1 PROJECT SCOPE Agricultural History Farm Park Barn A. Introduction The Montgomery County Department of Parks (Parks) is requesting proposals from qualified restoration and preservation contractors to design and modify the historic Bank Barn located in Agricultural History Farm Park, Muncaster Rd., Derwood, MD 20855, to use it for interpretive programming, group tours, and special events. Work includes but not limited to reviewing the Condition Survey Report, surveying the existing conditions, analyzing the code requirements, designing the modifications, submitting the design documents to the permitting agencies, obtaining all the required permits, performing selective demolition as well as construction, and obtaining, after completion of all the required modifications, Use and Occupancy Certificate for Assembly Use. The 455-acre Agricultural History Farm Park, (including the bank barn structure) is listed in the Montgomery County Master Plan for Historic Preservation. This is on the Locational Atlas as part of the historic Bussard Farm, Site MP 22/007, and is of historic significance. All work on the structure including site work should be designed and constructed in accordance with National, State, and local codes and should follow recommended treatment guidelines stated in the Secretary of the Interior s Standards for Preservation of Historic Buildings. The design and construction modifications to the structure shall meet the Use and Occupancy requirements for Assembly while retaining the historic fabric, the building s historic form, features and detailing. The work shall comply with Chapter 24-A of the Montgomery County Code (historic preservation ordinance) and all requirements of the Montgomery County Department of Permitting Services and the Montgomery County Historic Preservation Commission (HPC). The Contractor, along with its sub-contractors shall be experienced in historic preservation and rehabilitation, which includes: architecture, preservation, restoration, structural, mechanical, electrical, and plumbing engineering, and associated site work. The Agricultural Bank Barn houses farm animals in the lower stable level of the building, which are part of an ongoing 4-H program on farm animals, farm life and agriculture. The Friends of Agricultural History Farm Park and the Master Gardeners also offer special programs throughout the year and provide demonstrations on historical farm life, agriculture, and plant-related programs. The park also includes the historic Bussard Farmhouse and historic farm outbuildings, as well as a modern farming Activity Center, which supports Montgomery County agriculture and houses several federal, state and county agencies. The Agricultural Bank Barn, circa 1895, is typical of bank barns found in Montgomery County at the turn of 20 th century and offers visitors a unique perspective on the County's rich farming heritage. Farm animals will remain housed in the lower stable level of the barn (the Undercroft). Hay was originally stored and grain threshed on the barn's main floor, which is currently accessible to the public and rented for weddings and social occasions, in addition to being used for other special events. Among other information, the Condition Survey Report includes the following information that requires verification by the selected Contractor: The barn is approximately 45' x 80' with interior clear space from the second floor to the roof. The building is constructed of solid oak timber beams and columns connected together with mortise and tenons. Joints are held together with wood pins, although supplemental cabling was added at a later date. The exterior shell is wood lap siding. The barn is built on a hill, in a north/ south direction, making it grade accessible on both the first and second floors. The approximate size of the barn is summarized below. 1

2 General Size and Use of the Building Undercroft 2,662 S.F. +/- Two (2) Storage Areas 480 S. F. Each Staff Area 265 S. F. Barn Floor 2,613 S.F. Total Barn Area on two floors: 3,358 S. F. B. Project History and Program of Requirements A Condition Survey of the Agricultural Bank Barn was prepared by Symmetry First Architects. The survey report identified the following issues to be addressed by the Design Build Contractor while designing and performing demolition and construction modifications for obtaining a Use and Occupancy Certificate for Assembly: Address requirements for ADA access from the parking to the activities inside the facility, including exit doors Address requirements for guardrails at the sliding door opening on the north wall to meet code requirements Address fire rating requirements of the two existing storerooms located at barn level Provide exit signs, interior and exterior emergency lighting Provide sprinkler system, heat detectors and fire alarm system Reinforce second floor framing (joists and beams) to meet 100 lbs/sf live load requirement Reinforce end walls to meet local wind and seismic requirements Reinforce mortise and tenon joints at interior column frames to meet structural requirements Verify structural integrity of the foundation, install connectors at wood column bases and install concrete wall at stone foundation wall. Reinforce roof rafters and beams to meet 30 lbs/sf live load requirement and replace roof The Condition Survey made several specific comments that may not be in keeping with an historic structure. The selected Contractor shall verify and confirm the project requirements early in the design process with the M-NCPPC staff team and ensure that the project goals and any consequent structural changes are achievable, while maintaining the historic integrity of the interior and exterior of the barn and meeting the requirements of all the permitting agencies. For example, the survey s recommendation to plaster over interior stone walls would destroy a character-defining historic surface and would not be approved by Park staff. In addition, the recommendations for storage rooms need to be reconsidered, as these alterations could be detrimental to the historic structure. In view of the limited funds available for the project, the cost of preparation of design drawings and obtaining the required permits for the reinforcements to the barn roof structure to meet the code shall be included in the base bid for this project. The cost for the demolition and construction modifications associated with this roof structure shall be submitted as an alternate. The current staff preference is to replace the existing roof with 5V crimp metal roofing, if approved by the HPC. This item may be added by M-NCPPC to the Contract by issuing a change order to the Contract during the contract period. The latest guidelines/requirements of the Americans with Disabilities Act (ADA) shall also be incorporated into public use areas of the barn, including the following: An ADA accessible route to provide access from parking or drop-off areas to the barn Access to and within the public areas of the building, compliant with the ADA requirements for Program Access Signage as required 2

3 Access to restroom facilities or portable toilets C. Schedule for Completion of the Construction: Scheduled and programmed activities occur within the barn from April through early December. The demolition and construction modifications must occur between December 15, 2013 and March 31, The Contractor shall prepare documentation and obtain construction permit by December 15, The Contractor may start construction related work earlier than December 15, 2013 if the Construction Manager approves the early start of work that does not interfere with the activities of the facility and does not require an approved permit. All other work shall start only after obtaining all the permits and after December 15, All work shall be completed on or before March 31, 2014 and Use and Occupancy certificate obtained. All the required material and equipment shall be procured in advance and preferably have it delivered before the required date to avoid delay due to severe adverse weather during winter months. D. M-NCPPC Project Management The Project Manager will be the Contractor s primary contact throughout the design and permitting phases of work. The Construction Manager will be the primary contact during the construction phase of work. E. Required Contractor Team The selected Contractor shall assemble an inter-disciplinary team to design and construct the major components of the project work. One Contractor Project Representative as a Project Manager for the project with documented experience in similar work and should be responsible for project management and coordination of inter-disciplinary team s contract work within the schedule. An architect with documented experience in code analysis, modifying, preserving, restoring, and/or rehabilitating historic properties for public and assembly use; Structural, civil, mechanical, plumbing, electrical engineers with experience in designing modifications to historical preservation projects, ; experts in value analysis cost estimating, fire suppression and alarm systems; A Project construction Superintendent who is knowledgeable with documented experience in similar work. F. Scope of Work Design Activity All work should be designed and installed in accordance with National, State, and local codes and should follow recommended treatment guidelines in the Secretary of the Interior s Standards for Preservation 3

4 of Historic Buildings. The following tasks are considered essential to complete the Project for intended use; however the selected Contractor may add more tasks to complete the project. 1. Visit site, review and field verify all the information included in the Condition Survey Report for performing the design and preparing the construction documents. 2. Immediately after receiving the Notice to Proceed, participate in a kick-off meeting with the M- NCPPC Project team members to discuss and understand the role of M-NCPPC representatives in completing the project and introduce all the key personnel of the Contractor. 3. Prepare and submit within seven (7) calendar days of receiving the Notice to Proceed letter (NTP) a detailed completion schedule listing starting and completion dates for all tasks required to accomplish project goals and objectives. The schedule shall show how all the design, permitting, demolition, construction and obtaining the Use and Occupancy Certificate will be completed on or before March 31, Submit the project schedule electronically using Microsoft Project or similar software approved by the M-NCPPC. 4. Upon completion of site visit and verification of all the available information submit a report if any of the required tasks have to be modified to complete the project for intended use. Make a presentation of work plan, preservation/stabilization methods, sequence of work and alternate methods of work with the M-NCPPC project team and address their comments. Prepare and submit 3 sets of preliminary plans, including sections, elevations, photography and sketches that are required to complete the proposed work. If requested by the Project Manager, meet with M-NCPPC project team, and address the recommended revisions. 5. Review preliminary plans, including all exterior and site modifications affecting the barn, with Historic Preservation Commission (HPC) staff. Attend a preliminary consultation meeting with the HPC (at their regularly scheduled meeting) if recommended by HPC staff. Prepare all presentation materials as required by the HPC. 6. Attend a preliminary meeting with the Department of Permitting Services to discuss any proposed work that may require clarification or interpretation of code requirements (such as obtaining a waiver from specific requirements for the historic structure.) 7. Attend a public meeting to present the proposed work for public information and comment. Prepare all presentation materials (including a PowerPoint presentation) and handouts, and present the project with the M-NCPPC project manager. Provide and set up any equipment that is required for the presentation. Project Manager will prepare and send out public notices and reserve the room for the meeting. 8. Prepare and submit 3 sets of 90% construction documents and specifications for the project by addressing the review comments from the HPC, DPS, M-NCPPC staff, members of the public, and current code requirements. Prepare site plan showing existing and proposed features including but not limited to topography, construction access, staging, security fence, silt fence, clearing, grubbing, grading, and public access to the preserved/stabilized building. Include all necessary graphics (plans, sections, elevations, details) to convey the design concepts. Include details for architectural, mechanical, electrical, plumbing, structural, security/fire alarm, fire suppression and utilities. Prepare and submit all drawings in AutoCAD 2010 or later version. If requested by the Project Manager, meet with M-NCPPC project team, and address recommended revisions. 4

5 9. Attend all required permit approval meetings and obtain all necessary final permits, including but not limited to a Historic Area Work Permit (and final Historic Preservation Commission approval,) and all required building permits from Montgomery County. 10. Prepare and submit to M-NCPPC final 100% construction documents, specifications, copies of all the required permits and revised project schedule if needed. Submit one set of original signed and sealed documents and five copies of 100% construction documents. (See Deliverable Requirements.) Construction Activity 11. Following M-NCPPC acceptance of the 100% construction documents proceed with construction work in accordance with the approved plans and specifications. Refer to Paragraph D (above) for schedule and restrictions. 12. Attend a pre-construction meeting with the M-NCPPC Project and Construction Manager. 13. Attend regularly scheduled construction progress meetings with the Construction Manager while the construction is in progress. 14. Submit shop drawings and all other submittals to the Construction Manager for approval using Submittal Exchange Web site. Refer to Special conditions for complying with the requirements of using Submittal Exchange for submittal approval process. 15. Perform all work in accordance with project and permit requirements. 16. Upon completion of the work, obtain approval from all the permitting agencies including obtaining Use and Occupancy Certification. 17. Request the Construction Manager to inspect the completed project for acceptance by the M- NCPPC. Upon completion of inspection, if the project is accepted for intended use, the Construction Manager will issue a substantial completion letter with a punch list attached to it if any of the minor items of work are not completed. 18. Prepare and submit as-built drawings in AutoCAD, following M-NCPPC requirements, and submit for review and acceptance by the M-NCPPC Construction Manager. Revise drawings as requested by Construction Manager. 5

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone:

Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: Choctaw Date Recorded: Permit # RESIDENTIAL - BUILDING Permit APPLICATION Physical Address/Intersection: Name of Project: Within a NFIP 100/500yr Floodzone: YES NO Sec., Township, Range/Subdivision: Acres/Block:

More information

Exhibit C: Scope of Work and Schedule of Deliverables

Exhibit C: Scope of Work and Schedule of Deliverables Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza

More information

Residential Building Permits

Residential Building Permits LANE COUNTY PUBLIC WORKS Residential Building Permits LAND MANAGEMENT DIVISION 3050 N. DELTA HWY, EUGENE OR 97408 i CONTACT PHONE NUMBERS: Building Program: (541) 682-4651 Inspection Requests: (888) 299-2821

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

4460.1 REV 1. 4-1. GENERAL. All instructions of this Handbook apply to rehabilitation projects unless modified by this Chapter.

4460.1 REV 1. 4-1. GENERAL. All instructions of this Handbook apply to rehabilitation projects unless modified by this Chapter. 4460.1 REV 1 CHAPTER 4. REHABILITATION 4-1. GENERAL. All instructions of this Handbook apply to rehabilitation projects unless modified by this Chapter. 4-2. DEFINITIONS. A. Substantial Rehabilitation.

More information

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION

REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION

More information

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R

COMMON FOR ARCHITECTS AND ENGINEERS Excerpts from HB 2284, 82 nd R Legislation passed by the 82 nd legislature has modified the Texas Engineering Practice Act and the Texas Architect Practice Act. In order to give the public a clearer understanding of these changes, the

More information

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx.

City of La Vernia 102 E. Chihuahua Street, La Vernia, Texas 78121 Phone: (830)779-4541 Fax: (830) 253-1198 cityoflavernia@lavernia-tx. cityoflavernia@lavernia-tx.gov Commercial New/Remodel Building Requirements This document is not meant to modify any Federal or State laws or City Ordinances. It is intended to be informative and to be

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

Enrolled Copy S.B. 117

Enrolled Copy S.B. 117 1 COMMERCIAL INTERIOR DESIGN CERTIFICATION 2 MODIFICATIONS 3 2016 GENERAL SESSION 4 STATE OF UTAH 5 Chief Sponsor: Luz Escamilla 6 House Sponsor: Mike Schultz 7 8 LONG TITLE 9 General Description: 10 This

More information

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or

9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org. Incidental improvements: improvements that do not qualify as minor or 9770 CULVER BOULEVARD CULVER CITY, CA 90232-0507 www.culvercity.org Construction Permitting Guidelines for Businesses Moving into Existing Buildings in Culver City If your business is moving into an existing

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA

FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA FIRE SUPPRESSION INSTALLATION CITY OF HARRISONBURG, VIRGINIA I. PURPOSE The purpose of this document is to provide planners and designers with information necessary in the design and construction of sprinkler

More information

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:

When is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are: When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory

More information

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

More information

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

D Sample Notices to Property Owners, Sample Affidavits, and Other Material D Sample Notices to Property Owners, Sample Affidavits, and Other Material These samples are offered to illustrate specific points in the Desk Reference. States and communities should examine them carefully

More information

Request for Qualifications 2015-162

Request for Qualifications 2015-162 Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015

More information

Planning and Construction Management Services

Planning and Construction Management Services Planning and Construction Management Services Construction Project Management Services New construction, major renovations or improvements to building structures and systems are part of the Department's

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below

More information

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

M E M O R A N D U M PLANNING AND COMMUNITY DEVELOPMENT DEPARTMENT CITY OF SANTA MONICA PLANNING DIVISION

M E M O R A N D U M PLANNING AND COMMUNITY DEVELOPMENT DEPARTMENT CITY OF SANTA MONICA PLANNING DIVISION M E M O R A N D U M PLANNING AND COMMUNITY DEVELOPMENT DEPARTMENT CITY OF SANTA MONICA PLANNING DIVISION DATE: September 10, 2007 TO: FROM: The Honorable Landmarks Commission Planning Staff SUBJECT: 11A.

More information

Building Permits Permit Counter

Building Permits Permit Counter Building Permits Permit Counter APPLICATION CHECKLIST SUBMITTAL REQUIREMENTS: 1. Completed signed and notarized Development Services Department Permit Application, submit to Permit Counter. 2. Copy of

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Civil Engineering and Architecture (CEA) Detailed Outline

Civil Engineering and Architecture (CEA) Detailed Outline Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of

More information

Structural Engineering Services

Structural Engineering Services DRH Engineers, PLC (DRH) is a small veteran owned civil/structural engineering firm located in Warrenton, VA. DRH has a distinguished record of providing quality structural engineering and project management

More information

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes

T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes T170 Interior Design Technology MTCU Code 61833 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes The graduate has reliably demonstrated the ability to 1. analyze a client's needs

More information

Revised Work Scope Dated April 23 rd, 2015

Revised Work Scope Dated April 23 rd, 2015 Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March

More information

Miami Beach Building Department

Miami Beach Building Department Miami Beach Building Department Documents Required To Be Signed and Sealed By A Design Professional (FLORIDA BUILDING CODE) GENERAL CONTRACTOR: If the plans are prepared by a design professional that is

More information

APPLICATION FOR HISTORIC MIRAMAR COMMERCIAL REHABILITATION PROGRAM (TARGET AREA)

APPLICATION FOR HISTORIC MIRAMAR COMMERCIAL REHABILITATION PROGRAM (TARGET AREA) Application No. APPLICATION FOR HISTORIC MIRAMAR COMMERCIAL REHABILITATION PROGRAM (TARGET AREA) (954) 602-3264 www.ci.miramar.fl.us Page 1 of 11 CONTENTS 1. Introduction...3 2. Map of Program Area....4

More information

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal.

All substantial design decisions and budget confirmation shall be resolved for the College to approve the Design Development Submittal. 2.02 DESIGN DEVELOPMENT PHASE GENERAL The Architect shall prepare the Design Development Documents from the approved Schematic Design. The Design Development Documents shall consist of drawings and other

More information

REFERENCES-COMMERCIAL. Montgomery County Community College. 60,000 Sq. Ft. Montgomery County Community College 12,000 Sq. Ft.

REFERENCES-COMMERCIAL. Montgomery County Community College. 60,000 Sq. Ft. Montgomery County Community College 12,000 Sq. Ft. Montgomery County Community College West Campus Expansion 60,000 Sq. Ft. Warehouse adaptive reuse of the former Vaughn Knitting Mill, a major architectural component of Pottstown s Industrial Heritage.

More information

TD AMERITRADE Park Omaha

TD AMERITRADE Park Omaha TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment

More information

Introduction to Building Permit Procedures on VA Tech Properties. Presented by the VA Tech Office of the University Building Official.

Introduction to Building Permit Procedures on VA Tech Properties. Presented by the VA Tech Office of the University Building Official. Introduction to Building Permit Procedures on VA Tech Properties. Presented by the VA Tech Office of the University Building Official. Before we begin... This presentation should run 45-60 minutes Time

More information

FIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011

FIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011 Office of the Fire Marshal 1.0 PERMITS FIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011 1.1 To acquire an installation

More information

TruexCullins Architecture Fairfield Center School Bid Documents Kitchen and Bathroom Renovation March 1, 2015

TruexCullins Architecture Fairfield Center School Bid Documents Kitchen and Bathroom Renovation March 1, 2015 Fairfield Center School Kitchen and Bathroom Renovation Project Specifications Owner: Fairfield Center School, 57 Park Street, Fairfield VT 05455 Franklin Central Supervisory Union, 28 Catherine Street,

More information

Solar Panel Installations

Solar Panel Installations Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.

More information

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:

THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows: Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM

More information

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME 1 THE BUILDING PROCESS The focus of Woodland Homes building department is Quality, Service and Predictability. Through

More information

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL

Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 OVERLEA HIGH SCHOOL Schematic Design Presentation S. Dallas Dance, Superintendent October 22, 2013 0 Overlea High School - Facility Summary Facility Opened: Auditorium Addition: Activity Room Addition: School Rated Capacity

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED*

ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* ADVERTISEMENT FOR PREQUALIFICATION FOR THE FOLLOWING BID PACKAGES *RE-ADVERTISED* BID PACKAGE DESCRIPTION REQUIRED LICENSE Bid Package No. 1 Asbestos Abatement C22 or B, with ASB & HAZ Certification Bid

More information

SWAN POINT YACHT & COUNTRY CLUB

SWAN POINT YACHT & COUNTRY CLUB SWAN POINT YACHT & COUNTRY CLUB PROJECT INFORMATION: SCOPE OF WORK: INTERIOR ALTERATIONS ABBREVIATIONS: VICINITY MAP 33 East Charles Street PO Box 598 30-934-8078 PROPERTY MANAGER: DOTTIE HARPER BROOKFIELD

More information

Design Development Quality Management Phase Checklist Project Phase Checklist Series

Design Development Quality Management Phase Checklist Project Phase Checklist Series Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

RESIDENTIAL BUILDING PERMIT REQUIREMENTS

RESIDENTIAL BUILDING PERMIT REQUIREMENTS RESIDENTIAL BUILDING PERMIT REQUIREMENTS The Building Inspection Division has compiled this packet to help our customers obtain a Building Permit. Enclosed we have listed all departments and inspection

More information

ADDENDUM #2 FORMAL BID 2015-174

ADDENDUM #2 FORMAL BID 2015-174 ADDENDUM #2 FORMAL BID 2015-174 KITSAP COUNTY PARKS DEPARTMENT LOBE FIELD IMPROVEMENTS PHASE 1 TO: FROM: All Respondents Colby Wattling, Buyer CLOSING DATE: December 16, 2015 at 3:00PM (UNCHANGED) REF

More information

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY HOWARD COUNTY MARYLAND ARCHITECTURAL DESIGN ACADEMY Architectural Design 1 Introduction / Overview of Course This course will introduce the basic principles

More information

Building Code Inspections and Fees

Building Code Inspections and Fees St. Mary s County Department of Land Use & Growth Management Customer Assistance Guide 22 Building Code Inspections and Fees May 10, 2014 This guide is intended to assist in the proper construction sequence

More information

Commercial Building Permit Application & Submittal Guidelines

Commercial Building Permit Application & Submittal Guidelines Building Inspection Department 1625 13 th Street, Suite 106 Lubbock, Texas 79457 (806) 775-2087 (806) 775-2088 http://buildinsp.ci.lubbock.tx.us/ Commercial Building Permit Application & Submittal Guidelines

More information

General Fire Code Requirements Within Commercial Tenant Spaces

General Fire Code Requirements Within Commercial Tenant Spaces FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

Building Permit, Fire Inspection and Operating Permit Fee Schedule

Building Permit, Fire Inspection and Operating Permit Fee Schedule Chenango County Code Enforcement Building Permit, Fire Inspection and Operating Permit Fee Schedule Building Permit Exceptions: Buildings being used solely for the purpose of agriculture. As per Agricultural,

More information

The Florida Building Code

The Florida Building Code Setting New Standards for Safety The Florida Building Code Florida Building Commission Florida Department of Community Affairs The Florida Building Code System The Florida Building Commission Florida Building

More information

ATLANTA, April 19, 2004 Swan House, a Neoclassical style home-turned-historic house

ATLANTA, April 19, 2004 Swan House, a Neoclassical style home-turned-historic house News Release FOR IMMEDIATE RELEASE Contact: Ken Higa Lord, Aeck & Sargent 404-253-6732 khiga@lasarchitect.com or Ann Kohut Kohut Communications Consulting 770-913-9747 annielk@bellsouth.net Swan House

More information

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT Project Description and Scope The City and County of Broomfield, Colorado (Broomfield) hereby solicits this Request for Qualifications (RFQ) to prequalify and shortlist up to five (5) foundation repair

More information

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842

Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 Upper Southampton Township Department of Licenses and Inspections 939 Street Rd. Southampton, Pa. 18966 Phone: 215-322-9700 Fax: 215-322-5842 APPLICATION for ZONING and BUILDING PERMIT APPLICATION INSTRUCTIONS:

More information

CITY OF WEST PALM BEACH HISTORIC PRESERVATION AD VALOREM TAX EXEMPTION APPLICATION

CITY OF WEST PALM BEACH HISTORIC PRESERVATION AD VALOREM TAX EXEMPTION APPLICATION CITY OF WEST PALM BEACH HISTORIC PRESERVATION AD VALOREM TAX EXEMPTION APPLICATION OFFICIAL USE ONLY CASE NUMBER: SUBJECT PROPERTY ADDRESS: DATE RECEIVED: ACCEPTED BY: APPLICATION REQUIREMENTS (please

More information

Lake Charles Ward 3 Recreation Improvements To University Park

Lake Charles Ward 3 Recreation Improvements To University Park DATE APRIL 2015 Drawing Index A0.0 Cover Survey A1.0 Site Plan & Details A2.0 Pool Area Site Plan & Demo Plan A2.1 Pool Area Building Improvements A2.2 Pool Area Elevations & Wall Section A3.0 Basketball

More information

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County

Building Permit Application Packet. BUILDING CODES Adopted by La Plata County For Enforcement In The Unincorporated Areas Of La Plata County Building Permit Application Packet The purpose of Building Codes is to establish the minimum requirements to safe guard the public health, safety and general welfare through structural strength, means

More information

Patio Covers / Carports

Patio Covers / Carports Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE) If your home or business is located within a 100-year floodplain and it was constructed through a County Building

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

REQUEST FOR PROPOSAL Historic Structure Report for the Charnley-Persky House, a National Historic Landmark. The Society of Architectural Historians

REQUEST FOR PROPOSAL Historic Structure Report for the Charnley-Persky House, a National Historic Landmark. The Society of Architectural Historians REQUEST FOR PROPOSAL Historic Structure Report for the Charnley-Persky House, a National Historic Landmark 1365 N. Astor Street Chicago, Illinois 60610 Issued July 31, 2015 All inquiries concerning this

More information

Saint Cloud Business Center

Saint Cloud Business Center Saint Cloud Business Center 14 7th Avenue North Saint Cloud, MN 56303 For Sale Located on 7th Avenue in the heart of downtown across from the Court House Square. A large professional reception area with

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

Building Code Clarifications - 7. Fire Resistance

Building Code Clarifications - 7. Fire Resistance Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,

More information

C I T Y O F P E A R S A L L

C I T Y O F P E A R S A L L The Largest City Between San Antonio and Laredo COMMUNITY DEVELOPMENT C I T Y O F P E A R S A L L A Business-Friendly, Family-Oriented Community Building Department Application Information (Please read

More information

The Orange County Farmers Museum Emergency Preparedness Plan

The Orange County Farmers Museum Emergency Preparedness Plan The Orange County Farmers Museum Emergency Preparedness Plan TABLE OF CONTENTS Section Page Introduction. 2 1. Coordination with an Emergency Response Agency. 2 2. Policies of the Board 2 3. Procedures

More information

MOBILE HOME LAW. Revised November 2001

MOBILE HOME LAW. Revised November 2001 MOBILE HOME LAW Revised November 2001 TABLE OF CONTENTS: SECTION 1: SECTION 2: SECTION 3: SECTION 4: SECTION 5: SECTION 6: SECTION 7: SECTION 8: SECTION 9: SECTION 10: SECTION 11: SECTION 12: INTENT DEFINITIONS

More information

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS

MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS COMMERCIAL FIRE SPRINKLER SYSTEMS Page 1-5 SCOPE: Fire sprinkler systems in the City of Mercer Island shall meet the criteria as set forth

More information

Data Center Due Diligence List

Data Center Due Diligence List Data Center Due Diligence List Name and address of site facility Date constructed Building owner/date purchased by current owner Name of previous owner Adjacent Property Descriptions North South East West

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning

ISSUE BRIEF. Understanding the Hospital Planning, Design, and Construction Process. Introduction. Background. Phase 1: Project Definition and Planning Understanding the Hospital Planning, Design, and Construction Process Introduction California s acute care hospitals are an essential health care resource that serve a wide range of patients during times

More information

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following:

July 29, 2014. Revise Section 1.1 (BACKGROUND AND CONTEXT) to the following: ADDENDUM NO. 2 TO REQUEST FOR QUALIFICATIONS FOR NEW DEVELOPMENT OF OAKLAND UNIFIED SCHOOL DISTRICT PROPERTIES, INCLUDING THE PARCELS HOUSING THE PAUL ROBESON ADMINISTRATION BUILDING AND DEWEY HIGH SCHOOL

More information

Terms of Reference. Egypt Post - Several position: Architects, Interior Design, Structure Design, Site Engineer and Electromechanical Design.

Terms of Reference. Egypt Post - Several position: Architects, Interior Design, Structure Design, Site Engineer and Electromechanical Design. Terms of Reference Duty Station: Type of contract: Title: Duration of the contract: Egypt Service Contract (Only Egyptians) Egypt Post - Several position: Architects, Interior Design, Structure Design,

More information

Health Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE

Health Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE Health Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE CHAPTER 420-5-22 SUBMISSION OF PLANS AND SPECIFICATIONS FOR HEALTH CARE FACILITIES TABLE OF

More information

ALABAMA STATE DEPARTMENT OF EDUCATION

ALABAMA STATE DEPARTMENT OF EDUCATION ALABAMA STATE DEPARTMENT OF EDUCATION CONSTRUCTION REQUIREMENTS FOR COUNTY AND CITY PUBLIC SCHOOLS PROJECTS TOTALLY FUNDED WITH LOCAL FUNDS AND SUBMITTAL OF ALL PLANS AND SPECIFICATIONS Thomas R. Bice,

More information

Slavic Village Building Condition Review

Slavic Village Building Condition Review Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities

More information

RESIDENTIAL/COMMERCIAL

RESIDENTIAL/COMMERCIAL RESIDENTIAL/COMMERCIAL CONTRACTOR S INFORMATION MANUAL FOR City of Senatobia Disclaimer The residents or contractors using this information are responsible for complying with the applicable ICC Residential,

More information

SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS

SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS Rebuilding or repairing your home/business after the storm? Adding on, renovating, or remodeling your home/business? Here s information YOU need

More information

PROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)

PROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.) APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of

More information

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW Parcel Number: Owner s Name: Co-Owner s Name: Owner s Mailing Address: Owner Phone Number: FIRM Panel: Lowest Floor Elevation (excluding garage):

More information

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011

Number Northern Arizona University Facility Services Section Page. Effective April 1, 2011 Facility Services Section Page Recharge Services, Maintenance and Construction PURPOSE 1 of 6 The purpose of this policy is to set forth standards for chargeable services for maintenance and construction

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG info@tlhamatsi.co.za CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement

More information

2. What building projects are exempted? (permit not required)

2. What building projects are exempted? (permit not required) BUILDING AND SAFETY DEPARTMENT 1. What building projects require a permit? Following is a list of projects that require building permits based on Appendix chapter 1 of the California Building Code and

More information

www.citiesinspection.com October 5, 2015 Dear Client,

www.citiesinspection.com October 5, 2015 Dear Client, www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.

More information

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Brochure More information from http://www.researchandmarkets.com/reports/2214808/ Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Description: This estimating guide for repair and remodeling

More information

Project Building Permit No. One complete set of Record or as-built drawings (electronic) One complete set of Record or as-built drawings (hard copy)

Project Building Permit No. One complete set of Record or as-built drawings (electronic) One complete set of Record or as-built drawings (hard copy) University at Albany, State University of New York Office of Facilities Management Code Administration Certificate of Occupancy/Compliance Records Checklist On-site Inspection Items Not Included Project

More information

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications

More information

Facility Assessment for. 11801 East Main Street, Huntley, IL

Facility Assessment for. 11801 East Main Street, Huntley, IL Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested

More information

REQUEST FOR ARCHITECTURAL SERVICES (RFS)

REQUEST FOR ARCHITECTURAL SERVICES (RFS) REQUEST FOR ARCHITECTURAL SERVICES (RFS) For the Development of three parcels into affordable housing: Highland Ave Site, 9 Manahan Street in Chelmsford and 173 Carlisle Rd. in Westford CHOICE Inc., an

More information

NUNAVUT HOUSING CORPORATION. Home Repair Program (HRP)

NUNAVUT HOUSING CORPORATION. Home Repair Program (HRP) NUNAVUT HOUSING CORPORATION Home Repair (HRP) October 2014 Home Renovation (HRP) Date October 201 TABLE OF CONTENTS OBJECTIVE... 1 SUMMARY... 1 ENABLING LEGISLATION... 1 ELIGIBLE CLIENTS... 1 PRIORITY

More information

2301.1 Scope: Communications and Electronic Systems addressed in this section include:

2301.1 Scope: Communications and Electronic Systems addressed in this section include: Chapter 23 COMMUNICATIONS / ELECTRONIC SYSTEMS SECTION 2301 - GENERAL 2301.1 Scope: Communications and Electronic Systems addressed in this section include: 1. Fire Alarm System 2. Telecommunication and

More information

FARMERS MUTUAL INSURANCE COMPANY UNDERWRITING GUIDELINES HOMEOWNER PROGRAM

FARMERS MUTUAL INSURANCE COMPANY UNDERWRITING GUIDELINES HOMEOWNER PROGRAM UNDERWRITING GUIDELINES HOMEOWNER PROGRAM The following guidelines should be considered when offering insurance for certain types of risks. When evaluating the acceptability of a risk, the company underwriter

More information

Suffolk County Department of Health Services. Division of Environmental Quality

Suffolk County Department of Health Services. Division of Environmental Quality Suffolk County Department of Health Services Division of Environmental Quality Guidelines For the Construction of Storage Areas for Portable Containers ~~~~ Clare B. Bradley, M.D., M.P.H. Suffolk County

More information

BUSINESS USE PERMIT APPLICATION

BUSINESS USE PERMIT APPLICATION BUSINESS USE PERMIT APPLICATION Instructions and Information for Business Use Permits and Temporary Certificates of Occupancy are included at the end of this application. Planning and Development Services

More information