VISAKH SPM REFINERY PROJECT

Size: px
Start display at page:

Download "VISAKH SPM REFINERY PROJECT"

Transcription

1 VISAKH SPM REFINERY PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA PREPARED FOR HINDUSTAN PETROLEUM CORPORATION LIMITED (HPCL) INTECSEA PROJECT NO :

2 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA TABLE OF CONTENTS 1. INTRODUCTION Objective DISCUSSION, CONCLUSION AND RECOMMENDATION Discussion Conclusion & Recommendation LONG TERM REMEDY General Remedial Action Piled Support for Pipeline... 5 ATTACHMENTS POST DREDGING SURVEY DATA REMEDIAL DETAILS SOIL BOREHOLES (BH-12/R13) DATA Pipeline Remedy Action.doc

3 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA 1. INTRODUCTION Hindustan Petroleum Corporation Limited Visakh Refinery (HPCL-VR) is planning to develop crude unloading facilities to handle a large crude parcel of size about 300,000 MT by VLCC Tankers to meet the crude requirement of their existing as well as future crude processing requirements. HPCL-VR is presently receiving crude at Offshore Tanker Terminal (OSTT) of Visakhapatnam Port Trust (VPT). The tanker size at OSTT is limited by the available water depth of 19m, and can not receive VLCC. HPCL-VR proposes to install Single Point Mooring (SPM) Terminal and connected facilities off the coast of Visakhapatnam Port to receive and offload crude by VLCC tankers. HPCL-VR as part of this project, will install Single Point Mooring (SPM) terminal and related facilities at the water depth of about 35m, at a distance of about 4.0 km from the coast. Crude from SPM will be pumped and transported via 48 inch NB line pipe from SPM to Crude Oil Storage Facility of Indian Strategic Petroleum Reserves LTD (ISPRL) and also will be hooked up to the existing 36 crude oil pipeline to refinery. The offshore section of the pipeline route is about 4.0 km from SPM to LFP (Land Fall Point) and onshore section from LFP to ISPRL is 1.2 km. 1.1 Objective This document presents the long term remedial action proposed for the 260m section of the offshore pipeline route i.e. from Ch150 to Ch410 m wherein the seabed and pipeline profile was noticed to have been changed from the as-built status due to sand dredging activity by Visakhapatnam Port Trust (VPT) in the close vicinity of the 48 HPCL pipeline route. Pipeline Remedy Action.doc

4 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA 2. DISCUSSION, CONCLUSION AND RECOMMENDATION 2.1 Discussion The current situation is due to dredging too close to the pipeline by the Dredger hence removing the soil below the pipeline, allowing pipeline to be vertically displaced and free spanning at few locations. It is understood that the dredging operation has been carried out by Dredging Corporation of India on behalf of VPT using one Hopper Suction Dredger. Some of the soil might have also been removed by the propellers of the dredger. Temporary measures were undertaken immediately to reduce the free spans which were developed due to the removal of sand underneath the pipeline. There were several sand bag supports placed in order to reduce the length of the free spans which occurred due to dredging. Survey of the pipeline profile and the seabed profile was performed before and after placement of the sandbag supports. The survey data had revealed important changes in subsoil and pipeline levels with free spanning of pipeline at some locations which are within the allowable limits. The dredging in the sand trap area is the routine annual activity of VPT. Since 48 crude pipeline is located in very close proximity of sand trap area, permanent solution is considered necessity in order to avoid further increase in pipeline spans and stress levels. A detailed feasibility study was performed to evaluate the possible remedial action that will aim to permanently protect the pipeline from such dredging mishaps on account of slippage of sand support from underneath of the pipeline. The following action was identified as part of the study and the most feasible which is recommended as the way forward for the long term remedial action to permanently protect the pipeline. The remedial action is discussed in detail in Section 3.0 of this report: Remedial Action Piled Support for Pipeline 2.2 Conclusion & Recommendation Conclusion It is concluded that a long term remedial action is required due to the impact of sand trap dredging works on the 48 subsea pipeline to ensure the pipeline is protected during the entire operation life and the pipeline stresses & spans are always within the allowable limits to maintain operability in a safe condition. VPT while discussions on the subject indicated that movement of sand towards the sand trap shall also not get unduly obstructed otherwise it may affect the port operation on long term basis. Pipeline Remedy Action.doc

5 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA Recommendation The following action is recommended which needs to be implemented in consultation with VPT/ CWPRS and IIT Chennai: Remedial Action introducing permanent piled supports for the pipeline at a certain interval in the pipeline section of concern i.e. Ch150 to Ch410 m. Pipeline Remedy Action.doc

6 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA 3. LONG TERM REMEDIAL ACTION 3.1 General Following the sand trap dredging activity by DCI in the month of March 2010, Leighton Contractors (India) Pvt. Ltd. had performed a survey and based on the review of the survey data it is found that the subsoil and pipeline levels have been affected. The bathymetric survey data and cross sections after the sand trap dredging are presented in Appendix A. As part of the short term remedial action, Leighton Contractors have undertaken the following actions for quick support of the pipeline free span sections. a) Conduct full video survey of 48 pipeline and surrounding sea bed, KP 200 through KP 320 (visibility permitting). Pipeline condition to be confirmed as acceptable. b) Provide four nos. of sand bag supports in the region where free spans were found to be more than 20m. c) Conduct full video survey of pipeline confirming (or not) adequate support afforded pipeline at KP s 210, 260 and 320. INTECSEA have also performed the bottom roughness analysis of the section of the pipeline in the sand trap area and the findings concluded that all existing spans along the pipeline route from KP0.0 to KP0.51 are within the allowable span limits. Equivalent stresses also do not exceed the pipeline allowable stresses limits. It is noted that natural backfilling occurs from time to time that fills up the pipeline free spans space and further covers the pipeline in relatively short terms. However, considering the frequency of the dredging works (yearly basis) a long term remedy is required and following is the selected remedial measure to be implemented as the permanent solution. 3.2 Selected Remedial Action Piled Support for Pipeline The selected remedial action is a proposal to provide permanent steel supports for the pipeline at regular intervals along the pipeline section in the proximity of sand trap area. These steel pipeline supports are bolted to the two piles driven adjacent to the pipeline. Please refer to the attachments for details of piles and support. The 48 pipeline shall be supported by a plate connected to a beam which is further held by 2 piles driven into the seabed on either side of the HPCL pipeline. This arrangement will always hold the pipeline in its vertical as well as horizontal alignment even if the dredger removes sand below the pipeline. This also will have minimum restrictions to Pipeline Remedy Action.doc

7 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA sand movement towards the sand trap. In view of all above this action is considered most appropriate. Thus, the piled support for the 48 pipeline is recommended as this action provides an effective solution to protection for the entire pipeline design life. This action also ensures continuous movement of sand towards the sand trap area. The piled support consists of a 12.7mm thick 300mm wide plate supporting the 48 pipeline. This plate shall be connected to a horizontal beam with stiffener plates which will be on top of the pipeline with an acceptable clearance. The beam will be held by means of bolted connections to 2 piles driven into the seabed adjacent to the pipeline on both the sides of pipeline i.e. sand trap side and Dolphin Hill side. The piles to be driven shall be mm thick structural steel. Diagrammatic detail of the remedial action is presented in the attachment of this report. The additional scope of this remedial work (Engineering, Procurement, Construction and Installation EPCI) shall be undertaken under a separate tender package which is planned to be executed before the next dredging season of Feb Pipeline Remedy Action.doc

8 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL ACTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA POST DREDGING SURVEY DATA Pipeline Remedy Action.doc

9

10

11

12

13 XYZ DATA EVERY 5m INTERVAL CHAINAGE EASTING NORTHING SEABED TOP OF PIPE

14 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL WORK OPTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA REMEDIAL OPTION DETAILS Pipeline Remedial Option - ITB.doc

15

16

17 HPCL - VISAKH REFINERY SPM PROJECT LONG TERM REMEDIAL WORK OPTION PROPOSED FOR HPCL SUBSEA PIPELINE AT THE SAND TRAP AREA SOIL BOREHOLES (BH-12/R13) DATA Pipeline Remedial Option - ITB.doc

18

19

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

LNG A Different Approach The Teesside GasPort Project

LNG A Different Approach The Teesside GasPort Project LNG A Different Approach The Teesside GasPort Project Presented to Winter Outlook Seminar by John Baldwin of Gas Strategies and James Ball On behalf of Rob Bryngelson, Executive Vice President and Chief

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

OVERLAND PIPELINE OPTIONS

OVERLAND PIPELINE OPTIONS Working Document of the NPC Study: Arctic Potential: Realizing the Promise of U.S. Arctic Oil and Gas Resources Made Available March 27, 2015 Paper #7-9 OVERLAND PIPELINE OPTIONS Prepared for the Technology

More information

Pipelines and seabed intervention

Pipelines and seabed intervention Workshop on seabed habitats of environmental concern Jørn Spiten Content Pipeline - route design Seabed Intervention - Trenching - Ploughing - Dredging - Rock installation 2 Pipeline routes 3 Pipeline

More information

Offshore Structures. Offshore Drilling Equipment

Offshore Structures. Offshore Drilling Equipment Offshore Structures Offshore Drilling Equipment The drill string is lowered through a conduit (riser). The drill string consists of a drill bit, drill collar and drill pipe. Drill pipe sections are added

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

FINAL REPORT ON SOIL INVESTIGATION

FINAL REPORT ON SOIL INVESTIGATION FINAL REPORT ON SOIL INVESTIGATION FOR PROPOSED CONSTRUCTION AT SS-6B AREA AT HPCL VISAKH REFINERY VISAKHAPATNAM ANDHRA PRADESH J.J. ASSOCIATES(VISAKHAPATNAM) AETP(P) LIMITED #11-6-3, RockDale Layout,

More information

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

More information

Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors

Profile. Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different. Dredging and Marine Contractors Profile Marine ingenuity In just two words, we show what we do, how we do it, and what makes us different Dredging and Marine Contractors Company profile Artemis is one of the most powerful self-propelled

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Mercator Limited. Driven by growth Sustained by values

Mercator Limited. Driven by growth Sustained by values Mercator Limited Group Driven by growth Sustained by values 1 Mercator at a Glance History Incorporated in 1983. Listed on both NSE and BSE Capacity Expansion by more than 1200% since 31 st March 2003

More information

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India

Structural concepts for minimum facility platforms for Marginal field development in western offshore, India Structural concepts for minimum facility platforms for Marginal field development in western offshore, India A collaborative project By IIT Madras and IEOT,ONGC 24 April 2007 1 Outline Conventional Wellhead

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

THE BALTIC SEA OFFSHORE PROJECTS

THE BALTIC SEA OFFSHORE PROJECTS OFFSHORE PROJECTS OFFSHORE PROJECTS 3 OFFSHORE PROJECTS The start of LUKOIL's offshore operations dates back to 1999, when the Company started exploratory drilling with its in-house ASTRA selfelevating

More information

Geotechnical Design Monopile Foundations for Offshore Wind Turbines

Geotechnical Design Monopile Foundations for Offshore Wind Turbines Geotechnical Design Monopile Foundations for Offshore Wind Turbines R.J.N.J. Luiken, Structural specialist Van Oord Dredging and Marine Contractors Copyright Van Oord 2012 1 Content Content - Company profile

More information

The information and materials contained in this disc are provided as is and as available.

The information and materials contained in this disc are provided as is and as available. The information and materials contained in this disc are provided as is and as available. Whilst every effort is made to ensure that the information and materials provided are correct, the Land Transport

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

Söderströmtunnel: immersion in downtown Stockholm, Sweden

Söderströmtunnel: immersion in downtown Stockholm, Sweden Söderströmtunnel: immersion in downtown Stockholm, Sweden J. Glückert Dipl.-Ing, Züblin Ground Engineering, Stuttgart, Germany N.H.J. Vink MSe, M. Reijm BSc, P.T. van Westendorp BSc Strukton Immersion

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

HV Submarine Cable Systems Design, Testing and Installation

HV Submarine Cable Systems Design, Testing and Installation HV Submarine Cable Systems Design, Testing and Installation CIGRE Ireland Technical Seminar 6 th October 2010 Robert Donaghy Senior Consultant Engineer, ESB International Presentation Overview Applications

More information

Horizon Survey and Geotechnical Companies

Horizon Survey and Geotechnical Companies Oil & Gas Directory Middle East - 2013 147 Horizon Survey and Geotechnical Companies Corporate P r ofile OUR PEDIGREE Horizon provides comprehensive survey and geotechnical services to the offshore industry

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan

Triton Knoll Offshore Wind Farm Limited Electrical System. Outline Traffic Management Plan Triton Knoll Offshore Wind Farm Limited Electrical System Outline Traffic Management Plan October 2014 RWE Innogy UK Triton Knoll TMP Copyright 2014 RWE Innogy UK Ltd All pre-existing rights reserved.

More information

Proposed Minimum Subterranean Termite Treatment Standards

Proposed Minimum Subterranean Termite Treatment Standards Proposed Minimum Subterranean Termite Treatment Standards Introduction This document is intended to serve as a model for states considering the adoption of standards for soil application of termiticides.

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS

AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS AN INNOVATIVE SOLUTION FOR FIXED OFFSHORE LNG REGASIFICATION TERMINALS Augusto Bulte Project Manager Foster Wheeler C/Gabriel García Márquez 2 Las Rozas 28232 Madrid (Spain) ABSTRACT Several developments

More information

Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales

Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales www.gov.uk/defra www.wales.gov.uk Consultation on integrating flood defence consents into the Environmental Permitting regime in England and Wales Annex 2; Proposed exclusions Emergencies and licensable

More information

Frequently Asked Transmission Pipeline Questions

Frequently Asked Transmission Pipeline Questions Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).

More information

Prepared and Submitted by

Prepared and Submitted by Technical Feasibility Study Report of Proposed Sulfuric Acid and Phosphoric Acid Unloading Facilities, Acid Storage Tanks at the existing Wharf and Acid Transfer Pipeline Falling within the CRZ area &

More information

Single Point Mooring System (SPM) for an Offshore LNG Terminal

Single Point Mooring System (SPM) for an Offshore LNG Terminal Single Point Mooring System (SPM) for an Offshore LNG Terminal GASTECH 2005, Session 7 - Technical Bilbao, March 15 th, 2005 Max Krekel Senior Naval Architect Bluewater Offshore Production Systems Neal

More information

Enbridge Class Location Change Management Plan. 1.1 Additional Information for Identified Changed Class Locations

Enbridge Class Location Change Management Plan. 1.1 Additional Information for Identified Changed Class Locations Information Request No. 1-1.1 Additional Information for Identified Changed Class Locations Reference: i. (A70936) Preamble: ii. Canadian Standards Association (CSA) Z662-15, Oil and Gas Pipeline Systems

More information

CASE HISTORY #2. APPLICATION: Piping Movement Survey using Permalign Laser Measurement System

CASE HISTORY #2. APPLICATION: Piping Movement Survey using Permalign Laser Measurement System CASE HISTORY #2 APPLICATION: Piping Movement Survey using Permalign Laser Measurement System EQUIPMENT: Dresser-Clark Hot Gas Expander (Turbine), 60-inch Inlet Flange HISTORY: Piping support modifications

More information

Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan

Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan Advanced Natural Gas Storage (ANGAS) Project and Verification Tests of Experimental Lined Rock Cavern in Japan Toru Komatsubara THE JAPAN GAS ASSOCIATION Taku Watanabe TOKYO GAS CO.,LTD. Satoshi Murase

More information

Electric heat tracing

Electric heat tracing PIPELINE DESIGN Figure 1. Shorter, more complex piping at a process plant. Electric heat tracing Neil Malone, Heat Trace, UK, discusses electric heat tracing of long pipelines. In considering electric

More information

Permits to Dig / Permits to Excavate / Permits to work near underground services

Permits to Dig / Permits to Excavate / Permits to work near underground services Permits to Dig / Permits to Excavate / Permits to work near underground services Aim and purpose The aim of this guidance is to identify what should be included in a permit to excavate / dig and additional

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

Optimising plate girder design

Optimising plate girder design Optimising plate girder design NSCC29 R. Abspoel 1 1 Division of structural engineering, Delft University of Technology, Delft, The Netherlands ABSTRACT: In the design of steel plate girders a high degree

More information

OWPST & Titan 200 & UK Offshore

OWPST & Titan 200 & UK Offshore OWPST & Titan 200 & UK Offshore A look at the Company, our Product and the Technology being applied in the UK Offshore Market Introduction Douglas Hines CEO/President Offshore Wind Power Systems of Texas

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Offshore Work Packages

Offshore Work Packages Rampion Offshore Wind Farm Offshore Work Packages Meet The Buyer Naren Mistry, Engineering Manager 26 th Feb 2014 Rampion Offshore Project Scope Design, manufacture, transportation and Installation: Up

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

OFFSHORE FIELD DEVELOPMENT

OFFSHORE FIELD DEVELOPMENT OFFSHORE FIELD DEVELOPMENT OPTIONS & STRATEGY By: Nguyen Ngoc Hoan M.Sc of Petroleum Engineering Hoannn@pidc.com.vn PRESENTATION CONTENT Field Development Consideration Field Development Options & Strategy

More information

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION

ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION ATTACHMENT F ONSHORE PIPELINES DECOMMISSIONING GUIDELINE 1. INTRODUCTION After concession is expired or at the end of its economic life, pipeline network and all associated structures are due for decommissioning

More information

London Array. Operations and Maintenance

London Array. Operations and Maintenance London Array londonarray.com London Array Operations & Maintenance Base Port of Ramsgate Military Road Ramsgate CT11 9LG Registered in England and Wales No 04344423 Operations and Maintenance 1 2 Operations

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

DREDGING IN FIGURES 2011

DREDGING IN FIGURES 2011 DREDGING IN FIGURES 2011 INTERNATIONAL ASSOCIATION OF DREDGING COMPANIES DREDGING IN FIGURES 2011 Dredging in Figures is an annual review of the global dredging market. This document focusses on the situation

More information

Boskalis: at home in the Middle East

Boskalis: at home in the Middle East Boskalis: at home in the Middle East Boskalis Westminster Middle East Ltd ( Boskalis ) has been active in all countries of the Middle East since the Oil States emerged in the early seventies. Dredging

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

PIPELINE INSPECTION UTILIZING ULTRASOUND TECHNOLOGY: ON THE ISSUE OF RESOLUTION By, M. Beller, NDT Systems & Services AG, Stutensee, Germany

PIPELINE INSPECTION UTILIZING ULTRASOUND TECHNOLOGY: ON THE ISSUE OF RESOLUTION By, M. Beller, NDT Systems & Services AG, Stutensee, Germany ABSTRACT: PIPELINE INSPECTION UTILIZING ULTRASOUND TECHNOLOGY: ON THE ISSUE OF RESOLUTION By, M. Beller, NDT Systems & Services AG, Stutensee, Germany Today, in-line inspection tools are used routinely

More information

Final thesis. Feasibility of Chinese offshore market. Hogeschool van Utrecht IHC HOLLAND. Supervisor: Mr R.kok

Final thesis. Feasibility of Chinese offshore market. Hogeschool van Utrecht IHC HOLLAND. Supervisor: Mr R.kok Final thesis Feasibility of Chinese offshore market Hogeschool van Utrecht IHC HOLLAND Supervisor: Mr R.kok Mediatheek HVU 1. INTRODUTION ABSTRACT 1.1 Company profile.........l 1.2 Thesis definition....

More information

Arctic HSE seminar 1. Ice behavior in northern regions, availability and need for metocean & ice data. Paul Verlaan 24 th March 2014

Arctic HSE seminar 1. Ice behavior in northern regions, availability and need for metocean & ice data. Paul Verlaan 24 th March 2014 Arctic HSE seminar 1 Ice behavior in northern regions, availability and need for metocean & ice data. Paul Verlaan 24 th March 2014 DEFINITIONS & CAUTIONARY NOTE Reserves: Our use of the term reserves

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS

SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS SERIES NG 400 SAFETY FENCES, SAFETY BARRIERS AND PEDESTRIAN GUARDRAILS Contents Clause Title Page NG 401 Performance Criteria for Safety Fences and Safety Barriers 2 NG 402 Components for Safety Fences

More information

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05

Dimensional and Structural Data for Elliptical Pipes. PD 26 rev D 21/09/05 Dimensional and Structural Data for Elliptical Pipes 21/09/05 Page 1 of 15 1. Foreword This document details a method for the structural design of Stanton Bonna Elliptical pipes for the common conditions

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

COCHIN PORT TRUST INVITATION EXPRESSION OF INTEREST FOR

COCHIN PORT TRUST INVITATION EXPRESSION OF INTEREST FOR COCHIN PORT TRUST INVITATION EXPRESSION OF INTEREST FOR SETTING UP OF EXPORT ORIENTED OIL REFINERY / OIL TRADING HUB IN THE PROPOSED OUTER HARBOUR OF COCHIN PORT COCHIN PORT TRUST INVITATION EXPRESSION

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

PROPOSAL FOR CONTRACTORS ALL RISKS

PROPOSAL FOR CONTRACTORS ALL RISKS PROPOSAL FOR CONTRACTORS ALL RISKS 1. Title of contract (If project consist of several sections, specify section(s) to be insured) 2. Location of site Country/Province/district City/town/village 3. Name

More information

KIRLOSKAR FIRE FIGHTING PUMPS AND PACKAGES

KIRLOSKAR FIRE FIGHTING PUMPS AND PACKAGES KIRLOSKAR FIRE FIGHTING PUMPS AND PACKAGES PUMPS CONFORMING TO U L R NFPA R TAC KIRLOSKAR BROTHERS LIMITED Kirloskar Brothers Limited, (KBL) the largest manufacturer and exporter of pumps in India is one

More information

CH. 2 LOADS ON BUILDINGS

CH. 2 LOADS ON BUILDINGS CH. 2 LOADS ON BUILDINGS GRAVITY LOADS Dead loads Vertical loads due to weight of building and any permanent equipment Dead loads of structural elements cannot be readily determined b/c weight depends

More information

FUNDAMENTALS OF LANDSCAPE TECHNOLOGY GSD Harvard University Graduate School of Design Department of Landscape Architecture Fall 2006

FUNDAMENTALS OF LANDSCAPE TECHNOLOGY GSD Harvard University Graduate School of Design Department of Landscape Architecture Fall 2006 FUNDAMENTALS OF LANDSCAPE TECHNOLOGY GSD Harvard University Graduate School of Design Department of Landscape Architecture Fall 2006 6106/ M2 BASICS OF GRADING AND SURVEYING Laura Solano, Lecturer Name

More information

QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE

QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE GA Insurance House, Ralph Bunche Road, P O Box 42166-00100 Nairobi, Kenya. Telephone: 2711633 Fax 2714542 E-mail: insure@gakenya.com QUESTIONNAIRE AND PROPOSAL FOR CONTRACTORS ALL RISK INSURANCE AGENT:

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire

More information

BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof.

BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof. BUILDING MATERIALS, Wood, Laminated (Page 1 of 3) Viz.: Rafters; Arches; Beams; Joists; Timbers or Planks, structural or roof. 1155 & 4155 LCL: Applies to all freight in less than container load quantities.

More information

Method Statement for Static Load Testing (Compression) for Micropiles

Method Statement for Static Load Testing (Compression) for Micropiles Method Statement for Static Load Testing (Compression) for Micropiles 1. INTRODUCTION This vertical compression pile maintained load test is usually carried out to ensure the structural and geotechnical

More information

UNLOCKING MAJOR COST SAVINGS ON OIL & GAS PROJECTS

UNLOCKING MAJOR COST SAVINGS ON OIL & GAS PROJECTS UNLOCKING MAJOR COST SAVINGS ON OIL & GAS S $ RESPONDING TO A LOW-PRICE OIL ENVIRONMENT THE BENEFITS OF EARLY INVOLVEMENT: In our experience early involvement on a project is key when it comes to securing

More information

Multisensor Data Integration in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall

Multisensor Data Integration in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall Multisensor Data in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall ESA Oil and Gas Workshop 15/09/2010, Frascati, Italy Satellite Products and Services during a typical O&G project Project Life

More information

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,

More information

Certificate Programs in. Program Requirements

Certificate Programs in. Program Requirements IHRDC Online Certificate Programs in OIL AND GAS MANAGEMENT Program Requirements IHRDC 535 Boylston Street Boston, MA 02116 Tel: 1-617-536-0202 Email: certificate@ihrdc.com Copyright International Human

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Mersin, TURKEY. Port extension project

Mersin, TURKEY. Port extension project Mersin, TURKEY Port extension project Mersin is situated on the Mediterranean Sea, on the southeast coast of Turkey. Several international contracting companies were invited to bid for the upgrading of

More information

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS

2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS 2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include

More information

Drew University Ladder Safety Program Policy and Inspection Procedure Draft 0412

Drew University Ladder Safety Program Policy and Inspection Procedure Draft 0412 PURPOSE To establish and define the procedures to ensure that ladders at Drew University are installed, used, inspected and maintained in accordance with applicable standards. REFERENCES OSHA Portable

More information

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since. Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since. Liftech is the structural review engineer of record for most

More information

COMPANY PRESENTATION

COMPANY PRESENTATION Engineering and Construction Ltd. Co. COMPANY PRESENTATION Contents Preface 3 Quality Policy 5 Health and Safety Policy 6 Environmental Policy 7 Examples from our Consultation Services 8 Superstructural

More information

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long

More information

Communication Links for Offshore Platforms. A User s Guide to Troposcatter Communications

Communication Links for Offshore Platforms. A User s Guide to Troposcatter Communications Communication Links for Offshore Platforms A User s Guide to Troposcatter Communications 1.0 INTRODUCTION Offshore platforms, whether for coastal defense systems, environmental monitoring, pipe line operations,

More information

Final Australia's Emergency Liquid Fuel Stockholding Update 2013: Oil Storage Options & Costs

Final Australia's Emergency Liquid Fuel Stockholding Update 2013: Oil Storage Options & Costs Auxiliary Report Final Australia's Emergency Liquid Fuel Stockholding Update 2013: Oil Storage Options & Costs Prepared for the Department of Industry, Canberra 22 October 2013 This report was produced

More information

OPERATIONAL LIMITATIONS DUE TO COMPLIANCE WITH THE JONES ACT

OPERATIONAL LIMITATIONS DUE TO COMPLIANCE WITH THE JONES ACT Working Document of the NPC Study: Arctic Potential: Realizing the Promise of U.S. Arctic Oil and Gas Resources Made Available March 27, 2015 Paper #7-5 OPERATIONAL LIMITATIONS DUE TO COMPLIANCE WITH THE

More information

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

Annex IV of MARPOL 73/78. Regulations for the Prevention of Pollution by Sewage from Ships

Annex IV of MARPOL 73/78. Regulations for the Prevention of Pollution by Sewage from Ships Annex IV of MARPOL 73/78 Regulations for the Prevention of Pollution by Sewage from Ships Annex IV of MARPOL 73/78* Regulations for the Prevention of Pollution by Sewage from Ships Regulation 1 Definitions

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

Handling, Erection and Bracing of Wood Trusses

Handling, Erection and Bracing of Wood Trusses Handling, Erection and Bracing of Wood Trusses Follow these guidelines for safe installation of Wood Trusses. These guidelines should not be considered to be the only method for erecting and bracing of

More information

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR

LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR LARGE DIAMETER PIPELINE INNOVATIVE FAST TRACKED REPAIR ABSTRACT Phil Hubbard, P.E., HRSD Paul Wilson, P.E., Brown and Caldwell* Mark Harber, P.E., Brown and Caldwell *301 Bendix Road, Suite 400 Virginia

More information

PART 4: SITE INFORMATION

PART 4: SITE INFORMATION TRANSNET PIPELINES TENDER NUMBER: PYP/W1/6/21/1646 DESCRIPTION OF THE WORKS: CONSTRUCTION OF THE FIRE PROTECTION SYSTEM UPGRADE FOR THE FUEL HANDLING AREAS OF THE TARLTON DEPOT AND IRP REFRACTIONATOR ONLY

More information

Marine Transportation of Compressed Natural Gas

Marine Transportation of Compressed Natural Gas Marine Transportation of Compressed Natural Gas Omid Shakeri, Aghil Barati Iranian Fuel Conservation Organization (IFCO), September 26-27, 2009, The 3rd Iran Gas Forum Introduction Natural gas is rapidly

More information