1 Orange County Convention Center Orlando, Florida June 3-5, 2014 Using SAP PS Earned Value to Manage IT Projects Michael Kim

2 AGENDA What is a typical problem with IT projects? What is Earned Value (EV)? How can EV help IT projects?

3 LEARNING POINTS Steps to get IT projects ready for Earned Value (EV) Steps to set up SAP EV in Project System (PS) How to make the best use of EV for your organization

4 TYPICAL PROBLEM WITH IT PROJECTS Unlike projects that build physical objects such as buildings or houses, it is hard to measure progress on IT projects On IT projects, it is easy to spend money without knowing where it is being spent Money is spent with no meaningful or measurable progress Money & resources are gone and you still have work that is not complete By the time you realize your mistakes, it is TOO LATE You cannot Manage what you cannot Measure

5 WHAT IS EARNED VALUE (EV)? Earned Value Management is a project management technique for measuring project performance and progress in an objective manner. EV is commonly used by government contractors and companies that work on Engineering and Construction projects, such as Power Plants and Aircraft Development NASA, DOD, DOE, Utilities, Aerospace & Defense Contractors and Construction Companies are some of the biggest EV users Using the objectivity EV provides, it can help alleviate the typical IT problem we discussed earlier For more examples and explanations of EV, please refer to

6 Most Reports do not show Progress Most Plan vs. Actual Reports show planned vs. actual only This does not provide enough insight into progress Is the project shown below behind or ahead on schedule and budget? Cum. Budget Cum. Actual Period Cum. Budget Cum. Actual

7 EV adds the third dimension, Progress EV ($54) is greater than Actual Costs ($50), i.e., project earned more than it spent got more bang for the buck EV ($54) is less than Plan ($60) project is behind schedule Cum. Budget EV Cum. Actual Period Remarks Cum. Budget BAC (Budget At Completion) % Complete 15% 30% 45% PC (Percent Complete) Earned Value EV = PC * BAC Cum. Actual

8 How can EV help IT projects? Using EV forces Project Manager to use rigor & discipline Since you cannot manage what you cannot measure, break up IT deliverables in measurable chunks of work For each project, come up with a list of deliverables or tasks in chunks of 80 to 100 hours each For example, if an Enhancement requires 400 hours of work, try to divide it down to four 100 hours per deliverable Use an objective EV method such as Start/Finish (0/100, 20/80, or 50/50) or Milestones to determine progress If possible, try to avoid Percent Complete (Estimates) method - it is hard to make this a consistently objective figure Measure progress every week or two, and identify issues and risks early on, before these turn into disasters EV can be used as an early warning system for IT projects.

9 EV Methods Supported in Standard PS Eight EV methods are supported in Standard SAP PS For IT Projects Milestones & Start/Finish Methods are recommended

10 Steps to set up SAP EV in Project System Shown below are the minimum CONFIGURATION Steps Required Create a Progress Version (a special CO Version) 100 is a Standard Progress Version reserved for EV, so this can be used More than one Progress Version can be used Set Plan Version, EV basis, Early/Late Dates Set up PS Value Categories Labor, Material, ODC, OH, G&A, etc. are recommended The best way to do this is to map CO CE Groups to PS Value Categories Assign Default Methods for WBS, NW Activity, CO/PM Order, etc.

11 Steps to set up SAP EV in Project System Shown below are APPLICATION Steps Required Depending on business requirements, more steps may be required Use CJ20N to perform the following tasks: Plan labor, material, and ODC on WBS or Network Activity Assign EV methods on WBS or Network Activity Perform Progress Update on WBS or NWA each period Use CNE1 to calculate EV After the EV parameters are set up, CNE1 should run to update EV figures in ECC Run EV Reports CNE5 Tabular Report and Period Drilldown Report S_ALR_ Report Painter Report

12 EV Set Up in Project Builder Using a typical PS structure, EV can be set up on the WBS element or NW Activity Level The Start/Finish 20/80 Method is selected

13 EV Set Up in Project Builder The Milestones Method is shown as an example Milestones method chosen for both Plan & Actual Prog. Analysis must be checked with POC completed Multiple Milestones can be set up for WBS/NWA

14 EV Set Up in Project Builder Using a typical PS structure, EV can be set up on the WBS element or NW Activity Level The Estimates Method is shown as an example

15 How to make the best use of EV for your team Resistance from Change Management Perspective Many PM s will view EV as a tax on their time and resources How to Handle the Challenge After Senior Management agrees to implement EV, use a small number of key projects to implement EV to demonstrate the following: EV is a standard solution in SAP it is free and you already have it You already have it. Why not use it to improve project management and objectivity in evaluating performance? Use 3 to 6 pilot projects and savvy Project Analysts to start with After initial training and set up, EV is simple to maintain EV - by definition - will enforce discipline among project personnel Incorporate lessons learned from pilot Come up with company-wide EV requirements and Rollout to strategically important projects

16 SAP PS EV Standard Reports CNE5 shows the basic three key figures in EV: BCWS, BCWP and ACWP or Plan EV, Actual EV and Actual Costs. In CNE5 use Period Drill Down Menu Selection for the Graph

17 SAP PS EV Standard Reports S_ALR_ shows the key EV figures as well as Performance Indicators such as CPI, SPI and EAC This is a Report Painter Report that can be modified without ABAP

18 Steps to get IT projects ready for EV Get Senior Management Buy In - without this you will fail Allocate budget for EV implementation it takes time to set up and maintain Educate Project Managers and PM Analysts on Earned Value Align the Charge Numbers - Cost Objects such as WBS, Network Activity, Internal Order, PM/PP Order, etc. - with the Work or Work Packages for which you want to implement EV Ideally, the charge numbers to work packages should be one to one However, in reality, many organizations using one charge number for multiple work packages and EV can still work if you set it up properly

19 Key Learnings What is Earned Value? Project Management Technique used by many PM s How can it help IT projects? By introducing rigor and discipline, it can be useful as an early warning system for IT projects What will it take for EV to be successful for my organization? Management Leadership, Commitment, and Support Business Readiness Rigor and Discipline Willingness to put in rigor for meaningful and measurable progress

20 FOLLOW US

21 THANK YOU THANK YOU FOR PARTICIPATING Please provide feedback on this session by completing a short survey via the event mobile application. SESSION CODE: 2204 For ongoing education on this area of focus, visit

Basic Concepts of Earned Value Management (EVM)

Basic Concepts of Earned Value Management (EVM) Basic Concepts of Earned Value Management (EVM) This article provides an introduction to the basic concepts of earned value management (EVM), from initial project planning through execution including data

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion

Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Rules on using templates 1) Must reference the template used 2) Use

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Ensuring Contract Compliance through integration of Ariba Contracts and SAP ECC Michael Chavez and Sean Rhoades, Deloitte Consulting LLP

Ensuring Contract Compliance through integration of Ariba Contracts and SAP ECC Michael Chavez and Sean Rhoades, Deloitte Consulting LLP Orange County Convention Center Orlando, Florida June 3-5, 2014 Ensuring Contract Compliance through integration of Ariba Contracts and SAP ECC Michael Chavez and Sean Rhoades, Deloitte Consulting LLP

More information

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government

More information

COINS EVA Earned Value Analysis

COINS EVA Earned Value Analysis COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Monster Energy Energizes Its ERP Testing With Panaya

Monster Energy Energizes Its ERP Testing With Panaya Orange County Convention Center Orlando, Florida June 3-5, 2014 Monster Energy Energizes Its ERP Testing With Panaya Speakers: Tami Fox Monster Energy Avishai Shafir - Panaya Typical Packaged ERP Systems

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH By Nghi M. Nguyen, Ph.D., PE, PMP. * INTRODUCTION The management of engineering projects

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

SAP Workflow Classics Session 803 Martin Maguth, Norikkon Torsten Schnorpfeil, Norikkon

SAP Workflow Classics Session 803 Martin Maguth, Norikkon Torsten Schnorpfeil, Norikkon SAP Workflow Classics Session 803 Martin Maguth, Norikkon Torsten Schnorpfeil, Norikkon AGENDA 1. Introduction 2. Purchase requisition release 3. Parked invoice approval 4. TMS transport release KEY LEARNING

More information

Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck?

Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck? Bid & Proposal Cost: How can Government and Industry work to get Better Bang for your Buck? Breakout Session #: F05 Presented by: Gail Guseman Deloitte Consulting, LLP Date: July 23, 2013 Time: 4:00 pm

More information

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples

PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples PROJECT MANGEMENT PLAN EXAMPLES Prepare Project Support Plans and Documentation - Technical Baseline Development and Control Examples Example 40 5.0 PROJECT MANAGEMENT AND CONTROL The Project Management

More information

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

Earned value theory or earned value management

Earned value theory or earned value management PMI Virtual Library 2010 Francisco-Javier Rodriguez Impact of Revenue Recognition Methods in Project Cost Control Through Earned Value By Francisco-Javier Rodríguez, MBA, PMP Earned value theory or earned

More information

Orange County Convention Center Orlando, Florida June 3-5, 2014. Streamlining LSO Online Course Functionality Rob Becker

Orange County Convention Center Orlando, Florida June 3-5, 2014. Streamlining LSO Online Course Functionality Rob Becker Orange County Convention Center Orlando, Florida June 3-5, 2014 Streamlining LSO Online Course Functionality Rob Becker Who Are We Lockheed Martin Corporation Global defense, security, aerospace, and advanced

More information

SAP BusinessObjects (BI) 4.1 on SAP HANA Piepaolo Vezzosi, SAP Product Strategy. Orange County Convention Center Orlando, Florida June 3-5, 2014

SAP BusinessObjects (BI) 4.1 on SAP HANA Piepaolo Vezzosi, SAP Product Strategy. Orange County Convention Center Orlando, Florida June 3-5, 2014 SAP BusinessObjects (BI) 4.1 on SAP HANA Piepaolo Vezzosi, SAP Product Strategy Orange County Convention Center Orlando, Florida June 3-5, 2014 Learning points SAP HANA scenarios for business intelligence

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

] Joan R. Ward, Excellus BlueCross BlueShield Amy Clark, Excellus BlueCross BlueShield Ina Mutschelknaus, SAP

] Joan R. Ward, Excellus BlueCross BlueShield Amy Clark, Excellus BlueCross BlueShield Ina Mutschelknaus, SAP Orange County Convention Center Orlando, Florida May 15-18, 2011 Information Governance in Insurance: How to Establish your Organization, and How to Grow in Smart Ways ] Joan R. Ward, Excellus BlueCross

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight SUBJECT: FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT NUMBER: 12.PM-006 RESPONSIBILITY: Office of Project Management Oversight REVISION: 54 APPROVED BY: TITLE DRAFT FOR DISCUSSION Head, Office

More information

Human Performance & the Role of Human Resources

Human Performance & the Role of Human Resources DEFENSE LOGISTICS AGENCY AMERICA S COMBAT LOGISTICS SUPPORT AGENCY Human Performance & the Role of Human Resources Ms. Cheryl Steptoe-Simon July 20, 2016 Human Performance Functions Human Performance Components

More information

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget Contract Cash Flow & Performance Analysis PERCEPTION Helping The Shipyard Stay On Budget 1 Shipyards that know their true costs are more likely to be profitable and are in a better position to challenge

More information

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional

Selftestengine..PMI-SP.270 questions PMI-SP. PMI Scheduling Professional Selftestengine..PMI-SP.270 questions Number: PMI-SP Passing Score: 800 Time Limit: 120 min File Version: 5.1 PMI-SP PMI Scheduling Professional This study guides are so comprehensible that anyone can understand

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY

CLARITY PPM TIPS, TRICKS, and TERMINOLOGY CLARITY PPM TIPS, TRICKS, and TERMINOLOGY Clarity PPM Knowledge Sharing Series Helping the Clarity PPM Community Members Benefit from Best Practice TABLE OF CONTENTS 1 OVERVIEW... 3 2 OVERVIEW PAGE...

More information

Six top tips for travel managers to create savings in 2015

Six top tips for travel managers to create savings in 2015 Six top tips for travel managers to create savings in 2015 E-Guide 2 Introduction Savings remain a key focal point for Travel Managers in 2015 and through regular reviews and analysis, using management

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Earned Value Management Guidelines

Earned Value Management Guidelines Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application

More information

Orange County Convention Center Orlando, Florida June 3-5, 2014

Orange County Convention Center Orlando, Florida June 3-5, 2014 Orange County Convention Center Orlando, Florida June 3-5, 2014 It Ain t Easy Being Green: The Andersons Story Of Staying On Track While Implementing A Multiple- Domain Governance Program In Parallel With

More information

An Oracle White Paper September 2009. Mastering Project Management Fundamentals Critical for Successful Earned Value Management

An Oracle White Paper September 2009. Mastering Project Management Fundamentals Critical for Successful Earned Value Management An Oracle White Paper September 2009 Mastering Project Management Fundamentals Critical for Successful Earned Value Management Executive Overview Earned value management (EVM) is a program management technique

More information

Integrated Project Management in SAP ERP

Integrated Project Management in SAP ERP Integrated Project Management in SAP ERP SAP Project Cost Forecast, SAP Project Cost Forecasting, SAP Project Forecast, SAP Project Forecasting, SAP Project System, SAP PS, SAP Project Management, SAP

More information

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10.

10.1 Communications Planning 10.2 Information Distribution Figure 10 1 10.3 Performance Reporting 10.1 Communications Planning 10. PROJECT 10 COMMUNICATIONS MANAGEMENT Project Communications Management includes the processes required to ensure timely and appropriate generation, collection, dissemination, storage, and ultimate disposition

More information

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004

EVA (C/SCSC) and Basics of Project Control. Nathaniel Osgood 4/7/2004 EVA (C/SCSC) and Basics of Project Control Nathaniel Osgood 4/7/2004 Topics Monitoring cont d EVA (C/SCSC) Definitions and examples Forecasting Project Control General Performance-adjustments adjustments

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

DISCUSSION AND CONCLUSIONS

DISCUSSION AND CONCLUSIONS Chapter Twelve DISCUSSION AND CONCLUSIONS TRANSITION TO LEAN MANUFACTURING The components of the lean manufacturing system have been widely publicized over the past few years; how the specific improvement

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,

More information

Earned Value User s Guide

Earned Value User s Guide ENTC 419 Project Management Earned Value User s Guide Jacob Terkelsen Project Manager Digerati Group Table of Contents TABLE OF CONTENTS... 2 INTRODUCTION... 3 REQUIREMENTS... 3 LAYOUT... 4 IMPLEMENTATION...

More information

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects

Towards a Multi-Dimensional Framework for Assessing the Value of. Software Projects Towards a Multi-Dimensional Framework for Assessing the Value of Software Projects by John Richard Kopp Submitted in partial fulfillment of the requirements for the Master s degree in Software Development

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

How SAP Business Objects Dashboards Are Improving Decision Making at Caterpillar Parts Distribution

How SAP Business Objects Dashboards Are Improving Decision Making at Caterpillar Parts Distribution How SAP Business Objects Dashboards Are Improving Decision Making at Caterpillar Parts Distribution Greg Lauer & John Buckhold Caterpillar Inc. SESSION CODE: 0705 DASHBOARDS Dashboards at Cat Parts Distribution

More information

ECM for SAP Software: The Business Case

ECM for SAP Software: The Business Case Orange County Convention Center Orlando, Florida May 15-18, 2011 ] Thomas Lynch ECM for SAP Software: The Business Case Sr. Principal, Value Engineering SAP America, Inc. Kris Inapurapu Director, Value

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

The Journey to Legal Project Management Software at Sutherland Asbill & Brennan By Jennifer Parker and Monica Ulzheimer

The Journey to Legal Project Management Software at Sutherland Asbill & Brennan By Jennifer Parker and Monica Ulzheimer The Journey to Legal Project Management Software at Sutherland Asbill & Brennan By Jennifer Parker and Monica Ulzheimer November 2011 Sutherland s journey to develop customized technology for Legal Project

More information

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International

Project Portfolio Management: James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Project Portfolio Management: Metrics that Work James C. Brown Sr. Manager, Research PMO Pioneer Hi-Bred International Agenda PPM Interest What is Project Portfolio Management? Challenges Myths Benefits

More information

Olav Jones, Head of Insurance Risk

Olav Jones, Head of Insurance Risk Getting you there. What is Risk Management of an Insurance Company, a view of a Head of Insurance Risk? Olav Jones, Head of Insurance Risk Olav Jones 29-11-2006 1 Agenda I. Risk Management in Insurance

More information

Predictive Analytics for Procurement Lead Time Forecasting at Lockheed Martin Space Systems

Predictive Analytics for Procurement Lead Time Forecasting at Lockheed Martin Space Systems Orange County Convention Center Orlando, Florida June 3-5, 2014 Session Code: 0204 Predictive Analytics for Procurement Lead Time Forecasting at Lockheed Martin Space Systems Using SAP HANA, R, and the

More information

Indirect Cost Rates The hidden contract cost driver? Professor Greg Martin Defense Acquisition University 703-805-3007 gregory. martin@dau.

Indirect Cost Rates The hidden contract cost driver? Professor Greg Martin Defense Acquisition University 703-805-3007 gregory. martin@dau. Indirect Cost Rates The hidden contract cost driver? Professor Greg Martin Defense Acquisition University 703-805-3007 gregory. martin@dau.mil Workshop # 92 PDI 2016 Why this topic. 1. Increase knowledge

More information

Brillig Systems Making Projects Successful

Brillig Systems Making Projects Successful Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

Business Dashboard. Develop a high performance business overnight!

Business Dashboard. Develop a high performance business overnight! Business Dashboard Develop a high performance business overnight! MAUS Dashboard is a web based KPI, Policies & Procedures, OHS & HR system all in one. Business Dashboard was developed as a tool to turn

More information

Basics of Cost and Schedule Control

Basics of Cost and Schedule Control Basics of Cost and Schedule Control Topics Monitoring and Scheduling: Two Parts of a Feedback System. Definitions Schedule Updates from Monitoring Components of Effective Monitoring Cost Control As A Management

More information

How To Manage A Project

How To Manage A Project Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management

More information

Creating High Performance Project Teams

Creating High Performance Project Teams Creating High Performance Project Teams EDWARD BYERS, PMP, S SGB ONIT MANAGEMENT CONSULTING e d w a r d. b y e r s @ o n i t m c. c o m 2013 AGENDA 1. Describe the value of a systematized approach in building

More information

VIII. Project Management Glossary

VIII. Project Management Glossary https://www.wrike.com/project-management-guide/glossary/ VIII. Project Management Glossary Project management, like any other industry, has its share of unique terms. Don t be overwhelmed. Here is our

More information

Business User driven Scorecards to measure Data Quality using SAP BusinessObjects Information Steward

Business User driven Scorecards to measure Data Quality using SAP BusinessObjects Information Steward September 10-13, 2012 Orlando, Florida Business User driven Scorecards to measure Data Quality using SAP BusinessObjects Information Steward Asif Pradhan Learning Points SAP BusinessObjects Information

More information

DCMA DCMA-EA PAM 200.1. October 2012

DCMA DCMA-EA PAM 200.1. October 2012 DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE

More information

Project Cost Management

Project Cost Management Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present

More information

Project Management vs. Change Management Presentation to the National Institutes of Health July 21, 2015

Project Management vs. Change Management Presentation to the National Institutes of Health July 21, 2015 Project Management vs. Change Management Presentation to the National Institutes of Health July 21, 2015 Presentation Objectives 1. Understand the key challenges and linkages between the disciplines. 2.

More information

Agenda. Copyright 2012 2013 Acuity Business Solutions, LLC All Rights Reserved

Agenda. Copyright 2012 2013 Acuity Business Solutions, LLC All Rights Reserved Agenda Understand the reasons your firm purchased Vision analyzing your company s pain points What is an ERP and how is it different? Project Lifecycle Reasons why firms fail at implementation or user

More information

SKF Implements Single Multi-Channel E-commerce Solution for SAP ERP & Legacy Applications

SKF Implements Single Multi-Channel E-commerce Solution for SAP ERP & Legacy Applications Orange County Convention Center Orlando, Florida June 3-5, 2014 SKF Implements Single Multi-Channel E-commerce Solution for SAP ERP & Legacy Applications Michaela Fath SKF Milind Joshi CDI Technology Agenda

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

top tips to help you save on travel and expenses

top tips to help you save on travel and expenses 5 top tips to help you save on travel and expenses Save money Increase control Free up staff Our 5 top tips for saving time and money on T&E Travel and Expenses (T&E) are amongst some of the highest costs

More information

7 Characteristics of High Performing Firms. Smartsoftware Seminar

7 Characteristics of High Performing Firms. Smartsoftware Seminar 7 Characteristics of High Performing Firms Smartsoftware Seminar Key Characteristics 1. Rock Solid Reputation 2. Determined Leadership 3. Enlightened Management 4. Well Managed Projects 5. Innovative Culture

More information

Project Execution - PM Elements

Project Execution - PM Elements Performance Initial Release 1. Introduction to Project Tracking and Reviewing Once a project has advanced to the phase of performance, the consistent and constant flow of information on the true status

More information

PROJECTS SCHEDULING AND COST CONTROLS

PROJECTS SCHEDULING AND COST CONTROLS Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to

More information

Hollister Experience with SAP CRM Upgrade from 4.0 to 7.0

Hollister Experience with SAP CRM Upgrade from 4.0 to 7.0 Orange County Convention Center Orlando, Florida May 15-18, 2011 Hollister Experience with SAP CRM Upgrade from 4.0 to 7.0 ] Severina Vilenchik Hemanth Singh Incorporated Introduction - About us Severina

More information

Winning with People in Project Portfolio Management. From Accidental Change Management to Intentional Change Leadership

Winning with People in Project Portfolio Management. From Accidental Change Management to Intentional Change Leadership Winning with People in Project Portfolio Management From Accidental Change Management to Intentional Change Leadership Agenda The Change Management Role in Project Portfolio Management The Accidental Change

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Analysis and Application of Earned Value Management in Software Development

Analysis and Application of Earned Value Management in Software Development Analysis and Application of Earned Value Management in Software Development Frank Tsui School of Computing and Software Engineering Southern Polytechnic State University, Marietta, Georgia, USA 30060 Abstract

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

Integrated Project Management Solutions for Capital and Maintenance projects in SAP PS enhanced by Noveco epm

Integrated Project Management Solutions for Capital and Maintenance projects in SAP PS enhanced by Noveco epm Integrated Project Management Solutions for Capital and Maintenance projects in SAP PS enhanced by Noveco epm Program and Project Management Long Term Strategic & Operational Portfolio Management Short

More information

Why Two Thirds of Enterprise Architecture Projects Fail

Why Two Thirds of Enterprise Architecture Projects Fail Why Two Thirds of Enterprise Architecture Projects Fail An explanation for the limited success of architecture projects Sven Roeleven Solution Manager Business White Paper December 2010 Contents Introduction

More information

Windows Server 2003 migration: Your three-phase action plan to reach the finish line

Windows Server 2003 migration: Your three-phase action plan to reach the finish line WHITE PAPER Windows Server 2003 migration: Your three-phase action plan to reach the finish line Table of contents Executive summary...2 Windows Server 2003 and the big migration question...3 If only migration

More information

Why are PMO s are Needed on Large Projects?

Why are PMO s are Needed on Large Projects? Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects

More information

The Success Story Behind Contact and Account Management at OPUBCO Communications Group

The Success Story Behind Contact and Account Management at OPUBCO Communications Group Orange County Convention Center Orlando, Florida May 15-18, 2011 The Success Story Behind Contact and Account Management at OPUBCO Communications Group Pam Harris, OPUBCO Communications Group Mohan Menon

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Marathon Petroleum Company: Automating Testing with SAP Quality Center, SAP Solution Manager and SAP TAO Myra Egbert, Betsy Buckley

Marathon Petroleum Company: Automating Testing with SAP Quality Center, SAP Solution Manager and SAP TAO Myra Egbert, Betsy Buckley Marathon Petroleum Company: Automating Testing with SAP Quality Center, SAP Solution Manager and SAP TAO Myra Egbert, Betsy Buckley Orange County Convention Center Orlando, Florida June 3-5, 2014 Agenda

More information

Brief Introduction to Earned Value Management (EVM)

Brief Introduction to Earned Value Management (EVM) Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing

More information

Tips and tricks for using SAP BusinessObjects Web Intelligence with SAP BW

Tips and tricks for using SAP BusinessObjects Web Intelligence with SAP BW Orange County Convention Center Orlando, Florida May 15-18, 2011 Tips and tricks for using SAP BusinessObjects Web Intelligence with SAP BW Deepu Sasidharan ] [ Agenda Introduction System Landscape Advanced

More information

Tracking Software Development Progress with Earned Value and Use Case Point

Tracking Software Development Progress with Earned Value and Use Case Point ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

BEST PRACTICES IN CHANGE MANAGEMENT

BEST PRACTICES IN CHANGE MANAGEMENT BEST PRACTICES IN CHANGE MANAGEMENT 2016 EDITION Executive Summary Best Practices in Change Management 2016 edition slide 1 THE LARGEST BODY OF KNOWLEDGE ON CHANGE MANAGEMENT Continuing to lead the discipline

More information

Orange County Convention Center Orlando, Florida June 3-5, 2014

Orange County Convention Center Orlando, Florida June 3-5, 2014 Orange County Convention Center Orlando, Florida June 3-5, 2014 EHP6- Implementing Employee and Manager Self Service at SSM Healthcare Guru Sundaresan Director, Clarkston Consulting Becki Feldmann Project

More information

Applied Project Management ( APM )

Applied Project Management ( APM ) Applied Project Management Applied Project Management ( APM ) TRAINING PROGRAM Page 1 Of 7 APPLIED PROJECT MANAGEMENT PRO PROGRAM OVERVIEW This course provides in-depth Project Management Training and

More information

Optimizing Rewards and Employee Engagement

Optimizing Rewards and Employee Engagement Optimizing Rewards and Employee Engagement Improving employee motivation and engagement, and identifying the right total rewards strategy to influence workforce effectiveness. Kevin Aselstine, Towers Perrin

More information

Getting more bang for your buck! 8 Quick Tips to boost elearning revenue

Getting more bang for your buck! 8 Quick Tips to boost elearning revenue Association Learning Getting more bang for your buck! 8 Quick Tips to boost elearning revenue Introduction More than ever before, elearning has gained a significant foothold in association education initiatives.

More information

PROJECT SCHEDULING AND TRACKING

PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING PROJECT SCHEDULING AND TRACKING Software project scheduling is an activity that distributes estimated effort across the planned project duration by allocating the effort

More information

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by: Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective