1 Achieving Code Level Five with Concrete and Masonry A mainstream approach for high performance, low-cost social housing.

2 Achieving Code Level Five with Concrete and Masonry Since the introduction of the Code for Sustainable Homes in 2006, the housing sector has made good progress in developing solutions to meet its tough performance standards, at all levels of the Code. Going forward, the next challenge is bringing the lessons learned into mainstream housing, in a cost-effective and practical manner. For social housing this challenge is particularly demanding, since energy efficiency enhancements to the fabric and services must not impact on the core design requirements within this sector, which include: Affordability Low maintenance Simplicity (easy to operate) Use of systems with a proven track record Robust and durable solutions The RSL partner for this project is A2Dominion Group The A2Dominion Group is one of the country s leading providers of high quality housing. The Group now provides over 30,000 homes across London and southern England with thousands in development. It offers a wide range of housing options, including homes for rent, sale and shared ownership, as well as temporary, student, sheltered, supported and key worker accommodation. 2 Meeting the challenge

3 Meeting the challenge A design team, which included a Registered Social Landlord (RSL), A2Dominion Group, and a contractor, was established to develop an outline design and specification for a three-bedroom, five-person house compliant with Code for Sustainable Homes (CSH) level 5. The optimal 85m 2 design secures the maximum funding available in its band and is suitable for both mid and end-of-terrace plots, and could form part of an RSL s national programme of construction. The basis for collaboration on this project was recognition that both concrete and masonry solutions provide an effective way of meeting the specific design needs of social housing, and benefits from using mainstream construction methods supported by a well-established supply chain. For the purpose of the project, the plot was assumed to have a north/south orientation, low flood risk and relatively low ecological value. The design meets the RSL specific design and quality standards, and also complies with requirements of the Lifetime Homes and Secured by Design standards. This publication gives a brief overview of the key decisions taken, and lessons learnt by the design team in working up the plans and specification. Particular attention is paid to the thermal performance of the building fabric and the overall energy and CO2 rating, which can account for over a third of the total points available in the Code. Key findings The specification of conventional concrete and masonry construction presented no particular thermal performance limitations at code level 5, notwithstanding the need for larger cavities and enhanced measures to minimise cold bridging. (This point is also relevant for code level 6, because the difference between code levels 5 and 6 largely relates to the provision of renewable energy.) Many of the newer systems and technologies associated with code level 5/6 performance were discounted early on as they did not fit well with the particular needs for social housing i.e. for simple, durable, cost-effective solutions with a low maintenance requirement. The specified concrete and masonry construction elements attractedgood scores in the BRE Green Guide, which is used to assess the environmental performance of materials within the Code for Sustainable Homes. Most suppliers of concrete and masonry products operate environmental management schemes compliant with ISO (or equivalent). This attracts points in the Responsible Sourcing category of the Code. Further points can be scored by specifying materials from suppliers compliant with the new standard for responsible sourcing of construction products (BES 6001). The design exercise underlying this document highlighted that: The house building industry using concrete and masonry solutions can make the step change required to deliver zero carbon housing by Code level 5 homes built with concrete and masonry are affordable and scalable. Code level 5 homes built with concrete and masonry can use existing construction methods and skills with a simple renewable energy strategy. The local supply chain, short lead times and a flexible programme offered by concrete and masonry construction continue to be a key benefit. 3

4 Achieving Code Level Five with Concrete and Masonry The design team and process The RSL and its contractor partner appointed the design team which worked closely with their in-house team to develop a design that addressed the following objectives. 1. RSL objectives (taken from original brief) RSLs are currently funded on code level 3 and the next step in 2010 to code level 4 is relatively straight-forward with the use of small amounts of renewables and modest upgrade to the fabric. The timing of this proposal means that units could be delivered around the time that all RSL projects need to meet code level 4. It has therefore been decided that this project should aim to produce a house/apartment of code level 5/6. Code level 6 being mandatory by 2013 for RSL work. The design should aim to follow Lifetime Homes guidelines as well as other RSL design criteria (HQIs [1] etc) which are needed to obtain funding. To facilitate the management of rented units on a whole life basis, the build method should use traditional materials and skills that are readily available, robust and flexible, enabling alterations at a later date. The design should be traditional, both inside and out, allowing it to harmonise with the local vernacular. 2. What lessons did the RSL hope to learn? Whilst a date does not currently exist for the implementation of level 5, level 4 will be introduced in April 2010 and level 6 in April Housing Corporation funding is currently given on the basis of meeting the relevant mandatory CSH level. Part of this project will show (using current and simple technology) how a level 5 house might be achieved and at what cost. This evidence may then be used to support higher funding levels. The current house type used as a basis to develop the proposals is on the maximum size of its band for funding reasons but still lacks things like home office space. The design exercise aims to learn how to maximise the points scored through good design and to assess any additional costs arising. To understand design techniques and systems required to consistently reach an air tightness of 2m 3 /(h.m 2 ) will be essential for future build. Low build costs and repeatability are key requirements, ensuring best value for grant funding. The brief was defined by the RSL to meet current standards and address future energy efficiency requirements. 4 The design team and process

5 Brief summary Must have 1. Brick/block external walls. 2. HQI space standards. 3. Design Quality Standards (DQS) [2]. 4. Minimum level 5 Code for Sustainable Homes. 5. Traditional methods of construction and common trades. 6. Design layout and materials which could be used virtually anywhere. 7. Monitor costs and produce a completed product cost based on an imaginary site. 8. Finish and fit out as standard. 9. Reflect an end-of-terrace unit (approx. site area 8x4m deep) but also consider the affect when this unit could be used as mid-terrace. We have already learnt how easy it is to reduce the heat loss through the building through better insulation methods and the effect it has on the overall efficiency of the house and its running costs and we need to explore and optimise this. We need to understand and identify low-carbon technologies which are relevant to both new and existing housing, helping facilitate future upgrades and their management. To reflect on the legacy of the current stock, consider effective remedial solutions and ultimately consider its design life. Desirable but not essential 1. Three-storey house with no garage (three-bed, five-person). 2. Green Guide A grade construction materials. 3. Life Time Homes [3]. Items we might consider 1. 12V lighting system to reduce power consumption. With PV connection. 2. Grey water/rain water harvesting. Roles and responsibilities of the design team The role of the chosen contractor and their design team, code assessor and construction team was to develop and evaluate an RSL s standard house types for code level 5, that was cost-effective and buildable. The material selection was made by the RSL in conjunction with the housebuilder/design team to ensure that the brief was met within the constraints of the cost and buildability parameters. Best value for grant funding. 5

6 Achieving Code Level Five with Concrete and Masonry Street elevation: Ground floor: potential positions for wheelchair platform lift. Ground floor plan 6 The design team and process

7 Rear elevation: First floor: potential positions for wheelchair platform lift. First floor plan 7

8 Achieving Code Level Five with Concrete and Masonry Meeting level 5 of the Code for Sustainable Homes Figure 1 provides a summary of the anticipated performance in each of the Code categories. This reflects the credits that are likely to be achieved when designed as an end-of-terrace house on a typical site. The code category of primary relevance to the design team was Energy and CO 2 as this has specific implications for the choice of materials and method of construction. It also scores by far the greatest number of the available points, and for these reasons this category was the main focus during the design process (and this document). It is also the only section underpinned by regulation i.e. Part L of the Building Regulations. With the exception of the Materials category of the Code, the remaining points are less directly influenced by the method of construction. The environmental impact of the specified materials gained 4.5 of the 7.2 points available, scoring well for environmental performance with the external walls and roof achieving an A+, the windows scoring an A and the internal walls and floors achieving a B. All the materials could easily be sourced from suppliers operating an environmental management scheme (typically ISO 14001), which attracts half the points available in the Responsible Sourcing sub-category. However, since the completion of this project, a new standard for the responsible sourcing of construction products (BES 6001) has been introduced. Concrete and masonry material sourced from suppliers meeting this standard will score full points for responsible sourcing. Energy & CO2 (Code Category One) A key outcome of the design process was that the specification of conventional concrete/masonry construction presented no particular thermal performance limitations at code level 5, albeit larger cavities are required and enhanced measures are needed to minimise cold bridging. Whilst not part of the Code, the heavyweight approach has the added energy efficiency benefit of enabling a wet plaster finish to be used, which provides a simple, durable means of ensuring long-term air tightness and also increases the thermal mass of the walls (details of the construction elements are provided on page 11). 1. Dwelling Emission Rate (DER) The Target Carbon Dioxide Emission Rate (TER) for the house was calculated to be kg/m 2, and to achieve level 5 of the Code this had to be completely offset. i.e. a Dwelling Carbon Dioxide Emission Rate (DER) of 0 kg/m 2 or lower was required. The final design produced a DER of kg/m 2 which is an improvement of 101 per cent. This scores 14 out of a potential 15 credits. 2. Heat Loss Parameter (HLP) Credits are available in the non-mandatory part of the Energy category for a low HLP (1 credit for an HLP smaller than or equal to 1.3, increasing to 2 credits for a value of 1.1 or lower). The house achieves an HLP of 0.81, scoring the full 2 credits. ENERGY & CO2 96% HEALTH & WELLBEING 83% LAND USE & ECOLOGY 56% Figure 1: Code for Sustainable Homes - percentage category scores MANAGEMENT WATER MATERIALS WASTE 62% 100% 100% 100% POLLUTION 75% SURFACE WATER RUN-OFF 100% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Category Score a % of Maximum Available Code level 5 was set by the RSL to confirm the ongoing viability of concrete and masonry construction 8 Meeting level 5 of The Code for Sustainable Homes

9 3. Internal lighting The specification required 75 per cent or more of the lighting installation to comprise low energy fittings/lamps, attracting 2 credits; the maximum available. 4. Drying space A rotary dryer in the garden was specified, attracting 1 credit which is the maximum available. Whilst incurring additional cost, an alternative option for sites with a favourable orientation is to add a lobby/sunspace which could double as drying area and would also improve the dwelling s thermal performance (see passive solar design below). 5. Eco-labelled white goods The specified dishwasher and washing machine are both A rated under the EU Energy Efficiency Labelling Scheme, and the fridge/freezer has an A+ rating, jointly achieving the maximum score of 2 credits. 6. External lighting At the design stage assessment of the Code, no points were included for external lighting. It was considered relatively simple to add external lighting later if additional points were deemed necessary during the construction phase. 7. Low or zero carbon energy technologies 27m 2 of Photovoltaics (PV) is specified for the south facing area of the roof. This provides around 3kW of peak electrical output, reducing CO 2 emissions by more than 15 per cent, which achieves the maximum score of 2 credits. 8. Cycle storage The provision of a timber shed for the storage of three bikes (which corresponds to the number of bedrooms) attracts the maximum score of 2 credits. 9. Home office Provision has been made in the layout of one of the smaller bedrooms for a home office, gaining the maximum score of 1 credit. It has been designed to meet code requirements for a quiet, well-ventilated space with a minimum wall length of 1.8m for a desk, chair and filing cabinet. Thermal mass Whilst thermal mass does not fall within the scope of the Code, making use of it was nevertheless an important design requirement, particularly as it is an inherent property of heavyweight construction. Its key function in the design is to reduce the risk of summertime overheating and provide a degree of adaptation to our warming climate. It also has the potential to improve the energy efficiency of the dwelling during the heating season through its ability to store and release solar gains and heat from internal sources. This is influenced by orientation and window location/size, and is currently outside the scope of the SAP tool used to calculate the thermal performance of dwellings. However, revisions to SAP currently underway are likely to address this issue, potentially enabling a modest improvement in the energy/co 2 rating for dwellings that take advantage of their mass. The provision of thermal mass was one of the factors considered in the selection of materials and finishes, and was assessed in terms of admittance. This is effectively a measure of effective thermal mass; with admittance values around 1 W/m 2 K being low and values of around 4W/m 2 K or more considered to be relatively high. The values achieved for the specified construction elements are shown in Figure 2. External walls: Medium density aggregate block inner leaf (1400 kg/m 3 ), wet plaster finish. Admittance value: 4.2 W/m 2 K. Internal Walls: Ground floor: Upper floor: Medium density aggregate blocks (1400 kg/m 3 ) exposed both sides, wet plaster finish. Admittance value: 3.7 W/m 2 K. Concrete beam & block. 90mm of screed on insulation, tiled finish. Admittance value: 4.0 W/m 2 K. Concrete beam & block. Finish: carpet/lino on 75mm screed. Ceiling to first floor: plasterboard on battens. Approximate admittance value for top and bottom surfaces W/m 2 K Figure 2: Admittance values for key construction elements Surface finish - walls A wet plaster finish for both the internal and external walls ensures the inherent thermal mass in the concrete blocks is fully utilised. The thermal conductivity of the plaster is similar to that of the blocks, helping maximise heat flow back and forth between the room and walls. The use of plaster increases the wall s admittance value by around 1.4 W/m 2 K compared to the usual alternative of plasterboard on dabs. Others drivers for a wet plaster finish were air tightness, durability and resistance to flood damage. Surface finish ground floor Whilst the thermal mass contained in the beam and block floor is isolated by the insulation located above it, there is still a useful amount provided by the screed and tiled surface. The choice of a tiled finish was driven by a combination of: compatibility with underfloor heating, increased mass, durability and resistance to flood damage. Passive solar design Plots with a favourable orientation and minimal overshadowing could potentially benefit from the addition of a lobby/sun space. This would provide a thermal buffer, reducing heat loss from the adjoining wall and improve energy efficiency during the heating season, particularly in the spring and autumn when its contribution to the space heating will be at its greatest. The minimum floor area could be that needed for a drying space and cycle storage. 9

10 Achieving Code Level Five with Concrete and Masonry Summary of detailed specification Roof structure: A+ rated timber trussed cold roof construction Roof covering: Concrete single lap interlocking tiles Roof insulation: 450mm mineral wool External walls: A+ rated cavity wall construction Facing brick: Walls and reveals Cavity insulation: 200mm full fill polystyrene bead Inner walls: Medium density aggregate block with wet plaster Windows: A rated UPVC and doors Lintels: Pre-stressed concrete inner leaf with outer steel C lintels First floor: B rated pre-stressed concrete beam and block, 75mm sand cement screed Ceiling to u/s of first floor: Metal framed ceiling laths with plasterboard and skim Ground floor: B rated, pre-stressed concrete beam and block, 90mm sand cement screed and 200mm polystyrene insulation Internal walls: Medium density concrete block with wet plaster finish Staircase: Timber softwood Heat source: Condensing gas boiler Heat distribution: Wet underfloor heating Renewables: 27m 2 of photovoltaic panels Ventilation: Mechanical ventilation with heat recovery system Foundations: Precast piles and precast ground beams The material selection was made by the RSL and its design/construct team, within the cost and buildability context. 10 The building fabric

11 The building fabric Ground floor Two types of beam and block construction were evaluated for the ground floor, one using polystyrene blocks and the other with concrete blocks. Both had a 90mm screed finish, containing underfloor heating pipes. For U-values down to 0.15 W/m 2 K, the polystyrene option requires no additional insulation. However, to achieve the very low design value of 0.12 W/m 2 K, approximately 50mm of extra insulation is necessary. The concrete block option requires 200mm of insulation, resulting in an overall floor depth that is around 150mm greater than that required with polystyrene blocks. Other factors taken into consideration centred on cost and the environmental rating for which the polystyrene option scores an A+ rating in the Green Guide. However, it was decided to go with the concrete block option as the potential exists to upgrade this from a B to an A rating by specifying screed with a high recycled content, and also because the overall floor depth was not considered to be a particular design issue. The design U-value of 0.15 W/m 2 K was achieved using a 200mm cavity fully filled with polystyrene beads and medium density aggregate block for the inner leaf. The choice of medium density blocks over other options was marginal, but was driven by a combination of cost and the added benefit of their reasonably high mass. However, had wall thickness and lower thermal conductivity been more of a driver, the greater insulating properties of aircrete blocks would have reduced the depth by around 10mm, or 15mm when using a thin-joint system, which would also be likely to reduce build time. With the chosen combination of medium density aggregate blocks and polystyrene beads, the wall has an overall thickness of around 415mm, including finishes. The design team also considered using mineral wool quilt, blown fibre and phenolic foam board with a 50mm cavity, which would have reduced the overall wall thickness to around 385mm; however with low build cost as a key requirement, the benefit of this option was judged to be of less importance than the comparatively lower price of polystyrene insulation. It also enabled the optimum cavity width to be specified as this was not determined by standard manufactured insulation thicknesses. Roof The design of the roof structure required a minimum pitch, defined by the need to achieve optimum performance in terms of weathering, whole life costs and the use of solar panels to achieve code level 5 performance targets. Consideration was given to the selection of either timber cut roofing members or trussed roofing. A timber trussed roof was specified as it represents best value and is readily available. A safe access zone formed part of the design, allowing proper accesses to the mechanical ventilation plant. Mineral wool, polyurethane board and natural wool were all considered for the cold roof structure. The final choice was 450mm of mineral wool, which was found to be the most economical way of achieving the required U-value of 0.12 W/m 2 K. A traditional roof covering was a fundamental design requirement in order to meet the aspirations of the RSL for a traditional design acceptable to planning authorities on a national basis. The roof covering has to be compatible with solar panels. Double lap and single lap interlocking concrete tiles were considered, with the single lap option selected for being the most cost-effective. External walls A primary objective of the external walls is to meet the NHBC requirements, BBA certification, and RSL requirements for cost-efficient, mainstream construction methods and materials. The result was a cavity wall, with a choice between facing bricks for the outer leaf or concrete blocks with a rendered finish, to suit whatever the local architectural style might require. Thermal performance targets achieved. 11

12 Achieving Code Level Five with Concrete and Masonry Windows Timber and UPVC windows were evaluated for thermal performance, maintenance requirements, ease of cleaning and durability. Despite lower levels of embodied CO 2, timber was ultimately ruled out due to higher maintenance requirements; an issue of particular importance to the RSL. This left UPVC windows as the preferred option and they were ultimately selected. In addition to the maintenance issue, the decision was also influenced by cost and the recent improvement in the Green Guide environmental rating for UPVC windows, which has moved from C to A, reflecting the material s good whole life performance i.e. low maintenance requirement and ability to be recycled at end of life. The design U-value was initially estimated to be around W/m 2 K, reflecting the typical performance of energy efficient windows from UK suppliers. However, this was revised down to 0.8 W/m 2 K when it was found that a mainstream supplier can provide this level of performance in its UK manufactured UPVC windows by incorporating triple glazing with krypton gas and low emissivity glass. Internal walls Concrete blocks, timber studs and steel studwork were all considered for the internal walls, but as a wet plaster finish was the preferred option for the external walls, it made sense to extend this to all of the walls. Consequently it was decided to use medium density aggregate blocks on the ground and first floor, which in turn brought the added benefit of a tough finish, greater mass and good resilience to damage in areas at risk from flooding. First floor Both timber and concrete solutions were considered, however the benefits of thermal mass and better acoustic and fire separation led to a choice of concrete. A pre-stressed concrete wide span floor and pre-stressed concrete beam and block floor were both considered by the design team, with little to choose between them. But as the design assessment was for a single dwelling it was assumed that there would not be a crane on-site, which in turn favoured the beam and block option. For volume build the choice may be different. Lintels The design constraint of a 200mm cavity with load bearing masonry required the consideration of readily available solutions using separate lintels for each wall leaf. The design team considered steel C lintels, precast stone, and reinforced concrete inner lintels before selecting reinforced concrete inner lintels with an outer steel C lintel. Thermal bridging Non-repeating cold bridging at junctions, lintels etc. is minimised through the use of high performance construction details with an overall y-value of 0.04 W/m 2 K which, in a modern semi-detached house, can reduce CO 2 emissions by around 7 per cent compared with standard Part L performance. Low conductivity basalt fibre ties, with a thermal conductivity around 20 times less than stainless steel, are specified for the cavity walls. For the cavity closers, extruded PVC with a rigid urethane insulated core was chosen. At least one manufacturer can provide these closers with jointing clips to allow the smaller, more commonly used sizes of mm to be extended for cavities up to 200mm (as used in this project). Staircase The design team considered a precast concrete stair solution; however, on balance, for this single development a timber stair was seen as a cost-effective and readily available solution. For volume build, where there is more likely to be a crane on-site, the concrete option would become a more realistic choice. Air tightness The design air leakage rate was set at 2 m 3 /(h.m 2 ). Whilst challenging, this is a realistic target, as demonstrated by the recent Stamford Brook development of around 700 highly insulated masonry homes. A key lesson from Stamford Brook was that a masonry house can achieve an air leakage rate of 2 m 3 /(h.m 2 ) provided that care is taken with detailing and sequencing of trades on site. The choice of primary air barrier was made early in the design process. A rough sand and cement parging coat on the blockwork inner leaf would have provided an effective solution; however this approach is generally used in conjunction with a plasterboard finish, which the design team wanted to avoid for reasons already described. Consequently, the chosen solution was wet plaster, which seals the blockwork in the same manner as parging but with the advantage of being able to conduct more heat to and from the wall than is possible with plasterboard on dabs (see surface finish section on page 9). Other points in its favour are its resilience to flood damage and general robustness which is a requirement of social housing programmes. Points against a wet plaster finish are the time and skill needed to apply it, although modern projection plastering techniques can significantly speed up the process. Drying time can also be seen as a disadvantage. 12 Building fabric and services

13 Building services Heat source/hot water The main design requirements influencing the choice of heat source centred on the following issues: ease of maintenance cost use of a known technology code score compatibility with other aspects of the design. A small wood chip biomass boiler was initially considered as this represents the type of technology that would ideally be used as part of a much larger district heating scheme serving a whole social housing development. This pointed the way to a wet heating system which could be supplied with hot water from a range of sources (either on-site or nearby), helping future proof the heating design. However, the use of a small wood chip boiler was subsequently ruled out on the grounds of practicality for a single house. A ground source heat pump was discounted on the grounds of cost and because, like all heat pumps, it does not attract any code credits under the Pollution category. In contrast, credits can be scored for the low NOx emissions from a condensing boiler, which was the eventual choice since it is was also best able to match all the design requirements listed above. A class 5 boiler was specified with an overall efficiency greater than 90 per cent, attracting 2 credits for low NOx emissions. As condensing boilers provide relatively cheap hot water, it was not felt worthwhile to also install a solar hot water system, which would have added complexity, cost and been difficult to site on a roof with PV panels already occupying most of the south facing area of the roof. Photovoltaic (PV) technology Since a key requirement for the RSL was low maintenance and the use of proven technologies, it was decided that photovoltaic panels would be installed to meet the entire on-site renewable energy requirement. This decision was also driven by the need to reduce the overall complexity and maintenance requirements of any low/zero carbon technologies installed in the house, and limiting the design to a single technology makes it easier for the occupants to operate. Heat distribution Affordable housing design parameters are complex because of the need for designers to work within the wide range of mandatory compliance criteria, including Housing Quality Indicators. As a result, the furniture layouts and window/wall space have an impact on the limited positions for radiators. Options considered included underfloor heating and pressed steel radiators, from which it was decided that to fulfil requirements for even heat distribution and compatibility with the mass of the floors, an underfloor solution was the most effective option. The decision was also influenced by the very thermally efficient windows (0.8 W/m 2 K), which have minimal downdraughts, so have little need for radiators to counter them. This in turn frees up space and allows the furniture layout to be optimised. A further benefit of underfloor heating is the low flow and return temperature, which helps save gas by enabling the boiler to operate in condensing mode for much of the time. In terms of comfort, underfloor heating makes floor tiles a more practical option than would otherwise be the case, and their use also allows access to thermal mass in the screed. So, there is some synergy between underfloor heating, thermal mass and tiled floors, which also provide a durable surface. Mechanical ventilation Mechanical ventilation with heat recovery (MVHR) was specified since, without it, the low air leakage rate of 2m 3 /(h.m 2 ) is likely to result in poor air quality and the potential for condensation problems. The ability to recover waste heat in mechanical systems can also make a useful contribution to overall energy efficiency of dwellings and reduce CO 2 emissions. For example, the use of MVHR in a modern semi-detached house with an air leakage rate of 2m 3 /(h.m 2 ) can reduce emissions by around 6 per cent compared with natural ventilation alone. The MVHR system selected for the project is compliant with Appendix Q of SAP, and combines low fan power with a counter flow heat exchanger that recovers up to 91 per cent of the heat in the discharge air. During warm weather, a bypass system diverts the incoming air around the heat exchanger, preventing the warm discharge air from increasing the supply temperature. The unit takes and exhausts air through the roof. The three bedrooms, lounge and kitchen each have a fresh air supply, with extract points located in the kitchen, bathroom and ground floor WC. Figure 3: MVHR layout (blue = supply/ red = extract) The choice of underfloor heating increased space planning flexibility. 13

14 Achieving Code Level Five with Concrete and Masonry Summary and lessons learnt Figure 4: Summary of key design information House type Code level 5 Floor area 85m 2 Air tightness 2m 3 /(h.m 2 ) Heat loss parameter 0.81 Cold bridging y-value 0.04 Ground floor Walls Roof Windows Upper floor Internal walls Ventilation Heat source Heat distribution Three-bedroom, five-person, end or mid-terrace Beam and block, 0.12W/m 2 K Brick and block, 0.15 W/m 2 K Timber-trussed, concrete tiles, 0.12 W/m 2 K UPVC, triple glazed, 0.8 W/m 2 K Beam and block Block MVHR Class 5 condensing boiler Wet, underfloor Renewables Photovoltaic panels, 27m 2 Water consumption Home office Lifetime Homes Secured by Design Estimated code points 1. Energy 2. Water 3. Materials 4. Surface water run-off 5. Waste 6. Pollution 7. Health and well-being 8. Management 9. Land use and ecology 80l/p/day Yes Yes Yes out of out of out of out of out of out of out of out of out of 12 Lessons learnt It is important for specifiers to talk to their supply chain as manufacturers may have new products available that can help score credits within the Code. Talk to the technical and sales people to get different options. Evaluate the cost/benefit of different insulation materials to avoid overspecification. For example, with this project it was found that polystyrene bead insulation provided a good balance between cost and performance for the cavity walls. It also enabled the optimum cavity width to be specified as this was not determined by standard insulation thicknesses. Beware of agreeing to changes in the original product specification, as substitute materials and systems may not score the same credits in the post-construction assessment. A generic design can be produced up to a point, but window size and location should ideally take account of site specifics (orientation and overshadowing) so that daylighting and passive solar gain can be optimised. This can influence the credits scored, as can other site specific details such as flood risk and ecological value. Talk to your code assessor early in the design process, and if possible include them in the project team. Their involvement at the outset will assist in maximising the points scored and help avoid missed opportunities. Total estimated code points out of Summary and lessons learnt

15 Summary This design exercise utilised the expertise of an RSL client, design team, contractor/housebuilder and was based on a developed standard house type. It shows that concrete and masonry construction can produce cost-effective, locally and responsibly sourced solutions to the higher levels of the Code for Sustainable Homes. This can all be achieved, whilst at the same time addressing the needs of the public sector for long-term, durable and flexible construction solutions. References: 1. Housing Quality Indicators, version 4, April Design and Quality Standards, Housing Corporation, April The Lifetime Homes Standards, Lifetime Homes Durability, long-life and future adaptability are all integral to the solution. 15

16 The Concrete Centre Riverside House, 4 Meadows Business Park, Station Approach, Blackwater, Camberley, Surrey GU17 9AB Ref: TCC/04/09 ISBN: First published 2009 MPA - The Concrete Centre, 2009 The Concrete Centre is part of the Mineral Products Association, the trade association for the aggregates, asphalt, cement, concrete, lime, mortar and silica sand industries. All advice or information from MPA -The Concrete Centre is intended only for use in the UK by those who will evaluate the significance and limitations of its contents and take responsibility for its use and application. No liability (including that for negligence) for any loss resulting from such advice or information is accepted by Mineral Products Association or its subcontractors, suppliers or advisors. Readers should note that the publications from MPA - The Concrete Centre are subject to revision from time to time and should therefore ensure that they are in possession of the latest version.

Building your own energy efficient house

Building your own energy efficient house GOOD PRACTICE GUIDE 194 Building your own energy efficient house Why save energy How to achieve integrated design Checklist for a low energy home Further information GOOD PRACTICE GUIDE 194 2001 2001 EDITION

More information

exceed your energy performance levels

exceed your energy performance levels exceed your energy performance levels www..ie discover the better way to build Welcome to Thermohouse Thermohouse is one of the highest quality low energy building system available in Europe today. Thermohouse

More information

Case Study 1 Code level 3

Case Study 1 Code level 3 Case Study 1 Code level 3 Norbury Court Staffordshire Is a development of seven three bedroom houses, one two bedroom house and one three bedroom bungalow. Design Team Contractor - LHL Development Ltd

More information

Masonry: Cavity Wall Insulation: Partial Fill Isometric cut-away view

Masonry: Cavity Wall Insulation: Partial Fill Isometric cut-away view Legend Insulation zone Blue text Air tightness barrier (note: this can also act as a vapour control layer) Guidance on thermal continuity Red text Guidance on air tightness Values used in psi calculations

More information

Timber Frame Isometric cut-away view

Timber Frame Isometric cut-away view Legend Insulation zone Blue text Red text Air tightness barrier (note: this can also act as a vapour control layer) Guidance on thermal continuity Guidance on air tightness Values used in psi calculations

More information

Module 3.8. Window U-value

Module 3.8. Window U-value Module 3.8 Window U-value Learning Outcomes On successful completion of this module learners will be able to - Describe the concept of U-values and alternative energy rating system for windows. 2 Calculation

More information

Case Studies of Successful Code for Sustainable Homes Projects

Case Studies of Successful Code for Sustainable Homes Projects Case Studies of Successful Code for Sustainable Homes Projects Sustainable Homes publish the Sustainable Homes Index For Tomorrow (SHIFT) and are a leading trainers of Code for Sustainable Homes assessors.

More information

TIMBER FRAME APPLICATION NOTES INTRODUCTION

TIMBER FRAME APPLICATION NOTES INTRODUCTION Tŷ-Mawr Ecological Building Materials TIMBER FRAME APPLICATION NOTES INTRODUCTION This application guidance is aimed at ensuring you make the best use of the Thermafleece range of insulation when used

More information

Energy Company Obligation (ECO): Technical Monitoring Questions

Energy Company Obligation (ECO): Technical Monitoring Questions Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified

More information

James Sweet Commercial Director - C4Ci Limited Consultants for Construction Innovation

James Sweet Commercial Director - C4Ci Limited Consultants for Construction Innovation James Sweet Commercial Director - C4Ci Limited Consultants for Construction Innovation The Opportunity and Entry Requirements for the UK Residential House Building Market 22/23 January UK Snapshot Main

More information

Garage conversion guidance note

Garage conversion guidance note Garage conversion guidance note Bracknell Forest Building Control POLICY GUIDANCE THE BUILDING REGULATIONS 2010 Regulation 3, Schedule 1 This Guidance Note is for the benefit of local architects, builders

More information

Structural Timber Association Building Low Carbon Timber Frame Homes

Structural Timber Association Building Low Carbon Timber Frame Homes Structural Timber Association Building Low Carbon Timber Frame Homes STA what we do TRADE BODY for - Timber Frame SIPS- CLT- Glulam Engineered wood products (see www.structural timber.co.uk for more information)

More information

Rockwool Flexi Insulation Application Guide

Rockwool Flexi Insulation Application Guide Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed

More information

Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings

Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings Duchy Homes Site: Cantley Lane Doncaster Proposal to achieve Code for Sustainable Homes Level 3 for a development of 7 detached dwellings 22 nd February 2013 Leanne Brooksbank Accredited Energy & Code

More information

Report Date: 04/03/2014. Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669

Report Date: 04/03/2014. Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669 Report Date: 04/03/2014 Assessor: John Doyle Address: BLOCK K APT 108 SANDYFORD VIEW DUBLIN 18 BER: 106178106 MPRN: 10301589669 About this Advisory Report Energy use in our homes is responsible for almost

More information

Code for Sustainable Homes Guidelines

Code for Sustainable Homes Guidelines Canoldir Penrhos Anglesey LL65 2TS Phone: 01407 860666 Email: saps@easonline.co.uk www.easonline.co.uk Code for Sustainable Homes Guidelines A CSH rating is the responsibility of the Developer/ Architect

More information

Contents. APA Construction Details. Full fill cavity walls 2-13. Partial fill cavity walls 14-25. Solid externally insulated walls 26-37

Contents. APA Construction Details. Full fill cavity walls 2-13. Partial fill cavity walls 14-25. Solid externally insulated walls 26-37 Contents Pages Full fill cavity walls 2-13 Partial fill cavity walls 14-25 Solid externally insulated walls 26-37 Appendix (BRE confirmation of Ψ and y-values) 38-40 Page 1 of 40 APA Construction Details

More information

Timber Frame Walls Rethinking Construction

Timber Frame Walls Rethinking Construction Insulation Fifth Issue November 2007 Timber Frame Walls Rethinking Construction INSULATION BEST PRACTICE FOR THE 21ST CENTURY Summary 9 mm OSB sheathing 3 mm skim coated 15 mm plasterboard Rock or glass

More information

Masonry Cavity Wall and Plasterboard Laminate

Masonry Cavity Wall and Plasterboard Laminate Issue 1, September 2013 CI/SfB (2 -) Rn7 (M2) Masonry Cavity Wall and Plasterboard Laminate Introduction Celotex is the brand leading manufacturer of PIR insulation boards, with its range encompassing

More information

STANDARD TECHNICAL DETAILS

STANDARD TECHNICAL DETAILS STANDARD TECHNICAL DETAILS CONTENTS PAGE QL-TD-01 Quinn Lite Foundation Blocks (solid floor) 1 QL-TD-02 Quinn Lite Foundation Blocks (suspended floor) 2 QL-TD-03 Quinn Lite Foundation Blocks (stone cladding

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 11 Hirwain Street CARDIFF CF24 4JG Dwelling type: Date of assessment: Date of certificate: Reference number: Total floor area: Mid-terrace house 23 July 2009 24 July 2009

More information

XT/TF. High performance PIR timber frame insulation board. Insulation for timber framed walls. OCTOBER Affordable innovation.

XT/TF. High performance PIR timber frame insulation board. Insulation for timber framed walls.  OCTOBER Affordable innovation. OCTOBER 2010 Affordable innovation. High performance PIR timber frame insulation board Insulation for timber framed walls XT/TF COST EFFECTIVE THERMAL SOLUTIONS www.xtratherm.com Timber Frame Insulation

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 159, Moy Road CARDIFF CF4 4TH Dwelling type: Mid-terrace house Date of assessment: 1 July 009 Date of certificate: 4 July 009 Reference number: 801-663-680-8419-40 Total

More information

U-Value Calculations

U-Value Calculations Leaving Certificate Revision Notes U-Value Calculations www.constructionstudies.ie Construction Studies Notes vapour barrier insulation plasterboard Notes: Thermal insulation U value calculations timber

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 47 Penydarren Drive CARDIFF CF14 2TT Dwelling type: Date of assessment: Date of certificate: Reference number: Type of assessment: Total floor area: Mid-terrace house 27

More information

Design of an Eco Friendly and Self Sufficient Cabin

Design of an Eco Friendly and Self Sufficient Cabin Design of an Eco Friendly and Self Sufficient Cabin This project is a real programme which is to develop a prototype of an eco friendly cabin. In this project, I choose two sites, Aberdeen and Brighton,

More information

The Visqueen VAPOUR control

The Visqueen VAPOUR control VAPOUR CONTROL LAYERS Visqueen VAPOUR BARRIERS Range suitable for all internal building conditions. Used within roof, wall and floor constructions. Reduces the likelihood of interstitial condensation.

More information

Module 3.7. Thermal bridging

Module 3.7. Thermal bridging Module 3.7 Thermal bridging Learning Outcomes On successful completion of this module learners will be able to - Describe construction details which influence thermal bridging. 2 Introduction to thermal

More information

BUBBLE FOIL INSULATION

BUBBLE FOIL INSULATION BUBBLE FOIL INSULATION Save on heating costs Easy fit installation, no mess Safe - Non Toxic, hypoallergenic, mould resistant Tel: 08 787 SINGLE FOIL INSULATION Yuzet produce single foil insulation which

More information

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most

More information

Topic 3 Understanding the Energy Requirements

Topic 3 Understanding the Energy Requirements Topic 3 Understanding the Energy Requirements Planning for Climate Change - Delivering Sustainable Buildings & Quality Design Learning Objectives By the end of this session, you should have a basic understanding

More information

Rev 1-12.2013. Code of Practice. SIP Technology. www.uksips.org

Rev 1-12.2013. Code of Practice. SIP Technology. www.uksips.org Rev 1-12.2013 Code of Practice SIP Technology www.uksips.org What are Structural Insulated Panels (SIPS)? SIPS are prefabricated, high performance, lightweight, building panels that can be used in floors,

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 177, Heritage Park, St. Mellons Dwelling type: Mid-terrace house CARDIFF CF3 0DT Date of assessment: Date of certificate: Reference number: Type of assessment: 27 November

More information

Part L 2010 where to start: An introduction for house builders and designers

Part L 2010 where to start: An introduction for house builders and designers Part L 2010 where to start: An introduction for house builders and designers Acknowledgements This guide was written and published for NHBC Foundation by Richards Partington Architects www.rparchitects.co.uk

More information

Appendix 4 - Standard technical monitoring questions

Appendix 4 - Standard technical monitoring questions Appendix 4 - Standard technical monitoring questions General questions Survey company Name of surveyor completing form Name of householder Address of householder Date of installation Date of inspection

More information

Part 3 Ancillary technologies. Chapter 3.2. Mechanical ventilation with heat recovery

Part 3 Ancillary technologies. Chapter 3.2. Mechanical ventilation with heat recovery Part 3 Ancillary technologies Chapter CONTENTS SCOPE Clause Page DESIGN Design standards D1 1 Statutory requirements D2 1 System design D3 1 Building integration D4 2 Noise D5 2 Access and controls D6

More information

Green Build Timber Frame. Helping you build a greener future

Green Build Timber Frame. Helping you build a greener future Timber Frame Helping you build a greener future Timber Frame Helping you build a greener future Today s homes demand a reliable, robust, high thermal performance building envelope, which drives energy-efficiency,

More information

PRINCIPLES OF ENERGY EFFICIENT HOUSE DESIGN

PRINCIPLES OF ENERGY EFFICIENT HOUSE DESIGN PRINCIPLES OF ENERGY EFFICIENT HOUSE DESIGN David Baetge B Ec, Dip ME, Grad IE(Aust), P Eng Thermal Performance Assessor B: (03) 5962 6410 M: 0417 319 830 W: www.postbeam.com.au E: david@postbeam.com.au

More information

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.

Section 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01. Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice

More information

Table 1: DWELLING HOUSES AND FLATS SEPARATING WALLS, FLOORS and STAIRS THAT HAVE A SEPARATING FUNCTION. NEW BUILD

Table 1: DWELLING HOUSES AND FLATS SEPARATING WALLS, FLOORS and STAIRS THAT HAVE A SEPARATING FUNCTION. NEW BUILD Guidance Note Issued 01// Rev A Page 1 of 5 Approved document E came into force on the 1 st July 2003 and details new acoustic performances for residential dwellings, flats, rooms used for residential

More information

URSA GLASSWOOL URSA Timber Frame Roll & URSA Timber Frame Slab

URSA GLASSWOOL URSA Timber Frame Roll & URSA Timber Frame Slab URSA TF Roll (Tim & Met) - 065_Layout 1 22/07/2015 12:38 Page 1 URSA UK LTD Crest House 102-104 Church Road Teddington, Middlesex TW11 8PY United Kingdom Tel : 020 8977 96 97 Fax : 020 8977 94 56 Web :

More information

INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS. Multi-Layer Technology provides increased strength.

INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS. Multi-Layer Technology provides increased strength. INTERIOR WALLS AND BASEMENTS CHOOSING THE RIGHT MEMBRANE FOR INTERIOR WALLS Multi-Layer Technology provides increased strength. Specifically designed for interior applications. Compatible with most internal

More information

Building codes are presently moving towards new

Building codes are presently moving towards new Heating and cooling challenge in nzeb Experiences from built houses and detailed building simulations calls for a careful and integrated approach when designing heating and cooling systems for nearly zero

More information

Energy efficiency and the Code for Sustainable Homes

Energy efficiency and the Code for Sustainable Homes CE291 Energy efficiency and the Code for Sustainable Homes Level 4 Also available: Energy efficiency guidance for level 3 Energy efficiency guidance for levels 5 and 6 Contents 1. Introduction 3 1.1 Energy

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 87, Cardiff Road Dwelling type: End-terrace house ABERDARE Date of assessment: 02 October 2009 CF44 6TR Date of certificate: 15 October 2009 Reference number: 0328-5914-6290-6021-1084

More information

FABRIC ENERGY EFFICIENCY FOR PART L 2013

FABRIC ENERGY EFFICIENCY FOR PART L 2013 Informing the Part L 2013 consultation FABRIC ENERGY EFFICIENCY FOR PART L 2013 WORKED EXAMPLES AND FABRIC SPECIFICATIONS February 2012 Introduction This report has been produced by the Zero Carbon Hub

More information

Timber frame solutions

Timber frame solutions . Leeds Carnegie, student accommodation. Contents Section overview Introduction 0 Separating floors 0-05 Internal floors 06 Separating walls loadbearing 07 Separating walls non-loadbearing 08 Internal

More information

2014 British Columbia Building Code Changes

2014 British Columbia Building Code Changes 2014 British Columbia Building Code Changes A City of Kelowna interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most notable revisions and staff interpretations.

More information

SAP 2012 IN A NUTSHELL

SAP 2012 IN A NUTSHELL SAP 2012 IN A NUTSHELL The consultation version of the SAP 2012 methodology was published by the Department of Energy and Climate Change (DECC) on January 4th 2012. This article from Dyfrig Hughes of National

More information

Assessment Methods. 15 th November 2010 Huw Jenkins Simon Lannon

Assessment Methods. 15 th November 2010 Huw Jenkins Simon Lannon Assessment Methods 15 th November 2010 Huw Jenkins Simon Lannon Assessment Methods Program Country Year Program Country Year 1 R-2000 Canada 1982 12 LEED US 2000 2 P-mark Sweden 1989 13 ECO-Quantum Netherlands

More information

Case study Seven Oaks Crescent, Bramcote

Case study Seven Oaks Crescent, Bramcote Case study Seven Oaks Crescent, Bramcote Project: Extension & alterations, Seven Oaks Crescent, Bramcote, Notts. Contractor: P C Griffiths & Son (Derby) Engineer: Cameron Darroch Associates Completion:

More information

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010

BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Building Control Charnwood Borough Council Southfield Road Loughborough LE11 2TN BUILDING CONTROL GUIDANCE SHEET REPLACEMENT WINDOWS AND DOORS Last updated 16/11/2010 Page 1 of 6 PURPOSE: This Guidance

More information

Ecojoist. Practical benefits of Ecojoist. www.eleco.com/gang-nail

Ecojoist. Practical benefits of Ecojoist. www.eleco.com/gang-nail Ecojoist Practical benefits of Ecojoist. www.eleco.com/gang-nail Gang-Nail Systems, an Eleco plc company, offer integrated solutions f the timber engineering industry which assist in reducing design, production

More information

Life Cycle Primary Energy Use and Carbon Emission of Residential Buildings

Life Cycle Primary Energy Use and Carbon Emission of Residential Buildings Life Cycle Primary Energy Use and Carbon Emission of Residential Buildings Ambrose Dodoo Sustainable Built Environment Linnaeus University 26 January 2012 VÄXJÖ Global primary energy supply Mtoe 1 Mtoe

More information

SUSPENDED BEAM & BLOCK FLOOR

SUSPENDED BEAM & BLOCK FLOOR www.supremeconcrete.co.uk SUSPENDED BEAM & BLOCK FLOOR The Supreme Beam and Block Flooring System saves time and cost on site. The floor is quick to install without the need for specialist skills. Site

More information

Manual lifting and handling

Manual lifting and handling Manual lifting and handling When installing British Gypsum products and systems care should be taken to ensure that appropriate methods of handling and lifting are adopted. The following guidance details

More information

CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME

CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME Press Release CASH SAVING BEATS ECO CONCERNS AS MAIN REASON TO GREEN YOUR HOME Saving money is now our main motivation for carrying out green home improvements ahead of concerns for the environment. One

More information

6 STAR ENERGY EFFICIENCY HOUSES

6 STAR ENERGY EFFICIENCY HOUSES YOUR GUIDE TO 6 STAR ENERGY EFFICIENCY HOUSES IN TASMANIA 2014 Department of Justice Building Standards and Occupational Licensing P: 1300 366 322 E: wstinfo@justice.tas.gov.au W: www. justice.tas.gov.au

More information

HANLO The WELCOME HOME Experience.!! Simply better homes!!

HANLO The WELCOME HOME Experience.!! Simply better homes!! HANLO The WELCOME HOME Experience!! Simply better homes!! The Mission Our mission is to provide individual, sustainable and affordable homes to self builders and developers that can be built fast, efficient

More information

Energy Efficiency HOSPITALITY. www.energia.ie

Energy Efficiency HOSPITALITY. www.energia.ie Energy Efficiency HOSPITALITY www.energia.ie Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could make a real

More information

The A-rated Energy-Efficient Concrete Home

The A-rated Energy-Efficient Concrete Home Concrete Built is Better Built Concrete is present in almost every home in Ireland. Its strength, durability, fire resistance, sound insulation and water resistant qualities make it indispensable in foundations,

More information

Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in

Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in REV 1-12.12.11/TB002 Technical Bulletin Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in conjunction with TRADA Technology and is intended to provide the reader with introductory

More information

URSA GLASSWOOL URSA Cavity Batts

URSA GLASSWOOL URSA Cavity Batts Cavity Batts 065_Layout 1 13/07/2015 14:43 Page 1 UK LTD Crest House 102-104 Church Road Teddington, Middlesex TW11 8PY United Kingdom Tel : 020 8977 96 97 Fax : 020 8977 94 56 Web : www.ursa-uk.co.uk

More information

Building Control Guidance Note

Building Control Guidance Note Issued 01/01/13 Rev Page 1 of 5 If you intend to convert an existing loft space into additional rooms you will need to apply for Building Regulation Approval. You may also need Planning Permission if you

More information

ENERGY STATEMENT for a proposed new residential care home at Great North Road, Doncaster, South Yorkshire, DN6 7EJ

ENERGY STATEMENT for a proposed new residential care home at Great North Road, Doncaster, South Yorkshire, DN6 7EJ ENERGY STATEMENT for a proposed new residential care home at Great North Road, Doncaster, South Yorkshire, DN6 7EJ Ref. No: 12/02870/FULM Contents 1. General... 2 2. Planning Condition... 2 3. Development...

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate Flat 2 Bagshot House Redhill Street LONDON NW1 4BY Dwelling type: Date of assessment: Date of certificate: Reference number: Total floor area: Ground-floor flat 09 April

More information

GILLING ROAD, RICHMOND, NORTH YORKSHIRE

GILLING ROAD, RICHMOND, NORTH YORKSHIRE GILLING ROAD, RICHMOND, NORTH YORKSHIRE This is a development of four new sympathetically designed deceptively spacious, semi-detached family properties. High Energy Efficiency Rating. Parking Small Front

More information

Environmental drivers & opportunities:- Impacts on housing sector in UK

Environmental drivers & opportunities:- Impacts on housing sector in UK Dr. Vahik Enjily International Director Building Research Establishment (BRE) Watford, England Environmental drivers & opportunities:- Impacts on housing sector in UK Die britische Bauwirtschaft und ihre

More information

Sports Buildings: budget costs for the Flood Relief Fund

Sports Buildings: budget costs for the Flood Relief Fund Sports Buildings: budget costs for the Flood Relief Fund The list below provides typical costs for flood insurance works, typically required by sports clubs or facilities. The list is not exhaustive but

More information

PRESTRESSED CONCRETE FLOORING BEAMS

PRESTRESSED CONCRETE FLOORING BEAMS PRESTRESSED CONCRETE FLOORING BEAMS TRIED & TRUSTED Introduction Established in 2001 TT Concrete Products Limited has become a prominent manufacturer of prestressed concrete flooring beams throughout the

More information

FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS

FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS FACTORS AFFECTING ENERGY CONSUMPTION OF BUILDINGS 1 Ralf Lindberg, Professor Minna Korpi, M.Sc. Juha Vinha, Dr.Tech. June 11, 2008 Department of Civil Engineering, Tampere University of Technology 2 BACKGROUND

More information

Energy Efficiency. Bars & RestauRants. www.energia.ie

Energy Efficiency. Bars & RestauRants. www.energia.ie Energy Efficiency Bars & RestauRants www.energia.ie 2 Your chance to reduce your business energy usage by as much as 20%! 20% is a significant figure and reducing your energy bill by this amount could

More information

Code for Sustainable Homes. A step-change in sustainable home building practice

Code for Sustainable Homes. A step-change in sustainable home building practice A step-change in sustainable home building practice www.communities.gov.uk community, opportunity, prosperity December 2006 On 5th May 2006 the responsibilities of the Office of the Deputy Prime Minister

More information

HP Partial Fill Cavity Slab

HP Partial Fill Cavity Slab CONSTRUCTION TYPE: CAVITY WALLS DECEMBER 2011 HP Partial Fill Cavity Slab Robust, long-lasting protection HP Partial Fill Cavity Slab insulation has a robust outer surface, designed to withstand on-site

More information

HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015. May 2015

HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015. May 2015 HOUSING STANDARDS POLICY TRANSITION STATEMENT IMPLEMENTATION: OCTOBER 2015 May 2015 MAYOR OF LONDON Housing Standards: Transition Policy Statement. On 25 March 2015 through a written ministerial statement,

More information

Section 3.1.2. Timber Frame Walls. Single layer between studs. Single layer between studs with service void. Between studs with insulated lining

Section 3.1.2. Timber Frame Walls. Single layer between studs. Single layer between studs with service void. Between studs with insulated lining Section Timber Frame Walls Single layer between studs Product: Earthwool FrameTherm Rolls and Slabs Tf01 Single layer between studs with service void Product: Earthwool FrameTherm Rolls and Slabs Tf02

More information

System 26 Hi+ Bi-Fold

System 26 Hi+ Bi-Fold System 26 Hi+ Bi-Fold Since 1985 Metal Technology has been defining spaces through its architectural glazing solutions and has grown to become one of the UK and Ireland s leading designers and suppliers

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate Flat 8 Ravenscourt 108-114, Richmond Road CARDIFF CF24 3BW Dwelling type: Ground floor flat Date of assessment: 26 June 2009 Date of certificate: 28 June 2009 Reference number:

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 51, Peabody Cottages Rosendale Road LONDON SE24 9DW Dwelling type: Ground floor maisonette Date of assessment: 10 December 2008 Date of certificate: 11 December 2008 Reference

More information

Beam & Block Flooring

Beam & Block Flooring Beam & Block Flooring Beam & Block FLOORING Beam and block System overview 4 Benefits 5 Installation guide 6 Construction details 7 Load span tables 8-9 Nationwide service 10-11 As part of a comprehensive

More information

Rainwater Harvesting

Rainwater Harvesting Rainwater Harvesting With climate change now a reality rather than a speculated possibility, the demand on water resources has gone up, whilst the amount of water available for supply has gone down. Forth

More information

Green House, Hungary

Green House, Hungary Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support noel.morrin@skanska.se Green House, Hungary Case Study 109 Aspects of Sustainability This project

More information

(81-91) (69-80) (55-68) (39-54) (21-38) (1-20)

(81-91) (69-80) (55-68) (39-54) (21-38) (1-20) Energy Performance Certificate 120, Loudoun Road Dwelling type: Mid-terrace house LONDON Date of assessment: 10 February 2011 NW8 0ND Date of certificate: 11 February 2011 Reference number: 8908-4305-7529-9096-6293

More information

thermal cavity closers

thermal cavity closers thermal cavity closers cavity closers thermal bridging solutions from Manthorpe THERMAL BRIDGE THERMAL BREAK Poorly insulated door and window reveals can lead to significant heat loss and damp issues.

More information

INSULATING CONCRETE FORMWORK SYSTEM. ReadyWallform BUILDING SOLUTIONS FOR THE HOUSING & COMMERCIAL SECTORS

INSULATING CONCRETE FORMWORK SYSTEM. ReadyWallform BUILDING SOLUTIONS FOR THE HOUSING & COMMERCIAL SECTORS INSULATING CONCRETE FORMWORK SYSTEM BUILDING SOLUTIONS FOR THE HOUSING & COMMERCIAL SECTORS ReadyWallform DESIGNING HOMES & BUILDINGS WITH EFFICIENCY Practical, energy efficient construction to accommodate

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 60, Lon-y-Celyn CARDIFF CF14 7BW Dwelling type: Top floor flat Date of assessment: 7 May 2009 Date of certificate: 7 May 2009 Reference number: 8311-6525-6680-8103-9002 Total

More information

BER Assessors Dwellings Technical Bulletin

BER Assessors Dwellings Technical Bulletin BER Assessors Dwellings Technical Bulletin Issue No. 2/12 April 2012 Contents: 1. SUPPLEMENTARY ELECTRIC WATER HEATING IN SUMMER... 2 2. PITCHED ROOF U-VALUE CALCULATIONS... 8 2.1. PITCHED ROOF, INSULATED

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate 10, Northfleet Road Eccles MANCHESTER M30 7PQ Dwelling type: Semi-detached house Date of assessment: 11 February 009 Date of certificate: 1 February 009 Reference number:

More information

Energy Performance Certificate

Energy Performance Certificate Energy Performance Certificate Address of dwelling and other details 4F1 27 EAST PRESTON STREET EDINBURGH EH8 9QE This dwelling's performance ratings Dwelling type: Top-floor flat Name of approved organisation:

More information

GIL23. Cavity wall insulation: Unlocking the potential in existing dwellings

GIL23. Cavity wall insulation: Unlocking the potential in existing dwellings GIL23 Further information The Energy Saving Trust sets energy efficiency standards that go beyond building regulations for use in the design, construction and refurbishment of homes. These standards provide

More information

Timber frame separation walls (party walls)

Timber frame separation walls (party walls) Appendix 8: Timber Frame Detailing This appendix illustrates with typical details major design and construction issues, which must be considered when using a timber frame approach. The details shown are

More information

APPROVALS. Jabfill has been assessed and approved by the British Board of Agrément for use in cavity walls to

APPROVALS. Jabfill has been assessed and approved by the British Board of Agrément for use in cavity walls to Section Cavity-Wall Insulation: Full-Fill is a cavity-wall insulation system designed to be incorporated into new masonry walls during construction to satisfy the Building Regulations U-value requirements.

More information

Section 4.3. Separating Floors. Timber frame floor with I-Beams. Upgrading existing timber floor with new ceiling. Timber frame floor with

Section 4.3. Separating Floors. Timber frame floor with I-Beams. Upgrading existing timber floor with new ceiling. Timber frame floor with Section Separating Floors Timber frame floor with I-Beams Product: Earthwool Acoustic Roll and Floorfoam Easy Edge Strip Timber frame floor with solid timber joists Product: Earthwool Acoustic Roll and

More information

Thermablok Aerogel Insulation Blanket Thermablok Aerogel Blanket

Thermablok Aerogel Insulation Blanket Thermablok Aerogel Blanket Uniclass 68152 Thermablok Aerogel Insulation Blanket Ultra Thin Internal Solid Wall, Ceiling & Floor Insulation Systems for New Build & Refurbishment Unique insulation with the lowest Thermal Conductivity

More information

V2/0815/CWI/TD02. KORE Fill Cavity Wall Insulation. Wall Insulation Design Guide

V2/0815/CWI/TD02. KORE Fill Cavity Wall Insulation. Wall Insulation Design Guide V2/0815/CWI/TD02 Cavity Wall Insulation Wall Insulation Design Guide Bonded Bead Key Features Meets and exceeds building regulations Suitable for passive house construction Installed by insulation experts

More information

Integrated Solar Radiant Systems

Integrated Solar Radiant Systems Integrated Solar Radiant Systems William Shady PE President Topics Radiant heating Indoor air quality Radiant Cooling Project Photos Questions and answers The goal for our clients Healthy Comfort Why Radiant

More information

plumbing products guide

plumbing products guide plumbing products guide radiator pipe guide & seals A significant development in the drive to reduce air leakage and heat loss. Installations such as that shown are all too common. The detail is poorly

More information

DOM 8: GUIDE TO THE DESIGN OF ELECTRIC SPACE HEATING SYSTEMS FEBRUARY

DOM 8: GUIDE TO THE DESIGN OF ELECTRIC SPACE HEATING SYSTEMS FEBRUARY DOM 8: GUIDE TO THE DESIGN OF ELECTRIC SPACE HEATING SYSTEMS FEBRUARY 2006 The Electric Heating and Ventilation Association Westminster Tower, 3 Albert Embankment, London SE1 7SL t: +44 (0) 20 7793 3008

More information

ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests

ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests ANSI/ASHRAE Standard 140-2004 Building Thermal Envelope and Fabric Load Tests DesignBuilder Version 1.2.0 (incorporating EnergyPlus version 1.3.0) - June 2006 1.0 Purpose The ANSI/ASHRAE Standard 140-2004

More information