AGC Winter Conference CPM Schedule Review Workshop. Lowell Lingo, PE Dan Moore, PE Mary Harding December 2015

Size: px
Start display at page:

Download "AGC Winter Conference CPM Schedule Review Workshop. Lowell Lingo, PE Dan Moore, PE Mary Harding December 2015"

Transcription

1 AGC Winter Conference CPM Schedule Review Workshop Lowell Lingo, PE Dan Moore, PE Mary Harding December 2015

2 Presenter Lowell E. Lingo, PE 15 Years of Experience MO Project Management Office Region 7 Planning Office Project Management for the Bridge Program MO Office of Structures Bridge Inspections (Prudent) Bridge Design (Sear-Brown) M

3 Presenter Dan Moore, PE 23+ Years at NYSDOT MO Project Management Office MO Legal, Claims Unit 6 years Region 1 Construction EIC / PM Work on I-87 Exit 6 Single Point Urban Interchange 16 years Region 1 Design PM Designer Squad Leader M

4 Presenter Mary Harding 9.5 Years at NYSDOT 1 year MO Project Management Office 4 years MO Local Programs Bureau SRTS and TAP Program Management 4 years MO External Relations Community Relations State and Local Government Relations M

5 Course Agenda PMO Introduction I. NYSDOT Requirements for Scheduling II. III. Improved Business Processes for Scheduling PMO Assistance with High Level P6 schedule Review a) Importance of Schedule attributes b) Monthly Schedule Reports c) Benefits of a P6 Schedule as a Communication Tool M

6 Project Management Office Established February 2014 To provide project management, support and services for the Department s major projects and the capital program Identify opportunities to standardize project management practices in Planning, Design and Construction Focus on continuous improvement associated with on-time and on-budget delivery Consolidated scheduling responsibilities from Offices of Design and Construction High level and detailed schedule review M

7 PMO Management Structure Director Eric Celia Construction Project Management Lowell Lingo Planning and Design Project Management Dan Moore Reporting & Performance Measures Janet Simson Training and Communication Mary Harding *Policy and Governance - TBD M

8 Handouts This presentation Schedule Report Samples Schedule Checklist Schedule Importer Instructions Process for Automated Access Request Form M

9 Project Goals Contractor Safety Profitability Quality On-Time NYSDOT Safety Quality Budget On-Time Common Goals

10 Project Management Knowledge Areas Include: Integration Scope Time Budget Quality Resource Communication Risk Stakeholders Procurement How does a Project Schedule support the above PM practices?

11 Integration Management Coordinated interaction CPM Coordinates all activities via logic Defines how all parties interact and perform Provides a written record of the construction execution plan

12 Time Management Coordinated timing and execution of activities Plan to achieve on-time delivery CPM: Coordinates, allocates and measures performance Document and analyze time impacts if they occur Understand time related impacts Measure consequences of delays & impacts

13 Budget Management Planned Cost vs Actual Costs for on-budget delivery CPM: Can be cost loaded Can manages budget accountability and predict possible delay costs of impacts

14 Quality Management Ensures quality standards and requirements are met CPM: Baseline schedule formation should ensure that all quality standards are contemplated & met Incorporate all required elements to ensure quality Ensures consistency across the state

15 Resource Management Planned resources vs Actual resources CPM: Allows resources to be managed and measured during project execution Allows understanding of needed resources based on planned work or altered work Allows resource forecasting

16 Communications Management Plan, measure and control communication CPM: Allows planning, documenting and communicating the execution plan Uses reports, layouts and status to determine Responsible party On-schedule or Late Critical Path Identify impacts to whom, what, and when via the schedule Formalizes discussion of plan in documented format to share and exchange information

17 Risk Management Plan, identify and analyze risk Identify risk response to control risk CPM: Understand impacts of risk from scope change Performance measurement Impacts to critical path can be analyzed, monitored and controlled Forecast impacts

18 Stakeholder Management Manage and control stakeholders CPM: Identifies who does what and when Understand performance impacts to project External stakeholder identification.business impacted, traveling public impacts by schedule changes

19 A high quality, up-to-date project schedule is much more than just a Time Management tool! It facilitates many of the Project Management practices necessary to achieve a successful project!

20 I. NYSDOT Requirements for Scheduling

21 P6 Schedule Requirements Work in the NYSDOT Primavera P6 Environment Log-in through Citrix Get involved early! Timely baseline submission after Award Know who to contact CPM Scheduling Section M

22 NYSDOT Resources M

23 Specification Requirements NYSDOT Type 2 Scheduling Spec (Item 639.xxxx) HDM Chapter 21 references when this applies CPM Schedule Submission on Primavera P6 Software Prepared on NYSDOT network servers Revise and update the progress schedule Use it in planning, coordinating and performing all work Shall accurately depict the entire scope of work Narratives are required D

24 Specifications NYSDOT Scheduling Specification details Preconstruction Schedule Meeting Three types of Baseline Schedules Draft Baseline Schedule Baseline Progress Schedule at Award Final Baseline Progress Schedule at Award Progress Update Schedules D

25 Rules for Baseline Progress Schedule at Award Contractor to submit 10-days after Award Logical and realistic plan to execute the requirements of the contract This is the full Baseline Schedule submission Contractor s plan at the time of Bid Requires full in-depth review Baseline Schedule Includes: Schedule Narrative D

26 What should be in Baseline Schedule? All physical activity to complete the work detailed in the plans Procurement process Important Milestones Contractual constraints 3 rd party work that affects project (utilities) More if it can affect the schedule it should be in the schedule D

27 What Should be in a Baseline Narrative D-number Potential conflicts and issues Project name, location Contractor name Contract Award Date Current Contract Completion Date Scheduled completion of all work Interim milestone dates Critical and near-critical work elements 3rd party influences NYSDOT influences Key plans Identify acronyms and abbreviations General approach to the work Reasons for sequencing in schedule Resource limitations D

28 Preconstruction Schedule Meeting At the Preconstruction Schedule Meeting: Bring draft BL to facilitate discussion: Scheduling of project activities Resolve questions regarding contract requirements WBS structure Proposed Calendars and Activity Codes Milestones and Time-Related Clauses D

29 Best Practices Get to a Baseline Quickly Think about during bid process Recommend system access early At-Risk development possible NYSDOT can assist with draft baseline review Ask questions/clarify as needed L

30 II. Improved Business Processes for Scheduling Schedule data exporter On-line, automated request forms P Upgrade Schedule Manual Monthly Schedule Reports M

31 Schedule Importer Upload new data from any CPM Software to Department systems Data directly entered into an Excel spreadsheet, or using copy/paste functionality from external systems. Bulk Upload Template allows Contractors to create schedule logic in their own environment without the risk of corrupting NYSDOT global data. M

32 Automated Access Request Form Expedites the issuance of a P6 account Form completed and submitted on-line. Sign and notarize and scan to return. Upload of required documentation saves time and reduces the potential for data-entry error dot.ny.gov/ Identify your User ID/Log on in the Application to have new projects added Please remember to notify the PMO if an employee is no longer assigned to a project so the Department can remove that user s access to the software application and project data. M

33 P Upgrade Goal to complete by end of 2015 Corrects known bugs in software Does not significantly change user experience or processes Improves ability to connect with other enterprise system at NYSDOT: Unifier (Contract Management) D

34 Scheduling Manual Scheduling management best practices Goal is to shorten spec Remove instructional language Spec will be requirements only Manual will provide instruction Creates more user friendly Spec Scheduling resource for CPM Schedule users and preparers L

35 Monthly Schedule Reports PDF package reflecting High Level Schedule review Sent to NYSDOT staff and Contractor Ease of use More detail later.. L

36 III. High Level Schedule Review by NYSDOT s PMO Compliance with Section 100 High Level Review vs Detailed Review

37 a) Importance of a Good Schedule A well maintained schedule is a useful tool in project management. Becomes a tool to help support, verify and analyze project management ideas, scenarios and decisions. Good data supports reporting and schedule integrity In order to maintain the schedule, it has to be at the forefront of the project. It needs to be updated, reviewed and discussed continuously. The goal is to analyze schedule updates as close to when the work actually occurred as possible: Continuously adjust the schedule to reflect changes in the project plan Understand schedule movement and responsibility L

38 Important Schedule Attributes Work Breakdown Structure (WBS) Primary sort structure for P6 NYSDOT Provides high level structure in System Contractor creates own WBS under high level Activity IDs Activity Names Appropriate Calendars Activity Codes Activity Durations M

39 Good Practices when creating Contractor WBS WBS Names should reflect the detail of the project. Bridge Names and Staging and Phasing should be included in each level of the WBS so that a user of the schedule always knows where they are in the schedule. Upper levels match CPM Specification requirements Logical flow Detailed descriptions Information cascades from upper levels to lower levels M

40 Activity IDs Reasonable Intelligent Identify fabrication and delivery Identify Bridge Identify Stage M

41 The following activities shall be incorporated into the Progress Schedule: M

42 Activity Names What are you looking for? All Activity Names are unique Activity Name can stand alone Activity Name does not rely on WBS Scope of work is fully understood Has action verb Location of work is clear Stage or phase is clear Understanding of abbreviations Length is not excessive Work described is measurable Consistency M

43 Activity Names Activity Names are clear and uniquely defined descriptions of scope and location Detailed narrative description consisting of the following: A verb or work function (i.e. excavate, form, erect, install, place, etc.) An object (i.e. deck, footing, wing wall, parapet, etc.) A structure identifier (i.e. Bridge 1 - Br1 or B1, Pondfield Bridge - P-Br) A location (i.e. Pier 1, P1, East Approach, EA, Station to 40+00, Sta , etc.) Stage identifier (i.e. Phase 1, Ph1, Stage 3A, Stg 3A, etc.) M

44 Activity Codes Well defined codes enable schedule sorting for particular information Responsible Party (DOT vs Contractor) Stage Area of Work Type of Work Subcontractor (Subcontractor, Utilities, Railroads) Pay Item M

45 Activity Durations What are you looking for? Reasonable Original Durations Durations follow specification requirements Consistent durations Correct quantity assumptions Like work has similar durations Like work of increased quantity has increased durations Order of magnitude assessments Duration accuracy with calendar assigned Verify that all durations are whole numbers M

46 Calendars Calendars consider days and hours Define work and non-work periods Identify standard days and hours that Contractor plans to work Identify standard holidays Should extend beyond completion of project by 1-year Global, Resource or Project M

47 Compliance with Section 100 Topics Worth Discussing: NYS Department of Transportation Standard Specifications: Changes, Contingencies, Extra Work & Deductions Differing Site Conditions Suspension of Work Directed by the Engineer Notice & Recordkeeping Value Engineering Change Proposal (VECP) Disputed Work and Dispute Resolution Progress Schedule Completion Date Failure to Complete Work on Time Delay Provisions D Time Related Dispute Compensation D

48 High Level Review Immediate Rejection & NYSDOT Checklist Review schedule to ensure compliance with NYSDOT specifications (Type 2 Spec and Section 100) Identify schedule deficiencies as a basis of immediate rejection Use of Schedule Updates in Monthly Review Report for Type 2 Schedules M

49 High Level Review Immediate Rejection Failure to: Schedule as of the Data Date Include the Schedule Log (Leveling Report) Include Claim Digger Report Include a Narrative Inclusion of: Actual dates greater than the Data Date Invalid relationships M

50 High Level vs Detailed PMO performs high level reviews on all schedules Detailed review by PMO, EIC or CI agreement

51 Schedule Updates Goal is to maintain the integrity of the schedule so it can be used as a project management and communication tool. Use of a P6 schedule to make construction management decisions. Predict/forecast problems Measure project status Analyze information related to time disputes & appropriately allocate responsibility for delay Collaborate with stakeholders to find solutions to problems In general, be better informed regarding execution aspects of the project via detailed written communication. L/D

52 Contractor s Schedule Update Narrative Should reflect changes and progress Critical Path Discuss Critical Paths, driving Critical Path activities and changes to the Critical Paths Project Delays/Issues Discuss delays/issues/concerns experienced in the update period Suspended Work Discuss any work that has been suspended and why Schedule Changes Provide details on the changes and specifics on why each change was made Procurement/Submittals Discuss status of procurement submittals and RFIs that are in review or are upcoming Look Ahead Discuss work planned for next update period and any potential problems or concerns that could develop L D

53 b) PMO Monthly Schedule Reports using Global Layouts Layouts are customizable views of project information that can be saved so they can be used over again. How to use P6 schedule data in reports

54 Using Layouts Global Layouts Created by the CPM Scheduling Section Can t be modified Can be copied to the User and Project Layout areas and modified as needed by individual users. Project Layouts Specific to a project Can be exported with a project User Layouts Created by individual users and are only available to the user unless shared with another user. Can be used in any project that the user has open. M

55 NYSDOT PMO Generated Monthly Schedule Report Layouts for Construction: Use primarily in Baseline Review Layout 01: Milestones Constraint Level of Effort Layout 02: Longest (Critical) Path Layout 03: Longest (Critical) Path by WBS Primarily used internally Layout 12: NYSDOT Resp Party Layout 18: Type of Work Other: Layout 11: Near Critical Total Float <=20d Layout 14: Summary Roll-up Layout 15: All Date Changes from Last Update Layout 16: Full Schedule Layout 17: Remaining Schedule <100% Use in Monthly /Weekly Meetings Layout 00: 2 weeks out; 1 week back Layout 04: Slipping and Total Float <=20d Layout 05: All Slipping Activities Layout 06: New Near Critical Total Float <=20d Layout 07: Actuals in Last 5 Weeks Layout 08: 30d Look-Ahead Layout 09: 30d Look-Ahead Near Critical Layout 10: Negative Float Layout 13: Winter Activities <100% L

56 Using Layouts and Reports Schedule Layouts for Construction: M

57 Using Layouts and Reports Monthly Schedule Reports for Construction: M

58 Reviewing the Longest (Critical) Path Layout: 02_Longest (Critical) Path What are you looking for? A contiguous Critical Path from the Data Date to the end of the project Look at the near-critical paths, do they make sense? Do you think the near-critical work is really that important to the project? Is the Critical Path loaded with DOT responsible activities? Is the Critical Path loaded with 3rd party activities? Review/Track Critical Path to various contractual milestones Review/Track Critical Path to various key project milestones L

59 Reviewing the Longest (Critical) Path (Layout: 02_Longest (Critical) Path) L

60 Reviewing the Longest (Critical) Path L

61 Reviewing Near-critical Paths Layout: 06_New Near Critical Total Float <=20d What are you looking for when reviewing Near-critical Paths? Activities that are planned in the next few months that could possibly impact the project if they are delayed Activities with Late Finish Dates in the next few months of the project Elements of the project that you need to monitor and possibly expedite to prevent them from affecting the Critical Path or project completion dates Ways you can make sure NYSDOT, 3rd Party and even Contractor responsible activities are completed in a timely fashion without affecting the completion of the project Using the data to proactively managing project L

62 Reviewing Near-critical Paths L

63 Reviewing Updates Monthly Submissions Actual and Planned work Remaining Durations Logic Connections Added or Deleted Activities (104-02) Activity Code Assignments L

64 Reviewing Updates What are you looking for? Layout: 11 Near Critical Total Float <=20d Layout: 09 30d Look Ahead Near Critical Use 30 Day Look-Ahead in weekly progress meetings to ensure Contractor and NYSDOT have same expectations Near-critical paths Finding what activities are near-critical Management of the activities on these paths to prevent them from affecting the Critical Path and the contractual milestones Movement of near-critical activities in the schedule and why L

65 Reviewing Updates Original Duration Changes Layout: 07 Actuals in Last 5 Weeks Original Duration changes represent a change to the original plan. From the list prepared by the comparison software, you can pull up each activity and see how its change affected the predecessor and successor activities in the schedule. Review to insure that you are ok with the changes Reasonable Don t affect the Critical Path of project completion dates L

66 Reviewing Updates Duration Variances Layout: 05_All Slipping Activities Duration Variances are activities that are taking longer than scheduled or are progressing faster than scheduled. The most concerning Duration Variances are the activities that are taking longer than expected. A simple export of activities from P6 to Excel can produce a Duration Variance table Compare the Original Duration to the Actual Duration of each activity Focus on low float activities Check 3rd party activities and activities that are NYSDOT s responsibility L

67 Layout: 05_All Slipping Activities

68 Reviewing Updates Activities with Negative Float Layout: 10 Negative Float Check for Negative Float activities in each update even if the project is on or ahead of schedule. Negative float on a project that is on or ahead of schedule may indicate that an interim milestone is behind schedule, a constraint was added, an error in data input, incorrect constraints or bad logic. On projects that are behind schedule, activities with negative float should be reviewed to gain an understanding of what logic paths are behind schedule. Tend to focus on the Critical Path and the driving Critical Path activity as the cause of the slippage and the delay Near-critical paths may also be behind schedule and have negative float, indicating that more than one path and work element has to be mitigated in order to bring the project back on schedule. Use the Default Negative Float filter L

69 Reviewing Constraints Layout: 01_Milestones Constraint Level Of Effort (LOE) What To Look For All Contract I/D or LD periods and interim milestones should be included. Review LOE durations compared to Contract durations. Has scheduled duration increased (negative Variance)? Review Primary Constraint Dates to make sure they match Contract dates. Review Constraint Start/Finish dates versus Primary Constraint Dates. Are they on schedule? Are they slipping (negative Variance)? Are there Constraints that are not Contractual and not approved by the EIC? L

70 Schedule Meetings Verifying Progress Contractor responsibility to monitor schedule and update based on work complete and work planned Progress should be verified Verify actual dates - start/actual finish and remaining durations Use Layout: 07_Actuals in Last 5 Weeks D

71 c) Communication Tool: Importance of Schedule Layouts Can use the schedule to engage project staff Distribute specific look ahead schedules to inspection staff Targeted look ahead printouts give inspectors understanding of the Contractor s plan for the work Discuss at project meetings, including: Progress Meetings: Critical Path / Near-critical activities (Layout 02; Layout 03; Layout 06) Construction Look ahead (Layout 08; Layout 09) Construction activities taking longer than expected (Layout 04; Layout 05) Construction activities projecting delays (Layout 09; Layout 11; Layout 15) Submittal Meetings Look ahead Prioritizing submittals/rfis Submittals taking longer than expected Verifying submittal revise and re-submit durations Quantifying remaining duration for submittal review activities Verifying that all submittals/subcontractors are approved for upcoming construction work D

72 NYSDOT CPM Schedule Quick Reference Guide Checklist Monthly Report Layouts accomplish this as well M

73 Questions? Lowell E. Lingo, P.E. Construction Management Section (Primary contact)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

How To Use P6 For A Project Scheduling System

How To Use P6 For A Project Scheduling System Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS

SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project

More information

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software. DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

California Department Of Transportation. Class # G0C094

California Department Of Transportation. Class # G0C094 California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,

More information

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster Andrew Avalon, P.E., PSP and Curtis W. Foster LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment // Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...

More information

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative,

More information

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]

5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name] 231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION:

ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION: DESCRIPTION: Under this item the Contractor shall provide an individual(s), designated the Document Control Specialist. The Document Control Specialist shall use a software to prepare, status, electronically

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received

More information

CPM Scheduling with Primavera Unifier

CPM Scheduling with Primavera Unifier CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (August 2008) --------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (July 2007) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS

CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS CALCULATION DIFFERENCES WHEN IMPORTING FROM MICROSOFT PROJECT 2003-2010 INTO ORACLE PRIMAVERA P6 VERSION 7 BY PAUL E HARRIS OF EASTWOOD HARRIS TABLE OF CONTENTS 1 INTRODUCTION 3 2 AIM 3 3 SUMMARY 3 4 LEVELS

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

Project Time Management

Project Time Management Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-981-3 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-981-3 The material contained within

More information

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON

SCT AND MCAS MIRAMAR FOTS SOUTHERN CALIFORNIA TRACON 1-5 CONSTRUCTION SCHEDULES 1-5.1 General, Network Analysis System (NAS).- 1-5.1.1 Applicable documents.- The Publication listed below forms a part of this specification and is applicable to the extent

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS

UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

AACE International Recommended Practices

AACE International Recommended Practices AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,

More information

Schedule analytics tool

Schedule analytics tool Schedule analytics tool As capital project spend increases and aggressive deadlines are built into project schedules, the reliance on accurate, transparent and meaningful schedule practices is growing.

More information

Why are PMO s are Needed on Large Projects?

Why are PMO s are Needed on Large Projects? Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE DIVISION PROCEDURES MANUAL PROGRAM AND PROJECT MANAGEMENT SECTION 6: QUALITY ASSURANCE PROCEDURE: PM 6.02 TITLE: QUALITY ASSURANCE AUDITS DATE:

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Work Breakdown Structure Element Dictionary Construction

Work Breakdown Structure Element Dictionary Construction Initiation CON 5.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope, including the solicitation for a contractor

More information

DCMA 14-Point Assessment Metrics

DCMA 14-Point Assessment Metrics DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,

More information

Design Consultant Project Management Requirements

Design Consultant Project Management Requirements Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

PROJECT PLAN TEMPLATE

PROJECT PLAN TEMPLATE Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Management/Information Technology PROJECT PLAN TEMPLATE Document Revision Draft

More information

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide

Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Primavera P6 Enterprise Project Portfolio Management 8 Essentials (1Z0-567) Exam Study Guide Margy Girdzius Director, Partner Enablement WWA&C Objective & Audience Objective Help you prepare to take the

More information

Scheduling Best Practices

Scheduling Best Practices RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding

More information

Construction Project Scheduling: Keys to Success

Construction Project Scheduling: Keys to Success View the online version at http://us.practicallaw.com/0-574-8625 Construction Project Scheduling: Keys to Success KELLY M. HEUER AND JAMES G. ZACK, JR., NAVIGANT CONSULTING, INC., WITH PRACTICAL LAW REAL

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

Common File Server The secure common file server provided by the Department for storage of all contract documents.

Common File Server The secure common file server provided by the Department for storage of all contract documents. DESCRIPTION: Under this item the Contractor shall prepare, status, electronically file and send all project correspondence, Shop Drawings, Requests For Information, meeting minutes, and schedule narratives

More information

Schedule Assessment Guide. Best Practices for Project Schedules

Schedule Assessment Guide. Best Practices for Project Schedules Schedule Assessment Guide Best Practices for Project Schedules December 2015 PREFACE The U.S. Government Accountability Office is responsible for, among other things, assisting the Congress in its oversight

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM

San Antonio Water System Standard Specifications for Construction ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM ITEM NO. 903 CONSTRUCTION QC/QA PROGRAM 903.1 DESCRIPTION: This item shall govern the preparation and implementation of the Contractor s Construction Quality Control/Quality Assurance (QC/QA) Program for

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

PLANNING FOR YOUR PROJECT

PLANNING FOR YOUR PROJECT PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

The Fast Track Project Glossary is organized into four sections for ease of use:

The Fast Track Project Glossary is organized into four sections for ease of use: The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

1. Interpretation of this Schedule

1. Interpretation of this Schedule Schedule 6 Programming Requirements 1. Interpretation of this Schedule 1.1 Primavera The following capitalised terms used in this Schedule 6 have the meanings given to them in the proprietary computer

More information

Local Government Energy Efficiency Resources Guidebook 5: Project Management

Local Government Energy Efficiency Resources Guidebook 5: Project Management Local Government Energy Efficiency Resources Guidebook 5: Project Management Prepared for: Los Angeles County ISD 1100 North Eastern Ave Los Angeles, CA 90063 Prepared by: The Energy Coalition 523 W. Sixth

More information

ORACLE PROJECT PLANNING AND CONTROL

ORACLE PROJECT PLANNING AND CONTROL ORACLE PROJECT PLANNING AND CONTROL (Formerly Oracle Project Management) KEY FEATURES COLLABORATIVE PROJECT PLANNING Define a project work breakdown structure to align plans to execution Coordinate financial

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Health Check Summary Reports Performance Trend Schedule Trace Schedule Compare Margin Tracker Health Check Indicators Missing Predecessors

More information

Project Management Framework

Project Management Framework Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

Integrating Project Schedule & Resources Whitepaper By Ted Barth, Managing Partner BNW Manufacturing Associates LLC

Integrating Project Schedule & Resources Whitepaper By Ted Barth, Managing Partner BNW Manufacturing Associates LLC Integration of Project Resources and Schedules Whitepaper By Ted Barth, BNW Manufacturing Associates LLC Introduction: When project driven organizations have multiple projects competing for the same resources:

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

Working for America s Workforce

Working for America s Workforce Office of Inspector General Washington, DC. 20210 July 8, 2004 MEMORANDUM FOR: SAMUEL T. MOK Chief Financial Officer FROM: SUBJECT: ELLIOT P. LEWIS Assistant Inspector General for Audit The e-payroll Quicksilver

More information

Agenda. CPM Key Performance Indicators (KPIs) CPM Performance Evaluation. How KPIs are Measured. KPI Roll out Schedule

Agenda. CPM Key Performance Indicators (KPIs) CPM Performance Evaluation. How KPIs are Measured. KPI Roll out Schedule CPM Key Performance Indicators (KPIs) September 17, 2013 David Wood, PMO 1 Agenda CPM Performance Evaluation How KPIs are Measured Details of each KPI KPI Rollout Schedule 2 1 Key Performance Indicators:

More information

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 Designer & Builder Symposium Construction Scheduling Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 FOCUS AREAS Current processes (where implemented) Scheduling specification changes

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

Instructions for use:

Instructions for use: TRANSMISSION MONTHLY PROJECT PROGRESS REPORT INSTRUCTIONS FOR COMPLETION TEMPLATE Instructions for use: PURPOSE OF FORM: The Transmission monthly Project Progress Report form is to be used by the Transmission

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

Appendix 3: Project Management Substation Guidelines (General Process Flow Template)

Appendix 3: Project Management Substation Guidelines (General Process Flow Template) 365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It

More information

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration

MISSISSIPPI STATE UNIVERSITY Office of Planning Design and Construction Administration SECTION 01 311 NETWORK ANALYSIS SCHEDULE Part 1.1 DESCRIPTION A. Scope: Provide projected network analysis schedules for the entire Work and revise periodically. This type of schedule is acceptable for

More information

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM

More information

IT Baseline Management Policy. Table of Contents

IT Baseline Management Policy. Table of Contents Table of Contents 1. INTRODUCTION... 1 1.1 Purpose... 2 1.2 Scope and Applicability... 2 1.3 Compliance, Enforcement, and Exceptions... 3 1.4 Authority... 3 2. ROLES, RESPONSIBILITIES, AND GOVERNANCE...

More information

The Amazing History of Primavera Software

The Amazing History of Primavera Software The Amazing History of Primavera Software (as told by a Complete Outsider) By Ron Winter, PSP Schedule Analyzer Software History? There is nothing new in the world except the history you do not know. Harry

More information

Covance Construction Management Staffing Plan Chandler, Arizona

Covance Construction Management Staffing Plan Chandler, Arizona INTRODUCTION: This Construction Management (CM) Staffing Plan has been prepared for Covance to identify the critical organizational structure necessary to successfully complete the Chandler project according

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Oracle EBS Service Contracts Extensions for Oracle Endeca

Oracle EBS Service Contracts Extensions for Oracle Endeca Oracle EBS Service Contracts Extensions for Oracle Endeca Amit Jha Project Leader, Product Management Oracle EBS Procurement & Contracts October 02, 2014 Safe Harbor Statement The following is intended

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

Introduction... 4. Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4. RFC Procedures... 5

Introduction... 4. Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4. RFC Procedures... 5 Remedy Change Management Version 3.0 Modified: 10/27/2015 Table of Contents Introduction... 4 Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons... 4 RFC Procedures... 5 Process Flow

More information

Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE. www.astadev.com

Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE. www.astadev.com Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE www.astadev.com WHY INVEST IN A PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOLUTION? Today s management challenges need innovative

More information

Project Engineers and Supervisors Conference. CPM Scheduling

Project Engineers and Supervisors Conference. CPM Scheduling Project Engineers and Supervisors Conference March 15 th and 16 th 2010 CPM Scheduling Prepared and Presented By Project Engineers and Supervisors Conference Benefits of CPM Scheduling Lessons Learned

More information

Introduction to Project Management

Introduction to Project Management L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You

More information

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I

U.S. Department of Veterans Affairs. Facilities Management. Critical Path Method. Guidelines for Preparation of CPM Schedule Volume I VA U.S. Department of Veterans Affairs Facilities Management Critical Path Method design DECEMBER 2012 Volume I Design Manual for & TABLE OF CONTENTS, Volume I 1. INTRODUCTION... 3 1.1. Purpose and Scope...

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table

More information

CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS

CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS CHAPTER 5 - SAFETY ASSESSMENTS, LOG OF DEFICIENCIES AND CORRECTIVE ACTION PLANS A. INTRODUCTION... 1 B. CHAPTER-SPECIFIC ROLES AND RESPONSIBILITIES... 1 C. SAFETY PROGRAM ASSESSMENT PROCESS... 3 D. FACILITY-MAINTAINED

More information

Engineering and Construction

Engineering and Construction Engineering and Construction I Manage risk. Protect profit. Today s engineering and construction market is highly competitive, driving profit margins down as risks increase. It only takes one failed project

More information

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18

BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS BUSINESS PROJECT MANAGEMENT CERTIFICATE/DIPLOMA IN K/502/5459 LEVEL 3 UNIT 18 Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS BUSINESS PROJECT MANAGEMENT K/502/5459 LEVEL 3 UNIT 18 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 BUSINESS PROJECT

More information

Reviewing a Baseline Schedule

Reviewing a Baseline Schedule Reviewing a Baseline Schedule by Ron Winter, PSP July 21, 2014 Copyright Ron Winter Consulting, 2014 OVERVIEW The accepted, initial schedule is often referred to as the baseline schedule. The use of this

More information

TRICKS AND TRAPS PRESENTATION

TRICKS AND TRAPS PRESENTATION Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 TRICKS AND TRAPS PRESENTATION Copyright of Eastwood Harris Pty Ltd Page 1 Purpose of the Presentation To demonstrate the P6 Version 7 bars

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Scott M. Francis, P.E., PSP Table of Contents 1. INTRODUCTION...

More information