1 nora Flash Coving, Sanitary Base and Wall Base Systems Installation Guide

2 nora Flash Coving, Sanitary Base and Wall Base Systems Installation Guide Site Conditions The following shall be achieved prior to installing nora flooring. 1. Service temperature and relative humidity or 68 F ± 5 F and 50% RH ± 10% for 48 hours before, during and 72 hours after the installation. Flooring, adhesives, and accessories must also be acclimated for a minimum 48 hours in advance of the installation. Note: do not use gas fueled blowers. 2. Areas of the flooring subjected to direct sunlight (example: through doors or windows) must be covered using blinds, curtains, cardboard or similar throughout the installation and for a period of 72 hours after the installation to allow the adhesive to cure. Moisture Testing 1. nora systems, Inc. recommends the following test methods for all concrete subfloors regardless of age: ASTM F2170 Standard Test Method for Determining Relative Humidity in Concrete Floor Slabs Using in situ Probes when tested with Wagner Rapid RH meters, or ASTM F2420 Standard Test Method for Determining Relative Humidity on the Surface of Concrete Floor Slabs Using Relative Humidity Probe Measurement and Insulated Hood. Please visit for copies of the standards. 2. The maximum allowable results shall be as follows: ASTM F2170 = 80 % RH (with Wagner Rapid RH), when using 410, 414, PU 310 and PU 316. ASTM F2170 = 75 % RH (with Wagner Rapid RH), when using PS adhesive and nora dryfix. ASTM F2420 = 70 % RH 3. For all on or below grade concrete subfloors, a permanent effective vapor retarder with a low permeance (less than 0.1) having a minimum thickness of 10 mils, or meeting the requirements of the latest edition of ASTM E1745 (Standard Specification for Water Vapor Retarders Used in Contact with Soil or Granular Fill under Concrete Slabs) and shall be placed directly underneath the concrete, above the granular fill. 4. All on or below grade concrete slabs that do not have a permanent effective vapor retarder underneath will require a Surface Moisture Suppression System. Please contact the manufacturer of the system prior to use to confirm that the permeance is less than 0.1, and for the required coverage (sq. ft. per gallon) and any other specific usage instructions that shall be followed. Concrete Slab Dry Granular Material Vapor Retarder 5. For above grade concrete slabs with moisture readings above the maximum allowed, or slabs that have a permanent effective vapor retarder placed directly underneath with readings above the maximum allowed, use a Surface Moisture Suppression System that is fully warranted to avoid any moisture / ph related failures with the given conditions/test results. Please contact the manufacturer of the system prior to use for confirmation and specific usage and preparation instructions including the required coverage (sq. ft. per gallon) and any other specific instructions that shall be followed. 2

3 Subfloor Preparation Concrete Subfloors 1. Concrete subfloors shall be dry, clean, smooth, structurally sound and prepared per ASTM F710 Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring. Note: all local, state and federal regulations shall be followed. 2. Test for moisture and confirm the slab is permanently dry or take corrective measures. 3. The concrete subfloor shall be smooth and flat to an acceptable tolerance to the end user, who must also be aware that undulations in the subfloor may show through the finished flooring. 4. If required, use a suitable Portland Cement based smoothing compound (minimum 3,000 PSI compressive strength). A primer may be required prior to the smoothing compound. Please refer to the manufacturer s written instructions. 5. All other manufacturer s products used shall be installed according to their written instructions and be fully warranted for product defect, product performance and workmanship. 6. The substrate shall be free of dust, dirt, wax, oil, grease, solvent, residual adhesive, adhesive removers, coatings, sealers, finishes, film forming curing compounds, silicate penetrating curing compounds, alkaline salts, mold, mildew, excessive carbonation or laitance or anything that may affect the adhesive bond. 7. Concrete subfloors shall be porous (this does not mean a skim coat of smoothing compound). To test this, place a droplet of water on the surface of the subfloor (without a skim coat). It should begin to absorb into the concrete within 5 minutes to be considered porous. If the subfloor is not porous, then please contact the nora Technical Department. 8. Do not use chemical removers; please refer to the Resilient Floor Covering Institute s (RFCI) recommended work practices for removal of existing floor coverings and adhesives available on 9. Use water based sweeping compounds or a vacuum. Do not use wax, oil or silicon based sweeping compounds. 10. Mat Bond Tests are always recommended as they can be a useful indicator in determining subfloor compatibility. 11. Saw cuts shall be cleaned and prepared correctly; follow the written instructions of the selected product manufacturer after ensuring that the product is fully warranteed for the intended use. 12. Do not install over any expansion joints. 13. For recommendations on installing over radiant heated concrete, please contact the nora Technical Department. Wood Subfloors 1. nora flooring shall not be laid on wooden substrates that are directly in contact with concrete subfloors on or below grade even if built on sleepers. All suspended wood floors shall have adequate underfloor ventilation and a permanently effective moisture vapor retarder shall be placed on the ground beneath the air space. Note: all local, state and federal regulations shall be followed. 2. American Plywood Association (APA) underlayment grade plywood shall be used and installed as per ASTM F1482 Standard Practice for Installation and Preparation of Panel Type Underlayments to Receive Resilient Flooring. 3. Please note: as plywood may expand and contract due to changes in moisture content and temperature, nora systems, Inc. can not accept any liability of the joints telegraphing through the finished floor. Other Substrates 1. Please contact nora Technical Department for specific recommendations. 3

4 Flash Coving System (Boot Method) 1. Unroll the sheet product and allow it to relax (lay flat before cutting). 2. Install any required cove cap strip following the manufacturer s written instructions. Ensure that the opening is sufficient to accommodate the thickness of the flooring material. 3. Install nora basefix (using the correct size), to a clean, dry, smooth wall (keeping it close to the subfloor). 4. Cut the nora cove stick to size, mitering all corners. 5. Cut and remove the bottom 1 of wax paper from the basefix and adhere the cove stick to the wall (no need to adhere it to the subfloor). 6. Vacuum the entire prepared area. 7. The dry lay method is required (no more than will be installed that day). The end user, architect or designer should decide the layout of the flooring. 8. noraplan rolls have arrows printed on the back; these shall all point in the same direction. 9. Locate your start line, then cut the sheets to the required lengths making sure to leave the flooring lapped up the wall (so it can be trimmed into the capping strip later) and begin laying the rolls into position. 10. Make relief cuts to avoid tears at any corners. 11. All seams shall have a minimum 1 1/4 (1.25 ) overlap. Be careful to insure the tapered edges/uncut edges are underneath. The flooring pattern does not always continuously flow into the tapered edge, so check before cutting to remove the tapered edge and be sure to maintain the flow of the flooring pattern. 12. All seams are to be double-cut using one of the methods listed below. When cutting seams, keep in mind that all seams shall have a neat fit (do not pressure fit), regardless of whether the seams are to be welded or not. For seam cutting of noraplan acoustic, please refer to Method III. 13. Cut or trim in the sides of the area using a scriber, suitable trimming tool or, if preferred, free hand. The end cuts may also be completed now or after adhering. 14. Cut all corners using either the Internal or External corner Method (detailed below). Internal Corners Method 4

5 a. Push the flooring into the internal corner as far as possible without damaging the flooring. b. Cut a straight line in the flooring, starting at the base of the cove stick through to the top edge of the flooring at a 45 (center of the corner). c. Place one side into position and trim off the excess material, resulting in a straight cut down the center of the corner and through to the base of the nora cove stick. d. Repeat with the second side. External Corners Method a. Using a pencil, or similar, make reference marks from the corner at a 45 angle to where the floor seam will be (for use as a guide when cutting). b. Cut the flooring from the outside corner to the guide marks (45 angle), then cut the flooring approximately 2 perpendicular to the wall. Finally, make a vertical cut up the wall. Carefully remove the excess (in one piece) for use as a template. c. Trace cut the removed section onto a new piece of flooring. The front vertical shall be cut up (large) from the Uplift a workable section of flooring and apply the specified adhesive system as detailed below, allowing open time etc. 16. At the walls, carefully fold the flooring back and be careful not to crease or tear the flooring. Remove the wax paper and keeping the floor tight to the cove stick, place the flooring into the Basefix tape, rubbing into place to ensure a good bond. 5

6 17. Carefully place any external corners (Boot) into the Basefix and rub into place. 18. Trim the flooring to fit the cap strip and insert. 19. All vertical seams shall be cold welded as detailed in the nora Welding Installation Guide, available at ESD flooring installations (ed products) 1. In rooms up to 2,500 sq. ft. in size, a copper strip must be applied directly to the subfloor (minimum 4 ft under the floor) and extended to a predetermined grounding point (to be connected by a qualified electrician). In rooms larger than 2,500 sq. ft., additional grounding points shall be defined and copper strips installed as mentioned above 2. nora specified conductive adhesive shall be used for the installation of noraplan ESD protection flooring, using the recommended trowel serration. Method I 1. Double cut using the nora knife. The nora knife can be adjusted to cut left or right handed, using a standard utility straight blade. 2. Use two small pieces of scrap flooring as shown to adjust how deep you want the blade to cut. Adjust the blade to cut completely through the top sheet and about 3/4 through the bottom sheet. The blade holder (section with R and L on it) should also be set at a depth to slide on top of your straight edge. 3. Position the straight edge about 1/2 from the top edge. Slide the nora knife blade along the side of the straight edge while pressing down. This will remove the factory edge and - at the same time - cut well into the bottom sheet. 4. Using a utility knife with a straight blade and a straight edge cut the last six inches of the seam at both ends, making sure you cut completely through both while keeping the knife blade as vertical as possible. 5. Remove the trimming from the top sheet, then to remove the waste from the bottom sheet, choose one of the following to avoid a burred edge: Place a screwdriver at one end horizontally between the tapered edge waste, and the balance of the lower sheet, making sure that the screwdriver handle is over the top sheet. Slide the screwdriver along the seam and remove the tapered edge (in a downward direction). 6

7 Pull the tapered edge in a downward direction (pulling it under itself). Method II 1. When double cutting the seam, use a straight edge as a guide. Position the straight edge about 1/2 from the top edge. Cut through the top sheet and approximately 3/4 of the thickness of the bottom sheet using a utility knife and a sharp straight blade. When making the cut, hold the utility knife as vertical as possible. 2. Remove the trimming from the top sheet, then to remove the waste from the bottom sheet, choose one of the following to avoid a burred edge: Place a screwdriver at one end horizontally between the tapered edge waste, and the balance of the lower sheet, making sure that the screwdriver handle is over the top sheet. Slide the screwdriver along the seam and remove the tapered edge (in a downward direction). Pull the tapered edge in a downward direction (pulling it under itself). Method III (Acoustic Sheet Flooring) 1. Using Method I or II, cut through the top sheet and 3/4 through the bottom sheet. 2. Using a utility knife with a large hook blade, complete the cut through the bottom sheet, at a slight angle, resulting in a slight undercut, and remove the trimmings. 3. All noraplan acoustic sheet flooring seams must be heat or cold welded. Sanitary Base System 1. Use a pencil and straight edge to mark the subfloor 2 from the wall. 7

8 2. Install nora Basefix to the wall. 3. Dry lay the flooring as detailed in the Flash Coving System (Boot Method), cutting any required seams and ensuring the flooring is at a length and width between the wall and 2 pencil line (where sanitary base is required). 4. Uplift a workable section and apply the specified adhesive system, detailed below. Note: If a wet adhesive is to be used, it should be applied only up to the pencil lines (2 from the wall). 5. Trim the floor at the perimeter using a straight edge and utility knife 2 from the wall (where sanitary base is required), and flush at all doorways, etc. 6. If a wet adhesive system was used apply nora Basefix 50 to the subfloor between the flooring and the wall. 7. Dry cut the nora sanitary base to size, miter the foot and ensure an even gap between sections of about 1/8 as these seams shall be cold welded later. 8. Remove the wax paper from the tape and place the sanitary base into position and press firmly into place, keeping it tight to the flooring. 9. Tap the sanitary base with a rubber mallet or roll with a hand roller to ensure a good bond. nora Wall Base System 1. The walls shall be clean, dry and smooth. 2. nora wall base can be adhered using one of the following adhesives: a. nora Basefix 90 (applied to the wall) b. Cove Base adhesive (applied to the wall or wall base following the manufacturer s written instructions) 3. Internal corners can be cut and tightly butted or completed in one piece by heating with a heat weld gun and creasing, hold it in the creased position and allow to cool then cut and miter the foot (in situ). 4. External corners shall be heated using a heat weld gun, creased, then allowed to cool. nora systems, Inc does not recommend shaving the back as this will weaken the corners. 5. Adhere to the wall, positioning it carefully using your chosen adhesive method and press or roll (using a hand roller) to obtain a strong bond. nora Acrylic 410/414 System It is necessary to use the dry lay method (no adhesive while laying/cutting the flooring). 1. Uplift a workable area and vacuum the subfloor and back of the flooring to remove any debris. 2. The adhesive shall be applied using a 1/16 x 1/16 x 1/16 V-notched trowel (such as Gundlach ACT), without the formation of puddles or any missed patches. Note: do not overlay fresh adhesive over drying adhesive as this will create an adhesive line. 3. Allow the appropriate open time - a minimum of 10 minutes. Times will vary according to air temperature, subfloor temperature, subfloor porosity, humidity and air circulation. The adhesive must be able to transfer to your finger tips with a light touch and just start to string while the core of the serrations remains wet (resulting in adhesive transfer). If the adhesive is dry, do not install the flooring - remove and replace the adhesive. 8

9 4. Carefully replace the noraplan sheets into the adhesive and check that you have adhesive transfer before continuing. Make sure the seams are together without stress; do not pressure fit (force seams together). 5. If you have not already done so, cut in the ends of the adhered area using the free hand method or a suitable trimming tool. 6. Using a 100 lb. roller, roll slowly in both directions to remove all air bubbles and result in good adhesive transfer. nora systems, Inc. recommends using carpet off-cuts and double sided tape to cover the roller, which will help remove all air pockets from any dips in the substrate. This is far more effective and will help avoid a punch list. 7. Repeat the procedure for the second half of this area, then the balance of the project. 8. Remove any fresh adhesive from the surface of the flooring with a damp clean cloth (water). Dried adhesive shall be removed with Isopropyl alcohol and a clean cloth. 9. Do not allow any foot traffic for 12 hours. No heavy rolling loads to be allowed for 72 hours (hospital beds, operating tables or similar). 10. If required, after 12 hours protect the flooring using plywood, Masonite, or a similar product ensuring first that the flooring surface is free of all loose debris. Lay the panels so that the edges form a butt joint and tape the joint to prevent excess movement of the panel and to prevent debris entrapment under the joint. nora PU 310/316 System 1. This system is not normally recommended for use with sheet products. If needed, please contact the nora Technical Department for specific recommendations. nora dryfix System 1. The nora dryfix tape should be installed prior to dry laying the flooring. 2. Carefully vacuum the required area to remove all loose debris. 3. Unroll the nora dryfix tape into position. If required, it can be repositioned providing no downward pressure was applied. Overlap all seams by at least 1/2 and press into place using a broom to remove all air. 4. Allow a minimum of 15 minutes before cutting seams. If the tape has stretched it will return to its original size. 5. Trace cut all seams without damaging the subfloor, resulting in no overlaps or gaps, then remove the excess material. The use of a straight edge is recommended. 6. If required, the tape can now be patched to remove any debris trapped underneath (or repair any short cuts). 7. Dry lay the flooring as detailed in appropriate nora Installation Guide available at 8. Cut in any seams and, if preferred, the perimeters, or leave them until after adhering. 9

10 9. Uplift a workable area and vacuum the surface of the nora dryfix and ensure the back of the flooring is clean. 10. Remove the protective wax paper, fold or roll the wax paper for ease of disposal. 11. Replace flooring onto the exposed tape and do not stand on it until you are sure of correct positioning, as it is still possible to reposition. 12. Use a carpet covered roller to remove any air bubbles and ensure a good bond. 13. Weld all seams. This can be done immediately. For detailed instructions, please refer to nora Welding Systems Installation Guide, available at nora systems, Inc. can not accept any liability for seams that open up or peak due to climate/temperature change when seams are not welded. nora Acrylic PS System (2mm flooring only) 1. nora Acrylic PS adhesive shall not be used on radiant heated floor systems or unconditioned areas (without permanent temperature and humidity controls). 2. The adhesive must be spread uniformly without the formation of puddles or missed patches. 3. The adhesive shall be applied using only a 1/32 x 1/16 x 1/32 fine U-notched trowel (such as Gundlach FFA). Do not use larger notched trowels. 4. Allow the adhesive to dry (no longer white) and place the flooring into the adhesive immediately. 5. Roll slowly with a 100 lb. three section roller in both directions, first from the center out so air does not get trapped under the material, then lengthwise. Repeat the procedure for the second half of this area, then the balance of the project. 6. Remove any fresh adhesive from the surface of the flooring with a damp clean cloth (water). Dried adhesive shall be removed with Isopropyl alcohol and a clean cloth. 7. Do not allow any foot traffic for 12 hours. No heavy rolling loads to be allowed for 5 days (hospital beds or similar). 8. If required, protect the flooring using plywood, Masonite, or a similar product ensuring first that the flooring surface is free of all loose debris. Lay the panels so that the edges form a butt joint and tape the joint to prevent excess movement of the panel and to prevent debris entrapment under the joint. nora systems, Inc. 94 Glenn Street Lawrence, MA Tel: (800) 332-NORA Fax: (978) info-us@nora.com Internet: 05/2010

BENTLEY ELEMENTS COLLECTION LVT

BENTLEY ELEMENTS COLLECTION LVT This document refers to the following products: Product Size Installation direction Seams treatment Elements Tiles See specifications 90 None Elements Planks See specifications Stair Step None Note: This

More information

Fiberglass-Reinforced Sheet Flooring Installation System

Fiberglass-Reinforced Sheet Flooring Installation System Fiberglass-Reinforced Sheet Flooring Installation System Product Adhesive Comments Residential Use Only CushionStep Value Good Better Best FlexStep Duality Premium Premium Plus Modified loose lay method

More information

Vinyl Composition Tile Installation System

Vinyl Composition Tile Installation System Vinyl Composition Tile Installation System Product Gauge Size Vinyl No-Wax (Dry Back) Urethane No-Wax (Dry Back) 0.045" (1.1 mm) 0.080" (2.0 mm) IMPERIAL TEXTURE 0.094" (2.4 mm) STONETEX ChromaSpin COMPANION

More information

INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles

INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles INSTALLATION RECOMMENDATIONS Outdoor Rubber Tiles Prior to Installation: The Outdoor Rubber Tiles and accessory transition pieces intended for this installation have been shipped to you via a freight carrier

More information

Herringbone Pattern Flooring

Herringbone Pattern Flooring Herringbone Pattern Flooring If it s not marked NOFMA, it s not certified. Handling, Storage, Installation and Tips Herringbone is generally manufactured from 3/4 x 2 ¼ or ¾ x 1-1/2 standard tongue & groove

More information

Laminate Flooring T-Lock Angle-Drop Installation Instructions

Laminate Flooring T-Lock Angle-Drop Installation Instructions TECHNICAL SERVICE Laminate Flooring T-Lock Angle-Drop Installation Instructions March 23, 2012 Read all instructions carefully before beginning installation. Make sure that the instructions are the most

More information

Carpet Tile Installation Guidelines

Carpet Tile Installation Guidelines NOTICE FAILURE TO FOLLOW THESE GUIDELINES CAN RESULT IN VOIDING THE CARPET WARRANTY. Installation Guidelines The following instructions should be reviewed prior to installation. Shaw Industries will not

More information

Installation System. Existing Resilient Sheet Floors

Installation System. Existing Resilient Sheet Floors Vinyl Composition Tile Installation System Product Adhesive/Full Spread Adhesive/Tile-On Comment Imperial Texture MultiColor RAVE Stonetex Companion Square Feature Tile/Strips ARTEFFECTS SAFETY ZONE Vinyl

More information

Commercial/Residential Linoleum Sheet Installation System

Commercial/Residential Linoleum Sheet Installation System Commercial/Residential Linoleum Sheet Installation System COMMERCIAL USE ONLY Product MARMORETTE GRANETTE COLORETTE UNI WALTON LINORETTE Gauge 0.080" (2.0 mm) 0.100" (2.5 mm) 0.125" (3.2 mm) 0.100" (2.5

More information

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking) INSTALLATION INSTRUCTIONS FOR GTI CONNECT TILES This document refers to the following products: Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking) 635 X 635 mm 25.5 x 25.5

More information

The Mohawk Group Installation Guidelines for

The Mohawk Group Installation Guidelines for The Mohawk Group Installation Guidelines for Uniplus System II Double Stick Unibond RE Wet Set The Mohawk Group 1975 West Oak Circle Marietta, GA 30062 800-554-6637 www.themohawkgroup.com Field Services

More information

How to Install Hardwood Flooring Over a Sub Floor

How to Install Hardwood Flooring Over a Sub Floor How to Install Hardwood Flooring Over a Sub Floor Installation Preparation Instructions Read the entire instructions before starting your project. 1) INSPECT EACH PLANK (see fig. a) Wood is a natural product

More information

Armstrong Do-It-Yourself Tile Installation System

Armstrong Do-It-Yourself Tile Installation System Armstrong Do-It-Yourself Tile Installation System What tools will I need to install my tile floor? You'll need just the basics: - floor tile (make sure you have enough tile to finish the job) - adhesive

More information

Moisture and Resilient Floor Covering

Moisture and Resilient Floor Covering Moisture and Resilient Floor Covering Moisture related failures of resilient floor coverings installed over concrete have focused unfairly over the years on the premise that the flooring product itself

More information

Fiberglass-Reinforced Sheet Flooring Installation System

Fiberglass-Reinforced Sheet Flooring Installation System RESIDENTIAL USE ONLY Fiberglass-Reinforced Sheet Flooring Installation System Product Gauge Comments FlexStep Value FlexStep Good 0.055" (1.4 mm) 0.065" (1.65 mm) Modified loose lay method: Acrylic double-faced

More information

Bella Cera Engineered Hardwood Flooring Installation Instructions. Check for Proper Color Selection Prior to Installation

Bella Cera Engineered Hardwood Flooring Installation Instructions. Check for Proper Color Selection Prior to Installation Bella Cera Engineered Hardwood Flooring Installation Instructions Check for Proper Color Selection Prior to Installation 1 Important Information before You Begin 1.1 Installer/Owner Responsibility Carefully

More information

INSTALLATION INSTRUCTIONS FOR LAMINATE FLOORING

INSTALLATION INSTRUCTIONS FOR LAMINATE FLOORING INSTALLATION INSTRUCTIONS FOR LAMINATE FLOORING Introduction Laminate flooring is designed to be a floating floor that may be installed over virtually any type of sub floor. It is not nailed or glued to

More information

Adhesive Recommendation for Altro Flooring. Porous (absorbent) subfloors (most wood subfloors and some concrete)

Adhesive Recommendation for Altro Flooring. Porous (absorbent) subfloors (most wood subfloors and some concrete) Adhesive Recommendation for Altro Flooring Product Safety Sheet Flooring Smooth Sheet Flooring Porous (absorbent) subfloors (most wood subfloors and some concrete) Altrofix 30/31 (excessively heavy rolling

More information

Guide Specifications for Maple Flooring Systems

Guide Specifications for Maple Flooring Systems Guide Specifications for Maple Flooring Systems MFMA Guide Specification for Resilient Pre-Engineered Fixed Panel System Purpose This Guide Specification is designed to assist in the production of actual

More information

Installation Guidelines for Modular Carpet

Installation Guidelines for Modular Carpet Installation Guidelines for Modular Carpet Ecoflex Urethane Cushion Backed Carpet Tiles PVC Backed Carpet Tiles Thermoplastic Backed Carpet Tiles Self Lock Carpet Tiles 1975 West Oak Circle Field Services

More information

Please calculate with around 5% more square meters than needed because you will have material loss due to cutting and sorting.

Please calculate with around 5% more square meters than needed because you will have material loss due to cutting and sorting. 1. TEKA Soft Loc Installation Guide Thank you for having chosen TEKA Parquet. To guarantee a constant quality product TEKA engineered hardwood flooring is made out of selected wood species and runs only

More information

Tested to BS 6375: Part 1: 1989 and achieved a weathertightness classification of 2000 Pa (Special)

Tested to BS 6375: Part 1: 1989 and achieved a weathertightness classification of 2000 Pa (Special) THE B6 GLAZING SYSTEM GLAZING SYSTEMS FOR SEPTEMBER 2013 THE B6 HEEL BEAD SEAL SECURITY GLAZING SYSTEM Page 1 DESCRIPTION The B6 Heel Bead Seal Security Glazing System is suitable for installing all types

More information

12 POLYURETHANE ADHESIVE (PU 105)

12 POLYURETHANE ADHESIVE (PU 105) 12 POLYURETHANE ADHESIVE (PU 105) DISCLAIMER: Refer to page 5 of this document. 12.1 DESCRIPTION PU 105 is a high performance two-part polyurethane adhesive for both indoor installations of Mondo rubber

More information

GENERAL RUBBER LINING PRINCIPLES

GENERAL RUBBER LINING PRINCIPLES GENERAL RUBBER LINING PRINCIPLES I. METAL PREREQUISITES Metal to be lined should meet the requirements as stated in section 8 Metal Fabrication and section 12 Blasting and Cementing Procedures. The surface

More information

Shower Walls and Tub Surrounds

Shower Walls and Tub Surrounds Reverso en español TEC Skill Set How-To Project Guide Shower Walls and Tub Surrounds 3 Steps to a Beautiful Tile Surface! 1. Prepare the surface 2. Set the tile 3. Grout and caulk H.B. Fuller Construction

More information

INSTALLATION THE SIMPLIFIED VERSION

INSTALLATION THE SIMPLIFIED VERSION Fo Subfloor has to be flat, permanently dry, solid and clean. ng INSTALLATION THE SIMPLIFIED VERSION Floori rbo Adhésif Modul up pr é c o n is e Trim off over lengths leaving 1mm gap all around the walls.

More information

PRODUCT CONSTRUCTION ROLL WIDTH

PRODUCT CONSTRUCTION ROLL WIDTH products Inlaid: Fine Fields / Magna Homogenous Inlaid: BioSpec MD / Lifelines II Heterogeneous Light: Aberdeen Collection / Insight Plus Slip-Retardant Sheet: Mannington Assurance II roll widths PRODUCT

More information

VINYL CLICK FLOORING INSTALLATION GUIDE

VINYL CLICK FLOORING INSTALLATION GUIDE VINYL CLICK FLOORING INSTALLATION GUIDE Owner/Installer Responsibility Prior to installing a single board, you or the installer must determine that the job-site environment and the sub-surfaces meet the

More information

ENGINEERED FLOORING INSTALLATION

ENGINEERED FLOORING INSTALLATION ENGINEERED FLOORING INSTALLATION ATTENTION! INSTALLER/OWNER RESPONSIBILITIES Beautiful hardwood floors are a product of nature and, therefore, they will show variations in color, grain, texture, and appearance.

More information

VC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised

VC 104+ Rigid Grade / Rigid Grade Imagine VC 104 Rigid Grade Commercial Customised Page 1 of 6 instructions VC 104+ Rigid Grade / VC 104+ Rigid Grade Imagine / (for the rest of this document referred to as VC 104) can be applied to new and used trucks and trailers with painted rigid

More information

DIY CABINET REFACING INSTALLATION GUIDE

DIY CABINET REFACING INSTALLATION GUIDE DIY CABINET REFACING INSTALLATION GUIDE CABINET REFACING INSTALLATION Are you ready to reface your outdated cabinets? This guide will show you how to install your new Facelifters Cabinet Refacing Products

More information

Division 9. SignaFlor Pad and Pour Flooring System

Division 9. SignaFlor Pad and Pour Flooring System Division 9 SignaFlor Pad and Pour Flooring System SPECIFICATIONS Page 1. General... 2 1.1 Description 2 1.2 Quality Assurance 2 1.3 Submittals 2 1.4 Delivery and Storage 3 1.5 Warranty 3 1.6 Working Conditions

More information

COMMERCIAL RESILIENT INSTALLATION GUIDELINES

COMMERCIAL RESILIENT INSTALLATION GUIDELINES COMMERCIAL RESILIENT INSTALLATION GUIDELINES GENERAL INFORMATION All substrates to receive moisture sensitive floor covering require proper moisture testing. Use only Portland based patching and leveling

More information

Amorim Rubber Flooring Specifications

Amorim Rubber Flooring Specifications Amorim Rubber Flooring Specifications Test Method Amorim Typical Value Durometer, Shore A, points of hardness ASTM D2240-97 60 Density, lbs/ft 3 ASTM D297-93 Part A, Section 16.3 64 Compressibility @ 100

More information

Minor Cracks in Horizontal Surfaces

Minor Cracks in Horizontal Surfaces Cracks, chips and broken or flaking areas in concrete are not only unsightly, they can lead to further deterioration of the surface. The result is a costly replacement project as opposed to a simple repair.

More information

Your guide to home maintenance. Flat Roofs

Your guide to home maintenance. Flat Roofs Your guide to home maintenance Flat Roofs Your guide to home maintenance is a series of information leaflets that gives you all the information you need to keep your home in tiptop condition. Flat Roofs

More information

ITEM 599.06060008 THERMOPLASTIC MEMBRANE ROOFING

ITEM 599.06060008 THERMOPLASTIC MEMBRANE ROOFING DESCRIPTION Construct adhered membrane roofing system, roof insulation, and vapor retarder in accordance with these specifications. MATERIALS: General: Provide installed roofing membrane and base flashings

More information

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials SECTION 03 92 50 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings,

More information

CHAPTER 3 MOISTURE TESTING

CHAPTER 3 MOISTURE TESTING CHAPTER 3 MOISTURE TESTING Part I - Moisture Testing for Wood Subfloors A. Testing Requirements 1. Test for moisture at several locations in the room a minimum of 20 per 1,000 square feet and average the

More information

Installation Instructions for Fletco Carpets

Installation Instructions for Fletco Carpets Table of Contents The backing is a very important part of a carpet, as well as the installation and the daily use are concerned, so therefore these installations instructions are based on the different

More information

INSTALLATION IMPORTANT INSTALLER/OWNER RESPONSIBILITY TOOLS & EQUIPMENT NEEDED FOR INSTALLATION PRE-INSTALLATION PROCEDURES & JOBSITE CONDITIONS

INSTALLATION IMPORTANT INSTALLER/OWNER RESPONSIBILITY TOOLS & EQUIPMENT NEEDED FOR INSTALLATION PRE-INSTALLATION PROCEDURES & JOBSITE CONDITIONS IMPORTANT It is important that you read & understand the following information and instructions in their entirety before proceeding with installation. Please thoroughly inspect all Flooring products in

More information

HOW-TO LAY HARDBOARD OR PLYWOOD FLOOR OVERLAY

HOW-TO LAY HARDBOARD OR PLYWOOD FLOOR OVERLAY HOW-TO HOW-TO LAY HARDBOARD OR PLYWOOD FLOOR OVERLAY Most floor coverings, if laid over uneven wooden floors, will wear unevenly and look unsightly. The answer is to cover the old boards with hardboard

More information

INSTALLATION INSTRUCTIONS for PATTERNED CARPETS with ACTION BAC

INSTALLATION INSTRUCTIONS for PATTERNED CARPETS with ACTION BAC ACTION BAC, PERMIAN BAC and PERMIAN BAC MP (pages 1 9) CAMBRIAN LAMINATE BAC, ELEMENT CUSHION BAC, FIRMA CUSHION BAC, FUSION BAC, and TERRA CUSHION BAC SYSTEMS (pages 10-11) INSTALLATION INSTRUCTIONS for

More information

Installation for Wood Flooring

Installation for Wood Flooring Installation for Wood Flooring Tarkett wood flooring offers a beautiful variety of options from species and colour, to plank widths and finishes. We developed enhanced locking system, T-lock, and the best

More information

GigaCrete Specification PlasterMax

GigaCrete Specification PlasterMax GigaCrete Inc. 6775 Speedway Blvd. Suite M105 Las Vegas, NV 89115 Ph (702) 643-6363 Fax (702) 643 1453 www.gigacrete.com GigaCrete Specification PlasterMax PlasterMax : Fire Rated Plaster for Direct Application

More information

How To Level A Subfloor

How To Level A Subfloor Skill Level: INTERMEDIATE Give these projects a try if you're a confident DIYer with a good working knowledge of a variety of tools. They can take a day or more to complete. If you can build a birdhouse

More information

Read and understand all installation instructions and precautions before installing. GENERAL APPLICATION INSTRUCTIONS

Read and understand all installation instructions and precautions before installing. GENERAL APPLICATION INSTRUCTIONS AC TOPSEAL SELF-ADHERED, GRANULAR SURFACED, SINGLE PLY, LOW SLOPE ROLLED ROOFING 3 X 33.3 = 100 SQ. FT. 10 YEAR MATERIAL LIMITED WARRANTY For Use on Porches / Sheds / Utility Buildings / Accessory Buildings

More information

NEW ELECTRICAL SUBSTATION Building 300 SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK

NEW ELECTRICAL SUBSTATION Building 300 SECTION 07 53 23 ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK ETHYLENE-PROPYLENE-DIENE-MONOMER ROOFING WORK PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12

WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12 87 88 GOOD INDUSTRY PRACTICES 12 WATERPROOFING OF REINFORCED CONCRETE FLAT ROOF 12.1 BACKGROUND Most roofs in Singapore are constructed using reinforced

More information

M50 RUBBER/PLASTICS/CORK/LINO/CARPET TILING/ SHEETING

M50 RUBBER/PLASTICS/CORK/LINO/CARPET TILING/ SHEETING M50 M50 RUBBER/PLASTICS/CORK/LINO/CARPET TILING/ SHEETING To be read with Preliminaries/General conditions. TYPE(S) OF COVERING 130 CARPET: - Base: o Existing concrete base o Levelling screed o Timber

More information

Installation Instructions for staple/nail down applications

Installation Instructions for staple/nail down applications Installation Instructions for staple/nail down applications General Notes Inspect all materials carefully before installation. Warranties do not cover materials with visible defects once they are installed.

More information

SECTION 07530 SINGLE PLY MEMBRANE ROOFING. 4. Minor repair to adjacent clay tile roofing and flashings.

SECTION 07530 SINGLE PLY MEMBRANE ROOFING. 4. Minor repair to adjacent clay tile roofing and flashings. SECTION 07530 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section includes the flowing: 1. Removal of existing roofing membrane. Existing bur roof has one overlay and penetration mastic is asbestos containing.

More information

APPENDIX C MOISTURE GUIDELINES & MOISTURE TESTING

APPENDIX C MOISTURE GUIDELINES & MOISTURE TESTING APPENDIX C MOISTURE GUIDELINES & MOISTURE TESTING Appendix C Moisture Guidelines Determining moisture content is an essential part of quality control within the flooring installation process. Flooring

More information

Care and Maintenance for Wood Flooring

Care and Maintenance for Wood Flooring Care and Maintenance for Wood Flooring The finishing technology used for Tarkett wood floorings makes them the best choice for easy maintenance. To preserve all the beauty of your Tarkett wood flooring,

More information

Composite Stone Veneer

Composite Stone Veneer Composite Stone Veneer Installation Guide Ver 1 Jun 2015 www.compstone.com Composite Stone Veneer Installation Guide Contents Introduction & Overview 3 Required Tools 4 Optional Tools 4 Attachment Guidelines:

More information

Add a Splash of Imagination

Add a Splash of Imagination Add a Splash of Imagination Installation Instructions AirStep Evolution AirStep Plus AirStep Basix AirStep Advantage Installation Instructions for AIRSTEP ADVANTAGE, AIRSTEP EVOLUTION, AIRSTEP PLUS and

More information

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS AN ERGONARMOR COMPANY TECHNICAL INFORMATION SPECIFICATION FOR INSTALLATION 07/11 SUPERSEDES 04/00 PAGE 1 OF 6 CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS 1. SCOPE 1.1 This specification

More information

How To Install Hardwood Flooring

How To Install Hardwood Flooring phone: 1.855.Ludaire e-mail: info@ludaire.com Solid Flooring Installation Instructions These Instructions and Guidelines are for the typical installation of ¾ Pre-finished Solid Hardwood Flooring manufactured

More information

Hardwood Flooring. Urbania Flooring

Hardwood Flooring. Urbania Flooring Engineered Hardwood Flooring Installation Guide for Urbania Flooring BEFORE STARTING THE INSTALATION - Please take the time to read and ensure that you understand the information contained in this document.

More information

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,

More information

Window Installation Instructions

Window Installation Instructions Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for

More information

Engineered Hardwood Flooring Installation Instructions

Engineered Hardwood Flooring Installation Instructions Engineered Hardwood Flooring Installation Instructions Tip: Check for proper color selection and style prior to Installation. No claims will be accepted after installation Important Information before

More information

Grand Mesa Plus LAMINATE - WIRE BRUSHED. GAGVGM81012A Prairie. GAGVGM80012NA Colorado. GAGVGM84012A Pecan Rustic. GAGVGM85012A Saddle Walnut

Grand Mesa Plus LAMINATE - WIRE BRUSHED. GAGVGM81012A Prairie. GAGVGM80012NA Colorado. GAGVGM84012A Pecan Rustic. GAGVGM85012A Saddle Walnut MARCH 2015 Grand Mesa Plus LAMINATE - WIRE BRUSHED Specifications 12.3mm 6.5 wide x 47-13/16 long 19.42 sf/ctn 48 ctn/plt Triple Plate Embossing Wire Brushed Texture Micro-Bevel & Waxed Edges Warranty

More information

Guide Specification SECTION 09 68 16 SHEET CARPETING PART 1 - GENERAL 1.1 SUMMARY. A. This Section includes broadloom carpet. 1.

Guide Specification SECTION 09 68 16 SHEET CARPETING PART 1 - GENERAL 1.1 SUMMARY. A. This Section includes broadloom carpet. 1. SECTION 09 68 16 SHEET CARPETING PART 1 - GENERAL 1.1 SUMMARY A. This Section includes broadloom carpet. 1.2 STANDARDS A. Except as modified by governing codes and by the Contract Documents, comply with

More information

QWALL 4 ACRYLIC SHOWER WALL INSTALLATION INSTRUCTIONS

QWALL 4 ACRYLIC SHOWER WALL INSTALLATION INSTRUCTIONS QWALL 4 ACRYLIC SHOWER WALL INSTALLATION INSTRUCTIONS IMPORTANT DreamLine TM reserves the right to alter, modify or redesign products at any time without prior notice. For the latest up-to-date technical

More information

Application Instructions for Avery Dennison Films SF100-843-S LTR EZ RS, Conform Chrome

Application Instructions for Avery Dennison Films SF100-843-S LTR EZ RS, Conform Chrome Application Instructions for Avery Dennison Films SF100-843-S LTR EZ RS, Conform Chrome Instructional Bulletin #4.00.2 (Revision 0) Dated: 04/05/2012 1.0 Consult Product Data Bulletin Before starting application,

More information

INSTALLATION INSTRUCTIONS FOR RIGID VINYL WALLCOVERING

INSTALLATION INSTRUCTIONS FOR RIGID VINYL WALLCOVERING INSTALLATION INSTRUCTIONS FOR RIGID VINYL WALLCOVERING HIGH IMPACT, PROTECTIVE, STAIN-RESISTANT RIGID VINYL WALLCOVERING SHEETS FOR: HEALTHCARE/ELDERCARE FACILITIES LODGING & HOSPITALITY RETAIL ESTABLISHMENTS

More information

Knauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap

Knauf Aquapanel Interior. Tile Backing. Cement board for wet areas. Will not deteriorate in water. Easy to score and snap Tile Backing Will not deteriorate in water Easy to score and snap Resistant to mould and mildew Knauf Aquapanel Interior Cement board for wet areas Knauf Aquapanel Interior Cement Board Drywall for Wet

More information

PANELIZED HOME INSTALLATION GUIDELINE

PANELIZED HOME INSTALLATION GUIDELINE PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.

More information

installation Mannington Works. 800 241 2262 manningtoncommercial.com Mannington Commercial Luxury Vinyl Tile Installation Instructions GENERAL

installation Mannington Works. 800 241 2262 manningtoncommercial.com Mannington Commercial Luxury Vinyl Tile Installation Instructions GENERAL GENERAL These instructions cover all fully adhered s of Mannington Commercial LVT; Assurance Squared, Create, Nature s Paths, Nature s Paths Select and Walkway luxury vinyl flooring. Nature s Paths LockSolid

More information

SECTION 03 35 43 POLISHED CONCRETE FINISHING

SECTION 03 35 43 POLISHED CONCRETE FINISHING SECTION 03 35 43 POLISHED CONCRETE FINISHING PART 1 - GENERAL 1.01 SUMMARY A. Provide polished concrete finishing system where indicated on drawings, complete. This section includes the following: 1. Concrete

More information

Aspect Metal Peel & Stick Tile Installation Guide

Aspect Metal Peel & Stick Tile Installation Guide Aspect Metal Peel & Stick Tile Installation Guide Proper surface preparation is essential for a successful project Failure to follow recommended surface preparation instructions may void the warranty Read

More information

OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. GeneralShale.com

OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide. GeneralShale.com OLD BRICK ORIGINALS KILN-FIRED THIN BRICK VENEER Installation Guide GeneralShale.com OLD BRICK ORIGINALS THIN BRICK VENEER Page 2 INTRODUCTION Check local building codes for proper installation guidelines

More information

Engineered Installation Instructions

Engineered Installation Instructions Engineered Installation Instructions Please read all instructions carefully before attempting installation. Improper installation may void the warranty. PRODUCT USE DIVINE Flooring Engineered products

More information

Eucaboard / Eucaplac/ Eucatile paneling is intended for dry interior use only and requires care in handling.

Eucaboard / Eucaplac/ Eucatile paneling is intended for dry interior use only and requires care in handling. i This instruction sheet describes the proper methods for installing Eucatex decorative wall paneling. Eucaboard / Eucaplac/ Eucatile paneling is intended for dry interior use only and requires care in

More information

Solvent Cementing Instructions For Plastic Pipe & Fittings

Solvent Cementing Instructions For Plastic Pipe & Fittings Solvent Cementing Instructions For Plastic Pipe & Fittings Description Solvent cementing is the process of fusing plastic pipe and fittings by the use of an adhesive containing a suitable active solvent

More information

SECTION 03 54 00 RESURFACING CAST IN PLACE CONCRETE

SECTION 03 54 00 RESURFACING CAST IN PLACE CONCRETE Page 1 SECTION 03 54 00 RESURFACING CAST IN PLACE CONCRETE Specifier Notes: This guide specification is written according to the Construction Specifications Institute (CSI) format. The section must be

More information

DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H

DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H Soil Drainage Mat with Built-In Protection Layer POLYGUARD DRAINAGE MATS are three-part prefabricated geocomposite drain consisting of a

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS INSTALLER/OWNER RESPONSIBILITIES Hardwood flooring is a product of nature and its inherent beauty stems from the fact that each piece is unique with no two pieces the same. Due to the fact that this flooring

More information

Pipe and Equipment Insulations. Zeston. PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems

Pipe and Equipment Insulations. Zeston. PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems Pipe and Equipment Insulations Zeston PVC Insulated Fitting Covers Installation Instructions for Hot, Cold and USDA Piping Systems Zeston PVC Insulated Fitting Covers Installation Instructions for Hot,

More information

LAYING BLOCK AND BRICK

LAYING BLOCK AND BRICK LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct

More information

Sikaflex Sealant Installation. Sika Corporation

Sikaflex Sealant Installation. Sika Corporation Sikaflex Sealant Installation 1 Critical Success Factors Substrate preparation If done properly would probably eliminate 95% of all call backs Most common mode of sealant failure Must remove all weak material

More information

GUIDE SPECIFICATION COMBINATION SURFACE SYSTEM FOR NEW HOT MIX ASPHALT TENNIS COURTS I. PART 1 - GENERAL

GUIDE SPECIFICATION COMBINATION SURFACE SYSTEM FOR NEW HOT MIX ASPHALT TENNIS COURTS I. PART 1 - GENERAL COMBINATION SURFACE SYSTEM FOR NEW HOT MIX ASPHALT TENNIS COURTS I. PART 1 - GENERAL 1.1 SUMMARY A. This section is a part of the entire set of Contract Documents and shall be coordinated with the applicable

More information

FRAMED & MOUNTED TILE MURAL

FRAMED & MOUNTED TILE MURAL Page 1 of 5 There is no denying that tile murals have taken the sublimation industry by storm. The unique ability to take a customer s artwork or high resolution photograph, tile it using your software

More information

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side

More information

WESTERN COOL ROOF SYSTEMS Sustainable - Energy Efficient FLUID APPLIED REINFORCED ROOF SYSTEM

WESTERN COOL ROOF SYSTEMS Sustainable - Energy Efficient FLUID APPLIED REINFORCED ROOF SYSTEM WESTERN COOL ROOF SYSTEMS Sustainable - Energy Efficient FLUID APPLIED REINFORCED ROOF SYSTEM SPECIFICATION NO. SMAA-2P-8xE UPGRADE SMOOTH SURFACE / CAP SHEET / SINGLE PLY 2 PLY POLYESTER REINFORCED ACRYLIC

More information

INSTALLATION INSTRUCTIONS for Bifold Doors (JII103)

INSTALLATION INSTRUCTIONS for Bifold Doors (JII103) Thank you for selecting JELD-WEN products. Attached are JELD-WEN s recommended installation instructions for premium composite, hollow and solid core molded Bifold Doors. Bifolds are designed for fast

More information

Technical Data wedi Subliner Dry Waterproofing Shower and Wet Area System

Technical Data wedi Subliner Dry Waterproofing Shower and Wet Area System Technical Data wedi Subliner Dry Waterproofing Shower and Wet Area System Technical Data wedi Subliner Dry Waterproofing Shower and Wet Area System General Product Description Waterproof, thin-layer, crack

More information

How to Build a Poker Table

How to Build a Poker Table How to Build a Poker Table www.pokertablematerials.com 10-Person Poker Table- 96 x 48 These are step by step instructions for building a poker table. The table will measure 48" x 96" and have a 4" wide

More information

DASH KIT INSTALLATION

DASH KIT INSTALLATION ÿÿÿÿÿ ÿÿÿÿÿÿÿÿÿÿÿÿ ÿÿÿ ÿÿÿÿÿ ÿÿ ÿÿÿ ÿÿÿÿÿÿÿÿÿÿÿÿÿÿ ÿÿÿÿÿÿÿÿÿÿ ÿÿÿÿ ÿÿÿÿ ÿÿ ÿÿÿÿÿ ÿÿÿÿÿÿÿÿ PROUDLY MADE IN THE USA DASH KIT INSTALLATION These instructions are aimed at the do-it-yourself installer. Read

More information

FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS

FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS No. 8 Brands Hatch Close Kyalami Business Park Kyalami Tel: 011 466 0701 Fax: 011 466 2919 Email: nici@forestflooring.co.za FLOOR MAINTENANCE GUIDE EXPECTATIONS AVOIDING PROBLEMS Please keep this folder

More information

Euro Oak Installation

Euro Oak Installation STYLE TIMBER FLOOR Bring your life in style Euro Oak Installation Before Starting Installation Your floor has been manufactured with the best possible care. However we would still advise you to check the

More information

Construction. Sikadur-Combiflex. Sealing system for cracks and problem joints with large movements DESCRIPTION

Construction. Sikadur-Combiflex. Sealing system for cracks and problem joints with large movements DESCRIPTION Sikadur-Combiflex REVISED JULY 2002 Sealing system for cracks and problem joints with large movements Construction DESCRIPTION USES ADVANTAGES The Sikadur-Combiflex joint sealing system consists of two

More information

INSTALLING LINOLEUM FLOORING

INSTALLING LINOLEUM FLOORING INSTALLING LINOLEUM FLOORING Congratulations on choosing to install linoleum flooring in your home or office. When it comes to installing linoleum, you have a variety of options. This guide is designed

More information

Foundation. Foundation

Foundation. Foundation Moisture Aside from structural concerns, the most important consideration for foundation design is moisture. No client wants a wet basement. No client wants a damp basement. No client wants mold in their

More information

Basic Spring Motor Roller Shades

Basic Spring Motor Roller Shades Comprehensive Roller Shade Installation Guide Basic Spring Motor Roller Shades ATTENTION!!! READ CAREFULLY! This shade has a reliable long-lasting Spring Motor. The Spring Motor must have proper tension

More information

STAIR TREAD & RISER INSTALLATION GUIDELINES

STAIR TREAD & RISER INSTALLATION GUIDELINES STAIR TREAD & RISER INSTALLATION GUIDELINES ARTISTIC FINISHES DOES NOT WARRANTY THE COMPLETENESS OR ACCURACY OF ANY INSTALLATION. THE INSTALLATION CONTRACTER MUST HAVE THE EXPERIENCE AND KNOWLEDGE TO COMPLETE

More information

DELTA Premium Moisture Management Systems for Foundations.

DELTA Premium Moisture Management Systems for Foundations. DELTA protects property. Saves energy. Creates comfort. DELTA Premium Moisture Management Systems for Foundations. DELTA Premium Moisture Management Systems provide the best protection for foundations.

More information

Acrylic Walls Installation Instructions

Acrylic Walls Installation Instructions Acrylic Walls Installation Instructions IMPORTANT Please read carefully the following instructions before installing your shower acrylic walls. If you have any questions on this shower acrylic walls installation

More information

G VYCOR DECK PROTECTOR

G VYCOR DECK PROTECTOR G VYCOR DECK PROTECTOR Self-Adhered Flashing Contractor s Guide DECKS AND DETAIL AREAS For longer lasting decks, install Grace Vycor Deck Protector. FROM THE MAKERS OF G Ice & Water Shield What Self-Adhered

More information