PUBLIC PRIVATE PARTNERSHIP: A SERVICE INNOVATION The Treasury Building case

Size: px
Start display at page:

Download "PUBLIC PRIVATE PARTNERSHIP: A SERVICE INNOVATION The Treasury Building case"

Transcription

1 PUBLIC PRIVATE PARTNERSHIP: A SERVICE INNOVATION The Treasury Building case Jean Carassus, Centre Scientifique et Technique du Bâtiment (CSTB).Paris, France. carassus@cstb.fr Abstract A Public Private Partnership (PPP) contract combines the competences of a client, a bank, a designer, a construction company and a facilities manager, to finance, design, build and manage a building or an infrastructure. It is a service innovation analysed through a case study: the PPP/PFI Treasury Building refurbishment and operation project in London. The analysis method is the Barcet and Tannery one [1], specifying the service as an aim, as a concept, as a process and using specific means and resources. PPP is a process service innovation, following a methodological trajectory, which is the result of a change of competences and technical (material and immaterial) characteristics [2]. The main innovation through PPP is the combining of usually separated competences: client, architect, construction firm, facilities managers and users. This combining of competences is revolutionary in an industry where design and build have been for a long time separated from facilities management and use. This combining competences innovation is just beginning through a quite long learning by doing process. Keywords: Public Private Partnership, service innovation, service key performance indicators, competences, facilities management. 1. Introduction Most of the time, government or local authorities fund public buildings and infrastructures, and the building of the facility and its operation after completing are separated. On the one hand, the construction of the facility is provided by designers and construction firms through public procurement (design bid build, design and build, construction management)1, on the other hand, 1 for a comparison between the different procurement procedures, see for example Konchar and Sanvido [3] for the US and UK procurement processes and the special issue of Building Research and Information, edited by Graham Winch, on procurement procedures in the European Union [4]. 647

2 the public authority manages the operation and maintenance of the facility itself and with sub contractors (for heating, lifts, cleaning ). Public private partnership (PPP) is a new way to finance, build and manage public buildings and infrastructures. Usually, in a PPP process, the public authority negotiates, through a competitive procurement process, a single contract with a private consortium specifying the funding, the design, the construction and the operation, for ten to forty years, of the facility. The public authority pays the investment and the operation through annual rents after the completion of the building. When the contract is achieved after ten to forty years, the facility is owned by the public authority. PPP is a feature of ongoing change of the construction sector, from the structures to the service [5] [6]. 2. A service innovation Even if the facility may be different on technical aspects through PPP, in comparison with a usual public procurement, this new way is obviously not a technological innovation. It is a service innovation Gallouj [2] has highlighted five kinds of services, namely: «quasi products» (whenever the service is highly standardized), operational or manual services, informational or relational services, intellectual or professional services, and finally the packages of products and services. The final service of a PPP process is the package of a product (the building) and a service (the management of the building), Sundbo s typology [7] inspired by Schumpeter s one [8] specifies four service innovation categories: Service innovations: new service, Process innovations: change in the service elaboration procedures, Organizational innovations: change in the management modes, Marketing innovations: marketing, sales, and so forth. PPP practice is a change in the package (building plus services) elaboration procedures; it is fundamentally a process innovation. Gallouj [2] defines a service as a set of characteristics and competences, the final characteristics of the service Ym resulting from the simultaneous mobilization of competences (coming from the service provider Cp and the client C q ) and technical characteristics Tn (material and immaterial). Innovations are particular movements of those competences and characteristics. 648

3 According to him, service innovations evolve according to different possible innovation trajectories, namely: the material transformation trajectory ŒM (Y), which corresponds in the alteration of the material basis of the service, the information processing trajectory ŒI (Y), corresponding to new data, new uses of data, network sharing of information, etc, the methodological trajectory ŒK (Y), dealing with the implementation of formalized methods for knowledge processing, the «pure» service trajectory ŒC (Y) corresponds to the direct mobilization of competences, regardless of any material, informational or methodological support. PPP is a service innovation evolving essentially according to a methodological trajectory through formalized methods, even if it normally makes necessary the use of new data and if alters the material basis (the building) through life cycle cost design. We will highlight the weight of the implementation of new formalized methods used to specify and to control the PPP process. We have already analysed service innovations in the construction sector [9] [10]. How to analyse PPP as a service innovation? To study and set up a service innovation, Barcet and Tannery [1] suggest a method in four analysis levels summed up in the following table. 649

4 Table 1. The service innovation analysis method Analysis level Question Topic Meaning 1. The client What for? The functionalities The service as an aim system Whom for? 2. The result of the performance What? The service product The service as a concept 3. The supply system How? The performance The service as a process 4. The means and resources What with? The tools, methods, information, technical means, skills, competences To implement, or to obtain, means and competencies From Barcet and Tannery (1998) To be more specific, a PPP case will be analysed: the refurbishment and the operation of the Treasury Building in London. This project is one of the ten PPP cases studied in the UK, Italy, Denmark and France, by a French team, assisted by European experts [11] 2. The project is one of the notable British Project Finance Initiative (PFI) investments, in the political frame specified by the Conservative government in 1992, amended by the Labour government in The service as an aim The first analysis level is the service as an aim, the client system. Her Majesty Treasury (HMT) had three main goals through this PPP/PFI refurbishment project of its head offices: To spread the payment of a significant investment, in a context of low level of financial public means, To design a building to back a new business process in the ministry, focused on a team and network way of working more than a hierarchical one, To provide a high level of day to day service to the employees. Usual public procurement systems do not allow differed payment of a public investment. Conversely, to design a building to back a new business process and to provide a high quality service to the end users are normally possible through usual public procurement procedures. 2 Then this team made the framework of a French Public Sector Comparator (PSC), available at igd.org/ [12] and the PSC dedicated to the French hospitals. This PSC is included in the French PPP guide for hospitals, available at [13] 3 On recent evolution of British PFI, see Allen et alii [14], Weill and Biau [15], and the following websites: [16], [17], [18]. 650

5 4. The service as a concept The second analysis level is the service as a concept, the service product. The concept offered by the PPP/PFI process has two main characteristics: The private partner pays the investment, the public authority spreads the reimbursement through rents paid during a long period, the first rent being paid after the completion of the building, A single team, dealing with the funding, the design, the construction and the facilities management is responsible for the package, refurbished building plus the services provided for a long period. This concept, in comparison with the usual public processes, is a very innovative one: commonly public procurement plans a payment of the investment by the public authority during the design and construction time, and separated processes for construction and facilities management. 5. The service as a process The third analysis level is the service as a process, the supply system. The PPP/PFI process has four main characteristics: A new procurement system with, in the case of the Treasury Building, two tenders: one for the package building and services, one for the funding, A transfer of risks from the public authority to the private consortium, The valuation of the transferred risks in the amount of the rent, A long term partnership between the two parties. In 1995, an invitation to tender was issued for the refurbishment and operation of the HM Treasury s offices in London. Exchequer Partnership was selected in September 1996 as preferred bidder after a competitive procurement process, but Labour Government elected in 1997 considered it inappropriate to proceed at that time. Following a review of the project a contract was signed in August HMT had also to set up a new tender on funding which was concluded in January 2000 [19]. The facility was successfully delivered one month early in July 2002, when payment of the unitary annual charge for 35 years commenced. The two parties negotiated a complex contract specifying the package design, refurbishment, hard and soft facilities management by Exchequer Partnership (EP), a Special Purpose Vehicle Company, created by a construction company (Bovis Lend Lease), a developer (Stanhope) and a facilities manager (Chesterton), and the funding through index linked bonds insured by Ambac 651

6 (monoline insurer). Johnson Workplace then controlled Chesterton. The facilities manager was no longer EP s shareholder. Forster and Partners are the architects of the project. Figure 1 sums up the present construction and property business system. We have studied the first half of the refurbishment, the second one, specified by another PFI contract with the same partners, is in progress. The risks allocated to the private consortium are: Obtaining Planning permission and listed building consents, Design and construction compliance to achieve the occupier brief and deliver output brief performance, 652

7 Bovis Lend Lease (construction firm and hard facilities manager) Stanhope (developper) 50% 50% Ambac (monoline insurer) Index linked bonds HM Treasury (client) 35 years service contract Exchequer Partnership (Special Purpose Vehicle Company) Funding contract 95% 5% Design and Build contract 35 years hard facilites management contract 35 years soft facilities management contract Shareholders Bovis Lend Lease Forster and Partners Bovis Lend Lease (construction branch) Bovis Lend Lease (hard facilities management branch) Johnson Workplace (soft facilities manager) Stanhope Figure 1. Treasury Building PPP/PFI project : the construction and property business system 653

8 Construction and latent defects risk, which was significant in a poorly maintained 100 year old building, Service delivery risk, which lasts through the life cycle of the facility. Many of these risks were then re allocated to the FM sub contractors by Exchequer Partnership (EP), although these risks were capped and above a threshold are retained by EP, Bankruptcy risk. Should EP fail, Ambac are obliged to step in to assure service delivery, Regulatory changes requiring changes in the output or occupier briefs, Letting risk i.e finding a tenant for other half of the building. The risks shared include inflation, in that the unitary charge is index linked. The risks retained by the Treasury include changes in user requirements implying changes in the output or occupational briefs other than those required due to changes in national regulations. The valuation of the project and the transferred risks is embodied in an annual unitary charge of 14M during 35 years. The cost of the project was 141M, of which 112M represents design and refurbishment. The amount of 29M corresponds to the negotiation costs and the funding costs, among them, preparation and negotiation costs were about 7M for Exchequer Partnership. The PPP/PFI process involves a long term partnership between the parties. According to the interviewees, this partnership works very well. In our opinion, success factors for such a partnership are: The willingness of the parties for the success of the HMT head offices refurbishment in a PFI process, The high level competences of the partners, The quality of the tools and methods (see infra) The profitability of the contract for the private partner. No specific information is available on the profitability, but we think that it is very difficult to manage a serene partnership, when the contract has been under priced by the private partner and is not profitable4. 6. The methods and the competences We are dealing now with the fourth analysis level suggested by Barcet and Tannery (1998), the means and resources one: tools, methods, information, technical means, skills, competences. Our analysis highlights five aspects dealing with the means and resources: The competitive procurement process, The funding method, The occupier brief and associated tools, 4 See for instance the problems of the under priced STEPS deal between Inland Revenue and Mapeley [20]. 654

9 The output brief and tied tools, The combining of usually separated competencies. We will also underline some lacks, especially the need of operating costs data bases. We did not get into details to analyse the competitive procurement process because we chose to study the Treasury Building case more than one year after completion of the refurbishment. In opposition to the usual procurement one, the PPP competitive procurement process is a performance based one. The occupier brief and the output brief specify the results to be obtained but do not define the solutions to meet them. The private partner elaborates the practical means to reach the objectives and to measure the output. The counterpart of this very productive process is the time and the cost. The negotiation between the public authority and the preferred bidder is long and pricey. The complexity of the long term contract explains a part of the cost, but solutions have to be fund to moderate the cost of PPP/PFI contracts5. The Labour government asked HMT to set up a separate tender for funding. An opportunity to innovate was created. Bank financing and bond financing competed. One solution was funds provided by one or several banks, through a negotiation between the project company and the bank. The other solution was funds provided by bond investors, through an agreement via an intermediary, a bond arranger. Bond financing was chosen for three reasons (NAO 2001): The project length, at 37 years, including design and construction, is 4 years longer than the longest period for which banks would have been willing to lend, Index linked finance can be cheaper than fixed rate finance and favours bonds, Monoline insurance of a bond reduces the interest rate bonds investors will require and increases the attraction of a wrapped, or insured, bond finance relative to bank borrowing. Although bond financing was more competitive than bank financing at the time of Treasury funding competition this may not be always the case. The occupier brief described the required functionality of the facility in technical terms. As we noticed one objective of HMT was a design to back a new business process in the ministry, focused on a team and network way of working more than a hierarchical one. This involved an occupier brief focused on a shift from wholly cellular to partially open plan offices. This activity included a pilot open plan office. This choice and technical aspects were discussed in many meetings between the design team and Treasury staff, dealing with space design, access control and security, health and safety, information technologies, lift, signage and way 5 Public task forces promoting the best practices, technical expertises put in common, free practical PPP guides, standardised contracts or parts of contracts, control of the cost of the advisers are some solutions; but the problem is complex. We just notice that PPP can also concern, like in Italy, small and non complex projects involving local authorities and regional construction firms, without many advisers. 655

10 According to the architects, the quality of the occupier brief is one of the success factors of the project. After completion of the refurbishment, the Post Occupation Evaluation is the tool in relation to the occupier brief. This survey, made six months after moving in, dealt with: Place: aesthetics, temperature, lighting, cleanliness, workplace, space for concentrated work, space for collaborative work, Technology and services: telephones, filing, printing, shredders, information technologies, catering, reception, People and processes: feelings, communication, openness and transparency, flexibility in working practices, productivity and innovation. The level of satisfaction was high: 83 % of respondents said that their working environment had improved in terms of functionality and afforded more opportunities for collaboration. Some critics concerned temperature monitoring, noise and privacy. To change attitudes regarding the suitability of open areas for private conversations was wished. The output brief and tied tools sound very innovative. The output brief deals with the facilities management issues in terms of the service delivered to the users. Facilities management deals with eleven topics: Hard services: Mechanical, Electrical, Plumbing (MEP), lifts, building fabric, pest control, furniture, Soft services: security, cleaning, catering, waste management, help desk and general facilities management being used for hard and soft FM. A Performance Incentive Scheme specifies service and availability deductions. Service deductions concern 38 hard and soft facilities management components and are measured by 80 Key Performance Indicators (KPI). The 67 type one indicators involve financial penalties, the 13 type two indicators do not involve financial penalties. 656

11 Performance Incentive Scheme Service deductions Availability deductions 38 Components 80 Key Performance Indicators Type 1 Type 2 Number of failures Measure of impact Building access Building loss, damage Legislative failure Security failing Failing to maintain temperature, lighting, ventilation, Failure of draining plumbing drinking water supplies, life safety systems, structured cabling, Power failure, Non compliance to Health & Safety legislation Figure 2. The Performance Incentive Scheme Source: Exchequer Partner Audits of FM made four times per year by the monocline insurer and permanent control by HMT facilities managers fill up this rather sophisticated service control system. The last topic dealing with methods and competences concerns maybe the most potentially innovative aspect of PPP: the combining of usually separated competences. Figure 3 sums up the separation of the different mobilized competences in separate contracts in a Design Bid Build process. Figure 4 illustrates the combining of the mobilized competences through a PPP long term contract. The client as investor and as facilities manager, the architect, the construction firms, the facilities management subcontractors work usually in a separate way. 657

12 Client as investor Design contract(s) Works contract(s) Designer Construction firms Employer Employees Client as facilities manager Maintenance and operation contracts Sub contractors Figure 3. The separated competences in a Design Bid Build process Client PPP long term contract Consortium Employer Employees Funder Designer Construction firm Facilities manager Figure 4. The combined competences in a PPP process 658

13 The PPP process obliges them to work together, the result of this combined work being written down in a long term contract. For the first time, the architects designed a building by working with the users and the facilities managers. They told us that this process forced them to look at the project in a new way. The combined competences of the architects and the facilities managers allowed to improve many aspects of the project: heat summer, ventilation, lighting, windows curtains, wall paint, carpet quality etc. The sophisticated service control system is also the result of combined competences of the client and the facilities managers. The players are not used to do so. PPP is a learning by doing process which requires time to learn how to combine the competences. This implies a cultural revolution in the construction industry. For ages, construction and facilities management have been separated. New ways to work together as client, architect, construction firm, facilities managers have to be invented. This also makes new tools necessary. For example, operation costs data bases are needed. Such data bases, giving the maintenance and operation costs and the link between them and the investment costs, are necessary. There must be practical life cycle costs data bases for each kind of building (offices, hospitals, schools, prisons ), based on real costs, not theoretical ones. Those data bases and contract contents could be designed in a sustainable way, with new incentives, for example the gains of energy consumption being shared between the public and the private partners. Long term PPP contracts are a very good opportunity to design, build and manage buildings in an environmental friendly way. 7. Conclusion The Barcet and Tannery (1998) method offers a comprehensive view of a service innovation. Success factors concern each of the four analysis levels. The players have to answer very clearly the strategic questions dealing with the service innovation: What for? What whom? What? How? What with? The high level quality of the tools and the combined mobilized competences are key success factors of the innovation. We agree with Gallouj (2002) when he specifies a service innovation as the result of a change of the service provider s and client s competences, and technical (material and immaterial) characteristics of a process. The analysis of a PPP/PFI project, such as the Treasury Building one, a process service innovation following a methodological trajectory, confirms this definition. The potential of innovation through PPP sounds high. The main innovation is the combining of usually separated competences. This combining of competences is revolutionary in an industry where construction has been for a long time separated from facilities management and use. The efficiency of the PPP process is that the players are obliged to write down in a long term contract the result of their innovative cooperation. 659

14 Innovation is just beginning. Practices will change progressively. Some innovations are still potential, such as practical life cycle costs data bases and long term sustainable facilities management. Actually many PPP innovations could be used to improve the usual Design Bid Build and facilities management processes. Accurate occupier and output briefs, cooperation with the facilities managers and the users, financial incentives to make the works time shorter, multi service contracts, performance indicators, financial incentives for efficient operation are examples of PPP best practices which could be employed to improve usual procurement and facilities management processes. 8. Acknowledgements I would like to thank, for all the information given through interviews: Mr Nick Gray, Faithful & Gould, Mr Thomas Huw and Philipp Eichstadt, Forster and Partners, Mr Barry Kearton, Chesterton, Mr Paul Lewis, Stanhope, Exchequer Partnership, Mr Richard Lewis, Bovis Lend Lease, FM branch, Mr Karen Mangroo, Exchequer Partnership, Mr Paul Pegler, HM Treasury. I would like to express them all my deep gratitude. Nevertheless, I alone am responsible for the text and any errors in this paper. References [1] Barcet A. and Tannery F. (1998), Innovation de service. Synthèse du Séminaire ANVIE, Paris : Centre National de la Recherche Scientifique (CNRS). [2] Gallouj, F. (2002), Innovation in the Service Economy: the new wealth of nations, London: Edward Elgar Publishers. [3] Konchar, M.D. and Sanvido, V.E. (1999), A Comparison of US and UK Project Delivery Systems. In Bowen, P. and Hindle, R (eds) Consumer Satisfaction: A focus for research and practice. CIB W 55 & W 65 Joint Triennal Meeting. [4] Winch, G. (special editor guest), Construction business systems in the European Union, special issue of Building Research and Information, 2000, 28 (2). [5] Carassus, J. (2002) Construction : la mutation. De l ouvrage au service, Paris : Presses des Ponts et Chaussées. [6] Carassus, J. (ed) (2004), Construction sector system: an international comparison. CIB W55 W65 Construction industry comparative analysis Project Group report, CIB Publication 293, available at [7] Sundbo, J. (1998), The organisation of innovation in services, Roskilde: University Press. 660

15 [8] Schumpeter, J. (1934), The Theory of Economic Development, French translation, Paris: Dalloz, [9] Carassus, J. (2003), Construction sector system and innovation in stock management, in Uwakwek, B.O. and Minkarah, I. A. (eds), Construction Innovation and Global Competitiveness, University of Cincinnati, CIB, Boca Raton: CRC Press. [10] Carassus, J. (2004), Construction sector system, innovation and services. CIB Congress Proceedings. Toronto. Canada. [11] Bougrain, F., Carassus J., Colombard Prout M. (2004), with the support of Antonini E., Koch C., Winch G., Partenariat Public Privé et bâtiment en Europe : quels enseignements pour la France? Retours d expériences du Royaume Uni, d Italie, du Danemark et de France, Paris : Plan Urbanisme, Construction, Architecture (PUCA) and Centre Scientifique et Technique du Bâtiment (CSTB), to be published in 2005 by Paris : Les Presses de l Ecole Nationale des Ponts et Chaussées. [12] Institut de la Gestion Déléguée, (2004), Evaluation des contrats globaux de partenariat (PPP contracts evaluation), available at igd.org/ (2004 April 22 nd Report). [13] Mission nationale d Appui à l INvestissement Hospitalier (MAINH), (2005), Guide du Bail Emphytéotique Hospitalier (PPP Hospital Guide), available at [14] Allen S., Abbott C., Lenard, D. (2003), Private Finance and Public Private Partnership: a Review, Centre for Construction Innovation, UMIST, Salford University. [15] Weill S. and Biau V. (2003), Le développement de la procédure de PPP/PFI en Grande Bretagne, Paris: Mission Interministérielle pour la Qualité des Constructions Publiques (MIQCP). [16] PPP/PFI UK central task force. [17] PPP/PFI UK task force for the local authorities, [18] UK National Audit Office reports, [19] NAO (2001), Innovation in PFI Financing :The Treasury Building Project, available at [20] NAO (2004), PFI: The STEPS deal, available at 661

Executive Part- Time Master Real Estate, Building & Energy. Jean Carassus & James Gilbert Director & academic head

Executive Part- Time Master Real Estate, Building & Energy. Jean Carassus & James Gilbert Director & academic head Executive Part- Time Master Real Estate, Building & Energy Jean Carassus & James Gilbert Director & academic head Summary 1/ Objectives, ambition, target 2/ An accredited post- graduate programme 3/ Active

More information

Executive Part-Time Master Real Estate, Building & Energy. Jean Carassus & James Gilbert Director et academic head January 2013

Executive Part-Time Master Real Estate, Building & Energy. Jean Carassus & James Gilbert Director et academic head January 2013 Executive Part-Time Master Real Estate, Building & Energy Jean Carassus & James Gilbert Director et academic head January 2013 Summary 1/ Objectives, ambition, target 2/ An accredited post-graduate programme

More information

Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk. Respondent details. Mark Redhead. Head of Policy

Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk. Respondent details. Mark Redhead. Head of Policy REFORM OF THE PRIVATE FINANCE INITIATIVE RESPONSE Please send your responses via email, to: PFIevidence@hmtreasury.gsi.gov.uk The deadline for responses is Friday 10 February 2012. Respondent details Your

More information

Appendix 5D Ernst & Young Accounting Treatment

Appendix 5D Ernst & Young Accounting Treatment Appendix 5D Accounting Treatment (Ernst & Young) Appendix 5D Ernst & Young Accounting Treatment Introduction An off balance sheet treatment from the position of the Authorities is a fundamental requirement

More information

private finance initiative

private finance initiative private finance initiative Lessons Learned We recently held a series of PFI Roundtable Discussions in collaboration with Trowers & Hamlins LLP. Finance managers from throughout the UK were invited to share

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

2.6 Select a. procurement route. cabe. Contents

2.6 Select a. procurement route. cabe. Contents 2.6 Select a procurement route 2.6.1 Procurement routes Procurement is the purchasing of products, work and services. It is more important than its unglamorous name suggests and plays a major part in any

More information

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice Department of Health PFU & PPP Forum Benchmarking and market testing in NHS PFI projects Code of Best Practice This Code of Best Practice provides guidance and advice on good practice to NHS Trusts, Project

More information

TAXATION OF PRIVATE LANDLORDS

TAXATION OF PRIVATE LANDLORDS TAXATION OF PRIVATE LANDLORDS The Tax Position of the Small Private Landlord The private rented sector is possibly the only sector of the economy where the tax and regulatory systems work to prevent the

More information

PPP Seminar : Health Royal Liverpool Hospital Case study

PPP Seminar : Health Royal Liverpool Hospital Case study PPP Seminar : Health Royal Liverpool Hospital Case study Gavin Quantock Deloitte Corporate Finance 23 July 2014 Case study Royal Liverpool hospital PPP and Health Background Deloitte involvement Structure

More information

CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE

CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE Professor Mustafa Alshawi 11/20/2009 Chairman Iraq Institute for Economic Reforms (IIER) Baghdad,

More information

Availability Payment Mechanisms For Transit Projects ADVISORY

Availability Payment Mechanisms For Transit Projects ADVISORY Availability Payment Mechanisms For Transit Projects ADVISORY Agenda Availability Payments Overview Structure Financial Implications Case Study Additional Considerations KPMG Infrastructure 2 What is an

More information

Democratic and Popular Republic of Algeria Ministry of Energy and Mining

Democratic and Popular Republic of Algeria Ministry of Energy and Mining This translation is provided for information purposes only and have no legal force. The french version will prevail Democratic and Popular Republic of Algeria Ministry of Energy and Mining National Agency

More information

THE PRIVATE DELIVERY OF PUBLIC SERVICES

THE PRIVATE DELIVERY OF PUBLIC SERVICES THE PRIVATE DELIVERY OF PUBLIC SERVICES Report of seminar 143 held on 3rd June 2008 at Freshfields Bruckhaus Deringer, London SUMMARY KEY CONCLUSIONS The PFI market in the UK is now mature, with over 600

More information

Guidance Note: Calculation of the Authority s Share of a Refinancing Gain

Guidance Note: Calculation of the Authority s Share of a Refinancing Gain Guidance Note: Calculation of the Authority s Share of a Refinancing Gain 1.1 INTRODUCTION 1.1.1 Clause 34.6 of the model clauses on Refinancing set out in Section 34.8 of Standardisation of PFI Contracts

More information

Postgraduate Strategic Facility Management

Postgraduate Strategic Facility Management Postgraduate Strategic Facility Management THE STRATEGIC IMPORTANCE OF FACILITY MANAGEMENT Managers are aware of the strategic importance of Facility Management. The finding that Facility Management after

More information

SUPPLEMENTARY GREEN BOOK GUIDANCE

SUPPLEMENTARY GREEN BOOK GUIDANCE SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance

More information

Bidding / Contracts General Information

Bidding / Contracts General Information Bidding / Contracts General Information We have provided this information sheet on various requirements and terminology when bidding on or completing various service and/or construction contracts for the

More information

Y O U R A N N U A L S E R V I C E C H A R G E E X P L A I N E D

Y O U R A N N U A L S E R V I C E C H A R G E E X P L A I N E D Y O U R E X P L A I N E D 02 Contents What is an annual service charge? 03 How we set up service chargeable accounts 04 Service chargeable items and descriptions 05 Understanding the paperwork 06 Annual

More information

Facilities Management Shared Learning Seminar

Facilities Management Shared Learning Seminar Facilities Management Shared Learning Seminar How the National Procurement Service Can Help Welsh public services to improve their Facilities Management 1 st May 2014 Overview of the National Procurement

More information

How are companies currently changing their facilities management delivery model...?

How are companies currently changing their facilities management delivery model...? Interserve and Sheffield Hallam University market research 2012 Page 2 www.commercial.interserve.com How are companies currently changing their facilities management delivery model...? we have a strategy

More information

HICL Infrastructure Company Limited. Case Study. Queen Alexandra Hospital. September 2010. www.hicl.com 1

HICL Infrastructure Company Limited. Case Study. Queen Alexandra Hospital. September 2010. www.hicl.com 1 HICL Infrastructure Company Limited Case Study Queen Alexandra Hospital September 2010 www.hicl.com 1 Queen Alexandra Hospital ( QAH ) a PFI project case study Queen Alexandra Hospital ( QAH ) PFI project

More information

Policy Recommendations for Managing Risk in Social Innovation

Policy Recommendations for Managing Risk in Social Innovation European Policy Brief Policy Recommendations for Managing Risk in Social Innovation LIPSE: Learning from Innovation in Public Sector Environments (Work Package 4) Sophie Flemig (University of Edinburgh)

More information

Framework Policy for the Governance of Major Public Infrastructure Projects

Framework Policy for the Governance of Major Public Infrastructure Projects Framework Policy for the Governance of Major Public Infrastructure Projects Framework Policy for the Governance of Major Public Infrastructure Projects For further information on the Framework Policy for

More information

How To Manage Construction In Brazilian Building Construction

How To Manage Construction In Brazilian Building Construction Linking quality management, teamwork and integration to define a new model of design management for building construction S. B. Melhado silvio.melhado@poli.usp.br Dept. of Civil Construction Eng., Escola

More information

Service Failure Points and Replacement of Sub-Contractors

Service Failure Points and Replacement of Sub-Contractors PFI GUIDANCE NOTE Service Failure Points and Replacement of Sub-Contractors In recent PFI deals, issues have arisen in relation to what happens if a poorly performing service provider is replaced. In particular,

More information

Future delivery of BIM-based & standard-based applications and services: an insight in French and European developments. A vision from CSTB

Future delivery of BIM-based & standard-based applications and services: an insight in French and European developments. A vision from CSTB Future delivery of BIM-based & standard-based applications and services: an insight in French and European developments A vision from CSTB CIB IDDS FIATECH Workshop Westin Arlington Gateway Hotel in Ballston,

More information

BRISTOL CITY COUNCIL. Cabinet. 27 November 2008

BRISTOL CITY COUNCIL. Cabinet. 27 November 2008 AGENDA ITEM NO 16 BRISTOL CITY COUNCIL Cabinet 27 November 2008 Report of: Title: Ward: Strategic Director of Transformation Improving ICT Resilience : Data Centre II N/A Officer Presenting Report: Head

More information

Performance audit report. Ministry of Education: Management of the school property portfolio

Performance audit report. Ministry of Education: Management of the school property portfolio Performance audit report Ministry of Education: Management of the school property portfolio Office of the Auditor-General Private Box 3928, Wellington Telephone: (04) 917 1500 Facsimile: (04) 917 1549

More information

operating under private management, but with payments from the public to the private partner much higher than initially contracted.

operating under private management, but with payments from the public to the private partner much higher than initially contracted. BEST PRACTICE UNECE PPP Newsletter Issue 3 PPP hospitals and the Portuguese experience Mr. Rui Sousa Monteiro, Senior Economist PPP Unit, Parpública SA, Portugal Mr. Rui Sousa Monteiro is one of the region

More information

Evaluating public-private partnerships

Evaluating public-private partnerships RAMAU - Réseau Activités et Métiers de l Architecture et de l Urbanisme Evaluer les partenariats public-privé Evaluating public-private partnerships Session 2 : L impact des PPP sur la qualité des bâtiments

More information

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project

P3 Value for Money Assessment and Project Report. Evan Thomas Water and Wastewater Treatment Facility Project P3 Value for Money Assessment and Project Report Evan Thomas Water and Wastewater Treatment Facility Project July 2013 Table of Contents 1. Summary: Using a P3 for a Water Treatment Plant - did it work?

More information

Professional Practice Commission: March 2013. Alternative Project Delivery Systems

Professional Practice Commission: March 2013. Alternative Project Delivery Systems Professional Practice Commission: March 2013 Alternative Project Delivery Systems UIA Accord Building project delivery systems. Definition Building project delivery systems are defined as the contractual

More information

Data Centre Construction. Paul Jayson - Partner 20 March 2012

Data Centre Construction. Paul Jayson - Partner 20 March 2012 Data Centre Construction Paul Jayson - Partner 20 March 2012 Buy Benefits Control over facilities that handle and store data Bespoke rather than generic design and housing Security Disadvantages Build

More information

Facilities Management in Kuwait. Opportunities, challenge and added value. Kuwait Municipality

Facilities Management in Kuwait. Opportunities, challenge and added value. Kuwait Municipality Kuwait Municipality Facilities Management in Kuwait Opportunities, challenge and added value Presented by: Osama Alduaij Daputy Director General Kuwait Municipality Facilities Management A PROVEN PROCESSFOR

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

NPD Model Explanatory Note

NPD Model Explanatory Note NPD Model Explanatory Note December 2011 FOREWORD In recent years a number of public authorities in Scotland have procured privately financed infrastructure projects using the non-profit distributing or

More information

T 0845 605 55 56 F 01923 664690 E

T 0845 605 55 56 F 01923 664690 E Who should read this fact sheet? This fact sheet introduces the principles of whole life costing for organisations that are new to the subject or in the early stages of working with whole life costing.

More information

Refurbishment Mas Thibert / Arles

Refurbishment Mas Thibert / Arles Refurbishment Mas Thibert / Arles Gonzague Descoqs 13 Habitat 10th october 2012, Steering Committee, Malaga 13 Habitat, short presentation Social housing organisation, based in Marseille Around 32000 dwellings

More information

Présentation Investisseurs / Investor Presentation PROGRAMME

Présentation Investisseurs / Investor Presentation PROGRAMME Présentation Investisseurs / Investor Presentation PROGRAMME 12.15 13.30 Accueil Buffet 12.15 13.30 Welcome Buffet 13.30 17.00 SFDI, une plate-forme de croissance pour BNP Paribas - Introduction (Pierre

More information

BUILDING COST UPDATE: Q1 2014 COMMERCIAL FIT-OUT AND REFURBISHMENT

BUILDING COST UPDATE: Q1 2014 COMMERCIAL FIT-OUT AND REFURBISHMENT BUILDING COST UPDATE: Q1 2014 COMMERCIAL FIT-OUT AND REFURBISHMENT UK BUILDING CONSULTANCY COST CONSULTANCY 2014 EDITION A A 2 BUILDING COST UPDATE INTRODUCTION The construction industry is reporting activity

More information

PUBLIC-PRIVATE PARTNERSHIP (PPP)

PUBLIC-PRIVATE PARTNERSHIP (PPP) PUBLIC-PRIVATE PARTNERSHIP (PPP) Virginia Tan, Allen & Overy Type: Published: Last Updated: Keywords: Legal guide June 2012 June 2012 PPP, infrastructure assets, public and private sectors This document

More information

Standardisation of PF2 Contracts. Draft

Standardisation of PF2 Contracts. Draft Standardisation of PF2 Contracts Draft December 2012 Standardisation of PF2 Contracts Draft December 2012 Official versions of this document are printed on 100% recycled paper. When you have finished

More information

Contents. Public Sector Comparator

Contents. Public Sector Comparator Contents Introduction 7 Module 1: Inception report 17 Step 1a: basics: product, plan and parties involved 19 Step 1b: the change protocol 24 Step 1c: the communication plan 24 Module 2: Crude PSC 35 Step

More information

ST. JAMES S PLACE UNIT TRUST GROUP

ST. JAMES S PLACE UNIT TRUST GROUP ST. JAMES S PLACE UNIT TRUST GROUP SUPPLEMENTARY INFORMATION DOCUMENT PARTNERS IN MANAGING YOUR WEALTH This document sets out terms and conditions which summarise how we will manage your investment. Words

More information

Corporate governance. 1. Implementation and reporting on corporate governance. 2. IDEX s business. 3. Equity and dividends

Corporate governance. 1. Implementation and reporting on corporate governance. 2. IDEX s business. 3. Equity and dividends Corporate governance Update resolved by the board of directors of IDEX ASA on 16 April 2015. This statement outlines the position of IDEX ASA ( IDEX or the Company ) in relation to the recommendations

More information

Sustainable Assessment of Rehabilitation Works of Residential Buildings, in France

Sustainable Assessment of Rehabilitation Works of Residential Buildings, in France Sustainable Assessment of Rehabilitation Works of Residential Buildings, in France Ana Miguel CUNHA; Xavier DANIEL Group QUALITEL a.cunha@qualitel.org ; x.daniel@cerqual.fr 1 INTRODUCTION TO THE RESIDENTIAL

More information

PPP in Australia: Hospital Sector Case Study

PPP in Australia: Hospital Sector Case Study PPP in Australia: Hospital Sector Case Study Richard Foster Executive Manager, Partnerships Victoria Kylee Anastasi Consultant, World Bank Institute Knowledge Sharing on Infrastructure - Public Private

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships Budapest, Hungary March 7 8, 2007 The views expressed in this paper are those of the

More information

Quality Management System Manual Revision G

Quality Management System Manual Revision G Revision G 2800 Louis-Lumière, Suite 100, Québec (QC), G1P 0A4, CANADA Table of Contents Mission... 3 What We Do... 3 Our Values... 3 Passion... 3 Customer Focus... 3 Reliability... 3 Empowerment... 3

More information

Suggested Procedures for School Boards

Suggested Procedures for School Boards Suggested Procedures for School Boards The Chronology of a Project: Some of the steps described may not apply to certain types of projects, or might occur concurrently with others. As you confer with the

More information

6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES

6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES 6 FAM 1700 SPACE ALLOCATION AND RELATED SERVICES 6 FAM 1710 OFFICE SPACE ASSIGNMENT AND UTILIZATION, DESIGN AND CONSTRUCTION (CT:GS-174; 05-29-2013) (Office of Origin: A/OPR/RPM) 6 FAM 1711 GENERAL PROVISIONS:

More information

The certification of European construction products

The certification of European construction products The certification of European construction products Every year, SCOR Global P&C s Inherent Defects team organises a morning seminar for its clients (Matinée Décennale), during which a technical subject

More information

Comparing Alternate Procurement Operations The Case of Hospital Soft FM Service in England

Comparing Alternate Procurement Operations The Case of Hospital Soft FM Service in England Comparing Alternate Procurement Operations The Case of Hospital Soft FM Service in England Alex Murray Teaching Fellow, School of Construction & Project Management, The Bartlett, University College London

More information

How has outsourcing affected public service delivery in Hong Kong? Illustrate with relevant cases.

How has outsourcing affected public service delivery in Hong Kong? Illustrate with relevant cases. How has outsourcing affected public service delivery in Hong Kong? Illustrate with relevant cases. By Brenda Chan, David Wong, Hooly Leung, Olga Chan and Boris Siu Outsourcing through the eyes of Government

More information

FAM100-001: Review of current procurement. practice in the Facilities Management sector

FAM100-001: Review of current procurement. practice in the Facilities Management sector Executive Summary FAM100-001: Review of current procurement practice in the Facilities Management sector This report describes the procurement processes currently followed within the Facility Management

More information

R A I S I N G F U N D S I N SWEDEN

R A I S I N G F U N D S I N SWEDEN R A I S I N G F U N D S I N SWEDEN Raising funds in Sweden Sweden can offer good opportunities and many ways to raise finance for businesses. The costs of establishing a Swedish limited company are low

More information

What is Facilities Management?

What is Facilities Management? What is Facilities Management? The definition of Facilities Management is always evolving and many people and Organisations have different views. Your feedback and thoughts on the definitions below would

More information

Residential Rehabilitation Loan Program Guidelines

Residential Rehabilitation Loan Program Guidelines Residential Rehabilitation Loan Program Guidelines City of Middletown Department of Planning, Conservation and Development Community Development Division February 1999 Table of Contents Purpose 1 General

More information

BLOEMFONTEIN, SOUTH AFRICA. Case Study (Healthcare) Project Summary:

BLOEMFONTEIN, SOUTH AFRICA. Case Study (Healthcare) Project Summary: BLOEMFONTEIN, SOUTH AFRICA Case Study (Healthcare) Project Summary: The Republic of South Africa has a population of 48 million people, living in nine provinces. Since the abolition of apartheid in the

More information

Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project. Outline Business Case. Appendix 10a Soft FM Services Review

Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project. Outline Business Case. Appendix 10a Soft FM Services Review Sandwell and West Birmingham Hospitals NHS Trust Midland Metropolitan Hospital Project Outline Business Case Appendix 10a Soft FM Services Review SANDWELL AND WEST BIRMINGHAM HOSPITALS NHS TRUST PFI PROJECT

More information

Full-year trading update Support services Contract wins in the Defence and Justice sectors. 10 December 2014

Full-year trading update Support services Contract wins in the Defence and Justice sectors. 10 December 2014 Full-year trading update Support services Contract wins in the Defence and Justice sectors 10 December 2014 1 Agenda Full year trading update 2014 Carillion Services Defence sector Ministry of Defence

More information

THE FINANCIAL STRUCTURE OF PRIVATE FINANCE INITIATIVE PROJECTS

THE FINANCIAL STRUCTURE OF PRIVATE FINANCE INITIATIVE PROJECTS THE FINANCIAL STRUCTURE OF PRIVATE FINANCE INITIATIVE PROJECTS Akintola Akintoye 1, Matthias Beck 2, Cliff Hardcastle 1, Ezekiel Chinyio 1 and Darinka Asenova 2 1 Department of Building and Surveying;

More information

The refinancing of the Fazakerley PFI prison contract

The refinancing of the Fazakerley PFI prison contract Report by the Comptroller and Auditor General The Prison Service The refinancing of the Fazakerley PFI prison contract Ordered by the House of Commons to be printed 26 June 2000 LONDON: The Stationery

More information

REAL ESTATE AND RENTAL INCOME TAXATION FREQUENTLY ASKED QUESTIONS (FAQS)

REAL ESTATE AND RENTAL INCOME TAXATION FREQUENTLY ASKED QUESTIONS (FAQS) ISO 9001:2008 CERTIFIED REAL ESTATE AND RENTAL INCOME TAXATION FREQUENTLY ASKED QUESTIONS (FAQS) 1. What is considered rental income for tax purposes? Rent, a premium or similar consideration is considered

More information

ABOUT OUR SERVICES AND COSTS AND HOW WE DO BUSINESS WITH YOU

ABOUT OUR SERVICES AND COSTS AND HOW WE DO BUSINESS WITH YOU Wesleyan Financial Services Ltd Colmore Circus Birmingham B4 6AR ABOUT OUR SERVICES AND COSTS AND HOW WE DO BUSINESS WITH YOU About this document This document explains the service we offer, how you will

More information

Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases

Chapter 14 Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Special Report for the Public Accounts Committee Evergreen and Wackenhut Leases Contents Background.............................................................. 183 Scope...................................................................

More information

Contents. 1.0 Introduction 3. 2.0 Project definition 5. 3.0 Project brief 10. 4.0 Accommodation guidelines 15. 1.1 Objective 4

Contents. 1.0 Introduction 3. 2.0 Project definition 5. 3.0 Project brief 10. 4.0 Accommodation guidelines 15. 1.1 Objective 4 Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project definition 5 2.1 Pre-design studies 7 3.0 Project brief 10 4.0 Accommodation

More information

Guidance on the template contract for social impact bonds and payment by results

Guidance on the template contract for social impact bonds and payment by results Guidance on the template contract for social impact bonds and payment by results Introduction These guidance notes have been prepared to assist users of the Cabinet Office template contract. The guidance

More information

Design quality and the private finance initiative

Design quality and the private finance initiative Design quality and the private finance initiative This paper sets out CABE s perspective on the ability of the private finance initiative (PFI) to deliver well-designed public buildings, and considers

More information

Bank Payroll Tax. Technical Note, Draft legislation and Explanatory Notes

Bank Payroll Tax. Technical Note, Draft legislation and Explanatory Notes Bank Payroll Tax Technical Note, Draft legislation and Explanatory Notes 9 December 2009 1 Contents Introduction Chapter 1 Chapter 2 Chapter 3 Technical Note Draft Legislation Draft Explanatory Notes 2

More information

ASEAN Bilateral Program 2012

ASEAN Bilateral Program 2012 ASEAN Bilateral Program 2012 Presentation on PPP Financial Structures 30 October 2012 Contents Introduction Our PPP Experience Key Elements of a PPP Project Risk Allocation The Payment Mechanism Financing

More information

Factsheet 18: Insurance

Factsheet 18: Insurance Factsheet 18: Insurance When considering insurance, it can be difficult to know what is necessary and appropriate for the needs of your organisation. There are a few basic types of insurance that most

More information

Doing Business. with Hydro-Québec

Doing Business. with Hydro-Québec Doing Business with Hydro-Québec Contents A Word from the Director Procurement... 1 Introduction... 2 Hydro-Québec s Rules of Ethics... 3 Quality at Hydro-Québec... 3 Acquisition of Goods and Services...

More information

Commercial Property Investment Guide. Your guide to purchasing and managing a commercial investment property

Commercial Property Investment Guide. Your guide to purchasing and managing a commercial investment property Commercial Property Investment Guide Your guide to purchasing and managing a commercial investment property Contents Introduction 1 The benefits of commercial property investment 2 Why invest in property?

More information

2015 No. [INSURANCE] The Flood Reinsurance Scheme Funding and Administration Regulations 2015

2015 No. [INSURANCE] The Flood Reinsurance Scheme Funding and Administration Regulations 2015 Draft Regulations laid before Parliament under section *** of the Water Act 2014, for approval by resolution of each House of Parliament. S T A T U T O R Y I N S T R U M E N T S 2015 No. [INSURANCE] The

More information

HEALTH CARE ACT: The Time To Start Planning Is Now

HEALTH CARE ACT: The Time To Start Planning Is Now WINTER 2013 CONSTRUCTION INSIDER / Winter 13 HEALTH CARE ACT: The Time To Start Planning Is Now It s been nearly three years since the Patient Protection and Affordable Care Act was signed into law. And

More information

TERMS & CONDITIONS FULLY MANAGED SERVICE

TERMS & CONDITIONS FULLY MANAGED SERVICE TERMS & CONDITIONS FULLY MANAGED SERVICE For the purpose of this agreement the following definitions will apply:- Keywest Estate Agents Ltd shall be known as The Agent... shall be known as The Owner..

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

Investment income. chapter 2. Contents

Investment income. chapter 2. Contents chapter 2 Investment income Contents Introduction Examination context Topic List 1 Property income 2 Individual Savings Accounts (ISAs) 3 Enterprise Investment Scheme (EIS) 4 Venture Capital Trusts (VCT)

More information

Property Framework 2014-2018

Property Framework 2014-2018 Property Framework 2014-2018 Schedule of Services 1. Property consultancy services 2. Property Agency services 3. Estate Management services 4. Property Investment and Financial services 5. Valuation Services

More information

ST. JAMES S PLACE UNIT TRUST GROUP

ST. JAMES S PLACE UNIT TRUST GROUP ST. JAMES S PLACE UNIT TRUST GROUP SUPPLEMENTARY INFORMATION DOCUMENT PARTNERS IN MANAGING YOUR WEALTH This document sets out terms and conditions which summarise how we will manage your investment. Words

More information

How To Write An Integrated Construction Project

How To Write An Integrated Construction Project GUIDANCE FOR ENGINEERING CONSULTANCY FIRMS INTEGRATED CONTRACTS PREFACE Our industry is facing new integrated business models with increasing frequency. The processes driving these models are very different

More information

Being a Good Tenant. What is a tenant? Generally speaking, a tenant is any person who pays a landlord for the use of their accommodation.

Being a Good Tenant. What is a tenant? Generally speaking, a tenant is any person who pays a landlord for the use of their accommodation. Being a Good Tenant What is a tenant? Generally speaking, a tenant is any person who pays a landlord for the use of their accommodation. What should you look for in rented accommodation? Before renting

More information

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008

The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008 The South Africa PPP Program The Inkosi Albert Luthuli Hospital Transaction Cairo, May 25 26, 2008 1 USAID Support (1999-2005) to: Establish the PPP Unit (2000) Develop the policy/regulatory y framework

More information

Sapphire COMPANY PROFILE

Sapphire COMPANY PROFILE INTERIOR DESIGN PROJECT MANAGEMENT MAIN CONTRACTORS COMPANY PROFILE Sapphire House, 18 Gladstone Road, Croydon, Surrey, CR0 2BQ Telephone:- 020 8665 6226 Fax:- 020 8664 8927 Email:- sales@sapphirecontractors.co.uk

More information

PART VI METHODS OF PROCUREMENT AND THEIR CONDITIONS FOR USE

PART VI METHODS OF PROCUREMENT AND THEIR CONDITIONS FOR USE PART VI METHODS OF PROCUREMENT AND THEIR CONDITIONS FOR USE Selection of a method of procure ment 63.-(1) Except as otherwise provided for by these Regulations, a procuring entity engaging in procurement

More information

Agencies and Public Bodies Team Public Bodies: A Guide for Departments

Agencies and Public Bodies Team Public Bodies: A Guide for Departments Agencies and Public Bodies Team Public Bodies: A Guide for Departments Chapter 7: Financial Management Planning, Funding and Control Chapter 7: Financial Management - Planning, Funding and Control FINANCIAL

More information

A business insurance package available for self employed persons and small businesses (including limited companies) with up to 5 employees.

A business insurance package available for self employed persons and small businesses (including limited companies) with up to 5 employees. 6758_WLI354NZ_POL.qxd 17/8/04 8:49 Page 1 VENTURE PLUS Summary of Cover A business insurance package available for self employed persons and small businesses (including limited companies) with up to 5

More information

Public Private Partnership in Hospitals

Public Private Partnership in Hospitals Public Private Partnership in Hospitals Presentation to the International Health Seminar Brazil - Canada October 20, 2010 2008 The Canadian Council for Public-Private Partnerships Overview Healthcare in

More information

Bonding for Contractors. Barrie Construction Association September 17, 2015

Bonding for Contractors. Barrie Construction Association September 17, 2015 Bonding for Contractors Barrie Construction Association September 17, 2015 1 Topics What do bonds do? How does a bond benefit you? How do you get a bond? What are the information requirements? What is

More information

PROPERTY MANAGEMENT AGREEMENT [HEREINAFTER REFERRED TO AS. hereby appoint QUADRANT PROPERTY MANAGEMENT LTD

PROPERTY MANAGEMENT AGREEMENT [HEREINAFTER REFERRED TO AS. hereby appoint QUADRANT PROPERTY MANAGEMENT LTD Quadrant PROPERTY MANAGEMENT LTD Kennedy House 115 Hammersmith Road London W14 0QH Telephone 020-7386 8800 Facsimile 020-7386 0440 e-mail: managers@quadman.co.uk website: www.quadrantpm.co.uk Your Ref

More information

RC & IRS ON THE HORIZON: IN THE EUROPE UNITED STATES. risk compliance RISK & COMPLIANCE MAGAZINE. & compliance REPRINTED FROM: JAN-MAR 2016 2014 ISSUE

RC & IRS ON THE HORIZON: IN THE EUROPE UNITED STATES. risk compliance RISK & COMPLIANCE MAGAZINE. & compliance REPRINTED FROM: JAN-MAR 2016 2014 ISSUE JAN-MAR 2014 R E P R I N T risk compliance & IRS ON THE HORIZON: PARTNERSHIP DATA PRIVACY AUDIT REFORM IN THE EUROPE UNITED STATES REPRINTED FROM: RISK & COMPLIANCE MAGAZINE JAN-MAR 2016 2014 ISSUE risk

More information

PPP Basics and Principles of a PPP Framework

PPP Basics and Principles of a PPP Framework Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership

More information

Public / private mix in health care financing

Public / private mix in health care financing Public / private mix in health care financing Dominique Polton Director of strategy, research and statistics National Health Insurance, France Couverture Public / private mix in health care financing 1.

More information

LANDLORDS INFORMATION PACK

LANDLORDS INFORMATION PACK ESTATE AGENTS Surveyors, Lettings & Management LANDLORDS INFORMATION PACK HAVE A HOUSE TO LET? LET US TAKE THE WEIGHT OFF YOUR SHOULDERS 16 Laburnum Terrace, Ashington, NE63 0XX Telephone: 01670 521 122

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

Ministry Of Health Registration of Interest

Ministry Of Health Registration of Interest Ministry Of Health Registration of Interest Intermediaries Social Bond Pilot(s) Part 1 Instructions and Supporting Information What s inside? Introduction to Social Bonds Purpose of the ROI Instructions

More information

EDUCATION PPP PROJECTS Pre-FINANCIAL CLOSE KEY STAGE REVIEW SCOTTISH EXECUTIVE FINANCIAL PARTNERSHIPS UNIT

EDUCATION PPP PROJECTS Pre-FINANCIAL CLOSE KEY STAGE REVIEW SCOTTISH EXECUTIVE FINANCIAL PARTNERSHIPS UNIT Twinning PPP CZ: Annex 4 to Component 2 fact-finding report EDUCATION PPP PROJECTS Pre-FINANCIAL CLOSE KEY STAGE REVIEW SCOTTISH EXECUTIVE FINANCIAL PARTNERSHIPS UNIT June 2006 Pre-FC Education KSR June

More information