Design Product Evaluation Criteria Handbook

Size: px
Start display at page:

Download "Design Product Evaluation Criteria Handbook"

Transcription

1 CALIFORNIA DEPARTMENT OF TRANSPORTATION Design Product Evaluation Criteria Handbook Evaluation Criteria for Design products Office of Project Development Procedures 3/15/2013 This handbook is for use in evaluating highway design products during the initiation, preliminary design, and final design phases of a project. This is to be used by core PDT members in identifying and prioritizing issues prior to these becoming problems or risks.

2 Table of Contents Contents Introduction/Background... 4 Applicability... 5 Project Development Team Members... 5 Product Evaluation... 6 Project Development Team Meeting... 8 Risk Management prior to Ready to List Milestone... 9 Applicability during Project Reviews... 9 Evaluations Guidance Design Product Evaluation Template Evaluation Criteria Overall Criteria Design Purpose and Need Design Designs Standards Compliance Design Optimization Project Management Cost Management (Page 1 of 4) Project Management Schedule Management Project Management Optimization Structure Design Design Standards Compliance (1 of 2) Structure Design Optimization Right of Way Right of Way Minimization & Compliance Environmental Purpose and Need Environmental Environmental Commitments, Minimization, & Compliance Page 2

3 Office Engineer Construction Contract Standards Compliance (Page 1 of 3) Construction Protective Features (Page 1 of 2) Construction Construction Contract Standard Compliance (Page 1 of 2) Construction Constructible Structure Construction Constructible (1 of 3) Traffic Operations Protective Features Traffic Operations Design Standard Compliance Traffic Operations Designed to Operate as Planned Maintenance Protective Features (Page 1 of 2) Maintenance Maintainable Planning Purpose and Need (Page 1 of 3) Planning Designed to Operate as Planned (Page 1 of 4) Evaluation Criteria Index Design Project Management Structure Design Right of Way Environmental Office Engineer Construction Structure Construction Traffic Operations Maintenance Planning Page 3

4 Introduction/Background This handbook establishes a framework for implementation of evaluation criteria to improve the quality of design products developed during the project delivery process. Caltrans has historically relied on conformance to standards and practices, and often individual preferences, to define a project s quality. Consistent application of these standards and practices can be problematic given the various expertise and opinions of the product evaluator. By establishing these evaluation criteria, which are based on product outcomes, and referencing these criteria to the actual standards and practices, it is anticipated that a more consistent application of quality evaluation will be achieved. These evaluation criteria were developed by experts within the key functional units who own and must manage the outcomes of design products, essentially Design s partners and customers. It is critical that these partners and key customers form the core of the Project Development Team (PDT) which will guide the project through the delivery process. These PDT members also own the evaluation of those design characteristics which were developed by their respective functional experts. By continuously evaluating the design product utilizing the identified characteristics, risks to project quality will be identified and can be prioritized and resolved in an efficient manner. Page 4

5 Applicability The project development team (PDT) is encouraged to apply the design product characteristics to all projects on or proposed to be on the SHS regardless of implementing agency, sponsor or funding source. Project Development Team Members During the project initiation and project approval phases, PDT members consist of nine core functional areas representatives from project management, design, structure design, environmental, right of way, traffic operations, transportation planning, construction, and maintenance. Furthermore, during the final design phase the PDT increases by two core functional areas to include representatives from office engineer and structure construction. Each of these functions owns one to three performance characteristics to evaluate, based on the interests, expertise and accountability of the functional area. The performance characteristics and responsible functional areas are listed in the figure below. Performance Characteristic Protective Features x x x Purpose & Need x x x Cost Management x Schedule Management x Design Standards Compliance x x x Environmental Commitments, Minimization & Compliance x R/W Minimization & Compliance x Construction Contract Standards Compliance x x Constructible x x Designed to Operate as Planned x x Maintainable x Optimization x x x Project Management Design Structure Design Environmental Right of Way Office Engineer Construction Structure Construction Traffic Operations Transportation Planning Maintenance Page 5

6 Although there may be additional PDT members, this handbook was based on the core functional areas described above. The functional area manager should select the most appropriate representative to participate on PDT teams. This representative should be knowledgeable of the project development process, and have technical expertise in the function s manuals, policies, standards, laws, and regulations. Acknowledging that some representatives have limited technical knowledge of some aspects within their functional areas, these representatives should consult technical advisors within their functional areas when needed. Product Evaluation The PDT members should assess the emerging design product using their function s evaluation criteria. One or more functional areas are accountable for each performance characteristic. Each of the eleven functional areas has interests, expertise, and accountability regarding different performance characteristics. When a functional area representative applies an evaluation to a performance characteristic, it becomes a project performance measure. When a project s performance measures are displayed all at once, the display is called a project dashboard. The figure below shows an example project dashboard with 23 performance measures. This type of dashboard should be quickly created and displayed during each PDT meeting. In this example, the team should use the dashboard to prioritize issues, beginning with red (1), which indicates needs significant attention. In the example below, the PDT should develop a plan to involve the necessary PDT members and technical advisors to address Constructible-Construction and Protective Features- Maintenance before the next PDT meeting. Page 6

7 Project Dashboard (with sample evaluations) Functional Area Performance Characteristic Evaluation Design Purpose & Need 4 Design Standards Compliance 2 Optimization 3 Project Cost Management 4 Management Schedule Management 3 Optimization 3 Structure Design Standards Compliance 2 Design 1 Optimization 3 Right of Way R/W Minimization & Compliance 3 Environmental Purpose & Need 4 Environmental Commitments, Minimization & Compliance 3 Office Construction Contract Standards Compliance 2 Engineer 2 Construction Protective Features 3 Constructible 1 Structure Construction 1,2 Construction Contract Standards Compliance 2 3 Constructible 2 Traffic Protective Features 3 Operations Design Standards Compliance 3 Designed to Operate as Planned 3 Maintenance Protective Features 1 Maintainable 5 Planning Purpose & Need 3 Designed to Operate as Planned 3 NOTE: 1 Recommended for projects with structure(s) 2 Recommended during the final design phase (a.k.a. PS&E phase). Page 7

8 Project Development Team Meeting Project Managers are to facilitate the PDT issue prioritization as follows: 1. Project Status Page 8 The project engineer, or a representative from the design unit, will provide an overview of the project status and issues in order for the PDT to have sufficient information to provide assessments consistent with the evaluation criteria. Below are possible ways to provide this information: a. A design product, Gantt chart, aerial photo etc. b. The last approved document and intermediate outline or draft document c. Recent project review comments (see below) d. The resolution or status of prior PDT meeting issues 2. Evaluation Each functional area representative individually evaluates the project relative to his or her performance characteristic(s) utilizing the evaluation criteria to assess information and/or products provided. (Refer to the respective evaluation criteria in this handbook.). 3. Display Evaluations (see example above) The PM obtains the evaluation number/color from each functional area representative and displays the resulting project dashboard to the team. 4. Discuss high risk performance measures Performance measures that received an evaluation of Needs Significant or Needs are sources of risk for a project. Beginning with the Needs significant attention measures, the Project Manager facilitates a discussion with the representative who provided the risk assessment(s). As time permits, this step is repeated until all the high risk performance measures have been discussed with the PDT. 5. Prioritize The PDT determines priorities and selects the most significant issues that will require an action plan prior to the next PDT meeting, if any. 6. Next Steps The PDT decides next steps and which technical advisors are necessary to solve each prioritized issue. 7. Risk Registry

9 The PDT determines which unresolved issues should be incorporated into the risk register in accordance to the Project Risk Management Handbook. 8. Record The PM records the responses of steps 2 thru 7 in the meeting notes. Risk Management at Project PS&E, (Milestone 380) Prior to Milestone 380, Project PS&E, any measures listed as needs significant attention must have completed a thorough collaboration with the appropriate HQ functional unit and then be added to the Risk Register per PD-09, Project Risk Management. If any of the following performance measures are listed as needs significant attention the Legal Division should be consulted in order to develop a risk strategy for the project records. The conversation with the Legal Division is protected by attorney/client privileges and the resulting strategy will assure that risks are fully addressed. Need and Purpose - Design Protective Features - Traffic Operations Protective Features - Maintenance Protective Features - Construction Design Standards Compliance - Traffic Operations Design Standards Compliance - Design Design Standards Compliance - Structure Design Construction Contract Standards Compliance - Construction Designed to Operate as Planned- Traffic Operations Maintainability - Maintenance Optimization - Design Optimization - Structure Design Applicability during Project Reviews The results of district circulation, safety reviews, constructability reviews, and any other technical reviews need to be studied and understood by the appropriate PDT members prior to the PDT meeting, so that these findings can be incorporated into the comprehensive project performance assessment by the PDT. For example, once a safety review has been performed, the project engineer should distribute the results to the PDT members who evaluate Protective Features - the PDT members representing Construction, Page 9

10 Traffic Operations, and Maintenance. At the next PDT meeting, the safety review results should be considered when determining the evaluations for Protective Features. Similarly, once a constructability review has been performed, the project engineer should distribute these results to Construction, Structures Construction, and Office Engineer PDT members for their consideration when evaluating Constructible and Construction Contract Standards Compliance. Evaluations Guidance Each performance measure is made up of several aspects. Note that there are evaluation criteria for each aspect. Each PDT member should use his/her professional judgment to decide which aspect(s) should be the basis of the evaluation. This assessment should take into consideration the project s schedule, cost, project phase, or other factors. Coming up with a numerical evaluation for a performance characteristic involves: 1. Familiarizing himself/herself with each of the respective functional area s performance characteristics, aspects, and criteria, 2. Reviewing the current status of the project, or, if available, the draft design product, 3. Contrasting the proposed design solutions with applicable standards, policies and practices, 4. Determining the impact of the issues on the performance characteristic (outcome), and 5. Assigning a numerical evaluation consistent with the evaluation criteria The numerical evaluation is dependent on the PDT member professional judgment. For example, suppose the standard calls for a 10-foot shoulder, but the plan proposes a 9-foot shoulder. Professional judgment is needed to determine if the Design Standards Compliance measure is deemed needs attention" or "needs significant attention. If the design product is a 30% PS&E, this issue might need attention, but at 95% the issue might need significant attention. Another example: if the 9-foot shoulder is on an off ramp, it may need attention, but if it is on a freeway mainline it may need significant attention. Remember, the purpose of the evaluation criteria is to help the PDT prioritize issues, and to create a greater degree of consistency statewide. In order to assist in keeping the evaluation criteria as objective as possible, the Design Product Evaluation Criteria Handbook has indexed the evaluation criteria to policies, manuals, regulations, or practices. The more the evaluations are based on Department policies, standards and practices, the more useful and credible this prioritization process will be. Page 10

11 Design Product Evaluation Template Project No: PDT Meeting Date: Functional Area Performance Characteristic Evaluation Design Project Management Structure Design Purpose & Need Design Standards Compliance Optimization Cost Management Schedule Management Optimization Design Standards Compliance Optimization Right of Way R/W Minimization & Compliance Environmental Purpose & Need Environmental Commitments, Minimization & Compliance Office Construction Contract Standards Compliance Engineer Construction Protective Features Structure Construction Traffic Operations Constructible Construction Contract Standards Compliance Constructible Protective Features Design Standards Compliance Designed to Operate as Planned Maintenance Protective Features Planning Maintainable Purpose & Need Designed to Operate as Planned Page 11

12 Evaluation Criteria Overall Criteria 5 State of the Art 4 Good 3 Acceptable 2 Needs 1 Needs Significant Complete No changes are necessary Project consistent with master plan and meets future needs Stakeholder expectations exceeded, without controversy Work plan is excellent in all aspects Outstanding clarity of communication Complete, but not outstanding Standards, policies and practices are reasonably well met Presentation and communication clear Comprehensive risk response plan Complete, but minor changes may be called for No mandatory changes required Stakeholder needs are met Compliance with minimum standards Enough information to justify the project moving forward Risk response plan is included Not complete, but should not stop the project Needs justifiable reason to move forward Does not meet minimum requirements or standards, and documentation has not been provided Incomplete risk response plan Not complete, contains major omissions Does not meet the transportation need Fatally flawed in terms of funding, resources, scope, or schedule Does not meet mandatory requirements or standards (all areas) and contains no associated exceptions Totally missing customers expectations Ignores the needs of stakeholder(s) or key functional area(s) No risk response plan Page 12

13 Design Purpose and Need State of the Art Good Acceptable Needs Needs Significant Need (symptoms) and deficiency (what is broken) clearly and succinctly defined. Clearly and succinctly demonstrates a transportation need and deficiency. Clearly stated deficiency is the cause of the transportation problem. Demonstrates a need and related deficiencies - minor changes/clarification can be made. Demonstrates need and deficiencies stated should address problem, maybe some ambiguity or missing minor information. Not well demonstrated, some ambiguous, vague, or incomplete. Need not demonstrated or incomplete. Proposed stated deficiency does not address the need, or existing deficiency not stated. Purpose statement identifies deficiency and defines intended outcome the project will address. A clearly defined transportation deficiency the project intends to address and discusses those that will not be addressed Defines intended outcome, promotes a suitable range of alternatives, and relates to need statement. Discusses transportation deficiencies the project intends to address, but need minor clarification. May not address all deficiencies not to be addressed. Intended outcome is not as specific or comprehensive as it could be, minor clarification or detail may be needed. Defines transportation deficiencies the project intends to address, but need some minor clarification. May not discuss deficiencies not to be addressed. Intended outcome needs some clarification, a little vague or limiting. Purpose does not adequately address transportation deficiencies and is too vague and limiting. Purpose not stated nor has no relation to need statement. Have no idea neither what deficiency the project intends to fix, nor what the intended outcome is--too vague allows too broad of a range of alternatives, or so narrow that it precludes study of reasonable alternatives. Purpose statement states the proposed alternative. Alternatives or proposed design meet the expectations stated in the Need and Purpose? Expectation exceeded, scope exactly met, and limits of work met, no scope creep. Good variety of alternatives - including minimum standard. Expectation met, scope met with very little scope creep. A variety of alternatives - including minimum standard. Expectation, scope, and limits of work met or very close, may have some scope creep. Several alternatives, adequate variety, but no obvious alternative missing- including minimum standard. Expectations not completely met, scope and limits of work missing elements of purpose statement, or exceeded limits, too much creep, original scope lost. Little variety of alternatives, obvious alternatives missing, or is missing minimum standard. Expectations not met, scope and limits of work does not conform to need, too much creep from original scope lost or too much missing. No variety of alternatives, single alternative with other obvious missing - missing minimum standard. Supporting Evidence Evidence clearly demonstrates and identifies transportation deficiency. Demonstrates transportation deficiency - minor changes/clarification are needed, may need more information but no additional studies needed. Demonstrates transportation deficiency - minor changes/clarification can be made, may need more information but no additional studies needed Does not have strong support for need or studies are out of date or incomplete. Does not support need, inadequate support, or evidence not provided/ incomplete. Page 13

14 Design Designs Standards Compliance Highway Design Manual (HDM) & Design Informational Bulletin (DIB) - PR & 95% Highway Design Manual (HDM) & DIB - PID, DPR, 30%, 60% State of the Art Good Acceptable Needs Needs Significant Most minimum standards exceeded and few design exceptions (not because of constraints but to improve the design). Most minimum standards exceeded and few design exceptions (not because of constraints but to improve the design). Some minimum standards exceeded or met, and approved design exceptions. Some minimum standards exceeded or met, and approved design exceptions. DIB-82 Most minimum standards exceeded All minimum standards met or exceeded. AASHTO/Local Standard - Local facilities All local roads exceeded CT or AASHTO standards. All design guidance and standards met and some exceeded. All design standards minimums met or design exceptions approved. All design standards minimums met or design exceptions approved. All minimum standards met or approved design exception. Most design guidance and standards met or exceeded, and documented concurrence for variations. Non-standard features no approved design exceptions Non-standard features no approved design exceptions. May require minor re-design to get design exception approved. Non-standard features no approved design exceptions. Requires minor re-design to get design exception approved. Design guidance and standards not fully met no documented concurrence for variations. Non-standard features no approved exception, Issues with approval. Requires re-design to get design exception approved. Non-standard features no approved exception; No conversations with Design Coordinator or Reviewer; Critical issues with approval; Requires major re-design to get design exception approved. Non-standard features no approved exception. Requires major re-design to get design exception approved. Non-standard features no documented concurrence for variations, Issues with approval. Project Development Procedures Manual (PDPM) - PID/PR/PSE Meets all PDPM requirements with all issues clearly defined and fully discussed, and all alternatives sufficiently explored Meets all PDPM requirements with all issues defined and discussed, and variety of alternatives explored. Meets PDPM requirements with issues defined and may not be fully discussed, and few alternatives explored. Does not meet PDPM requirements with issues not clearly defined or discussed, and only single alternatives explored, no other mentioned. Does not meet PDPM requirements with issues not defined or discussed, and only single alternatives explored no other mentioned. PDPM - New/Modified Public Road Connection. Existing interchanges and/or local roads to be improved along with new connection to satisfactorily accommodate traffic demand. New public road connections and work on existing local roads will have positive effects on facility operation. Demonstrated that the existing interchanges and/or local roads cannot be improved to satisfactorily accommodate traffic demand. New public road connections will have no detrimental effects that would diminish facility operation. Demonstrated that the existing interchanges and/or local roads cannot be improved to satisfactorily accommodate traffic demand. New public road connections will affect but have no detrimental effects that would diminish facility operation. Incomplete analysis or questionable that the existing interchanges and/or local roads cannot be improved to accommodate traffic demand New public road connections will have detrimental effects that would diminish facility operation or incomplete analysis. No demonstration that the existing interchanges and/or local roads cannot be improved to accommodate traffic demand New public road connections will have detrimental effects that would diminish facility operation or no analysis. Page 14

15 Design Optimization HDM 81Design Philosophy State of the Art Good Acceptable Needs Needs Significant Project provides the greatest public good over the long term for the total cost. Excellent cost/results Good cost/benefit Project provides public good over the Design Life for the Total cost. Acceptable cost/benefit Marginal cost/benefit The project chose the lowest cost alternative for a very narrowly focused purpose or short term benefits, leaving a system that down the road may be a costly to maintenance and operations with little or no long term benefit. Poor cost/benefit Reasonably accommodates all users All uses have clearly been taken care of and may even have separate facilities (Pedestrian Over Crossing or truck bypass), including during construction All users should be able to safely navigate through project limits, including during construction. Adequate accommodations for all uses all have short comings to accommodate other users. Reasonable safety for all, including during construction Access cutoff/blocked for one or more users, as designed and/or during construction One or more users clearly excluded by design, including during construction. Accommodate future of facility (beyond design life) Project facilitates future expansion to ultimate facility configuration and area build out. (Beyond design year) All new large capital outlay structures will work with future expansion Minor element will need to be rebuilt with future expansion. Although does not preserver ultimate foot print, does not encourage growth that would prohibit ultimate expansion. To accommodate future/ultimate expansion will require complete or major reconstruction. Project prohibits future growth, by putting in very expensive structures that will have to be completely rebuilt, or will encourage local growth which would prohibit future expansion. Compatibility/ Consistency with adjacent facility Compatible with or facilitates adjacent existing features, or is part of evolution of a facility for one type to another (conventional to freeway/expressway) Project is compatible with adjacent project/existing features, yet accommodates future needs. Project works with adjacent project/existing features Issues/conflicts with adjacent project/ existing features No compatibility with adjacent project/ existing features Driver Expectation/ standard practice No Driver confusion, Intuitive to travel Meets driver expectation Meets driver expectation, some signing may be needed to clarify. Driver indecision signing may not be enough to clarify. Driver confusion route/ alignment too complicated signing may not help. Page 15

16 Project Management Cost Management (Page 1 of 4) State of the Art Good Acceptable Needs Needs Significant Support Cost Estimate Support Cost Estimate from completed and approved Workplan -- Resourced Loaded Schedule -- using WBS Level 5 (or lower Level 6, Level 7, etc.) Activities and Milestones with Logic. Support Cost Estimate used for planning, programming, or budgeting support and is consistent with District Director Approved Project Study Report (PSR), Project Report (PR), Supplemental Project Report (PR) and/or Cooperative Agreement (Co-op). Support Cost Estimate partially complete or not up to date, i.e. missing activities, milestones, resources, etc. May require updated workplan, PSR, PSSR, PR, supplemental PR, and/or Cooperative Agreement. Support Cost Estimate not available. May require workplan, PSR, PR, supplemental PR, and/or Cooperative Agreement. Support Cost Component Estimate Project Support Cost Estimate summarized into the four support components -- SB-45 Components -- PA&ED, PS&E, R/W Support, and Construction Support -- according to the approved Workplan (Resourced Loaded Schedule). Support Estimate includes escalation rate according to the year the work is estimated. Support estimate includes the appropriate ICRP (Indirect Cost Rate %) for Caltrans Support versus Reimbursed Work. Project Support Cost Component used to identify support budget in PSR, PR, Supplemental PR, and/or Cooperative Agreement. Support Cost Estimate summarized by components partially complete, i.e. updated schedule, additional resources, escalation factor, correct ICRP, etc or not included in PSR, PR, supplemental PR, and/or Cooperative Agreement. May require updated workplan, escalation calculation, support component calculation, PSR, PR, or Supplemental PR. Support Cost Estimate summarized by components not available. May require workplan, PSR, PR, or Supplemental PR. IQA Support Cost Estimate (For Projects performed by Local Agency -- Not Applicable if work is performed by Caltrans) IQA Support Estimate from Completed Workplan -- Resource Loaded Schedule -- using WBS Level 6 Activities, Milestones with logic, and consistent with District Director Approved PSR, PR, Supplemental PR, Environmental Document, and/or Cooperative Agreement. IQA Support Estimate partially complete. May require updated workplan, PSR, PR, Supplemental PR, and/or Cooperative Agreement. IQA support estimate and/or Cooperative Agreement not available. May require IQA workplan, PSR, PR, Supplemental PR, and/or Cooperative Agreement. Page 16

17 Project Management Cost Management (Page 2 of 4) Programmed Support Cost (Or Approved Support Budget if project is not programmed in STIP or SHOPP, i.e. Reimbursed Work) Forecast Support Cost Estimate at Completion Support Cost Performance Index (CPI) -- Earned Value (If available) State of the Art Good Acceptable Needs Needs Significant Forecast Support Cost Component Estimate at Completion within 90% to 110 % of the approved Programmed Amount. Forecast Support Cost Component Estimate at Completion within 85% to 115 % of the approved Programmed Amount. Support Estimate Components used to program PA&ED, PS&E, R/W Support, and/or Construction Support in approved Program Document or other Financial Planning Document (RTP, FTIP, etc.). Include appropriate escalation rate and ICRP rate. Includes any approved Cooperative Agreement with local agencies for other funding. Forecast Support Cost Component Estimate at Completion within 80% to 120 % of the approved Programmed Amount (i.e. PA&ED, PS&E, R/W Support, and Construction Support). May require updated workplan, PSR, PR, Supplemental PR, Cooperative Agreement, and/or program cost change. Support Cost Estimate Components not consistent with Program Document or other financial planning document. May require updated workplan, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program cost change. Forecast Support Cost Component Estimate at Completion within 70% to 130% of the Programmed Amount (i.e. PA&ED, PS&E, R/W Support, and Construction Support). May require updated workplan, PSR, PR, Supplemental PR, Cooperative Agreement, and/or program cost change < CPI < 1.25 CPI < 0.75 or CPI > 1.25 May need to adjust project budget and/or program budget change. Support Estimate Components not available to validate support budget in program document. May require workplan, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program change. Forecast Support Cost Component Estimate less than 70% or greater than 130% of the Programmed Amount. (i.e. PA&ED, PS&E, R/W Support, and Construction Support). May require updated workplan, PSR, PR, Supplemental PR, Cooperative Agreement, and/or program cost change. Construction Capital Cost Estimate Construction Capital Cost Estimate prepared according to the approved Department's cost estimating methodology, i.e. 6 page estimate, etc., and is consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, Permit/Mitigation Requirement(s), and/or Cooperative Agreement. Construction Capital Cost Estimate needs to be updated according to the approved Department's cost estimating methodology, i.e. 6 page estimate, etc., and/or is not consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, and/or Permit/Mitigation Requirement(s). May require an updated Construction Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Construction Capital Cost Estimate not available or not based upon District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, and/or Permit/Mitigation requirements, and/or not based upon approved Department cost estimating methodology -- i.e. 6 page estimate, etc. May require a Construction Capital Estimate, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program change. Page 17

18 Project Management Cost Management (Page 3 of 4) State of the Art Good Acceptable Needs Needs Significant Right of Way Capital Estimate Right of Way Capital Cost Estimate prepared according to the approved Department's cost estimating methodology, i.e. R/W Data Sheet, Environmental Mitigation, Utility Relocation, Railroad, etc., and is consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, Permit/Mitigation Requirement(s), and/or Cooperative Agreement. Right of Way Capital Cost Estimate needs to be updated according to the approved Department's cost estimating methodology, i.e. R/W Data Sheet, Environmental Mitigation, Utility Relocation, Railroad, etc., and/or is not consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, and/or Permit/Mitigation Requirement(s). May require an updated Right of Way Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Right of Way Capital Cost Estimate not based upon District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, and/or Cooperative Agreement, and/or not based upon the approved Department cost estimating methodology -- i.e. R/W Data Sheet, etc. May require R/W Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program change. Environmental Capital Estimate Environmental Mitigation Capital Cost Estimate prepared according to the approved Department's cost estimating methodology, i.e. PEAR, MCCE, etc., and is consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, Permit/Mitigation Requirement(s), and/or Cooperative Agreement.. Environmental Mitigation Capital Cost Estimate needs to be updated according to the approved Department's cost estimating methodology, i.e. PEAR, MCCE, etc., and/or is not consistent with the District Director Approved PSR, PSSR, PR, Supplemental PR, Environmental Document, and/or Permit/Mitigation Requirement(s). May require an updated Environmental Mitigation Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Environmental Mitigation Capital Cost Estimate not based upon District Director Approved PSR, PSSR, PR, Supplemental PR, and/or Environmental Document using the approved Department cost estimating methodology -- PEAR, MCCE, etc. May require a PEAR/MCCE Capital Estimate, Supplemental PR, Cooperative Agreement, and/or program change. Programmed Construction Capital Construction Capital Cost Estimate from approved PSR, PSSR, PR, or Supplemental PR used to program Construction Capital in approved Program Document or other Financial Planning Document. Construction Capital Cost Estimate not consistent with Approved Program Document. May require an updated Capital Construction Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program change. Construction Capital Cost Estimate not available to verify Approved Program Document or other Financial Planning Document. May require a Construction Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Cooperative Agreement, and/or program change. Page 18

19 Project Management Cost Management Page 4 of 4) Programmed Right of Way Capital State of the Art Good Acceptable Needs Needs Significant Right of Way Capital Cost Estimate from approved PSR/PSSR/PR used to program Construction Capital in approved Program Document or other Financial Planning Document. Right of Way Capital Cost Estimate not consistent with Approved Program Document. May require an updated Right of Way Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Co-op, and/or program change. Right of Way Capital Cost Estimate not available to verify Approved Program Document or other Financial Planning Document. May require a Right of Way Capital Estimate, PSR, PSSR, PR, Supplemental PR, Co-op, and/or program change. Construction Capital Forecast Cost Estimate at Completion Forecast Construction Capital Cost Estimate at Completion within 90% to 110 % of the approved Programmed Amount. Forecast Construction Capital Cost Estimate at Completion within 85% to 115 % of the approved Programmed Amount. Forecast Construction Capital Cost Estimate at Completion within 80% to 120 % of the approved Programmed Amount. Forecast Construction Capital Cost Estimate at Completion within 70% to 130% of the Programmed Amount. May require an updated Construction Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Forecast Construction Capital Cost Estimate less than 70% or greater than 130% of the Programmed Amount. May require an updated Construction Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Right of Way Capital Forecast Cost Estimate at Completion Forecast Right of Way Capital Cost Estimate at Completion within 90% to 110 % of the approved Programmed Amount. Forecast Right of Way Capital Cost Estimate at Completion within 85% to 115 % of the approved Programmed Amount. Forecast Right of Way Capital Cost Estimate at Completion within 80% to 120 % of the approved Programmed Amount. Forecast Right of Way Capital Cost Estimate at Completion within 70% to 130% of the Programmed Amount. May require an updated Right of Way Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Forecast Right of Way Capital Cost Estimate less than 70% or greater than 130% of the Programmed Amount. May require an updated Right of Way Capital Cost Estimate, PSR, PSSR, PR, Supplemental PR, Permit/Mitigation Requirement(s), Cooperative Agreement, and/or program change. Page 19

20 Project Management Schedule Management Workplan Development (Planning) State of the Art Good Acceptable Needs Needs Significant All WBS Level 5 (or lower Level 6, Level 7, etc.) Activities and Milestones with logic identified in workplan schedule and consistent with District Director Approved PSR and/or Project Report. Workplan schedule not consistent in Approved PSR/PR/Environmental Document and may require the schedule to be updated. No Workplan schedule developed or included in Approved PSR/PR. Programmed Schedule Workplan delivery schedule for PA&ED, PS&E, Right of Way, and Construction used to identify delivery schedule and consistent with approved programming document. Forecast Schedule at Completion and Progress Forecast Schedule at Completion for WBS Activities and Milestone progress on schedule according to the approved program document schedule. Schedule activities, milestones, and progress (percent complete) up to date (no past due dates or missing progress). Delivery Milestones and updated progress up to date in Delivery Plan and Contract for Delivery. Schedule consistent with District Director Approved PSR/PSSR/Project Report/Environmental Document, or Supplemental Project Report and Revalidated Environmental Document. Workplan delivery schedule for PA&ED, PS&E, Right of Way, and Construction not consistent with program delivery schedule in an approved programming document which may require program schedule change. Forecast Schedule at Completion and WBS Activity and Milestone Progress not up to date and may require program schedule change. Workplan Development Schedule not used to schedule program delivery in an approved programming document. Forecast Schedule at Completion or WBS Activity and Milestones not Progressed and/or does not match approved program document. Schedule Performance Index (SPI) -- Earned Value (Not Applicable if Earned Value Calculation not available) SPI = 1.0 SPI > 1.0 SPI < 1.0 Page 20

CHAPTER 20 Project Development Cost Estimates Table of Contents

CHAPTER 20 Project Development Cost Estimates Table of Contents Chapter 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates... 20-3 SECTION 1 Project Cost

More information

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL

LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT CONSTRUCTION PLANS QUALITY CONTROL / QUALITY ASSURANCE MANUAL August 2008 TABLE OF CONTENTS Section 1 - Introduction... 3 1.1 Defining Plan Quality...

More information

CALTRANS PROJECT MANAGEMENT HANDBOOK

CALTRANS PROJECT MANAGEMENT HANDBOOK CALTRANS PROJECT MANAGEMENT HANDBOOK Fifth Edition October, 2007 Office of Project Management Process Improvement Caltrans Office of Project Management Process Improvement 1120 N Street, Mail Station 28

More information

CHAPTER 6 Project Cost, Scope, and Schedule Changes Table of Contents

CHAPTER 6 Project Cost, Scope, and Schedule Changes Table of Contents Chapter 6 Project Cost, Scope, and Schedule Changes Table of Contents CHAPTER 6 Project Cost, Scope, and Schedule Changes Table of Contents CHAPTER 6 Project Cost, Scope, and Schedule Changes... 6-3 ARTICLE

More information

CHAPTER 27 New Public Road Connections. Table of Contents

CHAPTER 27 New Public Road Connections. Table of Contents Chapter 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections Table of Contents CHAPTER 27 New Public Road Connections... 27-3 ARTICLE 1 - General... 27-3 Responsibility...

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS

QUALITY ASSURANCE. and QUALITY CONTROL PROCESS GUIDE. for PROJECT MANAGERS QUALITY ASSURANCE and QUALITY CONTROL PROCESS GUIDE for PROJECT MANAGERS MDOT Trunkline Projects January 2005 TABLE OF CONTENTS Discussion.. 2 Scope Verification Meeting..... 3 Overview 3 Procedure...

More information

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005

FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 FHWA Colorado Division Control of Access to the Interstate and its Right-of-Way February 2005 Background: It is in the national interest to maintain the Interstate System to provide the highest level of

More information

Texas Department of Transportation

Texas Department of Transportation Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0

More information

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

Quality Control and Quality Assurance Guide

Quality Control and Quality Assurance Guide Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...

More information

Design-Build Process for Project Managers

Design-Build Process for Project Managers Vermont Agency of Transportation Design-Build Process for Project Managers This document provides guidance on the preliminary engineering and procurement process and roles and responsibilities of key personnel

More information

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1

Appendix. Change Management Plan. Communication Plan. QA/QC Plan. Transition and Closure Plan C-1 Appendix C Change Management Plan Communication Plan QA/QC Plan Transition and Closure Plan C-1 CHANGE MANAGEMENT PLAN Whether the effects of changes are positive or negative, managing change is an important

More information

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A

Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement

More information

Chapter 22. Lump Sum Project Guidelines

Chapter 22. Lump Sum Project Guidelines Chapter 22 Lump Sum Project Guidelines 22.1 General...22-1 22.2 Project Selection...22-3 22.3 Plans Preparation...22-5 22.4 Preliminary Estimate...22-7 22.5 Specifications...22-9 22.6 Contracts Administration...22-11

More information

CHAPTER 2 LCCA APPROACHES

CHAPTER 2 LCCA APPROACHES 2.1 LCCA Basis CHAPTER 2 LCCA APPROACHES When making decisions about pavement design, LCCA: Compares pavement alternatives; and Identifies the best strategy based on current information as well as meeting

More information

Implementing Agency Responsibilities on State Highway Projects Revised June 2006

Implementing Agency Responsibilities on State Highway Projects Revised June 2006 Implementing Agency Responsibilities on State Highway Projects Purpose of this Document... 1 Background... 2 Sponsors, Implementing Agencies and Project Components... 2 Quality Assurance... 2 Key Roles...

More information

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST

DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST State of California Business, Transportation and Housing Agency DISTRICT 3 TRAFFIC MANAGEMENT PLAN CHECKLIST District / EA: District 3/ EA 03-3E380 Date Prepared: 1/10/2013 Prepared By: Robert Himes Stage

More information

Project Risk Management Handbook: A Scalable Approach

Project Risk Management Handbook: A Scalable Approach Project Risk Management Handbook: A Scalable Approach Version 1 (June 2012) Risk Monitoring Qualitative Risk Analysis Risk Response A LETTER FROM THE CHIEF ENGINEER Welcome to the new Caltrans Project

More information

and the statewide and metropolitan transportation planning and programming process in California:

and the statewide and metropolitan transportation planning and programming process in California: Financial constraint... and the statewide and metropolitan transportation planning and programming process in California: A GUIDE TO FEDERAL AND STATE FINANCIAL PLANNING REQUIREMENTS Prepared by: Federal

More information

Project Delivery Process Overview

Project Delivery Process Overview New Jersey Department of Transportation Project Delivery Process Overview Presented by the Program Management Office January, 2012 Project Delivery Process Overview The New Jersey Department of Transportation

More information

Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents

Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents 1.0 Introduction 1.1 Quality Management Policy and Practices 2.0 Quality System Components 2.1 Quality Management Plans 2.2 Quality

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS

NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS NCDOT MAPPING GUIDELINES FOR PLANNING AND DESIGN ACTIVITIES MAPPING PRODUCTS FOR ROADWAY DESIGN AND PDEA STEPS FOR REQUESTING MAPPING PRODUCTS DESIGN TYPE DEFINITIONS YEARLY MAPPING NEEDS REQUEST DESCRIPTION

More information

ADA POST INSPECTION CHECKLIST. Job No. Route County Location

ADA POST INSPECTION CHECKLIST. Job No. Route County Location ADA POST INSPECTION CHECKLIST Job No. Route County Location SIDEWALKS All sidewalks constructed within the project limits are ADA compliant. Sidewalks are 5 or greater in width. Exception, existing sidewalks

More information

Oregon Access Management Manual. Chapter 3. Guidelines and Resources for Access Management in Project Development

Oregon Access Management Manual. Chapter 3. Guidelines and Resources for Access Management in Project Development Oregon Access Management Manual Chapter 3 Guidelines and Resources for Access Management in Project Development i TABLE OF CONTENTS ACRONYMS...IV INTRODUCTION...V CONTEXT SENSITIVE SOLUTIONS...V FAQ S...VI

More information

Strategies for creating accurate updates of CPM construction schedules.

Strategies for creating accurate updates of CPM construction schedules. Session No. 2247 Strategies for creating accurate updates of CPM construction schedules. Todd Dunn, P.E. Associate Professor, Rochester Institute of Technology Civil Engineering Technology Abstract: The

More information

Data Analysis - How to Write a Need Statement

Data Analysis - How to Write a Need Statement Section I: Analyzing Data and Writing Need Statements Step 3: Gather and Analyze Data Activities Recommended Tasks Highly Recommended Analyze data and write Need NAC analyzes data and Each Need Statement:

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Business Continuity Position Description

Business Continuity Position Description Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary

More information

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices : A CDOT Guide to Better Project Management Practices Project Management practices have been a part of the CDOT culture for many years. However, with a transitioning workforce and increasing demands, it

More information

Actuarial Standard of Practice No. 23. Data Quality. Revised Edition

Actuarial Standard of Practice No. 23. Data Quality. Revised Edition Actuarial Standard of Practice No. 23 Data Quality Revised Edition Developed by the General Committee of the Actuarial Standards Board and Applies to All Practice Areas Adopted by the Actuarial Standards

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS

CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS HIGHWAY DESIGN MANUAL 600-1 May 7, 2012 CHAPTERS 600 670 PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS Topic 601 - Introduction Pavement engineering involves the determination of the type and thickness

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP)

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) Local Assistance Program Guidelines Chapter 4 CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) CONTENTS Section Subject Page Number 4.1 INTRODUCTION... 4-1 4.2 ELIGIBILITY CRITERIA... 4-1 General... 4-1

More information

LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL

LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL State of California Department of Transportation Division of Maintenance Pavement Program LCCA Procedures Manual August 213 DISCLAIMER This manual is intended

More information

Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL

Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL Chapter 7 PURPOSE AND NEED MDT ENVIRONMENTAL MANUAL October 2010 Table of Contents Section Page 7.1 OVERVIEW... 7-1 7.2 LAWS, REGULATIONS AND GUIDANCE... 7-2 7.2.1 40 CFR 1500 through 1508 CEQ Regulations...

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources

Objectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management

More information

CHAPTER 29 Landscape Architecture Table of Contents

CHAPTER 29 Landscape Architecture Table of Contents Chapter 29 Landscape Architecture Table of Contents CHAPTER 29 Landscape Architecture Table of Contents CHAPTER 29 Landscape Architecture... 29-5 SECTION 1 General... 29-5 Introduction... 29-5 Aesthetic,

More information

Contract Administration

Contract Administration Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306

More information

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST

FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST FHWA Minnesota Division Guidance for the Preparation of a FHWA INTERSTATE ACCESS REQUEST August 2003 Background: The Federal Highway Administration (FHWA) has retained all approval rights to the control

More information

Project Management Manual Update 2006. Transportation Department City of Edmonton

Project Management Manual Update 2006. Transportation Department City of Edmonton Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Assessing Paved Trails for Compliance with Standards and Best Practices

Assessing Paved Trails for Compliance with Standards and Best Practices Assessing Paved Trails for Compliance with Standards and Best Practices Session Presenters: Kristin Maravilla, Planner/Designer Masters in Landscape Architecture (UC Berkeley) Masters in City and Regional

More information

Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016

Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016 Wilmington Urban Area Metropolitan Planning Organization Surface Transportation Program Direct Attributable Project Submittal Guide Fiscal Year 2016 Date of Release: September 14, 2015 Pre application

More information

ROLE DESCRIPTIONS BY COMPETENCY LEVEL

ROLE DESCRIPTIONS BY COMPETENCY LEVEL UNIVERSITY OF NORTH CAROLINA WILMINGTON Business Systems Analyst DESCRIPTION OF WORK: The principle role of the Business Systems Analyst is to plan, design, examine, analyze, develop, implement, administer

More information

Attachment 5 Electrical Engineering

Attachment 5 Electrical Engineering A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or

More information

Solvency II Data audit report guidance. March 2012

Solvency II Data audit report guidance. March 2012 Solvency II Data audit report guidance March 2012 Contents Page Introduction Purpose of the Data Audit Report 3 Report Format and Submission 3 Ownership and Independence 4 Scope and Content Scope of the

More information

SCHEDULE 3. Milestones and Deliverables. Redacted Version

SCHEDULE 3. Milestones and Deliverables. Redacted Version SCHEDULE 3 Milestones and Deliverables Redacted Version This Schedule 3 sets out the Service Provider s obligations in respect of the milestones and deliverables relating to the implementation and operation

More information

Project Zeus. Risk Management Plan

Project Zeus. Risk Management Plan Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related

More information

Oregon Department of Transportation

Oregon Department of Transportation Oregon Department of Transportation Guidelines For Project Teams November 1997* (Revised November 1999) Page M - 8 Page M - 9 Edward Deming: Preface Effective Work is not possible without understanding

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL

LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL Note to the User To use this manual, the reader must have the life-cycle cost analysis software program RealCost, Version 2.2 California Edition. The program

More information

Surface Transportation Program (STP)

Surface Transportation Program (STP) Project Name: Project Sponsor: FEDERAL FUNDS PROJECT APPLICATION TRANSPORTATION IMPROVEMENT PROGRAM 2008-2013 SALT LAKE and OGDEN/ LAYTON URBAN AREAS Surface Transportation Program (STP) Urban Surface

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Essential Elements for Any Successful Project

Essential Elements for Any Successful Project In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable

More information

Development, Acquisition, Implementation, and Maintenance of Application Systems

Development, Acquisition, Implementation, and Maintenance of Application Systems Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of

More information

Surface Transportation Program (STP) Projects

Surface Transportation Program (STP) Projects Toledo Metropolitan Area Council of Governments American Reinvestment and Recovery Act (Economic Stimulus Program) Application Packet for: Surface Transportation Program (STP) Projects APPLICATIONS DUE

More information

Exhibit A Scope of Work

Exhibit A Scope of Work Exhibit A Scope of Work The agreement for S.P. 3116-142 (T.H. 169-Cross Range Expressway) includes final design plans for a 1.55 mile length of a 2 lane to 4 lane expansion project located 0.66 miles SW

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)

CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB

More information

How To Write A Right Of Way Certificate

How To Write A Right Of Way Certificate CHAPTER 14 RIGHT OF WAY CERTIFICATION TABLE OF CONTENTS 14.01.00.00 INTRODUCTION 01.00 General 01.01 Definition 02.00 Projects Requiring R/W Certification 03.00 Projects Exempt From R/W Certification 04.00

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

Project Management On-line Guide

Project Management On-line Guide Project Management On-line Guide Project Life Cycle Processes Flowchart Department Policy Memorandum Project Management Policy To support the Project Management Initiative, respond to Policy Agreement

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS CHAPTER 11 - Project Continuity Contents Introduction... 2 Phase Hand-Offs... 3 Project Feedback... 9 Project Management Team Approach... 10 Page 1 of 15 Introduction A primary objective of all Project

More information

SYSTEMWIDE REQUIREMENTS

SYSTEMWIDE REQUIREMENTS SYSTEMWIDE REQUIREMENTS for the Peninsula Rail Program San Francisco to San Jose on the Caltrain Corridor Description of the Systemwide Context for the High Speed Train Project This document provides a

More information

The University of Adelaide Business School

The University of Adelaide Business School The University of Adelaide Business School MBA Projects Introduction There are TWO types of project which may be undertaken by an individual student OR a team of up to 5 students. This outline presents

More information

Professional Engineers Using Software-Based Engineering Tools

Professional Engineers Using Software-Based Engineering Tools GUIDELINE Professional Engineers Using Software-Based Engineering Tools CONTRIBUTORS Eric Brown, P. Eng. Colin Cantlie, P. Eng. Norm Fisher, P. Eng. Jeremy Jackson, P. Eng. Tibor Palinko, P. Eng. Daniel

More information

Initial Professional Development - Professional Values, Ethics, and Attitudes (Revised)

Initial Professional Development - Professional Values, Ethics, and Attitudes (Revised) IFAC Board Exposure Draft July 2012 Comments due: October 11, 2012 Proposed International Education Standard (IES) 4 Initial Professional Development - Professional Values, Ethics, and Attitudes (Revised)

More information

SITE PLAN APPROVAL PROCESS INTRODUCTION

SITE PLAN APPROVAL PROCESS INTRODUCTION SITE PLAN APPROVAL PROCESS INTRODUCTION File Manager System for Site Plan Approval Process Site Plan Control in the City of London The City of London utilizes site plan control to ensure high quality site

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

PROJECT MANAGEMENT IN GEOTECHNICAL SERVICES

PROJECT MANAGEMENT IN GEOTECHNICAL SERVICES PROJECT MANAGEMENT IN GEOTECHNICAL SERVICES INTRODUCTION Geotechnical Services (GS) is dedicated to delivering quality projects within budget and on schedule. In pursuing this goal, GS closely collaborates

More information

KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS

KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS I. GENERAL The following policy shall apply when the intent of the project is to

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

Eastern Illinois University EISE Configuration Management Plan

Eastern Illinois University EISE Configuration Management Plan Eastern Illinois University EISE Configuration Management Prepared by: Bill Witsman Version: 10.0 Create Date: April 13, 2005 Approval Date: Last Revision Date: December 17, 2009 CM Analyst: Project Manager:

More information

PRIORITIZATION PROCESSES

PRIORITIZATION PROCESSES PROJECT SELECTION & PRIORITIZATION PROCESSES STIP Workshop Presented by: Bill Lawrence April 2011 Purpose and Review Overview of Project Selection Process Review Various Prioritization Processes Tk Take

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

Toronto Maintenance Management System Application Review. the exercise to harmonize business practices is completed;

Toronto Maintenance Management System Application Review. the exercise to harmonize business practices is completed; STAFF REPORT March 30, 2004 To: From: Subject: Audit Committee Auditor General Toronto Maintenance Management System Application Review Purpose: The purpose of this audit was to assess how well the Toronto

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

ProjectMinds Quick Guide to Project Management

ProjectMinds Quick Guide to Project Management ProjectMinds Quick Guide to Project Management By Manjeet Singh msingh@projectminds.com 1 A D I F F E R E N T K I N D O F C O P Y R I G H T No rights reserved. All the parts of this book can be reproduced,

More information

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL

Chapter Forty-seven. RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Chapter Forty-seven RURAL TWO-LANE/MULTILANE STATE HIGHWAYS (New Construction/Reconstruction) BUREAU OF DESIGN AND ENVIRONMENT MANUAL Illinois RURAL TWO-LANE/MULTILANE STATE HIGHWAYS December 2009 2 Illinois

More information

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE STATE OF IDAHO DEPARTMENT OF ADMINISTRATION DIVISION OF PURCHASING REVISED 01 01 14 Table of Contents I. Purpose... 1 II. Overview of Contract Management and

More information

I. EVENTS CALENDAR... 2 II. INTRODUCTION... 2 III. INQUIRIES... 4 IV. SUBMISSIONS... 4 V. GENERAL INFORMATION... 5

I. EVENTS CALENDAR... 2 II. INTRODUCTION... 2 III. INQUIRIES... 4 IV. SUBMISSIONS... 4 V. GENERAL INFORMATION... 5 REQUEST FOR TECHNICAL PROPOSALS to provide ENVIRONMENTAL AND ENGINEERING SERVICES to prepare a PROJECT STUDY REPORT-PROJECT DEVELOPMENT SUPPORT (PSR-PDS) on the ETHANAC ROAD/STATE ROUTE 74/NICHOLS ROAD

More information

OE PROJECT CHARTER TEMPLATE

OE PROJECT CHARTER TEMPLATE PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,

More information

Brillig Systems Making Projects Successful

Brillig Systems Making Projects Successful Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.

More information

NABL NATIONAL ACCREDITATION

NABL NATIONAL ACCREDITATION NABL 160 NABL NATIONAL ACCREDITATION BOARD FOR TESTING AND CALIBRATION LABORATORIES GUIDE for PREPARING A QUALITY MANUAL ISSUE NO. : 05 AMENDMENT NO : 00 ISSUE DATE: 27.06.2012 AMENDMENT DATE: -- Amendment

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS

APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS APPLYING PROJECT MANAGEMENT TECHNIQUES TO QEHS Mary F. McDonald, CQA President/Principal Consultant Individual Solution Options/Quality Services (ISO/QS), Inc. Austin, TX 78739 Tel: (512) 282-0181 E-mail:

More information

COLORADO DEPARTMENT OF TRANSPORTATION. LINKING PLANNING and THE NATIONAL ENVIRONMENTAL POLICY ACT GUIDANCE

COLORADO DEPARTMENT OF TRANSPORTATION. LINKING PLANNING and THE NATIONAL ENVIRONMENTAL POLICY ACT GUIDANCE COLORADO DEPARTMENT OF TRANSPORTATION LINKING PLANNING and THE NATIONAL ENVIRONMENTAL POLICY ACT GUIDANCE Yates Oppermann March 2007 Introduction The purpose of this guidance is to provide the Colorado

More information

Recognition of Prior Learning (RPL) BSB40515 Certificate IV in Business Administration

Recognition of Prior Learning (RPL) BSB40515 Certificate IV in Business Administration Recognition of Prior Learning (RPL) BSB40515 Certificate IV in Business Administration What is RPL? RPL recognises that you may already have the skills and knowledge needed to meet national competency

More information

Chapter 6: Design Management

Chapter 6: Design Management Chapter : Design Management Department of Main Roads Chapter Design Management June 2005 i Department of Main Roads Chapter : Design Management Manual Contents Chapter 1 Planning and Design Framework Chapter

More information

Transportation Management Plan Template

Transportation Management Plan Template DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County

More information

Presentation to Community Task Force July 9, 2007

Presentation to Community Task Force July 9, 2007 Alternative Evaluation Results Presentation to Community Task Force July 9, 2007 Outline of Presentation Overview of alternative evaluation Alternative evaluation methodology Process and assumptions General

More information

Within seconds of answering the phone, those ominous

Within seconds of answering the phone, those ominous EST.10 Preparing a Basis of Estimate Mr. Todd Pickett, CCC Within seconds of answering the phone, those ominous words were muttered by the project manager, "do you remember that estimate you did for me

More information

Tier II FEIS Appendix G DEIS Comments and Responses Page G-158 SR 167 Puyallup to SR 509

Tier II FEIS Appendix G DEIS Comments and Responses Page G-158 SR 167 Puyallup to SR 509 RESPONSE L06-003 WSDOT is coordinating with the Port on the Port's Expansion plans. The Taylor Road/SR 509 intersection is outside the scope of this EIS. The crossing at Alexander Avenue is still required,

More information