCY AUDIT REPORT NO. 3311-2002K11010001

DEFENSE CONTRACT AUDIT AGENCY AUDIT REPORT NO. 3311-2002K11010001 DEFENSE CONTRACT AUDIT AGENCY AUDIT REPORT NO. 3311-2002K11010001 PREPARED FOR: Corporate Administrative Contracting Officer (CACO) ATTN: DCMDW-GEOSB (Ms. Catharina N. Ignacio) Defense Contract Management

More information

DCAA Compliant Accounting Systems

DCAA Compliant Accounting Systems DCAA Compliant Accounting Systems State Designated as Florida s Principal Provider of Business Assistance [ 288.001, Fla. Stat.] Helping Businesses Grow & Succeed About Your Presenter Jenny W. Clark With

More information

The Devil is in the Details Compliance with the Business Systems Rule

The Devil is in the Details Compliance with the Business Systems Rule Metropolitan Area Corporate Counsel Association WMACCA Conference on Ethics and Compliance for Government Contractors The Devil is in the Details Compliance with the Business Systems Rule April 1, 2014

More information

Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies

Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies Inspector General U.S. Department of Defense Report No. DODIG-2016-001 OCTOBER 1, 2015 Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies INTEGRITY

More information

Thank You for Joining Us, The Webinar Will Begin Shortly. While you are waiting please check out the Upcoming Webinars on www.giveme5.com.

Thank You for Joining Us, The Webinar Will Begin Shortly. While you are waiting please check out the Upcoming Webinars on www.giveme5.com. Thank You for Joining Us, The Webinar Will Begin Shortly. While you are waiting please check out the Upcoming Webinars on www.giveme5.com. Before we begin just a few notes: During the presentation lines

More information

UNIT 34: COST ACCOUNTING STANDARDS

UNIT 34: COST ACCOUNTING STANDARDS UNIT CERTIFICATION Statement of Completion has satisfactorily completed training in the duty of this Unit under the conditions described below and in accordance with the overall standard(s) for this Unit.

More information

Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63)

Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Defense Contract Audit Agency: What Do They Do and How Does It Affect ME as a Resource Manager? (Breakout #63) Pat Fitzgerald Director Defense Contract Audit Agency The views expressed in this presentation

More information

Testimony. Patrick J. Fitzgerald Director, Defense Contract Audit Agency. before the. Commission on Wartime Contracting In Iraq and Afghanistan

Testimony. Patrick J. Fitzgerald Director, Defense Contract Audit Agency. before the. Commission on Wartime Contracting In Iraq and Afghanistan Testimony of Patrick J. Fitzgerald Director, Defense Contract Audit Agency before the Commission on Wartime Contracting In Iraq and Afghanistan July 26, 2010 Chairman Thibault, Chairman Shays, and members

More information

CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE

CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE By Eric Sobota, Kelley Doran and Barron Avery Contractors that work for the Department of Energy (DOE) under agreements

More information

NASA Office of Inspector General

NASA Office of Inspector General NASA Office of Inspector General National Aeronautics and Space Administration Office of Audits COSTS INCURRED ON NASA S COST-TYPE CONTRACTS December 17, 2014 Report No. IG-15-010 Office of Inspector General

More information

Understanding Unallowable Cost so You Don t Pay the Price

Understanding Unallowable Cost so You Don t Pay the Price Understanding Unallowable Cost so You Don t Pay the Price Identification and Definition of Unallowable Costs per CAS and FAR An unallowable cost is one that: Under the provisions of any pertinent law,

More information

Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers

Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers Curtis Matthews, Managing Partner Government Accounting, Estimating, and Billing Systems: Pitfalls and Answers Findley Gillespie, Senior Manager May 18, 2011 1 The material appearing in this presentation

More information

Post Award Accounting System Audit at Nonmajor Contractors

Post Award Accounting System Audit at Nonmajor Contractors Activity Code 17740 B-1 Planning Considerations Post Award Accounting System Audit at Nonmajor Contractors To provide general guidance for the audit of the adequacy and suitability of nonmajor contractor

More information

Types of Contracts. A quick walk through FAR Part 16

Types of Contracts. A quick walk through FAR Part 16 Types of Contracts A quick walk through FAR Part 16 Contract Types Contract types vary according to -- (1) The degree and timing of the responsibility assumed by the contractor for the costs of performance;

More information

Business Systems Compliance Guide

Business Systems Compliance Guide McKenna Government Contracts, continuing excellence at Dentons Government Contractor Business Systems Compliance Guide 2nd Edition Thomas A. Lemmer Steven M. Masiello Michael J. McGuinn Kelly P. Garehime

More information

DCAA Contract Audits: Current Trends and Issues

DCAA Contract Audits: Current Trends and Issues DCAA Contract Audits: Current Trends and Issues Presented to: NCMA Huntsille, AL Chapter August 25, 2011 Darryl L. Walker, CPA Technical Director Beason & Nalley, Inc. Copyright 2011 Beason & Nalley, Inc.

More information

DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member

DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member DCAA / DCMA: Progress or Status Quo? Presented By: Christine Williamson, CPA, Member Kristen Soles, CPA, Member Agenda State of the Agencies DCAA/DCMA What does GAO have to say? What does DOD IG have to

More information

Introduction and DCAA Overview

Introduction and DCAA Overview Introduction and DCAA Overview Industry Engagement Session 10/29/2015 The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations DCAA 1965-2015:

More information

INSPECTOR GENERAL UNITED STATES POSTAL SERVICE

INSPECTOR GENERAL UNITED STATES POSTAL SERVICE OFFICE OF INSPECTOR GENERAL UNITED STATES POSTAL SERVICE Trends and Systemic Issues in Defense Contract Audit Agency Audit Work for Fiscal Years 2009-2012 Management Advisory Report Report Number March

More information

Provisional Billing Rates. Beth Citeroni Acquisition Cost/Price Analyst

Provisional Billing Rates. Beth Citeroni Acquisition Cost/Price Analyst Provisional Billing Rates Beth Citeroni Acquisition Cost/Price Analyst Definition FAR 42.701 Provisional rate or billing rate is an established temporary indirect rate applicable to a specified period

More information

Master Document Audit Program. Version No. 2.9, updated November 2015 B-1 Planning Considerations

Master Document Audit Program. Version No. 2.9, updated November 2015 B-1 Planning Considerations Activity Code B-1 Planning Considerations Cost Realism Audit Specific Independence Determination Members of the audit team and internal specialists consulting on this audit must complete the Audit Specific

More information

MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security

MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security MEMORANDUM OF UNDERSTANDING Between Defense Contract Audit Agency and Department of Homeland Security 1. PURPOSE This memorandum sets forth an understanding of contract audit coverage and related audit

More information

Master Document Audit Program. Version 4.14, dated November 2015 B-1 Planning Considerations

Master Document Audit Program. Version 4.14, dated November 2015 B-1 Planning Considerations Activity Code 17200 B-1 Planning Considerations Claim Audit, Other Audit Specific Independence Determination Members of the audit team and internal specialists consulting on this audit must complete the

More information

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers

STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers STOC II Draft RFP (W900KK-08-R-0001) Questions & Answers Answers to questions submitted, but not included in this set of Q&As,will be provided in a subsequent posting of Q&As in the near future. As the

More information

Public Vouchers. Further information is available in the Information for Contractors Manual under Enclosure 5

Public Vouchers. Further information is available in the Information for Contractors Manual under Enclosure 5 Public Vouchers Further information is available in the Information for Contractors Manual under Enclosure 5 The views expressed in this presentation are DCAA's views and not necessarily the views of other

More information

Property Management System (GPMS)

Property Management System (GPMS) Property Management System (GPMS) Business System Overview Sep 20, 2013 Marcia D. Whitson, CPPM, CF NPMA National President DFARS 252.242-7005 Contractor Business Systems DoD Business Systems Rule - Clarifies

More information

AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING

AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING AGENDA FOR LUNCH SEMINAR WITH FMI AUGUST 28, 2008 12:30 PM INTRODUCTION TO GOVERNMENT CONTRACTING 1. NICRA - What is a NICRA? - Who has a NICRA? - Do I need a NICRA? - How do I get a NICRA? 2. INDIRECT

More information

CONTRACTOR INVOICE REVIEW AND APPROVAL PROCESS

CONTRACTOR INVOICE REVIEW AND APPROVAL PROCESS SECTION XVI. CONTRACTOR INVOICE REVIEW AND APPROVAL PROCESS For purposes of this Guidebook, the terms "voucher" and "invoice" are used interchangeably. A. PURPOSE The purpose of this document is to provide

More information

GOVERNMENT CONTRACT COSTS, PRICING & ACCOUNTING REPORT

GOVERNMENT CONTRACT COSTS, PRICING & ACCOUNTING REPORT Reprinted with permission from Government Contract Costs, Pricing & Accounting Report, Volume 10, Issue 2, K2015 Thomson Reuters. Further reproduction without permission of the publisher is prohibited.

More information

Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update

Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update Government Contracting in 2015: Balancing Risks to Reap Rewards - Compliance Update Baker Tilly Beers & Cutler, PLLC, is a wholly-owned subsidiary of Baker Tilly Virchow Krause, LLP. 2015 Baker Tilly Beers

More information