Research on the System Construction of the Railway Enterprise Project Contract Management

Size: px
Start display at page:

Download "Research on the System Construction of the Railway Enterprise Project Contract Management"

Transcription

1 doi: /ijmser Research on the System Construction of the Railway Enterprise Project Contract Management Qin Yebin Economics and Management School of Wuhan University, Wuhan , Hubei, China Abstract Contract management is the core of project management in the railway construction. It s particularly important to strengthen the construction of railway project contract management. In order to construct the contract management system of railway enterprise in our country, this paper makes some suggestions on the basis of in-depth analysis current situation of contract management of railway enterprise, such as establishing a sound system of contract management system, making the contract management stylized, staying whole process tracking management, attaching great importance to personnel training in contract management, and improving employees' comprehensive quality. Keywords Contract Management; System Construction; Procedural Work; Personnel Training Introduction In the railway engineering construction of our country, whether it is a new or renovative project, it should be a system engineering, which concludes characteristics of capital-intensive, long construction cycle, complex environment, a lot of construction risk and so on. Starting from the investment decision to the stages of the operation, every aspect of the railway construction project involves the signing and implementation of the contracts of the construction projects. Once the contract appears minor errors, it is likely to cause significant economic losses to the enterprise, so to strengthen the contract management is an important measures, which can make the railway enterprise guard against legal risks, reduce economic disputes, and improve the economic benefit. To ensure contracts standardization and promote long-term healthy development of the railway companies, railway companies should strengthen contract management, and construct a contract management system with its own characteristics. Contract Management Contract for construction project refers to an economic contract, in which the project development, survey, design, construction, material supply and other units are signed to accomplish a certain number of construction engineering tasks. Its content includes the conclusion, performance, alteration, termination and dispute resolution of the construction contract, business contract, subcontract, lease contract, loan contract and so on. In the process of railway project construction, the construction progress, the quality and cost of each new project or renovation project determines the speed of the recovery of funds, products own life cycle and corporate profit margins. While the performance of the contract determines the Project price, time and quality and specifies the responsibilities, rights and interests between the parties, the enterprise can control the construction progress of the project, quality and cost to a certain extent. Therefore, contract management is the core of the project management. Different from the industrial enterprises, companies have their own characteristics on contract management railway: a) It has long project duration, big project quantity, high price. In this process, contract is a continuous and uninterrupted, which starts from the planning contract until the contract is completed. Contract management has a direct impact on the implementation of the project investment cost and budgets. A tiny 38

2 International Journal of Management Science and Engineering Research Volume 2, Issue 2, deviation can cause significant investment losses. b) The work of the contract management is extremely complex and cumbersome. The contract types of Railway enterprise involve passenger and cargo transport and dealing, contracting, engineering, construction, technology, investment, loan guarantees, leasing, commission and other contracts. A large number of the signed types, big quantity, complex contract conditions, plenty of contract terms and contract documents, require the high engineering technology and quality standards of the railway enterprise, and also require the appropriate level of technical management on the contract implementation to be higher. Implementation of the contract must be timely adjusted according to actual changes in the construction, so the contract management must be dynamic, the efforts of contract control and change management need to be continuously strengthened. c) Contract management involves multiple units. Railway enterprise contract type are various, and it involve multiple business units such as the main contractor, subcontractors, material suppliers, equipment suppliers, design units, supervision units, transport units and insurance companies more than a dozen or even dozens. And because the dynamic performance of the contract in the contract process changes a lot, contract management not only ensures the legitimate rights and interests of the railway companies, but also ensures the legitimate rights and interests of the participating units and cooperative unit. d) Contract implementation process is complex, and it is difficult to execute the contract management. Throughout the process of the contract from planning to the end, the contract implementation contains contracts documents for acquisition and processing, contracts proper execution, handle and waiting of the contract disputes, and a little negligence will lead to direct economic losses. In engineering process, the various contract documents and range relevant information lead to a certain degree of difficulty on the work of obtain them timely, handle them seriously and preserve them properly. And contract management involves a number of units. To overally coordinate and manage the perform acts of these units and ensure their legitimate rights and interests, the enterprise has to pay a certain amount of manpower, material and financial resources so that the smooth implementation of the contract can be ensured. Meanwhile, with the increasing of contract disputes in recent years, the railway companies need to enhance human rights awareness, and ensure that their rights are not violated. These factors have determined that the difficulty of railway enterprise contract management to achieve a comprehensive, systematic, dynamic scientific management can t be imagined. Situation Analysis on the Project Contract Management of Railway Enterprise Railway construction enterprise projects contract has large bid amount, which involves a wide law range; and respect and relationships involved are many and complex. Only clearly to write down the complex relationships and responsibilities between the parties and regulate the behavior of all parties by the contract management can the project success be ensured. For our current situation, the important role of contract management is far from widespread attention and management level is uneven, although our country also has a series of regulations to emphasize according to contract to manage the project, but the reality is still poor. First, the contract management system is not perfect. At present, the railway enterprise contract management system has been established, but still not perfect. And managers consciousness of controlling the entire process of contract management is seriously enough. All of these leads to extensive contract management. On the one hand, railway enterprises generally lack the appropriate management system or there are loopholes in contract management system, and enterprise can t take effective management on the contract; on the other hand, many companies do not realize the dynamics of contract management, so that it is difficult to control risk throughout all aspects and entire process of contract management, achieve full control, full management, overall grasp of the whole process of the contract management, resulting in frequent occurrence of contractual risk accidents. At the same time, management institutions are not perfect, responsibilities and rights system are not clear, contract risk prevention system is not complete, these lead to the difficulty to ensure layers control on the contract management. Unreasonable contract management system is difficult to effectively control contract legal risk from the source, and restricted the long-term healthy development of the railway companies to some extent, so railway companies of our country urgently need to improve contract management system of construction project. 39

3 Second, the contract management system implementation does not reach the designated position, the whole process control consciousness is not strong. At present, railway enterprise has established a contract management system, but due to lack of knowledge of literacy education on the contract law, insufficient promotion and implementation of the contract management system, inadequate execution of the assessment and accountability system on contract management and so on, especially the lack of the attention to controlling the whole process of contract management, there comes lots of problems, including the corporate staff s weak legal awareness, less attention to the contract and unawareness about the contents of the contract management system, ineffective reaching of contract management system implementation to the designated position, and the existence of the phenomenon,that is, signing a contract without observing contract management system is often occurred. Third, the enterprise management personnel is lack of legal consciousness, and their comprehensive quality is not high. Parts of the railway enterprise managers are accustomed to the old planned economy management mode, and do not set up the concept of contract and legal consciousness performing the contract strictly. Meanwhile, part organ of railway administrations and stations' management personnel lack knowledge of the contract and the relationship of the market with the contract, the contract and contract management, which result in the poor quality of contract management and the weak contract risk awareness. At present, the contract management personnel's overall quality is not high, especially the legal quality is low, which has become one of the main obstacles to improve the railway enterprise contract management. Fourth, the professional contract management personnel is absolutely starved for talent. Contract management is a professional, highly technical requirements work, and it need high-quality talent to assume this task, who is able to grasp the overall situation. Contract management personnel should not only be familiar with legal knowledge, but also be proficient in the operation of the project. However, in reality the railway enterprise legal affairs administration is equipped with legal counsel focuses on the Railway Bureau, and the proportion of professional contract management personnel is extremely low in the establishments, so that the force of law is very weak in basic units. The most prominent contradiction is at the basic units, due to the staff s lack of appropriate legal knowledge and professional practice, they are unable to participate credit investigation contract negotiations, drafting, signing, perform and other work in the whole process, and then it is difficult to make management work on contract effective and strict and it even has some adverse effects on project quality, construction progress and project costs, or may leads to more serious loss of control of project management. Establish and Improve the Railway Enterprise Contract Management System Combined with the present situation of the railway enterprise contract management, from the perspective of railway project management within the enterprise, the enterprise should pay attention to the contract management, improve the contract management system, ensure the implementation of contract signing (advance prevention), the contract performance (in-process control), contract disputes (remedial), attach importance to talent cultivation on contract management, improve the overall quality of staff, construct the contract management system with its own characteristics, and enhance the level of legal risk management on contracts. Improve the Contract Management System Contract management system is an important condition for institutionalized, standardization and legalization of the contract management. On the one hand, railway enterprise shall be in accordance with relevant laws and regulations to guide enterprises to improve the effective contract management system and the operational procedures, improve the cooperation constraints accountability mechanisms between the various departments within the enterprise, and form a more complete contract management system. Through the management standard to strengthen execution of management system to achieve the clear management level, clear responsibilities and program specification in the managing process, the enterprise can avoid companies suffered economic losses when the contract is in the signing, performance or change, then make the contract signing, performance, disputes, assessment and other in the effective control state. Achieve the Procedural Contract Management and Track Management of the Whole Process The entire document (with the exception of setting Level-1 headings in Arial Black) should be in Palatino Linotype 40

4 International Journal of Management Science and Engineering Research Volume 2, Issue 2, font. Type 3 fonts must not be used. Other font types may be used if needed for special purposes. Working the contract management programmed is in favor of the contract and the contract analysis file to reach the responsible person, achieve the implementation of the management on each contract, and clear the powers stipulated in the contract and so on. Thus the enterprise can implement the tracking and diagnosis to the project, control the project schedule, cost and quality, then ensure the execution and the implementation of the contract management system, and make the contract management system continuously improve and perfect further in the operation process. a) Contract signing. Each work is put in place to ensure the contract signing process mainly from the following aspects of the control. The first is the contract subject management, which must strictly examine the main contract signing qualifications, qualifications, reputation and economic status. The second is the text management of the contract. Enterprises regards engineering contracts as a crucial part, and the completeness and applicability of the contract text is essential. The third is the contract triage management. After the contract text is drafted, the contract review process should be fulfilled, then consult and modify in accord with the advice which is solicited by the business, plan, finance, and contract management units to ensure that funding sources of the contract is implement, the contract is legal, and there is no legal risk in the contractual terms. The fourth is the official seal management of the contract. Foreign contracts, should use contract official seal, and execute commissioner management and the registration system based on the system content. b) Contract performance. Each work is put in place to ensure the contract performance process mainly from the following aspects of the control. The first is disclosure of the contract. The contracts contractor sector and contractors should be carried out comprehensive disclosure for all contracts, and all of the contract shall be in the form combined with meeting and reading report to introduce problems to participants that what should be paid attention to in the contract performance. Then breaking down the responsibility of the contract, and fulfilling functional departments and individuals concretely. The second is the full implementation of the contract. In addition to tracking contract contractors and supervise the contract, the contract management staff should also supervise and inspect the performance of the contract. We can learn the fulfillment of the contract through monitoring, detect the problems affecting the contract performance, take timely and effective measures to solve the problem, remove the obstacles, and prevent the occurrence of default. The third is the contract s file management, contract files cover the original contract, the supplementary agreement, meeting minutes and contract form, etc., and the storage contracts file should follow the principle of timely filed, scientific classification, complete custody. c) Contract disputes. When contract disputes occur, the contract contractor, departments and contractors should promptly report to the unit leaders and contract management agency, and determine the response the principle of equality and mutual benefit and seeking truth from facts rather than simply ignorance. If the situation is complex, we should promptly consult with legal staff strive and then consult with adversary to solve it. When negotiations fail in the resolution process of contract dispute between the parties, we should apply for arbitration or bring a lawsuit to the people's court proceeds from safeguarding the legitimate rights and interests of enterprises. Maximize the Personnel Training and Improve Employees' Comprehensive Quality Contract management is a highly professional work, and it requires the contract management personnel to be equipped with appropriate professional quality and legal awareness. At present, more efficient method mainly has the following three functions which can improve the overall quality of contract management staff of the railway enterprise. a) Strengthen recruitment and training of the special talent on the contract management. Contract managers should be transferred between the person who possesses high quality, learning ability, extensive knowledge and strong sense of responsibility, and before induction he should pass the examination and professional training of the railway organization. b) Enhance the overall quality and legal awareness of employees. According to business and market practice, the railway enterprise should organize on-the-job learning of the contract management staff, improve contract management personnel's responsibility consciousness, and strengthen training and assessment of 41

5 the relevant personnel. Then perfect the certificates system, and let them increased their business level, carries on education of professional ethics and legal knowledge, and improve the legal consciousness of the contract. c) Establish incentive mechanism. The railway enterprise should establish and improve the mechanism of job competition and incentive mechanisms, clear the responsibilities, rights and interests of contract management staff, and inspect, assess and evaluate the work of the various departments of enterprises, units of the contract management and operational staff according to contract management assessment and reward system. Finally, honors will be given to recognition and reward; for persons with poor performance, notice of criticism, and economic sanctions must be given depending on the seriousness. Conclusions Contract management is the basic work of enterprise management, which always runs through the whole process and all aspects of project construction, and it can control the entire project management, while controlling and ensuring the implementation and investment of the project. In order to improve the level of contract management of railway enterprise, the railway enterprise should try its utmost to construct the normative contract management system, ensure the implementation of contract signing (advance prevention), the contract performance (in-process control), contract disputes (remedial), attach importance to talent cultivation on contract management, improve the overall quality of staff, construct the contract management system with its own characteristics, and enhance the level of legal risk management on contracts. REFERENCES [1] Wu Ruobing. Problems and Countermeasures of Railway enterprise contract management, Railway Economics Research, No.4,pp.38-40,2004. [2] Cao Shuli. Research on the Problems of the Contract Management in Railway Engineering, Engineering and Technology Research,No.8,pp ,2012. [3] Zhou Jianrong. Research on railway engineering contract management, Shanxi Architecture,Vol.36,No.9,pp ,2010. [4] Guan Xiaowei. Contract management of the project in the realty development enterprises, Shanxi Architecture,Vol.34,No.11,pp ,2008. [5] Wen Yanping. system construction of the project contract management in the real estate enterprise, Management,No.3,pp.64-65,2004. [6] Shao Xianpeng. Research on the problems and countermeasures of Railway enterprise contract management, Law System Development,No.1,pp.78-81,2010. [7] Hu Pinghai. Think of contract management in the railway enterprise, Railway transport and Econmy,Vol.29,No.12,pp.74-76,2007. [8] Ruan Guanhua. Introduction on strengthening railway enterprise contract Management, Manager Journal,No.7,pp. 98,2015. Qin Yebin (1973- ) is a MBA in Economics and Management School of Wuhan University. His primary interests are project management. 42

Regulation on Credit Reporting Industry

Regulation on Credit Reporting Industry Translated from Chinese Order of the State Council (No. 631) The Regulation on the Credit Reporting Industry, as adopted at the 228th session of the executive meeting of the State Council on December 26,

More information

Research on Practical Teaching for Human Resource Management Major. Chenlei Mao

Research on Practical Teaching for Human Resource Management Major. Chenlei Mao 3rd International Conference on Management, Education, Information and Control (MEICI 2015) Research on Practical Teaching for Human Resource Management Major Chenlei Mao Jiangxi University of Technology,

More information

Client Contracts: Business Risk, Professional Liability & Insurance Coverage

Client Contracts: Business Risk, Professional Liability & Insurance Coverage Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design

More information

On protection of employee rights and interests in management of tourist hotel in China

On protection of employee rights and interests in management of tourist hotel in China SHS Web of Conferences 24, 01 017 (2016) DOI: 10.1051/ shsconf/20162401017 C Owned by the authors, published by EDP Sciences, 2016 On protection of employee rights and interests in management of tourist

More information

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

CONTRACTOR DEFAULT & SURETY PERFORMANCE: CONTRACTOR DEFAULT & SURETY PERFORMANCE: A PRACTICAL GUIDE FOR UNDERSTANDING AND NAVIGATING A BOND DEFAULT SITUATION TEXAS CITY ATTORNEYS ASSOCIATION SUMMER CONFERENCE JUNE 9-11, 2010 SOUTH PADRE ISLAND,

More information

The Law of Energy Management Contract

The Law of Energy Management Contract The Law of Energy Management Contract ZHANG Yudong School of Economic and Trade law, Shandong University of political science and law, China, 250014 zhangyudongde@yahoo.com.cn Abstract: Introducing the

More information

The promotion of entrepreneurship and employment work of college students by communist youth league

The promotion of entrepreneurship and employment work of college students by communist youth league Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(7):883-887 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 The promotion of entrepreneurship and employment

More information

GUIDANCE FOR MANAGING THIRD-PARTY RISK

GUIDANCE FOR MANAGING THIRD-PARTY RISK GUIDANCE FOR MANAGING THIRD-PARTY RISK Introduction An institution s board of directors and senior management are ultimately responsible for managing activities conducted through third-party relationships,

More information

Incentive paradox analysis in the process of applied talents training of private colleges

Incentive paradox analysis in the process of applied talents training of private colleges SHS Web of Conferences 24, 02008 (2016) DOI: 10.1051/ shsconf/20162402008 C Owned by the authors, published by EDP Sciences, 2016 Incentive paradox analysis in the process of applied talents training of

More information

Effects and Countermeasures of Replacing Business Tax with VAT to Real Estate Industry

Effects and Countermeasures of Replacing Business Tax with VAT to Real Estate Industry Modern Economy, 2016, 7, 586-590 Published Online May 2016 in SciRes. http://www.scirp.org/journal/me http://dx.doi.org/10.4236/me.2016.75064 Effects and Countermeasures of Replacing Business Tax with

More information

Research on Construction Surety Bond Types in Land Consolidation in China

Research on Construction Surety Bond Types in Land Consolidation in China Research on Construction Surety Bond Types in Land Consolidation in China ZHANG Pengtao 1, WANG Lixiang 2 1 College of Rural and Urban Construction, Agricultural University of Hebei, Baoding, Hebei, P.

More information

PRINCIPLES OF BANKING ETHICS (*)

PRINCIPLES OF BANKING ETHICS (*) 1 THE BANKS ASSOCIATION OF TURKEY PRINCIPLES OF BANKING ETHICS (*) I. Introduction: Ethics can be defined as a system of criteria and measures examining the values, norms and rules underlying the individual

More information

Reinforcement of Safety Awareness Training to Construction Workers in Subcontracted Enterprises

Reinforcement of Safety Awareness Training to Construction Workers in Subcontracted Enterprises Reinforcement of Safety Awareness Training to Construction Workers in Subcontracted Enterprises Qing Fengshou School of Management of Shanghai University of Engineering Science Songjiang University Town

More information

Technology Transfer Principle & Strategy

Technology Transfer Principle & Strategy Technology Transfer Principle & Strategy Chapter 1: The Fundamental Principle & Strategy of Technology Transfer Understanding the necessity of technology transfer & the importance of technology outsourcing

More information

Analysis of Development Causes and Risk Prevention to Logistics Financing

Analysis of Development Causes and Risk Prevention to Logistics Financing Analysis of Development Causes and Risk Prevention to Logistics Financing SHUAI Bin 1, YAN Ying 2 1. School of Traffic and Transp., Southwest Jiaotong University, Chengdu 610031, China 2. School of Logistics,

More information

A Study of the Application of Supply Chain Management in Construction Industry

A Study of the Application of Supply Chain Management in Construction Industry Association for Information Systems AIS Electronic Library (AISeL) WHICEB 2013 Proceedings Wuhan International Conference on e-business 5-25-2013 A Study of the Application of Supply Chain Management in

More information

Reflections on the Internal Operating Mechanism of Scientific and Technological Innovation of Colleges

Reflections on the Internal Operating Mechanism of Scientific and Technological Innovation of Colleges Reflections on the Internal Operating Mechanism of Scientific and Technological Innovation of Colleges SUN Yan Henan Polytechnic University, Jiaozuo, Henan, China, 454003 sunyanyj@hpu.edu.cn Abstract:With

More information

OUTSOURCING GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS, 2008

OUTSOURCING GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS, 2008 OUTSOURCING GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS, 2008 BANK OF TANZANIA PART I PRELIMINARY 1 These guidelines may be cited as the Outsourcing Guidelines for Banks and Financial Institutions,

More information

MODEL STANDARDS OF CONDUCT

MODEL STANDARDS OF CONDUCT MODEL STANDARDS OF CONDUCT FOR MEDIATORS AMERICAN ARBITRATION ASSOCIATION (ADOPTED SEPTEMBER 8, 2005) AMERICAN BAR ASSOCIATION (APPROVED BY THE ABA HOUSE OF DELEGATES AUGUST 9, 2005) ASSOCIATION FOR CONFLICT

More information

APEC General Elements of Effective Voluntary Corporate Compliance Programs

APEC General Elements of Effective Voluntary Corporate Compliance Programs 2014/CSOM/041 Agenda Item: 3 APEC General Elements of Effective Voluntary Corporate Compliance Programs Purpose: Consideration Submitted by: United States Concluding Senior Officials Meeting Beijing, China

More information

Credit risk management of commercial bank

Credit risk management of commercial bank Available online www.jocpr.com Journal of Chemical and Pharmaceutical Research, 2014, 6(5):1784-1788 Research Article ISSN : 0975-7384 CODEN(USA) : JCPRC5 Credit risk management of commercial bank Qian

More information

Current Situation and Development Trend of Applied Linguistics Fang Li

Current Situation and Development Trend of Applied Linguistics Fang Li International Conference on Education Technology and Social Science (ICETSS 2014) Current Situation and Development Trend of Applied Linguistics Fang Li Zhengzhou Vocational College of Industrial Safety

More information

THE RISKS OF OUTSOURCING TRANSPORT FUNCTIONS IN RELATIONS BETWEEN THE COOPERATION FIRMS

THE RISKS OF OUTSOURCING TRANSPORT FUNCTIONS IN RELATIONS BETWEEN THE COOPERATION FIRMS 274 656.96 THE RISKS OF OUTSOURCING TRANSPORT FUNCTIONS IN RELATIONS BETWEEN THE COOPERATION FIRMS Paweł Romanow, Professor, Doctor of Philoso hy, Poznan School of Logistics, Poznan, Poland Abstract. The

More information

Research on Risks and Strategies of Enterprise s HR Management Outsourcing

Research on Risks and Strategies of Enterprise s HR Management Outsourcing Research on Risks and Strategies of Enterprise s HR Management Outsourcing LI Huiyan,2, WANG Shuen 2 School of Management, Shenyang University of Technology, P.R.China, 24 2 School of Management, Tianjin

More information

The Leadership Pipeline Ram Charan, Stephen Drotter, and James Noel

The Leadership Pipeline Ram Charan, Stephen Drotter, and James Noel The Big Idea The Leadership Pipeline Ram Charan, Stephen Drotter, and James Noel There is a growing need to develop leaders within many corporations. The demand for leaders greatly outpaces the supply.

More information

The ABC Wind Power Station Construction Project Management Performance Study. 15356-Project Performance Improvement

The ABC Wind Power Station Construction Project Management Performance Study. 15356-Project Performance Improvement The ABC Wind Power Station Construction Management Performance Study 15356- Performance Improvement Yi Gao 11672096 16-06-2014 Abstract At the present, there are too many academic researches concentrated

More information

LOGGING SUBCONTRACT. Recital

LOGGING SUBCONTRACT. Recital LOGGING SUBCONTRACT This Logging Contract (this Contract ) is entered as of the day of, 200, by and between ("Contractor") and ("Subcontractor") as follows: Recital The owners of certain timber growing

More information

CODE OF ETHICS. CARLO GAVAZZI IMPIANTI S.p.A

CODE OF ETHICS. CARLO GAVAZZI IMPIANTI S.p.A CODE OF ETHICS CARLO GAVAZZI IMPIANTI S.p.A Doc. OR-050-P Version 1 of 27.02.2009 Date: 27.02.2009 Page 1 of 10 CONTENTS 1.0 INTRODUCTION 2.0 ADOPTION OF THE CODE OF ETHICS BY CARLO GAVAZZI IMPIANTI S.p.A.

More information

Provisional Measures for Construction Project Management

Provisional Measures for Construction Project Management Provisional Measures for Construction Project Management Article 1 Article 2 Purpose and Basis This Provisional Measure is promulgated in accordance with relevant Chinese laws and administrative regulations

More information

Notice of the China Banking Regulatory Commission (CBRC) and the National Development and Reform Commission (NDRC) on Issuing the

Notice of the China Banking Regulatory Commission (CBRC) and the National Development and Reform Commission (NDRC) on Issuing the Notice of the China Banking Regulatory Commission (CBRC) and the National Development and Reform Commission (NDRC) on Issuing the Energy Efficiency Credit Guidelines CBRC (2015) No.2 CBRC local offices,

More information

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of

Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of TM Document A101 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum GENERAL INFORMATION Purpose. AIA Document A101 2007 is intended

More information

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES

PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES PROCUREMENT PRACTICES AT PUBLIC HOUSING AGENCIES Table of Contents Procurement Regulations and Agency 3 Procurement Policies and Procedures 3 Roles and Responsibilities 4 Board of Commissioners 4 Sample

More information

BCS, The Chartered Institute for IT Consultation Response to:

BCS, The Chartered Institute for IT Consultation Response to: BCS, The Chartered Institute for IT Consultation Response to: A Comprehensive Approach to Personal Data Protection in the European Union Dated: 15 January 2011 BCS The Chartered Institute for IT First

More information

Kobe Steel, Ltd. Corporate Code of Ethics. Corporate Ethical Principles

Kobe Steel, Ltd. Corporate Code of Ethics. Corporate Ethical Principles This is an English translation of the Corporate Code of Ethics originally published in Japanese. Kobe Steel, Ltd. Corporate Code of Ethics Formulated in June 2000 Amended in April 2008 Corporate Ethical

More information

Construction Contract

Construction Contract Construction Contract Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS IS A MODEL DOCUMENT FOR USE IN RENOVATION OR CONSTRUCTION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND IS

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

Quality & Safety Manual

Quality & Safety Manual Purpose: This Quality & Safety Manual is intended to clarify and document the Quality and Health & Safety policies of GGS Oil and Gas Systems and to describe how the organization organizes its activities

More information

Causes, Effects and Minimization of Delays in Construction Projects

Causes, Effects and Minimization of Delays in Construction Projects Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi

More information

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004

Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 Guidelines for Financial Institutions Outsourcing of Business Activities, Functions, and Processes Date: July 2004 1. INTRODUCTION Financial institutions outsource business activities, functions and processes

More information

Reasons for Change Orders

Reasons for Change Orders T E X A S D E PA R T M E N T O F T R A N S P O R TAT I O N A change order is defined in the 2004 Standard Specification Book as a written order to the Contractor detailing changes to the specified work,

More information

GUIDELINES FOR FORENSIC LABORATORY MANAGEMENT PRACTICES INTRODUCTION

GUIDELINES FOR FORENSIC LABORATORY MANAGEMENT PRACTICES INTRODUCTION GUIDELINES FOR FORENSIC LABORATORY MANAGEMENT PRACTICES INTRODUCTION The American Society of Crime Laboratory Directors is a professional organization of managers and supervisors employed in forensic laboratories.

More information

Development of a vocational college course on metro service telephone communication system maintenance based on work process

Development of a vocational college course on metro service telephone communication system maintenance based on work process World Transactions on Engineering and Technology Education Vol.12, No.2, 2014 2014 WIETE Development of a vocational college course on metro service telephone communication system maintenance based on

More information

Small Joint-stock Commercial Bank Lending to Small Business Risk Analysis

Small Joint-stock Commercial Bank Lending to Small Business Risk Analysis Small Joint-stock Commercial Bank Lending to Small Business Risk Analysis WANG Shuying, YAN Chao School of Management, Zhengzhou University, P.R.China, 450001 yanmaohou@yahoo.com.cn Abstract: in China

More information

Comparative Study on Quality Assurance of Construction Project in Taiwan and Japan

Comparative Study on Quality Assurance of Construction Project in Taiwan and Japan Comparative Study on Quality Assurance of Project in Taiwan and Japan Tsung Chieh, T. National Yunlin University of Science & Technology, Taiwan (email: tctsai@ce.yuntech.edu.tw) Furusaka, S. Kyoto University,

More information

Consumers, Contractors, and Contracts

Consumers, Contractors, and Contracts Consumers, Contractors, and Contracts Hawaii Contractors License Board Protecting the public interest under the law... Your Contractor Checklist In the planning of work, during the progress of work, and

More information

2.2 Stipulations deviating from these conditions must be agreed in writing.

2.2 Stipulations deviating from these conditions must be agreed in writing. GENERAL PURCHASE CONDITIONS OF THE MEMBERS OF THE NEDERLANDSE VERENIGING VAN ZIEKENHUIZEN [NETHERLANDS ASSOCIATION OF HOSPITALS], ARCARES, GGZ NEDERLAND AND THE VERENIGING GEHANDICAPTENZORG NEDERLAND [ASSOCIATION

More information

Research on Tech SME Intellectual Property Innovation Mode

Research on Tech SME Intellectual Property Innovation Mode International Business and Management Vol. 6, No. 2, 2013, pp. 57-63 DOI:10.3968/j.ibm.1923842820130602.1030 ISSN 1923-841X [Print] ISSN 1923-8428 [Online] www.cscanada.net www.cscanada.org Research on

More information

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication.

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication. SUSTAINABILITY POLICY AND COMMUNICATION GUIDELINES Why communicate about sustainability? IFU encourages all our investments to be transparent and informative about business and sustainability performance

More information

Small and Medium-Sized Enterprise Human Resources Management Outsourcing Feasibility Study in China

Small and Medium-Sized Enterprise Human Resources Management Outsourcing Feasibility Study in China International Journal of Business and Social Science Vol. 5, No. 7; June 2014 Small and Medium-Sized Enterprise Human Resources Management Outsourcing Feasibility Study in China Hepeng School of Management

More information

The Analysis on Employability Gap of Students in China Vocational-Technical School and Its Causes

The Analysis on Employability Gap of Students in China Vocational-Technical School and Its Causes The Analysis on Employability Gap of Students in China Vocational-Technical School and Its Causes WANG Ting Business School of China University of Political Science and Law, Beijing, P.R.China, 102249

More information

Samsung Engineering Co., Ltd.

Samsung Engineering Co., Ltd. Introduction to Our Compliance Program Samsung Engineering Co., Ltd. 500 Samsung GEC, Sangil-dong, Gangdong-gu, Seoul, Korea 134-090 +82-2-2053-3000 www.samsungengineering.com 03 Since its establishment

More information

The Second Action Plan on. Information Security Measures for. Critical Infrastructures. Safety as a matter of course for our daily lives

The Second Action Plan on. Information Security Measures for. Critical Infrastructures. Safety as a matter of course for our daily lives The Second Action Plan on Information Security Measures for Critical Infrastructures Safety as a matter of course for our daily lives - Safe and secure social infrastructure for everybody - February 3,

More information

Construction Project Management in China and Its Development Prospect

Construction Project Management in China and Its Development Prospect CIB TG 23 International Conference, October 2003, Hong Kong Page 1 of 8 Construction Project Management in China and Its Development Prospect Bosen He Email: hetju@hotmail.com Management School, Tianjin

More information

General Terms and Conditions of Purchase and Cooperation for Services

General Terms and Conditions of Purchase and Cooperation for Services General Terms and Conditions of Purchase and Cooperation for Services 1. General principles / Scope of application 1.1 Solely these General Terms and Conditions of Purchase and Cooperation for Services

More information

Temporary Measures on Overseas Use of Foreign Exchange Insurance Funds 保 险 外 汇 资 金 境 外 运 用 管 理 暂 行 办 法

Temporary Measures on Overseas Use of Foreign Exchange Insurance Funds 保 险 外 汇 资 金 境 外 运 用 管 理 暂 行 办 法 Temporary Measures on Overseas Use of Foreign Exchange Insurance Funds 保 险 外 汇 资 金 境 外 运 用 管 理 暂 行 办 法 Chapter I General Provisions Article 1 These Measures are formulated in accordance with the Insurance

More information

SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998

SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998 1 (6) SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998 Offer If the offer diverges from the invitation to tender, it must be mentioned explicitly and relevantly in order to be able

More information

CONTRACTING HINTS AND TIPS

CONTRACTING HINTS AND TIPS CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising

More information

GEORGIA S LAW FIRM. JamesBatesLLP.com

GEORGIA S LAW FIRM. JamesBatesLLP.com GEORGIA S LAW FIRM JamesBatesLLP.com James-Bates-Brannan-Groover-LLP is a full-service business law firm delivering high-quality, cost-effective legal services for individuals and businesses throughout

More information

7.4.1 Be required to make exhaustive or continuous on-site reviews;

7.4.1 Be required to make exhaustive or continuous on-site reviews; SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific

More information

A Study On Factors Influencing Construction Contract Claim Management

A Study On Factors Influencing Construction Contract Claim Management A Study On Factors Influencing Construction Contract Claim Management K.Sundhar #1, N.Nandhini #2 #1 PG Student (M.E Construction Engineering and Management), #2 Assistant Professor ( Department of civil

More information

CODE OF ETHICS POLICY

CODE OF ETHICS POLICY CODE OF ETHICS POLICY The YMCA's reputation is dependent upon the good judgment, ethical standards and personal integrity of every individual in the YMCA. As the YMCA continues to grow, it is of paramount

More information

Code of Ethics and Business Conduct (CEBC)

Code of Ethics and Business Conduct (CEBC) Code of Ethics and Business Conduct (CEBC) Amadeus Group October 2015 Index _ Preamble... 3 _ Our People... 3 _ Beyond Compliance... 3 _ Commitment to the Environment... 3 _ Conflicts of Interests, Gifts,

More information

Dear chairman, dear members of the Committee!

Dear chairman, dear members of the Committee! To: Aarhus Convention Compliance Committee From: Ecological Society Green Salvation City of Almaty, Republic of Kazakhstan. March 9, 2012. Dear chairman, dear members of the Committee! According to the

More information

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS LAW OF MONGOLIA 28 January 2010 State Palace, Ulaanbaatar city Article 1. Purpose of the law ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS 1.1. The purpose of this law is to regulate matters related to

More information

Guide on drawing up contracts for large industrial works

Guide on drawing up contracts for large industrial works Guide on drawing up contracts for large industrial works Topic: Construction, installation of plant, engineering Source: United Nations Economic Commission for Europe Palais des Nations Genève, Switzerland

More information

To Establish the Art Design Personnel Training Mode with Combination of A + T

To Establish the Art Design Personnel Training Mode with Combination of A + T IOSR Journal of Research & Method in Education (IOSR-JRME) e-issn: 2320 7388,p-ISSN: 2320 737X Volume 4, Issue 1 Ver. III (Jan. 2014), PP 18-22 To Establish the Art Design Personnel Training Mode with

More information

Israel LEVITAN, SHARON & CO. Peggy Sharon and Dror Zamir office@levitansharon.co.il. 1. Insurance intermediation activities

Israel LEVITAN, SHARON & CO. Peggy Sharon and Dror Zamir office@levitansharon.co.il. 1. Insurance intermediation activities Israel LEVITAN, SHARON & CO. Peggy Sharon and Dror Zamir office@levitansharon.co.il 1. Insurance intermediation activities 1.1 Is the distribution of insurance products (hereinafter referred to as insurance

More information

CODE ON PROFESSIONAL ETHICS OF LAWYERS, ASSOCIATES AND LAWYER'S APPRENTICES OF THE MACEDONIAN BAR ASSOCIATION

CODE ON PROFESSIONAL ETHICS OF LAWYERS, ASSOCIATES AND LAWYER'S APPRENTICES OF THE MACEDONIAN BAR ASSOCIATION CODE ON PROFESSIONAL ETHICS OF LAWYERS, ASSOCIATES AND LAWYER'S APPRENTICES OF THE MACEDONIAN BAR ASSOCIATION The Code of Professional Ethics of the lawyers is a sum of adopted principles, which should

More information

RUSSIAN FEDERATION FEDERAL LAW ON THE CONTRACT SYSTEM IN STATE AND MUNICIPAL PROCUREMENT OF GOODS, WORKS AND SERVICES

RUSSIAN FEDERATION FEDERAL LAW ON THE CONTRACT SYSTEM IN STATE AND MUNICIPAL PROCUREMENT OF GOODS, WORKS AND SERVICES April 5, 2013 No. 44-FZ RUSSIAN FEDERATION FEDERAL LAW ON THE CONTRACT SYSTEM IN STATE AND MUNICIPAL PROCUREMENT OF GOODS, WORKS AND SERVICES Adopted by the State Duma March 22, 2013 Approved by the Federation

More information

Food Safety Control from the Perspective of Supply Chain

Food Safety Control from the Perspective of Supply Chain International Conference on Education Technology and Economic Management (ICETEM 2015) Food Safety Control from the Perspective of Supply Chain Weiyan Xie Guangxi Vocational College of Technology and Business,

More information

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.

Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws. The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Internal Revenue Service September 14, 2010 Reference Number: 2010-10-115 This report has cleared the Treasury Inspector General for Tax Administration

More information

Document Service Level Agreement

Document Service Level Agreement Document Service Level Agreement Version: 1.2 Last updated: April 21, 2016 1 SLA Service Level Agreement Definitions Supplier Supplier means the freelance translator or the translation agency providing

More information

The condominium form of ownership in the United

The condominium form of ownership in the United A Lender s Primer: Major Repair Loans for Condominiums and Other Common Ownership Communities By Richard A. Rosner The condominium form of ownership in the United States is the product of enabling legislation

More information

REQUEST FOR QUOTATION Quote #30-452-1808 CAR WASH PUMP REPLACEMENT (This Is Not A Sealed Bid)

REQUEST FOR QUOTATION Quote #30-452-1808 CAR WASH PUMP REPLACEMENT (This Is Not A Sealed Bid) Purchasing Division 211 West Oakley Street Flint, Michigan 48503 Ph: 810.767.4920 Fax: 810.767.4405 Quotations will be received by the Purchasing Division of Genesee County Road Commission, until 1:45

More information

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components

Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart. General Conditions of Purchase for Components Trelleborg Sealing Solutions Germany GmbH Handwerkstr. 5-7, 70565 Stuttgart General Conditions of Purchase for Components 1. Basic Provisions 1.1 The General Conditions of Purchase of Trelleborg Sealing

More information

TACKLING MANAGEMENT TASKS

TACKLING MANAGEMENT TASKS TACKLING MANAGEMENT TASKS Asset Soundness Results of Processing Non-Performing Loans in FY2005 We have calculated write-offs and reserve amounts for non-performing loans based on results from selfassessment

More information

CHAPTER 3.0: PROCUREMENT AND CONTRACTING

CHAPTER 3.0: PROCUREMENT AND CONTRACTING CHAPTER 3.0: PROCUREMENT AND CONTRACTING This chapter outlines the requirements for using Federal funds to purchase materials, products, or services under the CDBG Entitlement program. Whether you are

More information

AGREEMENT AMERICAN TRANSLATORS ASSOCIATION GUIDE TO A TRANSLATION SERVICES AGREEMENT

AGREEMENT AMERICAN TRANSLATORS ASSOCIATION GUIDE TO A TRANSLATION SERVICES AGREEMENT THE FOLLOWING GUIDE DOES NOT RESTRICT ANYONE FROM CONTRACTING FOR SERVICES ON TERMS AND CONDITIONS DIFFERENT FROM THOSE BELOW. THE USE OF ANY CLAUSE IS STRICTLY VOLUNTARY. NEITHER THE AMERICAN TRANSLATORS

More information

SPECIALIST HEALTH AND SOCIAL CARE SOLICITORS

SPECIALIST HEALTH AND SOCIAL CARE SOLICITORS SPECIALIST HEALTH AND SOCIAL CARE SOLICITORS QualitySolicitors Burroughs Day SPECIALIST HEALTH AND SOCIAL CARE SOLICITORS Our specialist Health & Social Care Team has built a strong reputation for advising

More information

The dental profession s peer review program is a process to resolve disputes between a

The dental profession s peer review program is a process to resolve disputes between a HOW THE DENTAL PEER REVIEW SYSTEM WORKS AND WHAT YOU EXPECT FROM IT Introduction The dental profession s peer review program is a process to resolve disputes between a patient and a dentist or a third

More information

Overseas Investment in Oil Industry and the Risk Management System

Overseas Investment in Oil Industry and the Risk Management System Overseas Investment in Oil Industry and the Risk Management System XI Weidong, JIN Qingfen Northeast Electric Power University, China, 132012 jelinc@163.com Abstract: Based on risk management content,

More information

Chief Executive Officers of All National Banks, Department and Division Heads, and All Examining Personnel.

Chief Executive Officers of All National Banks, Department and Division Heads, and All Examining Personnel. AL 2000 9 O OCC ADVISORY LETTER Comptroller of the Currency Administrator of National Banks Subject: Third-Party Risk TO: Chief Executive Officers of All National Banks, Department and Division Heads,

More information

Ethics Everywhere Jones Lang LaSalle Incorporated Annual Report for Calendar Year 2013 Program

Ethics Everywhere Jones Lang LaSalle Incorporated Annual Report for Calendar Year 2013 Program Ethics Everywhere Jones Lang LaSalle Incorporated Annual Report for Calendar Year 2013 Program Introduction JLL is committed to a corporate culture that embraces and promotes strong principles of business

More information

On-Site Examination Policy for Fiscal 2016. Examination Policy for Fiscal 2016" briefly reviews on-site examinations carried out in

On-Site Examination Policy for Fiscal 2016. Examination Policy for Fiscal 2016 briefly reviews on-site examinations carried out in March 29, 2016 Bank of Japan On-Site Examination Policy for Fiscal 2016 1. On-Site Examination by the Bank of Japan The Bank of Japan (hereinafter, the Bank) formulates the on-site examination policy every

More information

The study on the Human Resource Management of the Logistics Enterprises Based On the Competency Model

The study on the Human Resource Management of the Logistics Enterprises Based On the Competency Model , The study on the Human Resource Management of the Logistics Enterprises Based On the Competency Model You Chun Li Yanping School of Economics and Management Wu Han University,Luojia Mountain, Hubei,P.R.China,430072

More information

Vendor Management Best Practices

Vendor Management Best Practices 23 rd Annual and One Day Seminar Vendor Management Best Practices Catherine Bruder CPA, CITP, CISA, CISM, CTGA Michigan Texas Florida Insight. Oversight. Foresight. SM Doeren Mayhew Bruder 1 $100 billion

More information

AGREEMENT FOR PROFESSIONAL LAND SURVEYING SERVICES WITNESSETH: ARTICLE 1

AGREEMENT FOR PROFESSIONAL LAND SURVEYING SERVICES WITNESSETH: ARTICLE 1 AGREEMENT FOR PROFESSIONAL LAND SURVEYING SERVICES This Agreement, made as of the 29 th day of January, 1999, by and between the County of Wake (hereinafter, the "Owner") and McKim & Creed Engineers, P.A.,

More information

Code of Business Conduct and Ethics THE WOODBRIDGE WAY. integrity honesty respect responsibility

Code of Business Conduct and Ethics THE WOODBRIDGE WAY. integrity honesty respect responsibility Code of Business Conduct and Ethics THE WOODBRIDGE WAY integrity honesty respect responsibility Reissued June 12, 2015 Code of Business Conduct and Ethics THE WOODBRIDGE WAY INTRODUCTION Woodbridge Foam

More information

GC GUIDANCE ON INHERENTLY GOVERNMENTAL FUNCTIONS

GC GUIDANCE ON INHERENTLY GOVERNMENTAL FUNCTIONS GC GUIDANCE ON INHERENTLY GOVERNMENTAL FUNCTIONS Federal law prohibits contractors from performing inherently governmental functions. But determining which functions may be performed by contractors and

More information

Professional ideal. Professional ideal for the Danish Union of Teachers

Professional ideal. Professional ideal for the Danish Union of Teachers Professional ideal The Danish Union of Teachers has adopted a professional ideal at its congress 2-4 October 2002. Before that, the professional ideal has been the subject of a comprehensive member debate

More information

The Albany Law School - Career Center has adopted and expanded upon:

The Albany Law School - Career Center has adopted and expanded upon: Employment Policies The Albany Law School - Career Center has adopted and expanded upon: National Association for Law Placement (NALP) Principles and Standards for Law Placement and Recruitment Activities

More information

DAIMLER GROUP NORTH AMERICAN COMPANIES

DAIMLER GROUP NORTH AMERICAN COMPANIES DAIMLER GROUP NORTH AMERICAN COMPANIES General Purchasing Conditions for IT Part H Individual Software Development, Maintenance and Customization 1 Subject Matter / Scope of Performance 1.1 General The

More information

China s Social Medical Insurance System Needs the Support of a Sound Medical Service System

China s Social Medical Insurance System Needs the Support of a Sound Medical Service System Network of Asia-Pacific Schools and Institutes of Public Administration and Governance (NAPSIPAG) Annual Conference 2005 BEIJING, PRC, 5-7 DECEMBER 2005 THEME: THE ROLE OF PUBLIC ADMINISTRATION IN BUILDING

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY 1. Preamble: Rail Vikas Nigam Ltd (RVNL) is a Public Sector Undertaking specializing in development and execution of railway projects. In the course of its operations, it is prone

More information

Provisional Regulations on Administration of Stock Investment0020of Insurance Institutional Investors 保 险 机 构 投 资 者 股 票 投 资 管 理 暂 行 办 法

Provisional Regulations on Administration of Stock Investment0020of Insurance Institutional Investors 保 险 机 构 投 资 者 股 票 投 资 管 理 暂 行 办 法 Provisional Regulations on Administration of Stock Investment0020of Insurance Institutional Investors 保 险 机 构 投 资 者 股 票 投 资 管 理 暂 行 办 法 Chapter 1 General Provisions Article 1 These Regulations are formulated

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

Research on the Employment Psychology of Graduate in Colleges and Universities

Research on the Employment Psychology of Graduate in Colleges and Universities Research on the Employment Psychology of Graduate in Colleges and Universities GUO Jing 1, QI Lei 2 1. College of Agronomy, Agricultural University of Hebei, Hebei Baoding, 071001 2. College of Civil Engineering,

More information

1. Dream, Mission, Vision and Values

1. Dream, Mission, Vision and Values 1. Dream, Mission, Vision and Values This document constitutes Chapter 1 of the Fundamental Texts of CGI Group Inc. It begins with the mission statement of the company and is followed by the vision, the

More information

Obtaining, Maintaining & Effectively Using Surety Credit

Obtaining, Maintaining & Effectively Using Surety Credit Obtaining, Maintaining & Effectively Using Surety Credit CONTENTS: Introduction The Surety Industry What Does a Surety Expect from a Contractor? What Should the Contractor Expect from the Surety? The Partnership

More information