Review of Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs

Size: px
Start display at page:

Download "Review of 01310 Schedule Specification Requirements District SAP/WBS breakdown Asset template Cost & Resource Loading Stored Material Costs"

Transcription

1 Agenda Topics: 1. Oracle/Primavera buyout Within the last year, Oracle bought Primavera. Primavera support has been tailored to Oracle s standard. stead of initially speaking to a support representative, you have to go online and enter your username and password to access their support site and enter a service request. You will then have a Service Request number tied to your request, similar to what you had with Primavera. Oracle will call you to discuss your request within 24 hours. So far, the support has been good and prompt. 2. P3eC Vs. P3 - As you probably know, P3e was the name for the new platform of internet compatible Primavera scheduling software, replacing P3. Although P3 is still being sold, it is no longer being enhanced. The last revision was P3.1 (P3 stands for Primavera Project Planner) was built on the old 8-bit platform with Btrieve database. P3 stands for Primavera Project Planner (the 3 P s) and P3e is called Primavera Project Manager. P3 was not really compatible for the new technology of internet capabilities. P3e was a separate software package purchased by Primavera because it had the more advanced 32 bit platform adaptable to the ternet and was designed for advanced resource and cost management capabilities. Primavera wanted to break into the large corporate market with the ability to interface with Oracle, SQL, and various accounting systems. They recognized a need for shared scheduling of multiple projects by multiple users across the Enterprise utilizing the network and internet. P3e accomplished that need. As revisions to the software were published, the name changed to P3eC (C for construction to attract the construction market) and then P4, P5, P6 and currently P6, Version 7. Primavera Contractor is a scaled down version of P3e(P7) and sells for $1,295. Contractor Vs. P6 is similar to what SureTrak and P3 were. SureTrak was the scaled down version of P3. Although SureTrak and P3 are still around, their future is probably short lived. 3. As competition increases and funding declines, construction firms wanting to maintain a competitive edge need to respond to Owner s demands for more accurate and precise project status information. 4. today s construction environment, scheduling specifications must be written to not only provide information format standards, but also standards in operation features of the scheduling software and the quality of the information provided. Customization in reports, layouts and software features is essential for developing consistent and accurate results that can be easily compared and evaluated. Primavera provides that level of sophistication, which is not found in other scheduling software. That is why Primavera has become the standard in the industry for both public and private entities.

2 5. Review of Schedule Specification Requirements: A. District SAP/WBS breakdown Refer to the attached Asset template This is the breakdown of items to be used in all schedules for the grouping and sorting of activities by the District s SAP accounting codes. Note that for STA work there is a specific breakdown of categories and items within each category. Likewise, a Pump Station project has its own breakdown of categories and items. The appropriate breakdown must be created in P6 or Contractor as the WBS breakdown structure. Each schedule activity must be assigned to the lowest appropriate level of the breakdown. The Contractor should also include a SAP code of General Conditions at the top of the breakdown. The Contractor should create breakdowns under the General Conditions code for various activities such as Milestones, Mobilization, Bond & surance or other activities that do not belong to the other specific codes given. The numbering and order of the codes should follow the general outline shown on the template. B. Cost & Resource Loading Note that the schedule spec A shows the following materials that need to be tracked in the schedule: CY Cast in Place Concrete CY or LF Earthwork (Excavation) CY or LF Earthwork (Embankment) TONS Reinforcement Steel SF Concrete Formwork EA Mechanical and Process Equipment AC Clearing AC Grassing SY Geo-grid DAYS Dewatering The materials should be loaded as material resources with the appropriate quantities and unit/measure with units applied in each update so that a resource report can be generated showing the progress of quantities in place during the project. Costs (revenue loading of the schedule based on the breakdown of the schedule of values) should be loaded as resources as well. By loading cost and quantities as resources, both will add up to the contract value. Stored Material Costs All stored material costs must be included in the schedule cost loading. Stored material costs should be assigned to the associated procurement activities and statused so as to reflect those costs in the submitted payment application schedule of values. The total contract amount and total payment application amount must be reflected in the schedule.

3 C. Schedule Naming Convention - Schedule naming was explained for itial Baseline, Revised Baselines and Updated Baseline Schedules. Schedule names cannot exceed 20 charactrers. Therefore, all schedules will have the general naming format prefix with a shortened name of the project, such as C-111- FPDA- followed by the revision number (R0 for Revision 0) and Update no. (U0 means no update). Therefore, C-111-FPDA-R0-U0 represents the initial accepted Baseline Revision 0 (R0). C-111-FPDA-R0-U1 represents the first update of the initial accepted baseline. Each subsequent accepted revised baseline shall be numbered sequentially. Updated baselines will begin with U1 and continue sequentially until another revised baseline is accepted. D. Activity Description formatting All activity descriptions will contain a prefix for the geographic area. Each activity description must be unique. E. Activity Breakdown Avoid long duration activities. Activities should be broken down into shorter duration activities to allow better tracking of the work and assessing a more accurate percent complete. Avoid activity durations more than one month in duration. Concrete work should include activities for forming, rebar and pouring for a specific piece of the structure, including base slab, walls, ceiling, each wing wall, etc.. Refer to item B above. F. Reporting The required reports & barcharts will be discussed. Their layouts are attached for import into P6 or Contractor. G. Revisions to the Baseline 1. The following changes are allowed to the updated baseline schedule without requiring a revision to the baseline: a) When an activity s predecessor or successor has a Finish to Start relationship that is out of sequence and can be corrected by changing the relationship to a Start to Start or Finish to Finish. All other out-of-sequence changes require a revision to the baseline schedule. 2. Start to Finish relationships or negative lag are not allowed to be used in the schedule. 3. Actual Start, Actual Finish, Percent completes for units, costs or duration, actual cost and actual units must be manually entered for each reporting period. Any other changes to the updated baseline schedule must be approved by the District and will require a revision to the baseline schedule. H. Two Week Look-Ahead Schedule A sample two week look-ahead schedule is attached for the Contractor s use. The two week look-ahead schedule should show activities of work done in the past two weeks as well as activities of work planned for the next two weeks. The dividing line should be the date of the progress meeting. Note that abbreviations should be entered for actual start, actual finish, planned start and planned finish as well as rain days. CPM Schedule activity numbers should also be included so that work done weekly can be cross

4 referenced to the accepted schedule. A Comment area is included for specific comments about the item. I. Schedule of Values for Payment Request vs. P6 Cost Loading - The Contractor should ensure that the Construction Baseline and updated baseline schedules are fully cost loaded so that the total contract amount is reflected in the schedules. The Contractor must create the body of the payment request in P6 and format a layout or report to match the payment request format submitted. Actual Cost must be manually entered each update period and remaining cost will be automatically generated if the proper calculation settings are made. Primavera instructions are attached that explain the process of cost and resource loading and adjusting settings in P6. Always run a cost report to check whether statused activities having a budgeted cost have a current cost % complete, actual cost and remaining cost. The payment request submitted to the District must agree with the cost loading and cost statusing of the CPM schedule. Executed Change orders for time and/or dollars must be included in the schedule. The District must approve how they are added to the schedule and the Contractor must include them in their monthly update narrative. 6. Review of P6 schedule features and functions: A. Screen Layouts The attached PLF files are for importing into the Screen Layout portion that shows barcharts on the screen that can be printed. They can be imported into P6 or Contractor. B. Report Layouts - The attached ERP files are for importing into the report portion of P6 or Contractor. C. Cost & Resource assignments - As referenced in Item 2.B. above, activities must be created as follows: 1. Activities for pouring concrete at specific sections will have a resource assignment of CY of Cast-in-Place concrete and a resource assignment of Lump Sum Cost (also assigned to cost account) for the activity. 2. Activities for forming at specific sections will have a resource assignment of SF of Forms and a resource assignment of Lump Sum Cost (also assigned to cost account) for the activity. 3. Activities for rebar at specific sections will have a resource assignment of TONS of Rebar and a resource assignment of Lump Sum Cost (also assigned to cost account) for the activity. D. Creating and Assigning Baselines A copy of the most recent accepted Baseline will be assigned to the current updated baseline schedule as the baseline and primary baseline schedule. Refer to Maintain and Assign Baselines. E. Creating WBS structure Vs. Activity Codes A dummy project named SAMPLE SAP-WBS CODES IMBEDDED IN PROJECT, containing the SAP/WBS structure is attached and can be cut and pasted into the Contractor s project WBS structure.

5 The following directions explains how to copy and paste the SAP/WBS into your project: First, import the sample project. Then open your project and the sample project at the same time. Go to the sample project and then go to Project->WBS and select the Tree Structure view and do a CTRL-A to select all the breakdown I have in the sample project and then do a CTRL-C to copy it. Then go to your project and go to Project->WBS and select the Tree Structure view and do a CTRL-A to select all the breakdown that you might have in your project and delete it. Then do a CTRL-V to paste what you copied from the Sample project into your project. Scroll up and down to make sure you don t have any other WBS structure in your project. That s it. You re done. F. Project Vs. Activity Settings & Calculations Refer to the attached Primavera Note files in PDF for instructions on various settings or definitions of fields. The Contractor must set the Project Calculation to show Longest Path. G. Global Changes - The attached PCF files are for importing into the report portion of P6 or Contractor. The Unit Price PCF file will calculate unit price for activities with a budgeted Cost assignment and/or one resource assignment. Be sure to import the Calculate Unit Price PCF file into Global change and execute it first, since some of the barchart layouts use the unit price. The attached SOV excel file shows the SOV report that can be generated from P6 or Contractor. Note the Unit price. It is generated from the Global Change for unit price and then the user defined field for unit price can be shown on the report. Variance calculations PCF files are attached for use when showing those variances in the attached screen layout barcharts. H. Importing various layouts Follow the menus shown in () to import the appropriate files. PCF = Global Change (Tools->Global Change->Import) PLF = Layout (Screen layouts that you can print (View->Layout->Open- >Save existing layout? =No->Import) ERP = Report (Tools->Reports->Look for Import icon on the far right, just above Wizard icon) If you have any questions, please contact Paul D. Lannom, CCC, CPM, SFWMD Schedule/Project Controls Principal, , ext 4204, plannom@sfwmd.gov.

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule

SOUTH FLORIDA WATER MANAGEMENT DISTRICT CONTRACTOR CPM SCHEDULE SUBMITTAL - DISTRICT REVIEW General Contractor CPM Schedule Contract No. CPM Schedule Project Id SOUTH FLORIDA WATER MANAGEMENT DISTRICT General Contractor CPM Schedule Project Name NTP DATE Data Date CONTRACT DURATION 0 ORIGINAL CONTRACT AMOUNT Date Schedule Received

More information

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

Collaborative Scheduling using the CPM Method

Collaborative Scheduling using the CPM Method MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines

More information

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE

PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

EXHIBIT 2-2-C PROGRESS SCHEDULES

EXHIBIT 2-2-C PROGRESS SCHEDULES EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,

More information

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,

More information

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.

MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software. DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose

More information

Scheduling Best Practices

Scheduling Best Practices In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors)

IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) IDENTIFY ACTIVITIES STEP 2 By: Charlie Jackson (Hill International) & Hannah E. Schumacher (Kitchell Contractors) Abstract: Many Contract Documents are now requiring the use of the latest version of Primavera

More information

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6)

LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) LECTURE -08 INTRODUCTION TO PRIMAVERA PROJECT PLANNER (P6) GOAL In this lecture, we ll learn: Background of Primavera Project Planner (P6) Getting Started P6 Interface Basic Navigation and Operation Setting

More information

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar

More information

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS

USER CONVERSION P3, SURETRAK AND MICROSOFT PROJECT ASTA POWERPROJECT PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

Project Planning and Scheduling

Project Planning and Scheduling Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination

More information

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS

PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE. In An. Established Project Environment PAUL EASTWOOD HARRIS PROJECT PLANNING & SCHEDULING USING PRIMAVERA ENTERPRISE Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment BY PAUL EASTWOOD HARRIS Eastwood

More information

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016

Agenda. CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 CPM Scheduling at CDOT Laura Zamora, P.E. February 24, 2016 Agenda Revision of 108.03 Schedule How CDOT Uses Construction Schedules Critical Path Method Scheduling Microsoft Project Overview 1 Revision

More information

Primavera P6 Exercise Worksheet

Primavera P6 Exercise Worksheet Primavera P6 Exercise Worksheet P6 Exercise Worksheet Preparing for the Exercises Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

California Department Of Transportation. Class # G0C094

California Department Of Transportation. Class # G0C094 California Department Of Transportation ADVANCED CPM SCHEDULING WITH SURETRAK Class # G0C094 ADVANCED CPM SCHEDULING WITH SURETRAK September 2003 SureTrak is a registered trademark of Primavera Systems,

More information

Time Management. Part 5 Schedule Development. Richard Boser

Time Management. Part 5 Schedule Development. Richard Boser Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms

More information

Project Initiation and Revision Training Manual. Table of Contents

Project Initiation and Revision Training Manual. Table of Contents for Engineering and Construction v.4.1 Project Initiation and Revision Training Class Conducted by Evans Technology June 2005 Table of Contents Introduction to Primavera... 3 Project Management (P3eC)...

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Developing Critical Path Method Scheduling (CPM)

Developing Critical Path Method Scheduling (CPM) Developing Critical Path Method Scheduling (CPM) Pretest 1. An activity which is on critical path has a planned duration of 5 days. What is the total float for the activity? a. 0 b. 1 c. 2 d. 3 Pretest

More information

Planning and Scheduling Time it Right

Planning and Scheduling Time it Right Planning and Scheduling Time it Right Key drivers for Success Presentation by Mr Alan Bolger FIEAust to the Australian Cost Engineering Society, Victorian Branch 22 April 2013 Alan Bolger: Background Over

More information

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR

FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR FLORIDA DEPARTMENT OF TRANSPORTATION GUIDELINE FOR ESTABLISHING CONSTRUCTION CONTRACT DURATION July 2010 DISCLAIMER: The following documentation as a whole was derived from Federal Highway Administration

More information

The History of Primavera Scheduling Software Copyright February 10, 2013 by Ron Winter, PSP

The History of Primavera Scheduling Software Copyright February 10, 2013 by Ron Winter, PSP The History of Primavera Scheduling Software Copyright February 10, 2013 by Ron Winter, PSP Please Note: This is paper is the result of an independent project by Ron Winter Consulting LLC. The information

More information

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.

added to the task, using Project, it will automatically calculate the schedule each time a new resource is added. Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the

More information

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led

Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

The Amazing History of Primavera Software

The Amazing History of Primavera Software The Amazing History of Primavera Software (as told by a Complete Outsider) By Ron Winter, PSP Schedule Analyzer Software History? There is nothing new in the world except the history you do not know. Harry

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

Common File Server The secure common file server provided by the Department for storage of all contract documents.

Common File Server The secure common file server provided by the Department for storage of all contract documents. DESCRIPTION: Under this item the Contractor shall prepare, status, electronically file and send all project correspondence, Shop Drawings, Requests For Information, meeting minutes, and schedule narratives

More information

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010

Designer & Builder Symposium Construction Scheduling. Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 Designer & Builder Symposium Construction Scheduling Glenn Saito NAVFAC Pacific Construction Division December 1, 2010 FOCUS AREAS Current processes (where implemented) Scheduling specification changes

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling. Planning & Scheduling CSTM 462 Managing a project through time and resources. The need for proper planning and scheduling. Project Management Objectives 1. Eliminate or reduce project RISK. 2. Obtain a

More information

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A

Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Oracle Primavera P6 Enterprise Project Portfolio management Overview Programme Reference # 201A Programme Description: Dedicated one full day training module in a structured and professional manner to

More information

Preplanning And Scheduling Of Road Construction By Using PPM

Preplanning And Scheduling Of Road Construction By Using PPM Preplanning And Scheduling Of Road Construction By Using PPM 1 T.Subramani, M.Sekar 2 1Professor & Dean, Department of Civil Engineering, VMKV Engg. College, Vinayaka Missions University, Salem, India

More information

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions.

S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. S-1 (1803) PROGRESS SCHEDULES-CRITICAL PATH METHOD (CPM) The provisions of MnDOT 1803 are deleted and replaced with these Special Provisions. 1803.1 All SCHEDULES A General Requirements This section contains

More information

Construction Project Scheduling

Construction Project Scheduling Construction Project Scheduling Produced and Distributed by Engineer Educators 857 East Park Avenue Tallahassee, FL 32301 1 Disclaimer The material in this course manual is not meant to infringe on any

More information

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015

Baseline Schedule Metrics. Donald R. McNatty, PSP FAACE November 18, 2015 Donald R. McNatty, PSP FAACE November 18, 2015 1 Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order to preserve the quality of the audio for all attendees.

More information

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT 2010 AND PMBOK GUIDE FOURTH EDITION training course presented by Paul E Harris Administration Evacuation Timings, meals and facilities Mobile phones

More information

Product Comparison. www.sageestimating.com 800-628-6583. Windows Technology. Spreadsheet. Estimate Management. Takeoff

Product Comparison. www.sageestimating.com 800-628-6583. Windows Technology. Spreadsheet. Estimate Management. Takeoff The Sage Estimating application is available in two levels: Estimating and Estimating. The following chart describes the key features and capabilities differentiating the two products. Windows Technology

More information

PROMASTAR Instructor-led Professional Training Services

PROMASTAR Instructor-led Professional Training Services PROMASTAR Instructor-led Professional Training Services Primavera P6 Professional Fundamentals Rel 8.3 Primavera P6 Professional Fundamentals Rel 8.3 Page 1 Oracle Primavera Learning Experience Learning

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management Chapter 6 Managing Project Scheduling Information Systems Project Management: A Process and Team Approach, 1e Fuller/Valacich/George 2008 Prentice Hall 6-1 What is Project

More information

The work breakdown structure can be illustrated in a block diagram:

The work breakdown structure can be illustrated in a block diagram: 1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as

More information

An Introduction to the Management Principles of Scheduling

An Introduction to the Management Principles of Scheduling College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923

More information

Project Scheduling. with Primavera P6. Training Manual

Project Scheduling. with Primavera P6. Training Manual Project Scheduling with Primavera P6 Training Manual Development History June 2003, CPM Scheduling with SureTrak training materials developed by URS Corporation for Caltrans. SureTrak is a registered trademark

More information

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Project Cost & Schedule Monitoring Process Using MS Excel & MS Project Presented by: Rajesh Jujare About Us Solutions is founded with objectives a. To share its expertise and experiences to overcome the

More information

How To Use P6 For A Project Scheduling System

How To Use P6 For A Project Scheduling System Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

PROGRAMMING TECHNIQUES. Chapter 5(Part 2)

PROGRAMMING TECHNIQUES. Chapter 5(Part 2) PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate

More information

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 -

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision 7 - 44 - Jefferson Science Associates, LLC 600 Progress Status Project Control System Manual Revision 7-44 - 600 Progress Status This chapter of the JSA Project Control System Manual explains how the status of

More information

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003

Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Project Scheduling & Tracking

Project Scheduling & Tracking Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the

More information

<PROJECT NAME> PROJECT MANAGEMENT PLAN

<PROJECT NAME> PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Management Plan was controlled and tracked.

More information

MODEL SCHEDULING SPECIFICATION

MODEL SCHEDULING SPECIFICATION MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with

More information

P6 Analytics Reference Manual

P6 Analytics Reference Manual P6 Analytics Reference Manual Release 3.2 October 2013 Contents Getting Started... 7 About P6 Analytics... 7 Prerequisites to Use Analytics... 8 About Analyses... 9 About... 9 About Dashboards... 10 Logging

More information

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?...

PROJECT MANAGEMENT HANDBOOK, PART 1 - ISSUES COMMON TO ALL PROJECT MANAGERS. Table of Contents. Introduction... 2. Why Do We Need Schedules?... CHAPTER 15 - Scheduling Table of Contents Topic Page Introduction..... 2 Why Do We Need Schedules?.... 2 How Do We Use Schedules?...... 3 Responsibilities for Scheduling...... 3 The Basics of Scheduling........

More information

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7

PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 PROJECT MANAGEMENT IN PRIMAVERA P6 WEB ACCESS REL 7 Duration: 03 days INTRODUCTION This course provides hands-on training for Primavera s web-based solution. Participants will create a project, add activities

More information

ABSTRACT ASSESSING CPM SCHEDULING SOFTWARE FOR THE SMALL TO MID-SIZE CONSTRUCTION FIRM. Craig Vernon Hawkins, Master of Science, 2007

ABSTRACT ASSESSING CPM SCHEDULING SOFTWARE FOR THE SMALL TO MID-SIZE CONSTRUCTION FIRM. Craig Vernon Hawkins, Master of Science, 2007 BSTRCT Title of Thesis: SSESSING CPM SCHEDULING SOFTWRE FOR THE SMLL TO MID-SIZE CONSTRUCTION FIRM. Craig Vernon Hawkins, Master of Science, 2007 Thesis directed by: Kenneth J. O Connell, Ph.D. Department

More information

Project Engineers and Supervisors Conference. CPM Scheduling

Project Engineers and Supervisors Conference. CPM Scheduling Project Engineers and Supervisors Conference March 15 th and 16 th 2010 CPM Scheduling Prepared and Presented By Project Engineers and Supervisors Conference Benefits of CPM Scheduling Lessons Learned

More information

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)

108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10) CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCESA / NASA UFGS-01 32 01.00 10 (February 2015) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 32 01.00 10 (August 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

PROJECT COST ESTIMATES & FEASIBILITIES

PROJECT COST ESTIMATES & FEASIBILITIES PROJECT COST ESTIMATES & FEASIBILITIES Project Cost and budget management Project success elements Scope meet the scope defined for the project Budget It is within established budget Programme It is designed

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide

Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Schedule Test and Assessment Tool (STAT) STAT 4.0 User s Guide Health Check Summary Reports Performance Trend Schedule Trace Schedule Compare Margin Tracker Health Check Indicators Missing Predecessors

More information

Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group

Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Scheduling Best Practices Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Paul Brough has experience in multiple phases of project management, including

More information

Basic CPM Calculations

Basic CPM Calculations Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.

More information

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)

Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010) Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start

Tasks can be added manually by typing them into the list Manually adding tasks put the project manager in control and is a good way to start Project Management is the discipline of planning, organizing, and managing resources to complete a specific goal. Microsoft Project is software that helps you. Start your project Open Project 2010 and

More information

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION

SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION SECTION 013200a - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 Related Documents A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6)

Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) Guidelines for Accessing and Using the VDOT Scheduling Application (Primavera P6) CONSTRUCTION DIVISION (SCHEDULING & CONTRACTS) 1. INTRODUCTION To establish standards and consistent scheduling practices

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

Work Type Definition and Submittal Requirements 20.1 Project Scheduling. Work Type Definition

Work Type Definition and Submittal Requirements 20.1 Project Scheduling. Work Type Definition Work Type Definition Page 1-2 details the work type definition. In order to become pre-qualified for this work type, please see the Work Type Submittal Requirements on pages 3-6. I. Description Develop

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

WORK PROGRAM GUIDELINES

WORK PROGRAM GUIDELINES Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment

More information

Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012

Subcontractor Involvement Project Tracking Progress Curves. CSTM 462 Fall 2012 Subcontractor Involvement Project Tracking Progress Curves CSTM 462 Fall 2012 Subcontractor Involvement into the Critical Path Many building contractors get very little input into the schedule from their

More information

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule

763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule 763XXX Timing Analysis, Critical Path Method (CPM) Project Schedule Description: This work shall reflect a Contractor s anticipated work plan for constructing the project using a Critical Path Method Project

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006

Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006 Making CPM More Transparent By Ron Winter Ron Winter Consulting January 11, 2006 ABSTRACT This paper presents several new ideas that users of CPM software should demand of their software suppliers to increase

More information

5. Creating a Gantt Chart

5. Creating a Gantt Chart 5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the

More information