PRE-FEASIBILITY REPORT
|
|
|
- Chad Beasley
- 10 years ago
- Views:
Transcription
1 PRE-FEASIBILITY REPORT for INSTALLATION OF 1 No. 9 MVA AND 1 NO. 6 MVA SUBMERGED ARC FURNACE FOR PRODUCTION OF FERRO-MANGANESE, SILICO- MANGANESE & FERRO SILICON at HALDIA, PURBA MEDINIPORE, WEST BENGAL Project Proponent ELECTROSTEEL CASTINGS LTD. Page-1
2 1 INTRODUCTION Electrosteel Castings Ltd., a renowned name in Ductile Iron pipe manufacturing sector, intends to install two (2) nos. submerged arc furnaces, 1 no. of 9 MVA and 1 no. of 6 MVA capacities for the production of Ferro-Manganese, Silico-manganese & Ferro-silicon alloy, mainly for domestic market consumption. The proposed site is located at Haldia, Dist. Purba Medinipore, West Bengal. The intended production of the plant will be to the tune of 34,687 M.T. of saleable Ferro-manganese or 24,645 M.T. of saleable Silico-manganese or 9,475 M.T. of saleable Ferro-silicon per annum by operating 1 no. 9 MVA & 1 no. 6 MVA submerged arc furnaces. Since the proposed site is located at an already grown up industrial area of West Bengal, it is expected that all the necessary infrastructural facilities shall be available including electrical power. It would be worthwhile to mention here that the required power shall be fed to the proposed unit at 11 KV. Power requirement of the proposed plant would be around 12.5 MW, which will be sourced partly from the Captive Power Plant of the Coke Oven Plant of the company, operating in the adjacent land and partly from the supply system of WBSEDCL. The Ferro Alloy Industry is an essential and vital industry producing basic alloys, which are required for the growth of the steel industry to cater to both domestic and international market. Ferro alloys are the intermediate products used in making of steel as deoxidants alloying agent and for rust proofing. Steel demand in India has been forecast mainly on the basis of past trends, taking into account the relationship between GDP and steel consumption and then projecting specific assumed GDP growth rate for future years. The forecast of steel demand for made by INSDAG as per standard methodology assuming 6 & 6.5 percent annual compounded average growth rate of the GDP seems to be fairly realistic. As per this, demand for finish steel is likely to rise to 165/171 million tones respectively. To meet this demand only, the country will have to set up adequate facilities for production of million tonne crude steel. The total steel demand and required level of finished steel production (alloy & non-alloy) for the 12 th Five Year Plan, i.e had been estimated by the competent authority and it was to the tune of million tonne in the year It is also estimated that about 3.02 million tonne manganese alloys shall be required to meet the demand of Ferromanganese & silico-manganese alloys in the year However, at present, existing installed capacity for the plants manufacturing above alloys is 3.16 million tones and Page-2
3 corresponding capacity utilization is remained at 54% for a production of 1.7 million tonne as noted for the year ending As on today, it is seen that there is a positive growth for manganese alloys. Since it is linearly proportional with the growth of steel industry, it is apprehended that growth of the consuming industry would be substantial within a few years to come and therefore in order to meet the demand, manganese alloys industry shall have to make the way for it. Now, if it is assumed that all the plants those who are operating for manganese alloys now increased their operating efficiency level at 65% of the installed capacity, i.e. 11% higher than the earlier level then the total production would have been to the tune of million tonne per annum whereas the demand for manganese alloys has been projected as 3.02 million tonne leaving a gap of million tonne as short fall for the year However, the demand projection has been made after considering domestic as well as export demand for a year and it concludes that even after operating at appreciable level there would be enough scope for addition of new capacity plant in order to meet the growing demand. From the foregoing discussion a conclusion may be drawn that a fairly constant demand for the ferro-alloys shall be maintained and it will rise proportionately in accordance with the growth of steel production. It is apprehended that the growth of steel production will reach to an appreciable level within near future and therefore capacity additions for production of manganese alloys would be a necessity. Having first hand knowledge about the demand/ supply of the products, the promoters have justifiably embarked on the production of the same. All the figures mentioned in the above paragraphs have been obtained from the Papers Long Term Perspectives for Indian Steel Industry submittd by Dr. A.S. Firoz, Chief Economist, Economic Research Unit, and Manganese Ore and Ferro Alloys for Steel Production submitted by G.P. Kundargi, Director (Production & Planning), MOIL Limited. Page-3
4 SUMMARY Installed capacity: Ferro-manganese : 38,156 TPA or Silico-manganese : 27,109 TPA or Ferro-silicon : 10,421 TPA Main Production Equipment : 1 No. 9 MVA & 1 No. 6 MVA capacity submerged arc furnaces and material handling facility. Charge Mix in M.T. Mn-ore Coke Iron scrap Quartzite Mn Slag Ferro-manganese : Silico-manganese : Ferro-silicon : Utilities Maximum Demand : 14,000 KVA Annual energy consumption at targeted production in Million Kwh (MU) : Supply voltage : 11 KV Recirculation water : 500 M 3 /hr. Make-up water : 17.5 M 3 /hr. Compressed Air : 42 NM 3 /hr. (approx) Manpower Total no. in payroll : 178 Page-4
5 2 MANUFACTURING PROCESS & UTILITIES Most of the Ferro-alloys e.g. Ferro-silicon, Ferro-manganese, Silico-manganese, Ferrochrome, Charge Chrome, etc. are produced by smelting process. Smelting of the charged materials are carried out in submerged electric furnaces equipped with transformer of proper ratings. The process developed in India during the decade of 90 is based on basic process parameters as offered by ELKEM, Norway, in past. Various Indian furnace manufacturers successfully developed furnace design upto 12.5 MVA electrical ratings for manufacture of different grades of ferro-alloys based on ELKEM Technology. The process for the manufacture of Ferro Alloys viz. Silico Manganese, Ferro manganese and Ferro-Silicon by submersible Arc furnace technology is well established in India. All the companies manufacturing Ferro Alloys are using the above technology. The submerged arc process is a reduction smelting operation. The reactants consist of metallic ores (ferrous oxides, silicon oxides and manganese oxides) and a carbon-source reducing agent, usually in the form of coke, charcoal, high and low-volatility coal. Dolomite may also be added as a flux material. Raw materials are crushed, sized, and, in some cases, dried, and then conveyed to a mix house for weighing and blending. Conveyors, buckets, skip hoists, or cars transport the processed material to hoppers above the furnace. The mix is then gravity-fed through a feed chute either continuously or intermittently, as needed. At high temperatures in the reaction zone, the carbon source reacts with metal oxides to form carbon monoxide and to reduce the ores to base metal. Smelting in an electric arc furnace is accomplished by conversion of electrical energy to heat. An alternating current applied to the electrodes causes current to flow through the charge between the electrode tips. This provides a reaction zone at temperatures up to 2000 C. The tip of each electrode changes polarity continuously as the alternating current flows between the tips. The lower part of the submerged electric arc furnace is composed of a cylindrical steel shell with a flat bottom or hearth. The interior of the shell is lined with 2 or more layers of carbon blocks. The furnace shell may be water-cooled to protect it from the heat of the process. A water-cooled cover and fume collection hood are mounted over the furnace shell. Normally, 3 carbon electrodes arranged in a triangular formation extend through the cover and into the furnace shell opening. Prebaked or self baking (Soderberg) electrodes ranging from 76 to over 100 cm (30 to over 40 inches) in diameter are typically used. Raw materials are sometimes charged to the furnace through feed chutes from above the furnace. The surface of the furnace charge, which contains both molten material and unconverted charge during Page-5
6 operation, is typically maintained near the top of the furnace shell. The lower ends of the electrodes are maintained at about 0.9 to 1.5 meters (3 to 5 feet) below the charge surface. Three phase electric current arcs from electrode to electrode, passing through the charge material. The charge material melts and reacts to form the desired product as the electric energy is converted into heat. The carbonaceous material in the furnace charge reacts with oxygen in the metal oxides of the charge and reduces them to base metals. The reactions produce large quantities of carbon monoxide (CO) that passes upward through the furnace charge. The molten metal and slag are removed (tapped) through 1 or more tap holes extending through the furnace shell at the hearth level. Feed materials may be charged continuously or intermittently. Power is applied continuously. Tapping can be intermittent or continuous based on production rate of the furnace. Metallurgical Reactions involved during production of Ferro-manganese & Silico-manganese: 2MnO 2 + C Mn 2 O 3 + CO 3 Mn 2 O 3 + C 2Mn 3 O 2 + CO Mn 3 O 2 + C 3MnO + CO MnO + C Mn + CO Fe 2 O 3 + 3C 2Fe + 3CO SiO 2 + 2C Si + 2CO P 2 O 5 + 5C 2P + 5CO In the Ferro Silicon process, the important reactions are: SiO 2 + C = SiO + CO SiO + 2C = SiC + CO 2SiO 2 + SiC = 3SiO + CO SiO + SiC = 2Si + CO FERRO- MANGANESE High-carbon ferro-manganese is made in three phase open or closed top furnace of a power of 7,500-18,000 KVA at a linear voltage of V with a current of ka, operating at a voltage of V. The charge for making high-carbon ferro-manganese is composed of manganese ore and coke/coal. Physico-Chemical Conditions of the Process: High carbon ferro manganese is smelted by a continuous process with the electrodes submerged deep into the charge. The following processes take place when making high carbon ferro manganese: Pre-heating of the materials; Drying and removal of volatiles and moisture from the charge and heating of the charge by the heat of burning gases which leave the furnace and after-burn at the top; Reduction of oxides; Melting of the elements reduced with the formation of molten ferro-manganese; Formation and melting of slag; The iron contained in the manganese ore is reduced to a high extent in the process. Ferric oxides are reduced with carbon monoxide and hydrogen at low temperatures. Ferrous oxide Page-6
7 is first reduced with carbon monoxide and hydrogen at C temperature and after that with solid carbon in the deeper zones of the bath. The reduction of manganese from pyrolusite occurs stepwise: MnO 2 > Mn 3 O 4 > MnO > Mn 3 C. With a reducing atmosphere in the furnace, the dissociation of manganese oxides can take place at low temperatures. Carbon monoxide and hydrogen can also reduce Mn 3 O 4 to MnO at low temperatures. High Carbon ferro-manganese can be smelted with addition of fluxes or by fluxless process. In the latter case, a valuable by-product of the process is high manganese low phosphorus slag which is used in smelting silico manganese and manganese metal. SILICO-MANGANESE High-carbon Silico-Manganese is made in three phase open or closed top furnace of a power of 5,000-12,000 KVA, operating at a voltage of Volt. The composition of different grades of silico-manganese is given below: Content (in %) Manganese (Mn%) Silicon Carbon Sulphur Phosphorus (Si%) (C%) (S%) (P%) Size: 10-50mm (90% minimum) The charge for making high-carbon Silico-Manganese is composed of manganese ore, Quartz and coke. Physico-Chemical Conditions of the Process: The following processes take place when making high-carbon Silico-Manganese: (a) Removal of volatiles and moisture from the charge and heating of the charge by the heat of burning gases which leave the furnace and after-burn at the top; (b) Reduction of iron and ores with simultaneous formation of metal carbides; (c) Melting of the elements reduced with the formation of molten metal; (d) Formation and melting of slag; (e) Reduction of Manganese and silico from the slag. FERRO-SILICON Silicon is a metalloid having an atomic mass of , density of 2.37 gm/cm 3, melting point of 1414 C, and boiling point of 2287 C. In its electric properties, silicon is a semiconductor. Page-7
8 Silicon reacts with oxygen to form silica (SiO 2 ), whose melting point is 1710 C. Silica can exist in several modifications: quartz, tridymite, cristobalite, and silica glass. Ferro-silicon is made in submerged arc provided with three-phase transformers having power rating of 7,500-9,000 kva operating at a voltage of V. Generally, Semi- Closed-type stationary or tilting furnaces are mainly used for manufacturing ferro alloys. The physical state of the charge is of prime importance for successful operation of a furnace. The charge materials must have constant moisture content and lumps of coke breeze and quartzite should have only slightly varying size. The process of making Ferro-silicon produces little slag; this is tapped together with the metal through the same tap hole. Physico-chemical Conditions of the Process: The reaction of reduction of silicon from silica occurs with solid carbon: SiO 2l + 2CO g 2CO 2g + Si l 2CO 2g + 2C s 4CO g SiO 2l + 2C Si l + 2CO g A typical reaction producing ferro-silicon is shown below: Fe 2 O 3 + 2SiO 2 + 7C 2FeSi + 7 CO During the course of the reaction of silicon reduction is determined by the applied pressure of carbon monoxide. In an industrial furnace for smelting ferro-silicon, the pressure at the top is equal to atmospheric and the partial pressure of carbon monoxide that is established in the reduction zone is slightly above atmospheric pressure. With a constant value of P 2 CO, the equilibrium constant for a 45 per cent alloy is lower than that for 75 per cent alloy, which means that a lower temperature is required for making the former. During a melt for ferro-silicon, the iron dissolves the reduced silicon thereby removes it from the reaction zone and thus causes the reaction to be proceeded from left to right. The mechanism of reduction of silica is not described exhaustively in the above resulting reaction. An intermediate oxide silicon dioxide, and silicon carbide can also form in the process. Carbon causes final reduction of silica. The latter reacts with carbon both at the surface of lumps of coke breeze and in their core upon having penetrated through pores and fissures. Page-8
9 Samples taken from lower levels in the furnace usually contain much silicon carbide. According to P. V. Geld, the formation of SiC from the elements can only occur with large kinetic difficulties and requires a high mobility of atoms, which can only be achieved at temperatures above 1700 C. On the other hand, the reaction is thought to be probable. Thus, silicon carbide forms as an intermediate product. Solid inclusions of silicon carbide, if present in the slag, can impair the fluidity of already tough siliceous slags. At corresponding temperatures, silicon carbide can be destroyed by metals and oxides, its destruction by iron following the reaction SiC s + Fe l = FeSi l + C gr At high temperatures and in the presence of a solvent (iron with silicon) the aluminium and calcium, if present in the charge, are reduced by carbon and silicon. Industrial grades of ferro-silicon can thus contain up to 2 per cent Al and up to 1.5 per cent Ca. Under the reducing conditions, a great amount of phosphorus from the charge and ash pass to the melt, while sulphur is volatilized in the form of SiS2. In operation with rich quartzites, the process occurs with little slag, only 2-6 per cent of the mass of melt. The slag is formed from the alumina, calcium oxide and magnesia that are present in quartzite and coke breeze. A typical composition of slag is per cent Al 2 O 3, per cent SiO 2, 9-18 per cent CaO, 7-13 per cent BaO, 1-3 per cent MgO, 7-14 per cent SiC, and per cent FeO. The melting temperature of slag is C, i.e. low enough to cause slagging of the hearth. In practice, a trend is to operate with silica-rich quartzite and low-ash reducer in order to minimize the bulk of slag of this composition. The charge materials, prepared as indicated earlier, should be stored separately in furnacebay bins. Before supplying to the furnace, they should carefully be weighed and mixed. A dosing carriage is loaded first with coke breeze, then with turnings and quartzite, and finally with graphitization wastes. The general composition of a charge in kg, may be as follows: Material FS45 FS75 Quartzite Coke breeze Iron turnings/ Mill Scale Page-9
10 The flow diagram of Ferro Alloys Plant is presented hereunder: FIGURE 1.0: FLOW CHART OF FERRO ALLOYS PLANT Material Balance for the different products is presented as Annexure 1. Project Location The proposed plant is located adjacent to the existing site of the Coke Oven Plant at Mouza Kashbere, JL No.146, at Haldia, Purba Medinipore, West Bengal. The site falls under Sutahata CD Block and adjacent to Haldia Municipal Area. Haldia is a major river port town with an existing industrial base and therefore necessary infrastructural facilities shall be available for growth of the industries to be located in this area. The proposed location enjoys the territorial advantage of being situated near the National Highway as well as State Highway and therefore connected to most of the important cities of the country. The site thus combines many advantages such as access to market, transportation facilities, availability of manpower and other infrastructural facilities like electrical power and an already established industrial environment. Industrial water shall be available from Haldia Development Authority. Water pipeline for the same is available already in the area. The nearest electrical power substation is installed at Chiranjeevpur which is around 5/6 Kms from the site. Page-10
11 Plant General Layout The plant general layout has been designed to provide a rational disposition of production facilities, material logistics facilities, auxiliary & ancillary facilities and plant utilities & services. A properly designed layout is obviously essential for operational efficiency, plant economy and saving of capital cost. In developing the plant general layout, the factors which have been taken into consideration for appropriate flow of process materials are indicated below: i) Economical and uninterrupted receipt of major incoming materials, in plant movement of molten Ferro-alloys without hindrance and minimum counterflow of materials particularly inside the production shop in which major equipment is located. ii) iii) Logical locational arrangement of the production unit with respect to supporting facilities, plant services and ancillary facilities so as to ensure minimum capital and operating costs. Compactness of the plant layout minimizing inter-plant building for processing materials as well as adequate scope for future expansion. Most important aspect while making the layout is the establishment of a correct spatial relationship between the production facilities, material logistic facilities and auxiliary & ancillary facilities. Especially the production shop must provide easy access to all other sections so as to allow unimpeded movement of input materials and manufactured products. The production facilities, it may be recalled will consist of two (2) submerged arc furnace, the utilities and auxiliary facilities will include the electrical power system, water system, compressed air system, testing laboratory, general store, etc. and the ancillary facilities will comprise administrative building, ablution block, time & gate office, etc. Taking all these aspects into consideration, an appropriate production shop layout of the plant has been developed as shown in Figure 2.0; It shows the general arrangement of the smelting shops with buildings for auxiliary facilities. Behind the furnace bay, provision has been made for a two storied building for housing the furnace transformers, control panels and space for shop office & laboratory. Page-11
12 The electrical power substation as proposed shall be utilized and provision of adding new panels, etc. will be there for future installations. RAW MATERIALS REQUIREMENT & SOURCE Based on the production envisaged, the estimated requirements of raw materials & sources are given below: Raw Materials Annual Requirement in Tonnes Source of Supply 1. Quartzite 18,144 Mines in Chattisgarh, Bankura in W.B. 2. Mill Scale/ Iron Scrap 3,,468 Local Rolling Mills, Local market 3. Coke Breeze/Coal 17,343 Durgapur Steel Plant, DPL Coking Plant at Haldia & other major steel plants 4. Electrode Paste 772 Maharashtra Carbon Ltd. Graphite India Ltd. 5. Electrode Casing 43 SAIL/TISCO 6. Manganese ore 74,230 Mines in Orissa/M.P. 7. Dolomite 6,777 Mines in North Bengal Water System There will be no process water requirement. Water will be required for cooling purposes only. Hence, the water system of the proposed plant will provide for the following usages: a) Cooling of equipment b) Human consumption for drinking, washing & sanitary needs In the proposed unit, water will be required mainly for the following: Submerged Arc Furnaces : Cooling of transformers, furnace mechanicals, viz. water cooled jacketed furnace hood, electrode holder cooling, water cooled guides, etc. Page-12
13 To minimise the requirement of cooling water, a recirculation system with replenishment by make-up water will be adopted. The recirculating routes of cooling water for the different kinds of equipment are indicated below: Equipment Submerged Arc Furnace & Air Compressor Circulation Routes : Cold Sump Equipment Cooling Tower Cold Sump Quantity of Water Requirement The quantity of water required for meeting various specific needs is given in the following Table: QUANTITIES OF WATER REQUIRED FOR MEETING SPECIFIC NEEDS A. Recirculation Water Equipment 1. Submerged Arc Furnace, Transformer Electrode Holder & other components B. Make-up Water 1. Submerged Arc Furnace & other components and air compressor Requirement of Water in M 3 /hour Drinking & Sanitary purposes Water Balance is presented in Annexure 2. For cooling of different furnace parts and transformer, three (e) nos. centrifugal pumps have been considered for the furnaces. For two (2) Nos. furnaces, two (2) nos. pumps shall be in operation having flow rate of around M 3 /hour at a pressure of 4 kg/cm.sq. When two pumps are in operation, one pump having a flow rate of around cu.m/hr. at a pressure of 4 kg./cm.sq.g. shall be kept as stand-bye for the system. The pressure rating of the above mentioned pumps have been selected in such a way that after cooling of different furnace parts & compressor, the residual pressure of the return water shall be sufficient to Page-13
14 drive it on the top of cooling tower. After getting the required degree of cooling through cooling tower, the water shall be accumulated in the cold sump for recirculation. Suitable pump room has been provided for housing the above pumps. It is envisaged that main source of water will be Haldia Development Authority. The water shall be available through a dedicated pipeline and will be taken to a underground reservoir suitably located inside the plant site. Necessary pipelines, pumps and other accessories have been considered for making this secondary water source be effective at all times for plant operation. Compressed Air System Compressed air will be required for pneumatic operation as well as for the general cleaning of various items of equipment. The major utilisation of compressed air for operating equipment in a Ferro-alloy producing plant is for pneumatic control of submerged arc furnace component, e.g. clamping of electrodes, electrode adjustment, i.e. slipping of electrode hydro-pneumatically, etc. Apart from operation of equipment compressed air will also be required for general cleaning of equipment during operation of the plant. Material Handling System The plant shall be provided with material handling system for uninterrupted supply of raw material to the furnace. Since the charge to be handled is directly proportional to the output of molten metal from the submerged arc furnaces, the furnace feeding has been designed accordingly to ensure that the raw material feeding is maintained at adequate level. The system will however, consist of the following basic equipment. 1. Vibrating screen for feeding to the belt conveyor; 2. Belt conveyor for transfer of material from raw material storage area to day bins; 3. Fabricated day bins; 4. Load cells and transfer conveyor for feeding of raw materials to skip hoist; 5. Skip hoist, transfer cars, monorails for transfer and feeding of raw material to charging bins; 6. Charging bins and chutes with flow control/regulation valves for storage & charging of mixed raw materials to the furnace. Page-14
15 The basic raw materials to be handled for production of ferro-manganese/silico-manganese are Quartzite, Mn Ore, Coke Breeze, Iron Scrap, Dolomite, etc. Bulk raw material will be handled by means of Dumper Trucks & Pay Loaders and proposed arrangement has been considered to be adequate for handling the raw material for all the furnaces. Fume Extraction/Pollution Control System In the smelting process it generates large quantities of hot fumes consisting of mainly CO 2 along with dust particles having dust concentration of 500 mg/nm 3. Fume extraction system has now become a statutory obligation in the various industries specially in a melting or smelting unit. In order to minimise the abuse of the environment prevailing in the Smelting Shop, a system has been proposed by which fumes are to be sucked through suction hoods and the hood is required to be located immediately above the fume generating zone. In the proposed plant, fume shall be generated in the submerged arc furnace so long as smelting process runs. Fumes generated shall be sucked through a hood/canopy suitably located just above the main furnace mouth and shall be carried away by means of blower through ducting system and bag filter to the chimney for discharging it to the atmosphere. The system shall comprise Hood/Canopy, Duct, Exhaust Blower, Bag Filter, Chimney and other accessories. This will contain the dust concentration to below 50 mg/nm 3 before the ultimate discharge into the atmosphere. Ancillary Facilities The ancillary facilities comprising the administrative office, ablution block, time & gate office, security goomty, weighbridge goomty, canteen, etc. are required to be provided and to be located at appropriate places to ensure proper plant operation and administration. Project Implementation It has been planned to complete the installation and commissioning of the proposed plant within 18 months of go-ahead. The construction schedule has been prepared on the basis of the delivery periods of the major items of equipment as indicated by the supplier and the volume of civil, mechanical and constructional jobs involved. Project Cost The total capital cost of the project has been estimated as Rs. 50 crores. The capital cost towards Environment Management has been estimated as Rs. 2.0 Crores. Page-15
16 ELECTROSTEEL CASTINGS LTD. MATERIAL BALANCE For Production of High Carbon Ferro Manganese: Basis: 1000 kg. Finished Product Materials to be charged into the Submerged Arc Furnace : Mn ore Coke Iron scrap 2140 kg. 500 kg. 100 kg. Total: 2740 kg. Output from the furnace : kg. solid High Carbon Ferro-manganese For Production of Silico Manganese Alloy: Basis: 1000 kg. Finished Product kg. slag mainly containing MnO, SiO 2, Al 2 O 3, FeO kg. shall be lost in gaseous phase Materials to be charged into the Submerged Arc Furnace : Mn ore Mn slag obtained rom Fe.Mn operation Coke Quartzite Iron scrap Dolomite 490 kg kg. 500 kg. 300 kg. 100 kg. 275 kg. Total : 3065 kg. Output from the Furnace : kg. solid silico manganese alloy kg. slag mainly containing MnO, SiO 2, Al 2 O 3, CaO, MgO, etc kg. shall be lost in gaseous phase.
17 For production of Ferro-silicon Basis 1000 Kg finished product Inputs : Quartzite Coke Iron turnings Total: 1915 Kg 1275 Kg 240 Kg 3430 Kg Output : 1. Liquid metal 1063 Kg 2. Slag 64 Kg 3. Gas 2057 Kg 4. Volatiles 170 Kg 5. Moisture 6. Dust in Gas 76 Kg Total: 3430 Kg
18 ELECTROSTEEL CASTINGS LTD. WATER BALANCE 1. Water flow rate required for 1x9 MVA + 1x6 MVA furnace = 500 M 3 /hr. 2. Losses of circulating water during operation of the furnace is considered as follows = 1. Evaporation : 1.53% of the flow rate 2. Cooling tower blow down : 0.51% of the flow rate 3. Drift/leakage loss : 0.5% of the flow rate Total: 2.54% Make-up water considered: 2.5% of the total flow rate.
1.3 Properties of Coal
1.3 Properties of Classification is classified into three major types namely anthracite, bituminous, and lignite. However there is no clear demarcation between them and coal is also further classified
EXTRACTION OF METALS
1 EXTRACTION OF METALS Occurrence ores of some metals are very common (iron, aluminium) others occur only in limited quantities in selected areas ores need to be purified before being reduced to the metal
How To Make Calcium Carbide
11.4 Calcium Carbide Manufacturing 11.4.1 General Calcium carbide (CaC 2 ) is manufactured by heating a lime and carbon mixture to 2000 to 2100 C (3632 to 3812 F) in an electric arc furnace. At those temperatures,
THE PRODUCTION OF REFINED FERROMANGANESE AT CATO RIDGE ALLOYS
THE PRODUCTION OF REFINED FERROMANGANESE AT CATO RIDGE ALLOYS R. Burger 1 and M. Masukawa 2 1 ASSMANG Cato Ridge Works, Eddie Hagan Drive Cato Ridge, RSA. E-mail: [email protected] 2 Mizushima Ferroalloy
Opportunity for Investment. www.afarakgroup.com
Opportunity for Investment www.afarakgroup.com 1 2013 Introducing Afarak A vertically integrated ferroalloys producer from mine to customer Supplies specialist products to steel & stainless steel industries:
SINTERING AND PELLETISATION OF INDIAN IRON ORES
SINTERING AND PELLETISATION OF INDIAN IRON ORES By SURESH KUMAR* & T.M. SRINIVASAN** 1 * Vice President, Mineral Enterprises Limited, Bangalore ** Managing Director, FerroGreen Technologies Pvt. Ltd. Bangalore
STUDY OF THE EXPLOSIONS WHICH TAKE PLACE IN THE RECOVERY BOILERS AND LD CONVERTERS DURING THE PAUSES BETWEEN CHARGES
METAL 6-556, Hradec nad Moravicí STUDY OF THE EXPLOSIONS WHICH TAKE PLACE IN THE RECOVERY BOILERS AND LD CONVERTERS DURING THE PAUSES BETWEEN CHARGES Alexandru Ivanescu, Antoaneta Ene, Lilica Ivanescu,
HAZARD RISK ASSESSMENT
HAZARD RISK ASSESSMENT Mt Grace Batchelor Magnesium Project A hazard risk assessment was undertaken to identify and assess the consequences of unplanned incidents that may pose safety, environmental risks,
Xstrata Alloys in Profile
Southern African Pyrometallurgy 2006, Edited by R.T. Jones, South African Institute of Mining and Metallurgy, Johannesburg, 5-8 March 2006 Xstrata Alloys in Profile O. Naiker and T. Riley Xstrata Alloys,
LIFE-CYCLE IMPACTS AND COSTS OF MANGANESE LOSSES AND RECOVERY DURING FERROMANGANESE PRODUCTION
LIFE-CYCLE IMPACTS AND COSTS OF MANGANESE LOSSES AND RECOVERY DURING FERROMANGANESE PRODUCTION L.A. Westfall 1, M.H. Cramer 1, J. Davourie 1, D. McGough 2 and M. Ali 1 1 Hatch Ltd., 2800 Speakman Drive,
HYBRID WAY EAF OFF GAS HEAT RECOVERY -ECORECS- MASANARI YAMAZAKI*1, YASUHIRO SATO*2, RYUTARO SEKI*3
HYBRID WAY EAF OFF GAS HEAT RECOVERY -ECORECS- BY MASANARI YAMAZAKI*1, YASUHIRO SATO*2, RYUTARO SEKI*3 SYNOPSIS JP Steel Plantech Co. has developed Hybrid system for EAF off-gas heat recovery, with EAF
SILICOMANGANESE PRODUCTION PROCESS UNDERSTANDING
SILICOMANGANESE PRODUCION PROCESS UNDERSANDING S.E. Olsen 1 and M. angstad 1 Dep. of Materials echnology, Norwegian University of Science and echnology; N-7491 rondheim, Norway. E-mail: [email protected]
This is Outokumpu Tornio Site
Investor visit, 7th October 2015 Hannu Hautala, SVP - Business Line Tornio This is Outokumpu Tornio Site October 7, 2015 1 October 7, 2015 2 We believe that all accidents are preventable. Our target is
Coal Properties, Sampling & Ash Characteristics by Rod Hatt Coal Combustion, Inc. Versailles, KY 859-873-0188
Coal Properties, Sampling & Ash Characteristics by Rod Hatt Coal Combustion, Inc. Versailles, KY 859-873-0188 Introduction The Powder River Coal is classified as sub-bituminous ranked coal. Coal rank is
FERRO SILICON OPERATION AT IMFA A CRITICAL ANALYSIS
FERRO SILICON OPERATION AT IMFA A CRITICAL ANALYSIS Dhananjaya Senapati, E.V.S. Uma Maheswar and C.R. Ray 1 Indian Metals & Ferro Alloys Limited, Therubali, District: Rayagada, Orissa, India 1 Indian Metals
Balancing chemical reaction equations (stoichiometry)
Balancing chemical reaction equations (stoichiometry) This worksheet and all related files are licensed under the Creative Commons Attribution License, version 1.0. To view a copy of this license, visit
CHAPTER 7 THE DEHYDRATION AND SWEETENING OF NATURAL GAS
CHAPTER 7 THE DEHYDRATION AND SWEETENING OF NATURAL GAS Natural gases either from natural production or storage reservoirs contain water, which condense and form solid gas hydrates to block pipeline flow
PRELIMINARY CHARACTERIZATION OF THE SAMPLES TAKEN FROM A SUBMERGED ARC FERROCHROME FURNACE DURING OPERATION
PRELIMINARY CHARACTERIZATION OF THE SAMPLES TAKEN FROM A SUBMERGED ARC FERROCHROME FURNACE DURING OPERATION J. Ollila 1, P. Niemelä 2, A. Rousu 3 and O. Mattila 3 1 Outotec Oyj, Espoo, Finland; e-mail:
Iron and Steel Manufacturing
Pollution Prevention and Abatement Handbook WORLD BANK GROUP Effective July 1998 Iron and Steel Manufacturing Industry Description and Practices Steel is manufactured by the chemical reduction of iron
Residues from aluminium dross recycling in cement
Characterisation of Mineral Wastes, Resources and Processing technologies Integrated waste management for the production of construction material WRT 177 / WR0115 Case Study: Residues from aluminium dross
Steel production. Furnace linings made from carbon and graphite are applied for the production of primary iron.
Steel production Furnace linings made from carbon and graphite are applied for the production of primary iron. Graphite electrodes and nipples (connecting pins) are applied for the production of steel.
Pellet Process - Uses and Exposures
Pellet Process - Uses and Exposures 1 PROCESS - MANUFACTURING & USES 1 1.1 Manufacturing of pellets 2 Pellets are formed from the raw materials fine ores and additives of < 0.05 mm - into 9-16 mm spheres
AMMONIA AND UREA PRODUCTION
AMMONIA AND UREA PRODUCTION Urea (NH 2 CONH 2 ) is of great importance to the agriculture industry as a nitrogen-rich fertiliser. In Kapuni, Petrochem manufacture ammonia and then convert the majority
FURNACEPHOSPHORUS AND PHOSPHORICACID PROCESS ECONOMICS PROGRAM. Report No. 52. July 1969. A private report by. the
Report No. 52 FURNACEPHOSPHORUS AND PHOSPHORICACID by GEORGE E. HADDELAND July 1969 A private report by. the PROCESS ECONOMICS PROGRAM STANFORD RESEARCH INSTITUTE MENLO PARK, CALIFORNIA CONTENTS 1 INTRODUCTION........................
M/s. D.S. Alloyd Pvt. Ltd.
PRE-FEASIBILITY REPORT FOR PROPOSED MANUFACTURING OF MANGANESE OXIDE & EXPANSION OF VARIOUS FERRO ALLOYS AT C-235, MIDC BUTIBORI, DISTRICT NAGPUR, (M.S.) M/s. D.S. Alloyd Pvt. Ltd. EIA Consultant: Pollution
John KW Hou, Ph.D. World- Wide Director, Industry Solutions Member of IBM Industry Academy IBM Corporation. José R. Favilla Jr
1 A Big Data Approach to Optimize Energy Efficiency in the Steel Industry John KW Hou, Ph.D. Manager, IBM Center of Competence, Metals IBM Corporation José R. Favilla Jr World- Wide Director, Industry
COKE PRODUCTION FOR BLAST FURNACE IRONMAKING
COKE PRODUCTION FOR BLAST FURNACE IRONMAKING By Hardarshan S. Valia, Scientist, Ispat Inland Inc INTRODUCTION A world class blast furnace operation demands the highest quality of raw materials, operation,
FACTORS AFFECTING THE REDUCIBILITY OF SINTERED CHROMITE PELLETS AND CHROMITE LUMPY ORE
FACTORS AFFECTING THE REDUCIBILITY OF SINTERED CHROMITE PELLETS AND CHROMITE LUMPY ORE T. Lintumaa, H. Krogerus and P. Jokinen 1 Outokumpu Technology, Research Center, Pori, Outokumpu Research Oy Kuparitie
Weld Cracking. An Excerpt from The Fabricators' and Erectors' Guide to Welded Steel Construction. The James F. Lincoln Arc Welding Foundation
Weld Cracking An Excerpt from The Fabricators' and Erectors' Guide to Welded Steel Construction The James F. Lincoln Arc Welding Foundation Weld Cracking Several types of discontinuities may occur in welds
THE ROLE OF METALLURGY IN ENHANCING BENEFICIATION IN THE SOUTH AFRICAN MINING INDUSTRY
THE ROLE OF METALLURGY IN ENHANCING BENEFICIATION IN THE SOUTH AFRICAN MINING INDUSTRY Marek Dworzanowski, Presidential Address, SAIMM AGM, 22 August 2013 CONTENTS Introduction Definitions Phases of metallurgical
The MIDREX Process - The world s most reliable and productive Direct Reduction Technology
The MIDREX Process - The world s most reliable and productive Direct Reduction Technology Designed for Today, Engineered for Tomorrow CONTENTS 2 THE MIDREX PROCESS 3 MIDREX DIRECT REDUCTION FLEXIBILITY
Element D Services Plumbing
Medical Vacuum and Gas PART 1 - GENERAL 1.01 OVERVIEW A. This section addresses medical vacuum, waste anesthetic gas disposal, compressed air, oxygen, nitrous oxide, nitrogen and carbon dioxide systems.
ZERO WASTE ELECTRIC ARC FURNACE (EAF) STEELMAKING CHAPARRAL STEEL COMPANY TARGET
ZERO WASTE ELECTRIC ARC FURNACE (EAF) STEELMAKING CHAPARRAL STEEL COMPANY TARGET Libor F. Rostik ChaparraI Steel Company Midlothian Texas EPA Region III Waste Minimization/Pollution Prevention Technical
CHAPTER-3: EXPERIMENTAL PROCEDURE
CHAPTER-3: EXPERIMENTAL PROCEDURE 58 3. EXPERIMENTAL PROCEDURE This chapter presents the experimental set up used to carryout characterization of the samples, granulometry studies and pellet firing studies.
Best Practice in Boiler Water Treatment
Best Practice in Boiler Water Treatment Boiler Water Treatment Part 2 Internal Treatment Objectives of Internal Water Treatment 1 To control the level of total dissolved solids (TDS) within the boiler
G8 GALILEO. Innovation with Integrity. High-End Melt-extraction Analyzer. Inert Gas Method
G8 GALILEO High-End Melt-extraction Analyzer Innovation with Integrity Inert Gas Method Determination of O, N and H The market demands Metals, minerals, and inorganic compound markets demand high-quality
EXAMPLE EXERCISE 4.1 Change of Physical State
EXAMPLE EXERCISE 4.1 Change of Physical State State the term that applies to each of the following changes of physical state: (a) Snow changes from a solid to a liquid. (b) Gasoline changes from a liquid
How much do you know about HVAC? Try testing yourself with the following questions and then take a look at the answers on the following page.
Demystifying HVAC Test Your HVAC Knowledge By Ron Prager How much do you know about HVAC? Try testing yourself with the following questions and then take a look at the answers on the following page. 1)
THE MANUFACTURE OF STEEL
THE MANUFACTURE OF STEEL Steel refers to any iron-carbon alloy, although steels usually contain other elements as well. In New Zealand steel is made by BHP NZ at Glenbrook, where about 90% of New Zealand's
Environment Impact Assessment of Thermal Power Plant for Sustainable Development
International Journal of Environmental Engineering and Management. ISSN 2231-1319, Volume 4, Number 6 (2013), pp. 567-572 Research India Publications http://www.ripublication.com/ ijeem.htm Environment
Aluminium Production. Introduction The aluminium production process. Hall-Héroult Prebake Cell Pechiney technology Inert anode
Aluminium Production Introduction The aluminium production process Hall-Héroult Prebake Cell Pechiney technology Inert anode Aluminium Production: intro Aluminium can be produced by using anodes and cathodes
TRIAL CHEMICAL CLEANING OF FOULED APH BASKETS
TRIAL CHEMICAL CLEANING OF FOULED APH BASKETS Dr. Abhay Kumar Sahay, AGM(CC OS) Bijay Manjul, AGM( Operation) Kahalgaon Boiler has three inputs Steam generator 1. WATER 2. COAL 3. AIR Burner Air preheater
RECOVERING RESOURCES FOR ALL. Integra South East Energy Recovery Facility
RECOVERING RESOURCES FOR ALL Integra South East Energy Recovery Facility Integra South East Energy Recovery Facility (ERF) is the third of its kind to be built in Hampshire and is a leading example of
ENERGY BALANCE OF A 45 MW (FERRO-) SILICON SUBMERGED ARC FURNACE
ENERGY BALANCE OF A 45 MW (FERRO-) SILICON SUBMERGED ARC FURNACE N. E. Kamfjord 1, E H. Myrhaug 2, H Tveit 2 and B. Wittgens 3 1 Norwegian University of Science and Technology, Department of Materials
HEAT RECOVERY OPTIONS FOR DRYERS AND OXIDIZERS
HEAT RECOVERY OPTIONS FOR DRYERS AND OXIDIZERS William K. Scullion, Application Engineering Leader, MEGTEC Systems, De Pere, WI Introduction Competitive pressures continuously motivate us to examine our
BEST PRACTICES TOWARDS ENERGY EFFECIENCY. UltraTech Cement Limited. (Unit -Kotputli Cement Works)
BEST PRACTICES TOWARDS ENERGY EFFECIENCY UltraTech Cement Limited. (Unit -Kotputli Cement Works) Best Practices towards Energy Efficiency 1. Selected Vertical Mills installed at Raw Mill, Cement Mills
110. PROFILE ON PRODUCTION OF GLASS BOTTLES AND TUMBLERS
0. PROFILE ON PRODUCTION OF GLASS BOTTLES AND TUMBLERS 0-2 TABLE OF CONTENTS PAGE I. SUMMARY 0-3 II. PRODUCT DESCRIPTION & APPLICATION 0-3 III. MARKET STUDY AND PLANT CAPACITY 0-4 A. MARKET STUDY 0-4 B.
Half the cost Half the carbon
Half the cost Half the carbon the world s most efficient micro-chp What is BlueGEN? The most efficient small-scale electricity generator BlueGEN uses natural gas from the grid to generate electricity within
RECOVERY AND ENERGY SAVINGS OF ALUMINUM CAN BEVERAGE CONSUMED IN GENERAL AND VOCATIONAL TECHNICAL HIGH SCHOOLS
INTERNATIONAL JOURNAL OF ELECTRONICS, MECHANICAL AND MECHATRONICS ENGINEERING Volume 1. Number.1 pp.(67-73) RECOVERY AND ENERGY SAVINGS OF ALUMINUM CAN BEVERAGE CONSUMED IN GENERAL AND VOCATIONAL TECHNICAL
Effect of Magnesium Oxide Content on Final Slag Fluidity of Blast Furnace
China Steel Technical Report, No. 21, pp. 21-28, (2008) J. S. Shiau and S. H. Liu 21 Effect of Magnesium Oxide Content on Final Slag Fluidity of Blast Furnace JIA-SHYAN SHIAU and SHIH-HSIEN LIU Steel and
BRIEF PROJECT PROFILE ON WELDING ELECTRODE MANUFACTURING. Turn key project suppliers EUREKA SYSTEMS AND ELECTRODES PVT.LTD.
BRIEF PROJECT PROFILE ON ELECTRODE MANUFACTURING Turn key project suppliers EUREKA SYSTEMS AND ELECTRODES PVT.LTD. M A C H I N E R Y D I V I S I O N 11/15A, SELVARAJAPURAM, CHINTHAMANI PUDUR COIMBATORE
How To Manage Power Usage In South Africa
ELECTRICAL ENERGY MANAGEMENT IN THE FERROALLOY BUSINESS M.S. Rennie, P.J. Brereton-Stiles and N. Singh Mintek, P/Bag X3015, Randburg, 2125, South Africa. E-mail: [email protected]; [email protected]
MELTING EFFICIENCY - F2A Energy eco-efficiency opportunities in Queensland Foundries
MELTING EFFICIENCY - F2A Energy eco-efficiency opportunities in Queensland Foundries Charge preparation, energy management and metal reduction The metal casting industry is one of Queensland s most energy-intensive
Multi-pollutant control solutions for coal based power plants
Multi-pollutant control solutions for coal based power plants By Luca Mancuso and Hans Janssen Content SOx control Wet Scrubbers Open towers Dual Flow Tray Technology Semi-Dry SDA CFB Scrubbers Dust control
Data Mining Analysis of the Relationship Between Input Variables and Hot Metal Silicon in a Blast Furnace
MASTER S THESIS 2005:241 CIV Data Mining Analysis of the Relationship Between Input Variables and Hot Metal Silicon in a Blast Furnace PIERRE WIKSTRÖM MASTER OF SCIENCE PROGRAMME Chemical Technology Luleå
Estimated emissions and CO2 savings deriving from adoption of in-place recycling techniques for road pavements
Estimated emissions and CO2 savings deriving from adoption of in-place recycling techniques for road pavements Introduction Objective: to estimate the CO2 emissions produced by road surface construction
Chapter Test A. Elements, Compounds, and Mixtures MULTIPLE CHOICE. chemically combined? MIXs2 a. element b. compound c. mixture d.
Assessment Chapter Test A Elements, Compounds, and Mixtures MULTIPLE CHOICE Write the letter of the correct answer in the space provided. 1. What is a pure substance made of two or more elements that are
Aluminium Technology & Production in Russia
L Aluminium Technology & Production in Russia Victor Mann, Deputy General Manager, s Construction Division Soderberg technology Over 80% of aluminium in Russia is manufactured on the basis of Soderberg
Name Date Class CHAPTER 1 REVIEW. Answer the following questions in the space provided.
CHAPTER 1 REVIEW Matter and Change SECTION 1 SHORT ANSWER Answer the following questions in the space provided. 1. a Technological development of a chemical product often (a) lags behind basic research
PLASMA GASIFICATION: LESSONS LEARNED AT ECOVALLEY WTE FACILITY
Proceedings of the 18th Annual North American Waste-to-Energy Conference NAWTEC18 May 11-13, 2010, Orlando, Florida, USA NAWTEC18-3515 PLASMA GASIFICATION: LESSONS LEARNED AT ECOVALLEY WTE FACILITY Ken
RECOVERING RESOURCES FOR ALL. Integra North Energy Recovery Facility
RECOVERING RESOURCES FOR ALL Integra North Energy Recovery Facility Integra North Energy Recovery Facility (ERF) was the first of its kind to be built in Hampshire and one of the leading examples of best
Lecture 35: Atmosphere in Furnaces
Lecture 35: Atmosphere in Furnaces Contents: Selection of atmosphere: Gases and their behavior: Prepared atmospheres Protective atmospheres applications Atmosphere volume requirements Atmosphere sensors
UPGRADING OF Mn / Fe RATIO OF LOW-GRADE MANGANESE ORE FOR FERROMANGANESE PRODUCTION
UPGRADING OF Mn / Fe RATIO OF LOW-GRADE MANGANESE ORE FOR FERROMANGANESE PRODUCTION V. Kivinen 1, H. Krogerus 2 and J. Daavittila 3 1 Technology Director, Outotec Oyj, Finland 2 Senior Technology Adviser,
HVAC Processes. Lecture 7
HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump
Efficiency on a large scale CFB Steam Boilers
Efficiency on a large scale CFB Steam Boilers Circulating Fluidized Bed Steam Boiler The Circulating Fluidized Bed Steam Boiler is an offering from Bosch Thermotechnology a member of the worldwide Bosch
Corrosivity of Water Supplies
WD-DWGB-3-4 2009 Corrosivity of Water Supplies What is meant by Corrosivity? Corrosive water can be defined as a condition of water quality which will dissolve metals from metallic plumbing at an excessive
How Ground/Water Source Heat Pumps Work
How Ground/Water Source s Work Steve Kavanaugh, Professor Emeritus of Mechanical Engineering, University of Alabama Ground Source s (a.k.a. Geothermal s) are becoming more common as the costs of energy
understanding medium frequency induction melting furnace and its components
understanding medium frequency induction melting furnace and its components 9 Spruce Street, Jersey City, NJ 07306 USA [email protected] INDUCTION MELTING FURNACE AND ITS COMPONENTS The purpose
dryon Processing Technology Drying / cooling in outstanding quality we process the future
dryon Drying / cooling in outstanding quality we process the future Processing Technology task The basic process of drying is a necessary step in all sectors of industry. Drying has to be performed for
THE NWF WATER PURIFICATION PROCESS FRESH WATER IN A NATURAL WAY. Esko Meloni Ferroplan Oy
THE NWF WATER PURIFICATION PROCESS FRESH WATER IN A NATURAL WAY Esko Meloni Ferroplan Oy 1 The NWF Water Purification Process: list of contents 1. NWF biological purification of groundwater Iron and manganese
Swallow Street recycling facts and figures in partnership with Bywaters
Regent Street Direct Swallow Street recycling facts and figures in partnership with Bywaters 2013 Swallow Street produced 76 tonnes of cardboard Mission Recycling Ltd: Paper and Cardboard Paper of all
Total Plant Monitoring for an Integrated Steel Plant
Total Plant Monitoring for an Integrated Steel Plant J u l y 2013 TABLE OF CONTENTS Abstract... 3 Abbreviations... 4 Steel Manufacturing and Automation... 5 Steel Plant Operations... 5 Automation Systems
Prepared and Submitted by
Technical Feasibility Study Report of Proposed Sulfuric Acid and Phosphoric Acid Unloading Facilities, Acid Storage Tanks at the existing Wharf and Acid Transfer Pipeline Falling within the CRZ area &
Yu. F. Vasyuchkov*, M. Yu. Bykova* NEW TECHNOLOGY OF GAS EXTRACTION ON THE BASE OF A COAL TO A HYDROGEN TRANSFER
WIERTNICTWO NAFTA GAZ TOM 28 ZESZYT 1 2 2011 Yu. F. Vasyuchkov*, M. Yu. Bykova* NEW TECHNOLOGY OF GAS EXTRACTION ON THE BASE OF A COAL TO A HYDROGEN TRANSFER In modern period the useful extraction of energy
Subpart 1. Installation. All plumbing systems must be. installed and tested according to this chapter and chapter 4715,
4658.4500 PLUMBING SYSTEMS; NEW CONSTRUCTION. Subpart 1. Installation. All plumbing systems must be installed and tested according to this chapter and chapter 4715, the Minnesota Plumbing Code. Subp. 2.
Module 5: Combustion Technology. Lecture 33: Combustion air calculation
1 P age Module 5: Combustion Technology Lecture 33: Combustion air calculation 2 P age Keywords: Heat of combustion, stoichiometric air, excess air, natural gas combustion Combustion air calculation The
Performance of the Boiler and To Improving the Boiler Efficiency Using Cfd Modeling
IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) e-issn: 2278-1684,p-ISSN: 2320-334X, Volume 8, Issue 6 (Sep. - Oct. 2013), PP 25-29 Performance of the Boiler and To Improving the Boiler Efficiency
Wearpipe. Induction Hardened Chromium Carbide Overlay Ceramic Lined
Wearpipe Induction Hardened Chromium Carbide Overlay Ceramic Lined WEAR PIPE OPTIONS St. Lawrence Steel is a provider of wear resistant solutions serving heavy industry since 1955. We are a leader in supplying
Cambridge International Examinations Cambridge International General Certificate of Secondary Education
Cambridge International Examinations Cambridge International General Certificate of Secondary Education *0123456789* CHEMISTRY 0620/03 Paper 3 Theory (Core) For Examination from 2016 SPECIMEN PAPER 1 hour
Microwave absorbing tiles:
On the basis of the results obtained from the first project activities, the grinding conditions on a larger scale were determined. As regards the sintering, an adjustment has been made to the roller furnaces
In this experiment, we will use three properties to identify a liquid substance: solubility, density and boiling point..
Identification of a Substance by Physical Properties 2009 by David A. Katz. All rights reserved. Permission for academic use provided the original copyright is included Every substance has a unique set
Optimization of Steel and Methanol Production in an Integrated
Optimization of Steel and Methanol Production in an Integrated H. Ghanbari, H. Helle, M. Helle, F. Pettersson and H. Saxen Åbo Akademi University Heat Engineering Laboratory Åbo / Turku, Finland tel. +358
Nonrenewable Natural Gas. Natural Gas Basics. How Was Natural Gas Formed?
Did You Know? Because natural gas is colorless, odorless, and tasteless, mercaptan (a chemical that smells like sulfur) is added before distribution, to give it a distinct unpleasant odor (it smells like
Energy Efficiency HOSPITALITY. www.energia.ie
Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real
POLYCITY. Technical measures and experiences at a 6 MW cogeneration plant with wood chip furnace POLYCITY
Technical measures and experiences at a 6 MW cogeneration plant with wood chip furnace Content 1. Technical overview cogeneration plant and heating network 2. Investment of the facility 3. Experiences
DEVELOPMENTS IN THE DESIGN AND CONSTRUCTION OF DC ARC SMELTING FURNACES
DEVELOPMENTS IN THE DESIGN AND CONSTRUCTION OF DC ARC SMELTING FURNACES F.P. Greyling, W. Greyling and F.I. de Waal GLPS, Box 2360, Middelburg 1050, South Africa; [email protected] ABSTRACT The aspect of
What are the controls for calcium carbonate distribution in marine sediments?
Lecture 14 Marine Sediments (1) The CCD is: (a) the depth at which no carbonate secreting organisms can live (b) the depth at which seawater is supersaturated with respect to calcite (c) the depth at which
The soot and scale problems
Dr. Albrecht Kaupp Page 1 The soot and scale problems Issue Soot and scale do not only increase energy consumption but are as well a major cause of tube failure. Learning Objectives Understanding the implications
Recommendations Regarding the Handling of Norit GL 50 in Flue Gas Clean up Systems
Technical Bulletin Gas & Air Recommendations Regarding the Handling of Norit GL 50 in Flue Gas Clean up Systems 1. Introduction Norit GL 50 is a powdered activated carbon widely used for the removal of
AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries
AIR CONDITIONING EFFICIENCY F8 Energy eco-efficiency opportunities in Queensland Foundries Hot tips and cool ideas to save energy and money! Air conditioning units or systems are often used by foundries
TOP 10 NOISE CONTROL TECHNIQUES
TOP 10 NOISE CONTROL TECHNIQUES The following are 10 simple noise control techniques that have wide application across the whole of industry. In many cases, they will produce substantial noise reductions
2 MATTER. 2.1 Physical and Chemical Properties and Changes
2 MATTER Matter is the material of which the universe is composed. It has two characteristics: It has mass; and It occupies space (i.e., it has a volume). Matter can be found in three generic states: Solid;
A guide to volume measurement solutions for the. Mining Industry. Changing the market from level to volume
A guide to volume measurement solutions for the Mining Industry 1 Changing the market from level to volume Potash Production 2 Changing the market from level to volume Potash Production Potash Production
HEAVY-DUTY HAND CUTTING TORCHES AND ACCESSORIES. Page 1 Version no.: V0-090902
Page 1 HEAVY-DUTY HAND CUTTING TORCHES AND ACCESSORIES Page 2 Heavy-Duty Hand Cutting Torch HCT 663: With lever-operated valve for cutting oxygen, for cutting duties involving high thermal loads on slabs,
BOILER OPERATORS HANDBOOK
BOILER OPERATORS HANDBOOK prepared by National Industrial Fuel Efficiency Service Ltd. Graham & Trotman First published in 1959 as the New Stoker's Manual and in 1969 as The Boiler Operators Handbook This
Chem 1101. Highlights of last lecture. This lecture. Australian Mining Sites. A/Prof Sébastien Perrier. Metallurgy: (Extracting metal from ore)
Chem 111 A/Prof Sébastien Perrier Room: 351 Phone: 9351-3366 Email: [email protected] Unless otherwise stated, all images in this file have been reproduced from: Blackman, Bottle, Schmid, Mocerino
Igneous Geochemistry. What is magma? What is polymerization? Average compositions (% by weight) and liquidus temperatures of different magmas
1 Igneous Geochemistry What is magma phases, compositions, properties Major igneous processes Making magma how and where Major-element variations Classification using a whole-rock analysis Fractional crystallization
