HOW TO ESTIMATE THE COST OF T-BAR

Size: px
Start display at page:

Download "HOW TO ESTIMATE THE COST OF T-BAR"

Transcription

1 HOW TO ESTIMATE THE COST OF T-BAR ACOUSTICAL CEILINGS MICHAEL HILL DATE WRITTEN: MAY OF 2007 The author is Michael Hill, Estimator with Kaiser Foundation Hospitals, National Facilities Services Cost Engineering Group. Michael has been a member of ASPE since Michael has more than twenty-five years experience in the construction and remodeling of hospitals and office buildings. Experienced in all phases of construction including design, computer aided drafting (CAD), space design, estimating, scheduling, presentations, project management, supervision and project inspections. Michael has worked in the construction business with his father, a general contractor, and then for Kaiser Foundation Hospitals as a journeyman carpenter in Since then he has been in engineering, worked as a CAD (computer aided drafting) designer, designed databases for work order and equipment tracking, a project superintendent, a project manager, a space designer and an estimator. The Cost Engineering Group Michael works with oversees the maintenance and renovation estimating for eleven of the Kaiser Permanente Medical Centers. TABLE OF CONTENTS INTRODUCTION Main CSI Division Specific Subdivision/ Specification Section Brief Description TYPES AND METHODS OF MEASUREMENT Material take-off review FACTORS THAT AFFECT TAKE-OFF, PRICING, ETC Small versus large quantities Geographic location OVERVIEW OF LABOR, EQUIPMENT, MATERIAL, AND INDIRECT COSTS Sample of production rates SPECIAL RISK CONSIDERATION RATIOS AND ANALYSIS TOOLS TO TEST FINAL BID MISCELLANEOUS PERTINENT INFORMATION Sample ceiling specifications CONCLUSION DETAIL SHEETS Sample sketch Sample take-off sheet Sample pricing INTRODUCTION This paper will address the materials and methods used in cost estimating for acoustical suspension ceilings with acoustic ceiling tiles (commonly called T-bar because of the T shaped supports). The T-bar acoustical ceiling system is an extremely versatile product. Buildings that commonly use T-bar acoustical ceilings are commercial buildings, hospital buildings, schools, and residential modular homes. T-bar acoustical ceiling systems can be installed in all types of structures made from wood, metal, steel and concrete. Main CSI Division Division Nine, (9) Finishes Subdivision Specification Section Metal Support Assemblies Acoustical Suspension Specification Section Ceilings Acoustical Ceiling Brief Description The T-bar acoustical ceiling system provides the following benefits; sound attenuation, access to utilities above, architectural design enhancement, ease of maintenance, ease of replacement of tiles, suspension of lighting and room utilities. The T-bar grid system consists of main runners, cross runners, wall angles, support wires and struts. There are many methods used to install the T-bar grid system, depending on the system and design requirements. For example support wires are dropped through the pan-deck, shot in the ceiling using power actuated fasteners or anchored using drilled expansion anchors (see Details 3 & 5). The sections of anchored wires are then tied to the T-bar (see Detail 2). Additional grid wires are also installed to support other trade s ceiling installed items. For example light fixtures and HVAC (heating ventilation & air conditioning) registers which are also laid into the finished grid system. Acoustic tiles are then placed into the grid along with the other trades items to finish the ceiling work. Many tiles will need to be cut to provide openings needed for fire alarm, fire sprinklers, special lighting cans and security components. The support elements of these components are usually provided by the other trades and are not figured in the estimate. Acoustic tile sizes and material vary greatly depending on usage. Sizes include: 24 x 24 panels and 48 x 24 panels. There are fire rated tiles, fiberglass, plastic coated, aluminum and material fiber tiles in many styles and colors. There are also tin tiles with hundreds of patterns and colors. T-bar grid also comes in a variety of materials and colors. This paper will only review the heavy-duty T-bar acoustical ceiling system. Materials required to build a T-bar ceiling include: 1) Hanging wires Estimating Today 17 PDF processed with CutePDF evaluation edition

2 2) Seismic posts 3) Wall angle 4) Main runners 5) Cross runners 6) Acoustic drop in panels TYPES AND METHODS OF MEASUREMENT Methods used to create a material take-off used by T-bar acoustical ceiling estimators, are accomplished by using the following units of measurement: square feet, item count and linear feet. Direction of tiles needs to be reviewed. The layout of fire sprinklers, HVAC registers, lighting and fire alarm work all needs to be reviewed. Often the T-bar ceiling subcontractor is asked to supply and install hanger wires for the other trades. Information needed to estimate quantity of support wire counts, needs to include HVAC registers and light fixtures. Material take-off review The material take-off is done by first measuring the room for width and length. Material can be figured using a spreadsheet with calculations added (see Sample Material Take-off). AREA Area is calculated width of room multiplied by the length of room. PANEL Panel count is calculated Divide area by eight square feet for 2 X4 ceiling panels (subtract light and HVAC register square footage). MR Main runners are calculated in linear feet Area divided by four. CR 4 Four foot cross runners are calculated Main runners multiplied by two. CR 2 Two foot cross runners are calculated 2 x2 lights and HVAC registers multiplied by two. WA Wall angle length is calculated Width of room plus length of room multiplied by two. Note: The wall angle length may vary depending on the amount of cuts in a room, so a linear foot take-off may be required here. 2 STRUT Two foot strut calculation Width of room divided by two. 4 STRUT Four foot strut calculation Width of room divided by two. V WIRE V wire (vertical) is calculated - Main runner total length divided by four. P WIRE P wire (perimeter) is calculated Width of room divided by two plus length of room divided by four multiplied by two. Example: (W/2+L/4)x2. S POST S WIRE S LIGHTS 2X4 LIGHTS 2X2 HVAC S Posts (seismic) are calculated Area divided by 96. wire (seismic) is calculated Total S posts multiplied by five. Lights are counted from the reflected ceiling plan and multiplied by eight square feet. Lights are counted from the reflected ceiling plan and multiplied by four square feet. HVAC (heating ventilation & air conditioning) registers are counted from the reflected ceiling plan and multiplied by four square feet usually. There are many styles of registers, including 4 slot registers, that will needed to be reviewed so your take-off reflects the required wires and runners. Additional materials that need to be figured for the estimate includes the wall angle fasteners, pop and grid fasteners. These items are calculated on the Pricing sheet along with labor, taxes and mark-up. Wall angle fasteners are calculated One for each wall angle. Pop and grid fasteners are calculated Wall angles divided by five. FACTORS THAT MAY AFFECT TAKE-OFF, PRICING, ETC. Small versus large quantities of material can affect the overall productivity on projects. Factors that may affect productivity include manpower, material, jobsite stocking and equipment. Shop drawings, engineering and sub consultants may be required on larger projects. Large projects can increase installation efficiency by assigning labor to specific tasks and for use of full days to complete tasks. Material can be stock piled on larger projects where there is room to do so. If man lift equipment is required, larger projects may increase installation productivity. Some buildings have continuous T-bar grid systems with walls that abut the ceiling. These walls will not have edge support angles except at firewalls or exterior walls, where the wall runs above the ceiling. On small projects the material quantity minimum purchase may exceed the actual quantity needed for installation. Smaller rooms use more wall angles per square foot. The estimator may need to include a full days pay for a partial days work. Geographic location does affect the labor and material costs of any project. This needs to be reviewed prior to finalizing the estimate. Geographic location is affected mostly on small projects. Travel time may also need to be included due to distance between small projects. Local labor availability, skill levels & cost per hour are also factored into costs. Material and Labor rates are always factored into the estimate and should reflect local costs. Uniform Building Code and state building code standards are to be reviewed, as some states may have other requirements. Commonly, the grid system is installed in an enclosed envelope of the building so weather is not a large consideration. However, support wires are typically installed in a new building after structural steel and pan deck are in place. In cold or windy weather this could affect the installation efficiency. OVERVIEW OF LABOR, EQUIPMENT, MATERIAL AND INDIRECT COSTS The T-bar acoustical ceiling systems are available in many styles many, which require special installation procedures and 18 Estimating Today

3 production costs. This paper will only review the heavy-duty T- bar acoustical ceiling system. A review of the construction documents will reveal conditions that will determine the production costs, type of material, equipment and any indirect costs. A hospital will require additional labor due to the need for drilled inserts for the seismic wires. Also, a hospital demands additional wire supports due to the additional HVAC ducts in the plenum above. For standard commercial applications, powder-actuated fasteners are used. Sample of production rates The information below is used in the example-pricing sheet (see page 26) One man can install about 300 wires a day, using a power actuated fastener or drill. One man can install about 60 wires a day using drilled in expansion anchors. Wires will be about 25% of the overall area. (100 square feet has approximately 25 wires). Grid installation rate is about 600 square feet per day, per man. One man can install approximately 800 square feet of drop in tile per day. One man can install approximately 25 seismic posts per day. One seismic post is required every 96 square feet of area. Wall angle installation is approximately 300 linear feet per day. Wall angle is approximately 25% of the area. (1,000 square feet has approximately 250 linear feet of wall angle). Journeyman Carpenter cost in the San Francisco Bay Area including burden is, approximately $ per day *. installations and ceiling panel installations, which means labor will need to be on hand and ready when other trades are complete (labor will have to come back twice to complete the ceiling work). Going on a job walk of the site to review conditions can eliminate many risks. RATIOS AND ANALYSIS TOOLS TO TEST FINAL BID Reviews of past projects of a similar type can be gathered. Historical data is used for ratios and reviews. This is particularity useful when figuring for man-hours and material. Projects may vary greatly depending on scope. Maintaining historical data from previous projects and post construction evaluations will support new estimates with true baseline information. Many percentages will hold true and assist in the analysis of the estimate. Post construction evaluations are preformed after your project is completed. This evaluation is a useful tool in looking into costs incurred, processes, products, services and review of any errors or changes from your final estimate. This process allows you to learn the best practices to estimate future projects. You will need to evaluate your final estimate versus actual costs, general requirements, direct costs, schedule impacts and change orders that affected the ceiling work. In a post construction evaluation you can review your production rates and update them as needed. Many computer programs can utilize this historical data to graph a project, creating a visual representation. The following Figures No. 1 and No. 2 show the sample pricing sheet (see page 26) percentages in two different formats. The sample displays the ratios of tasks needed to complete the estimate. SPECIAL RISK CONSIDERATION Risk considerations include: Schedule of work. Phasing of the project. Relationships with bidding general contractors and access to project location. Types of ceiling installations. Deck structure & material. Wall type. Anchor type. Grid type. Ceiling tile style. All the items above factor into the final costs and must be reviewed prior to completing the estimate. Complex ceiling designs will also need to be reflected in the estimate such as, curves, soffits, special curtain and lighting. Other trade commodities and their schedule can affect the estimate, including light fixture wires and installation of HVAC register wires. When reviewing the contract documents the reflective ceiling plan is the main drawing for review, it is also prudent to review the plumbing, HVAC and electrical drawings prior to completion of your take-off. A review of the ceiling specifications of a project is also required as they may explain items not shown on the plans (see Sample Specification). Schedules may indicate large periods between support wire Figure No. 1 Figure No. 2 Estimating Today 19

4 MISCELLANEOUS PERTINENT INFORMATION This paper is a review of how to estimate a T-bar acoustical ceiling system. The larger ceiling contractors utilize take-off digitizers and estimating programs. On Screen is the take off program of choice and Quick Bid is an estimating program that is very popular. The choice of which program or take-off method used depends on your company and specific type of work. Your company and labor resources will determine which method works best to meet the project needs. SAMPLE CEILING SPECIFICATIONS Ceiling Notes For Metal Suspension System For Lay In Panel Ceilings: Provide metal suspension system for lay in panel ceilings as follows: General: Requirements for design and installation of suspended acoustical ceiling systems are contained in the Uniform Building Code, and in the building code standards of the local state that work is being completed. 1.0 Ceiling Notes: The following notes are examples of specifications for ceiling systems whose total weight, including air conditioning grills and light fixtures, does not exceed four pounds per square foot. Heavier systems and those supporting lateral loads from partitions will require special design details gauge (minimum) hanger wires may be used for up to and including 4-0 x 4-0 grid and shall be attached to main runners (see Detail 2). 1.2 Provide 12 gauge hanger wires at the ends of all main and cross runners within eight inches (8 ) of the support or within one-fourth (1/4) of the length of the end tee, whichever is least, for the perimeter of the ceiling area. In some cases end connections for runners, which are designed and detailed to resist the applied vertical and horizontal forces may be used in lieu of the 12 gauge hanger wires, subject to review and approval. 1.3 Provide trapeze or other supplementary support members at obstructions to typical hanger spacing. Provide additional hangers, struts, or braces as required at all ceiling breaks, soffits or discontinuous areas. Hanger wires that are more than 1 in 6 out of plumb are to have counter-sloping wires. Obstructions such as large ductwork will require extra wires and will need to be added to the take-off. 1.4 Ceiling grid members may be attached to not more than 2 adjacent walls run diagonally to ceiling grid members shall be at least 1/2 inch free of other walls. If walls run diagonally to ceiling grid system runners, one end of main and cross runners should be free, and a minimum of 1/2 inch clear of wall (see Detail 2). 1.5 At the perimeter of the ceiling area where main or cross runners are not connected to the adjacent wall. Provide interconnection between the runners at the free end to prevent lateral spreading. A metal strut or a 16-gauge wire with a positive mechanical connection to the runner may be used (see Detail 1). Where the perpendicular distance from the wall to the first parallel runner is 12 or less, this interlock is not required. 1.6 Provide bracing assemblies consisting of a compression strut and four (4) 12 gauge splayed bracing wires oriented 90 degrees from each other at the following spacing (see Detail 1). 1. Place bracing assemblies at a spacing not more than 8 feet 12 feet on center. 2. Provide bracing assemblies at locations not more than one-half (1/2) the spacing given in 1 (1.6) 1 above from each perimeter wall and at the edge of vertical ceiling offsets. The slope of these wires shall not exceed 45 degrees from the plane of the ceiling and shall be taut. Splices in bracing wires are not to be permitted without special approval. 4. Suspended acoustical ceiling systems with a ceiling area of 144 square feet or less, and fire rated suspended acoustical ceiling systems with a ceiling area of 96 square feet or less, surrounded by walls which connect directly to the structure above, do not require bracing assemblies when attached to two adjacent walls. 1.7 Fasten hanger wires with not less than three (3) tight turns (see Detail 5). Fasten bracing wires with four (4) tight turns (see Detail 3). Make all tight turns within a distance of 1-1/2 inches. Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the wire aligns as closely as possible with the direction of the forces acting on the wire (see Details 3 & 5). Note: Wire turns made by machine where both strands have been deformed or bent in wrapping can waive the 1-1/2 requirement, but the number of turns should be maintained, and as tight as possible. 1.8 Separate all ceiling hanging and bracing wires at least six inches (6 ) from all un-braced ducts, pipes, conduits, etc. It is acceptable to attach lightweight items, such as single electrical conduit, not exceeding 3/4 nominal diameter, to hanger wires. 1.9 When drill-in concrete anchors or shot-in anchors are used in reinforced concrete for hanger wires, 1 out of 10 must be field tested for 200 pounds of tension, when drilled-in anchors are used for bracing wires, 1 out of 2 must be field tested to 440 pounds in tension. Shot-in anchors are not permitted for bracing wires. If any shotin or drilled-in anchors fail, a review of local building codes will be required. Note: Drilled-in or shot-in anchors will require special approval when used in pre-stressed concrete Attach all light fixtures and ceiling mounted air 20 Estimating Today

5 terminals or service, to the ceiling grid runners to resist a horizontal force equal to the weight of the fixtures. Screws or approved fastener are required Flush or recessed light fixtures and air terminals or services weighing 56 pounds or more must be supported directly on the runners of a heavy duty grid system but, in addition, they must have a minimum of two 12 gauge slack safety wires attached to the fixture at diagonal corners and anchored to the structure above. All flush or recessed light fixtures and air terminals or services weighing 56 pounds or more must be independently supported by not less than four (4) taut 12 gauge wires each attached to the fixture and anchored to the structure above regardless of the type of ceiling grid system used. The four (4) taut 12 gauge wires including their attachment to the structure above must be capable of supporting four (4) times the weight of the unit. SUSPENDED CEILING BRACING ASSEMBLY DETAIL Support surface mounted light fixtures by at least two positive devices which surround the ceiling runner and which are each supported from the structure above by a 12-gauge wire. Spring clips or clamps that connect only to the runner are not acceptable. Provide additional supports when light fixtures are 8 feet or longer Support pendant mounted light fixtures directly from the structure above with hanger wires or cables passing through each pendant hanger and capable of supporting four (4) times the weight of the fixture. A bracing assembly is required where the pendant hanger penetrates the ceiling. Special details are required to attach the pendant hanger to the bracing assembly to transmit horizontal forces Classification of ceiling grid (Manufacturer) - Classification of ceiling grid is heavy duty for this paper. - Manufacturer s catalog number - main runner - heavy duty. - Manufacturer s catalog number - cross runner - heavy duty. - Manufacturer s catalog number of detail for runner splice (see Detail 6). CONCLUSION In summary, this paper explains how to estimate the cost of T- bar acoustical ceilings. There are many factors that affect your take-off. For example, the project size, geographic locations and special risk considerations. In addition, a review of labor, equipment, material, and indirect costs are needed to complete the T-bar acoustical ceiling estimate. The types and methods of measurement used for take-offs are item count, square footage and linear footage. Lastly, an estimator should incorporate historical ratios and analysis tools to test final bid. HANGER WIRE CONNECTION TO GRID DETAIL 2 Estimating Today 21

6 SIESMIC (SPLAY) WIRE ATTACHMENT DETAIL 3 RUNNER SPLICE DETAIL 6 HANGER WIRE SPLICE DETAIL 4 VERTICAL WIRE ATTACHMENT DETAIL 5 22 Estimating Today SAMPLE SKETCH

7 SAMPLE TAKE-OFF AND PRICING SHEETS (See material take-off review for details) ** Carpenter Northern California trade union agreement with AGC dated January Estimating Today 23

CEILING SYSTEMS. Between us, ideas become reality. Installing. Suspended Ceilings. North America Version

CEILING SYSTEMS. Between us, ideas become reality. Installing. Suspended Ceilings. North America Version CEILING SYSTEMS Between us, ideas become reality Installing Suspended Ceilings North America Version 1 Installing Armstrong Suspended Ceilings An Armstrong suspended mineral fiber ceiling is functional,

More information

Standard Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions 1

Standard Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions 1 Designation: E 580/E 580M 09a Standard Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions 1 This standard is issued

More information

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table

More information

Clark County Fire Prevention

Clark County Fire Prevention Clark County Fire Prevention Mission Statement: To provide the highest level of fire protection and related services TITLE: REQUIREMENTS FOR A NEW SPRINKLER SYSTEM IN ACCORDANCE WITH THE 2002 EDITION OF

More information

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013

How to Estimate the Cost of Support of Excavation for Foundation Installation. CPE Candidate No. 0113013. May 15, 2013 How to Estimate the Cost of Support of Excavation for Foundation Installation CPE Candidate No. 0113013 May 15, 2013 1 How to Estimate the Cost of Support of Excavation for Foundation Installation Table

More information

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS

DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS DESIGN AND INSTALLATION OF RESIDENTIAL FLEXIBLE DUCTWORK SYSTEMS A. SCOPE 1. This information is intended to assist contractors, installers and code officials in the proper design and installation of flexible

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

Seismic Technical Guide

Seismic Technical Guide Technical Document Seismic Technical Guide Hanger Wire Attachment Code Requirements 1 The International Building Code (IBC) defines the requirement for hanger wire and their supports and attachment methods.

More information

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES

HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,

More information

UL 580 TEST REPORT. Rendered to: ARMSTRONG WORLD INDUSTRIES. SERIES/MODEL: MW Vector PRODUCT TYPE: Ceiling System, 3' OC

UL 580 TEST REPORT. Rendered to: ARMSTRONG WORLD INDUSTRIES. SERIES/MODEL: MW Vector PRODUCT TYPE: Ceiling System, 3' OC UL 580 TEST REPORT Rendered to: ARMSTRONG WORLD INDUSTRIES SERIES/MODEL: MW Vector PRODUCT TYPE: Ceiling System, 3' OC Report No.: Test Dates: 12/14/09 Through: 12/22/09 Report Date: 03/12/10 Expiration

More information

Guidelines for Earthquake Bracing Residential Water Heaters

Guidelines for Earthquake Bracing Residential Water Heaters Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT

SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT SECTION 23 05 29 - HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Pipe hangers and supports. 2. Hanger rods. 3. Inserts. 4. Flashing. 5. Equipment

More information

PART 1 GENERAL 1.1 SECTION INCLUDES

PART 1 GENERAL 1.1 SECTION INCLUDES J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including

More information

How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work. Section 2 Types of Methods of Measurements page 4

How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work. Section 2 Types of Methods of Measurements page 4 How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work Table of Contents Section 1 Introduction page 3 Section 2 Types of Methods of Measurements page 4 Section 3 Project Specific

More information

Tips for Professional Ceiling Installers

Tips for Professional Ceiling Installers Tips for Professional Ceiling Installers Over the years, Armstrong installation instructors and professional installers have solved many ceiling installation problems. Here is a compilation of their solutions...

More information

CEILING SYSTEMS. CI/SfB (35) Xy April 2006. [Between us, ideas become reality.] ULTIMA CANOPY. Data sheet. Acoustic performance meets High Design

CEILING SYSTEMS. CI/SfB (35) Xy April 2006. [Between us, ideas become reality.] ULTIMA CANOPY. Data sheet. Acoustic performance meets High Design CEILING SYSTEMS [Between us, ideas become reality.] CI/SfB (35) Xy April 2006 ULTIMA CANOPY Data sheet Acoustic performance meets High Design ULTIMA CANOPY Installation Instructions I. GENERAL 1. Product

More information

FORM DESIGN. easy to work with, and generally available.

FORM DESIGN. easy to work with, and generally available. Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods

More information

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders

Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids

More information

MRI RF SHIELDING DESIGN

MRI RF SHIELDING DESIGN MRI RF SHIELDING DESIGN Nelco s MRI RF Shielding is specifically designed for the MRI industry. Our engineers have developed a shielded enclosure made entirely of nonmagnetic materials that is unsurpassed

More information

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel

first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders

More information

4 Installation Requirements

4 Installation Requirements 4 Installation Requirements 9 4.1 Code Reference The authority having jurisdiction should be referenced to determine what law, ordinance or code shall apply in the use of flexible duct. Ducts conforming

More information

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION

More information

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS

RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

White Paper. Economic conditions are forcing engineers to re-evaluate IT cabling distribution methods.

White Paper. Economic conditions are forcing engineers to re-evaluate IT cabling distribution methods. White Paper Economic conditions are forcing engineers to re-evaluate IT cabling distribution methods. Current conditions and conventional methods in IT cabling design Both Technology and economics are

More information

ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS

ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and

More information

BUILDING PERMIT SPECIFICATIONS

BUILDING PERMIT SPECIFICATIONS BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide

More information

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the Chapter 7 PLUMBING AND ELECTRICAL 7.1 Introduction to Plumbing and Electrical Consideration of support services such as plumbing and electrical systems from the preliminary schematics phase through final

More information

SECTION 11 78 13 MORTUARY REFRIGERATORS

SECTION 11 78 13 MORTUARY REFRIGERATORS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in

More information

Final inspections are completed by site visit only. Access to fenced yards shall be planned.

Final inspections are completed by site visit only. Access to fenced yards shall be planned. ROOFING RESIDENTIAL BUILDING INSPECTIONS DEPARTMENT www.ci.blaine.mn.us This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building Code, Blaine City ordinances,

More information

How to Estimate the Cost of a. Laboratory Renovation. Candidate Number: 0714144

How to Estimate the Cost of a. Laboratory Renovation. Candidate Number: 0714144 How to Estimate the Cost of a Laboratory Renovation Candidate Number: 0714144 December 15, 2014 1 Table of Contents Cover Page Page 1 Table of Contents Page 2 Introduction Page 3 Types & Methods of Measurements

More information

WHI 90-Minute Rated Veneered Door Frame Installation Instructions

WHI 90-Minute Rated Veneered Door Frame Installation Instructions No. 940-03-10 INSTALLATION INSTRUCTIONS 90 MINUTE RATED VENEERED DOOR FRAME DOOR REQUIREMENTS: Consult the door manufacturer to make sure that the doors are qualified for the hardware to be installed,

More information

Construction Technologies Career Field Pathways and Course Structure

Construction Technologies Career Field Pathways and Course Structure Courses in Structural Systems (DD) Construction Technologies Career Field Pathways and Course Structure PATHWAY COURSES SUBJECT CODE Construction Technology-Core and Sustainable Construction 1 178000 Carpentry

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression

More information

Solar Water Heating and Solar Electric Generators Installed on One or Two Family Dwellings

Solar Water Heating and Solar Electric Generators Installed on One or Two Family Dwellings Solar Water Heating and Solar Electric Generators Installed on Category: Residential Construction Revised: [Paul L. Scarlett], Director Responsible Bureau Section: Development Services Center 1900 SW Fourth

More information

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings

More information

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront

SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS. System 402 Flush-Glazed Screw Spline Storefront PART 1 GENERAL 1.01 Work Included SECTION 08 41 1 ALUMINUM FRAMED ENTRANCES and STOREFRONTS System 402 Flush-Glazed Screw Spline Storefront A. Furnish and install aluminum architectural storefront system

More information

4.3.5 - Breakaway Walls

4.3.5 - Breakaway Walls 4.3.5 - Breakaway Walls Elevation of a structure on a properly designed foundation reduces the potential for water damage from flooding. When the space below the lowest elevated floor is maintained free

More information

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1 ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING January 24, 2014 06610-1 SECTION 06610 FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS MOLDED GRATING PART 1 - GENERAL 1.1 SCOPE OF WORK A. The CONTRACTOR

More information

Roof Curbs, Extensions and Equipment Supports

Roof Curbs, Extensions and Equipment Supports Roof s, Extensions and Equipment Supports December 2012 Roof Page s, Header Extensions and Equipment Supports Table of Contents Model GPI Standard and Optional Construction Features... 3 Model Number Code....

More information

ST. MONICA FOOD PANTRY HOUSTON, TEXAS

ST. MONICA FOOD PANTRY HOUSTON, TEXAS PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,

More information

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT SUBSTATION & EQUIPMENT SECTION SPECIFICATION EO-5023 REVISION 3 MARCH 2003 REQUIREMENTS FOR

More information

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request

SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table

More information

Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4

Cover Page page 1. Table of Contents page 2. Section 1 Introduction page 3. Section 2 Variable Air Volume System Components page 4 How to Estimate the Cost of a VAV Reheat HVAC System Table of Contents: Cover Page page 1 Table of Contents page 2 Section 1 Introduction page 3 Section 2 Variable Air Volume System Components page 4 Section

More information

APPENDIX K. Design/Layout Considerations for Ceiling/Overhead Lift Tracks. Ceiling Lift Motor Charging Options

APPENDIX K. Design/Layout Considerations for Ceiling/Overhead Lift Tracks. Ceiling Lift Motor Charging Options ArjoHuntleigh APPENDIX K Design/Layout Considerations for Ceiling/Overhead Lift Tracks At present, not all clinical units or areas require 100 percent ceiling lift coverage (Table I-1), but with expansion

More information

Asphalt Shingle Application Requirements

Asphalt Shingle Application Requirements Alberta Allied Roofing Association Asphalt Shingle Application Requirements Section 1 Roof Decks 1.1 General Asphalt Shingles are not permitted to be installed directly over rigid insulation. When Asphalt

More information

CLEAR-DIVISIONS APERTO

CLEAR-DIVISIONS APERTO CLEAR-DIVISIONS Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS moveable glass wall system. The yellow highlighted areas in the

More information

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996

Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 CITY OF SAN JOSE BUILDING DIVISION POLICY Policy on Water Heater Installations Policy No. UPC 510-1-94 Effective: September 1, 1995 Revised: February 10, 1996 All new and replacement water heaters installed

More information

Art Basel Miami Beach Dec 3 6 2015 Booth Design Regulations

Art Basel Miami Beach Dec 3 6 2015 Booth Design Regulations 1 6 1 BOOTH CONSTRUCTION The Art Basel in Miami Beach form an integral part of the contract between the exhibitor and Art Basel U.S. Corp. (see Art Basel in Miami Beach Exhibition Regulations). The following

More information

Ceiling Mounted Folding Attic Ladders Installation Instructions

Ceiling Mounted Folding Attic Ladders Installation Instructions Ceiling Mounted Folding Attic Ladders Installation Instructions WARNING Before you start installing your new Louisville Ceiling Mounted Folding Attic Ladder, you must read and understand the following:

More information

ACOUSTICS. Axiom Canopy Clouds Absorption Data Sabines (average 500, 1k, 2k, 4k Hz) ACOUSTICS TESTING DATA Sound Absorption in Sabines

ACOUSTICS. Axiom Canopy Clouds Absorption Data Sabines (average 500, 1k, 2k, 4k Hz) ACOUSTICS TESTING DATA Sound Absorption in Sabines ACOUSTICS ACOUSTICS TESTING DATA Sound Absorption in Sabines SABINE DEFINITION A Sabine is a measure of the sound absorption provided by a material when installed within an architectural space. The number

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.

Chapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS. Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures

City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures City of Tucson and Pima County Arizona Building Code Appendix Chapter 72 Straw-Bale Structures SECTION 7201 - PURPOSE The purpose of this appendix chapter is to establish minimum prescriptive standards

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall

More information

DE Frame with C Series Sidelight

DE Frame with C Series Sidelight TOOLS REQUIRED Tape measure 6' magnetic level 3' magnetic level Screw gun with clutch adjusted #2 phillips tip #3 phillips tip Screwdriver (used to adjust frame on will using oval slots) Pry Bar Powder

More information

GreenGuard Housewrap Installation Guide

GreenGuard Housewrap Installation Guide 000768PACBPHW_Flashing Bro 5/23/03 2:52 PM Page 1 For the most current product information, go to www.green-guard.com. Pactiv Building Products believes the information and recommendations herein to be

More information

Services Enclosures and Protected Shafts - Maintaining Compartmentation

Services Enclosures and Protected Shafts - Maintaining Compartmentation Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping

More information

CH. 2 LOADS ON BUILDINGS

CH. 2 LOADS ON BUILDINGS CH. 2 LOADS ON BUILDINGS GRAVITY LOADS Dead loads Vertical loads due to weight of building and any permanent equipment Dead loads of structural elements cannot be readily determined b/c weight depends

More information

Suspended ceiling or open plenum?

Suspended ceiling or open plenum? CI/SfB (35) Xy 04/2015 Suspended ceiling or open plenum? Making the right choice. Recent studies illustrate the positive impact of suspended ceilings on life cycle costs, fire safety and the acoustic environment.

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10

VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 VOLUME V GUIDELINES FOR DESIGN CONSULTANT TABLE OF CONTENTS APPENDIX B: MASTER CONSTRUCTION SPECIFICATIONS AND PREPARATION GUIDE, DIVISIONS 0-10 SECTION B1: PREPARATION GUIDE B1.1 INTRODUCTION... B1-1

More information

Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10

Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10 Guideline for Fire Safety Elements of Solar Photovoltaic Systems July 17, 2008 Rev: 1/1/10 This document was developed by the Orange County Fire Chiefs Association, Orange County Fire Marshal Committee.

More information

WOODWORKS Linear. Assembly and Installation Instructions 1. GENERAL

WOODWORKS Linear. Assembly and Installation Instructions 1. GENERAL WOODWORKS Linear Assembly and Installation Instructions 1. GENERAL 1.1 Product Description WoodWorks Linear ceilings consist of unperforated nominal 4-1/2" wide x 8' long or 6" wide by 8' long wood plank

More information

TABLE OF CONTENTS" SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE 7"

TABLE OF CONTENTS SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE 7 2 TABLE OF CONTENTS SECTION 1: What is a Standing Seam Metal Roof PAGE 3 SECTION 2: Common Types of Standing Seam Metal Roofs..PAGE 5 SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

Herringbone Pattern Flooring

Herringbone Pattern Flooring Herringbone Pattern Flooring If it s not marked NOFMA, it s not certified. Handling, Storage, Installation and Tips Herringbone is generally manufactured from 3/4 x 2 ¼ or ¾ x 1-1/2 standard tongue & groove

More information

glass & Glazing Products

glass & Glazing Products glass & Glazing Products WallMaker Create an unlimited variety of bright, beautiful and secure interior environments with the easy-to-install Stylmark WallMaker glass wall system. This versatile system

More information

EcoTouch Insulation with PureFiber Technology

EcoTouch Insulation with PureFiber Technology PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.

More information

PART E SPECIFICATIONS

PART E SPECIFICATIONS PART E SPECIFICATIONS Page 1 of 5 PART E - SPECIFICATIONS GENERAL E1. APPLICABLE SPECIFICATIONS, STANDARD DETAILS AND DRAWINGS E1.1 The City of Winnipeg Works and Operations Division Standard Construction

More information

plenum slot diffusers

plenum slot diffusers light powered Redefine your comfort zone. www.titus-hvac.com dual-function smart logic light powered energy solutions Table of Contents PLENUM SLOT IFFUSERS products Plenum Slot iffusers Products... 4

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)

More information

Chapter 6 ROOF-CEILING SYSTEMS

Chapter 6 ROOF-CEILING SYSTEMS Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;

More information

Detailing of Reinforcment in Concrete Structures

Detailing of Reinforcment in Concrete Structures Chapter 8 Detailing of Reinforcment in Concrete Structures 8.1 Scope Provisions of Sec. 8.1 and 8.2 of Chapter 8 shall apply for detailing of reinforcement in reinforced concrete members, in general. For

More information

Suspended ceiling or open plenum? Making the right choice.

Suspended ceiling or open plenum? Making the right choice. CEILING SYSTEMS Between us, ideas become reality Recent studies illustrate the positive impact of suspended ceilings on life cycle costs, fire safety, and the acoustic environment Suspended ceiling or

More information

Solar Panel Installations

Solar Panel Installations Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.

More information

How To Compare Roofing Material

How To Compare Roofing Material Roofing Material Comparisons Housing Fact Sheets One of the great strengths of our market economy is the number of product choices we are provided with. So when it comes time to replace the roof on your

More information

BOQ SPECIFICATIONS. The Blind system consist of a coated aluminium tube of 38 mm diameter with provision of fabric clamping.

BOQ SPECIFICATIONS. The Blind system consist of a coated aluminium tube of 38 mm diameter with provision of fabric clamping. BOQ SPECIFICATIONS VERTICAL BLINDS Vertical Blinds made of glass fibre fabrics in width 5 (or 4 ). Minimum overlapping of ¾ in fabric. Top aluminium anodized rail of 1.4 mm thickness. 2 inch wide channel

More information

Engineering Specifications

Engineering Specifications PUREFLOW PEX PRODUCTS PART 1 GENERAL 1.1 SUMMARY 1.1.1 This specification covers Branch & Main, Parallel Water Distribution Systems (MANABLOC), Cross-linked Polyethylene tubing and fittings using PEX Press

More information

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

SECTION 02845 GUARDRAILS

SECTION 02845 GUARDRAILS SECTION 02845 GUARDRAILS PART 1 - GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, equipment and incidentals necessary and repair, replace or install all types of guardrails as specified herein

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

PUBLIC RESTROOMS, DESIGN INTENT

PUBLIC RESTROOMS, DESIGN INTENT PUBLIC RESTROOMS, DESIGN INTENT 1.01 STRUCTURAL A. Where feasible, metal stud partitions will be constructed on a 6 high concrete curb. 1.02 MECHANICAL A. Restrooms will have a minimum of 15 air changes

More information

Best Barns USA Assembly Book

Best Barns USA Assembly Book Best Barns USA Assembly Book Revised November 27, 2013 the Easton - R 12'x 20' Manufactured by Reynolds Building Systems, Inc. 205 Arlington Drive Greenville, PA 16125 724-646-3775 This manual is copyrighted.

More information

March 14, 2007. Installation of Bay, Bow and Garden Windows

March 14, 2007. Installation of Bay, Bow and Garden Windows March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed

More information