How to Design and Build a Fence/G traverse Bridge or Graffiti Project
|
|
- Milton Bradley
- 3 years ago
- Views:
Transcription
1
2 Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos
3 Project Location Project Limits: The Grand River east to Fuller Ave.
4 Project Description 1.75 miles of full depth road reconstruction with additional third through lane and merge weave lanes 4,000 feet of soldier pile & lagging Retaining Wall Replacement of five structure crossings: Coit Avenue over I-196 Eastern Avenue over I-196 Lafayette Avenue under I-196 Diamond Avenue over I-196 Fuller Avenue over I-196
5 Project Description Project Cost: $40 Million Schedule: Design Phase Summer 2007 Spring 2009 Bid Letting September 2009 Construction Start April 2010 Substantial Completion - November 2010
6 Project History Original freeway designed in 1962 and opened by 1964 Typical urban depressed limited access roadway Original bridges constructed as three or four span structures Substructures Pile supported abutments (40 ton CIP Concrete) and spread footing piers and abutments
7 Original Bridges Coit Avenue
8 Original Bridges Lafayette Avenue
9 Original Bridges Eastern Avenue
10 Original Bridges Diamond Avenue
11 Original Bridges Fuller Road
12 Site Constraints 130 ft. St. Isidore Church Constructed in ft
13 Photo courtesy of mlive.com
14 Site Constraints Grand Rapids Medical Mile: Van Andel Institute, Grand Rapids Community College's Calkins Science Center, Spectrum Health's Butterworth Hospital complex, Grand Valley State University's Cook-DeVos Center for Health Sciences, and Michigan State University Secchia Center Medical School
15 Photo courtesy of MDOT Grand Rapids TSC
16 Geotechnical Investigation Coit Ave., Lafayette Ave., and Eastern Ave. bridge designs began in 2006, at the beginning of when MDOT fully adopted the AASHTO LRFD Design Method. Final Geotechnical Investigation included performing borings for substructures, retaining walls, roadways, and signs. In total 17 bridge borings, 12 retaining wall borings (and 15 misc. borings (signal poles, signs, ITS) were performed over a 2 year period.
17 Generalized Soil Profiles Lafayette Bridges: Loose sand fill down to ft.± Dense to extremely dense sand to 85 ft.± (EB/south side) V. stiff to hard clay strata within similar extremely dense sand to 90 ft.± (WB/north side) Coit Bridge: Surficial sand fill down to 5 ft.± Loose to med. dense sand to 40 ft.± Alt. layers of hard clay and v. dense sand, 40 to 90 ft.±
18 Eastern Bridge: Surficial fill down to 5 ft.± V. loose to med. dense sand, increasing to med. dense to v. dense to 75 ft.± (with cobbles/boulders!) Hard clay/clayey silt to 100 ft.± Diamond Bridge: Loose to med. dense sand, transitioning to extremely dense to 100 ft.± (occ. clay layers below 50 ft.) Fuller Bridge: Loose to med. dense sand to 9 to 17 ft. ± depth Alt. sand, clay, silt, and gravel strata to 95 to 115 ft.± (occ. cobbles below 50 ft.) strength increasing with depth (extremely dense/hard)
19 Foundation Design Designed per AASHTO Load Resistance Factor Design Manual Section Preliminary Options: Driven H Piles HP14x73 at 600 kips nominal resistance HP12x53 at 400 kips nominal resistance Spread footings Service and Strength Limit State considerations Benefit of depressed freeway and prior loading
20 Foundation Selection Criteria Vibration considerations Limiting vibrations to adjacent sensitive structures 100 year old Church Medical Facilities (underground tunnels) Considerations for Shakedown Settlement (Service Limit State) Overlaying new structure footprint versus existing. Strength Limit State Looser soils with groundwater
21 Pile Foundation Design Iteration Pile Size and Maximum Nominal Pile Driving Resistance (R ndr ) selection Per MDOT Bridge Design Manual Estimate Pile Tip Depth/Elevation Per AASHTO LRFD Sec Refine Estimated Pile Tip Depth/Elevation based on structural loading Perform lateral pile analysis and determine Point of Fixity Again refine Estimated Pile Tip Depth/Elevation based on structural loading
22 Spread Footing Design Iteration Determine the Bearing Elevation of the footing Provide the Service Limit State and Strength Limit State soil pressures (preliminary design) Provide effective footing widths based on site constraints and preliminary design loading (ranges of B and associated bearing resistances). Evaluate the strength limit state of the soils per AASHTO LRFD Sec Evaluate the service limit state of the soils per AASHTO LRFD Sec
23 Specific Example Fuller Bridge & Wall Collaboration FOUNDATION SELECTION H-piles and pipe piles considered, but not preferred due to vibrations adjacent existing structure for part-width construction. Concerns with spread foundations due to loose sand soils and high groundwater at bearing elevation in some locations. Improvement options included extending footing deeper, remove and replace, or in-situ densification.
24 Soil and groundwater limitations related to both design and potential impacts during construction were discussed with the Bridge Engineer in order to design an appropriately-sized spread foundation that achieves the required resistance, minimizes differential settlement, and can also be practically constructed.
25 A spread foundation option was ultimately selected, achieved through a remove and replace operation. Where excavations encountered groundwater, large aggregate was worked into the subgrade for stabilization.
26 CONSTRUCTION ISSUES Temporary Retaining Wall for Part-Width construction Retained soil generally consisted of uniformly graded sand or sand fill (consistent with MDOT Class II or III sand gradations). Due to concerns with vibrations, a cantilever soldier pile/lagging wall system was selected.
27 RETAINING WALL ALONG I-196 URS worked closely with Somat to develop active and passive earth pressures for 4000 of soldier pile wall Large storm sewer was to be installed in front of the retaining wall after the wall was constructed. The pipe was to be located as close as 20 feet to the wall face. The pipe invert was to be situated at about 10 feet below the base of the exposed wall face. Excavation below the wall would compromise the passive resistance relied on in the retaining wall design. A temporary stabilizing berm was to be placed.
28 Conceptual Cross-Section
29 Summation Having the knowledge of subsurface conditions (or potential) during the planning/ pre-design phase has time-saving and cost-saving benefits to your project. Maintaining project-long (and open) communication between geotechnical and structural engineers is mutually beneficial.
30 Photo courtesy of MDOT Grand Rapids TSC
31 Photo courtesy of mlive.com
32 Photo courtesy of mlive.com
33 Photo courtesy of mlive.com
34 Photo courtesy of MDOT Grand Rapids TSC
35 Photo courtesy of MDOT Grand Rapids TSC
36
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationIH-635 MANAGED LANES PROJECT, SEG. 3.2
IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,
More informationTable of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1
Table of Contents Section Page 16.1 GENERAL... 16.1-1 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 16.1.2.1 Geotechnical Section/Bridge Bureau Coordination... 16.1-1 16.1.2.2 Geotechnical
More informationBRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM
BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for
More informationCivil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.
Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationKentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015
Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015 Presented by: Jeff Dunlap, P.E. Terracon Consultants 1 Project Site Kentucky Official
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationHow To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska
APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED
More informationCOMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2
(PREVIEW) SP 36 (Part 2) : 1988 COMPENDIUM OF INDIAN STANDARDS ON SOIL ENGINEERING PART 2 IS 1893 : 1979 (Reaffirmed 1987) CODE OF PRACTICE FOR SUBSURFACE INVESTIGATION FOR FOUNDATIONS 1.1 This code deals
More informationCOSMOS 2012: Earthquakes in Action COSMOS 2012
COSMOS 2012 What is SFSI and why is it important? Soil issues in Earthquakes Structures where SFSI important Retaining structures (lateral earth pressure) Foundations (spread and pile footings, bearing
More informationENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE
ENGINEERED FOUNDATIONS Department of Public Works Jeff Hill, PE What is an engineered foundation. A Foundation Design Developed by a Trained Professional (Engineer) Types of Foundations (All of which can
More informationUse of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
More informationENCE 4610 Foundation Analysis and Design
This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength
More informationTable of Contents. July 2015 12-1
Table of Contents 12.1 General... 3 12.2 Abutment Types... 5 12.2.1 Full-Retaining... 5 12.2.2 Semi-Retaining... 6 12.2.3 Sill... 7 12.2.4 Spill-Through or Open... 7 12.2.5 Pile-Encased... 8 12.2.6 Special
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationGeotechnical Building Works (GBW) Submission Requirements
Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.
More informationDESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA
DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76 Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA The Block 76 project includes the demolition and redevelopment of an entire city
More informationInformational Workshop Public Meeting Kanawha Falls Bridge Project
Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationWashington 98102-3699, mike.bailey@hartcrowser.com
LESSONS LEARNED FROM A STONE COLUMN TEST PROGRAM IN GLACIAL DEPOSITS Barry S. Chen 1, P.E., Member, Geo-Institute and Michael J. Bailey 2, P.E., Member, Geo-Institute ABSTRACT A stone column test program
More informationRetaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations
Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations The implementation of the AASHTO LRFD Bridge Design Specifications
More informationBUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
More informationEXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS
NMP 1.4 EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS Index Purpose... 2 Application... 2 Referral Agency... 2 Associated Requirements... 2 Referenced Standards...2 Definitions...
More informationChapter 4 SUBSURFACE INVESTIGATION GUIDELINES
Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary
More informationThe unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
More information3.1 Historical Considerations
3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible
More informationSECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
More informationPILE FOUNDATIONS FM 5-134
C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics
More informationSPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
More informationHow To Model A Shallow Foundation
Finite Element Analysis of Elastic Settlement of Spreadfootings Founded in Soil Jae H. Chung, Ph.D. Bid Bridge Software Institute t University of Florida, Gainesville, FL, USA Content 1. Background 2.
More informationGEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design
GEOTECHNICAL ENGINEERING FORMULAS A handy reference for use in geotechnical analysis and design TABLE OF CONTENTS Page 1. SOIL CLASSIFICATION...3 1.1 USCS: Unified Soil Classification System...3 1.1.1
More informationSPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT
SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration
More informationPorous Pavement Alternatives Cost Analysis
Porous Pavement Alternatives Cost Analysis Prepared by Century West Engineering for Metro This cost analysis compares the construction costs of six different types of pavement for three different scenarios.
More informationSECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
More informationCHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE
CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long
More informationEXECUTIVE SUMMARY CHAPTER 6
EXECUTIVE SUMMARY CHAPTER 6 This Bridge Development Report was prepared to document the decision process and recommendations for constructing a bridge carrying Maitland Boulevard (eastbound) over I-4 as
More informationSECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
More informationEXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL
EXAMPLE DESIGN OF CANTILEVERED WALL, GRANULAR SOIL A sheet pile wall is required to support a 2 excavation. The soil is uniform as shown in the figure. To take into account the friction between the wall
More informationChallenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26
2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,
More informationOhio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES
Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationUp-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
More informationHighway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting
Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.
More informationNational Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination
Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationTABLE OF CONTENTS. GENERAL PROJECT INFORMATION...3 Project Location... 3 Project Description... 3 STUDY OVERVIEW... 3 SITE EVALUATION TECHNIQUES...
App. P-2 TABLE OF CONTENTS GENERAL PROJECT INFORMATION...3 Project Location... 3 Project Description... 3 STUDY OVERVIEW... 3 SITE EVALUATION TECHNIQUES...4 SITE CONDITIONS... 4 Land Use and Zoning...
More informationSoils, Foundations & Moisture Control
Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations
More informationChapter 7 Substructure Design... 7.1-1 7.1 General Substructure Considerations...7.1-1 7.1.1 Foundation Design Process...7.1-1 7.1.
Chapter 7 Contents Chapter 7 Substructure Design... 7.1-1 7.1 General Substructure Considerations...7.1-1 7.1.1 Foundation Design Process...7.1-1 7.1.2 Foundation Design Limit States...7.1-3 7.1.3 Seismic
More information4.11 Geologic and Soil Resources
4.11 Geologic and Soil Resources Geology and soils are evaluated as part of an environmental document because conditions in the project area can influence the type and size of a project s structure, the
More informationBlock and Gravel Inlet Protection (BIP)
Block and Gravel Inlet Protection (BIP) Practice Description Block and gravel inlet protection is a sediment control barrier formed around a storm drain inlet by the use of standard concrete block and
More informationEngineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.
TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may
More informationEmergency repair of Bridge B421
Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)
More informationSoil Screw Design Manual Edition 2
Soil Screw Design Manual Edition 2 Page TOC-1 Hubbell Power Systems, Inc. All Rights Reserved Copyright 2015 CONTENTS CONTENTS TABLE of CONTENTS INTRODUCTION and APPLICATIONS Section 1 PURPOSE AND SCOPE...
More informationSettlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains
Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced
More informationWATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-02 WATER, SEWER AND TRAFFIC IT S ALL ABOUT THE FLOW Mark Oberschmidt, P.E., Stantec,
More informationGEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS
GEOTECHNICAL INVESTIGATION CITY OF HOUSTON SURFACE WATER TRANSMISSION PROGRAM CONTRACT 74A-1 WATERLINE COH WBS NO. S-000900-0109-3 HOUSTON, TEXAS Reported To: LAN, Inc. Houston, Texas by Aviles Engineering
More informationProject Manager & Key Staff Standards for Technical Proposals Projects using Level A and/or Level B prequalification disciplines
Projects using Level A and/or Level B prequalification disciplines Project Manager PROJECT MANAGER Key Staff/ ROADWAY DESIGN (TP Section 5) (TP Section 6) BACHELORS DEGREE 4 TO 8 YEARS (TP Sections 6 &
More information90 Brighton Road, Surbiton, Surrey
90 Brighton Road, Surbiton, Surrey Civil and Structural Engineering Basement Feasibility Report Mixed Use Scheme 108802-REP-002 March 2015 Contents 1. Executive Summary... 3 2. Site Description and Constraints...
More information2015 ODOT Bridge Design Conference May 12, 2014. DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.
2015 ODOT Bridge Design Conference May 12, 2014 DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement Mary Ann Triska 2015 HDR, all rights reserved. Presentation Outline Project
More informationDesign and Construction of Auger Cast Piles
Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.
More informationHow To Design A Foundation
The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural
More informationCIVL451. Soil Exploration and Characterization
CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally
More informationCaltrans Geotechnical Manual
Cone Penetration Test The cone penetration test (CPT) is an in-situ sounding that pushes an electronic penetrometer into soil and records multiple measurements continuously with depth. Compared with rotary
More informationAPPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT
APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of
More informationDesigned and Engineered to Perform
History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the
More information5/1/2013. Topics. The challenge is to better maintain native characteristics of soils during and after construction
PIN Foundations Topics Applications Design and Construction Flow Control Credits www.pinfoundations.com Copyright 2008, Pin Foundations, Inc. Curtis Hinman WSU Extension Faculty, Watershed Ecologist chinman@wsu.edu
More informationUNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA
UNDERPINNING OF NEW STUDENT HOUSING BUILDING USING MICROPILES, NORTH CAROLINA USA John R. Wolosick, P.E.,D.GE 1, Michael W. Terry, P.E. 2, W. David Kirschner 3 and Robert F. Scott Jr. P.E. 4 SYNOPSIS In
More informationHow To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationDesign of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam
Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More informationPreliminary Foundation Evaluation Oakland Army Base Reuse Study
Preliminary Foundation Evaluation Oakland Army Base Reuse Study Oakland, California Prepared for: Kimely-Horn and Associates 555 12 th Street, Suite 1230 Oakland, California February 2006 Project No. 10991
More informationRehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.
Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double
More informationSCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
More informationAUSTRALIAN PAVING CENTRE
AUSTRALIAN PAVING CENTRE The Concept 02 The concept of Ecopave permeable paving is already well established in many countries where development threatens already over-stretched drainage and river systems.
More informationEvaluating the Condition of Seawalls/Bulkheads
Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many
More informationREPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE
Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE
More informationDesign, Testing and Automated Monitoring of ACIP Piles in Residual Soils
Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore
More informationThere is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.
Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,
More informationGeotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples
Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com
More informationThe URETEK Deep Injection Process (UDI) For Roadways and Building Structures
The URETEK Deep Injection Process (UDI) For Roadways and Building Structures A URETEK USA/ICR White Paper www.worldofuretek.com 888-287-3835 Introduction Since the early days of modern civilization, road
More informationFEBRUARY 2014 LRFD BRIDGE DESIGN 4-1
FEBRUARY 2014 LRFD BRIDGE DESIGN 4-1 4. STRUCTURAL ANALYSIS AND EVALUATION The analysis of bridges and structures is a mixture of science and engineering judgment. In most cases, use simple models with
More informationCHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS
CHALLENGES AND INNOVATIVE SOLUTIONS FOR BRIDGE FOUNDATION REPAIRS Drew Monnier 1, P.Eng. (Presenting) Kimberly Yathon 2, B.Sc. CE (Presenting) Ruth Eden 1, M.Sc., P.Eng. Randy Fingas 1, P.Eng. Emile Shehata
More informationDewatering - Time and Cost Relief by way of Trenchless Construction
North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,
More informationSECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.
Page 1 Revised 3/2/10 See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway. For New/Reconstruction projects: The cross slope of the driving lanes range from 1.5% to
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationUSE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch
USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and
More informationSPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
More informationPrattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
More information3 Tappan Zee Bridge Rehabilitation Options
3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:
More informationComprehensive Design Example 2: Foundations for Bulk Storage Facility
Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently
More informationAlternatives Presentation Meeting Middlebury WCRS(23)
Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College
More informationDivision 2 Section 32 14 13.19 Section 02795
Note: The text must be edited to suit specific project requirements. It should be reviewed by a qualified civil or geotechnical engineer, or landscape architect familiar with the site conditions. Edit
More information817 - PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS & END SECTIONS SECTION 817
SECTION 817 PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS AND END SECTIONS 817.1 DESCRIPTION Install the size and type of pipe culvert, erosion pipe, storm sewer, sanitary sewer, end section
More informationEarth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers
PDHonline Course C155 (2 PDH) Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers Instructor: Richard P. Weber, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA
More informationValue of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective
Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning
More information2010-2011 Contractor of the Year
U.S. Army Corps of Engineers: Little Calumet River Stage VII Steel Sheet Piling Installation Hammond, Indiana Thatcher worked two rigs concurrently one on the north side and one on the south. The United
More informationGEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE
GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE Prof. J. N. Mandal Department of civil engineering, IIT Bombay, Powai, Mumbai 400076, India. Tel.022-25767328 email: cejnm@civil.iitb.ac.in Module - 4
More information