COMMONWEALTH OF VIRGINIA AT RICHMOND, OCTOBER 19,2011

Size: px
Start display at page:

Download "COMMONWEALTH OF VIRGINIA AT RICHMOND, OCTOBER 19,2011"

Transcription

1 COMMONEALTH OF VIRGINIA STATE CORPORATION COMMISSION AT RICHMOND, OCTOBER 19,2011 cc APPLICATION OF 7 0i 110 VIRGINIA ELECTRIC AND POER COMPANY CASE NO. PUE D/B/A DOMINION VIRGINIA POER For approval and certification of electric facilities : Hollymead 230 kv double circuit transmission line project FINAL ORDER On February 18, 201 1, Virginia Electric and Power Company d/b/a Dominion Virginia Power ("Dominion Virginia Power" or "Company") filed with the State Corporation Commission ("Commission") the Application of Virginia Electric and Power Company for Approval and Certification of Electric Facilities for the Hollymead 230 kv Double Circuit Transmission Line, Application No. 251 ("Application").' The Company proposes to replace its existing 230 kilovolts ("kv") Line #2054 radial single circuit transmission line tap ("Hollymead Tap line"), located entirely in Albemarle County, Virginia, with a double circuit 230 kv transmission line. The existing Hollymead Tap line runs a total of approximately 8.4 miles from the Line #2054 tap point at Cismont Junction to Rappahannock Electric Cooperative's Proffit Delivery Point and on to Dominion Virginia Power's existing Hollymead Substation, where it terminates. In addition to the proposed replacement of the Hollymead Tap line, the Company proposes to expand the existing Hollymead Substation in Albemarle County within the existing property lines and to add one 230 kv breaker and associated equipment (collectively, "Project"). According to Dominion Virginia Power, the Project is necessary to assure that reliable electric service will be provided to the customers served from the Company's Hollymead I Corrections and revisions to the Application and accompanying materials were filed by the Company on May 18, 201 1, May 31, 201 1, and June 13, See Ex. 2, 3, 4.

2 Substation and from Ra pahannock Electric Cooperative's Proffit 0 p Delivery Point consistent with mandatory North American Electric Reliability Corporation Reliability Standards for ca transmission facilities and the Company's planning criteria. 2 The Company initially estimated the cost of the Project as $40.7 million, based on the original proposal to use Aluminum Conductor Composite Reinforced conductors. 3 However, the estimated cost of the Project was lowered by $6.3 million, to $34.4 million, after the Company subsequently recommended using Aluminum Conductor Steel Reinforced conductors. 4 On March 17, 201 1, the Commission issued an Order for Notice and Hearing that, among other things, scheduled a public hearing to commence on July 14, ; established a procedural schedule for the filing of comments, notices of participation, and prepared testimony and exhibits ; and assigned a Hearing Examiner to conduct further proceedings and to issue a report. As noted in the Commission's Order for Notice and Hearing, the Commission's Staff ("Staff") requested the Department of Environmental Quality ("DEQ") to coordinate a review of the Project by state and local agencies and to file a report on the review. On May 18, 201 1, the DEQ filed its report ("DEQ Report"), which was admitted at the public hearing.' The DEQ Report contained the following recommendations with regard to the Project : 2 Ex. I at 1-2. Conduct an on-site delineation of all wetlands and streams within the [P]roject area with verification by the U.S. Army Corps of Engineers (Corps), using accepted methods and procedures, and follow DEQ's recommendations to avoid and minimize impacts to wetlands and streams (Environmental Iml2acts and Mitigation, item I (d), pages 9-10). 3 The initial estimate included $38.4 million for transmission and $2.3 million for substation work. Ex. I at 2. 4 This change affected only the estimate of transmission costs and did not affect the estimated cost for substation work. Ex. 2 ; Ex. 14 at 12. ' Ex. 12.

3 H Consider DEQ's recommendations, including reuse of CO vegetative waste in lieu of open burning, regarding air quality 40 protection (Environmental Iml2acts and Mitigation, item 4(f), page 14). Reduce solid waste at the source, reuse it and recycle it to the maximum extent practicable, and follow DEQ's recommendations to manage waste, as applicable (Environmental Impacts and Mitigation, item 5(e), page 15). Coordinate with [the Department of Conservation and Recreation] for updates to the Biotics Data System database if a significant amount of time passes before the [P]roject is implemented Environmental Impacts-and Mitigation, item 6(e), page 16). Coordinate with the Department of Game and Inland Fisheries regarding its recommendations for protected species and other wildlife (Environmental Impacts and Mitigation, item 7(c), pages 17-18). ork with the Department of Historic Resources and other appropriate parties regarding its recommendations to protect historic and archaeological resources, as applicable (LEnvironmental Impacts and Mitigation, item 9(d), pages 21 and 22). Coordinate with the Virginia Department of Transportation regarding its recommendations (Environmental Impacts and Mitigatio item I O(d), page 22). Coordinate with the Federal Aviation Administration (FAA) to ensure compliance with aviation regulations and with the Department of Aviation (DOAv) regarding its recommendations to ensure safety during construction at airports (Environmental Impacts and Mitigation, item I I (c), page 23). Coordinate with the Virginia Department of Health regarding its recommendations to protect water supplies, including implementation of best management practices Environmental Impacts and Mitigation, item 12(c), page 24). Follow the principles and practices of pollution prevention to the maximum extent practicable Environmental Impacts and Mitigation, item 13, page 24). OM 3

4 Limit the use of pesticides and herbicides to the extent practicable (Environmental Impacts and Mitigation, item 14, page 24) PA 00 Timely notices of participation were filed in this proceeding by Ronald L. Kerber ("Kerber"), G. David Phelps Hamar ("Hamar"), Leila Fiery Hamar, Marie B. LaRobardier, Scott H. Bolin, Raffaele Coscia, and Clara Coscia. 7 Nine (9) interested persons filed written comments, which raised concerns about the need for the new line ; environmental impacts ; route and structure selection ; use of overhead, rather than underground, construction ; and rate impact. The public hearing was convened on July 14, 201 1, before Hearing Examiner Michael D. Thomas. itnesses for the Company presented testimony and exhibits on the need for the Project, construction plans and process, and the impact of the project on the environment. The Staff offered testimony and exhibits on its review of the Project and concluded that the Company has reasonably demonstrated the need for networking the Hollymead Tap load to comply with the Company's reliability planning criteria. 8 The Staff testified about the criteria of the underground pilot program established by Chapter 799 of the 2008 Virginia Acts of Assembly ("HB 1319") and the unsuitability of the Project for this program. 9 Additionally, the Staff provided analysis on nine (9) alternatives to the Project.10 Finally, the Staff analyzed the height, costs, and right-of-way requirements associated with using different structure types for the segment of the line running from Cismont Junction to Proffit Delivery Point ("Cismont- 6 Id. at Respondents Leila Fiery Hamar, Marie B. LaRobardier, Scott H. Bolin, Raffaele Coscia, and Clara Coscia did not attend the hearing or otherwise participate in the formal proceeding. 8 Ex. 14 at Id. at '0 Id at , 33. 4

5 Proffit"), which traverses the Southwest Mountains Rural Historic District. The Staff s analysis focused on three structure types that would require the acquisition of no new right-of-way : (1) paired poles, as proposed by the Company ; (2) monopoles ; and (3) an H-frame design presented by the Staff." This comparison was illustrated by the Staff as folos :12 Double-circuit Double-circuit Double-circuit paired-pole monopole H-frame Av[erage] height (ft.) Project cost ($M) Incremental cost () Incr[emental] cost ($M/mile) Respondent Kerber presented testimony and exhibits on the aesthetic and historic value of the Southwest Mountains Rural Historic District where he lives and in which the Hollymead Tap line is located, his involvement in a citizen advisory group convened by the Company regarding the Project, and requirements that he recommends be placed on the Company if the Project is approved. Additionally, Respondent Kerber stated his preference for an alternative route and his concerns about the collocation of transmission lines. 13 Respondent Hamar presented testimony on recent projections of national load growth, which are lower than earlier national projections, the Southwest Mountains Rural Historic District in which he lives, and his concerns about the existing right-of-way. If the Project is approved, Respondent Hamar stated his preference for the paired-pole or H-frame design. 14 One public witness, Robert Marmet, testified at the hearing on behalf of the Piedmont Environmental Council ("Piedmont"). Piedmont testified that, while it prefers to advocate " Id at 20-23, Id. at 34 (option titles omitted). 13 Ex. 9 ; Tr Ex. 13 ; Tr

6 non-transmission alternatives wherever they are feasible, it is not in a position to dispute the Company's need analysis on the Project. Piedmont also testified about its participation in the 43 PA community advisory group on the Project and the importance of the Southwest Mountains Rural Historic District. Piedmont recommended adoption of the paired-pole or H-frame design and asserted that the incremental cost of adopting one of these two options, rather than the monopole design, is de minimis and justified by the location of the line. 15 On August 22, 201 1, the Hearing Examiner issued his report ("Hearing Examiner's Report"). The Hearing Examiner provided a summary of the evidence on the need for the Project, electric alternatives to the Project, alternative structure options for replacing the existing Hollymead Tap line with a double-circuit line, and the Project's environmental impacts. Following his analysis, the Hearing Examiner made the following findings : (1) The Company's load growth forecasts support the need for the proposed facilities ; (2) The proposed facilities meet the need for reliability at the Hollymead Substation and the Proffit [Delivery Point] ; (3) The Company's [demand-side management ("DSM")] programs will not eliminate the need for the proposed facilities ; (4) The proposed facilities have the least impact on the environment and adjoining landowners, and is the most cost-effective alternative to meet the Company's operational and reliability needs ; (5) The proposed facilities use existing rights-of-way to the maximum extent practicable ; (6) The proposed facilities are necessary for continued economic development in the area served by the Hollymead Substation and Proffit [Delivery Point] ; " Tr

7 P-t PA (7) The Staff s double circuit H-frame design (without cross-braces) a reasonably mitigates the Project's visual impact on the PA Southwest cc Mountains Rural Historic District ; (8) There are no adverse environmental impacts that would prevent the construction of the proposed facilities ; (9) The I I recommendations in the DEQ Report are desirable or necessary to minimize adverse environmental impact associated with the Project ; (10) The proposed facilities do not represent a hazard to human health, which finding is consistent with the Virginia Department of Health's report entitled Monitoring of Ongoing Research on the Health Effects of High Voltage Transmission Lines (Final Report) dated October 31, 2000 ; (11) There is no benefit to "reverse phasing" the Project's transmission lines ; (12) The proposed facilities do not represent a hazard to safe air navigation ; (13) The proposed facilities do not meet the criteria to be considered as an underground pilot project under HB 1319 ; (14) The Company's communications outreach program is adequate ; and (15) A certificate of public convenience and necessity should be issued for the Company to construct and operate the proposed facilities. 16 Based on his findings, the Hearing Examiner recommended that the Commission adopt the findings and issue a certificate of public convenience and necessity to the Company to construct and operate the proposed facilities. 17 The Hearing Examiner further recommended that the Commission : (1) approve the type of conductor proposed by the Company, rather than non-reflective conductors ; (2) require the Company to restore the right-of-way that crosses agricultural lands to its pre-construction condition, if requested by a landowner ; and (3) require the Company to provide the services of its forester to : (i) assist the landowner in delineating the 16 Hearing Examiner's Report at " Id. at

8 safe planting area for a visual buffer ; and (ii) provide the landowner with a landscape plan of Q PA 18 cc native trees and shrubs that may be safely planted next to an electric transmission right-of-way. (A In the only filed response to the Hearing Examiner's Report, the Company generally supported the Hearing Examiner's recommendations and findings but clarified that erosion and sediment control specifications may require temporary seeding with seed mix that best holds soil during construction. The Company further recommended that any Commission requirement for the Company's forester to provide services to landowners be clarified and limited to : (1) landowners whose property is actually crossed by the right-of-way for the Project and who request such assistance within six (6) months following the Project's in-service date ; and (2) the Company's forester assisting any such landowners in delineating safe planting areas and providing the Company's "Suggested Species Planting List."' 9 NO THE COMMISSION, upon consideration of this matter, is of the opinion and finds that Dominion Virginia Power's application to construct and operate the proposed double-circuit 230 kv transmission line in Albemarle County is justified by the public convenience and necessity, and a certificate of public convenience and necessity should be issued authorizing the construction and operation of the proposed Project, subject to the findings and conditions discussed below. Approval The statutory scheme governing the Company's application is found in several chapters of Title 56 of the Code of Virginia ("Code"). Section A of the Code provides that "[ilt shall be unlawful for any public utility to construct... facilities for use in public utility service, " Id. at 40. '9 Comments of Virginia Electric and Power Company on Hearing Examiner's Report, September 12, 201 1, at

9 without first having obtained a certificate from the Commission that the public convenience cc and necessity require the exercise of such right or privilege." (D Section of the Code further directs the Commission to consider several factors when reviewing the Company's application. Subsection A of the statute provides that : henever the Commission is required to approve the construction of any electrical utility facility, it shall give consideration to the effect of that facility on the environment and establish such conditions as may be desirable or necessary to minimize adverse environmental impact.... In every proceeding under this subsection, the Commission shall receive and give consideration to all reports that relate to the proposed facility by state agencies concerned with environmental protection ; and if requested by any county or municipality in which the facility is proposed to be built, to local comprehensive plans that have been adopted.... Additionally, the Commission (i) shall consider the effect of the proposed facility on economic development within the Commonwealth,..., and (ii) shall consider any improvements in service reliability that may result from the construction of such facility. Section B of the Code further provides that : "[a]s a condition to approval the Commission shall determine that the line is needed and that the corridor or route the line is to follow will reasonably minimize adverse impact on the scenic assets, historic districts and environment of the area concerned." The Code further requires the Commission to consider existing right-of-way easements when siting transmission lines. Section C of the Code provides that "[i]n any hearing the public service company shall provide adequate evidence that existing rights-of-way cannot adequately serve the needs of the company." In addition, C of the Code provides that "[plrior to acquiring any easement of right-of-way, public service corporations will consider the feasibility of locating such facilities on, over, or under existing easements of rights-of-way." 9

10 PA FA Finally, for inclusion of a project in the underground pilot program established by FIB 1319, the project must satisfy the following three criteria : Need (1) An engineering analysis demonstrates that it is technically feasible to place the proposed line, in whole or in part, underground ; (2) The estimated additional cost of placing the proposed line, in whole or in part, underground does not exceed 2.5 times the cost of placing the same line overhead, assuming accepted industry standards for undergrounding to ensure safety and reliability. If the public utility, the affected localities, and the State Corporation Commission agree, a proposed underground line whose cost exceeds 2.5 times the cost of placing the line overhead may also be accepted into the pilot program ; and (3) The governing body of each locality in which a portion of the proposed line will be placed underground indicates, by resolution, 20 general community support for the line to be placed underground. e agree with the Hearing Examiner and find that the Company's load growth forecasts support the need for the Project to ensure reliability at the Company's Hollymead Substation and at Rappahannock Electric Cooperative's Proffit Delivery Point. 21 No party or member of the Staff has disputed evidence in the record that peak demand on the Hollymead Tap line exceeded the Company's planning criteria for radial lines in 2009 and that peak demand on the line has increased at an annual rate of 5.5% over the period from 2001 to The Company's peak load forecasts presented in support of the Project are consistent with this historic trend and the undisputed addition of a large block load customer. 23 e agree with the Hearing Examiner that Va. Acts ch. 799, Enactment Clause 1, Hearing Examiner's Report at 31-33, Id. at ; Ex. 14 at Hearing Examiner's Report at 3 1 ; Ex. I at Appendix, Attachment I.B.3 and I.B.6. 10

11 the record does not support a finding that the Company's DSM programs, all of which are voluntary for customers, can eliminate the need for the Proj ect.24 M Economic Development and Service Reliability The evidence submitted in this proceeding supports the conclusion that the Project is necessary to serve load growth that includes a large block load of government office and data center facilities that is expected to increase significantly over the next few years. 25 Routing and Right-of-ay e agree with the Hearing Examiner that "[tlhe proposed facilities use existing rights-of-way to the maximw-n extent practicable. "26 The rebuilt Hollymead Tap line will be located entirely on existing right-of-way that has been occupied by the existing line for over twenty-five (25) years. 27 Additionally, the substation work associated with the Project will occur within the Company's existing property lines. 28 Thus, Dominion Virginia Power was not required, in accordance with C of the Code, to demonstrate that existing rights-of-way could not adequately serve its needs. For the reasons provided by the Hearing Examiner, we agree that the Project, compared to other electric and routing alternatives reviewed in this proceeding, has "the least impact on the environment and adjoining landowners, and is the most cost-effective alternative to meet the Company's operational and reliability needs." 29 2' Hearing Examiner's Report at Hearing Examiner's Report at 34 (citing Tr. Ex. at 115 ; Ex. 1, Appendix at 3 ; and Ex. 14). 26 Hearing, Examiner's Report at ' Ex. 22 at 2-3. " Ex. 7 at Hearing Examiner's Report at 33-34, 4 1.

12 ~A HB 1319 The Commission agrees with the Hearing Examiner that the Project does not meet the 00 M criteria necessary for consideration as a HB 1319 underground pilot project.30 Scenic Assets and Historic Districts As discussed above, the existing line has occupied the right-of-way for over twenty-five (25) years, and the rebuilt line will be located along the same route as the existing line and entirely in the existing right-of-way. Additionally, as we discuss below, the H-frame design recommended by the Hearing Examiner will reasonably minimize the impact to scenic assets and historic districts for the longest segment of the proposed line. Accordingly, adverse impact on scenic assets and historic districts in the region will be reasonably minimized consistent with B of the Code. The Company agreed with the Department of Historic Resources to continue its impact evaluation, including appropriate mitigation in accordance with the Guidelinesfor Assessing Impacts ofproposed Transmission Lines and Associated Facilities 31 on Hisioric Resources in the Commonwealth of Virginia (2008). e find that appropriate steps to protect historic and scenic assets have been taken. Environmental Impact Under A and B of the Code, the Commission is required to consider the proposed Project's impact on the environment and to establish such conditions as may be desirable or necessary to minimize adverse environmental impact. e agree with the Hearing Examiner and find that the H-frame (without cross-braces) design will reasonably minimize adverse environmental impact for construction of the Cismont-Proffit segment of the proposed 30 Id. at 39 (citing Ex. 14). " Ex. 22 at 8. 12

13 line. 32 As discussed by the Hearing Examiner, the H-frame design is materially shorter than the monopole design ; is less expensive than, but operationally equivalent to, the paired-pole design ; Q a PA ca is not opposed by the Company ; and reasonably protects the viewshed through the Southwest Mountains Rural Historic Distri Ct.33 Based on the specific facts of this case, the record supports conditioning our approval herein on construction with the H-frame (without cross-braces) design for the Cismont-Proffit segment of the Project.34 This finding is strictly limited to the facts of this case and, thus, does not serve as precedent for future transmission facilities proposed by Dominion Virginia Power or others. Section A of the Code further provides that the Commission shall receive and give consideration to all reports that relate to the proposed Project by state agencies concerned with environmental protection. As a requirement of our approval herein, the Company shall also comply with the recommendations from the DEQ Report, as recommended by the Hearing Examiner. 35 Finally, with respect to the additional conditions recommended by the Hearing Examiner regarding right-of-way restoration on agricultural lands and the provision of the Company's 32 For the other segments of the proposed line, we approve the structure types proposed by the Company. Additionally, we agree with the Hearing Examiner's finding that no benefit to "reverse phasing" has been demonstrated for this Project. Hearing Examiner's Report at 38 (citing Ex. 17). 33 Hearing Examiner's Report at e adopt the Hearing Examiner's finding that the additional cost of installing non-reflective conductors has not been justified. Hearing Examiner's Report at Although we agree with the Hearing Examiner that the record supports a finding that the Project does not represent a hazard to safe air navigation, we note that adoption of the DEQ Report recommendation that the Company coordinate with the Federal Aviation Administration will ensure compliance with any federal aviation regulations or guidelines applicable to the Project. Hearing Examiner's Report at

14 forestry services, we adopt those conditions subject to the clarifications and limitations cc 36 recommended by the Company and which we find to be reasonable. (A Accordingly, IT IS ORDERED THAT : (1) The Company is authorized to construct and operate the proposed 8.4 mile 230 kv double-circuit Hollymead Tap line on the route proposed in the Company's Application subject to the findings and conditions imposed herein. The Company is also authorized to expand its existing Hollymead Substation, as proposed in the Company's Application, and to operate the expanded substation. (2) Pursuant to , , and related provisions of Title 56 of the Code, the Company's Application for a certificate of public convenience and necessity to construct and operate the proposed double-circuit transmission line and associated substation work is granted as provided herein and subject to the requirements set forth in this Final Order. (3) Pursuant to the Utility Facilities Act, Chapter ( el seq.) of Title 56 of the Code, the Company is issued the following certificate of public convenience and necessity : Certificate No. ET-58k, which authorizes Virginia Electric and Power Company under the Utility Facilities Act to operate certificated transmission lines and facilities in Albemarle County, all as shown on the map attached to the certificate, and to construct and operate facilities as authorized in Case No. PUE , cancels Certificate No. ET-58j, issued to Virginia Electric and Power Company on September 27, 1984, in Case No. PUE (4) The Commission's Division of Energy Regulation shall forthwith provide the Company copies of the certificate issued in Ordering Paragraph (3) above with the detailed map attached. 36 Comments of Virginia Electric and Power Company on Hearing Examiner's Report, September 12,

15 I-A I-A (5) The transmission line and associated substation work approved herein must be constructed and operational by May 2014 provided, however, the Company is granted leave to apply for an extension for good cause shown. (6) As there is nothing further to come before the Commission, this matter is dismissed and the papers herein placed in the file for ended causes. ATTESTED COPY hereof shall be sent by the Clerk of the Commission to : Lisa S. Booth, Esquire, Senior Counsel, Dominion Resources Services, Inc., P. 0. Box 26532, Richmond, Virginia ; Stephen H. atts 11, Esquire, McGuireoods LLP, One James Center, 901 East Cary Street, Richmond, Virginia ; J. Randolph Parker, Esquire, Parker, McElwain & Jacobs, 2340 Commonwealth Drive, Charlottesville, Virginia ; Ronald L. Kerber, 3365 Stony Point Road, Charlottesville, Virginia ; Raffaele and Clara Coscia, 5045 Stony Point Pass, Keswick, Virginia ; Marie B. LaRobardier, 5284 Stony Point Pass, Keswick, Virginia ; G. David Phelps Hamar and Leila Fiery Hamar, 4025 Stony Point Pass, Keswick, Virginia ; and Scott H. Bolin, 3642 Stony Point Road, Charlottesville, Virginia ; and a copy shall be delivered to the Commission's Office of General Counsel and Division of Energy Regulation. 15

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER

COMMONWEALTH OF VIRGINIA LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF FINAL ORDER COMMONWEALTH OF VIRGINIA STATE CORPORATION COMMISSION LRK,'S UNCE AT RICHMOND, SEPTEMBER 7,2012 TRUL CE.. P 112 : 51 APPLICATION OF VIRGINIA ELECTRIC AND POWER COMPANY For approval and certification of

More information

Virginia State Corporation Commission efiling CASE Document Cover Sheet

Virginia State Corporation Commission efiling CASE Document Cover Sheet Virginia State Corporation Commission efiling CASE Document Cover Sheet Case Number (if already assigned) pue-201 1-00011 Case Name (if known) Application of Virginia Electric and Power Company for approval

More information

REBUILD IN ROCKBRIDGE COUNTY

REBUILD IN ROCKBRIDGE COUNTY COMMONEALTH OF VIRGINIA STATE CORPORATION COMMISSION"' PREFILED STAFF TESTIMONY ON THE VIRGINIA ELECTRIC AND POER COMPANY LEXINGTON-CLOVERDALE 500 kv TRANSMISSION LINE REBUILD IN ROCKBRIDGE COUNTY CASE

More information

COMMONWEALTH OF VIRGINIA, ex rel. I LI P

COMMONWEALTH OF VIRGINIA, ex rel. I LI P COMMONEALTH OF VIRGINIA STATE CORPORATION COMMISSION AT RICHMOND, NOVEMBER 14,2013 COMMONEALTH OF VIRGINIA, ex rel. I LI P 43 STATE CORPORATION COMMISSION Concerning the establishment of a renewable energy

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada

Q: PLEASE STATE YOUR NAME AND BUSINESS ADDRESS. A: Gerry Sheerin. Sheerin Technical, 25 Eastville Avenue, Toronto, Ontario Canada DIRECT TESTIMONY OF GERRY SHEERIN, P. ENG ON BEHALF OF PIEDMONT ENVIRONMENTAL COUNCIL BEFORE THE STATE CORPORATION COMMISSION OF VIRGINIA CASE NOS. PUE-00-0001 AND PUE-00-000 1 1 1 1 1 1 1 1 1 Q: PLEASE

More information

RESTRICTIVE COVENANTS. THIS DECLARATION OF RESTRICTIVE COVENANTS is made this day of, 20, by RECITALS

RESTRICTIVE COVENANTS. THIS DECLARATION OF RESTRICTIVE COVENANTS is made this day of, 20, by RECITALS STATE OF NEW YORK COUNTY OF DECLARATION OF RESTRICTIVE COVENANTS THIS DECLARATION OF RESTRICTIVE COVENANTS is made this day of, 20, by, ("Declarant"), A New York corporation with offices at,, New York.

More information

State Of Minnesota's Public Utilities Bill And Substation Number 11

State Of Minnesota's Public Utilities Bill And Substation Number 11 ENVIRONMENTAL ASSESSMENT FOR THE PROPOSED WORTHINGTON PUBLIC UTILITIES 115 KV TRANSMISSION LINE BY NOBLES COUNTY, MINNESOTA May 2011 ENVIRONMENTAL ASSESSMENT WORTHINGTON MUNICIPAL UTILITIES (WPU) PROPOSED

More information

COMMONWEALTH OF VIRGINIA ORDER FOR NOTICE AND HEARING. On July 8, 2015, Prince George Electric Cooperative ("PGEC" or "Cooperative") filed

COMMONWEALTH OF VIRGINIA ORDER FOR NOTICE AND HEARING. On July 8, 2015, Prince George Electric Cooperative (PGEC or Cooperative) filed COMMONWEALTH OF VIRGINIA STATE CORPORATION COMMISSION sj AT RICHMOND, JULY 24, 2015 _ ninc & :::c^;:;; :, ceiltrol CENTER APPLICATION OF 2315 JUL 2^ P ^"^ P tfuss PRINCE GEORGE ELECTRIC COOPERATIVE CASE

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

345 kv Brazos Valley Connection Project FAQs

345 kv Brazos Valley Connection Project FAQs 345 kv Brazos Valley Connection Project FAQs Overview 1. Who is CenterPoint Energy Houston Electric, LLC? CenterPoint Energy Houston Electric, LLC (CenterPoint Energy) is an electric utility that maintains

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

Control Number : 14637. Item Number : 5. Addendum StartPage : 0

Control Number : 14637. Item Number : 5. Addendum StartPage : 0 Control Number : 14637 Item Number : 5 Addendum StartPage : 0 Pubtic Utility Commission of Tex s 7800 Shoal Creek Boulevard Austin, Texas 78757-1098 512/458-0100. (Fax) 458-8340 Pat Wood, III Chairman

More information

Virginia State Corporation Commission efiling CASE Document Cover Sheet

Virginia State Corporation Commission efiling CASE Document Cover Sheet Case Number (if already assigned) Case Name (if known) Virginia State Corporation Commission efiling CASE Document Cover Sheet PUE-2015-00117 Application of Virginia Electric and Power Company For approval

More information

Wildlife Habitat Conservation and Management Program

Wildlife Habitat Conservation and Management Program Wildlife Habitat Conservation and Management Program Manual for Counties and Cities Oregon Department of Fish and Wildlife 2015 Table of Contents 1. Introduction Purpose of the habitat program Objective

More information

How To Amend A Stormwater Ordinance

How To Amend A Stormwater Ordinance Regulatory Alternatives to Address Stormwater Management and Flooding in the Marlboro Street Study Area Alternative 1: Amend Existing Local Regulations This proposed alternative provides an incremental

More information

Sec. 22a-1a page 1 (4-97)

Sec. 22a-1a page 1 (4-97) Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination

More information

UNITED STATES OF AMERICA 131 FERC 62,175 FEDERAL ENERGY REGULATORY COMMISSION. United Water Conservation District Project No.

UNITED STATES OF AMERICA 131 FERC 62,175 FEDERAL ENERGY REGULATORY COMMISSION. United Water Conservation District Project No. UNITED STATES OF AMERICA 131 FERC 62,175 FEDERAL ENERGY REGULATORY COMMISSION United Water Conservation District Project No. 2153-022 ORDER APPROVING SPOIL MANAGEMENT, EROSION, AND SEDIMENT CONTROL PLAN

More information

Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6

Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6 Conservation Tax Credit Regulations Chapter 391-1-6 A-1 RULES OF GEORGIA DEPARTMENT OF NATURAL RESOURCES CHAPTER 391-1-6 GEORGIA CONSERVATION TAX CREDIT PROGRAM TABLE OF CONTENTS 391-1-6-.01 Purpose and

More information

Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program

Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program Angora Fire Restoration Activities June 24, 2007 Presented by: Judy Clot Forest Health Enhancement Program California Tahoe Conservancy Independent California State Agency within the Resources Agency Governed

More information

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633

March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633 ADDENDUM TO THE MICHELSON WATER RECLAMATION PLANT PHASE 2 & 3 CAPACITY EXPANSION PROJECT FEBRUARY 2006 FINAL ENVIRONMENTAL IMPACT REPORT AND THE SAN JOAQUIN FRESHWATER MARSH ENHANCEMENT PLAN REVISED SEPTEMBER

More information

BEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN CITY OF WAUWATOSA S REPLY POST-HEARING BRIEF

BEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN CITY OF WAUWATOSA S REPLY POST-HEARING BRIEF PSC REF#:179804 BEFORE THE PUBLIC SERVICE COMMISSION OF WISCONSIN Joint Application of Wisconsin Electric Power Company, as an Electric Public Utility, for Authority to Construct a New Distribution Substation

More information

Thanks, Rob, Thanks, Rob,

Thanks, Rob, Thanks, Rob, From: Hingtgen, Robert J To: "Asha Bleier"; Patrick BROWN Cc: Gungle, Ashley; Hofreiter, Larry; Ramaiya, Jarrett; Waterman, Ryan R. Subject: RE: 3910 120005, Soitec Solar -- RE: Soitec - Key Viewshed Map

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

TOWER ORDINANCE TOWN OF OWLS HEAD

TOWER ORDINANCE TOWN OF OWLS HEAD TOWER ORDINANCE TOWN OF OWLS HEAD Adopted - August 30, 1999 Amended - August 26, 2002 Amended June 1, 2009 TABLE OF CONTENTS PAGE Section 1 Title.. 1 Section 2 Authority.. 1 Section 3 Purpose. 1 Section

More information

As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing

As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing N A T U R A L R E S O U R C E C O N S E R V A T I O N As stewards of the land, farmers must protect the quality of our environment and conserve the natural resources that sustain it by implementing conservation

More information

All routes and route segments included in this notice are available for selection and approval by the Public Utility Commission of Texas.

All routes and route segments included in this notice are available for selection and approval by the Public Utility Commission of Texas. Application of Brazos Electric Power Cooperative, Inc. to Obtain a Certificate of Convenience and Necessity for a Proposed Transmission Line in Denton County, Texas PUBLIC UTILITY COMMISSION OF TEXAS (PUC)

More information

Backyard Buffers that Work for People and Nature by Restoring Ecological Function

Backyard Buffers that Work for People and Nature by Restoring Ecological Function Backyard Buffers that Work for People and Nature by Restoring Ecological Function What is a Wetland Buffer? A wetland buffer is a simple land management practice that is employed by municipalities to protect

More information

Proposed General Plan Update Goals, Policies, and Implementation Actions

Proposed General Plan Update Goals, Policies, and Implementation Actions Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental

More information

3.1.8 Utilities and Service Systems

3.1.8 Utilities and Service Systems 3.1.8 Utilities and Service Systems This section discusses potential impacts to utilities and service systems, including water, wastewater, and solid waste hauling and disposal, resulting from the implementation

More information

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002 Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon

More information

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how

More information

A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1

A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 J. Bonham 2 and K. Stephenson Abstract Recently the US Army Corps of Engineers (the Corps) has increased

More information

State Environmental Trust Funds

State Environmental Trust Funds INFORMATION BRIEF Minnesota House of Representatives Research Department 600 State Office Building St. Paul, MN 55155 John Helland, Legislative Analyst 651-296-5039 December 2005 State Environmental Trust

More information

Section 1A Alternatives Analysis

Section 1A Alternatives Analysis Maine GenLead 115kV Generator Lead Transmission Line, Aroostook and Penobscot Counties, Maine Section 1A Alternatives Analysis Maine GenLead 115kV Generator Lead Transmission Line, Aroostook and Penobscot

More information

2015 -- H 6042 S T A T E O F R H O D E I S L A N D

2015 -- H 6042 S T A T E O F R H O D E I S L A N D LC00 01 -- H 0 S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 01 A N A C T RELATING TO TOWNS AND CITIES -- RHODE ISLAND COMPREHENSIVE PLANNING AND LAND USE ACT Introduced

More information

STORMWATER BEST MANAGEMENT PRACTICES (BMPs) & CONVEYANCES OPERATION & MAINTENANCE AGREEMENT

STORMWATER BEST MANAGEMENT PRACTICES (BMPs) & CONVEYANCES OPERATION & MAINTENANCE AGREEMENT Prepared by / Return to: West Pikeland Township 1645 Art School RD Chester Springs PA 19425 Being UPI # 34- - STORMWATER BEST MANAGEMENT PRACTICES (BMPs) & CONVEYANCES OPERATION & MAINTENANCE AGREEMENT

More information

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) PREFILED TESTIMONY OF SCOTT S. MALLORY ON BEHALF OF PETITIONERS

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) ) PREFILED TESTIMONY OF SCOTT S. MALLORY ON BEHALF OF PETITIONERS STATE OF VERMONT PUBLIC SERVICE BOARD Joint Petition of Vermont Transco, LLC, Vermont Electric Company, Inc. ( VELCO, City of Burlington Electric Department ( BED and Green Mountain Power Corporation for

More information

DELAWARE COUNTY STREAM CORRIDOR MANAGEMENT PROGRAM TWO-YEAR ACTION PLAN FOR THE WEST BRANCH DELAWARE RIVER CANNONSVILLE RESERVOIR BASIN

DELAWARE COUNTY STREAM CORRIDOR MANAGEMENT PROGRAM TWO-YEAR ACTION PLAN FOR THE WEST BRANCH DELAWARE RIVER CANNONSVILLE RESERVOIR BASIN DELAWARE COUNTY STREAM CORRIDOR MANAGEMENT PROGRAM TWO-YEAR ACTION PLAN FOR THE WEST BRANCH DELAWARE RIVER CANNONSVILLE RESERVOIR BASIN May 2011 - April 2013 1. Introduction 2. Recommendations Table of

More information

understanding Sustainable Landscaping & Tree Preservation Standards

understanding Sustainable Landscaping & Tree Preservation Standards understanding Sustainable Landscaping & Tree Preservation Standards Purpose To promote landscaping around development that is compatible with the existing environment, and which reduces greenhouse gas

More information

THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES MASSACHUSETTS ASSOCIATION OF CONSERVATION COMMISSIONS

THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES MASSACHUSETTS ASSOCIATION OF CONSERVATION COMMISSIONS THE LOCAL ROLE IN PERMITTING INTERSTATE NATURAL GAS PIPELINES PRESENTATION AT CITIZEN PLANNER TRAINING COLLABORATIVE CONFERENC E BY EUGENE B. BENSON, EXECUTIVE DIRECTOR, MACC MARCH 21, 2015 Massachusetts

More information

MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL

MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL MASSACHUSETTS COASTAL NONPOINT PROGRAM NOAA/EPA DECISIONS ON CONDITIONS OF APPROVAL FOREWORD This document contains the basis for NOAA and EPA s decision to fully approve Massachusetts Coastal Nonpoint

More information

1. Who is CenterPoint Energy Houston Electric, LLC?

1. Who is CenterPoint Energy Houston Electric, LLC? 1. Who is CenterPoint Energy Houston Electric, LLC? CenterPoint Energy Houston Electric, LLC (CenterPoint Energy or the Company) is an electric utility that maintains the wires, towers, poles, and electric

More information

Tucson Electric Power Company Rules and Regulations

Tucson Electric Power Company Rules and Regulations Original Sheet No.: 907 Introduction The Company will construct, own, operate and maintain lines along public streets, roads and highways which the Company has the legal right to occupy, and on public

More information

DOUGLAS COUNTY ZONING RESOLUTION Section 5 RR - Rural Residential District 3/10/99. -Section Contents-

DOUGLAS COUNTY ZONING RESOLUTION Section 5 RR - Rural Residential District 3/10/99. -Section Contents- SECTION 5 RR - RURAL RESIDENTIAL DISTRICT -Section Contents- 501 Intent...5-2 502 Principal Uses...5-2 503 Accessory Uses...5-3 504 Uses Permitted by Special Review...5-4 505 Land Dedication...5-4 506

More information

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC.

BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E DIRECT TESTIMONY RAJESH GUPTA PROJECT MANAGER, ENTERGY SERVICES, INC. BEFORE THE ARKANSAS PUBLIC SERVICE COMMISSION'^^ j E s : D IN THE MATTER OF THE APPLICATION OF ENTERGY ARKANSAS, INC. FOR A CERTIFICATE OF ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED TO CONSTRUCT AND OPERATE

More information

SOLAR ENERGY FACILITIES ZONING AMENDMENTS

SOLAR ENERGY FACILITIES ZONING AMENDMENTS SOLAR ENERGY FACILITIES ZONING AMENDMENTS 1. In Section 10, Special Regulations, of the Zoning Bylaw, insert a new Section 10.06, to be entitled Solar Energy Facilities and to read as follows: SECTION

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

DELAWARE TOWNSHIP ORDINANCE #2011-06LU

DELAWARE TOWNSHIP ORDINANCE #2011-06LU DELAWARE TOWNSHIP ORDINANCE #2011-06LU AN ORDINANCE SUPPLEMENTING AND AMENDING THE LAND USE ORDINANCE OF THE TOWNSHIP OF DELAWARE BY PERMITTING SOLAR ENERGY SYSTEMS. #2011-06LU WHEREAS, it is the purpose

More information

Virginia Electric and Power Company Subsection A 4 Rate Adjustment Clause. Direct Testimony and Exhibits

Virginia Electric and Power Company Subsection A 4 Rate Adjustment Clause. Direct Testimony and Exhibits Virginia Electric and Power Company Subsection A 4 Rate Adjustment Clause Table of Contents Direct Testimony and Exhibits David M. Wilkinson James D. Jackson, Jr. Paul B. Haynes Filing Schedule 46 Filing

More information

SEC. 4001. PURPOSE. SEC. 4002. DEFINITIONS. SEC. 4003. COLLABORATIVE FOREST LANDSCAPE RESTORATION PROGRAM.

SEC. 4001. PURPOSE. SEC. 4002. DEFINITIONS. SEC. 4003. COLLABORATIVE FOREST LANDSCAPE RESTORATION PROGRAM. TITLE IV--FOREST LANDSCAPE RESTORATION SEC. 4001. PURPOSE. The purpose of this title is to encourage the collaborative, sciencebased ecosystem restoration of priority forest landscapes through a process

More information

Corridor Goals and Objectives

Corridor Goals and Objectives Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty

More information

COMMONWEALTH OF KENTUCKY BEFORE THE KENTUCKY STATE BOARD ON ELECTRIC GENERATION AND TRANSMISSION SITING

COMMONWEALTH OF KENTUCKY BEFORE THE KENTUCKY STATE BOARD ON ELECTRIC GENERATION AND TRANSMISSION SITING COMMONWEALTH OF KENTUCKY BEFORE THE KENTUCKY STATE BOARD ON ELECTRIC GENERATION AND TRANSMISSION SITING In the Matter of the Application of The ) Cincinnati Gas & Electric Company for a ) Construction

More information

Roseman Technology Site *Caroline County, Virginia 110 Acres Seconds off Interstate 95

Roseman Technology Site *Caroline County, Virginia 110 Acres Seconds off Interstate 95 Roseman Technology Site *Caroline County, Virginia 110 Acres Seconds off Interstate 95 Water Service Provider: Caroline Location: I - 95 Route 639, Ladysmith Exit 110 County Suitable for Construction:110

More information

TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015

TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015 TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015 ARTICLE 8: The Town voted by 2/3 vote to amend its Zoning Bylaws by deleting the current Section 6.14 Wireless Communications Facilities

More information

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project

FINAL. Alternative Evaluation. for the. Proposed Burlington-Wray 230-kilovolt Transmission Project FINAL Alternative Evaluation for the Proposed Burlington-Wray 230-kilovolt Transmission Project Prepared by Tri-State Generation and Transmission Association, Inc. 1100 W. 116th Avenue Westminster, Colorado

More information

Adopted 9/23/98 CHATTAHOOCHEE CORRIDOR PLAN. The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are:

Adopted 9/23/98 CHATTAHOOCHEE CORRIDOR PLAN. The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are: CHATTAHOOCHEE CORRIDOR PLAN Adopted 9/23/98 PART 1: GOALS. POLICY. COVERAGE. A. Goals The goals of the Chattahoochee Corridor Plan (hereinafter also referred to as the Plan ) are: 1. Preservation and protection

More information

Notice to Proceed (NTP) Request #13 to Construct the Section 4 138 kilovolt (kv) Overhead Transmission Line

Notice to Proceed (NTP) Request #13 to Construct the Section 4 138 kilovolt (kv) Overhead Transmission Line Don Houston Environmental Project Manager 1010 Tavern Road Alpine, CA 91901 (T) XXX-XXX-XXXX (F) XXX-XXX-XXXX November 25, 2012 Ms. Lisa Orsaba Project Manager California Public Utilities Commission 505

More information

Gold Ray Dam Interagency Technical Team Meeting

Gold Ray Dam Interagency Technical Team Meeting Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,

More information

Minnesota Public Utilities Commission Staff Briefing Papers

Minnesota Public Utilities Commission Staff Briefing Papers Minnesota Public Utilities Commission Staff Briefing Papers Meeting Date: April 17, 2014...Agenda Item *3 Company: Docket No. Minnesota Power E015/GP-13-978 In the Matter of the Application of Minnesota

More information

COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT

COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT [Cite as Debt Recovery Solutions of Ohio, Inc. v. Lash, 2009-Ohio-6205.] COURT OF APPEALS ASHLAND COUNTY, OHIO FIFTH APPELLATE DISTRICT DEBT RECOVERY SOLUTIONS OF OHIO, INC. -vs- Plaintiff-Appellee JEFFREY

More information

PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA. LCB File No. R107-00. October 10, 2000

PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA. LCB File No. R107-00. October 10, 2000 PROPOSED REGULATION OF THE PUBLIC UTILITIES COMMISSION OF NEVADA LCB File No. R107-00 October 10, 2000 EXPLANATION Matter in italics is new; matter in brackets [omitted material] is material to be omitted.

More information

8. The City received a $100,000 grant from the Monterey Peninsula Water Management District to conduct initial planning and engineering analyses.

8. The City received a $100,000 grant from the Monterey Peninsula Water Management District to conduct initial planning and engineering analyses. RESOLUTION NO. 14-071 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PACIFIC GROVE CERTIFYING THE FINAL ENVIRONMENTAL IMPACT REPORT (FEIR), ADOPTING THE MITIGATION MONITORING AND REPORTING PLAN, AND APPROVING

More information

Control Number : 38597. Item Number: 373. Addendum StartPage: 0

Control Number : 38597. Item Number: 373. Addendum StartPage: 0 Control Number : 38597 Item Number: 373 Addendum StartPage: 0 { C31 ^ IOF DENTUN 215 E. McKINNEY DENTON, TX 76201 (940) 349-8230 FAX (940) 349-8120 UTILITY ADMINISTRATION September 21, 2010 Public Utility

More information

4-1 Architectural Design Control 4-1 ARCHITECTURAL DESIGN CONTROL 1

4-1 Architectural Design Control 4-1 ARCHITECTURAL DESIGN CONTROL 1 4-1 Architectural Design Control 4-1 CHAPTER 4 ARCHITECTURAL DESIGN CONTROL 1 4-1 Purposes of Chapter 4-2 Designations of Architectural Control Districts 4-3 Board of Architectural Review -- Established;

More information

Section 401 Water Quality Certification

Section 401 Water Quality Certification Section 401 Water Quality Certification Department of Health Environmental Management Division Clean Water Branch Voice: (808) 586-4309 Fax: (808) 586-4352 http://www.hawaii.gov/health/environmental/water/cleanwater/index.html

More information

PUBLIC NOTICE Application for Permit

PUBLIC NOTICE Application for Permit PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested

More information

Decision Memo. Restore Act Land Acquisition

Decision Memo. Restore Act Land Acquisition Decision Memo Restore Act Land Acquisition USDA Forest Service National Forests in Mississippi Background A broad coalition of federal. state, and municipal government agencies and private conservation

More information

SECTION 404 OF THE CLEAN WATER ACT

SECTION 404 OF THE CLEAN WATER ACT SECTION 404 OF THE CLEAN WATER ACT A. The Secretary may issue permits, after notice and opportunity for public hearings for the discharge of dredged or fill material into the navigable waters at specified

More information

HARDWICK TOWNSHIP WARREN COUNTY, NEW JERSEY

HARDWICK TOWNSHIP WARREN COUNTY, NEW JERSEY HARDWICK TOWNSHIP WARREN COUNTY, NEW JERSEY AN ORDINANCE TO AMEND CHAPTER XIII OF THE REVISED GENERAL ORDINANCES BEING THE LAND DEVELOPMENT ORDINANCE OF THE TOWNSHIP OF HARDWICK TOWNSHIP IN ORDER TO ADOPT

More information

Appendix E: Stewardship Program

Appendix E: Stewardship Program E Appendix E: Stewardship Program This section of the Open Space Plan establishes the basis and provides recommendations for a Stewardship Program for the Wake County Open Space Program. As Wake County

More information

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for:

REFERENCE. All National Grid personnel who plan and perform work involving protected water resources are responsible for: EG-30NY ENVIRONMENTAL GUIDANCE PAGE 1 of 9 DATE 10/1/10 EP 3 Natural Resource Protection 1.0 SCOPE AND RESPONSIBILITIES National Grid s New York service territory encompasses thousands of wetlands, lakes,

More information

ELECTRIC TRANSMISSION LINE CONSTRUCTION STANDARDS AND POLICIES

ELECTRIC TRANSMISSION LINE CONSTRUCTION STANDARDS AND POLICIES ELECTRIC TRANSMISSION LINE CONSTRUCTION STANDARDS AND POLICIES Recommended by the Illinois Department of Agriculture The following electric line construction standards and policies are recommended by the

More information

Chase Tower, Eighth Floor. P.O. Box 1588. July 7,2006

Chase Tower, Eighth Floor. P.O. Box 1588. July 7,2006 STEPTOE & JOHNSON ATTORNEYS AT LAW Chase Tower, Eighth Floor Writer's Contact Information P.O. Box 1588 Charleston, WV 25326-1588 (304) 353-8000 (304) 353-8180 Fax (304) 353-8113 www.steptoe-johnson.com

More information

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at

More information

CHECKLIST FOR TELECOMMUNICATION TOWER CO-LOCATION APPLICATIONS. Conditional Use Permit Approved by Board of Supervisors Date of approval:

CHECKLIST FOR TELECOMMUNICATION TOWER CO-LOCATION APPLICATIONS. Conditional Use Permit Approved by Board of Supervisors Date of approval: CHECKLIST FOR TELECOMMUNICATION TOWER CO-LOCATION APPLICATIONS Conditional Use Permit Approved by Board of Supervisors Date of approval: Site Plan Approval: Date of approval: Fees: $4,000 Licensed Co-location

More information

CERTIFIED RANGELAND MANAGEMENT LICENSING ISSUES

CERTIFIED RANGELAND MANAGEMENT LICENSING ISSUES State of California Memorandum To : Eric K. Huff, RPF Executive Officer - Foresters Licensing Program Board of Forestry and Fire Protection Sacramento Department of Justice 1515 Clay Street, 20 th Floor

More information

Electric system improvements near you South and West of Edmonton Area Transmission Development

Electric system improvements near you South and West of Edmonton Area Transmission Development Electric system improvements near you South and West of Edmonton Area Transmission Development SAUNDERS LAKE SUBSTATION AND TRANSMISSION LINES January 2014 Volume 2 PLEASE NOTE: We want to inform you that

More information

Comanche Trail Pipeline Project. September 2015

Comanche Trail Pipeline Project. September 2015 Comanche Trail Pipeline Project September 2015 2 Comanche Trail Pipeline Project The Comanche Trail Pipeline is a Texas intrastate pipeline (1) designed to transport 1.1 billion cubic feet per day of clean-burning

More information

MEMORANDUM. Managers, Administrators, Clerks, Attorneys, and Planners

MEMORANDUM. Managers, Administrators, Clerks, Attorneys, and Planners MEMORANDUM To: From: Managers, Administrators, Clerks, Attorneys, and Planners Kimberly S. Hibbard, General Counsel Date: September 15, 2013 Re: City Authority to Regulate Wireless Telecommunications HB

More information

House Research Department General Fund Appropriations in Flood Relief Bills

House Research Department General Fund Appropriations in Flood Relief Bills House Research Department General Fund Appropriations in Flood Relief Bills These tables included state funding from the major disaster bills enacted to respond to a disaster. Appropriations may have been

More information

COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1

COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1 COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES April 20, 2010 EXHIBIT 1 ELEMENT 4 WATER RESOURCES TABLE OF CONTENTS 4.1 INTRODUCTION 4.2 GOALS AND POLICIES 4.2.A General Goals and Policies 1 4.2.B

More information

Evaluation of Underground Electric Transmission Lines in Virginia

Evaluation of Underground Electric Transmission Lines in Virginia Report of the Joint Legislative Audit and Review Commission To the Governor and The General Assembly of Virginia Evaluation of Underground Electric Transmission Lines in Virginia HOUSE DOCUMENT NO. 87

More information

Section 6: Mitigation Strategy

Section 6: Mitigation Strategy Section 6: Mitigation Strategy The Mitigation Strategy section provides the blueprint for the participating jurisdictions in the Unifour Region to follow to become less vulnerable to the negative effects

More information

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) ) )

STATE OF VERMONT PUBLIC SERVICE BOARD ) ) ) ) ) STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. 7212 Petition of H.W. Ventures, L.C., for a certificate of public good, pursuant to 30 V.S.A. 248(j, authorizing the installation and operation of a temporary

More information

Natural Resource-Based Planning*

Natural Resource-Based Planning* Natural Resource-Based Planning* Planning, when done well, is among the most powerful tools available to communities. A solid plan, based on good natural resource information, guides rational land-use

More information

Frequently Asked Transmission Pipeline Questions

Frequently Asked Transmission Pipeline Questions Frequently Asked Transmission Pipeline Questions Who is PennEast, LLC? PennEast was formed by the partnership of AGL Resources, NJR Pipeline Company, South Jersey Industries and UGI Energy Services (UGIES).

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN 1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

2016 Virginia Resource Management Plan Development Request for Applications ( RFA )

2016 Virginia Resource Management Plan Development Request for Applications ( RFA ) 2016 Virginia Resource Management Plan Development Request for Applications ( RFA ) Sources of Funding: Federal EPA Chesapeake Bay Regulatory and Accountability Program Virginia General Fund Appropriation

More information

ON-SITE WASTEWATER TREATMENT SYSTEMS ACT

ON-SITE WASTEWATER TREATMENT SYSTEMS ACT ON-SITE WASTEWATER TREATMENT SYSTEMS ACT Revised and reproduced by the Colorado Department of Public Health and Environment June, 2012 (PLEASE NOTE: This is an unofficial copy of this statute. The official

More information

LIVING LANDS Helping Land Trusts Conserve Biodiversity

LIVING LANDS Helping Land Trusts Conserve Biodiversity LIVING LANDS Helping Land Trusts Conserve Biodiversity Land Trust Biodiversity Survey, Winter 2006 Purpose of Survey To better understand local land trusts current activities and interest in biodiversity

More information

v. Record No. 112070 OPINION BY JUSTICE DONALD W. LEMONS September 14, 2012 ADEL S. KEBAISH, M.D.

v. Record No. 112070 OPINION BY JUSTICE DONALD W. LEMONS September 14, 2012 ADEL S. KEBAISH, M.D. Present: All the Justices INOVA HEALTH CARE SERVICES, d/b/a INOVA FAIRFAX HOSPITAL, ET AL. v. Record No. 112070 OPINION BY JUSTICE DONALD W. LEMONS September 14, 2012 ADEL S. KEBAISH, M.D. FROM THE CIRCUIT

More information

RIGHT OF ENTRY RECITALS. A. WHEREAS, CITY owns and operates the Norman Y. Mineta San Jose International Airport ( Airport ); and

RIGHT OF ENTRY RECITALS. A. WHEREAS, CITY owns and operates the Norman Y. Mineta San Jose International Airport ( Airport ); and RIGHT OF ENTRY This Right of Entry Agreement ( AGREEMENT ) is made this day of, 2015, by and between NAME, [an individual/ a corporation/ a limited liability company/ a partnership] ( ENTRANT ) and the

More information

Virginia Department of Transportation Rural Rustic Road Program Manual

Virginia Department of Transportation Rural Rustic Road Program Manual Virginia Department of Transportation Rural Rustic Road Program Manual Prepared by Local Assistance Division Virginia Department of Transportation 1401 East Broad Street Richmond, Virginia 23219 Jennifer

More information

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA PLAINTIFF S BRIEF IN SUPPORT OF MOTION FOR SUMMARY JUDGMENT

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA PLAINTIFF S BRIEF IN SUPPORT OF MOTION FOR SUMMARY JUDGMENT IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA RICHMOND DIVISION MICHAEL GLENN WHITE, et. al. Plaintiffs v. VIRGINIA BOARD OF EDUCATION; et. al., Defendants. Case No. 3:00CV386

More information

CHAPTER 260. AN ACT concerning employee leasing companies. BE IT ENACTED by the Senate and General Assembly of the State of New Jersey:

CHAPTER 260. AN ACT concerning employee leasing companies. BE IT ENACTED by the Senate and General Assembly of the State of New Jersey: CHAPTER 260 AN ACT concerning employee leasing companies. BE IT ENACTED by the Senate and General Assembly of the State of New Jersey: C.34:8-67 Definitions relative to employee leasing companies. 1. For

More information

CITY COUNCIL CITY OF PALMDALE, CALIFORNIA RESOLUTION NO. CC 2011-006

CITY COUNCIL CITY OF PALMDALE, CALIFORNIA RESOLUTION NO. CC 2011-006 CITY COUNCIL CITY OF PALMDALE, CALIFORNIA RESOLUTION NO. CC 2011-006 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PALMDALE APPROVING THE AGREEMENT TO RESOLVE SPECIAL TAX/ASSESSMENT LIENS AND UNPAID

More information