Contents General Requirements Location Size Inlet and Outlet Piping Protection Security Electrical Automatic Meter Reading (AMR)
|
|
|
- Imogen Booker
- 10 years ago
- Views:
Transcription
1
2 The information in this booklet is provided to assist in planning your meter area requirements. Actual field conditions may result in additional requirements. For more information, please contact the ATCO Gas office in your area. Contents General Requirements 1 Location 1 Size 1 Inlet and Outlet Piping 4 Protection 4 Security 5 Electrical 5 Automatic Meter Reading (AMR) 5 For Additional Information 6
3 General Requirements Legal description and service address of the property/building to be serviced is required. An adequate meter area must be provided at no cost to ATCO Gas to install metering and regulating equipment, regardless of whether it is a new facility or an expansion to an existing facility. A meter area is the space set aside outside the building for metering and regulating equipment. The meter area must not be used for any other purpose. The meter area must be accessible at all times to authorized ATCO Gas personnel. The installation of the meter, regulator and house line must conform to the Alberta Building Code, CAN/CSA-Z662, CAN/CGA-B149.1, the Alberta Safety Codes Act and the Alberta Gas Code Regulations. Prior approval must be obtained from ATCO Gas when a Header Set is required. All meters, regulators, reliefs, bypasses, pipe and fittings installed by ATCO Gas remains the property of ATCO Gas. Location Meter must be outside The meter area must be adjacent to the building within the customer s property. Clear, unobstructed access is required to the meter area at all times. Location of the meter area at final grade is critical. Suitable provision, if required, must be made by the Mechanical Contractor to extend the regulator and/or relief vent lines to meet the specifications in the CAN/CSA B149.1,Natural Gas and Propane Installation Code. Size The minimum size of the meter area will be determined by ATCO Gas for each installation, based on gas load, inlet and outlet pressure, regulation equipment, and the number and type of meters. Special applications require consultation with ATCO Gas prior to continuing with the installation. Using the meter size for the appropriate flow rate, the required meter area size can be determined. 1
4 Meter Area Size (Elevated Pressure) Total Load Distance Between Service Riser and House Line K Unobstructed Area Required Length G Width H Width of Space to Right of House Line /Left of Riser J House Line Distance from Finished Wall I Height of House Line from Finished Grade 28 m³/h (1,000 cfh) ( m) ( m) (0.9 m) 12 (0.3 m) 6 (0.15 m) m³/h (1,001-5,000 cfh) 36 - ( m) (2.2 m) (0.9 m) m³/h (5,001-8,000 cfh) ( m) ( m) (1.5 m) Requires site visit by ATCO Gas m³/h (8,001-23,000 cfh) ( m) ( m) (1.5 m) 24 (0.6 m) Requires site visit by ATCO Gas Meter Area Size (Low Pressure) Total Load Distance Between Service Riser and House Line K Unobstructed Area Required Length Width G H Width of Space to Right of House Line/Left of Riser J House Line Distance from Finished Wall I Height of House Line from Finished Grade 0-13 m³/h (0-450 cfh) 16 (0.4 m) (1.0 m) (0.6 m) 12 (0.3 m) 4 (0.1 m) (1.2m) m³/h ( cfh) (1.1 m) (0.6 m) 12 (0.3 m) 4 (0.1 m) (1.2m) m³/h (751-1,000 cfh) 24 (0.6 m) 36 (0.9 m) 12 (0.3 m) 6 (0.15 m) m³/h (1, cfh) (2.0 m) (0.9 m) 16 (0.4 m) m³/h (5001-8,000 cfh) 84 (2.1 m) (3.4 m) (1.5 m) Requires site visit by ATCO Gas m³/h (8,001-23,000 cfh) 108 (2.7 m) 1 60 (3.7 m) (1.5 m) 24 (0.6 m) Requires site visit by ATCO Gas 2
5 Outside Set Area INSIDE BUILDING WALL HOUSE LINE OUTSIDE SERVICE RISER I J K J H G METER AREA REQUIRED The above meter space requirements are for one meter and one outlet pressure per location. Special applications including loads over 651 m³/h (23,000 cfh) or twin regulator runs require a mandatory site visit for specific spacing requirements. A concrete pad is required before the installation of any meter with a minimum capacity greater than 28 m³/h (1,000 cfh) or if any part of the meter set has to rest on the ground. The concrete pad must be finished, ground level and tied into the building foundation. Using the minimum space requirements for the meter set, required size of the concrete pad can be determined. 3
6 Meter Site Specifications Total Load 0-13 m³/h (0-450 cfh) m³/h (451-1,000 cfh) m³/h (1,001-5,000 cfh) m³/h (5,001-23,000 cfh) Riser & Meter Protection Unobstructed Distance from Wall 24 (0.6 m) 36 (0.9 m) 36 (0.9 m) 60 (1.5 m) Concrete Pad Required Roof Chain Link Fence Required No No No No No No Yes No May be required Yes May be required May be required Inlet and Outlet Piping The customer must indicate the desired meter location on a plan to be submitted to ATCO Gas. The final location of inlet and minimum outlet pipe sizes will be determined by ATCO Gas. The inlet piping must enter directly into the meter area on special applications. If the house line is larger than two inches, install a two-inch threaded-one end (TOE) fitting to allow for the connection of regulating and metering equipment. Protection ATCO Gas metering and regulating equipment must be protected from potential physical damage. Where there is potential for vehicular damage (including forklifts and other moveable equipment), the customer must provide a vehicle barrier or fencing. The meter area must be in a location that is free from falling ice or snow hazards. Snow must not be piled directly in front of or on the meter set. ATCO Gas will provide protection for piping, meter and regulating equipment where applicable. When a meter is located on a building, where the exterior is stucco or corrugated metal siding, ATCO Gas requires backing support on the inside wall (i.e. plywood) to attach riser brackets to keep single and multi-header meters secure. 4
7 Security ATCO Gas reserves the right to require a security enclosure to prevent tampering and vandalism. Enclosures must be closed and locked at all times when not occupied by ATCO Gas employees. The gates of these enclosures need to be six inches (0.15 m) above the finished grade for access during winter months. Enclosures may be locked by means of a conventional lock set, provided by ATCO Gas to ensure that employees can obtain access at all times to the area. Warning signs provided by ATCO Gas shall be attached to the outside of the enclosure. Electrical There must be a minimum of three feet (0.9 m) separation between any part of the gas meter/regulation installation and any sources of ignition (i.e. open flames, electrical panels, switches, meters, etc.). Automated Meter Reading (AMR) ATCO Gas may supply and install an Automated Meter Reading (AMR) device for your natural gas meter. This is simply a modem which may connect to the telephone system. A telephone line may be required for AMR purposes. A common analog loop start extension from an existing in house line is adequate; a dedicated service is not required. The telephone line must terminate as close as possible to the meter, but no closer than three feet (0.9 m) from the meter set equipment and piping. The cable is to be encased in weatherproof mechanical protection. It is recommended, where possible, that the cable be routed from the main phone panel in half-inch conduit. After telephone service has been provided to the meter area, ATCO Gas may install and commission the AMR device. 5
8 The information in this booklet is provided to assist in planning your meter area requirements. Actual field conditions may result in additional requirements. For more information, please contact the ATCO Gas office in your area. Notes 6
9 Notes 7
Gas Meter Clearances and Service Installation Requirements
March 2015 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE s Customer Construction Services 1-888-321-7779 or visit PSE.com/CustomerConstruction
Element D Services Plumbing
Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.
Gas Meter Clearances and Service Installation Requirements
March 2016 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE's Customer Construction Services 1 888 321 7779 or visit PSE.com/CustomerConstruction
Electric Service Conversion Overhead-to-Underground. Minnesota
Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections Minnesota Process Please fill out these forms and complete this checklist to begin your application process: 1) Overhead-to-Underground
Current as of 11/10/08 1 of 1
BEST PRACTICES STANDARDS FOR SCHOOLS UNDER CONSTRUCTION OR BEING PLANNED FOR CONSTRUCTION I. Site Layout A. School buildings shall be provided with a securable perimeter. A securable perimeter means that
The City of Basehor, Kansas
The City of Basehor, Kansas Residential and Miscellaneous Permits This list provides general information regarding permit requirements for various residential construction and maintenance activities. The
2. What building projects are exempted? (permit not required)
BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and
Industrial Suburban District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations
16.20.110 - Industrial Suburban District ( IS ) Figure REFERENCE Typical Buildings in the IS District Figure REFERENCE Site Plan of a typical development in the IS District Sections: 16.20.110.1 Composition
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE
BUILDERS AND CONTRACTORS GUIDE FOR ELECTRIC SERVICE Toll Free Telephone Numbers Residential Services 800.454.3853 Commercial Services 800.653.5307 Utility Locating Company N.C. 800.632.4949 S.C. 888.721.7877
IRRIGATION PUMPING Table of Contents - Section 900
IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS
2010 Residential Water Heater Replacement Check List
2010 Residential Water Heater Replacement Check List The intent of this check list is to provide installers a general reference for the enforcement of code requirements in the Greater San Diego Area. This
CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION
CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR
SWIMMING POOL, SPA, & HOT TUB GUIDELINES
SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015
Residential Building Permits Information
City of Bonham Building Department 514 Chestnut St. Bonham, Texas 75418 OFFICE: (903) 583-7555 FAX: (903)583-5761 Residential Building Permits Information Application for Permits: To apply for a permit,
Electrical Service Guidelines
Electrical Service Guidelines Middle Tennessee Electric Membership Corporation Revised: May 23, 2013 MTEMC's Electrical Guidelines TABLE OF CONTENTS Right-of-Way Clearance Guide 3 MTEMC Requirements 4
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems
NC State University Design and Construction Guidelines Division 26 Fire Alarm Systems 1.0 Purpose A. The following guideline provides the minimum standards and requirements for fire alarm systems. 2.0
UB1 AIR CONDITIONING UNIT INSTALLATION INSTRUCTIONS
UB1 AIR CONDITIONING UNIT INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS: Carefully read these instructions before installing your new air-conditioner. AUSTRALIAN AUTOMOTIVE AIR AL00500054E 1 Table
Meter Box Location Handbook
Document Code: NCN RF08 Document No.: NCN RF08 Page 1 of 75 This page is intentionally blank Document No.: NCN RF08 Page 2 of 75 Table of Contents 1 Introduction... 5 1.1 Background... 5 1.2 Purpose...
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:
Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial
G-704-0 SPECIFICATION: GAS METER AND REGULATOR INSTALLATION REQUIREMENTS. 3 and Gas Yellow Book. REVISIONS: (See ) 1/15/14 5 Years
LAST REVIEW DATE: REVIEW CYCLE: 1/15/14 5 Years SPECIFICATION: TITLE: VOLUME: G-704-0 3 and Gas Yellow Book REVISIONS: (See ) 1) This specification is being issued for the first time. G-704-0 Gas Operations
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES. EFFECTIVE MARCH 1, 1995 Revised 1/01/2013
CARROLL COUNTY ELECTRICAL DEPARTMENT SERVICE POLICIES EFFECTIVE MARCH 1, 1995 Revised 1/01/2013 CARROLL COUNTY ELECTRICAL DEPARTMENT 103 WEST PARIS ST. P. O. BOX 527 HUNTINGDON, TENNESSEE 38344 Telephone
CONSTRUCTION FIRE SAFETY PLANNING GUIDELINES
CONSTRUCTION FIRE SAFETY PLANNING GUIDELINES Review the following information pertaining to Construction Fire Safety Planning: B.C. Building Code Sections 8.1 up to and including Subsection 8.2.3 B.C.
TYPICAL FIRE SAFETY INSPECTION VIOLATIONS
TYPICAL FIRE SAFETY INSPECTION VIOLATIONS The following is a list of typical violations often found by inspectors and a generic solution. You can use this list to improve the safety of your facility, to
Development Services City of Lawrence, KS
Development Services City of Lawrence, KS Building Planning Table R301.2 (1) Climatic & Geographic Design Criteria Building Planning The design criteria for wind speed increased from 90 MPH to 115 MPH.
General Fire Code Requirements Within Commercial Tenant Spaces
FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding
BOROUGH OF OAKLAND COUNTY OF BERGEN STATE OF NEW JERSEY ORDINANCE 13-CODE-685
BOROUGH OF OAKLAND COUNTY OF BERGEN STATE OF NEW JERSEY ORDINANCE 13-CODE-685 AN ORDINANCE TO AMEND, SUPPLEMENT AND REVISE THE CODE OF THE BOROUGH OF OAKLAND, LAND USE, CHAPTER 59 ENTITLED LAND USE AND
Fiberstars Mini Lighted Laminar Flow Fountains
Fiberstars Mini Lighted Laminar Flow Fountains SAVE THESE DIRECTIONS! These directions are provided to ensure the proper installation and operation of Fiberstars Mini Lighted Laminar Flow Fountain. The
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:
ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to
Elevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
MOBILEHOME PARK INSPECTION RESIDENT INFORMATION BOOKLET
State of California Business, Transportation and Housing Agency Department of Housing and Community Development Division of Codes and Standards MOBILEHOME PARK INSPECTION RESIDENT INFORMATION BOOKLET *
Fiberstars Lighted Laminar Flow Fountain Installation Manual
Fiberstars Lighted Laminar Flow Fountain Installation Manual 79-15037-00 REV Xx http://www.fiberstars.com Page 1 of 8 SAVE THESE DIRECTIONS! These directions are provided to ensure the proper installation
Installation of Underground LP-Gas Systems
NPGA #412-94 Installation of Underground LP-Gas Systems SCOPE This bulletin provides guidelines for the installation and inspection of underground LP-Gas systems and outlines song of the unique problems
Builder/developer gas service application
Builder/developer gas service application All gas service applications will be processed within three business days of receipt. Apply for gas service by: Phone: 1-888-224-2710 option 2 Fax: 1-877-413-1152
CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT
Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide
SUBJECT CAN: 2-108. Temporary Systems, Utilities and Equipment. Effective: 4/09/2013. CODE SECTION 2010 California Building Code (CBC)
Facilities Development Division Office of Statewide Health Planning and Development 400 R Street, Suite 200 Sacramento, CA 95811 (916) 440-8300 700 N. Alameda Street, Suite 2-500 Los Angeles, CA 90012
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT
SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum
Suffolk County Department of Health Services. Division of Environmental Quality
Suffolk County Department of Health Services Division of Environmental Quality Guidelines For the Construction of Storage Areas for Portable Containers ~~~~ Clare B. Bradley, M.D., M.P.H. Suffolk County
Building Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
Automatic Fire Sprinkler Submittal Requirements
Automatic Fire Sprinkler Submittal Requirements All commercial and industrial buildings with a total floor area of 5000 sq. ft. shall have an approved automatic sprinkler system installed. The Windsor-Severance
How To Build A Power Plant For Cps Energy
Summary of Gas Service Standards For Engineers, Architects, Contractors and Developers May 2011 Copies of this manual are available online at http://www.cpsenergy.com/developers_builders/new_service/ Copyright
TOWN OF BRENTWOOD 4300 39 TH PLACE BRENTWOOD, MD 20722 (301) 927-3344 FENCE PERMIT APPLICATION
TOWN OF BRENTWOOD 4300 39 TH PLACE BRENTWOOD, MD 20722 (301) 927-3344 BEFORE YOU DIG ANY WHERE CALL MISS UTILITY 1-800-257-7777 It s the Law FENCE PERMIT APPLICATION (To be completed by applicant. Application
Single Family Residential Building Permit Questions & Answers
Single Family Residential Building Permit Questions & Answers Prepared by Dept. of Public Works Revised 07/01/13 200 East Park Street Edwardsville, IL 62025 (618) 692-7535 (618) 692-7505(Fax) Hours: Monday
Element D Services Plumbing
PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses domestic cold, hot and hot water return distribution systems within and to five feet beyond building perimeter. PART 2 - DESIGN CRITERIA 2.01 GENERAL
`Fall Protection Guidelines in Construction
`Fall Protection Guidelines in Construction A Publication Provided by: 1681 Campus Delivery Fort Collins, Colorado 80523 (970) 491-6151 email: [email protected] web: http://www.bernardino.colostate.edu/public/
RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS
RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional
Cold Weather Concrete Practices
Cold Weather Concrete Practices The Information below is an outline of common practice for residential foundation placement and winter construction utilize Edmonton and surrounding Area. Conditions in
PERMITS REQUIRED & PERMIT EXEMPTIONS
PERMITS REQUIRED & PERMIT EXEMPTIONS This guideline is intended to assist the applicant in determining what types of construction work require a permit. The 1997 California Uniform Administrative Code,
Please check with your local inspection authority for any additional requirements before installation.
Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be
GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables
Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,
Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10
Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10 This document was developed by the Orange County Fire Chiefs Association, Orange County Fire Marshal Committee.
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression
BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207
BUILDING DEPARTMENT 8748 W. 82 nd Place - Justice, IL 60458 Phone: (708) 458-2130 Fax: (708) 458-3207 SELF EVALUATION CHECKLIST FOR RESIDENTIAL AND MULTI-FAMILY DWELLING INSPECTIONS The attached checklist
Section 2 Gas Service
Section 2 Gas Service 2.1. Scope This section covers general gas service and gas meter-set requirements for residential and nonresidential installations. 2.2. Procedures for Establishing Gas Service 2.2.1.
ETL listed for installations within 5 ft. (1.5M) of outer edge of water www.srsmith.com 79-15152-00 Rev E2 9.14 Page 1 of 10
Color Light Streams Large Laminar Installation Manual (CLSLL) Input Power: Total Power: 12V AC 5W 4008814 ETL listed for installations within 5 ft. (1.5M) of outer edge of water 79-15152-00 Rev E2 9.14
WHEN IS A PERMIT REQUIRED?
WHEN IS A PERMIT REQUIRED? Any owner, builder, contractor, or other authorized agent who intends to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure,
FORENSIC INVESTIGATION QUESTIONNAIRE
FORENSIC INVESTIGATION QUESTIONNAIRE PSE Project Number: - - Project Name: Person(s) Interviewed: Relationship to House: Please answer the following questions to the best of your ability. Exact dates are
Underground Service Requirements and Instructions
This packet includes all FKEC underground service requirements, instructions, procedures and drawings. If you are considering underground power service please review this document in its entirety (3 page
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS
Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...
Gas Appliances and Gas Piping
Gas Appliances and Gas Piping Manual Owner: Paul Pirro REV 01.02 July 6, 2012 Record of Revisions July 6, 2012 Rev 1.02 Revision Number Revision Date Sections Revised Reason for Revision REV 01.00 September
City of Riverside Building & Safety Division Residential Electric Vehicle (EV) Charger Guidelines
Western Riverside County Code Uniformity Program City of Riverside Building & Safety Division Residential Electric Vehicle (EV) Charger Guidelines PHONE (951) 826-5697 3900 Main Street, Riverside, CA 92522
Name Of Occupancy Date. Yes No Describe
FIRE PREVENTION INSPECTION CHECKLIST For Class A Occupancy (For Assembly Buildings, Bars, Restaurants, Gyms, Churches, Arenas, Theatres or wherever people gather) Name Of Occupancy Date Physical Address
Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842
Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 APPLICATION for ZONING and BUILDING PERMIT APPLICATION INSTRUCTIONS:
When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:
When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory
Solar Panel Installations
Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.
Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes
CANTEX INC. 301 Commerce Ste 2700 Fort Worth, Texas 76102 817-215-7000 Fax: 817-215-7001 Conduit Fittings & Accessories Directional Drilling Conduit Utility Duct Telephone Duct Residential Boxes YOUR FULL
GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264
BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used
Hyperlinks are Inactive
Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)
Questions Regarding Proposed Utility Undergrounding in Kensington
Questions Regarding Proposed Utility Undergrounding in Kensington The following list of questions is being submitted by a group of Kensington residents at the request of Bob Coffin, chairperson for the
ENGINEERED DRAWINGS FOR PETROLEUM STORAGE TANKS
Facility Name: ENGINEERED DRAWINGS FOR PETROLEUM STORAGE TANKS The following is intended to be used as a guideline for information required to appear on engineered drawings involving petroleum storage
NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS
NTUA GUIDELINES FOR DESIGNING AN ELECTRICAL POWER DISTRIBUTION SYSTEM FOR NEW DEVELOPMENTS These guidelines are intended to familiarize Developers regarding some issues that are important to get electric
Electrical. This section applies to the design and installation of building power distribution systems.
Basis of Design This section applies to the design and installation of building power distribution systems. Design Criteria This section contains the architectural, structural and mechanical provisions
INSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
Charter Township of Shelby Harry Reese Building Director
Charter Township of Shelby Harry Reese Building Director Phone: (586) 731-5969 52700 Van Dyke Fax: (586) 803-2099 Shelby Township, MI 48316-3572 E-mail: [email protected] OUTLINE PROCEDURES FOR PRIVATE
Walking and Working Surface Checklist:
Walking and Working Surfaces Purpose: This information is presented to improve the level of safety in our operations, and to inform you that we will comply with the OSHA Standard 29 CFR 1910.23. Responsibility:
Residential Plan Review Emergency Vehicle Access and Water Supply Permit Information Packet
Residential Plan Review Emergency Vehicle Access and Water Supply Permit Information Packet 1. Definitions a. AHJ Authority Having Jurisdiction. The Fire Chief or Fire Marshal of a given Fire District
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE The University of Arizona has implemented a Keyless Access and Security System program to provide a cost effective, efficient, and maintainable means
Questions and Answers for Heating and A/C Contractors
1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded
0095.05 June 30. 2011 July 18, 2014 1 of 7
Standard Number: Superseding: Effective Date: Page: 0095.05 June 30. 2011 July 18, 2014 1 of 7 Pole Attachments, Automated Meter Reading and Cellular Phone Antennas 1. Scope 2. Application This standard
FALL PROTECTION PROGRAM
FALL PROTECTION PROGRAM Page 2 of 15 Table of Contents Applicability... 3 Overview... 3 Definitions... 3 Responsibilities... 5 Risk Assessment... 6 Risk Management... 7 Roof Access Procedure 10 Rescue
Town of Beaumont. Lot Grading Guidelines
Town of Beaumont Lot Grading Guidelines LOT GRADING APPROVAL PROCESS Lot Grading Guidelines... 3 Introduction... 3 Purpose... 3 Definitions... 3 Lot Grading... 3 Lot Grading Plan... 3 Lot Grading Certificate...
STANDARD OPEN PATIO COVER
STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist
ASX7-4-IOM-7 J30-08579
INSTALLATION INSTRUCTIONS 4" COMBUSTION AIR INLET KIT TUBULAR GAS FIRED DIRECT SPARK PROPELLER UNIT HEATERS UNIT CONVERSION & CATEGORY III VENTING FOR SEPARATED COMBUSTION For 30,000 to 75,000 BTU/HR SUPPLEMENT
Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
Basement Development Construction requirements for the development of basements in residential dwellings.
PLANNING, PROPERTY AND DEVELOPMENT DEPARTMENT Basement Development Construction requirements for the development of basements in residential dwellings. June 2009 contents GENERAL INFORMATION 3 BUILDING
Architectural Processing and Inspections for Home Mortgage Insurance
Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect
TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE
TYPICAL WIRING OF METER SOCKET FOR SINGLE PHASE, THREE WIRE OVERHEAD SERVICE A. GENERAL NOTES: Service entrance line and load conductors, conduit straps, weatherhead, lock nuts, bushings, connectors, and
Chapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
How to secure your property after a disaster
How to secure your property after a disaster The Red Guide to Recovery HOuse secured properly Board-Up of Windows, Doors and Roof Hole. Lot secured with Perimeter Fencing. Fires, floods, tornadoes, hurricanes,
INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1
City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE
TAB C-6 KEYLESS ACCESS AND SECURITY SYSTEM GUIDELINE The University of Arizona has implemented a Keyless Access and Security System program to provide a cost effective, efficient, and maintainable means
Services Enclosures and Protected Shafts - Maintaining Compartmentation
Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping
This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.
Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org
POST AND FRAME STRUCTURES (Pole Barns)
POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:
METERING INSTALLATION REQUIREMENTS
METERING INSTALLATION REQUIREMENTS Table of Contents Section 300 PARAGRAPH 300.0 METERING AND SERVICE ENTRANCE EQUIPMENT... 1 300.1 GENERAL... 1 300.2 METERED AND UNMETERED CONDUCTORS... 1 300.3 SEALING
MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS
MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS 01. SAFETY INSPECTION of service equipment at FPL Power Source 02. Construction GFI power outlets (Temp Pole for Construction) 03. 90 day temporary power
Utilities and existing services
Construction Services Building standards for mechanical and electrical installations Utilities and existing services October 2012 Directorate: Environment Construction Services - Building standards for