1 Attachment M Explore IRP Change Control Process 1.0 Purpose This project is a joint effort between The Michigan Department of State and Explore Information Services, LLC for the implementation of an IRP system per RFP # 071I issued by the State of Michigan. 2.0 Approach The purpose of this plan is to formalize a process that: 1. Ensures all changes to the project and application are reviewed and approved in advance. 2. Ensures all changes are coordinated across the entire project. 3. Ensures all stakeholders are notified of approved changes. 4. Details the methodology of application change management which includes the entire change life cycle (change request, change design, implementation and acceptance). The goals of this change management plan dealing with the deliverables for the lifecycle of this project: 1. Give due consideration to all requests for change. 2. Identify, define, evaluate, approve, and track changes through to completion. 3. Modify project plans to reflect the impact of the changes requested. 4. Bring the appropriate parties (depending on the nature of the requested change) into the discussion. 5. Negotiate changes and communicate them to all affected parties. 6. The project team will review the status of change requests on a weekly basis. 7. The decision will either be that a change request is required or an alternate method of solving the issue will be agreed on. 3.0 Roles and Responsibilities All Michigan IRP project team members and stakeholders have a role in change management throughout the lifecycle of the project. However, primary responsibility for managing the change management process resides with Explore s IRP Project Manager (Nikki Benz) and Michigan s IRP Project Manager (Joe Gawle). Changes with financial impact will be reviewed by the appropriate approval authorities within Explore and Michigan MDOS and jointly coordinated by both project managers. Explore Information Services, LLC 1
2 An overview of key stakeholders for the change management process is provided below: 4.0 Process The change management process occurs in several steps: 1. Initiation of a Change Request. Any Michigan MDOS team member can submit a written change request to the Michigan MDOS Project Manager (see appendix one for example of Change Request Form). Explore Information Services, LLC 2
3 2. Change Request Review. The Michigan MDOS IRP project team reviews for approval. 3. Change Request Submission. If approved, the Michigan MDOS IRP project manager submits the request to the Explore IRP project manager. Note, for complex change requests the process will follow all steps. For simpler change requests we can often agree to proceed directly to step Initial Change Request Evaluation. Explore will perform an analysis and impact assessment of the change request and submit an impact statement to the Michigan MDOS IRP project manager. a. Explore s goal is to respond to all change requests within 5 working days unless otherwise agreed to. b. Michigan MDOS staff may be required to be involved in the evaluation of the change request. c. Impact will be a high level estimate, often giving a range of cost and/ or schedule impact (i.e. 2-3 weeks schedule or hours) 5. Change Request Acceptance, Deferral or Rejection. Michigan will review the initial impact estimates from Explore and accept, defer or reject the change request within 5 working days unless otherwise agreed. a. If accepted, the change request will be forwarded back to Explore for finalizing the impact with a detailed estimate. b. If deferred, the change request will be put on an enhancement list for later consideration. c. If rejected, the change request will no longer be considered. 6. Detailed Change Request Evaluation. Explore will perform a detailed analysis and impact assessment of the change request and submit detailed estimates to the Michigan MDOS IRP project manager. a. Explore s goal is to respond to all change requests within 5 working days unless otherwise agreed to. b. Michigan MDOS staff may be required to be involved in the evaluation of the change request. c. Impact will be narrowed down to an estimate that can be evaluated for approval. 7. Change Request Acceptance, Deferral or Rejection. Michigan will review the detailed impact from Explore and accept, defer or reject the change request within 5 working days unless otherwise agreed. a. If accepted, the change request will be signed b. If deferred, the change request will be put on an enhancement list for later consideration. c. If rejected, the change request will no longer be considered. 8. Change Request Communication. The Michigan MDOS IRP project manager and Explore IRP project manager will communicate the disposition of change requests. Explore Information Services, LLC 3
4 4.1 Change Management Tracking & Reporting Storage: Each respective project manager will ensure that change request documents are stored in their respective project directories at Michigan and at Explore. Change Control Logs Updated: The change request document history will be continuously updated in the change control logs throughout the change management process. Weekly Status Report: The weekly status report contains a section listing all the change requests and their respective status. Change Request Log: A change request log of all open, pending and closed change requests will be kept and updated within a collaborative tool such as Excel or Tracker. 4.2 Change Request Nomenclature The name of the change request document will be MI IRP_CRxxx where xxx is the change request ID number. The ID number will be assigned by the Michigan MDOS IRP project manager upon initial receipt or creation. Explore Information Services, LLC 4
5 Appendix One Change Control Form PROJECT CHANGE REQUEST FORM Project Name: Michigan IRP (RFP #071I ) Tracking # 001 Prepared by: Date 1 Requestor Information Area of Change: (check all that apply) Application Scope Budget Schedule Quality Proposed Change Description and References: Provide information below concerning the requested change. Description: Justification: Attachments: Impact of Not Implementing Proposed Change: Alternatives Considered: Yes/no Alternative: Date Submitted for review CR Log Updated? 2 Initial Decision to Proceed with Change Request by MDOS Review Date: Review Comments: Action Signature(s) Approved for Initial Analysis Rejected Deferred Until CR Log Updated: Explore Information Services, LLC 5
6 3 Initial Impact Analysis by Explore Submission Date Configuration Items Affected Cost / Schedule Impact Analysis Required? (check one) Yes No Impact on Cost: Impact on Schedule: Impact on Resources: Risk associated with implementing the change: Risk associated with not implementing the change: Alternative Solution: Date Sent back to MDOS: 4 Evaluation of Explore s Initial Analysis by MDOS Review Date: Review Comments: Action Signature(s) Approved for Final Analysis Rejected Deferred Until CR Log Updated: 5 Final Impact Analysis by Explore Specific Requirements Definition: Data Final Analysis Request Received by Explore Cost / Schedule Impact Analysis Required? Yes No Impact on Cost: Impact on Schedule: Impact on Resources: Risk associated with implementing the change: Risk associated with not Explore Information Services, LLC 6
7 5 Final Impact Analysis by Explore implementing the change: Date Sent back to MDOS: 6 Evaluation of Explore s Final Analysis by MDOS Date Received Date Reviewed Final Recommendation Accepted Deferred Rejected Comments CR Log Updated? 7 Approval Signatures The signatures below indicate an approval for proceeding with development and implementation of the change request as indicated above. Name Title Signature Date Explore Information Services, LLC 7
PROJECT SCOPE CHANGE MANAGEMENT PLAN
PROJECT SCOPE CHANGE MANAGEMENT PLAN Clark County School District Report date: June 28, 2013 Objectives: Change Management Guidelines Roles and Responsibilities Change Management Process 2 Table of Contents
Process Improvement Plan
Doc ID: Date: Revision: Status: Abstract This document describes the process improvement plan for Company XXX. Approvals Approvals. Signed. Date. Author Page 2 of 19 Sample Process Improvement Plan.doc
RIVERSIDE SCHOOL DISTRICT NO. 2 FIXED ASSETS PROCEDURES MANUAL
RIVERSIDE SCHOOL DISTRICT NO. 2 FIXED ASSETS PROCEDURES MANUAL FIXED ASSETS ACQUISITION PROCESS The fixed assets acquisition process is responsible for the proper recording and distributing of any fixed
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
Change Management Procedure For Increase Bandwidth to University Buildings Project
Change Management Procedure For Increase Bandwidth to University Buildings Project Version number 1.0 Draft as of 4/11/2011 Printed on 7/1/2011 Author William M. Jones Owner William M. Jones Change Management
CHANGE MANAGEMENT PLAN TEMPLATE
CHANGE MANAGEMENT PLAN TEMPLATE This template allows a project manager to control, manage and monitor change requests that occur throughout the life of a project. This plan defines who has the authority
The Signalling Programme GSM-R Handheld Appendix 3, Attachment 1 Change Order Template
The Signalling Programme GSM-R Handheld Appendix 3, Attachment 1 Change Order Template Banedanmark Signalling Programme Amerika Plads 15 DK-2100 Copenhagen Ø Denmark Author: The Signalling Programme GSM-R
Title: DISASTER RECOVERY/ MAJOR OUTAGE COMMUNICATION PLAN
POLICY: This policy is intended to address organizational wide communication executed during a or major IS service outage. When a disaster occurs or when any critical system/infrastructure component is
Chapter 3. Adjusting the accounts. Appendix 3A: An alternative method of recording deferrals
1 Chapter 3 Adjusting the accounts Appendix 3A: An alternative method of recording deferrals 2 Learning objectives 1. Prepare adjusting entries for prepaid expenses originally recorded in an expense account
Change Management Plan Template
Change Management Plan Template Project Name: U.S. Department of Housing and Urban Development October, 2010 Change Management Plan Template (V1.0) Notes to the Author [This document is a template of a
Accepting your offer using eapplication
Accepting your offer using eapplication The University of Tasmania will notify you by email if you have received an offer of a place in a course. Alternatively, you can visit eapplication at any time to
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
Request Submission Confirmation Email
Request Submission Confirmation Email Email Subject: [Request Title] Request Confirmation Request Confirmation Thank you for your request. We ll send a confirmation once your request has been reviewed
1200 Project Control System Procedures
Control System Manual Jefferson Science Associates, LLC 1200 Control System Procedures 1200 Control System Procedures Control System Manual Revision 7-102 - Control System Manual PCS-01 Schedule Planning
Applicant Instructions
KSDE Online Application Instructions Step 1 Register for a Login Applicant Instructions Before you can submit your application, you must request a user name and password. To register, do the following:
GIF: CSPO-GIF-721 Status: Pending CB P Change Control Board (CCB) Review. Title: CSPO GIF 721 (ACT GIF 721) Proxy Trade Account Owner Access
Great Idea Form Requirement Summary GIF: CSPO-GIF-721 Status: Pending CB P Change Control Board (CCB) Review Submit Date: May 23, 2008 Title: CSPO GIF 721 (ACT GIF 721) Proxy Trade Account Owner Access
Certification Practice Statement
FernUniversität in Hagen: Certification Authority (CA) Certification Practice Statement VERSION 1.1 Ralph Knoche 18.12.2009 Contents 1. Introduction... 4 1.1. Overview... 4 1.2. Scope of the Certification
CDX Fuels Programs Registration User Guide for Responsible Corporate Officers. Version 3.02
CDX Fuels Programs Registration User Guide for Responsible Corporate Officers Version 3.02 CDX Fuels Programs Registration User Guide for Responsible Corporate Officers Version 3.02 Compliance Division
How To Approve a Change Request (CR) Using BMC Remedy Change Management System
How To Approve a Change Request (CR) Using BMC Remedy Change Management System There are three ways that you can approve a Change Request. - Approving via the Email Interface - Approving via the Remedy
THE GENESEE/SHIAWASSEE WORKFORCE DEVELOPMENT BOARD REQUEST FOR QUOTES FOR COMMERCIAL INSURANCE FOR THE PERIOD 2012-2015
THE GENESEE/SHIAWASSEE WORKFORCE DEVELOPMENT BOARD REQUEST FOR QUOTES FOR COMMERCIAL INSURANCE FOR THE PERIOD 2012-2015 QUOTE SHOULD BE SENT TO: Commercial Insurance Genesee/Shiawassee Michigan Works!
Attachment 1. PGW IS expects to use the Demand Management and Project Prioritization tools and methodologies to:
Attachment 1 1. Introduction 1.1 Overview Philadelphia Gas Works (PGW) has used Microsoft Project and Project Server to manage Information Services (IS) Projects since 2006. In 2014, PGW upgraded its Project
A Guide to the British Academy Electronic Submission System (e-gap2)
INTERNAL USER GUIDE A Guide to the British Academy Electronic Submission System (e-gap2) A Quick Guide for Applicants applying for funding using the e-gap2 System The British Academy web page: http://www.britac.ac.uk/
DIRECTIVE NUMBER: 141.03.04.001 v2.0. SUBJECT: Correctional Integration Systems Change Management Plan
DEPARTMENT OF CORRECTION SUPPORT Management Services DIRECTIVE NUMBER: SUBJECT: Correctional Integration Systems Change PAGE NUMBER: 1 of 10 Adopted: 12-15-03 01.00.00. POLICY OF THE DEPARTMENT It is the
Covered Entities Guide for Public Users. Registering a Contract Pharmacy
Registering a Contract Pharmacy Major Sections in This Guide: To jump to a specific section in this guide, click one of these links: Searching for a Covered Entity (page 4) Terminating an Existing Contract
1. Exhibit A: Fee/Cost proposal is missing from the copy I have. Would you please forward one to me?
ADDENDUM NUMBER: 1 THE MUNICIPAL HOUSING AUTHORITY FOR THE CITY OF YONKERS ADDENDUM TO REQUEST FOR PROPOSAL THE MUNICIPAL HOUSING AUTHORITY FOR THE CITY OF YONKERS 1511 CENTRAL PARK AVENUE CONTRACT: Request
Cleveland County Emergency Medical Services. PO Box 1210. Shelby, NC 28151 704-484-4984. Request for Proposal. For. Debt Collection Agency Services
Cleveland County Emergency Medical Services PO Box 1210 Shelby, NC 28151 704-484-4984 Request for Proposal For Debt Collection Agency Services Proposals Must Be Submitted by July 16, 2013 Issue Date: June
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE
PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution
Request for Proposals IT INFRASTRUCTURE MODERNIZATION
Request for Proposals IT INFRASTRUCTURE MODERNIZATION Deadline to Submit Questions for Response: March 25, 2015 by 4:00 pm Deadline for Proposal Submissions: March 27, 2015 by 4:00 pm REQUEST FOR PROPOSALS
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
Change Request Process Overview
Industry Best Practices Process Overview by Garth Wilcox This white paper outlines a process for requesting and managing changes to an application during the product development cycle. It also discusses
Electronic Medical Record (EMR) Request for Proposal (RFP)
Electronic Medical Record (EMR) Request for Proposal (RFP) SAMPLE Proposal Due: [INSERT DESIRED DUE DATE] Table of Contents SECTION 1 RFP INFORMATION... 2 I. Introduction... 2 A. Purpose and Background...
Meaningful Use: Registration & Attestation Eligible Professionals
Meaningful Use: Registration & Attestation Eligible Professionals Meaningful Use Webinar Overview Registration & Attestation: Review Registration Requirements Step by Step Instructional: EHR Incentive
LMI Aerospace PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012
PROJECT MANAGEMENT PLAN ACCESS REQUEST PROCESS IMPROVEMENT FEBRUARY 7, 2012 TABLE OF CONTENTS INTRODUCTION... 2 PROJECT MANAGEMENT APPROACH... 2 PROJECT SCOPE... 2 MILESTONE LIST... 2 SCHEDULE BASELINE
Request for Proposal Implementation Agents of Health Information Technology: Behavioral Health, Primary Care, and other Specialty Healthcare Providers
Request for Proposal Implementation Agents of Health Information Technology: Behavioral Health, Primary Care, and other Specialty Healthcare Providers ISSUE DATE: April 26 th, 2013 RESPONSE DUE DATE: May
[name of project] Service Level Agreement
[name of project] Service Level Agreement Policies and Procedures Posting: Nov.2008 Rev# xxx CIO Sign-Off: Approved and Reviewed By: Date: Document ID: SLA Revision 001 Authors: Disclaimer: Document sign-off
HENRY FORD HEALTH SYSTEM 2015 Nurse Tuition Funding Program Application Application Due September 14, 2015 PLEASE PRINT CLEARLY. (Last) (First) (M.I.
HENRY FORD HEALTH SYSTEM 2015 Nurse Tuition Funding Program Application PLEASE PRINT CLEARLY PERSONAL DATA: Name Address (Last) (First) (M.I.) (Street) HFHS Email Address (City) (State) (Zip Code) Telephone
Software and Hardware Configuration Management
DOWNLOADED AND/OR HARD COPY UNCONTROLLED Verify that this is the correct version before use. AUTHORITY DATE Jeffrey Northey (original signature on file) IMS Manager 07/09/2014 Doug Dorrer (original signature
Release Management Policy Aspen Marketing Services Version 1.1
Release Management Policy Version 1.1 John Toso 5/10/2010 2 Contents Release Management Policy Overview:... 3 Critical Success Factors... 3 Service Level Management (SLM)... 4 Key Performance Indicators:...
REQUEST FOR PROPOSAL (RFP)
REQUEST FOR PROPOSAL (RFP) Subject: Due Date/Time: Submit To: Financial Management & Utility Billing Software March 28, 201412:00 pm Eastern Standard Time Chris Wilson Village of Beverly Hills 18500 W
Manager s Portal Tools Recruiting Tab. Version 3.0 10/27/09
Manager s Portal Tools Recruiting Tab Version 3.0 10/27/09 Table of Contents Section Page Access PeopleSoft 3 Log In 4 Manager s Portal Tabs 5 Recruiting Tab 6 Position Request Form (PRF) 7 PRF Fields
Change Management in Projects
Change Management in Projects Overview About Change Management The Challenge: Manage change will remaining responsive to customer needs. You cannot hope to manage change if you have not done a good job
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
EDI Enrollment Status Messages and Descriptions
EDI Enrollment Status Messages and Descriptions APPROVALS Approved Claims Approved Remits Approved - Claims/Remits Approved Provider Approved DDE/PPTN Approved -New vendor Approved - Production Completed
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
REQUEST FOR PROPOSAL SCHOOL PHOTOGRAPHY SERVICES
REQUEST FOR PROPOSAL SCHOOL PHOTOGRAPHY SERVICES Enclosed please find a Request for Proposal for Manchester Community Schools school photography services. The RFP has eight sections: I. Introduction II.
Leverage Your Procurement Workflows in Release 12. Cal Kondratiuk O2Works, LLC
Leverage Your Procurement Workflows in Release 12 Cal Kondratiuk O2Works, LLC Learning Objectives After this presentation, you will be able to: Understand workflows in Advanced Procurement Analyze and
Top 10 Tips to Using a Service Catalogue
ARMED AND EXTREMELY DANGEROUS SERVICE CATALOGUE WEBINAR Karen Ferris Macanta Consulting Outline What is a Service Catalogue and what it is not Benefits Where to start Approach Static service catalogue
Electronic Claims Submission. The Future of Dental Claims
Electronic Claims Submission The Future of Dental Claims 1 Table of Contents Introduction 2 Why Submit Electronically 3 Getting Started 4 Technical Requirements 4 Submitting Electronic Claims 5 Special
Conflict of Interest Electronic Document Quick Reference Guide
Conflict of Interest Electronic Document Quick Reference Guide The following quick reference provides guidance for using the Electronic Document Signature (EDS) system for the Conflict of Interest (COI)
Minnesota Power PRE QUALIFICATION QUESTIONNAIRE. Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant
Minnesota Power PRE QUALIFICATION QUESTIONNAIRE Engineering, Procurement and Construction of a 10 MW Solar PV Power Plant December 1, 2014 CONTRACTOR s NAME: Project Description: Minnesota Power is developing,
Managing Submissions via ExpressO: A Guide for Law Review Editors
: A Guide for Law Review Editors Table of Contents List of Figures... 3 Welcome to ExpressO... 4 Contacting bepress Consulting Services... 4 Accessing ExpressO... 5 Editorial Privileges... 5 Editor Tools:
UC MERCED PERFORMANCE APPRAISAL AND DEVELOPMENT PLAN
Employee Name: Payroll Title: Bargaining Unit: Percent Appointment: Employee ID: Review Period: Department: Length of time in this position: Supervisor s Name: Supervised for entire review period? If not
<name of project> Software Project Management Plan
The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor
Part 2.13: Change and Baseline Management
PUBLIC IMO_PRO_0039 Market Manual 2: Market Administration Part 2.13: Change and Baseline Management Issue 3.0 Public This document describes the Market Place Change Management and Market Design Baseline
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW)
MICHIGAN DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET UCC and CPC MDOS Letters to FileNet PROJECT MANAGER STATEMENT OF WORK (SOW) A Pre-Qualification Program was developed to provide a mechanism for
FIPS 201 Evaluation Program Development - Configuration Management Plan
FIPS 201 Evaluation Program Development - Configuration Management Plan Version 1.0.0 February 28, 2006 Document History Status Version Date Comment Audience Draft 0.0.1 02/01/06 Document creation. Limited
Statement of Work. Systems Center Configuration Manager. Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.
Statement of Work Systems Center Configuration Manager Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.1 Released Prepared by Dom Vila Program Manager [email protected]
NMSU Online Staff Evaluation User Guide for https://evaluation.nmsu.edu/
NMSU Online Staff Evaluation User Guide for https://evaluation.nmsu.edu/ This user guide provides instructions for using the Exempt Staff and Nonexempt Staff Evaluation Web Application, from now on also
Chris Day, Acting Director of IT Services C Day. Configuration Manager Change Manager Change Assessors Change Implementers
Standard Operating Procedures (SOP) for: Configuration Management and Change Control SOP Number: DG25 Version Number: 1 Effective Date: 14/07/2014 Review Date: 14/07/2015 Author: Reviewer: Authorisation:
Project Management Guidelines
Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.
SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK
Office of Safety and Mission Assurance NASA-GB-9503 SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK AUGUST 1995 National Aeronautics and Space Administration Washington, D.C. 20546 PREFACE The growth in cost
SIS Board GRANT APPLICATION FORM
SIS Board GRANT APPLICATION FORM Received on: Criteria Check Completed by: Application Number: Submitted to Board on: Agenda Item : Finance Decision: FOR OFFICE USE ONLY Meeting Date: 1. Introduction This
How to Apply for an NCAA Participant Approval for Operators and Coaches
How to Apply for an NCAA Participant Approval for Operators and Coaches Go to NCAA Participant Approval Process (https://enterprise.fadv.com/pub/l/prospects/ncaa/events_and_camps) If you need to apply
Town of Brookfield, Connecticut Municipal Employee Pension Plan
Town of Brookfield, Connecticut Municipal Employee Pension Plan Request for Proposal Defined Contribution, Defined Benefit and OPEB Plan Administration October 9, 2015 1 Town of Brookfield, Connecticut
HomePath Online Offers Guide for Selling Agents
HomePath Online Offers Guide for Selling Agents The guide is designed to assist Fannie Mae Selling Agents using the HomePath Online Offers program. The HomePath Online Offers pilot is designed for Fannie
City of Winooski. Request for Proposals Department of Public Works ASSET MANAGEMENT SOFTWARE, IMPLEMENTATION AND TRAINING
City of Winooski Request for Proposals Department of Public Works ASSET MANAGEMENT SOFTWARE, IMPLEMENTATION AND TRAINING Issued: February 29, 2016 Deadline for Submissions: 4:00 p.m., March 25, 2016 INTRODUCTION
Redlined BSCP71 text for CP1430 Clarification to the ECVA/MVRN processes
Redlined BSCP71 text for CP1430 Clarification to the ECVA/MVRN processes This CP proposes changes to Sections 2.2, 3.11, 3.12, 4.6, and 4.12 of BSCP71. We have redlined these changes against Version 13.0.
CHG-11-G-001 Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 N/A. Edition workflows and process integrations?
Purpose: [C]ontrol the lifecycle of all changes, enabling beneficial changes to be made with minimum disruption to IT services. (ST 4.2.1) Activities include: Assessing the impact of business change on
Standard Operating Procedure
Standard Operating Procedure IT System Certification & Accreditation Process For Effective Date: 20080707 Expiration Date: 20110707 Responsible Office: Office of the Chief Information Officer Document
Information Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
City of Pinellas Park, FL ERP Project (RFP 13/025)
City of Pinellas Park, FL ERP Project (RFP 13/025) Vendor Questions and Responses City Initiated Clarification Items 1. Vendors should ensure to download a updated version of the RFP 13-025 - ERP PROJECT
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM W Form 1A, incorporated by reference in Florida Administrative Code Rule 60FF1-5.002 Rural County Grants, E911 Rural County Grant Application, effective
Tel: Fax: [Project Name] [Sub-Project, phase, etc.]
[Company Name] [Company Address] Tel: Fax: [Company Phone] [Company Fax] [Company E-mail] [Ref. number] [Author] Change Management Plan [Sub-Project, phase, etc.] The project change management plan is
OUTAGAMIE COUNTY REQUEST FOR INFORMATION / PROPOSAL FOR ENTERPRISE BACKUP SOLUTION FOR MIS DEPARTMENT
OUTAGAMIE COUNTY REQUEST FOR INFORMATION / PROPOSAL FOR ENTERPRISE BACKUP SOLUTION FOR MIS DEPARTMENT DUE BY: April 10, 2012 ADMINISTRATIVE INFORMATION 1.0 Introduction and Background The Outagamie County
CONFIGURATION MANAGEMENT PLAN
CONFIGURATION MANAGEMENT PLAN Integrated Procurement System U.S. Election Commission i CONFIGURATION MANAGEMENT PLAN TABLE OF CONTENTS Page # 1.0 CONFIGURATION CONTROL...3 1.1 Change Control Board (CCB)...3
Superconducting Magnet Division
Magnet Division Specification Specification Number: SMD-MAG-1001 Superconducting Magnet Division Revision: A Procedure for Preparation and Processing of ECR/ECN Prepared by: Design Group Supervisor: Production
IT Project: System Implementation Project Template Description
2929 Campus Drive Suite 250 IT Project: System Implementation Project Template Description Table of Contents Introduction... 2 Project Phases... 3 Initiation & Requirements Gathering Milestone... 3 Initiation
REQUEST FOR PROPOSAL #2016-001
REQUEST FOR PROPOSAL #2016-001 Audit Services for REGIONAL TRANSIT AUTHORITY OF SOUTHEAST MICHIGAN 1001 Woodward Ave., Suite 1400 Detroit, MI 48226 SECTION I. GENERAL CONDITIONS AND PROVISIONS A. Objective
Department of the Interior Infrastructure Services Division
Department of the Interior Infrastructure Services Division Standard Operating Procedure Web Filter Exception Request Process May 20, 2014 WFER SOP Final Version 1.4 Page 1 of 10 Table of Contents 1. Purpose...
Installation and Operational Qualification Protocol (Reference: SOP )
Project Name Equipment Process Line/Location Project Number Serial Number Model Number Protocol number WRITTEN BY: REVIEWED BY: Position APPROVAL TO EXECUTE: Position: PROTOCOL COMPLETION APPROVAL: Position:
Frequently Asked Questions
Frequently Asked Questions Q1: Which type of Digital Signature is required for Registration? Whether Encryption Certificate is also required? A: As a legal requirement, Class3 certificate (preferably with
Access Online Cardholder Transaction Approval Training
Access Online Cardholder Transaction Approval Training The Website is https://access.usbank.com 1 Contents Introduction.3 Cardholder Transaction Approval.5 View Transactions... 6 Reallocate a Transaction.....11
Corporate Purchasing. Manual: Organizational Approved By: President & C.E.O. Section: Finance Original Date Issued: March 2011
Corporate Purchasing Manual: Organizational Approved By: President & C.E.O. Section: Finance Original Date Issued: March 2011 Reviewed/Revised Date: Revised Reviewed December 2011 PREAMBLE The Pembroke
Request for Proposal. Contract Management Software
Request for Proposal Contract Management Software Ogden City Information Technology Division RETURN TO: Ogden City Purchasing Agent 2549 Washington Blvd., Suite 510 Ogden, Utah 84401 Attn: Sandy Poll 1
REQUEST FOR PROPOSAL FOR RADIO/INTERNET RADIO ADVERTISING 2015
REQUEST FOR PROPOSAL FOR RADIO/INTERNET RADIO ADVERTISING 2015 INQUIRIES AND PROPOSALS SHOULD BE DIRECTED TO: Kate Snyder, APR; Principal Strategist Piper & Gold Public Relations 517-999-0821 [email protected]