1 Lecture 8 (Chapter 11): Project Analysis and Evaluation Discounted cash flow analysis is a very powerful tool, but it is not easy to use. We have already seen one difficulty: How do we identify the cash flows? Today we begin to focus on a second difficulty: What if our cash flows are not certain? Risk plays a crucial part in DCF analysis. To understand cash fl ow risk, we will use several tools: Scenario analysis Sensitivity analysis Break-even analysis Operating leverage Simulation analysis Lecture 8: Project Analysis and Evaluation 1 Capital Rationing Definition: A situation where a firm has positive NPV projects, but cannot obtain funding to undertake them. Soft Rationing: Firm sets internal limits on capital available to its divisions. Used by firms as an alternative means of controlling investments where DCF is too hard or not understood. Hard rationing: Capital markets refuse to finance the firm. If the firm was willing to pay a high enough rate, could it find someone to invest? If so, perhaps the opportunity cost of capital was calculated incorrectly. If not, perhaps the cash flows are not correct. Market inefficiency (asymmetric information) Lecture 8: Project Analysis and Evaluation 2 1
2 Evaluating NPV Estimates The cash flows that we use in DCF analysis are projections of the future. What will be the effect if these projections turn out to be inaccurate? Forecasting risk: bad projections can lead to bad decisions One way to look for problems in DCF is to ask: Why should we expect this project to have a positive NPV? The project must be better than all the alternatives available to the investor (opportunity cost of capital) Where is the source of value? Innovation, Low cost, Market niche, Economies of scale/scope How competitive is the market? Lecture 8: Project Analysis and Evaluation 3 What-if Analysis What happens if our projections turn out to be wrong? Start with a Base Case that gives our best estimate of the future cash flows. Then vary the cash flows using Scenario analysis: imagine different possible states of the world, and project cash flows and NPVs for each state. Sensitive analysis: change one input variable and see how this affects the resulting NPV. Break-even Analysis: find the value of an input variable (typically sales) that sets the projects NPV to zero Operating Leverage: the degree to which a change in sales impacts the NPV Simulation analysis: use random variables as inputs and calculate NPV many times to determine the distribution of possible NPVs. Lecture 8: Project Analysis and Evaluation 4 2
3 Example Base Case Fairways Driving Range expects rentals to be 20,000 buckets at $3 per bucket. Equipment costs $20,000 and will be depreciated straight-line over 5 years and have a $0 salvage value. Variable costs are 10% of rentals and fixed costs are $45,000 per year. Assume no increase in working capital nor any additional capital outlays. The required return is 15% and the tax rate is 15%. Lecture 8: Project Analysis and Evaluation 5 Scenario Analysis Imagine three states of the world: Base case (our best estimate) Rent 20,000 buckets Variable costs are 10% of revenues Best case (everything works out perfectly) Rent 25,000 buckets Variable costs are 8% of revenues Worst case (nothing goes like it should) Rent 15,000 buckets Variable costs are 12% of revenues How will this change our decision? Lecture 8: Project Analysis and Evaluation 6 3
4 Sensitivity Analysis Change only one input variable at a time and see how the NPV is affected. Find which assumptions are the most important We can then spend more time checking these assumptions Gives us an idea of the riskiness (variability) of our NPV estimate Focus on variables that cannot be directly controlled by the firm to see the effects of nature on our project. For example, try optimistic and pessimistic values. Lecture 8: Project Analysis and Evaluation 7 Break-Even Analysis Find the level of sales that the project must achieve to have a positive NPV Remember finding the bid price from Lecture 7? Set NPV = 0 and solve for sales. Often it won t be so easy to solve by hand. Question: What is the break-even level of the discount rate called? Lecture 8: Project Analysis and Evaluation 8 4
5 Accounting Break-Even Analysis Level of sales that results in zero EBIT and Net Income EBIT = Sales*3*(1-0.1) 45,000 4,000 = 0 Sales = 18,148 General formula: Sales = (FC + Dep)/(Price var cost) Note that when EBIT = 0, Net Income = EBIT*(1-tax) = 0 Accounting break-even < Financial break-even (typically) Ignores time-value of money So NPV < 0 at accounting break-even level of sales What is the IRR? Lecture 8: Project Analysis and Evaluation 9 Cash Break-Even Analysis Level of sales that results in zero yearly cash flow OCF = { [Sales*3(1 0.1) 45,000 4,000]*(1-0.15) + 4,000} = 0 Sales = 16,405 Textbook General formula: Sales = FC/(Price var cost) But this ignores effect of taxes Cash break-even < Accounting break-even < Financial break-even Initial investment completely ignored NPV = -Investment IRR = -100% Cash Break-Even is useful for the treasurer/cash manager to determine working capital needs Lecture 8: Project Analysis and Evaluation 10 5
6 Operating Leverage Degree of Operating Leverage (DOL): The degree to which a change in sales affects Operating Cash Flow Can also be expressed as: the ratio of fixed costs to OCF DOL = 1 + FC/OCF Projects with high operating leverage have high fixed costs and low variable costs Intuition: In a project with high fixed costs and low variable costs, a change in the level of sales will have a large impact on OCF because revenues will increase while costs will stay steady. High operating leverage? riskier OCF Lever Lecture 8: Project Analysis and Evaluation 11 Leverage The Degree of Operating Leverage is often a choice of the firm. High DOL examples: Low DOL examples: A related concept is Financial Leverage : the degree to which changes in EBIT affect earnings. Financial leverage is higher for firms with higher debt loads Changes in revenues have greater effect on shareholders Resulting rate of return is riskier Operating leverage and financial leverage are chosen to compliment each other. Lecture 8: Project Analysis and Evaluation 12 6
7 Simulation Analysis Scenario analysis and sensitivity analysis are both very limited in their ability to reflect all the possible outcomes. Simulation analysis lets us describe possible values of the inputs in a much more complete way (often as random variables), and lets us vary many inputs at the same time. Too difficult to solve analytically Monte Carlo Simulations Sample the input variables many times, and each time calculate the NPV, then analyze the distribution of possible NPVs. Time consuming, so let the computer do it. Lecture 8: Project Analysis and Evaluation 13 Managerial Flexibility (Options) We have imagined the sole job of the manager as a yes/no then wait for the outcome. In reality, managers get the big bucks because they need to be constantly making decisions as the project progresses: Should we wait before deciding Should we expand/contract the project Should we switch inputs Should we abandon the project This flexibility increases the value (and hence the true NPV) of the project Lecture 8: Project Analysis and Evaluation 14 7
8 Valuing Managerial Flexibility Our basic DCF analysis cannot handle decisions made after a project is accepted, but all is not lost. Decision trees: Map out all the possible outcomes and the decisions that we will take in each case, and then value the resulting cash flows. Real Options: Use the techniques developed for financial options (call options, put options, etc), to value options on real assets. These techniques are very powerful and important, but they must await another course. Lecture 8: Project Analysis and Evaluation 15 What we know now DCF analysis is hard: cash flows are not certain. We have techniques for dealing with uncertainty: Scenario analysis: analyze different possible states of the world Sensitivity analysis: Change one input and see the results Break-even analysis: how far can we drop before the project is bad Degree of operating leverage: how are changes in cash flows reflected in earnings Simulation analysis: Allows more complete description of possible future risks Managerial flexibility increases the value of projects Capital rationing is a friction that sometimes prevents the use of DCF analysis Lecture 8: Project Analysis and Evaluation 16 8
Finance for Cultural Organisations Lecture 9. Capital Budgeting: Project Analysis and Evaluation
Finance for Cultural Organisations Lecture 9. Capital Budgeting: Project Analysis and Evaluation Lecture 9. Capital Budgeting: Project Analysis & Evaluation Understand forecasting risk and sources of value
Chapter. Project Analysis and Evaluation. McGraw-Hill/Irwin. Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved.
Chapter 11 Project Analysis and Evaluation McGraw-Hill/Irwin Copyright 2006 by The McGraw-Hill Companies, Inc. All rights reserved. Key Concepts and Skills Understand forecasting risk and sources of value
11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs
385 356 PART FOUR Capital Budgeting a large number of NPV estimates that we summarize by calculating the average value and some measure of how spread out the different possibilities are. For example, it
Project cash flows and NPVs may be estimated under different assumptions to improve the decision process.
FIN 301 Class Notes Chapter 9: Project Analysis WHAT-IF Analysis Project cash flows and NPVs may be estimated under different assumptions to improve the decision process. Sensitivity Analysis A. Changing
Chapter 011 Project Analysis and Evaluation
Multiple Choice Questions 1. Forecasting risk is defined as the: a. possibility that some proposed projects will be rejected. b. process of estimating future cash flows relative to a project. C. possibility
Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14
Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 I. Additional Issues in Capital Budgeting. A. Capital rationing: Use profitability index
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO SELECTED END-OF-CHAPTER QUESTIONS 11-1 a. Cash flow, which is the relevant financial variable, represents the actual flow of cash. Accounting
Chapter 9. Project Analysis
Chapter 9 Project Analysis 9-2 Topics Covered How Firms Organize the Investment Process Some what if Questions Sensitivity Analysis Scenario Analysis Break Even Analysis Real Options and the Value of Flexibility
CHAPTER 14 COST OF CAPITAL
CHAPTER 14 COST OF CAPITAL Answers to Concepts Review and Critical Thinking Questions 1. It is the minimum rate of return the firm must earn overall on its existing assets. If it earns more than this,
CHAPTER 10: UNCERTAINTY AND RISK IN CAPITAL BUDGETING: PART I
CHAPTER 10: UNCERTAINTY AND RISK IN CAPITAL BUDGETING: PART I 10-1 Year ATCF 0-2,500,000 Initial Investment = $2,500,000 1 $1,280,000 Annual Operating Cash Flows 2 $1,280,000 Revenues $5,000,000 3 $1,280,000
Pro Forma Income Statements Sales $50,000 Var. costs 30,000 Fixed costs 5,000 Depreciation 7,000 EBIT $8,000 Taxes (34%) 2,720 Net income $5,280
Project Analysis: Suppose we want to prepare a set of pro forma financial statements for a project for Norma Desmond Enterprises. In order to do so, we must have some background information. In this case,
CHAPTER 11. Proposed Project. Incremental Cash Flow for a Project. Treatment of Financing Costs. Estimating cash flows:
CHAPTER 11 Cash Flow Estimation and Risk Analysis Estimating cash flows: Relevant cash flows Working capital treatment Inflation Risk Analysis: Sensitivity Analysis, Scenario Analysis, and Simulation Analysis
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the
Capital Budgeting. Financial Modeling Templates
Financial Modeling Templates http://spreadsheetml.com/finance/capitalbudgeting.shtml Copyright (c) 2009-2014, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility for any adverse affect
Chapter 18. Web Extension: Percentage Cost Analysis, Leasing Feedback, and Leveraged Leases
Chapter 18 Web Extension: Percentage Cost Analysis, Leasing Feedback, and Leveraged Leases Percentage Cost Analysis Anderson s lease-versus-purchase decision from Chapter 18 could also be analyzed using
Chapter 11 Cash Flow Estimation and Risk Analysis
Chapter 11 Cash Flow Estimation and Risk Analysis ANSWERS TO END-OF-CHAPTER QUESTIONS 11-1 a. Cash flow, which is the relevant financial variable, represents the actual flow of cash. Accounting income,
Chapter 9 Making Capital Investment Decisions Introduction
Chapter 9 Making Capital Investment Decisions Introduction The cash flows that should be included in a capital budgeting analysis are those that will only occur if the project is accepted These cash flows
CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING
CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING Answers to Concepts Review and Critical Thinking Questions 1. No. The cost of capital depends on the risk of the project, not the source of the money.
Things to Absorb, Read, Do
McGraw-Hill/Irwin Copyright 2012 by The McGraw-Hill Companies, Inc. All rights reserved. Things to Absorb, Read, Do Need to Absorb - There are three important areas in this chapter; decision trees, sensitivity/
On the Applicability of WACC for Investment Decisions
On the Applicability of WACC for Investment Decisions Jaime Sabal Department of Financial Management and Control ESADE. Universitat Ramon Llull Received: December, 2004 Abstract Although WACC is appropriate
How To Calculate Discounted Cash Flow
Chapter 1 The Overall Process Capital Expenditures Whenever we make an expenditure that generates a cash flow benefit for more than one year, this is a capital expenditure. Examples include the purchase
DUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #7 Prof. Simon Gervais Fall 2011 Term 2.
DUKE UNIVERSITY Fuqua School of Business FINANCE 351 - CORPORATE FINANCE Problem Set #7 Prof. Simon Gervais Fall 2011 Term 2 Questions 1. Suppose the corporate tax rate is 40%, and investors pay a tax
Cash Flow, Taxes, and Project Evaluation. Remember Income versus Cashflow
Cash Flow, Taxes, and Project Evaluation Of the four steps in calculating NPV, the most difficult is the first: Forecasting cash flows. We now focus on this problem, with special attention to What is cash
MODULE 2. Capital Budgeting
MODULE 2 Capital Budgeting Capital Budgeting is a project selection exercise performed by the business enterprise. Capital budgeting uses the concept of present value to select the projects. Capital budgeting
Strategy and Analysis in Using NPV. How Positive NPV Arises
Strategy and Analysis in Using NPV (Text reference: Chapter 8) Topics how positive NPV arises decision trees sensitivity analysis scenario analysis break-even analysis investment options AFM 271 - Strategy
Which projects should the corporation undertake
Which projects should the corporation undertake Investment criteria 1. Investment into a new project generates a flow of cash and, therefore, a standard DPV rule should be the first choice under consideration.
Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions
Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Chapter 8 Capital Budgeting Concept Check 8.1 1. What is the difference between independent and mutually
Financial and Cash Flow Analysis Methods. www.project-finance.com
Financial and Cash Flow Analysis Methods Financial analysis Historic analysis (BS, ratios, CF analysis, management strategy) Current position (environment, industry, products, management) Future (competitiveness,
Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS
Chapter 13 Capital Budgeting: Estimating Cash Flow and Analyzing Risk ANSWERS TO END-OF-CHAPTER QUESTIONS 13-3 Since the cost of capital includes a premium for expected inflation, failure to adjust cash
Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows
Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Chapter 7: 1,5,7,8,27,32 Chapter 8: 1,3,5,8,13 (clarification for problem 13b:
Part 7. Capital Budgeting
Part 7. Capital Budgeting What is Capital Budgeting? Nancy Garcia and Digital Solutions Digital Solutions, a software development house, is considering a number of new projects, including a joint venture
Project Management Seminars. Financial Management of Projects
Project Management Seminars Financial Management of Projects.inproject managementandsystems engineering, is a deliverable-oriented decomposition of a project into smaller components. (source: Wikipedia)
Course 3: Capital Budgeting Analysis
Excellence in Financial Management Course 3: Capital Budgeting Analysis Prepared by: Matt H. Evans, CPA, CMA, CFM This course provides a concise overview of capital budgeting analysis. This course is recommended
Investment Decision Analysis
Lecture: IV 1 Investment Decision Analysis The investment decision process: Generate cash flow forecasts for the projects, Determine the appropriate opportunity cost of capital, Use the cash flows and
WHAT IS CAPITAL BUDGETING?
WHAT IS CAPITAL BUDGETING? Capital budgeting is a required managerial tool. One duty of a financial manager is to choose investments with satisfactory cash flows and rates of return. Therefore, a financial
Capital Investment Appraisal Techniques
Capital Investment Appraisal Techniques To download this article in printable format click here A practising Bookkeeper asked me recently how and by what methods one would appraise a proposed investment
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After three years, the project
EMBA in Management & Finance. Corporate Finance. Eric Jondeau
EMBA in Management & Finance Corporate Finance EMBA in Management & Finance Lecture 5: Capital Budgeting For the Levered Firm Prospectus Recall that there are three questions in corporate finance. The
UNIVERSITY OF WAH Department of Management Sciences
BBA-330: FINANCIAL MANAGEMENT UNIVERSITY OF WAH COURSE DESCRIPTION/OBJECTIVES The module aims at building competence in corporate finance further by extending the coverage in Business Finance module to
(Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics)
Capital Budgeting: Net Present Value vs Internal Rate of Return (Relevant to AAT Examination Paper 4 Business Economics and Financial Mathematics) Y O Lam Capital budgeting assists decision makers in a
EXAM 1 REVIEW QUESTIONS
EXAM 1 REVIEW QUESTIONS 1) Free cash flow. Consider the following financial statements for United Technologies Corp. What is UT's free cash flow (total cash flow from assets) for 2001? UNITED TECHNOLOGIES:
On the Rate of Return and Valuation of Non-Conventional Projects
On the Rate of Return and Valuation of Non-Conventional Projects Carlos Heitor Campani Professor of Finance at COPPEAD Graduate School of Business (Federal University of Rio de Janeiro) Research Associate
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Answers to Concepts Review and Critical Thinking Questions 1. A payback period less than the project s life means that the NPV is positive for
ADVANCED INVESTMENT APPRAISAL
RELEVANT TO ACCA QUALIFICATION PAPER F9 Studying Paper F9? Performance objectives 15 and 16 are relevant to this exam Investment appraisal is one of the eight core topics within Paper F9, Financial Management
Real Options. The Big Picture: Part II - Valuation
Real Options The Big Picture: Part II - Valuation A. Valuation: Free Cash Flow and Risk April 1 April 3 Lecture: Valuation of Free Cash Flows Case: Ameritrade B. Valuation: WACC and APV April 8 April 10
CHAPTER 8 CAPITAL BUDGETING DECISIONS
CHAPTER 8 CAPITAL BUDGETING DECISIONS Q1. What is capital budgeting? Why is it significant for a firm? A1 A capital budgeting decision may be defined as the firm s decision to invest its current funds
NPV with an Option to Delay and Uncertainty
NPV with an Option to Delay and Uncertainty In all the examples and the theory so far, we have assumed perfect foresight when making investment decisions and analyzing future variables. We have also ignored
KEY EQUATIONS APPENDIX CHAPTER 2 CHAPTER 3
KEY EQUATIONS B CHAPTER 2 1. The balance sheet identity or equation: Assets Liabilities Shareholders equity [2.1] 2. The income statement equation: Revenues Expenses Income [2.2] 3.The cash flow identity:
CHAPTER 8: ESTIMATING CASH FLOWS
CHAPTER 8: ESTIMATING CASH FLOWS 8-1 a. Straight line depreciation = ($15 - $3)/10 = $1.20 Annual Tax Savings from Depreciation = $ 1.2 (0.4) = $0.48 Present Value of Tax Savings from Depreciation = $
Chapter 10 Risk and Capital Budgeting
Chapter 10 Risk and Capital Budgeting MULTIPLE CHOICE 1. Operating leverage describes the relationship between... a. EBIT and sales b. taxes and sales c. debt and equity d. fixed costs and variable costs
In the business world, the rearview mirror is always clearer than the windshield. - Warren Buffett
ENGM 401 & 620 X1 Fundamentals of Engineering Finance Fall 2010 Lecture 29: Sensitivity Analysis & Uncertainty In the business world, the rearview mirror is always clearer than the windshield. - Warren
Chapter 10 Richard A. Brealey Stewart C. Myers Slides by Matthew Will McGraw Hill/Irwin
Principles of Corporate Finance Chapter 10 A Project Is Not a Black Box Seventh Edition Richard A. Brealey Stewart C. Myers Slides by Matthew Will - 2 Topics Covered Sensitivity Analysis Break Even Analysis
1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600 1,600 1,600 1,600 1,600
Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2011 Answers 1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600
ITU / BDT- COE workshop. Network Planning. Business Planning. Lecture NP- 3.5. Nairobi, Kenya, 7 11 October 2002
ITU / BDT- COE workshop Nairobi, Kenya, 7 11 October 2002 Network Planning Lecture NP- 3.5 Business Planning October 8th ITU/BDT-COE Network Planning/ Business Planning - O.G.S. Lecture NP - 3.5 - slide
CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS
CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS Answers to Concepts Review and Critical Thinking Questions 1. In this context, an opportunity cost refers to the value of an asset or other input that will
Performance Review for Electricity Now
Performance Review for Electricity Now For the period ending 03/31/2008 Provided By Mark Dashkewytch 780-963-5783 Report prepared for: Electricity Now Industry: 23821 - Electrical Contractors Revenue:
Chapter 7 Fundamentals of Capital Budgeting
Chapter 7 Fundamentals of Capital Budgeting 7-1. Pisa Pizza, a seller of frozen pizza, is considering introducing a healthier version of its pizza that will be low in cholesterol and contain no trans fats.
Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6. Part One. Multiple Choice Questions.
Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6 Part One. Multiple Choice Questions. 1. Similar to the example given in class, assume that a corporation has $500 of cash revenue and $300
Chapter 17 Corporate Capital Structure Foundations (Sections 17.1 and 17.2. Skim section 17.3.)
Chapter 17 Corporate Capital Structure Foundations (Sections 17.1 and 17.2. Skim section 17.3.) The primary focus of the next two chapters will be to examine the debt/equity choice by firms. In particular,
Content Chapter 3.5. Role of business Planning today. Basic concepts. Telecom business modeling. Typical evaluation results
ITU / BDT- COE workshop Bangkok, Thailand, 11 15 November 2002 Network Planning Lecture NP- 3.6 Business Planning November 12th ITU/BDT-COE Network Planning/ Business Planning - O.G.S. Lecture NP - 3.6
PRODUCTIVITY & GROWTH
Productivity Financial Tools There are a number of financial tools that can be used to measure the financial performance and potential contribution of improvement projects to the productivity of a business.
Overview of Financial Management
Overview of Financial Management Uwadiae Oduware FCA Akintola Williams Deloitte 1-1 Definition Financial Management entails planning for the future for a person or a business enterprise to ensure a positive
Paper F9. Financial Management. Fundamentals Pilot Paper Skills module. The Association of Chartered Certified Accountants
Fundamentals Pilot Paper Skills module Financial Management Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Do NOT open this paper
Risk Analysis and Quantification
Risk Analysis and Quantification 1 What is Risk Analysis? 2. Risk Analysis Methods 3. The Monte Carlo Method 4. Risk Model 5. What steps must be taken for the development of a Risk Model? 1.What is Risk
Break-Even and Leverage Analysis
CHAPTER 6 Break-Even and Leverage Analysis After studying this chapter, you should be able to: 1. Differentiate between fixed and variable costs. 2. Calculate operating and cash break-even points, and
CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA
CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Answers to Concepts Review and Critical Thinking Questions 1. Assuming conventional cash flows, a payback period less than the project s life means
DUKE UNIVERSITY Fuqua School of Business. FINANCE 351 - CORPORATE FINANCE Problem Set #1 Prof. Simon Gervais Fall 2011 Term 2.
DUKE UNIVERSITY Fuqua School of Business FINANCE 351 - CORPORATE FINANCE Problem Set #1 Prof. Simon Gervais Fall 2011 Term 2 Questions 1. Two years ago, you put $20,000 dollars in a savings account earning
The Reinvestment Assumption Dallas Brozik, Marshall University
The Reinvestment Assumption Dallas Brozik, Marshall University Every field of study has its little odd bits, and one of the odd bits in finance is the reinvestment assumption. It is an artifact of the
CHAPTER 4: FINANCIAL ANALYSIS OVERVIEW
In the financial analysis examples in this book, you are generally given the all of the data you need to analyze the problem. In a real-life situation, you would need to frame the question, determine the
Net Present Value and Other Investment Criteria
Net Present Value and Other Investment Criteria Topics Covered Net Present Value Other Investment Criteria Mutually Exclusive Projects Capital Rationing Net Present Value Net Present Value - Present value
1.1 Introduction. Chapter 1: Feasibility Studies: An Overview
Chapter 1: Introduction 1.1 Introduction Every long term decision the firm makes is a capital budgeting decision whenever it changes the company s cash flows. Consider launching a new product. This involves
INCOME APPROACH Gross Income Estimate - $198,000 Vacancy and Rent Loss - $9,900
INCOME APPROACH The Income Approach considers the return on Investment and is similar to the method that investors typically use to make their investment decisions. It is most directly applicable to income
Solutions to Chapter 8. Net Present Value and Other Investment Criteria
Solutions to Chapter 8 Net Present Value and Other Investment Criteria. NPV A = $00 + [$80 annuity factor (%, periods)] = $00 $80 $8. 0 0. 0. (.) NPV B = $00 + [$00 annuity factor (%, periods)] = $00 $00
Business Valuation under Uncertainty
Business Valuation under Uncertainty ONDŘEJ NOWAK, JIŘÍ HNILICA Department of Business Economics University of Economics Prague W. Churchill Sq. 4, 130 67 Prague 3 CZECH REPUBLIC [email protected] http://kpe.fph.vse.cz
Chapter 10: Making Capital Investment Decisions
Chapter 10: Making Capital Investment Decisions Faculty of Business Administration Lakehead University Spring 2003 May 21, 2003 Outline 10.1 Project Cash Flows: A First Look 10.2 Incremental Cash Flows
TIP If you do not understand something,
Valuing common stocks Application of the DCF approach TIP If you do not understand something, ask me! The plan of the lecture Review what we have accomplished in the last lecture Some terms about stocks
CHAPTER 13 Capital Structure and Leverage
CHAPTER 13 Capital Structure and Leverage Business and financial risk Optimal capital structure Operating Leverage Capital structure theory 1 What s business risk? Uncertainty about future operating income
CHAPTER 7: NPV AND CAPITAL BUDGETING
CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental
Investing in unlisted property schemes?
Investing in unlisted property schemes? Independent guide for investors about unlisted property schemes This guide is for you, whether you re an experienced investor or just starting out. Key tips from
Ch. 18: Taxes + Bankruptcy cost
Ch. 18: Taxes + Bankruptcy cost If MM1 holds, then Financial Management has little (if any) impact on value of the firm: If markets are perfect, transaction cost (TAC) and bankruptcy cost are zero, no
How much is your pre-revenue company worth?
How much is your pre-revenue company worth? RIC Centre Presentation Summary Andrew Maxwell April 14 2011 Introduction 2 Investors and entrepreneurs often ask me to shed some light on how to value prerevenue
Capital budgeting & risk
Capital budgeting & risk A reading prepared by Pamela Peterson Drake O U T L I N E 1. Introduction 2. Measurement of project risk 3. Incorporating risk in the capital budgeting decision 4. Assessment of
Instructions for Using the Casio FC range of Business/Financial Calculators
Instructions for Using the Casio FC range of Business/Financial Calculators These instructions are based on the Casio FC-100 Financial Consultant calculator, and may vary slightly with different models.
Week- 1: Solutions to HW Problems
Week- 1: Solutions to HW Problems 10-1 a. Payback A (cash flows in thousands): Annual Period Cash Flows Cumulative 0 ($5,000) ($5,000) 1 5,000 (0,000) 10,000 (10,000) 3 15,000 5,000 4 0,000 5,000 Payback
Managing The Firm s Assets
CHAPTER OUTLINE Spotlight: The United Companies (http://www.uniteddc.com) 1 The Working-Capital Cycle Describe the working-capital cycle of a small business. Working-capital management Define working capital
Capital Structure II
Capital Structure II Introduction In the previous lecture we introduced the subject of capital gearing. Gearing occurs when a company is financed partly through fixed return finance (e.g. loans, loan stock
Valuation of Your Early Drug Candidate. By Linda Pullan, Ph.D. www.sharevault.com. Toll-free USA 800-380-7652 Worldwide 1-408-717-4955
Valuation of Your Early Drug Candidate By Linda Pullan, Ph.D. www.sharevault.com Toll-free USA 800-380-7652 Worldwide 1-408-717-4955 ShareVault is a registered trademark of Pandesa Corporation dba ShareVault
Cost Benefits analysis
Cost Benefits analysis One of the key items in any business case is an analysis of the costs of a project that includes some consideration of both the cost and the payback (be it in monetary or other terms).
Chapter 10. What is capital budgeting? Topics. The Basics of Capital Budgeting: Evaluating Cash Flows
Chapter 10 The Basics of Capital Budgeting: Evaluating Cash Flows 1 Topics Overview and vocabulary Methods NPV IRR, MIRR Profitability Index Payback, discounted payback Unequal lives Economic life 2 What
Chapter 7: Net Present Value and Capital Budgeting
Chapter 7: Net Present Value and Capital Budgeting 7.1 a. Yes, the reduction in the sales of the company s other products, referred to as erosion, should be treated as an incremental cash flow. These lost
Chapter 5 Capital Budgeting
Chapter 5 Capital Budgeting Road Map Part A Introduction to finance. Part B Valuation of assets, given discount rates. Fixed-Income securities. Common stocks. Real assets (capital budgeting). Part C Determination
1. CFI Holdings is a conglomerate listed on the Zimbabwe Stock Exchange (ZSE) and has three operating divisions as follows:
NATIONAL UNIVERSITY OF SCIENCE AND TECHNOLOGY FACULTY OF COMMERCE DEPARTMENT OF FINANCE BACHELOR OF COMMERCE HONOURS DEGREE IN FINANCE PART II 2 ND SEMESTER FINAL EXAMINATION MAY 2005 CORPORATE FINANCE
The central question: Does the bankruptcy process make sure that firms in bankruptcy are inefficient, and that inefficient firms end up in bankruptcy?
Bankruptcy White (1989) Bankruptcy the closing down of firms that are inefficient, use outdated technologies, or produce products that are in excess supply. The central question: Does the bankruptcy process
STUDENT CAN HAVE ONE LETTER SIZE FORMULA SHEET PREPARED BY STUDENT HIM/HERSELF. FINANCIAL CALCULATOR/TI-83 OR THEIR EQUIVALENCES ARE ALLOWED.
Test III-FINN3120-090 Fall 2009 (2.5 PTS PER QUESTION. MAX 100 PTS) Type A Name ID PRINT YOUR NAME AND ID ON THE TEST, ANSWER SHEET AND FORMULA SHEET. TURN IN THE TEST, OPSCAN ANSWER SHEET AND FORMULA
Econ Pro Valuation Methods - General recap and pitfalls. October 1, 2010
Econ Pro Valuation Methods - General recap and pitfalls October 1, 2010 1 Agenda Valuation Dimensions & Applications Valuation Methods Market method Cost method Income method Income method for Intangible
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS Phil Thompson Business Lawyer, Corporate Counsel www.thompsonlaw.ca Rules of thumb and financial analysis
Using simulation to calculate the NPV of a project
Using simulation to calculate the NPV of a project Marius Holtan Onward Inc. 5/31/2002 Monte Carlo simulation is fast becoming the technology of choice for evaluating and analyzing assets, be it pure financial
Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions
Solutions to Chapter 9 Using Discounted Cash-Flow Analysis to Make Investment Decisions 1. Net income = ($74 $42 $10) [0.35 ($74 $42 $10)] = $22 $7.7 = $14.3 million Revenues cash expenses taxes paid =