1 Responsive Space System Engineering: methodologies and tools prototype DOC-TAS-EN-001 Technical University of Lisbon, Lisbon,

2 Summary This paper reports the activities performed by Thales Alenia Space (F) and Daysha Consulting (IRL) to assess system engineering methods and tools to be developed for usage in responsive space programs for ESA. 2 Responsive Space concepts are available in the US, developed primarily for military purposes. Responsive missions are categorized in terms of rapidity from kick-off to operational phase as Tier 1 (one week), Tier 2 (one month) or Tier 3 (one year). The interest in RSSE methodology for ESA is to minimize the duration of the spacecraft development life cycle and to open new mission capabilities. Responsive Space Concepts are emerging especially in US ESA interest is to minimize S/C development cycle and open new mission capabilities

3 State of the Art methods and tools. Activity started with analysis of the State of the Art methods and tools Responsive Space Systems Engineering Activities were identified ongoing worldwide, the majority occurring in the USA. Responsive Space is at the point of operational use, and that Responsive Spacecraft development is possible, even in a timeframe as short as seven days. No single method or tool is employed to achieve Responsive satellite development, in achieved Responsive Space development M&T are used in combination, Through Brainstorming Sessions with senior engineers, 140 new ideas of tools and methodologies to minimize development duration were found. These could be condensed in 35 of particular interest for the study. These 18 SE Activities and the 35 ideas could then be regrouped in a list of 10 Methods and Tools Categories. The first activity was a Survey of State of the Art M&T. Outcome is the definition of a list of 10 Methods and Tools Categories including 53 identified M&T

4 Methods and tools categories Parallelisation of tasks: behind this concept there is the idea that tasks should be parallelised at the maximum extent 4 Building Block Modular Approach: behind this concept there are two ideas, the definition of modular spacecraft and stocks or databases of these modules Standardisation of Interfaces: behind this concept there is the idea that the building blocks interfaces are completely defined and validated for each crosscoupling Standardisation of Requirements: behind this concept there is the idea that no requirement have to be written a second time, everything is included in the definition of the constituting blocks Accept Higher Risk and possibly of Lower Quality: behind this concept there is the idea that validations could be avoided accepting higher risks and diminishing the quality of the Spacecraft design

5 Methods and tools categories Integrated Design Tool: behind this concept there is the idea that the design part could be completely automated 5 Test by Simulator: behind this concept there is the idea that many tests could be made on virtual entities Fast AIT: behind this concept there is the idea that many tests could be made on virtual entities Avoidance of Just in time procurement: behind this concept there is the idea that the procurement have to run outside the project lifecycle, every block should be already manufactured prior the start Responsive Procurement Method: behind this concept there is the idea that the procurement have to be managed differently than for standard projects, These M&T are cross-coupled

6 Applicability to ESA Each of the tools / methods identified is analysed in terms of applicability to the ESA environment. 6 Every tool has at least some applicability to the ESA environmental context Many touch critical aspects of both the ESA Systems Engineering process, as well as the overall ESA Development Cycle. The applicability of the identified M&T to ESA environment is analysed. M&T are applicable, but touching critical aspects

7 Applicability to ESA Mission needs Requirements Standardization 2 NECESSARY STEP * Applicable to ESA * Mandatory for rapid procurement * Large expected «R.O.I.» TOP LEVEL NEED * Highly applicable to ESA * Pre-requisite for RSSE 2 Interface Standardization Building Block Catalog 1 HIGH IMPORTANCE ASPECT * Applicable to ESA * Mandatory for rapid BB connections * Possible share benefit with usual prog. Complete BB virtual models Depends on Mission type Anticipated h/w production 1? 2 HIGH IMPORTANCE ASPECT * Mandatory for Tier2 * Necessary for many BB in Tier3 case * If h/w not OTS at Service call-up complete virtual models shall be available in advance 7 1 RS S/C procurement Design origin? ESA or Industry? Integrated Design Tools 2 Fast AIT 3 CONCEPT TO BE INVESTIGATED * Applicable to ESA, TBC * New concept * TBD way of implementation HIGH LEVEL NEED * Highly applicable to ESA * ESA current process very long * Necessary big change in ESA procurement philosophy LARGE NEED OF TOOL DEVT * Highly applicable to ESA * Tools shall cover all aspects, not only Design * Ultimate goal: Global tool connecting all the RS aspects (Spec, design, AIT, h/w, s/w, processes, ) 2 Test by Simulation 3 NOT A NEW CONCEPT * Applicable to ESA * TBD way of implementation Acceptance of Higher Risks and possibly Lower Quality Parallelization of tasks 3 Legend: Preliminary priority level NOT A NEW CONCEPT * Applicable to ESA * Will improve the responsiveness but not as major contributor BROAD CONCEPT * Highly applicable to ESA * Request a cultural step in ESA * TBD way of implementation Methods and Tools are analysed in term of compatibility with ESA environment, ranked in term of priority and interconnected in the design development flow

8 Spacecraft Development Cycle Analysis The study decided to focus on two LEO S/C categories to correctly estimate the impact that every M&T identified has on the development cycle: a mini satellite compliant with Tier 3 case, a micro satellite compliant with Tier 2 case. Tier 1 was considered out of scope of the analysis. 8 The study examined the defined M&T combined with the industrial practices and lessons learned from past projects to determine a first estimate of the S/C development cycle duration for both cases, the best tools implementing the methodologies, the requirements of these tools in a top down approach, the costs and development planning of these tools the applicability these tools have to CDF environment When analysing current Thales Alenia Space products it is possible to note that various methodologies identified are already in place up to a certain level. Ex: Proteus and Prima Standard Mini Satellite class Platforms are already part of the NASA RSDO (Rapid Spacecraft Development Office) catalogue. Methods and Tools are analysed in term of compatibility with ESA environment, ranked in term of priority and interconnected in the design / development flow

9 Responsive Spacecraft Development Cycles 9 Tier 2 (left) and Tier 3 (right) development flow as retained possible adopting all the identified M&T

10 Tools supporting RS Development Cycles 10 The Tools identified as necessary to achieve RS capabilities are: MDT: Mission Design Tool To generate a mission design rapidly considering all the RS context through dynamic links with all RS databases SPT: Satellite Procurement Tool To rapidly elaborate the procurement package following a specific responsive format BBMT: Building Block Management Tool To exploit the RS various databases (satellites components, launcher capacities, RS facilities, etc ) and link them to the other RS tools (MDT, SVM, DMT, ) SVM: Satellite Virtual Model Complete model of the satellite used as the reference for the whole spacecraft development sequences (design, performances assessment, manufacturing, testing) DMT: Development Management Tool To simulate accurately all the times aspects related to the satellite development (as well for anticipation as for activities follow-up or tracking or reporting) TOG: Teams Organization & Geo-location To optimize and organize all the RS resources and facilities SPAT: Staff Performance Assessment Tool To manage and optimize the work efficiency of the shared activities (especially when several teams are working in parallel), to optimize the information exchange between the team members and 7 tools are identified as necessary to support Responsive Space Development Cycles

11 Responsive Space Tools Trade-Offs 11 The consortium performed a complete analysis of the gains expected coming from the use of the tools in the various phases. The tools used in the development phase showed good planning benefits, they play an important role in matching the planning of an RS project. This is consistent with the fact that those tools are applicable to the development and production phases phases that have the longest timeframes and largest resource consumption. Two tools show similar planning benefits and are expected to play a major role in the matching of RS projects planning for both TIER categories The Satellite Virtual Model The Development Management Tool with the TOG and SPAT plug-ins A complete trade-off among tools is performed to determine the most efficient. The winners are the Satellite Virtual Model and the Development Management Tool

12 Responsive Space Tools Trade-Offs 12 The trade is based on multiple criteria, covering costs, development duration and effort, applicability to Industry, ESA in general and to CDF in particular

13 Responsive Space Tools Development Plan 13 The road map for RS capabilities implementation in ESA requires successive tools and methodologies development. Activities should be made in cooperation with interested industries helping to support the road map. Activities should be held with a specific mission in the road map to stimulate industry to concur to the solution proposing innovation. In principle a tight planning can provide a first RS prototype application in 5 years, a time scale equivalent with standard satellites. In fact most of the program duration would be taken to define the supporting tools and methodologies. Advantages will be seen only as from the second application. Complete development plan is estimated on the basis of the development duration of the various tools and their interdependencies. The time scale is equivalent with std satellites, advantages will arrive since the 2 nd satellite

14 Responsive Space Tools Development Plan 14 ID Task Start End Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q Q Q1 Q2 Q3 Q Q1 Q2 Q3 Q4 1 Call for Interested Industries 01/01/ /09/ Standard IF definition 01/05/ /05/ Definition of Responsive Procurement normative framework 28/03/ /09/ Definition of acceptable quality and complexity for RS missions 01/04/ /04/ Definition of Virtual Models and frame for testing and validation through simulators 04/10/ /04/ Standard requirements definition 01/06/ /06/ Building Block Catalogue 03/10/ /12/2018 Standard equipments and procedures 8 07/04/ /01/2018 for automatic AIT/AIV 9 MDT 09/06/ /12/ BBMT 21/11/ /12/ SVM 24/04/ /12/ SPT 01/12/ /12/ DMT 23/05/ /12/ TOG 23/03/ /12/ SPAT 05/06/ /12/ First RS mission 05/01/ /01/ years is a good time scale to develop RS capabilities. Shorter time frame could be possible when starting with smaller satellites.

15 Tool prototype definition 15 To finalize the study the team developed a prototype edition of the RS environment. To limit development duration only a subset of the identified tools, and a mock up edition of the remaining was achieved. One tool in particular, the programmatics domain specific tool was the central focus of the effort as it deemed the most interesting from CDF perspective. Due similarities the tool development went in parallel: one dedicated to RSSE a version applicable to Concurrent Engineering and CDF Sessions. Thales Alenia Space and Daysha Developed a mock-up of an entire RS framework, prototyping only few fonctionalities. The focus was the Development Management tool interesting also for CDF

16 Tool prototype schema 16 RSSE Environment Intelligence Standard High Level Requiements Design Algo s Planning Algo s Risk Algo s DST Visualiser Staff performance assessment Agenda (TOG) RS BB DB Virtual Models DST Environment/s CATIA Simulators Planning Others DBs Functions completely prototype are encircled Supporting functions, partially prototyped are dotted Other parts are only mocked-up

17 Planning Algorithm To develop a version of the tool for usage in standard project in CDF a specific planning for standard project was also included on the basis of past projects planning. 17 The same set of projects was used to derive statistical data and define a planning algorithm as core of the tool. Proteus Jason 1 + 5PF (Calypso, Corot, SMOS, Jason 2, Jason 3) Myriade Picard (CNES) Herschel and Plank The first two classes are applicable for RSSE area of interest, but they benefit from the product line effect. The various Proteus Platforms are derived from the first model (Jason 1), with lessons learned helping to decrease the development duration for each subsequent mission. H/P is introduced to provide good single-model prototype base. CDF studies, with ESA s science department often the customer, are more related to single-model prototypes than product lines. Planning Algorithm is introduced to support programmatics discipline to determine the planning for CDF studies using TAS planning database

18 Building Block Database 18 To support the prototype demonstration the Building Blocks database is filled with two existing spacecraft functional chains compatible Tier 2 and Tier 3: The ELiTe P/F TheTAS Myriade P/F Myriade and Elite P/Fs data are used to support prototype demonstration

19 Mission Design Tool 19

20 Building Block Database 20

21 Development Management Tool 21

22 Development Management Tool Algorithm 22

23 Development Management Tool Algorithm settings 23

24 Development Management Tool Algorithm settings 24

25 Development Management Tool Probability Chart 25

26 Building Block Database Timeline view 26

27 Development Management Tool Export 27

28 Conclusions The analyses performed on the study gave a better insight on a complex matter that is how to diminish program duration to its lower level. 28 It is challenging, but possible to develop a complete Spacecraft in time as short as one month. Multiple methodologies exist and many are already partially implemented in spacecraft lifecycle especially on commercial products. All the methodologies found are applicable to ESA environment, but requiring critical changes in the current process. Responsive Space System Office should be possibly created with ad hoc policies in order to bypass current limitations that can remain for standard project. Many of the methodologies are applicable to standard project helping in minimizing the duration, but also allowing a better reuse of products, reducing delta-developments and delta-qualifications. The software layer is important to implement the methodologies. Many tools could play an important role to diminish the duration of studies or to better assess duration of standard projects since the beginning. It is possible to perform Responsive Space Program in timeline as short as 7 days also in ESA environemnt. Methodologies and Tools exists and could be possibly help reducind duration also of standard programs

29 Conclusions An extensive analysis of each tool, allowed to determine the best suited tool to be prototyped in the frame of the study a consistent road map for Responsive Space Capabilities implementation in ESA. 29 RS capabilities can be implemented for ESA in a timeframe comparable with short standard programs, roughly five years. It may be possible to shorten this timeframe implementing RS capabilities for nano-satellites first. While the RS framework had to be only mocked-up for study limitations, the focus of the development was ported to the Development Management Tool. This tool was determined to be the most valuable for the study and to achieve RS capabilities. It was possible to make it applicable to the CDF for standard studies. A complete analysis of the tools is performed allowing to determine the best tool suite to be prototyped and a consistent development plan

IFS-8000 V2.0 INFORMATION FUSION SYSTEM

IFS-8000 V2.0 INFORMATION FUSION SYSTEM IFS-8000 V2.0 INFORMATION FUSION SYSTEM IFS-8000 V2.0 Overview IFS-8000 v2.0 is a flexible, scalable and modular IT system to support the processes of aggregation of information from intercepts to intelligence

More information

PLM Customer Reference. Grundfos. Revolutionising pump technology with PLM solutions from IBM and Dassault Systèmes

PLM Customer Reference. Grundfos. Revolutionising pump technology with PLM solutions from IBM and Dassault Systèmes PLM Customer Reference Grundfos Revolutionising pump technology with PLM solutions from IBM and Dassault Systèmes Grundfos Objectives Constantly innovate product design to meet strict efficiency targets

More information

OCDT-DEE. Open Concurrent Design Tool Deployment, Enhancement and Exploitation

OCDT-DEE. Open Concurrent Design Tool Deployment, Enhancement and Exploitation OCDT-DEE Open Concurrent Design Tool Deployment, Enhancement and Exploitation OCDT Background OCDT developed to provide ESA with an upgraded infrastructure built around the ECSS-E-TM-10-25 data model support

More information

SAP RAPID DEPLOYMENT FOR APPLICATION LIFECYCLE MANAGEMENT WAVE TEST MANAGEMENT INFORMATION SHEET FOR SERVICE DELIVERY

SAP RAPID DEPLOYMENT FOR APPLICATION LIFECYCLE MANAGEMENT WAVE TEST MANAGEMENT INFORMATION SHEET FOR SERVICE DELIVERY SAP RAPID DEPLOYMENT FOR APPLICATION LIFECYCLE MANAGEMENT WAVE TEST MANAGEMENT INFORMATION SHEET FOR SERVICE DELIVERY In the context of application lifecycle management testing is a significant phase to

More information

The Software Process. The Unified Process (Cont.) The Unified Process (Cont.)

The Software Process. The Unified Process (Cont.) The Unified Process (Cont.) The Software Process Xiaojun Qi 1 The Unified Process Until recently, three of the most successful object-oriented methodologies were Booch smethod Jacobson s Objectory Rumbaugh s OMT (Object Modeling

More information

The DLR Concurrent Engineering Facility (CEF)

The DLR Concurrent Engineering Facility (CEF) The DLR Concurrent Engineering Facility (CEF) January 2011 Andy Braukhane DLR Institute of Space Systems System Analysis Space Segment Slide 1 Overview DLR Institute of Space Systems System Analysis Space

More information

REDUCE COSTS AND ACHIEVE YOUR GOALS WITH EFFECTIVE MANPOWER PAYROLL PLUS

REDUCE COSTS AND ACHIEVE YOUR GOALS WITH EFFECTIVE MANPOWER PAYROLL PLUS REDUCE COSTS AND ACHIEVE YOUR GOALS WITH EFFECTIVE MANPOWER PAYROLL PLUS PAYROLL PLUS One of the most significant factors giving the competitive edge to all corporations is human resources. Welltrained

More information

For more information about UC4 products please visit www.uc4.com. Automation Within, Around, and Beyond Oracle E-Business Suite

For more information about UC4 products please visit www.uc4.com. Automation Within, Around, and Beyond Oracle E-Business Suite For more information about UC4 products please visit www.uc4.com Automation Within, Around, and Beyond Oracle E-Business Suite Content Executive Summary...3 Opportunities for Enhancement: Automation Within,

More information

ENHANCING INTELLIGENCE SUCCESS: DATA CHARACTERIZATION Francine Forney, Senior Management Consultant, Fuel Consulting, LLC May 2013

ENHANCING INTELLIGENCE SUCCESS: DATA CHARACTERIZATION Francine Forney, Senior Management Consultant, Fuel Consulting, LLC May 2013 ENHANCING INTELLIGENCE SUCCESS: DATA CHARACTERIZATION, Fuel Consulting, LLC May 2013 DATA AND ANALYSIS INTERACTION Understanding the content, accuracy, source, and completeness of data is critical to the

More information

COMOS. The software solution for integrated plant management. www.siemens.com/comos

COMOS. The software solution for integrated plant management. www.siemens.com/comos COMOS The software solution for integrated plant management www.siemens.com/comos COMOS From Integrated Engineering to Integrated Operations Increasing global competition requires productivity and quality

More information

Reducing Total Cost of Ownership for Oracle Retail

Reducing Total Cost of Ownership for Oracle Retail WHITE PAPER Reducing Total Cost of Ownership for Oracle Retail Introduction... 2 Batch Integration and Scheduling for Retail Applications... 2 UC4 Retail Solution Overview... 3 Subset of Oracle Retail

More information

Eldorado Research Institute. Photo: Halo, Aug 2008 Campinas sky in the first working day at new Eldorado building

Eldorado Research Institute. Photo: Halo, Aug 2008 Campinas sky in the first working day at new Eldorado building Eldorado Research Institute Photo: Halo, Aug 2008 Campinas sky in the first working day at new Eldorado building Agenda Context: Sw offshoring and tech tendencies What is Eldorado Institute? Eldorado experience

More information

REGIONAL ROVER FOR 1: MARS ANNEXE B SYSTEM REQUIREMENTS SCOUTING AND SAMPLE COLLECTION PART MARS ROVER CHASSIS DOCUMENT

REGIONAL ROVER FOR 1: MARS ANNEXE B SYSTEM REQUIREMENTS SCOUTING AND SAMPLE COLLECTION PART MARS ROVER CHASSIS DOCUMENT document title/ titre du document REGIONAL MARS ROVER FOR SCOUTING AND SAMPLE COLLECTION PART 1: MARS ROVER CHASSIS ANNEXE B 1: SYSTEM REQUIREMENTS DOCUMENT prepared by/pré paré par ESA reference/ré ference

More information

IMA for space Status and Considerations

IMA for space Status and Considerations IMA for space Status and Considerations Paul ARBERET CNES DCT/SB/LV L IMA dans tous ces états - Toulouse 21 Juin 2007 1 IMA for Space Status and considerations Introduction Standardisations tentatives

More information

Concurrent Engineering Applied to Space Mission Assessment and Design

Concurrent Engineering Applied to Space Mission Assessment and Design r bulletin 99 september 1999 Concurrent Engineering Applied to Space Mission Assessment and Design M. Bandecchi & B. Melton Mission Control Systems Division, ESA Directorate for Technical and Operational

More information

CMII-100H. CMII Standard for Enterprise-Wide Configuration Management and Integrated Process Excellence. by the Institute of Configuration Management

CMII-100H. CMII Standard for Enterprise-Wide Configuration Management and Integrated Process Excellence. by the Institute of Configuration Management CMII-100H CMII Standard for Enterprise-Wide Configuration Management and Integrated Process Excellence by the Institute of Configuration Management and CMII Research Institute Revision H; Released March

More information

System Engineering Data Repository

System Engineering Data Repository System Data Repository 09:00 data in the MBSE life-cycle 09:20 EGS-CC in the system context 09:40 Conceptual Modelling and ECSS 10:00 ecascade 10:20 A snapshot of systems engineering data management in

More information

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended.

TDWI strives to provide course books that are content-rich and that serve as useful reference documents after a class has ended. Previews of TDWI course books offer an opportunity to see the quality of our material and help you to select the courses that best fit your needs. The previews cannot be printed. TDWI strives to provide

More information

Tableau Metadata Model

Tableau Metadata Model Tableau Metadata Model Author: Marc Reuter Senior Director, Strategic Solutions, Tableau Software March 2012 p2 Most Business Intelligence platforms fall into one of two metadata camps: either model the

More information

Future Multi-Mission Satellite Operations Centers Based on an Open System Architecture and Compatible Framework

Future Multi-Mission Satellite Operations Centers Based on an Open System Architecture and Compatible Framework Future Multi-Mission Satellite Operations Centers Based on an Open System Architecture and Compatible Framework GSAW 2014 Thomas J. Sullivan, Aerospace Ground Systems Lab Rico Espindola, MMSOC Flight Operations

More information

Project Management and Budgeting for Communicators MPPR- 837-01. Office hours: By appointment and before class

Project Management and Budgeting for Communicators MPPR- 837-01. Office hours: By appointment and before class Course: Project Management and Budgeting for Communicators MPPR- 837-01 Fall 2014 August 28 December 11 Thursdays 8pm to 10:30 pm Downtown Campus Professor Eileen Marcus Office hours: By appointment and

More information

TRIAX- D. Consulting services to accelerate your supply chain automation outcomes. The resourceful services of Logi-D

TRIAX- D. Consulting services to accelerate your supply chain automation outcomes. The resourceful services of Logi-D 010100101001010101010100110010101010101100110011010101010101011001100011010101011 0101010011010100110101001101010010100110101010010101001001010010 0101001011000101011010101100010101001110010010110011010100110101

More information

RETAIL MANAGEMENT SYSTEM

RETAIL MANAGEMENT SYSTEM RETAIL MANAGEMENT SYSTEM Introduction & presentation of problem Store Lifecycle Tool: optimising power for your company Efficient company management is the foundation of a successful business. The Store

More information

Accelerating Time to Market with Agile Testing

Accelerating Time to Market with Agile Testing WHITEPAPER Accelerating Time to Market with Agile Testing By Balaji Uppili To discover how GAVS can help you innovate and bring greater value to your business, write to inquiry@gavstech.com or visit www.gavstech.com.

More information

Service Portfolio Management PinkVERIFY

Service Portfolio Management PinkVERIFY -11-G-001 General Criteria Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 Edition workflows and process integrations? -11-G-002 Does the tool have security controls in place to

More information

PLM Center of Excellence PLM for Embedded Product Development - Challenges, Experiences and Solution. M a y 2 0 0 9

PLM Center of Excellence PLM for Embedded Product Development - Challenges, Experiences and Solution. M a y 2 0 0 9 PLM Center of Excellence PLM for Embedded Product Development - Challenges, Experiences and Solution M a y 2 0 0 9 Table of Contents Abstract 3 Introduction 4 Embedded product development life cycle 4

More information

IBIS DOCUMENT TYPE: INSTRUMENT MANAGEMENT PLAN. DOCUMENT No.: TL PAGE: I of V,26. PROJECT Ref.: ISSUE No.: Draft DATE: January, 97 CHECKED BY:

IBIS DOCUMENT TYPE: INSTRUMENT MANAGEMENT PLAN. DOCUMENT No.: TL PAGE: I of V,26. PROJECT Ref.: ISSUE No.: Draft DATE: January, 97 CHECKED BY: DOCUMENT TYPE: PLAN TITLE: INSTRUMENT MANAGEMENT PLAN DOCUMENT No.: TL PAGE: I of V,26 PROJECT Ref.: ISSUE No.: Draft DATE: January, 97 PREPARED BY: G. FUGGETTA CHECKED BY: SYSTEM MANAGER: DATE: PAPM:

More information

Smart Industrial Manufacturing

Smart Industrial Manufacturing Robots-as-a-Service 2016 TM Forum Live! 2016 1 Best New Catalyst Award TMF Live 2016, Nice, France 2016 TM Forum Live! 2016 2 This Catalyst goes beyond the scope of traditional Machineto-Machine (M2M)

More information

Non-Stop Manufacturing Excellence. Automotive. Answers for industry.

Non-Stop Manufacturing Excellence. Automotive. Answers for industry. Non-Stop Manufacturing Excellence. Automotive Answers for industry. Answers to your challenges How can the potential of emerging markets be best economically tapped? What possibilities are there of reducing

More information

focus, A NEW CONCEPT ON FLIGHT DYNAMICS OPERATIONS

focus, A NEW CONCEPT ON FLIGHT DYNAMICS OPERATIONS focus, A NEW CONCEPT ON FLIGHT DYNAMICS OPERATIONS Miguel Angel Molina Cobos Flight Engineering Business Unit Director GMV c/ Isaac Newton, 11; PTM Tres Cantos 28760 Madrid (Spain) Tf: +34 918072100; Fax:

More information

State of Oregon. State of Oregon 1

State of Oregon. State of Oregon 1 State of Oregon State of Oregon 1 Table of Contents 1. Introduction...1 2. Information Asset Management...2 3. Communication Operations...7 3.3 Workstation Management... 7 3.9 Log management... 11 4. Information

More information

On-board Software Reference Architecture for Payloads

On-board Software Reference Architecture for Payloads On-board Software Reference Architecture for Payloads Presenters Victor Bos, phone: +358 400897907, email: victor.bos@ssf.fi Adam Trcka, phone: +420 736650822, email: adam.trcka@evolvsys.cz Introduction

More information

VISION. Inventory management with the intelligence to help you balance supply with demand throughout the supply chain BROCHURE

VISION. Inventory management with the intelligence to help you balance supply with demand throughout the supply chain BROCHURE VISION Inventory management with the intelligence to help you balance supply with demand throughout the supply chain BROCHURE THE VISION ADVANTAGE Range and category management should not be a monthly

More information

Federal Secure Cloud Testing as a Service - TaaS Center of Excellence (CoE) Robert L. Linton

Federal Secure Cloud Testing as a Service - TaaS Center of Excellence (CoE) Robert L. Linton Session 5: Federal Secure Cloud Testing as a Service - TaaS Center of Excellence (CoE) Robert L. Linton Agenda HP ALM Solution Review HP Cloud Potential Cloud Portal HP ALM Solutions in a virtual environment

More information

Software Development Life Cycle (SDLC)

Software Development Life Cycle (SDLC) Software Development Life Cycle (SDLC) Supriyo Bhattacharjee MOF Capability Maturity Model (CMM) A bench-mark for measuring the maturity of an organization s software process CMM defines 5 levels of process

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

Qlik UKI Consulting Services Catalogue

Qlik UKI Consulting Services Catalogue Qlik UKI Consulting Services Catalogue The key to a successful Qlik project lies in the right people, the right skills, and the right activities in the right order www.qlik.co.uk Table of Contents Introduction

More information

IEEE SESC Architecture Planning Group: Action Plan

IEEE SESC Architecture Planning Group: Action Plan IEEE SESC Architecture Planning Group: Action Plan Foreward The definition and application of architectural concepts is an important part of the development of software systems engineering products. The

More information

Introducing ECSS Software-Engineering Standards within ESA

Introducing ECSS Software-Engineering Standards within ESA r bulletin 111 august 2002 Introducing ECSS Software-Engineering Standards within ESA Practical approaches for space- and ground-segment software M. Jones & E. Gomez Ground Segment Engineering Department

More information

Network Discovery Protocols Status. Peter Mendham

Network Discovery Protocols Status. Peter Mendham Network Discovery Protocols Status Peter Mendham 22 April 2012 Agenda Activity overview Requirements approach Requirements overview Protocol approach Protocol status 2 SciSys Overview Activity Scope There

More information

Evaluation of agility in software development company

Evaluation of agility in software development company Evaluation of agility in software development company Gusts Linkevics Riga Technical University, Riga, Latvia, gusts@parks.lv Abstract Organization s and team s experience in agile methodology can be more

More information

2012 Global Retail, Fashion and Apparel PLM Product Differentiation Excellence Award

2012 Global Retail, Fashion and Apparel PLM Product Differentiation Excellence Award 2012 2012 Global Retail, Fashion and Apparel PLM Product Differentiation Excellence Award 2012 Frost & Sullivan 1 We Accelerate Growth Product Differentiation Excellence Award Retail, Fashion and Apparel

More information

EChO Ground Segment: Overview & Science Operations Assumptions

EChO Ground Segment: Overview & Science Operations Assumptions EChO Ground Segment: Overview & Science Operations Assumptions Matthias Ehle & the Science Ground Segment Working Group EChO Science Operations Study Manager ESA-ESAC, Madrid Science Operations Department/Division

More information

PRINTVIS: Your Printing Industry Solution Based on Microsoft Dynamics NAV

PRINTVIS: Your Printing Industry Solution Based on Microsoft Dynamics NAV PRINTVIS: Your Printing Industry Solution Based on Microsoft Dynamics NAV PrintVis: Your Printing Industry Solution Based on Microsoft Dynamics NAV From management and financials all the way to the production

More information

SMARTPLANT ENTERPRISE

SMARTPLANT ENTERPRISE INDUSTRY SMARTPLANT ENTERPRISE For the Metals and Mining Industry INDUSTRY CHALLENGES Metals and mining facilities are increasingly complex and large in scope, with mega-projects becoming the norm. There

More information

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy

Offshore Wind Farm Layout Design A Systems Engineering Approach. B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy Offshore Wind Farm Layout Design A Systems Engineering Approach B. J. Gribben, N. Williams, D. Ranford Frazer-Nash Consultancy 0 Paper presented at Ocean Power Fluid Machinery, October 2010 Offshore Wind

More information

ATV Data Link Simulator: A Development based on a CCSDS Layers Framework

ATV Data Link Simulator: A Development based on a CCSDS Layers Framework SpaceOps 2010 ConferenceDelivering on the DreamHosted by NASA Mars 25-30 April 2010, Huntsville, Alabama AIAA 2010-2089 ATV Data Link Simulator: A Development based on a CCSDS

More information

Enhanced spare part engineering support

Enhanced spare part engineering support Enhanced spare part engineering support Smart spare parts' design for a part standardisation The Airbus ing team has developed the capability to create efficient engineering solutions for the design of

More information

INCOSE Automotive Working Group Charter

INCOSE Automotive Working Group Charter 1 PURPOSE 2 GOALS 3 SCOPE To promote the application and advance the practice of Systems Engineering in the automotive industry, encompassing OEMs, suppliers and service providers in the private, commercial

More information

Essential NCPI Management Requirements for Next Generation Data Centers

Essential NCPI Management Requirements for Next Generation Data Centers Essential NCPI Requirements for Next Generation Data Centers By Ted Ives White Paper #14 1 Executive Summary The management of physical infrastructure in data centers can no longer be considered independently

More information

MANDARIN ORIENTAL HOTEL GROUP REPORT SUMMARY

MANDARIN ORIENTAL HOTEL GROUP REPORT SUMMARY MANDARIN ORIENTAL HOTEL GROUP REPORT SUMMARY THE COMPANY Established in Hong Kong in 1963. Mandarin Oriental Hotel Group is an international hotel investment and management group operating ten hotels in

More information

Defining, Modeling & Costing IT Services Integrating Service Level, Configuration & Financial Management Processes

Defining, Modeling & Costing IT Services Integrating Service Level, Configuration & Financial Management Processes Defining, Modeling & Costing IT Services Integrating Service Level, Configuration & Financial Management Processes In our cost driven economy IT is facing increasing pressure to account for and reduce

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

CRM University. Course Catalog. BC010 Boot Camp With a focus on the business use of Microsoft Dynamics CRM, the boot

CRM University. Course Catalog. BC010 Boot Camp With a focus on the business use of Microsoft Dynamics CRM, the boot Course Description Duration BC010 Boot Camp With a focus on the business use of Microsoft Dynamics CRM, the boot camp covers the entire application in detail. Using hands-on labs in a a training environment

More information

Introduction to Systems Analysis and Design

Introduction to Systems Analysis and Design Introduction to Systems Analysis and Design What is a System? A system is a set of interrelated components that function together to achieve a common goal. The components of a system are called subsystems.

More information

HP Brazil RFID CoE Center of Excellence

HP Brazil RFID CoE Center of Excellence HP Brazil RFID CoE Center of Excellence TEST CENTER DESCRIPTION: The RFID Center of Excellence is prepared to aid customers to visualize in their businesses possible RFID applications as well as to observe

More information

Australian Government Data Centre Strategy Industry Briefing - 2 December 2010

Australian Government Data Centre Strategy Industry Briefing - 2 December 2010 Australian Government Data Centre Strategy Industry Briefing 2 December 2010 Introduction The Australian Government s Data Centre Strategy (the Strategy) is a long term program of work with a primary objective

More information

The IBM Solution Architecture for Energy and Utilities Framework

The IBM Solution Architecture for Energy and Utilities Framework IBM Solution Architecture for Energy and Utilities Framework Accelerating Solutions for Smarter Utilities The IBM Solution Architecture for Energy and Utilities Framework Providing a foundation for solutions

More information

How To Understand The Business Analysis Lifecycle

How To Understand The Business Analysis Lifecycle Business Analysis Lifecycle by Sergey Korban Aotea Studios Ltd November 2011 Contents Introduction... 3 Business Analysis Lifecycle... 4 Practical Application... 5 Start-Up Phase... 5 Initiation Phase...

More information

Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007

Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007 Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT

More information

Space project management

Space project management ECSS-M-ST-80C Space project management Risk management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of ECSS Standards

More information

Use project management tools

Use project management tools Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding

More information

How to Become a Data Driven Business

How to Become a Data Driven Business January 2012 Executive summary Becoming a Data Driven Business, particularly from a Marketing perspective, presents significant benefits in helping your business to grow, develop and succeed, by working

More information

An Introduction to the ECSS Software Standards

An Introduction to the ECSS Software Standards An Introduction to the ECSS Software Standards Abstract This introduces the background, context, and rationale for the creation of the ECSS standards system presented in this course. Addresses the concept

More information

Mata : Garuda An advanced Network Monitoring System The S.L.A.D Network Security Framework. FIRST Conference Berlin, 19 June 2015

Mata : Garuda An advanced Network Monitoring System The S.L.A.D Network Security Framework. FIRST Conference Berlin, 19 June 2015 Mata : Garuda An advanced Network Monitoring System The S.L.A.D Network Security Framework FIRST Conference Berlin, 19 June 2015 1 Security in Real Life 2 3 Car Alarms Network Security Alarms 4 Our responsibility

More information

Simulated tests, real results

Simulated tests, real results Business white paper Simulated tests, real results These companies are using HP Service Virtualization to overcome testing challenges, accelerate delivery, and improve quality. So can yours. Table of contents

More information

Find, Control and Optimize your Engineering Simulation Information

Find, Control and Optimize your Engineering Simulation Information Aerospace & Defense Find, Control and Optimize your Engineering Simulation Information Bruno Marcantonio IBM - Software Group Brand Information Management Email: bruno.marcantonio@it.ibm.com Tel. +39 335

More information

CONDIS. IT Service Management and CMDB

CONDIS. IT Service Management and CMDB CONDIS IT Service and CMDB 2/17 Table of contents 1. Executive Summary... 3 2. ITIL Overview... 4 2.1 How CONDIS supports ITIL processes... 5 2.1.1 Incident... 5 2.1.2 Problem... 5 2.1.3 Configuration...

More information

Software Design Document (SDD) Template

Software Design Document (SDD) Template (SDD) Template Software design is a process by which the software requirements are translated into a representation of software components, interfaces, and data necessary for the implementation phase.

More information

Applying 4+1 View Architecture with UML 2. White Paper

Applying 4+1 View Architecture with UML 2. White Paper Applying 4+1 View Architecture with UML 2 White Paper Copyright 2007 FCGSS, all rights reserved. www.fcgss.com Introduction Unified Modeling Language (UML) has been available since 1997, and UML 2 was

More information

Background. Scope. Organizational Training Needs

Background. Scope. Organizational Training Needs 1 Training Plan Template As described in Section 4.2.1 of the Training Effectiveness Toolkit, a Training Plan will help define the specific activities that will be conducted to carry out the training strategy.

More information

Managing Commercial-Off-the- Shelf (COTS) Integration for High Integrity Systems: How Far Have We Come? Problems and Solutions in 2003

Managing Commercial-Off-the- Shelf (COTS) Integration for High Integrity Systems: How Far Have We Come? Problems and Solutions in 2003 GSAW 2003 Managing Integration Breakout Session Summary Managing Commercial-Off-the- Shelf () Integration for High Integrity Systems: How Far Have We Come? Problems and Solutions in 2003 Karen Owens, Suellen

More information

Automated Drop Ship Order Processing in R12

Automated Drop Ship Order Processing in R12 Automated Drop Ship Order Processing in R12 Kenneth B. Montgomery BizTech Introduction: This presentation will demonstrate the functional and technical aspects of an automated sourcing model for a non-profit

More information

Driving Reuse in the Supply Chain

Driving Reuse in the Supply Chain Driving Reuse in the Supply Chain The Cisco Systems Journey May 2014 2014 Perception Software. All rights reserved. 1 Contents Executive Summary The Cisco Challenge on Reuse 3 Why Reuse? 4 Cost, Quality

More information

OF 1.3 Testing and Challenges

OF 1.3 Testing and Challenges OF 1.3 Testing and Challenges May 1 st, 2014 Ash Bhalgat (Senior Director, Products), Luxoft Santa Clara, CA USA April-May 2014 1 Agenda OpenFlow : What and Why? State of OpenFlow Conformance Challenges

More information

Preparing for Unannounced Inspections from Notified Bodies

Preparing for Unannounced Inspections from Notified Bodies Preparing for Unannounced Inspections from Notified Bodies Europe has introduced further measures for unannounced audits of manufacturers by notified bodies. With this in mind, James Pink, VP Europe-Health

More information

Design Verification. Introduction

Design Verification. Introduction Design verification is an essential step in the development of any product. Also referred to as qualification testing, design verification ensures that the product as designed is the same as the product

More information

Telecom Equipment Assurance Testing

Telecom Equipment Assurance Testing Telecom Equipment Assurance Testing T.V.Prabhakar, Gopi Krishna S Garge, Indian Institute of Science Bangalore Agenda Overview of the TETC Security Testing & requirements Security Standards? Is there a

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

SIMATIC IT Production Suite Answers for industry.

SIMATIC IT Production Suite Answers for industry. Driving Manufacturing Performance SIMATIC IT Production Suite Answers for industry. SIMATIC IT at the intersection of value creation processes With SIMATIC IT, Siemens is broadening the scope of MES. Plant

More information

Buskerud University College: Program Systems Engineering

Buskerud University College: Program Systems Engineering : Program Systems Engineering - market and customer context life cycle context system architecting multi-disciplinary design mono-discipline mono-disciplinary engineering mono-discipline Frogs vei 41 P.O.

More information

Using big data in automotive engineering?

Using big data in automotive engineering? Using big data in automotive engineering? ETAS GmbH Borsigstraße 14 70469 Stuttgart, Germany Phone +49 711 3423-2240 Commentary by Friedhelm Pickhard, Chairman of the ETAS Board of Management, translated

More information

Arizona Association of Student Councils

Arizona Association of Student Councils 1. Communication 1.1 Student communicates effectively in large and small groupings 1.1.a Student develops content and ideas into organized presentations. 1.1b Student learn to monitor and adjust based

More information

ALM120 Application Lifecycle Management 11.5 Essentials

ALM120 Application Lifecycle Management 11.5 Essentials ALM120 Application Lifecycle Management 11.5 Essentials Instructor-Led Workshop OVERVIEW This course provides the tools you need to implement and use Quality Center 11.50. Students learn how to manage

More information

The PACS Software System. (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1.

The PACS Software System. (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1. The PACS Software System (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1.0 PICC-ME-DS-003 1. Introduction The PCSS, the PACS ICC Software System, is the

More information

Cisco IT Hadoop Journey

Cisco IT Hadoop Journey Cisco IT Hadoop Journey Srini Desikan, Program Manager IT 2015 MapR Technologies 1 Agenda Hadoop Platform Timeline Key Decisions / Lessons Learnt Data Lake Hadoop s place in IT Data Platforms Use Cases

More information

OPM3. Project Management Institute. OPM3 in Action: Pinellas County IT Turns Around Performance and Customer Confidence

OPM3. Project Management Institute. OPM3 in Action: Pinellas County IT Turns Around Performance and Customer Confidence Project Management Institute OPM3 case study : OPM3 in Action: Pinellas County IT Turns Around Performance and Customer Confidence OPM3 Organizational Project Management Maturity Model Project Management

More information

Space Project Management

Space Project Management EUROPEAN COOPERATION FOR SPACE STANDARDIZATION Space Project Management Configuration Management Secretariat ESA ESTEC Requirements & Standards Division Noordwijk, The Netherlands Published by: Price:

More information

Software Change Management for Engineering Systems

Software Change Management for Engineering Systems Audit Report Report Number IT-AR-16-007 June 13, 2016 Software Change Management for Engineering Systems Our objective was to evaluate the effectiveness of the software change management process for Engineering

More information

SNA Annual National Conference Web Based Supply Chain Management. June 2009

SNA Annual National Conference Web Based Supply Chain Management. June 2009 SNA Annual National Conference Web Based Supply Chain Management June 2009 AGENDA WBSCM Overview & Status Deployment Preparation WBSCM Demonstrations WBSCM Processes Questions & Answers WBSCM Program Overview

More information

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development

Project Type Guide. Project Planning and Management (PPM) V2.0. Custom Development Version 1.1 January 2014. PPM Project Type Custom Development Project Planning and Management (PPM) V2.0 Project Type Guide Custom Development Version 1.1 January 2014 Last Revision: 1/22/2014 Page 1 Project Type Guide Summary: Custom Development Custom software

More information

CHAPTER 1. Introduction to CAD/CAM/CAE Systems

CHAPTER 1. Introduction to CAD/CAM/CAE Systems CHAPTER 1 1.1 OVERVIEW Introduction to CAD/CAM/CAE Systems Today s industries cannot survive worldwide competition unless they introduce new products with better quality (quality, Q), at lower cost (cost,

More information

GSAW 2015 Session 11B: Frameworks in Action A Foundation for Service Based Architectures

GSAW 2015 Session 11B: Frameworks in Action A Foundation for Service Based Architectures National Aeronautics and Space Administration GSAW 2015 Session 11B: Frameworks in Action A Foundation for Service Based Architectures s Open Architecture Framework March 4, 2015 Los Angeles, California

More information

Customised programmes

Customised programmes Customised programmes for your company s needs Design your education programme Table of Contents P03 Steinbeis Business Academy P04 Your benefit - Project Competence Concept P05 Added value for the customer

More information

Test Automation -Selenium

Test Automation -Selenium Test Automation -Selenium Presented By: Sachin Kumar 10-Dec-2011 About Corbus Corbus, LLC, a global solutions provider founded in 1994, offers superior services combining years of experience, solid partnerships

More information

Cross platform Migration of SAS BI Environment: Tips and Tricks

Cross platform Migration of SAS BI Environment: Tips and Tricks ABSTRACT Cross platform Migration of SAS BI Environment: Tips and Tricks Amol Deshmukh, California ISO Corporation, Folsom, CA As a part of organization wide initiative to replace Solaris based UNIX servers

More information

Mission Operation Ground. Assurance @ ESA. Mario Merri GSAW, Los Angeles, USA 2 Mar 2011 ESA UNCLASSIFIED

Mission Operation Ground. Assurance @ ESA. Mario Merri GSAW, Los Angeles, USA 2 Mar 2011 ESA UNCLASSIFIED Mission Operation Ground Software Systems Product Assurance @ ESA Mario Merri GSAW, Los Angeles, USA 2 Mar 2011 The European Cooperation for Space Standardisation (ECSS) Established: in 1993 Goal: coherent,

More information

AIAA-2004-5820 Distributed Operation of a Military Research Micro Satellite Using the Internet

AIAA-2004-5820 Distributed Operation of a Military Research Micro Satellite Using the Internet AIAA-2004-5820 Distributed Operation of a Military Research Micro Satellite Using the Internet Chris Jackson * Surrey Satellite Technology Ltd., Guildford, England, GU2 7XH, UK Major Timothy J. Lawrence,

More information

Rapid Prototyping of Computer Systems 05-540, 05-872*, 18-540, 18-745*, 39-648 12 Units Carnegie Mellon University. Course Syllabus Spring 2013

Rapid Prototyping of Computer Systems 05-540, 05-872*, 18-540, 18-745*, 39-648 12 Units Carnegie Mellon University. Course Syllabus Spring 2013 Rapid Prototyping of Computer Systems 05-540, 05-872*, 18-540, 18-745*, 39-648 12 Units Carnegie Mellon University Course Syllabus Spring 2013 Lectures: Monday, Wednesday, 2:30-3:50, Hamburg Hall 2224

More information

Project Zeus. Risk Management Plan

Project Zeus. Risk Management Plan Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related

More information