1 Subject: Meeting: Milton Keynes CCG authorisation process- procurement strategy NHS Milton Keynes CCG Shadow Board Date of Meeting: 7 August 2012 Report of: Matthew Webb, Chief Financial Officer Introduction Milton Keynes CCG is undertaking a programme of work in support of its application for authorised status. As part of that programme of work the CCG needs to ensure that it has a procurement strategy and policy in place that ensures appropriate levels of control and maximises value for money. The strategy will also ensure that the CCG will meet its obligations under the Public procurement regulations 2006 and all key EU requirements. Purpose of this strategy This procurement Strategy sets out how the CCG will develop its procurement activities. It does not set out detailed procurement processes or approval routes as these will be covered by the CCG s Governance, Standing Financial Instructions and Scheme of Delegation. Recommendation The Board is asked to approve the procurement strategy. Page 1 of 11
2 Page 2 of 11
3 NHS Milton Keynes Clinical Commissioning Group Procurement Strategy Page 3 of 11
4 Table of Contents 1 Purpose 2 Aims 3 Principles 4 Objectives 5 Approach 6 Procurement Process 7 Accountability and Authorisation 8 Complaints and Dispute Resolution 9 Sustainability and Environmental Issues 10 Guidance Appendix 1 EU Directive procedures Appendix 2 Glossary of Terms Page 4 of 11
5 1.0 Purpose 1.1 This procurement Strategy sets out how the CCG will develop its procurement activities. It does not set out the detailed procurement processes or approval routes as these will be covered by the CCG s Governance, Standing Financial Instructions and Procurement Policies and Procedures. 1.2 This Procurement strategy has been designed to support the CCG through the authorisation process by showing an understanding of the current requirements and guidance for Procurement Activities of NHS Bodies. 1.3 The strategy will also ensure that the CCG meets its legal duty with regard to compliance with the Public Procurement Regulations Aims 2.1 This strategy has a number of specific aims : To ensure engagement with all stakeholders and relevant parties when a procurement is undertaken To ensure quality of services are achieved and maintained To enable greater choice for patients by expanding the number of qualified providers To ensure the CCG achieves value for money in its procurement activities To ensure the CCG makes the appropriate decision whether a procurement is necessary To avoid possible conflicts of interest where the CCG may be a Potential Provider 3.0 Principles 3.1 The following principles will guide the CCG as it develops : Commissioning and procurement shall be open, fair, transparent and nondiscriminatory Services are sourced with the active involvement of stakeholders The CCG will use providers best placed to meet patient needs. Services and Goods are sourced competitively where appropriate Achieves value for money Any Complaints regarding the procurement process are handled correctly via a dispute resolution process Page 5 of 11
6 4.0 Objectives 4.1 The objectives are to: To enable the CCG to secure its strategic objectives to commission efficiently and effectively to represent best value for the local population when purchasing clinical and non clinical services and goods. To enable the CCG to develop a supply base that ensures local access to a continuing, and expanding range of services that are required to meet the needs of the local population. To ensure all CCG employees, service providers and members of the public are aware of the agreed approach to the CCGs procurement activities. To set out a clear framework for deciding when competitive procurement is necessary; and when existing contracts can be maintained and improved using alternative means. To demonstrate compliance with the EU Principles, Public Procurement Directive and the principles of the PRCC. 5.0 Approach 5.1 The CCG recognises that effective engagement with stakeholders is a requirement of NHS organisations and will also offer substantial benefits to the generation of outcome-based service specifications. 5.2 Stakeholder engagement with new and existing providers, members of the public, clinicians and other service users will occur at key points in the service review and procurement processes. Where possible the input from these groups will be used to ensure the views of patients are included in the services being commissioned. 5.3 This will enable the CCG to decide whether these needs are best met through a competitive tendering exercise or if the service can be commissioned by another means. 5.4 When making this decision the CCG will comply with the EU Principles, the Public Contract Regulations and the guidance contained within the PCT Procurement Guide. Lower value contracts may be procured using alternative routes having taken into account the type of service and risk associated with commissioning them without reducing the quality requirements of the service. 5.5 Guidance in relation to the EU principles and how they apply to a specific case may be required and will be sought from a CSU, who will able to provide access to appropriate legal or other specialist advice on these issues, if considered necessary. Page 6 of 11
7 5.6 Any decision taken not to competitively tender will be clearly justified by the CCG and documented. 6.0 Procurement Process 6.1 The CCG will apply the Principles and Rules set out in the EU Procurement Directives and the Pubic Contracts Regulations 2006, which detail the rules that Public Bodies must follow for the procurement of Goods and Services The general principles of the EU Procurement Directive are:- Transparency Opportunities will be advertised on Supply2health and OJEU Evaluation processes, award criteria and decisions regarding procurement will be published Any conflicts of interest will be declared and managed Equal treatment Evaluation criteria will be objective, non-discriminatory and carried out in accordance with the published criteria All parties will have the opportunity to apply for any opportunity the CCG wishes to tender Proportionate The Procurement process will not be onerous and will be applied with consideration as to the complexity, risk and value of the service being commissioned Non-Discriminatory All bidders will be treated equally and information will be passed to all at the same time 6.2 The EU Procurement Directive has two different service types:- Part A Services to which the full EU Directive applies. Part B Services which includes healthcare and social services. The full EU Directive does not apply to these but the general principles of transparency, equal treatment, objectivity and non-discrimination apply Page 7 of 11
8 6.3 The Procurement of Goods is also subject to the full EU Directive 6.4 The CCG will adopt the principles which apply to Goods and Part A Services for its tendering exercises for Part B Services. This will minimise the risk to the CCG of any challenge during the Procurement Process. 6.5 These principles will also be adopted for the Any Qualified Provider process which may be used as a means of Commissioning Services on behalf of the CCG. 6.6 The EU Directive Timescales and stages for all procedures are shown in Appendix Accountability & Authorisation 7.1 At each stage of the procurement the CCG will ensure that the project is authorised in accordance with the CCG s Governance arrangements and Standard Financial instructions. 7.2 Where the CCG has used a CSU to provide the Procurement services the final decision as to the appointment of the contractor will be made by the CCG. 8.0 Complaints and Dispute Resolution 8.1 The CCG will have in place a Competition Dispute Resolution process to hear any complaints from organisations who consider that the CCG has not complied with this Strategy, the Rules for Co-Operation and Competition or any of its Policies and Procedures. 9.0 Environmental and Sustainability Issues 9.1 The CCG recognises that it as an organisation is responsible for environmental and sustainability issues and will produce policies for these which will consider the impact of procurement activities on both the social and economic environment. This will enable goods and services to be sourced in a sustainable and environmentally friendly way Guidance 10.1 The CCG has based this strategy on the following guidance:- Procurement Guide for Commissioners of NHS Funded Services Principles and Rules for Co-Operation and Competition Protecting and Promoting Patients Interests: the Role of Sector Regulation Page 8 of 11
9 Page 9 of 11
10 Appendix 1 EU Directive Procedures Page 10 of 11
11 Appendix 2 Glossary of Terms CCG CSU OJEU PRCC Clinical Commissioning Group Commissioning Support Unit Official Journal of the European Union Principles and Rules for Co-operation and Competition Page 11 of 11
Version Author Revisions Made Date 1.6 David Sharkey Executive Board 27 March 2012 2.0 Robin Hunt
Purchasing Policy Originator name: Section / Dept: Implementation date: Date of next review: Related policies: Policy history: Robin Hunt Procurement 1 December 2013 Finance Regulations, Purchase Card
More informationNHS Lancashire North CCG. Competition Dispute Resolution Policy and Process
NHS Lancashire North CCG Competition Dispute Resolution Policy and Process V1.4 Version No Amended by Date reviewed Date approved Next Date for Review 1.1 March 2009 March 2010 1.2 B Thomas 29.07.13 August
More informationEastern Cheshire Clinical Commissioning Group
Eastern Cheshire Clinical Commissioning Group Healthcare Procurement Policy and Strategy Responsible Person: Neil Evans, Head of Business Management Date Approved: TBC Committee: Governance and Audit Committee
More informationGoverning Body meeting (held in public)
ENCLOSURE: H Agenda Item: 114/15 Governing Body meeting (held in public) DATE: 30 July 2015 Title Procurement of Non Emergency Patient Transport Services (to Dartford & Gravesham Hospital Trust Non-emergency
More informationProcurement Policy 2015
NHS Bradford Districts CCG Procurement Policy 2015 Effective: April 2015 Sue Mundy-Jones Page 1 Version Control Sheet Document Title Author Procurement Policy Sue Mundy-Jones Lead Officer Chief Officer
More informationNHS Greater Huddersfield Clinical Commissioning Group. Remuneration Committee. Terms of Reference
NHS Greater Huddersfield Clinical Commissioning Group Remuneration Committee Terms of Reference Version: 1.0 Committee Approved by: Governing Body NHS Greater Huddersfield CCG Date Approved 1 st May 2013
More informationSUFFOLK COUNTY COUNCIL PROCUREMENT RULES. Version 2 Jan 2016. Page 1 of 19
SUFFOLK COUNTY COUNCIL PROCUREMENT RULES 2015 Version 2 Jan 2016. Page 1 of 19 TABLE OF CONTENTS 1. Introduction and Definitions... 3 2. Scope... 4 3. General Principles... 5 4. Responsibilities... 7 5.
More informationSR0001 Maintaining Business Continuity including the Council s response to major civil emergencies. (Interim Programme Lead)
STRATEGIC RISK REPORT QUARTER 1 APRIL TO JUNE 2007 APPENDIX A SR0001 Maintaining Business Continuity including the Council s response to major civil emergencies. (Interim Programme Lead) Over 75% of business
More informationThe post holder will be guided by general polices and regulations, but will need to establish the way in which these should be interpreted.
JOB DESCRIPTION Job Title: Membership and Events Manager Band: 7 Hours: 37.5 Location: Elms, Tatchbury Mount Accountable to: Head of Strategic Relationship Management 1. MAIN PURPOSE OF JOB The post holder
More informationContract Standing Orders and Procedure - A Guide For Council Employees
Hampshire County Council Constitution Part 3:F Contract Standing Orders 1. Interpretation 2. Status of, and Compliance with, Contract Standing Orders 3. Approval to Commence Procurement 4. Contract Value
More informationComplaints Policy. Complaints Policy. Page 1
Complaints Policy Page 1 Complaints Policy Policy ref no: CCG 006/14 Author (inc job Kat Tucker Complaints & FOI Manager title) Date Approved 25 November 2014 Approved by CCG Governing Body Date of next
More informationProcurement Services Document Control Sheet
Procurement Services Document Control Sheet Document Reference: Standing Orders for Contracts 2010 Log of Changes Issue Date Originator Authorisation V0.1 September Rebecca Document came into place 2010
More informationTo be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
More informationREQUEST FOR MAYORAL DECISION MD405. Title: Disaster Recovery Services
REQUEST FOR MAYORAL DECISION MD405 Title: Disaster Recovery Services Executive Summary: In May 2006, the GLA entered into an agreement with a recovery partner to offer immediate replacement IT equipment
More informationContract Management Guideline
www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract
More informationUpdate on NHSCB Key features of (proposed) NHSCB operating model for primary care
Aim to cover Update on NHSCB Key features of (proposed) NHSCB operating model for primary care NHSCB dental commissioning strategy all dental services Concept and context of local professional networks
More informationWales Procurement Policy Statement
Wales Procurement Policy Statement In December 2012 I launched the Wales Procurement Policy Statement (WPPS) setting out the principles by which I expect public sector procurement to be delivered in Wales.
More informationDoing business with the Council
Doing business with the Council Contents INTRODUCTION 1 POLICIES AND PROCEDURES 2 BUSINESS OPPORTUNITIES 3 TENDERING 4 WHAT THE COUNCIL LOOKS FOR 5 CONTRACTS 7 SUPPORTING LOCAL AREA 7 FREEDOM OF INFORMATION
More informationTender Evaluation and Contract Award
Brief 9 January 2011 Public Procurement Tender Evaluation and Contract Award C O N T E N T S Key principles governing the process of evaluation of tenders How does an evaluation panel operate? How does
More informationSummary of the role and operation of NHS Research Management Offices in England
Summary of the role and operation of NHS Research Management Offices in England The purpose of this document is to clearly explain, at the operational level, the activities undertaken by NHS R&D Offices
More informationNEATH PORT TALBOT LOCAL HEALTH BOARD CORPORATE GOVERNANCE HANDBOOK
NEATH PORT TALBOT LOCAL HEALTH BOARD CORPORATE GOVERNANCE HANDBOOK Purpose of this Handbook This handbook sets out, in broad terms, the Corporate Governance arrangements in place within Neath Port Talbot
More informationCCG: IG06: Records Management Policy and Strategy
Corporate CCG: IG06: Records Management Policy and Strategy Version Number Date Issued Review Date V3 08/01/2016 01/01/2018 Prepared By: Consultation Process: Senior Governance Manager, NECS CCG Head of
More informationStandard operating procedure
Standard operating procedure Title: Steps involved in outsourcing of services Status: PUBLIC Document no.: SOP/EMA/0083 Lead author Approver Effective date: 18-12-2014 Name: Caroline Maignen Name: Stefano
More informationCABINET. 24 March 2015
CABINET 24 March 2015 Title: Procurement of Electricity and Gas Supplies Report of the Cabinet Member for Finance Open Report with Exempt Appendix 4 Wards Affected: All Report Author: Andrew Sivess Group
More informationINTRODUCTION. The Merlin Principles. The Elements of each Principle
0 INTRODUCTION The development of the Merlin Standard has been progressed as a joint exercise between the Department for Work and Pensions (DWP) and its providers operating in the Welfare to Work (W2W)
More informationProcurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement
Procurement Policy Note Supporting Apprenticeships and Skills Through Public Procurement Action Note 14/15 27 August 2015 Issue 1. Raising skills levels within the UK workforce is key to delivering sustainable
More informationProcurement, Contracting and Contract Management Policy
Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources
More informationNorth East Lincolnshire Council. Debt Management Strategy
North East Lincolnshire Council Debt Management Strategy Section Title Page No 1. Introduction 2. General Principles 3. Principles common to all debts 4. Principles of Enforcement 5. Strategy specific
More informationAlign Technology. Data Protection Binding Corporate Rules Processor Policy. 2014 Align Technology, Inc. All rights reserved.
Align Technology Data Protection Binding Corporate Rules Processor Policy Confidential Contents INTRODUCTION TO THIS POLICY 3 PART I: BACKGROUND AND ACTIONS 4 PART II: PROCESSOR OBLIGATIONS 6 PART III:
More informationRef: S 9/21/05. 22 December 2011. To Heads of Departments / Offices
Ref: S 9/21/05 22 December 2011 To Heads of Departments / Offices Department of Public Expenditure & Reform Circular 15/2011: Mechanism to monitor compliance with employment law in outsourced operations
More informationClaims Management Policy
Claims Management Policy April 2015 Author: Responsibility: Janet Young, Governance & Risk Manager All Staff should adhere to this policy Effective Date: April 2015 Review Date: April 2017 Reviewing/Endorsing
More informationA guide on how to do business with Stockport NHS Foundation Trust. Procurement Buying In to Buying Locally
A guide on how to do business with Stockport NHS Foundation Trust Procurement Buying In to Buying Locally Contents Page Introduction 3 Aim of the guide 4 Corporate Citizenship more than a hospital 4 The
More informationHow to do business with Wiltshire Council
How to do business with Wiltshire Council A guide for local small and medium size businesses including voluntary and community sector organisations June 2013 Page 1 Index 1. Introduction... 3 2. General
More informationOutsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process
CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should
More informationInformation Commissioner's Office
Information Commissioner's Office IT Procurement Review Ian Falconer Partner T: 0161 953 6480 E: ian.falconer@uk.gt.com Last updated 18 June 2012 Will Simpson Senior Manager T: 0161 953 6486 E: will.g.simpson@uk.gt.com
More informationCONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1
CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 PART 3G Contracts Standing Orders 2015/16 Definitions Aggregation is the combining together of the total contract value from separate contracts
More informationPROCUREMENT PROCEDURE
PROCUREMENT PROCEDURE TITLE: Diversity in Procurement ISSUE: 1.0 REFERENCE: BTP/Procurement/Procedure/20 DATE: 11 July 2011 AUTHOR: Freddie Josland/Miranda Smith/ Laraine Jackett APPROVED BY: Tony Foster
More informationGuidance Developing Commissioning Support: Towards Service Excellence was published by the NHS Commissioning Board Authority in February 2012.
Commissioning support: Key facts Introduction The setting up of the new clinical commissioning system has given the NHS the opportunity to think about what support clinical commissioners need to more efficiently
More informationThe Small Business Friendly Concordat. A statement of principles for Basingstoke and Deane Borough Council
The Small Business Friendly Concordat A statement of principles for Basingstoke and Deane Borough Council Declaration of Support for the Small Business Friendly Concordat Basingstoke and Deane Borough
More informationDELEGATED POWERS REPORT NO. All reports 1. Governance Service receive draft report Name of GSO Paul Frost
DELEGATED POWERS REPORT NO. 2007 SUBJECT: Participation in London-wide procurement of NHS Complaints Advocacy Services Control sheet All of the following actions MUST be completed at each stage of the
More informationGrievance and Disputes Policy and Procedure. Document Title. Date Issued/Approved: 10 August 2010. Date Valid From: 21 December 2015
POLICY UNDER REVIEW Please note that this policy is under review. It does, however, remain current Trust policy subject to any recent legislative changes, national policy instruction (NHS or Department
More informationPolicy for the Receipt and Management of Petitions
Policy for the Receipt and Management of Petitions Title of document Type of document Description Target audience Author Directorate Approved by Policy for the Receipt and Management of Petitions Policy
More informationBusiness Continuity Policy and Business Continuity Management System
Business Continuity Policy and Business Continuity Management System Summary: This policy sets out the structure for ensuring that the PCT has effective Business Continuity Plans in place in order to maintain
More informationWelsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report
Welsh Government Response to the Report of the National Assembly for Wales Public Accounts Committee on Grant Management in Wales Final Report The Welsh Government appreciates both the time and effort
More informationAccounting standards support to English college finance staff
Accounting standards support to English college finance staff Invitation to Tender for Consultant Contract for Accounting Standards Support to further education (FE) College and Sixth Form College finance
More informationProgramme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
More informationInternal Audit Plan 2015/16
(Including Strategic Plan 2014-2017) Contents Executive Summary 1. Internal Audit Plan Approach 1.1 Internal Audit Plan Requirements 1.2 Plan Methodology 2. Your Strategic Internal Audit Plan 2.1 Risk
More informationProcurement, Competition and Choice in the new healthcare landscape
T 0844 381 4180 E info@psnc.org.uk www.psnc.org.uk Procurement, Competition and Choice in the new healthcare landscape May 2013 Monitor review - A fair playing field for the benefit of NHS patients On
More informationREGISTERS OF SCOTLAND SUPPLIER GUIDE TO PROCUREMENT
REGISTERS OF SCOTLAND SUPPLIER GUIDE TO PROCUREMENT 1. PURPOSE The purpose of this Guide is to provide suppliers with information and guidance on Purchasing and the Procurement function at Registers of
More informationBIG LOTTERY FUND Document archive and retention policy
BIG LOTTERY FUND Document archive and retention policy December 2010 Sonia Howe Head of Information Governance For further information regarding retention schedules please contact Page 1 of 18 Version
More informationSocial Value briefing
Social Value briefing About This Briefing This briefing is provided on behalf of the Department for Education s overarching strategic partnership for voluntary, community and social enterprise sector organisations
More informationHousing Related Support Contract Management Framework 2009/10
Housing Related Support Contract Management Framework 2009/10 0 If you would like this information in large print, audio tape or in any other format or language please contact the public information officer
More informationAWARD OF CONTRACT MAINTENANCE AND UPGRADE OF THE HIGHWAYS ASSET MANAGEMENT SYSTEM (REF: CU2373)
Wards Affected: All Wards ITEM 9 CABINET PROCUREMENT COMMITTEE 5 AUGUST 2014 AWARD OF CONTRACT MAINTENANCE AND UPGRADE OF THE HIGHWAYS ASSET MANAGEMENT SYSTEM (REF: CU2373) Author: Rachael Kingsley, Head
More informationwww.portsmouth.gov.uk Part 3D - Officers' Employment Procedure Rules 1
Part 3D - Officers' Employment Procedure Rules 1 These rules determine procedures to be followed in the recruitment of senior officers of the council and in any disciplinary action which may become necessary
More informationBrighton and Sussex University Hospital NHS Trust
Brighton and Sussex University Hospital NHS Trust Year Ending 31 March 2013 Annual Audit Letter July 2013 Ernst & Young LLP Executive summary Ernst & Young LLP 1 More London Place London SE1 2AF Tel: +44
More informationThe Future of Adventure Play in Islington
Children s Services 222 Upper Street, London N1 1XR Report of: Executive Member for Children and Families Meeting of: Date Ward(s) Executive 27 th November All Delete as appropriate Non-exempt SUBJECT:
More informationMPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT
MPA/MPS PROCUREMENT STRATEGY 2009-12 TO BE THE UK LEADER IN PUBLIC SECTOR PROCUREMENT CONTENTS Foreword ------------------------------------------------------------------------ 3 Executive Summary ---------------------------------------------------------
More informationContents. 1. Doing Business with Gwynedd Council. 1. 2. Council Structure and Contacts 2
Contents Page 1. Doing Business with Gwynedd Council. 1 2. Council Structure and Contacts 2 3. How to find out about the opportunities offered by Gwynedd Council 3 4. Types of Procurement 3 5. Tendering
More informationInternal Audit Report. Chief Executive s Unit. Review of Contract Management
Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY
More informationNHS Constitution Patient & Public Quarter 4 report 2011/12
NHS Constitution Patient & Public Quarter 4 report 2011/12 1 Executive Summary The NHS Constitution was first published on 21 st January 2009. One of the primary aims of the Constitution is to set out
More informationHealth and Safety Policy Part 1 Policy and organisation
Health and Safety Policy Part 1 Policy and organisation ICO H&S Policy Policy and organisation, June 2014 Page 1 of 6 1. Scope 1.1 The Health and Safety policy applies to all employees of the Information
More informationQuality Impact Assessment. Executive summary
Report to Public Trust Board 28 th February 2013 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Quality Impact Assessment Director of Quality and Safety/ Chief Nurse Director
More information(2) That the contract runs from 1 April 2015 for an initial period of seven years. The value of the contract will be in the order of 10m per annum.
Cabinet Member for Corporate Relations Redesign of Facilities Management Services April 2014 Report by Director Service Operations and Principal Manager Facilities Management Ref No: CR02(14/15) Key Decision:
More informationJob Description. Line Management of a small team of staff administrating and managing patient and professional feedback and incidents.
Job Description Job Title Pay Band Base Dept./Team Responsible to Accountable to Responsible for Complaints, Incidents and Governance Manager New Alderley House, Macclesfield Eastern Cheshire Clinical
More informationCode of Practice. Overall. A1.2 Segregation, identification and safeguarding of trust assets is paramount.
Code of Practice A Overall A1. Integrity A TACT member must conduct its business with integrity. A1.1 Members will ensure that their key persons and officers work with the highest integrity at all times
More informationDigital Inclusion Programme Started. BL2a
PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects
More informationDisability Action Plan
Disability Action Plan Northern Ireland Social Care Council (NISCC) March 2013 This document is available in audio format, Braille, Easy Read and as an accessible pdf. It can be made available on request
More informationCode of Practice for Ministerial Appointments to Public Bodies
This Code of Practice is published by the Commissioner for Public Appointments in fulfilment of his duties as set out in the Order in Council for Public Appointments 2002 (as amended). This Code is effective
More informationBecoming Tender Ready
Becoming Tender Ready Difference Between Procurement & Tendering Procurement is the process of acquiring goods, works and services, covering both acquisition from third parties and from in-house providers.
More informationBRITISH COUNCIL DATA PROTECTION CODE FOR PARTNERS AND SUPPLIERS
BRITISH COUNCIL DATA PROTECTION CODE FOR PARTNERS AND SUPPLIERS Mat Wright www.britishcouncil.org CONTENTS Purpose of the code 1 Scope of the code 1 The British Council s data protection commitment and
More informationThe Newcastle Upon Tyne Hospitals NHS Foundation Trust. Medical Devices Procurement Procedure
The Newcastle Upon Tyne Hospitals NHS Foundation Trust Medical Devices Procurement Procedure Version No : 4.1 Effective From 4 December 2012 Expiry Date: 30 November 2013 Date Ratified: 3 December 2012
More informationInvest in the future. Increase your knowledge.
Invest in the future. Increase your knowledge. Services for professional procurement. Be better informed, make better decisions. EU procurement training, advice, support and consultancy for regulated procurement
More informationCode of Corporate Governance
www.surreycc.gov.uk Making Surrey a better place Code of Corporate Governance October 2013 1 This page is intentionally blank 2 CONTENTS PAGE Commitment to good governance 4 Good governance principles
More informationTRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes
TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission
More informationDecisions 1. Permission to tender for a recruitment partner to supply 15 permanent social work practitioners with a contract value of 159,000.
ACTION TAKEN UNDER DELEGATED POWERS BY OFFICER 28 th October 2015 Title Report of Wards Status Recruitment of Children s Social Work Practitioners Nicola Francis, Family Services Director All Public Enclosures
More informationDerbyshire Trading Standards Service Quality Manual
Derbyshire Trading Standards Service Quality Manual This Quality Manual has been developed to give a broad outline of how the Trading Standards Division s range of services comply with the requirements
More informationPROCUREMENT & LOGISTICS DEPARTMENT
PROCUREMENT & LOGISTICS DEPARTMENT Tender/OJEU Procedure Overview This procedure applies to all purchases over 50,000 not covered by existing contracts and should be followed in conjunction with the Tender/OJEU
More informationTendering Policies and Procedures
Tendering Policies and Procedures Tendering Policies and Procedures Content Pg. Mission Statement..3 Introduction....4 Background to the EPS (formerly Shannon Consortium Procurement Network) 4 The Key
More informationJOB DESCRIPTION. Position Title and Number: Senior Procurement Officer (100618) Health, Wellbeing & Commissioning
JOB DESCRIPTION Position Title and Number: Senior Procurement Officer (100618) Grade: Department: Section: Responsible to: Responsible for: SO2 People Directorate Health, Wellbeing & Commissioning Team
More informationCode of Practice Revised Edition 2014
Code of Practice Revised Edition 2014 A CODE OF PRACTICE FOR ADVOCATES 1 Contents Page 1. Introduction... 3 2. The Advocacy Charter... 5 3. The Code of Practice... 7 4. References... 19 A CODE OF PRACTICE
More informationOpen Selection Funding Round Summary. Families and Communities Programme. Family Law Services Funding Round Summary
Families and Communities Programme Family Law Services Funding Round Summary August 2014 1 Family Law Services The Family Law Services Sub-Activity is funded by and under the policy responsibility of the
More informationPOLICY FOR THE REPORTING AND MANAGEMENT OF PATIENT COMPLAINTS
Item 9 POLICY FOR THE REPORTING AND MANAGEMENT OF PATIENT COMPLAINTS Authorship: Chief Operating Officer Approved date: 20 September 2012 Approved Governing Body Review Date: April 2013 Equality Impact
More informationGoverning Body Organisational Development Programme 2015/16
Governing Body Organisational Development Programme 2015/16 Governing Body meeting 5 February 2015 C Author(s) Julie Glossop, Senior Commissioning Manager Sponsor Idris Griffiths, Chief Operating Officer
More informationReporting The Project Board shall report to the sponsoring Department political board.
Appendix 13 La Mare de Carteret Schools Project Board Mandate Summary (Project restart version March 2014) Function The Project Board is accountable to the Education Department for all aspects contributing
More informationTRUST SECURITY MANAGEMENT POLICY
TRUST SECURITY MANAGEMENT POLICY EXECUTIVE SUMMARY The Board recognises that security management is an integral part of good, effective and efficient risk management practise and to be effective should
More informationHow to do Business with the London. Borough of Sutton
How to do Business with the London Borough of Sutton February 2013 1 About this guide This guide has been developed to assist businesses wishing to sell their goods and services to the Borough. Contents
More informationSECONDMENT POLICY. Reviewer: Grampian Area Partnership Forum. Signature Signature Signature. Review date:
SECONDMENT POLICY Co-ordinator: Reviewer: Approver: Director of HR and Strategic Change Grampian Area Partnership Forum Grampian Area Partnership Forum Signature Signature Signature Identifier: NHSG/POL/07/HR
More informationNHS Risk Management and Organising Requirements
www.nhsprotect.nhs.uk Standards for providers 2015-16 Security management Standards for providers 2015/16: Fraud, bribery and corruption Click here for index page Standards for providers 2015-16: Security
More informationClaims Management Policy
Claims Management Policy GOV 08 October 2007 GOV 08 Claims Management Policy 3.doc Page 1 of 12 Document Management Title of document Claims Management Policy Type of document Policy GOV 08 Description
More informationABERDEEN CITY COUNCIL. Name of Committee : Resources Management Committee
ABERDEEN CITY COUNCIL Name of Committee : Resources Management Committee Date of Meeting : 29 March 2007 Title of Report : CRM System Procurement Lead Officer : Jacek Nowak, Head of Customer Relations
More informationContract Management Handbook. A Guide to contract management at the University
Contract Management Handbook A Guide to contract management at the University July 2012 CONTENTS 1. INTRODUCTION... 4 2. PURPOSE... 4 2.1 Using this Handbook... 5 3. CONTRACT MANAGEMENT FRAMEWORK... 5
More informationEffective complaint handling
This guide sets out key information for state sector agencies about developing and operating an effective complaints process. It also provides information about the Ombudsman s role, as an independent,
More informationGuidance on Framework Agreements
1. Introduction Guidance on Framework Agreements The purpose of this document is to provide guidance to public purchasers on the operation of framework agreements as provided for under current public procurement
More informationAudit and Performance Committee Report
Audit and Performance Committee Report Date: 3 February 2016 Classification: Title: Wards Affected: Financial Summary: Report of: Author: General Release Maintaining High Ethical Standards at the City
More informationJob Description. To lead and effectively manage the Empty Homes team which is responsible for:
Job Description Post Title Post Number Service Area / Department SDU Accountable to (Line Manager) Responsible for (Direct Reports Post Title) Empty Homes Manager RT01008 Leasehold and Lettings Housing
More informationTHE FUNCTIONS OF CLINICAL COMMISSIONING GROUPS (UPDATED TO REFLECT THE FINAL HEALTH AND SOCIAL CARE ACT 2012)
THE FUNCTIONS OF CLINICAL COMMISSIONING GROUPS (UPDATED TO REFLECT THE FINAL HEALTH AND SOCIAL CARE ACT 2012) DH INFORMATION READER BOX Policy Clinical Estates HR / Workforce Commissioner Development IM
More informationBusiness Continuity Policy & Plans
Agenda Item 8.3a SNCCG Governing Body 11.03.2014 Business Continuity Policy & Plans Ref Number: Version: 1 Status: Pending Approval Author: A Brown Approval body Governing Body Date Approved Date Issued
More informationCABINET. 21 October 2014. Accountable Divisional Director: Glynis Rogers, Divisional Director of Commissioning and Partnerships
CABINET 21 October 2014 Title: Re-tender of Translating and Interpreting Services Report of the Leader of the Council Open Report Wards Affected: All Report Author: Mark Tyson, Group Manager, Integration
More informationOverview of the Transfer of Undertakings (Protection of Employment) Regulations 2006
TUPE Overview of the Transfer of Undertakings (Protection of Employment) Regulations 2006... 1 Service Provision Changes... 1 Employer Liability Information... 2 Liability for Failure to Inform and Consult
More informationDENTAL ACCESS PROGRAMME GUIDE TO THE USE OF SCHEDULE 18 (STAFF TRANSFER) AND TUPE TRANSFERS UNDER THE PDS PLUS AGREEMENT
DENTAL ACCESS PROGRAMME GUIDE TO THE USE OF SCHEDULE 18 (STAFF TRANSFER) AND TUPE TRANSFERS UNDER THE PDS PLUS AGREEMENT Beachcroft LLP 7 Park Square East Leeds LS1 2LW UK tel: +44 (0) 113 251 4700 fax:
More information