1 Sky-Lift Forming System

2 Sky-Lift System The Sky-Lift jump form system engineered for use on external elevated forming applications. It can be used with any Symons forming system, including the Aluminum Beam, Versiform, Steel-Ply, Max-A-Form and Flex-Form systems. The system consists of the Sky-Lift Frame and Carriage Assembly. The Carriage Assembly allows the gang form to be retracted from the face of the previously cast concrete. The whole Sky-Lift assembly is suspended from Jump Shoes that are bolted to inserts in the previous concrete lift. These features, combined with the 8 foot wide working platform, allow for stripping and cleaning of the form face. All gang form preparation can proceed without the assistance of a crane. When acrane is needed, the form and platform are hoisted as one unit and landed into Jump Shoes. The crane is attached to the Sky-Lift unit only during hoisting, landing and reinstallation of the safety pins. This entire lifting operation typically takes 10 minutes to complete. When properly anchored, typical Sky- Lift applications will withstand rated wind load and support platform loads up to 50 pounds per square foot. This capacity permits all forming activities to be performed from the Sky-Lift work platforms. With all of the activity described above taking place on the work platform, the Sky-Lift system never needs to be lowered to the ground or stored elsewhere on the project. 2

3 LIFTING BRACKET LUMBER BY OTHERS (TYPICAL) WIDE WALKWAY BRACKET GANG FORM WALL BRACE CARRIAGE/WALER BRACKET VERSIFORM WALER GUARD RAIL POST SCREW ASSEMBLY GLIDE RACK CARRIAGE ASSEMBLY SKY-LIFT FRAME SKY-LIFT FRAME EXTENSION BRACKET WING NUT TYBACK GUARD RAIL POST JUMP SHOE LUMBER BY OTHERS (TYPICAL) EXTENSION BRACKET PLATFORM 3

4 Component Parts Waler Lift Brackets Depending on the gang form used, the Sky-Lift assembly can be lifted by the forms or by the walers. When using the Waler Lift Bracket, it must be bolted to the Versiform Waler with two 5 /8" x 6" contour bolts and double nutted for safety. The working load of 4000 lbs (5:1 safety factor) assures a safe and secure lift. The use of a lifting beam and drop lines is recommended when the Sky-Lift assembly is being transported. Work Platforms Work Platforms are used to retract the gang form approximately 30" from the poured concrete wall. Final gang form adjustments, plumbing, and Jump Shoe attachment can all be done from the Work Platform. The Work Platform also can be used to clean and store gangs. This operation saves time compared to the conventional method of lowering the gangs by crane to clean and store them. The Work Platform is typically constructed with three aluminum beams secured to the Sky-Lift frame. The aluminum beams are designed with a 2" x 2" wood nailer strip to fasten ¾" plywood for the platform decking. Trailing Platforms Trailing Platforms provide a 30" wide work access to the previously poured concrete wall. This allows a safe platform to patch tie holes, remove Jump Shoes and complete any other necessary finishing work. The Trailing Platform is constructed with aluminum beams and ¾" plywood for the platform decking. 4

5 Screw Jack Assembly The Screw Jack Assembly consists of the Carriage Waler Bracket and the 1½" diameter screw jack. The Carriage Waler Bracket is bolted onto the Versiform Waler with two 5 /8" diameter x 5" contour bolts and the Screw Jack is pinned to the Glide Rack. The assembly supports the gang form and allows vertical adjustments of up to 10½" for the purpose of aligning the outside forms with the inside forms for tie placement. Jump Shoes The Jump Shoe is bolted to an insert in the previous poured concrete. A removable pin in the Jump Shoe supports the end of the Sky-Lift Frame. A locking pin in the Jump Shoe engages the top member, securing the Frame against possible uplift forces. This safety pin cannot be engaged if the frame is not correctly seated in the Jump Shoe, and provides a positive safety indicator before the crane is disconnected. Wall Braces The heavy duty, all steel Wall Braces are designed to simplify wall form alignment. Wall Braces are attached to the top of the gear housing on the retractable carriage, and to the gang form waler with 5 /8" diameter bolts. The Wall Braces are used to strip the gang form from the newly placed concrete surface. Once stripped, the entire assembly can move away from the wall on the Sky-Lift Glide Rack. LOCK/SAFETY PIN Jump Shoe Wall Brace 5

6 Sky-Lift Assembly Sequence First Lift Second Lift First lift Once the gang forms are assembled, the Sky-Lift side should be set first. Inserts are positioned on the face of the gang form for the Jump Shoes and Sky-Lift Frame connections. Rebar is then set in place and the opposite gang form is secured with ties. After the concrete walls are poured and the gang forms stripped, the Jump Shoes are bolted into the inserts. Second lift The Sky-Lift Frame assembly is lifted into position, lowered onto the Jump Shoe, and secured with the safety pin. The Sky-Lift Frame is now mounted to the wall and ready to have the gang form and Work Platform attached. The Wall Brace is pinned to the waler and the gear housing, so the entire unit can be positioned. The crane now can be safely released and the gang form moved forward by turning the gear assembly with a wrench. Inserts are again placed and the forming sequence repeats. Third lift The forming sequence for the third lift is similar to the previous lifts, except now the Trailing Platform has been added. The extension bracket is secured to the Sky-Lift frame. Aluminum beams, ¾" plywood decking, and guard rails are then added. When lifting the gang and platform to the next position, the Trailing Platform will swing into position. Install the remaining 1" diameter pin into the Extension Bracket to complete the Sky-Lift assembly. Third Lift 6

7 Stripping Additional lifts are achieved by first removing all ties and retracting the gang forms using the Wall Brace and providing access using the Glide Rack carriage. Place the Jump Shoes for the next lift and perform any maintainance that may be needed. Lifting Just before lifting, remove all of the Lock/Safety Pins from the Jump Shoes. When the Sky-Lift Assembly is initially lifted, the unit may tilt slightly. To adjust the unit to fly vertically, raise the Sky-Lift Assembly, making sure not to lift clear of the Jump Shoes. If the front of the platform dips and the rear of the platform raises, move the Sky-Lift Carriage forward. If the rotation is reversed, move the Sky-Lift Carriage backward. Additional fine adjustment can be achieved with the Wall Brace. Sky-Lift Assembly on Concrete Wall Sky-Lift Assembly to next Forming Position 7

8 Adjustable Column Form Form square or rectangular columns efficiently with a minimum number of steel panels. Aluminum Beams and Joists Lightweight beams and joists from 4' to 30' (122cm to 914cm) for deck or gangform applications. Box Culvert Traveler Rolling steel framework is compatible with Steel-Ply, Versiform and Max-A-Form. Chemicals Liquid, cement, epoxy and polymer systems for the construction and repair of concrete structures. Flex-Form The specially designed steel-faced system for forming curved walls and round tanks with no surface chording. Form Liner More than 30 standard patterns, in four different materials, create unique concrete textures. Garage Beam System A complete system designed to provide an economical, poured-in-place concrete parking garage. Max-A-Form A durable, all-steel forming system that requires no walers. Ideal for pier caps and self-spanning applications. Resi-Ply A low cost, 1 1 /8" (2.9cm) plywood forming system for residential construction. Available in 4-bar, 5-bar and 6-bar. Roller Deck Column mounted deck support system replaces conventional shoring, providing access for other trades. Room Tunnel One room per day, per form provides maximum forming productivity. Ideal for repetitive room designs, like hotels. Shoring Frames Provide 24,000 lb. (10,880kg) load capacity per frame with spacings from 3' to 15' (91.4cm to 457.2cm). Springform Reusable fiberglass column for forming round columns with a smooth finish and a single vertical seam. Steel-Ply The most popular modular system with more than 80 panel and filler sizes for handset or gangforming. Symons Soldier The next generation construction beam that can be used as a brace, strongback, waler or shore. Street Smart Equipment for residential curb and gutters, industrial slab forming and highway paving applications. Symons Silver A lightweight aluminum system that makes residential forming operations very efficient and productive. Versiform Steel frame/plywood face gangforming system that provides a smooth concrete finish. A DAYTON SUPERIOR COMPANY SYMONS CORPORATION 200 E. Touhy Avenue Des Plaines, IL USA FAX info@symons.com Call SYMONS Printed in U.S.A. 2001, Symons Corporation Product Code 99975

PUMP JACK SYSTEM AND ACCESSORIES

PUMP JACK SYSTEM AND ACCESSORIES Pump Jack Model # 2200 A low cost, easy to operate, safe, portable scaffolding built of rugged steel. It's perfect for shingling, siding, sheathing, insulating, painting, building, roofing, home repair

More information

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span formwork formwork Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span has grown to become one of the major players in the scaffolding and

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything

More information

Rack installation instructions

Rack installation instructions Rack installation instructions Review the documentation that comes with the rack cabinet for safety and cabling information. Before you install the server in a rack cabinet, review the following guidelines:

More information

STANDARD OPEN PATIO COVER

STANDARD OPEN PATIO COVER STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist

More information

CONFER ABOVE GROUND CURVE STEP / ABOVE GROUND CURVE STEP SYSTEM ASSEMBLY AND INSTALLATION MANUAL

CONFER ABOVE GROUND CURVE STEP / ABOVE GROUND CURVE STEP SYSTEM ASSEMBLY AND INSTALLATION MANUAL SAVE THESE INSTRUCTIONS DEALER/INSTALLER: GIVE TO HOMEOWNER CONFER ABOVE GROUND CURVE STEP / ABOVE GROUND CURVE STEP SYSTEM ASSEMBLY AND INSTALLATION MANUAL Model CCX-AG Note: 40 lbs. of sand required!

More information

R = Rate of Placement T = Outside Temperature

R = Rate of Placement T = Outside Temperature EXAMPLE #1 SINGLE WALER SYSTEM #1 15 High Wall X 100 Long Assuming a pour rate of 4 hour and a temperature of 70º Using this equation P = 150 + R X 9000 T P = 150 + 4 X 9000 70 = 664 PSF P = Lateral Form

More information

Ceiling Mounted Folding Attic Ladders Installation Instructions

Ceiling Mounted Folding Attic Ladders Installation Instructions Ceiling Mounted Folding Attic Ladders Installation Instructions WARNING Before you start installing your new Louisville Ceiling Mounted Folding Attic Ladder, you must read and understand the following:

More information

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION Table of Contents Executive Summary... 1 Introduction... 1 Installing

More information

Speed-Mat Rectangle Cutter

Speed-Mat Rectangle Cutter Speed-Mat Rectangle Cutter 1 Honeycomb baseboard. 2 Left hold down. 14 3 Bottom hold down. 4 4 Left / right rule. 8 5 8 5 Left / right rule pointer. 1 6 Top / bottom rule. 7 Top / bottom rule pointer.

More information

Chapter 10 - Scaffolding Systems

Chapter 10 - Scaffolding Systems Chapter 10 - Scaffolding Systems Contents Chapter 10 - Scaffolding Systems... 10-1 Check and Oil the Pump Jacks... 10-4 Set Pump Jack Brackets... Error! Bookmark not defined. Set Pump Jack Poles... 10-5

More information

Roll-Up Door Maintenance Guide

Roll-Up Door Maintenance Guide R Roll-Up Door Maintenance Guide Cable Replacement on Two Spring Type Balancer Page 1 Panel Replacement - Removable Roller Cover Type Bottom Panel Page 1 Panel Replacement - Removable Roller Cover Type

More information

INSTRUCTIONS THOROUGHLY BEFORE BEGINNING***************

INSTRUCTIONS THOROUGHLY BEFORE BEGINNING*************** Bill of Materials: RAC0012 Green Wing Aerodynamic Skirt Kit Item Part Number Description Quantity 1 RMC0218 Gen 2 Trailer Skirt Roadside 1 2 RMC0219 Gen 2 Trailer Skirt Curbside 1 3 RMC0041 Trailer Skirt

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

FORM DESIGN. easy to work with, and generally available.

FORM DESIGN. easy to work with, and generally available. Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods

More information

How to secure your property after a disaster

How to secure your property after a disaster How to secure your property after a disaster The Red Guide to Recovery HOuse secured properly Board-Up of Windows, Doors and Roof Hole. Lot secured with Perimeter Fencing. Fires, floods, tornadoes, hurricanes,

More information

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document Fall Protection in Residential Construction Table of Contents Executive Summary... 1 Introduction... 1

More information

Dock Hardware & Accessory Products Catalog

Dock Hardware & Accessory Products Catalog Dock Hardware & Accessory Products Catalog Product Page # Product Page # Angle Brackets/Clips 8 Back Up Plate 5 Backing Plate/Hurricane Stop 10 Carriage Bolt Sets 4 Chain Retainer 10 Connector Pin Set

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

AZEK Rail Install Guide

AZEK Rail Install Guide TRIM MOULDING DECK PORCH RAIL PAVERS AZEK Rail Install Guide Installing AZEK Rail with CableRail by Feeney... 1 Installing CableRail by Feeney for AZEK Rail... 7 Installing AZEK Rail Stairs with CableRail

More information

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 (See Supplemental Instructions for trailers with heavy duty round footplates and/or Power Leveling Systems) PHONE SUPPORT

More information

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders

More information

LG G5 Chassis Brace Gen 5 Camaro THE MOST POWERFUL HEADERS ON THE PLANET Brought to you by LG Motorsports 972-429-1963

LG G5 Chassis Brace Gen 5 Camaro THE MOST POWERFUL HEADERS ON THE PLANET Brought to you by LG Motorsports 972-429-1963 LG G5 Chassis Brace Gen 5 Camaro THE MOST POWERFUL HEADERS ON THE PLANET Brought to you by LG Motorsports 972-429-1963 Thank you for purchasing LG Motorsports products for your Gen 5 Camaro. Parts Inventory:

More information

HYDRAULIC LIFT TABLE CART 2200-LB.

HYDRAULIC LIFT TABLE CART 2200-LB. HYDRAULIC LIFT TABLE CART 2200-LB. OWNER S MANUAL WARNING: Read carefully and understand all MACHINE ADJUSTMENT AND OPERATION INSTRUCTIONS before operating. Failure to follow the safety rules and other

More information

FLAT ROOF BOX SPAN CARPORTS

FLAT ROOF BOX SPAN CARPORTS AGS/NC/03 FLAT ROOF BOX SPAN CARPORTS Thank you for choosing this quality product. We strongly recommend that you read these instructions thoroughly. Please take your time and do not rush the erection

More information

MGB Chrome Bumper Conversion

MGB Chrome Bumper Conversion MGB Chrome Bumper Conversion Installation Instructions For 1974 1/2-1980 MGB This kit requires cutting, welding, and painting. Professional installation recommended. Note: Every MGB body is slightly different

More information

Solar Water Heating and Solar Electric Generators Installed on One or Two Family Dwellings

Solar Water Heating and Solar Electric Generators Installed on One or Two Family Dwellings Solar Water Heating and Solar Electric Generators Installed on Category: Residential Construction Revised: [Paul L. Scarlett], Director Responsible Bureau Section: Development Services Center 1900 SW Fourth

More information

Mobile Home Pre-Inspection Checklist

Mobile Home Pre-Inspection Checklist Mobile Home Pre-Inspection Checklist TWO (2) STEP INSPECTION PROCESS STEP ONE: CALL FOR THE FIRST INSPECTION WHEN THESE ITEMS ARE COMPLETE. 1. Septic tank installed and plumbing complete. (SEE PLUMBING

More information

6 inch A-Arm Lift Kit WARNING: 16-018/16-019. installation instructions. will fit CLUB CAR DS. included:

6 inch A-Arm Lift Kit WARNING: 16-018/16-019. installation instructions. will fit CLUB CAR DS. included: Revised May 205 6-08/6-09 6 inch A-Arm Lift Kit will fit CLUB CAR DS installation instructions included: Rear Lift Blocks Main Suspension Assembly Spindles A-Arms Rear Shock Mounting Plates U-Bolts WARNING:

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

TONNEAU INSTALLATION GUIDE

TONNEAU INSTALLATION GUIDE TONNEAU INSTALLATION GUIDE Warranty, Care & Maintenance Model 4056 Toyota Tacoma Double Cab 5' Short Bed 2005-Current (With Multi-Track System) EASY AS 1-2-3! NORMAL INSTALLATION TIME 30 MINUTES For Warranty

More information

Owner s Manual Read and keep this manual. Patents World Wide

Owner s Manual Read and keep this manual. Patents World Wide Owner s Manual Read and keep this manual. Patents World Wide S & S Industries, Inc., Sarasota, FL, USA www.trail-gator.com Copyright 2008 All Rights Reserved The following manual is provided to assist

More information

TREX SELECT RAILING. Installation Instructions 1 800 BUY TREX PARTS G * I ** H *

TREX SELECT RAILING. Installation Instructions 1 800 BUY TREX PARTS G * I ** H * TREX SELECT RAILING NOTE: All Trex Select Railing lengths are manufactured at ON CENTER dimensions (spanning from center of each post): 67-5/8" (76.8 cm) for 6' (.83 m) on center, and 9-5/8" (35.3 cm)

More information

Miller Engineered Solutions Customized Fall Protection Solutions. NEW! Now featuring Rigid Rail Systems

Miller Engineered Solutions Customized Fall Protection Solutions. NEW! Now featuring Rigid Rail Systems Miller Engineered Solutions Customized Fall Protection Solutions NEW! Now featuring Rigid Rail Systems Custom systems for fall protection needs Vast network of trained and certified installer partners

More information

In-Ground Basketball System Owners Manual

In-Ground Basketball System Owners Manual In-Ground Basketball System Owners Manual Customer Service Center N53 W4700 South Corporate Circle Sussex, WI 53089 U.S.A. Write Model Number From Box Here: WARNING! 3 Capable Adults REQUIRED TOOLS AND

More information

TYPICAL PATIO COVERS 111

TYPICAL PATIO COVERS 111 City of Laguna Niguel Building Division 30111 Crown Valley Pkwy Laguna Niguel, CA 92677 (949) 362-4360 FAX 362-4369 www.cityoflagunaniguel.org TYPICAL PATIO COVERS 111 PLEASE NOTE: This information Bulletin

More information

RadianceRail Installation Guide

RadianceRail Installation Guide RadianceRail Installation Guide Installing RadianceRail with CableRail by Feeney... 2 Installing CableRail by Feeney for RadianceRail... 7 Installing RadianceRail Stairs with CableRail by Feeney... 10

More information

Wall braces with a swivel head are included to accommodate all roof pitches.

Wall braces with a swivel head are included to accommodate all roof pitches. ULTRA JACK MODEL # 2000 Wall braces with a swivel head are included to accommodate all roof pitches. Product Specifications Model # 2000 Description: Ultra Jack Unit Pack: Weight per Pack: 1 / Carton 32

More information

Best Barns USA Assembly Book

Best Barns USA Assembly Book Best Barns USA Assembly Book Revised November 27, 2013 the Easton - R 12'x 20' Manufactured by Reynolds Building Systems, Inc. 205 Arlington Drive Greenville, PA 16125 724-646-3775 This manual is copyrighted.

More information

The minimum reinforcement for the stem wall is the placement of:

The minimum reinforcement for the stem wall is the placement of: PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20

More information

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B

Installation Guide. Bath and Wall Surrounds SERIES 7104 1021861-2-B Installation Guide and Wall Surrounds SERIES 7104 1021861-2-B Thank You For Choosing Sterling We appreciate your commitment to Sterling value. Please take a few minutes to review this manual before you

More information

The ACR : Advanced Design Features for a Short Construction Schedule

The ACR : Advanced Design Features for a Short Construction Schedule Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for

More information

DIRECTIONS FOR ASSEMBLING BASE & WALL CABINETS

DIRECTIONS FOR ASSEMBLING BASE & WALL CABINETS DIRECTIONS FOR ASSEMBLING BASE & WALL CABINETS TheRTAStore.com STEP 1: CLEAR A WORK SPACE Place your RTA cabinet panels on a smooth, scratch resistant surface in a large, open area. (Some people like to

More information

Awning Instructions. Standard Manual 1.5m to 4.5m

Awning Instructions. Standard Manual 1.5m to 4.5m Awning Instructions Standard Manual 1.5m to 4.5m English Standard Manual Instructions Contents Warning 1.5m 3.0m Awnings 4 x Expansion bolts (2 per bracket)** 2 x brackets 1 x Awning 1 x Winder handle

More information

Owner's Manual & Assembly Instructions

Owner's Manual & Assembly Instructions Owner's Manual & Assembly Instructions PM01 BASE KIT Model No. FDN1014 717090311 CAUTION: SOME PARTS HAVE SHARP EDGES. CARE MUST BE TAKEN WHEN HANDLING THE VARIOUS PIECES TO AVOID A MISHAP. FOR SAFETY

More information

UNIVERSAL ASSEMBLY INSTRUCTIONS FOR VERSATUBE BUILDINGS CONTRACTOR SERIES 2 X 4 FRAMES

UNIVERSAL ASSEMBLY INSTRUCTIONS FOR VERSATUBE BUILDINGS CONTRACTOR SERIES 2 X 4 FRAMES UNIVERSAL ASSEMBLY INSTRUCTIONS FOR VERSATUBE BUILDINGS CONTRACTOR SERIES 2 X 4 FRAMES Our unique assembly process quickly transforms the individual pieces into a finished structure that will give you

More information

foot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.

foot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs. Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12

More information

INSTALLATION INSTRUCTIONS for Bifold Doors (JII103)

INSTALLATION INSTRUCTIONS for Bifold Doors (JII103) Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for premium composite, hollow and solid core molded Bifold Doors. Bifolds are designed for fast

More information

MEDIUM FLAT PANEL DISPLAY STATIC MOUNT MSR Series

MEDIUM FLAT PANEL DISPLAY STATIC MOUNT MSR Series INSTALLATION INSTRUCTIONS MEDIUM FLAT PANEL DISPLAY STATIC MOUNT The static mount accommodates medium flat panel displays weighing up to 125 lbs (57 kgs). The teardrop holes in the mount allow for quick

More information

CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS

CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS CHARISMA SHOWER/TUB DOOR INSTALLATION INSTRUCTIONS IMPORTANT DreamLine reserves the right to alter, modify or redesign products at any time without prior notice. For the latest up-to-date technical drawings,

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Removable Aluminium posts

Removable Aluminium posts Post Solent Sail Shades Ltd 120 Billington Gardens Hedge End Southampton SO30 2RT Tel/Fax: 01489 788243 www.solentsailshades.co.uk Email: info@solentsailshades.co.uk Removable Aluminium posts Single Pole

More information

SELF-STEERING AXLE TABLE OF CONTENTS

SELF-STEERING AXLE TABLE OF CONTENTS SELF-STEERING AXLE TABLE OF CONTENTS Section 1 - Introduction Section 2 - Pre-Installation Check List Section 3 - Ride Height Adjustments Section 4 - Suspension Mount Section 5 - Axle Mount Section 6 -

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Residential Decks Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

SAVE THESE INSTRUCTIONS DEALER/INSTALLER: GIVE TO HOMEOWNER MODEL #7200

SAVE THESE INSTRUCTIONS DEALER/INSTALLER: GIVE TO HOMEOWNER MODEL #7200 SAVE THESE INSTRUCTIONS DEALER/INSTALLER: GIVE TO HOMEOWNER MODEL #7200 ROLLGUARD A-FRAME LADDER LADDER MUST BE ATTACHED TO POOL FRAME. DO NOT USE WITH INFLATABLE POOLS ASSEMBLY AND INSTALLATION MANUAL

More information

Models HD920EV HD930EV LW5000EV WD962KEV WD962KPEV WD962MLEV 349544

Models HD920EV HD930EV LW5000EV WD962KEV WD962KPEV WD962MLEV 349544 .. Belt Drive Battery Backup Garage Door Opener Models HD920EV HD930EV LW5000EV WD962KEV WD962KPEV WD962MLEV 349544 FOR RESIDENTIAL USE ONLY Please read this manual and the enclosed safety materials carefully!

More information

www.cornholesupplies.com

www.cornholesupplies.com www.cornholesupplies.com How To Build Regulation Cornhole Boards Home of the Original Cornhole Bags and Boards Supply List: 1-4' X 8' Piece of Plywood (pre sanded) 4-2" X 4" X 8' Studs (2 by 4s make sure

More information

BRIO Modular scaffolding

BRIO Modular scaffolding BRIO Modular scaffolding // Versatile and multifunctional // Table of content Features Benefits Solutions Basic components 2 4 6 11 // Features BRIO Modular Scaffolding covers the different configurations

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

glass & Glazing Products

glass & Glazing Products glass & Glazing Products WallMaker Create an unlimited variety of bright, beautiful and secure interior environments with the easy-to-install Stylmark WallMaker glass wall system. This versatile system

More information

Bolt-on castor set B

Bolt-on castor set B 12/2010 Original Operating Instructions 999285502 en-gb Please retain for future reference Bolt-on castor set B rt. n 586168000 2008 models onward Basic drawings of product Product description The Bolt-on

More information

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,

More information

Roof Curbs, Extensions and Equipment Supports

Roof Curbs, Extensions and Equipment Supports Roof s, Extensions and Equipment Supports December 2012 Roof Page s, Header Extensions and Equipment Supports Table of Contents Model GPI Standard and Optional Construction Features... 3 Model Number Code....

More information

Structural Holding System

Structural Holding System Structural Holding System Users Manual November 2013 by Vehicle Service Group. All rights reserved. CO8812.1 502071 Rev. - 11/21/2013 CHIEF'S LIMITED ONE-YEAR WARRANTY & LIABILITY Chief Automotive Technologies

More information

Wisconsin Building Products Evaluation

Wisconsin Building Products Evaluation Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation

More information

Handling, Erection and Bracing of Wood Trusses

Handling, Erection and Bracing of Wood Trusses Handling, Erection and Bracing of Wood Trusses Follow these guidelines for safe installation of Wood Trusses. These guidelines should not be considered to be the only method for erecting and bracing of

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Monday, May 07, 2012 Lighthouse Engineering, L.L.C. Michael Gandy, P.E. Registered Professional Engineer (TX: 95672) Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website:

More information

39HQ Airovision Air Handling Units

39HQ Airovision Air Handling Units 39HQ Airovision Air Handling Units Mounting instructions CONTENTS 1 - TRANSPORT AND LIFTING INSTRUCTIONS... 3 1.1 - General... 3 1.2 - Transport and storage... 3 1.3 - Roof edge protection during transport

More information

Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails

Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails Manual No. 103-0045 REV. 12/08 Installation and Maintenance Manual for SPANCO Freestanding Modular Bridge Cranes & Monorails ISO 9001 REGISTERED 2 TABLE OF CONTENTS Important Dimensions for Modular Bridge

More information

9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards.

9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and guards. Section 9.8. Stairs, Ramps, Handrails and Guards 9.8.1. Application 9.8.1.1. General (1) This Section applies to the design and construction of interior and exterior stairs, steps, ramps, railings and

More information

Mounting Tripod Kit Installation Manual

Mounting Tripod Kit Installation Manual Mounting Tripod Kit Installation Manual For use with Davis s wireless and cabled Vantage Pro2 weather stations, the Mounting Tripod simplifies installation. The tripod supports the Integrated Sensor Suite

More information

Installation Instructions:

Installation Instructions: Portable Guardrail System Model Numbers: 7900060, 7900061, 7900062, 7900063 Installation Instructions: Portable Guardrail System This instruction is intended to meet the Manufacturer s Instructions requirement

More information

LAYING BLOCK AND BRICK

LAYING BLOCK AND BRICK LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct

More information

Exakta 6x6 No. 602246

Exakta 6x6 No. 602246 Page 1/7 Repair of Exakta 6x6, 2 1/4, Single Lens Reflex Exakta 6x6 No. 602246 Access to Film ounter & Winding Mechanism For convenience remove the lens. The lens release is on the left side of the camera

More information

BUILD A TABLETOP LOOM

BUILD A TABLETOP LOOM BUILD A TABLETOP LOOM From 1" x 2" stock (actual 3/4" x 1"1/2) cut: 4 pieces 15" long 4 pieces 5"1/2 long Use the above to make 2 frames for the front and back of the loom. From 1" x 4" stock (actual 3/4"

More information

1000-LB. TRAILER JACK OWNER S MANUAL

1000-LB. TRAILER JACK OWNER S MANUAL 1000-LB. TRAILER JACK OWNER S MANUAL WARNING: Read carefully and understand all INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions may result in serious

More information

OWNER S MANUAL Table Tennis Table Patent Pending

OWNER S MANUAL Table Tennis Table Patent Pending OWNER S MANUAL Table Tennis Table Patent Pending Be sure to write your model number and serial number here for future reference. You can find these numbers printed on the bottom of the table. MODEL # T8179

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLATION INSTRUCTIONS ODEON IN-WALL TANK K-6283K/ K-6284K/ K-6286K Read installation guide in illustration and word file carefully, and install the tank according to instructions in the guide to avoid

More information

2.9 WINDOW & DOOR BUCKS

2.9 WINDOW & DOOR BUCKS 2.9 WINDOW & DOOR BUCKS Bucks provide attachment surfaces for windows and doors while holding back concrete from these openings during concrete placement. Mark the center and edges of openings as you place

More information

OPERATOR S INSTRUCTION MANUAL

OPERATOR S INSTRUCTION MANUAL POWER JACK MATERIAL MOVER OPERATOR S INSTRUCTION MANUAL WARNING: Serious injury may result if this product is misused. The manufacturer provides the following instructions for use and care of this equipment

More information

RZ Guardrail System Installation Manual

RZ Guardrail System Installation Manual TM RZ Guardrail System Installation Manual RZ Guardrail System Compliance is based on OSHA standards: (Standards - 29 CFR) 1910.23 (e) and (Standards - 29 CFR) 1926.502 (b) Failure to read, understand

More information

GARAGE DOOR OPENER Model 3265 1/2 HP

GARAGE DOOR OPENER Model 3265 1/2 HP The Chamberlain Group, Inc. 845 Larch Avenue Elmhurst, Illinois 60126-1196 www.liftmaster.com GARAGE DOOR OPENER Model 3265 1/2 HP For Residential Use Only Owner s Manual Please read this manual and the

More information

PREASSEMBLED ELEMENTS FOR LIFTING AND SLIDING DOORS

PREASSEMBLED ELEMENTS FOR LIFTING AND SLIDING DOORS SYSTEM COMPONENTS PREASSEMBLED ELEMENTS FOR FIFTING AND SLIDING DOORS s r ood gn i d i l s dna gn i t f i f r o f s t neme l e de l bme s s ae r P PREASSEMBLED ELEMENTS FOR LIFTING AND SLIDING DOORS These

More information

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS

SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word

More information

1. Lay out 2 pieces of 7/8" tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1.

1. Lay out 2 pieces of 7/8 tubing and mark for bending as shown. Remember that the bend is in the shaded area as shown below in Figure 1. MINI BIKE PLANS Page 1 INTRODUCTION Before starting to build your Mini-Bike, be sure that you have all the parts shown on the material list. You will note that tubing has been used in the construction.

More information

1 Door Tall Unit ASSEMBLY GUIDE. Page 1 of 9. WARNING: Contains small parts, keep out of reach of children.

1 Door Tall Unit ASSEMBLY GUIDE. Page 1 of 9. WARNING: Contains small parts, keep out of reach of children. Page 1 of 9 ASSEMBLY GUIDE 1 Door Tall Unit IMPORTANT Before Commencing Assembly: Read all instructions COMPLETELY Ensure all listed parts are present If any parts are missing from Parts List 1, please

More information

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

Pulleys and Belt. Install the Major Accessory and Pulley. Install the Motor Pulley NOTE. Align the Motor Pulley and the Tool Pulley NOTE

Pulleys and Belt. Install the Major Accessory and Pulley. Install the Motor Pulley NOTE. Align the Motor Pulley and the Tool Pulley NOTE Pulleys and Belt Pulley Guard - 505862 Install the Major Accessory and Pulley 1. Place the short end of the mounting base holes, and insert - but don t tighten - the setscrews. If the Major Accessory has

More information

EXCAVATOR SAFETY TRAINING

EXCAVATOR SAFETY TRAINING EXCAVATOR SAFETY TRAINING INSPECTION CHECKLIST INSPECTION AREA INSPECTION RESULTS Sat. Unsat. N/A Comments Carrier & Car Body Rotation system Tracks Rollers Frame, welds, bolts Drive system Upper Structure

More information

Customer Service 800.780.8889 or visit us online at smithnoble.com. Wood Shutters. Step by Step Installation. Troubleshooting Tips

Customer Service 800.780.8889 or visit us online at smithnoble.com. Wood Shutters. Step by Step Installation. Troubleshooting Tips reflect your style TM Customer Service 800.780.8889 or visit us online at smithnoble.com Wood Shutters Step by Step Installation Troubleshooting Tips Easy Care Instructions STEP 1 Your New Shutter Thank

More information

Uncovered Decks & Porches

Uncovered Decks & Porches Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

Cedar Cottage Doghouse Plans

Cedar Cottage Doghouse Plans Overlapping cedar shingles add an element of charm to this medium size doghouse. The walls, floor, and trim are constructed of solid cedar, making it naturally weather resistant and provides excellent

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

BUGGY SETUP GUIDE. Volume GOKARTSUSA GY6 150, CN250. Buggy Setup Guide

BUGGY SETUP GUIDE. Volume GOKARTSUSA GY6 150, CN250. Buggy Setup Guide BUGGY SETUP GUIDE Volume 1 GOKARTSUSA GY6 150, CN250 Buggy Setup Guide GY6 150, CN250 DUNE BUGGY Buggy Setup Guide GOKARTSUSA.COM 2000 Highway 50 S. Lake Tahoe, CA 96150 Phone 800.603.1437 2 Table of Contents

More information

Balance Shoe and Balance Replacement

Balance Shoe and Balance Replacement and Replacement for E-Series Double-Hung and Single-Hung Windows Thank you for choosing Andersen. For questions call 1-888-888-7020. For more information and/or guides visit www.eaglewindow.com Please

More information