EDS GRID AND PRIMARY SUBSTATION EARTHING DESIGN

Size: px
Start display at page:

Download "EDS GRID AND PRIMARY SUBSTATION EARTHING DESIGN"

Transcription

1 THIS IS AN UNCONTROLLED DOCUMENT, THE READER SHALL CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS ENGINEERING DESIGN STANDARD EDS GRID AND PRIMARY SUBSTATION EARTHING DESIGN Network(s): EPN, LPN, SPN Summary: This standard details the earthing design requirements for grid and primary substations and 132kV and 33kV connections. Owner: Allan Boardman Approved By: Steve Mockford Approved Date: 22/05/2015 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Circulation UK Power Networks All UK Power Networks Asset Management Capital Programme Connections External G81 Website Contractors ICPs/IDNOs Meter Operators HSS&TT Network Operations UK Power Networks Services Other

2 Revision Record Version 3.0 Review Date 05/05/2017 Date 05/05/2015 Author Stephen Tucker Why has the document been updated: Periodic document review. Minor revision to include generation connections and ensure consistency with the earthing construction standard ECS while the review of national standards ENA TS and ENA ER S34 is being carried out. What has changed: Reference to generating station exclusion removed (Section 1 and Appendix C). Scope expanded to specifically include 132kV and 33kV connections including solar and wind farm generation (Section 2). Guidance on fault level for electrode sizing added and conductor sizes revised (Section 5.14 and Appendix F). Lightning protection reference updated (Section 5.16 and 6.2). Mobile phone base stations on towers reference added (Section 5.22). Bonding requirements for ancillary metalwork, metal trench covers, cable tunnel metalwork and basement cable support systems revised (Section 5.30). Version 2.0 Review Date 31/03/2015 Date 11/03/2013 Author Stephen Tucker Review date extended to tie in with the review of national standards ENA TS and ENA ER S34 Version 1.3 Review Date 31/03/2013 Date 22/08/2012 Author Stephen Tucker Reviewed for publishing on G81 website Version 1.2 Review Date 31/03/2013 Date 03/08/2011 Author Stephen Tucker Reclassification and reformatting of document from Earthing Design Manual Section 3. References to standard earthing arrangements updated Version 1.1 Review Date 31/03/2013 Date 17/03/2011 Author Peter Rix Document rebranded Version 1.0 Review Date 31/03/2013 Date 31/03/2008 Author Neil Fitzgerald Original UK Power Networks 2015 All rights reserved 2 of 59

3 Contents 1 Introduction Scope Abbreviations Overview Data Requirements Earth Potential Rise (EPR) Estimation Standard Design Detailed Design Review of Existing Substations Detailed Design Procedure Determination of Soil Resistivity Preliminary Site Assessment Initial Design of the Earth Grid - Standard Earthing Arrangement Initial Design of Earth Grid - Non-Standard Earthing Arrangement Calculation of the Earth Grid Resistance First Approximation Computer Modelling Calculation of the Grid or Overall Earth Impedance (taking into account parallel paths) The Earth Grid Bonded Foundation Structure Steel Reinforcement Bars Steel Tower Lines Cable Networks Fortuitous Earth Paths Data Required from the Power System Fault Study Earth Fault Current Returning via Earthwire/Cable Sheaths Due to Induction Introduction Overhead line with Earth Conductor Cables Calculation of the Earth Potential Rise (EPR) Primary Substations Grid Substations (including 132 kv and 33kV Connections) Calculation of External Potential Contours or Zones of Influence (e.g. HOT Zone) Accurate Representation Approximate Calculation UK Power Networks 2015 All rights reserved 3 of 59

4 5.11 Implications of a Substation being HOT Reducing the Area Covered by the HOT Zone Reduce the Earth Fault Current Reducing the Electrode Resistance Reduce the Impedance of Parallel Paths Calculation of Touch and Step Potentials Accurate Calculation Approximate Method Requirements of the Final Design Conductor Size and use of Metallic Structures Earthing Arrangements Applicable to 400/275/132kV Sites of Different Companies Earthing Arrangements Applicable to Sites with Generation Earthing Arrangements at Railway Supply Substations Earthing Arrangements at GIS Substations Earthing Arrangements for Surge Arresters and Capacitor VTs Positioning of Metal Supports for Security Lighting etc Near Fences Communication Towers within or adjacent to Substations Communication Masts Fitted to Towers LV Supplies to Third Party Equipment at Substations Reactors and AC to DC Converters Use of Earth Plates (cast iron pipes etc) Earthing of Instrument Transformer Windings Earthing of Cables Power Cables Protection and Control Cables General Guidance for Achieving Electromagnetic Compatibility (EMC) Earthing of Fences Adjacent Metal Structures Palisade Gates and Removable Fence Panels Metal Anti-climbing Guards Temporary, Site-Perimeter and Adjacent Landowners' Fencing Safety Advantages of a Separately Earthed Fence Metalwork Bonding Requirements Ancillary Metalwork Metal Trench Covers Cable Tunnel Metalwork Basement Cable Support Systems UK Power Networks 2015 All rights reserved 4 of 59

5 6 References UK Power Networks Standards National and International Standards Appendix A Standard Substation Earthing Arrangements Appendix B Calculation of Fault Current returning via the Ground B.1 Calculation of Fault Current Returning via the Ground B.2 Example of Cable Information Necessary where Network Reduction is Required to Estimate Earth Contribution from Cable Network B.3 Examples of Fault Current Information Required for Fault Current Reduction Appendix C Special Conditions Applicable to Generating Stations within or Adjacent to a Substation Appendix D Maximum Resistance Values for Electrodes at Pole-mounted Plant Appendix E Standard Substation Earthing Arrangements Resistance Values, Surface, Touch and Step Potential Contours E.1 132/33kV Substation Arrangements (EDS /EDS ) E.2 33/11kV Substation Arrangement Option 1 (EDS ) E.3 33/11kV Substation Arrangement Option 2 (EDS ) Appendix F Minimum Conductor Sizes Tables Table 5-1 Calculation of Ground Current for Cable Faults Table 5-2 Earthing and Bonding Electrode/Conductor Sizes Table 5-3 Tape and Stranded Conductor Specifications Table 5-4 Maximum Current Rating of Earthing Rods UK Power Networks 2015 All rights reserved 5 of 59

6 Figures Figure 4-1 Making a First Estimate of the Substation EPR... 9 Figure 5-1 Earthing System Components Figure 5-2 Estimating the Proportion of Fault Current Returning Through the Soil Figure 5-3 Scale Plan of Substation Showing Site Boundary Surface Potential Contours 23 Figure 5-4 Use of Separately Earthed and Bonded Fencing Arrangements at the Same Substation Figure 5-5 Separately Earthed Fence 2m away from Earth Grid Figure 5-6 Separately Earthed Fence 500mm away from Earth Grid Figure 5-7 Earth Grid Bonded incorrectly to Fence, which is 2m away from Earth Grid Figure 5-8 Earth Grid Bonded incorrectly to Fence, which is 500mm away from Earth Grid Figure 5-9 Fence 2m away from Earth Grid, Fence and Earth Grid Bonded with Potential Grading 1m away Figure 6-1 Calculation of Fault Current Returning via the Ground in a 132kV Network Figure 6-2 Calculation of Fault Current Returning via the Ground in a 66kV or 33kV Network Figure 6-3 Example of Cable Network Information Required Figure 6-4 Example showing 132kV Phase Currents for Transformer-feeder Arrangement Figure 6-5 Example showing 132kV Phase Currents for a Parallel-feeder Arrangement.. 50 Figure /33kV Substation Electrode System Surface Potential Contours Expressed as a % of the EPR Figure /33kV Substation Electrode System Touch Potential Contours Expressed as a % of the EPR Figure /33kV Substation Electrode System Step Potential Contours Expressed as a % of the EPR Figure /11kV (Option 1) Substation Electrode System Surface Potential Contours Expressed as a % of the EPR Figure /11kV (Option 1) Substation Electrode System Touch Potential Contours Expressed as a % of the EPR Figure /11kV (Option 1) Substation Electrode System Step Potential Contours Expressed as a % of the EPR Figure /11kV (Option 2) Substation Electrode System Surface Potential Contours Expressed as a % of the EPR Figure /11kV (Option 2) Substation Electrode System Touch Potential Contours Expressed as a % of the EPR Figure /11kV (Option 2) Substation Electrode System Step Potential Contours Expressed as a % of the EPR UK Power Networks 2015 All rights reserved 6 of 59

7 1 Introduction This standard (previously Section 3 of the Earthing Design Manual) details the earthing design requirements for grid and primary substations and associated connections at 132kV and 33kV. Definitions for the terms used and a catalogue of reference documents associated with earthing practice and the design criteria are detailed in EDS ECS provides construction guidance for grid and primary substations. There will be some situations where advice from an earthing specialist is required refer to EDS for further details. 2 Scope This standard applies to earthing design at: All new grid and primary substations. Existing grid and primary substations where a material alteration (including a significant increase in fault level) is to take place. All new connections at 132kV and 33kV (including solar and wind farm generation). Note: A new document (EDS ) has been prepared to provide additional guidance on all aspects of EHV and HV customer earthing. This document is intended for internal and external use. 3 Abbreviations Term DigSILENT PowerFactory EHV HV LV EPR ROEP Definition The power system analysis software used by UK Power Networks Extra High Voltage. Refers to voltages at 132 kv, 66kV and 33kV High Voltage. Refers to voltages at 20kV, 11kV and 6.6kV Low Voltage. Refers to voltages up to 1000V, typically 400V 3-phase and 240V single-phase Earth potential rise Rise of earth potential UK Power Networks 2015 All rights reserved 7 of 59

8 4 Overview 4.1 Data Requirements Before starting the following basic data is required: Substation layout drawing and an earthing drawing for existing substations. Plan of surrounding area (100m radius) with buildings and other utility services shown. Supply circuit type to source (cable or overhead line). Source earth fault current (see Section 5.7). Outgoing circuit type. Geographic plan showing existing bare metal sheathed or bare wire armoured cables and proposed cable routes within a 500m radius of substation. Outgoing earth fault current (max see Section 5.7). Thermal rating in ka required for earthing system. If in a rural location, estimate of soil resistivity. 4.2 Earth Potential Rise (EPR) Estimation This process is necessary as a first indication as to whether earthing is likely to be a significant issue at the site. If it is, then a more detailed design procedure can be followed from the outset. If not, then a standard arrangement with little or no further calculation should suffice. The main factors to consider are the incoming supply circuit type, whether the location is in ground that is detrimental to earthing (within infill material or on rocky ground), the outgoing circuit type and the fault level. The decision that can be reached by consideration of these factors is set out below. Using the flowchart in Figure 4-1 make a first estimate of the EPR. If the EPR is less than 430V follow the standard design procedure outlined in Section 4.3. If the EPR is greater than 430V follow the detailed design procedure outlined in Section 4.4. UK Power Networks 2015 All rights reserved 8 of 59

9 START Supply and outgoing circuits via cables? Yes No Supply circuits via towers and outgoing circuits cables? Yes Gross earth fault current less than 3kA? No No Carry out first estimates of fault current distribution (Section 5.2) From approx soil data and grid dimensions, estimate the approx grid resistance (see Section 5.5) and multiply by approx earth fault current No Gross earth fault current less than 500A? Yes EPR significantly less than 430V? Yes No Yes EPR V and sensitive installations nearby e.g. petrol storage (Section 5.12)? No Yes Use detailed design procedure (Section 4.4) Use standard design (Section 4.3) Figure 4-1 Making a First Estimate of the Substation EPR 4.3 Standard Design The standard design procedure can be used if the EPR is less than 430V and is outlined below. 1. Design earthing system as per standard design layout or approach (see Sections 5.3 and 5.4). 2. Lay earthwire with outgoing cable routes for 150m. UK Power Networks 2015 All rights reserved 9 of 59

10 4.4 Detailed Design A more detailed design procedure is required if the EPR is greater than 430V and is outlined below. 1. Obtain soil resistivity data or structure (see Section 5.1). 3. Design earthing system to optimise resistance in relation to soil structure or to avoid third party equipment (see Section 5.3 and 5.4). 4. Calculate earth grid resistance (see Section 5.5). 5. Calculate effect of parallel earth paths (Hessian cables, earthed tower lines, bare earthwire laid direct in ground with cables) (see Section 5.6). 6. Calculate overall earth impedance (see Section 5.6). 7. Obtain site specific earth fault current data and analyse how current splits to determine ground component (see Section 5.7 and 5.8). 8. Make more accurate calculation of EPR (see Section 5.9 and 5.9.2). If EPR <430V revert to standard design procedure (see Section 4.3). 9. Calculate touch and step potentials and compare to limits. Modify design to achieve compliance (see Section 5.12). 10. Estimate external voltage contours and effect on third parties. Liaise with third parties if necessary (see Section 5.10). 11. If significant mitigation costs likely, modify design to reduce impact if possible (see Section ). 12. If EPR exceeds threshold values, list additional design requirements and actions necessary. Produce HOT zone plot for third parties (see Section 5.11). 13. Augment design to cater for site specific equipment and arrangement (see Sections 5.13). For example, structure earths (5.14), surge arresters (5.19), security lighting (5.20) etc. 14. Select tape and joint sizes to match thermal and corrosion requirements (see Section 5.14). 15. Produce construction drawing. 4.5 Review of Existing Substations The assessment of existing substations for compliance with ENA ER S36 or this standard is covered in ECS Examples of the circumstances where this may be required are as follows: On receipt of a specific enquiry from a third party. Following a system incident. When modification work is being considered. Following changes to system fault levels. UK Power Networks 2015 All rights reserved 10 of 59

11 5 Detailed Design Procedure 5.1 Determination of Soil Resistivity An initial estimation of the soil resistivity can often be obtained from the EPR database or from published geological survey information. If the more pessimistic values of soil resistivity produce an acceptable EPR result then this may be used, otherwise soil resistivity measurements should be carried out according to Section Preliminary Site Assessment Before carrying out work at a green field site, the civil engineer will normally require a geotechnical survey. Wherever practicable, the same company should be required to carry out the soil resistivity and ph testing at the site. If boreholes are to be drilled, it may be possible for their positions to be selected such that they are suitable for earthing, whilst also providing the necessary data for the civil engineer (for example located just beyond the corners of the proposed building). On completion, 25mm x 4mm copper tape or stranded 70mm 2 conductor can be installed in each borehole prior to backfilling. The conductor should extend by about 500mm above the hole and this part is to be buried just below the surface of the soil to allow for later connection to the earth grid. The hole is to be backfilled with local soil or material that is non-corrosive to copper and electrically conductive. Concrete, soil, Bentonite or Marconite are all suitable for this purpose. The design engineer should avail himself of the Geo-technical Engineer s report plus any other published geological information relating to the site. The chemical analysis should include an assessment of the rate of corrosion to copper, lead and steel (normally the above average presence of chemicals such as chlorides, acids or sulphates increase the corrosion rate) and testing the ph value At an existing site, the buried electrode should be revealed at a number of locations and inspected to determine the conductor size, type and condition especially to see if there is any evidence of corrosion. If corrosion is evident, the new electrode size shall be increased and the copper tape surrounded by a minimum of 150mm radius of correct value ph soil. This may need to be imported if sufficient quantity is not available from other parts of the site. Stranded copper conductor should not be used, but if essential for small parts of the site the conductor shall have a small number of large cross sectional area strands. Monitoring checks (e.g. testing with clip on meters) shall also be included in the maintenance regime, together with a plan to alleviate any damage caused by corrosion to the existing conductor. Ash, cokebreeze or any other type of imported material which is corrosive to copper shall not be used as backfill. As an alternative to replacing the soil, the electrode may be surrounded by low sulphur content concrete, preferably with graded carbonaceous aggregate in place of the conventional sand or aggregate for a radius of 50mm. Marconite is suitable for this, but is more expensive. UK Power Networks 2015 All rights reserved 11 of 59

12 5.3 Initial Design of the Earth Grid - Standard Earthing Arrangement The standard is to make the substation safe and then to render the site COLD where practicable at reasonable cost. If it appears that extensive, costly modifications would be required to make the site COLD, an assessment shall be made of the costs involved in declaring the site HOT and this compared to the cost of extending the earthing. In most cases a compromise will provide the best solution, i.e. some additional earthing work will be needed to reduce the EPR, but to a level where the site is still HOT. It is preferable to use one of the standard designs given Appendix A but if these are not applicable, follow the general guidelines below to carry out the initial design of the earth grid. Ideally all services (such as water) should have standard insulated arrangements, to avoid possible transfer potentials. Metallic services should preferably be replaced with plastic type from 2m beyond the substation perimeter fence. If there is some uncertainty as to whether the site is HOT or not, it is sensible to introduce some of the less costly precautions at the construction stage. For example, insist on a plastic piped water supply and arrange for isolation units on any BT circuits. On the scale plan of the site, showing the plant arrangement, plot an earth grid to the following specification: 1. An outer (perimeter) loop of standard copper electrode should be installed, inside the fence line and ideally a minimum of 2m away (inside) from any metal fencing, at 600mm depth (installed in plastic duct where cable routes cross the earth tape). In addition, the electrode conductor should ideally be 1 metre outside any exposed metalwork of plant within the substation. This means in practice, that the gap between any item of plant and the metal fencing should ideally be 3m. The outer ring should encapsulate an area as large as possible. It is possible in many cases to allow the loop conductor to extend closer to the perimeter fence, so long as the resulting fence touch voltages are within safe limits. At least 2m separation between the fence and internal earthed equipment shall be maintained in all cases. 2. Convert the outer loop to a mesh by positioning standard conductor across the site, in two directions (at 90 to one-other), each conductor being parallel to one of the outer conductors, where practicable. The cross - members should form rectangles, should be spaced a nominal 10m maximum apart on the outer edges of the grid or 12m maximum apart in the central areas and installed to a depth of 600mm. They will be joined to the outer ring and at each crossing point. The conductor routes should be selected to coincide with planned excavations (such as adjacent to transformer bund walls) and run close to equipment/structures that require connection. 3. Care shall be taken when planning the grid layout to ensure that critical components such as transformer neutral connection points, switchgear earth bars etc., are provided with direct and duplicated routes through to the perimeter loop electrode. 4. At or near to the connection point of each cross member to the perimeter loop electrode, and at its corners, install one 3.6m x 16mm copper clad earth rod. Longer rods may be necessary in some soils or to reduce the grid resistance. Where rods of more than 5m length are used, at least two connections to permit testing are to be used. They should be on opposite edges of the site and will permit rapid testing and electrode location. 5. Provision may be necessary in the design of the grid layout to provide connection points for temporary neutral earth resistors or arc-suppression coils (ASC) to replace the normal unit during maintenance, particularly if the unit is shared between two or more transformers. UK Power Networks 2015 All rights reserved 12 of 59

13 6. Use shall be made of sheet piles and reinforcing bars in concrete piles wherever practicable. This will improve the resistance value and reduce installation costs. If vertical piles are to be plastic lined, then some copper tape should be installed on the outer edge of the piles to provide a low cost vertical electrode. An earth loop conductor shall be installed around the outside of the foundation any new switchroom and be incorporated into the design (this will have been installed as a standard feature at the civil stage). Methods of connecting rebar, piles and sheet steel are covered in Section 4. Horizontal foundation slabs of transformers and switch rooms are to have two rebar connectors fitted, one at either end of the foundation. Switch room rebar for new GIS equipment requires special attention and this will be addressed by the manufacturer or installer. Where the vertical piles have more than 5m of metal reinforcement in them, 20% of them are to be bonded direct to the earthing system. These will be selected at corner locations, on the outer edges of the structure or at locations that will assist with high frequency impulse attenuation. At Network Rail traction supply points the main reason for not bonding the rebar is the possible presence of DC return currents. 7. The metal fencing shall have its own electrode system. Details of fence earthing arrangements are covered in Section The clearance between the fencing and the earth grid is to provide electrical separation between the two systems. Fence earth rods should be close to the fence and not infringe the clearance zone. Any metallic pipes or cables which run under the fencing at a standard substation should be installed in plastic duct 2 either side of the fence. Metallic support columns for lighting or security cameras shall not be installed within the 2m clearance zone. Also see section Note: Electrode buried shallower than 600mm deep cannot be considered in calculating the resistance value, but can be included in calculations related to touch and step potentials. 8. Routing of electrode. Avoid laying earth electrode close and parallel to bare metal pipes, Hessian served power or multi-core cables. This reduces the risk of them being punctured due to high currents or voltage transients on the electrode. Ideally a separation of at least 300mm should be maintained. Where this is not practicable, for short lengths, then PVC tape or a split plastic duct should be applied around the Hessian sheathed cable or bare metal water pipe. This insulation should be applied for 500mm either side of a position were the cable or pipe crosses an earth electrode and the length over which the 300mm separation cannot be maintained. It is particularly important to ensure that this insulation is applied where a long earth electrode terminates. The end of the electrode shall be bent away from the cable or pipe, to increase the separation at this point, in addition to the insulation. For plastic sheathed cables, the separation can be reduced to 0.15m. When routing electrode off site, either to reduce the overall earth resistance or to provide a connection to external equipment such as terminal poles, routes that may be frequented by people with bare feet or animals are to be avoided. These include routes near caravan sites, animal drinking troughs or across access gates to stables or milking parlours. Where electrode crosses land that is to be ploughed, if it cannot be located near to hedgerows and so shall cross open areas, it is to be installed a minimum of 1m deep. UK Power Networks 2015 All rights reserved 13 of 59

14 5.4 Initial Design of Earth Grid - Non-Standard Earthing Arrangement This design is similar to the standard design with the following exceptions: Where the electrode is a loop outside the fence, this standard electrode shall be installed 1 metre deep and between 700mm to 2m outside any metallic fencing. Where the grid is being extended either to make the substation COLD or to limit the EPR, the outer conductor may be spaced more than 1 metre away from the fence-line at a distance indicated in the design study. Depending upon wayleaves and practical issues, the outer electrode spacing from the fence may not be symmetrical. For example, it may be 1 metre away on one side of the site and 15m away on the other. An additional electrode 1m outside the fence may also be needed in the latter case, if the EPR is high, to reduce fence touch voltages The internal electrode design will follow the same procedure as in Section 5.3, except that the cross members will pass under the fence and be bonded to it (see Section 4). Equipment bonded to the grid can be close to the fence, as there will be no touch voltage issue. When these guidelines have been translated into an actual design, the arrangement will be similar to those shown in Appendix A. 5.5 Calculation of the Earth Grid Resistance First Approximation The soil resistivity value is first required. The procedure for carrying out the resistance calculation is detailed in ENA ER S34. Table 1 of S34 contains a series of formulae to calculate the resistance of various forms of buried electrode. This method always has a margin of error, which can be significant if the soil is not uniform, especially when the soil has high resistivity layers underneath (e.g. rock). Where the soil is not uniform or the earth grid is complex, specialist advice shall be sought Computer Modelling The electrode arrangement can be modelled by computer if required to provide a more accurate value. Specialist advice should be sought. 5.6 Calculation of the Grid or Overall Earth Impedance (taking into account parallel paths) When a fault having an earth fault current occurs, the current that returns to the source(s) through the ground will pass through the earth grid together with any connected parallel paths. Before calculating the EPR it is necessary to estimate how much of the fault current flows in this way and how much returns via metallic routes (such as cable sheaths), to avoid over-estimating the EPR. In an urban located substation, the impedance of the parallel paths will often be an order of magnitude lower than the resistance of the substation grid, so it is vital that their contribution is accounted for. This will prevent unnecessarily declaring a substation as HOT, or overdesigning the grid earth. To be considered, the parallel paths shall be reliable and capable of carrying their proportion of anticipated maximum fault current, without duress. UK Power Networks 2015 All rights reserved 14 of 59

15 The overall impedance to earth is made up of the following components, shown also in Figure 5-1, connected in parallel: The earth grid. Bonded foundation sheet steel or reinforcement bars. Steel tower lines. Cable networks. Fortuitous earths, e.g. to/via other services and LV system. There are other parallel paths influencing the measured value. These include the electrode system of customers or adjacent substations, but these are not included in the design calculation unless they have been formally incorporated within an overall earthing design. EARTHING SYSTEM COMPONENTS Outgoing Earth Grid Incoming Electrical Sources Earth grid I Cable (XLPE) Cable (Pb) Steel reinforcing Cable (Pb) Cable (XLPE) KEY PVC serving on copper, aluminium or lead sheath. Hessian (conductive) serving on lead sheath. Figure 5-1 Earthing System Components The Earth Grid As described in Section 5.5, the earth grid resistance can be obtained by calculation, by computer modelling, or by graphical or interpolation methods Bonded Foundation Structure Steel Reinforcement Bars If these have been bonded to the earth grid, initially their effect can be ignored unless they increase the horizontal area encompassed by the earth grid or enter low resistivity soil underneath (such as long steel reinforced piles). If the total area is increased, the new total area should be used to recalculate the grid resistance. UK Power Networks 2015 All rights reserved 15 of 59

16 5.6.3 Steel Tower Lines Each tower has a natural resistance to earth of typically 5 to 20, due to the concrete-clad steel legs installed in the soil and the terminal tower at any substation shall be securely connected to the substation earth grid. The total combined resistance to earth of each tower, connected in series/parallel via the overhead earth conductor, is called the chain impedance. The calculated chain impedance value relies on the aerial earth conductor being bonded to the tower steelwork at each tower position and the actual value will be significantly higher if this has not been carried out. (Many older lines were originally constructed without bonds between the earthwire and tower) On site checks may thus be required to confirm satisfactory connection. Only towers continuously connected by an earthwire to the substation grid contribute to the chain impedance. For example, the contribution beyond a section of Trident or Portal type unearthed 132kV construction will not contribute. The tower line chain impedance has a reactive component due to the overhead earth conductor. On a new circuit, the individual tower footing resistance can be measured (before the earthwire is connected) and this is the preferred method. Alternatively the resistance can be calculated using the foundation depth, radius, spacing and soil resistivity. Computer modelling is the most accurate calculation method, for which specialist advice may be required. Once the tower footing resistance is known, a graph is provided (ENA ER S34, Figure 5) from which the chain impedance can be read. The graph assumes that there are at least 20 towers in a line, in similar soil conditions. In the absence of detailed information, a conservative estimate for a 132kV tower line with a minimum of 20 towers would be a chain impedance of 2 ohms at 34 degrees (lag), shown This assumes the tower line is not on rocky ground. If a tower line is shorter than 20 towers, or installed in rocky ground, then individual calculation is necessary and specialist advice may be necessary. The tower at a line cable interface should be fitted with potential grading and cable surge arresters. These are connected to earth directly via copper tape or stranded conductor and are also indirectly connected to earth via the tower. The rational behind this is that good earthing is necessary at the termination tower for insulation coordination and to prevent voltage doubling. The tower needs to be bonded to the substation earth at two points. This does not modify the substation earth resistance by very much. The difference the presence of the tower and earth wires make, is that a relatively low earth impedance will already exist. The high frequency impedance of a tower is much higher than at power frequency, so much so, that the impedance of the tower can have a second order effect. So a copper connection from the surge arresters is necessary with a few rods at the base. No measurements are necessary. Further details for high frequency earthing of surge arresters and capacitor voltage transformers (CVT) can be found in Section Cable Networks Where these exist, they are likely to be the most important factor governing the need, or otherwise, to extend the earthing system. Most existing 11kV cables have either a Hessian covered steel-wire (or tape) armouring, with a lead sheath; or are PVC served with an aluminium sheath. For Hessian covered cables, the outer lead sheath is in continuous contact with the soil throughout its length (except where installed in plastic ducts) and will provide a path for earth fault current to flow into the soil. UK Power Networks 2015 All rights reserved 16 of 59

17 Polymeric type cables are now increasingly being used and have a stranded copper sheath and a medium density polyethylene outer serving (MDPE). It is important that the sheath cross sectional area is sufficiently large to carry the anticipated fault current and not to have too high a longitudinal impedance. The sheath cross sectional area will also affect the proportion of fault current returning through the soil for an earth fault at the remote end of the cable and so will influence the EPR. This is often overlooked when cables are selected on a cost basis related to the load carrying capability only. A bare copper stranded earth electrode of 70mm 2 cross-sectional area is to be laid with each out-going group of insulated sheath cables for a typical distance of 150m from the substation (unless deemed not required by the Design Engineer) up to an overall maximum length as follows: In the absence of more specific design guidance, the total length of bare electrode installed in this way at a ground-mounted substation is to be 3.2 times the soil resistivity value, metres. The conductor required should ideally be shared equally amongst three or four routes running out in separate directions. If there are few routes and/or the distance to the first distribution substation is short (less than 200m), then it is advisable to run the electrode along it. If possible, the remote end of the electrode should be terminated at the electrode system of a distribution substation or to the sheath of a HV cable joint. This will provide a higher degree of reliability. Knowing the soil resistivity along the route, Figure 4 in ENA ER S34 provides a series of curves to enable the electrode resistance provided by the bare electrode or lead sheathed, Hessian served cables of different length to be estimated. As a first estimate, the resistance of up to three lengths of Hessian served cables, each following routes which are between 65 and 120 degrees apart, may be calculated using Figure 4 in ENA ER S34. The overall resistance can be obtained by assuming each of these and the earth grid to be in parallel. Short lengths of plastic sheathed cables or plastic ducts can normally be ignored. Also, for calculation purposes, any radial earth electrode installed along the route of a plastic sheathed underground cables can be treated the same as a Hessian served cable, provided it is not running in parallel with a Hessian served cable whose contribution is also to be included. The above approach will almost certainly provide a resistance value lower than the actual one. This is due to interaction between the outgoing cables and earth grid not being taken into account. Cables associated with different voltage systems may be included, provided their earth sheaths are connected at the substation concerned. The sheaths of many modern cables are plastic covered (PVC or MDPE) and hence insulated from earth. However, they are often connected to sections of older Hessian covered cable and to earthing systems at each 11kV substation. Due to this, a low overall impedance to earth may still be provided. The contribution from an entirely plastic served cable circuit may be calculated in a similar manner to that for a tower line, i.e. as a parallel set of chain impedances. The resistance of the HV electrode at the distribution substation (as specified in Section 4) is in series with the longitudinal impedance of the cable sheath (which may be found from ENA ER S34). As the distribution substations are generally several hundred metres apart, their individual electrode systems will not interact. This means that the contribution from nearly all the outgoing circuits may be taken as acting in parallel. It is important to note that the overall earth impedance will be significantly higher than for a comparative system of lead sheathed cables and will have a much larger inductive component. UK Power Networks 2015 All rights reserved 17 of 59

18 To enable an approximate calculation to be made for a typical network comprising of Hessian and plastic served cables, the following information is required: The area covered by the cable network, if less than 4km 2. The length of the buried cable. The proportion of Hessian served cable. Approximate distribution substation resistance if Hessian served cable accounts for less than 10% of the total. A value representing the proportion of the area used by the cable network (the active area). A factor which takes into account the effect of many Hessian served cables following similar routes. The approximate overall cable network impedance can then be found by use of an equation and/or graphs. Where a more precise estimate is required, for example when the cable network is relatively small or has a high amount of plastic sheathed cable, then specialist advice is required to calculate the overall earth return impedance. To facilitate calculations, the following information is required: Cable size and type. Sheath dimensions are particularly important. Typical installation depths. Distribution substation earthing value. Cable overlaying planned, especially where bare metal sheathed or bare wire armoured cable is to be replaced by PICAS/plastic served cable. Approximate cable routes, which show where bare metal sheathed or bare wire armoured cable is laid direct in the ground or in earthenware ducts. The above information is required for each circuit up to 1.5km from the site or up to the first section of overhead line. The areas of each circuit containing a high proportion of Hessian served cable are of particular interest. Where this cable is laid in earthenware ducts it has a measurable but much less effective earth resistance. A diagram showing the type and format of information necessary is provided in Appendix B. The overall earth return impedance may be calculated by considering the above paths to be in parallel. It is necessary to take proximity into account - for example if there is only one Hessian served cable and this runs in parallel with a tower line, the chain impedance of the tower line should be excluded as it will overlap that of the cable. Similarly, if the tower line passes through an area densely populated by Hessian served cable, its impedance should be neglected in the overall calculation Fortuitous Earth Paths These are provided by/via the LV system or other services at COLD substations. For example, at an old substation, there may be connection onto abandoned cable sheaths or pipes. Fortuitous earths are not included in design calculations, but may provide a further reduction in the overall resistance at the measurement stage. At a HOT substation, such fortuitous earths, especially if provided by LV cables, which leave the site boundary, could be a source of danger and are not permitted. If they exist, they shall be modified or disconnected. UK Power Networks 2015 All rights reserved 18 of 59

19 5.7 Data Required from the Power System Fault Study The objective is to determine the amount of earth fault current flowing into a substation s earth impedance (which includes the earth grid plus its parallel paths). This will be used to calculate the EPR and ensure that the earthing system can deal with the anticipated fault current. Note: The substation earth grid and main equipment bonds are sized to deal with the thermal requirements, i.e. the maximum earth fault current anticipated over a period of 3s (or 1 second at transmission sites). This means that any subsequent physical work on site should be kept to a minimum for moderate increases in fault current. Refer to Section 8 for the design issues it is necessary to consider when there is a significant increase in fault current. The network should be modelled using fault levels anticipated for five years into the future to obtain the maximum single phase to earth fault current available due to either an internal or external fault condition at the substation. The initial symmetrical short circuit current is to be calculated in accordance with IEC 909-HD 533. The internal fault is for example a highvoltage bushing or bus bar failure to earth or a fault thrower operation producing the highest earth fault current in the substation. (The highest voltage level may not necessarily produce the highest earth fault current). The worst case external fault condition normally involves an earth fault on a lower voltage outgoing circuit, particularly one supplied by unearthed overhead line, where the entire earth fault current will return through the ground. The switchgear earth fault rating should not be used for this calculation, as the rating is normally much higher than the actual earth fault current values. Switchgear with a high rating is often purchased due to high X/R ratios, not high earth fault current conditions. Use of these values would lead to un-necessary expenditure for internal earthing and external third party mitigation. Internal fault conditions within the substation at lower voltages do not normally require investigation, as most of the current should return via the installed electrode system back to the star point. This will not create a significant rise of earth potential, unless the earth grid has been incorrectly designed or is large (say at a power station). In this case, significant potential differences may occur across the substation. If the installed electrode system is not fully integrated, then specialist advice should be sought to determine whether a detailed analysis is required. A more detailed analysis is required for 132kV networks compared to those at 66kV and 33kV. These lower voltage networks are generally earthed at one point, whereas 132kV networks are multiple earthed i.e. at sending and receiving ends. This means that a portion of the fault current will return to source via phase conductors. To estimate the current returning in this way, the individual phase currents in each transformer winding during the fault are required and these need to be summated vectorially to find the residual current. This is subtracted from the gross earth fault current when calculating the EPR. Examples of the information required and how it is analysed for transformer feeder or parallel infeed arrangements are shown in Appendix B. For 66kV and 33kV overhead line networks supported on unearthed poles, because it is normal practice to provide a connection with earth at the source of supply only, all of the earth fault current returns to the source via the ground. UK Power Networks 2015 All rights reserved 19 of 59

20 It is important to include an estimate of the total earth return impedance (i.e. the series sum of the fault resistance, source resistance and circuit impedance) and fault position in the fault current analysis. Where the earth return impedance is significant, for example at rural locations supplied by 33kV lines, the prospective earth fault current will be significantly reduced. The above analysis, based on sequence modelling, will give approximate results where the earth fault current does not follow the same route back to source as the phase current. For example, when there are multiple cable sheath routes for the earth fault return current and only one route for the phase fault current. It is possible, to model the system more accurately by including independent phase and earth circuits. This can be carried out for specific cases, if required and specialist advice is necessary. 5.8 Earth Fault Current Returning via Earthwire/Cable Sheaths Due to Induction Introduction When a conductor lies parallel to another and an alternating current flows in one of them, then provided a complete circuit is available on the other, a current will be induced in it. This effect is experienced in tower lines and underground cables. The earthwire on a metal tower line forms a complete circuit as it is earthed at each end (and at intermediate towers), so current will be induced in it when earth fault current flows in a phase conductor. Similarly, if the metal sheath of a single core cable is earthed at each end, current will be induced in this when earth fault current flows in the cable core. The current induced into the cable sheath or aerial earth wire returns to source(s) without flowing through the ground locally. It will not pass through the earth grid and will therefore not contribute to any rise in potential. To arrive at an accurate estimate of the rise of earth potential under fault conditions, the fault current returning via metallic routes needs to be subtracted from the total fault current to give the current returning via the soil. Aerial earth I f I f Fault Substation A earth grid Substation B earth grid I gr (the current returned through the soil) for a cable fault is reduced by the value I f, which would be the current returning through the cable sheath. I f = Maximum earth fault current from fault study I f = Current induced into earth loop, opposite to I f I gr = I f I f Figure 5-2 Estimating the Proportion of Fault Current Returning Through the Soil UK Power Networks 2015 All rights reserved 20 of 59

21 5.8.2 Overhead line with Earth Conductor To determine the value of ground current, refer to Table 2 in ENA ER S34. However, note that the earthwire shall be continuous back to source. If a section of unearthed construction (e.g. Trident) is installed, then the table cannot be used and any induced return current will need to be individually calculated. Again, specialist advice should be sought to assist in this task Cables To determine the proportion of ground current, ENA ER S34 has a series of nomographs. These are summarised in Table 5-1. The nomographs are only suitable for relatively straight forward cases and are not available for polymeric cables. For these and more complex arrangements, for example where there are several sources or intermediate substations between the source and the substation of interest, specialist advice should be sought. Table 5-1 Calculation of Ground Current for Cable Faults ENA ER S34 Fault on Cable Section Figure No Voltage (kv) Size Type Supply Source 8 33 Standard PILC All cable mm 2 PILC or PICAS All cable Standard * PILC Via overhead line mm 2 3 x 1 PILC Via overhead line mm 2 3 x 1 PICAS Via overhead line Standard* PILC Cable mm 2 PILC or PICAS Cable * Standard includes 185mm 2, 240 mm 2 and 300mm 2. To use the nomographs, it is necessary to know the length of cable, the cable type, the earth impedance at each end, the fault position and method of earth connection at each cable end. Normally the sum of the two cable end resistances are divided by the cable length (in kilometres). The factor obtained is then used with the nomographs, to provide the percentage and phase angle of fault current returning through the ground, for each particular type of cable. 5.9 Calculation of the Earth Potential Rise (EPR) Primary Substations From Section 5.6, the overall earth impedance value will have been obtained. From Section 5.7 the maximum earth fault current will have been obtained. As a first estimate, the two should be multiplied together to obtain the EPR value. If this means a COLD substation, then no further calculation is generally necessary. If, the calculation indicates that the substation may be HOT, then the effects of current returning to the network by induction, as explained in Section 5.8 now have to be taken into account. See Appendix B. The EPR is then recalculated as the net (remaining) current through the overall earth impedance multiplied by that impedance. UK Power Networks 2015 All rights reserved 21 of 59

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

GroundRod AC Substation Earthing Tutorial

GroundRod AC Substation Earthing Tutorial 1 GroundRod AC Substation Earthing Tutorial 1. Functions of an earthing system The two primary functions of a safe earthing system are: To ensure that a person who is in the vicinity of earthed facilities

More information

ScottishPower Distribution Cables & Equipment. Metal Theft

ScottishPower Distribution Cables & Equipment. Metal Theft ScottishPower Distribution Cables & Equipment Metal Theft April 2012 As an aid to deterring to metal theft this booklet has been put together to help identify the types of utility power cables and associated

More information

Substation Grounding Study Specification

Substation Grounding Study Specification Substation Grounding Study Specification Introduction A grounding study is required for name of station, a / / kv substation located in name of location and connected to the following circuits: number

More information

Lightning Protection Introduction

Lightning Protection Introduction Lightning Protection Introduction Structural lightning protection design considerations BS 6651 (Protection of structures against lightning) clearly advises strict adherence to the provision of a conventional

More information

EDS 06-0016 LV NETWORK EARTHING DESIGN

EDS 06-0016 LV NETWORK EARTHING DESIGN THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 06-0016 ENGINEERING DESIGN STANDARD EDS 06-0016 LV NETWORK EARTHING DESIGN Network(s): EPN, LPN, SPN

More information

EDS 02-0027 11KV TRIPLEX CABLE

EDS 02-0027 11KV TRIPLEX CABLE THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 02-0027 ENGINEERING DESIGN STANDARD EDS 02-0027 11KV TRIPLEX CABLE Network(s): EPN, LPN, SPN Summary:

More information

Network Standard Advice No. 1420C 9/6/2011

Network Standard Advice No. 1420C 9/6/2011 Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Gulf Cable & Electrical Ind. Co.

Gulf Cable & Electrical Ind. Co. CONTENTS INTRODUCTION PRODUCT RANGE I PRODUCT DATA TABLES XLPE INSULATED 600/1000V CABLES Two Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 1 Three Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 2 Four Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC

More information

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET

More information

Consultants Handbook

Consultants Handbook Consultants Handbook CONSULTANTS HANDBOOK Welcome to our Wallis Designers Lightning Protection Handbook. This handbook offers a guide for any designers of the structural Lightning protection system to

More information

environment briefing02

environment briefing02 PRODUCED BY THE SAFETY, HEALTH & ENVIRONMENT GROUP OF THE ENERGY NETWORKS ASSOCIATION - JULY 2006 environment briefing02 transporting electricity Overhead Lines or Underground Cables? Introduction The

More information

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Cables, Cable Laying & Accessories Manual

Cables, Cable Laying & Accessories Manual Distribution Business Cables, Cable Laying & Accessories Manual Database ref: File Ref: Title Page & Revision Log For Cables & Access v4 - Nov 2003.doc Manual Name: Cables & Accessories Manual Version

More information

Specifications for Lightning Protection. ASAE Engineering Practice

Specifications for Lightning Protection. ASAE Engineering Practice Chapter 8: Lightning Specifications for Lightning Protection ASAE safety standards are not laws. They are recommended voluntary standards used by designers, engineers, manufacturers and users of the equipment,

More information

12 Appendix 12 Earth Electrodes And Earth Electrode

12 Appendix 12 Earth Electrodes And Earth Electrode 12 Appendix 12 Earth Electrodes And Earth Electrode Testing 12.1 Introduction This appendix provides guidance and background information an earth electrode testing and some limited information on earth

More information

Fault location on power cables. Fault location on power cables

Fault location on power cables. Fault location on power cables Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables

More information

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation

More information

Video Camera Installation Guide

Video Camera Installation Guide Video Camera Installation Guide The intent of this guide is to provide the information needed to complete or modify a video camera installation to avoid lightning and induced power surge damage. This guide

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

ECS 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

ECS 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: ECS 02-0019 ENGINEERING CONSTRUCTION STANDARD ECS 02-0019 INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

More information

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters

4 IX D N E P P A Installation methods Current-carrying capacity and voltage drop for cables Reference method IET Wiring Matters 8 Appendix 4 of BS 7671 by Mark Coles Appendix 4, Current-carrying capacity and voltage drop for cables and flexible cords, has seen significant changes with the publishing of BS 7671:2008. This article

More information

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw 4 937 DESIO Current valve for AC 24 V pulse/pause control of electrical loads up to 30 kw SEA45.1 Use The current valve is used for the control of electric heating elements in heating, ventilation and

More information

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application

Digital Energy ITI. Instrument Transformer Basic Technical Information and Application g Digital Energy ITI Instrument Transformer Basic Technical Information and Application Table of Contents DEFINITIONS AND FUNCTIONS CONSTRUCTION FEATURES MAGNETIC CIRCUITS RATING AND RATIO CURRENT TRANSFORMER

More information

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Grounding of Electrical Systems NEW CODE: Grounding and Bonding Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately

More information

Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria

Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria Assessment of Soil Resistivity on Grounding of Electrical Systems: A Case Study of North-East Zone, Nigeria Abstract Gabriel A. Adegboyega and Kehinde O. Odeyemi Department of Electrical and Electronic

More information

Grounding & Bonding Why it is done And How to Install Properly

Grounding & Bonding Why it is done And How to Install Properly Grounding & Bonding Why it is done And How to Install Properly The technical information provided herein is to assist qualifi ed persons in planning and installing electric service to farms and residences.

More information

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER.

Power Voltage Transformers for Air Insulated Substations. THE PROVEN POWER. Power Voltage Transformers for Air Insulated Substations THE PROVEN POWER. Introduction Trench Power Voltage Transformers (Power VTs) combine the attributes of an inductive voltage transformer with the

More information

EDS 06-0017 CUSTOMER LV INSTALLATION EARTHING DESIGN

EDS 06-0017 CUSTOMER LV INSTALLATION EARTHING DESIGN THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE Document Number: EDS 06-0017 ENGINEERING DESIGN STANDARD EDS 06-0017 CUSTOMER LV INSTALLATION EARTHING DESIGN Network(s):

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

SOIL RESISTIVITY MEASUREMENTS

SOIL RESISTIVITY MEASUREMENTS SOIL RESISTIVITY MEASUREMENTS APPENDIX B B Soil resistivity directly affects the design of a grounding (earthing) electrode system and is the prime factor that determines the resistance to earth of a grounding

More information

Coupling Effect in Substation Ground Measurements

Coupling Effect in Substation Ground Measurements SERBIAN JOURNAL OF ELECTRICAL ENGINEERING Vol. 9, No. 3, October 2012, 315-324 UDK: 621.316.13.011.2 DOI: 10.2298/SJEE1203315F Coupling Effect in Substation Ground Measurements Alex Farber 1, Boris Katz

More information

For business. Wiring your business for broadband. What happens when copper is required?

For business. Wiring your business for broadband. What happens when copper is required? For business Wiring your business for broadband Your cabling requirements are dependent on the size and complexity of your business. Smaller businesses should follow the wiring recommendations for residential

More information

Undergrounding high voltage electricity transmission. The technical issues

Undergrounding high voltage electricity transmission. The technical issues Undergrounding high voltage electricity transmission The technical issues This is an interactive PDF document with clickable links from the contents to all sections and back and also to URL and email links.

More information

EARTHING SYSTEM CALCULATION

EARTHING SYSTEM CALCULATION BAZIAN STEAL FACTORY S/S 132/11kV, 1x30/40MVA EARTHING SYSTEM CALCULATION Kurdistan Region Sulaimani May 2011 Bazian Steal Factory S/S 132/11kV, 1x30/40 MVA Contents: 1. Introduction... 3 2. List of references

More information

ELECTRIC FIELD LINES AND EQUIPOTENTIAL SURFACES

ELECTRIC FIELD LINES AND EQUIPOTENTIAL SURFACES ELECTRIC FIELD LINES AND EQUIPOTENTIAL SURFACES The purpose of this lab session is to experimentally investigate the relation between electric field lines of force and equipotential surfaces in two dimensions.

More information

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions

Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Operational Control of the UKPN Low Voltage Distribution Network for EPN and LPN Regions Owner Name Title Signature Steve White Head of Network Control and Operations Date 16 February 2016 Authoriser Name

More information

Technical Guidance Note 287. Third-party guidance for working near National Grid Electricity Transmission equipment

Technical Guidance Note 287. Third-party guidance for working near National Grid Electricity Transmission equipment Technical Guidance Note 287 Third-party guidance for working near National Grid Electricity Transmission equipment 02 Purpose and scope... 3 Part 1 Electricity Transmission infrastructure... 4 Overhead

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13 Interfacing electrification and system reliability Roger White Professional Head of Electrification and Plant Rail Abstract Integration is the term given to ensuring that the different elements of an electrified

More information

NEGRP TEST SUMMARY. Joseph A. Lanzoni, November 2005

NEGRP TEST SUMMARY. Joseph A. Lanzoni, November 2005 NEGRP TEST SUMMARY Joseph A. Lanzoni, November 2005 The National Electrical Grounding Research Project (NEGRP) was a project managed and sponsored by the National Fire Protection Association (NFPA) Research

More information

Screened cable and data cable segregation

Screened cable and data cable segregation December 2007 Screened cable and data cable segregation Can an armoured power cable be considered a screened cable and how does this relate to power and data cable segregation? The short answer is yes;

More information

High Voltage Systems. Today. The history of cables

High Voltage Systems. Today. The history of cables High Voltage Cables High Voltage Systems Today Prysmian Cables and Systems B.V. is part of the Prysmian Group, a leading player in the industry of high-technology cables and systems for energy and telecommunications,

More information

CONFLEX ELECTRIC CABLE

CONFLEX ELECTRIC CABLE CONFLEX ELECTRIC CABLE CONFLEX - 0.6/1kV Flexible VSD/EMC Cables Applications WW VSD/EMC cables are manufactured for use where electrical interference distorts signal transmission in electric motors. Standard

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

CURRENT TRANSFORMERS INSTALLATION GUIDE

CURRENT TRANSFORMERS INSTALLATION GUIDE CURRENT TRANSFORMERS INSTALLATION GUIDE Information contained within this document is subject to change without notice and does not represent a commitment on the part of PRI Ltd or its agents. E&OE. Copyright

More information

Session 14 Cable Support Systems

Session 14 Cable Support Systems Session 14 Cable Support Systems Cable Support Systems in the IEC World A new IEC Standard, IEC61537 2001 has been developed If full details of the cabling layout are available then the likely cable load

More information

6 ELECTRICAL PARAMETERS

6 ELECTRICAL PARAMETERS 6 ELECTRICAL PARAMETERS For power, low voltage and medium voltage cables, cross section nominal areas are calculated in taking into account several parameters as: permissible current carrying capacities

More information

EH-20 20m antenna. By VE3RGW

EH-20 20m antenna. By VE3RGW EH-20 20m antenna By VE3RGW Equivalent circuit of EH-20 (prototype 2A) antenna system. Upper cylinder Lower cylinder Ground Counter pose Phasing coil Impedance transformer and tune circuit Tune coil Feed

More information

Indicative costs for replacing SWER lines

Indicative costs for replacing SWER lines WIT.3019.005.0002 Indicative costs for replacing SWER lines 28 th August 2009 Department of Primary Industries Parsons Brinckerhoff Australia Pty Limited ABN 80 078 004 798 SWER_Replacement_Options_Report_v1_0

More information

How To Get A Power Line Extension

How To Get A Power Line Extension GUIDELINES FOR COMMERCIAL ELECTRIC SERVICE HOOKUP 1 Steps to Commercial Service Pay the Design Deposit Commercial Buildings: Up to 1, sq ft = $1,. 1, 5, sq ft = $2,. Over 5, sq ft = $3,. Commercial jobs

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin January 2016 CEC-10 [rev-9] Page 1 of 8 CANADIAN ELECTRICAL CODE SUBJECT: Section 10 Grounding and Bonding Rule 10-204 Grounding Connections for Alternating-Current

More information

MV CABLE TYPE C 33-226

MV CABLE TYPE C 33-226 MV CABLE TYPE C 33-226 Standards : CENELEC HD 620 C 33-226 Rated voltage Rated voltage : 12/20 (24) kv Design 1 Stranded aluminium, class 2 conductor 2 Extruded conducting screen on conductor 3 XLPE insulation

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD IEC 62305-3 Edition 2.0 2010-12 colour inside Protection against lightning Part 3: Physical damage to structures and life hazard INTERNATIONAL ELECTROTECHNICAL COMMISSION PRICE CODE

More information

Living with Electricity Easements

Living with Electricity Easements The Basslink electricity interconnector spans a total of 370 kilometers, from Georgetown in Tasmania, across Bass Straight to Gippsland where it connects with the Victorian electricity grid at Loy Yang.

More information

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to

More information

Section B: Electricity

Section B: Electricity Section B: Electricity We use mains electricity, supplied by power stations, for all kinds of appliances in our homes, so it is very important to know how to use it safely. In this chapter you will learn

More information

Strength and Durability for Life CORROSION CONTROL. The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines

Strength and Durability for Life CORROSION CONTROL. The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines Strength and Durability for Life CORROSION CONTROL The Effect of Overhead AC Power Lines Paralleling Ductile Iron Pipelines Last Revised: May 2016 Sharing of rights-of-way by AC power lines and buried

More information

How To Safely Dig For Natural Gas

How To Safely Dig For Natural Gas PNG DIAL B4-U-DIG book_final_nu 5/1/05 3:24 PM Page 2 Phoenix Natural Gas,197 Airport Road West, Belfast BT3 9ED. Tel. 08454 55 55 55. www.phoenix-natural-gas.com PNG DIAL B4-U-DIG book_final_nu 5/1/05

More information

Operating Instructions

Operating Instructions VMD202 Vehicle Motion Detector Operating Instructions CAUTIONS AND WARNINGS Never use the VMD202 as a safety reversing or presence detection system. The VMD202 requires that a vehicle be moving for detection.

More information

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

SF 6 Gas Insulated Switchgear Type SDF for 170 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDF for 170 kv 06B1-E-0001 With Trustworthy Technology, Structure Fuji Electric as a manufacturer of comprehensive substation equipment

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

UGVCL/SP/591/11KV HT AB CABLE

UGVCL/SP/591/11KV HT AB CABLE TECHNICAL SPECIFICATION FOR 11KV AERIAL BUNCHED CABLES FOR OVERHEAD LINES (CROSSED LINKED POLYTHENE DRY GAS CURED) 1. SCOPE This specification covers requirements of XLPE insulated, 11 KV Aerial Bunched

More information

Permits to Dig / Permits to Excavate / Permits to work near underground services

Permits to Dig / Permits to Excavate / Permits to work near underground services Permits to Dig / Permits to Excavate / Permits to work near underground services Aim and purpose The aim of this guidance is to identify what should be included in a permit to excavate / dig and additional

More information

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530)

Standards. www.nordx.com 5 ANSI/TIA/EIA-569-A (CSA T530) The primary focus of this standard is to provide design specifications and guidance for all building facilities relating to telecommunications cabling systems and components. This standard identifies and

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

Customer Substation Manual 08/05/02

Customer Substation Manual 08/05/02 Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

DESCRIPTION DWG DESCRIPTION DWG

DESCRIPTION DWG DESCRIPTION DWG DESCRIPTION DWG DESCRIPTION DWG Ferroresonance 3451/1 3451/2 3451/3 Electro-magnetic Fields (EMF) 3462/1 HV & LV Insulators (Links) 3463/1 A ORIGINAL ISSUE B 14.07.09 APPROVED DATE J. Brooks 25.02.03 INDEX

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

Utility Services. Increasing efficiency across the utilities network

Utility Services. Increasing efficiency across the utilities network Utility Services Increasing efficiency across the utilities network Sustainable engineering and design consultants Specialising in complex, infrastructure, process and built environments // UTILITY SERVICES

More information

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Requirements for the Attachment of Communication Cable Facilities on PPL Poles Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication

More information

Line Reactors and AC Drives

Line Reactors and AC Drives Line Reactors and AC Drives Rockwell Automation Mequon Wisconsin Quite often, line and load reactors are installed on AC drives without a solid understanding of why or what the positive and negative consequences

More information

Removal of EP 20 10 00 02 SP High Voltage Cable

Removal of EP 20 10 00 02 SP High Voltage Cable TN 018: 2014 Technical Note For queries regarding this document standards@asa.transport.nsw.gov.au www.asa.transport.nsw.gov.au TN 018: 2014 Issued date 12 March 2014 Effective dates 12 March 2014 Subject:

More information

Earth Ground Resistance

Earth Ground Resistance Principles, testing methods and applications Diagnose intermittent electrical problems Avoid unnecessary downtime Learn earth ground safety principles Earth Ground Resistance Why Ground, Why Test? Why

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

Work in Substations - General

Work in Substations - General Work in Substations - General Summary: This document supports the Power System Safety Rules and its requirements assembled under Work in Substations General Category 3 and apply to all persons working

More information

Document No Amendment No Approved By Approval Date Review Date NS112 DESIGN STANDARDS FOR INDUSTRIAL AND COMMERCIAL DEVELOPMENTS

Document No Amendment No Approved By Approval Date Review Date NS112 DESIGN STANDARDS FOR INDUSTRIAL AND COMMERCIAL DEVELOPMENTS Network Standard NETWORK Document No Amendment No Approved By Approval Date Review Date : : : : : NW000-S0041 1 Chief Engineer 26/10/2015 13/04/2018 NW000-S0041 NS112 DESIGN STANDARDS FOR INDUSTRIAL AND

More information

6/14/02 Chapter 14: Use of Electrical Test Equipment 1/20

6/14/02 Chapter 14: Use of Electrical Test Equipment 1/20 USE OF ELECTRICAL TEST EQUIPMENT Test equipment is necessary for determining proper set-up, adjustment, operation, and maintenance of electrical systems and control panels. The following is a general procedure

More information

Comparative study for cables and busbars

Comparative study for cables and busbars Comparative study for cables and busbars Preliminary considerations To compare the prices of two categories of product as different as traditional cables and busbars, it is necessary to make some preliminary

More information

AORC Technical meeting 2014

AORC Technical meeting 2014 http : //www.cigre.org B1-1055 AORC Technical meeting 2014 220 kv Long Distance Underground HVAC Cable Circuit NAVEED RAHMAN Nexans Olex Melbourne, Australia SUMMARY In 2009, the Victorian state government

More information

SECTION 18370 SIGNAL WIRE AND CABLE

SECTION 18370 SIGNAL WIRE AND CABLE SECTION 18370 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes requirements for all cable and wire required for signal and signal power system wiring to wayside shelters, junction boxes, and factory

More information

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN 5.1 Introduction So far in the development of this research, the focus has been to estimate the available insolation at a particular location on the earth s surface

More information

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

CHECKING AND TESTING ELECTRICAL INSTALLING WORK CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical

More information

Direction of current flow through conductor. Fig. 1 Magnetic field generated by current flow

Direction of current flow through conductor. Fig. 1 Magnetic field generated by current flow ingle Conductor Cable Copper heathed Cable heath Currents ingle conductor cables present certain application considerations that do not arise in multiconductor cable installations. These considerations

More information

Current Transformers

Current Transformers Tyco Electronics Corporation Crompton Instruments 1610 Cobb International Parkway, Unit #4 Kennesaw, GA 30152 Tel. 770-425-8903 Fax. 770-423-7194 Current Transformers Current transformers (CT's) provide

More information

NEW ZEALAND ELECTRICAL CODE OF PRACTICE. for ELECTRICAL SAFE DISTANCES

NEW ZEALAND ELECTRICAL CODE OF PRACTICE. for ELECTRICAL SAFE DISTANCES NZECP 34:2001 ISSN 0114-0663 NEW ZEALAND ELECTRICAL CODE OF PRACTICE for ELECTRICAL SAFE DISTANCES NZECP 34:2001 NEW ZEALAND ELECTRICAL CODE OF PRACTICE for ELECTRICAL SAFE DISTANCES Issued by: Manager,

More information

Chapter 22: Electric motors and electromagnetic induction

Chapter 22: Electric motors and electromagnetic induction Chapter 22: Electric motors and electromagnetic induction The motor effect movement from electricity When a current is passed through a wire placed in a magnetic field a force is produced which acts on

More information

Application Note. So You Need to Measure Some Inductors?

Application Note. So You Need to Measure Some Inductors? So You Need to Measure Some nductors? Take a look at the 1910 nductance Analyzer. Although specifically designed for production testing of inductors and coils, in addition to measuring inductance (L),

More information

The following table shows approximate percentage wise the

The following table shows approximate percentage wise the SHORT-CIRCUIT CALCULATION INTRODUCTION Designing an electrical system is easy and simple, if only the normal operation of the network is taken into consideration. However, abnormal conditions which are

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information