1 First reactor Greenfield challenges Elforsk seminar Stockholm, January 25, 2011 Juhani Hyvärinen
2 Initial challenge Site challenges Technology challenges Implementation challenges 2
3 The initial challenges Fennovoima was established in 2007 to build a new nuclear power plant for undersupplied Finnish electricity users, by 2020 New company, independent of existing nuclear operators in Finland: needs top quality staff + competent technical partners Needs a greenfield site The most modern technology by competent and reliable providers desired The first big milestone was the Decision-in-Principle (DIP) Mainly a political challenge, on two levels Local level: needed acceptance of candidate site communities, both decision makers and land owners National level: government and parliament approval 3
4 Fennovoima s ownership structure Operates as a cooperative, producing to owners at cost (non-profit) 54 local energy utilities 15 industrial and trade companies 55% 45% Voimaosakeyhtiö SF 66% E.ON Nordic 34% Fennovoima 4
5 70 Owners, 30% of Finnish electricity consumption; large, diverse ownership Metal, chemical, food and building materials industries; retail and services; local energy companies AGA Alajärven Sähkö Atria Boliden Harjavalta Boliden Kokkola Componenta E.ON Kärnkraft Finland Esse Elektro-Kraft Etelä-Savon Energia Finnfoam Haminan Energia Haukiputaan Sähköosuuskunta Herrfors Hiirikosken Energia Imatran Seudun Sähkö Itä-Lapin Energia Jylhän Sähköosuuskunta Jyväskylän Energia Kemin Energia Keminmaan Energia Keravan Energia Kesko Koillis-Satakunnan Sähkö Kokemäen Sähkö 5 Kotkan Energia Kruunupyyn Sähkölaitos KSS Energia Kuopion Energia Kuoreveden Sähkö Köyliön-Säkylän Sähkö Lahti Energia Lammaisten Energia Lankosken Sähkö Lehtimäen Sähkö Leppäkosken Sähkö Myllyn Paras Mäntsälän Sähkö Naantalin Energia Nurmijärven Sähkö Omya Oulun Seudun Sähkö Outokummun Energia Outokumpu Ovako Bar Paneliankosken Voima Parikkalan Valo Pietarsaaren Energialaitos Porvoon Energia Raahen Energia Rantakairan Sähkö Rauman Energia Rautaruukki Rovakairan Tuotanto Sallila Energia Seinäjoen Energia S-ryhmä Talvivaaran Kaivososakeyhtiö Tammisaaren Energia Tornion Energia Turku Energia Uudenkaarlepyyn Voimalaitos Vakka-Suomen Voima Valio Valkeakosken Energia Vantaan Energia Vatajankosken Sähkö Vetelin Sähkölaitos Vimpelin Voima Ålands Elandelslag Ääneseudun Energia
6 Fennovoima s owners are locate all over the country Energy industry 2/3 of local Finnish electricity companies Serve two million Finnish customers Foodstuff industry Retail Chemical industry Metals and mining Construction materials Local electrical utilities Biggest industrial and retail activities 6
7 Owners lack own generation capacity Shareholders use in total 30% of the electricity in Finland TWh Industry and retail Electricity from the market Power companies Own generation 7
8 E.ON and Fennovoima Simo Experienced and competent energy company Near staff Over 200 big power plants in Europe Pyhäjoki Europe s second largest producer of nuclear electricity 21 nuclear reactors in Germany and in Sweden nuclear experts Nuclear generation 80 TWh/a Strategic partnership Fennovoima is committed to using E.ON s nuclear expertise E.ON has already committed both full-time secondments and tens of part time experts to the project Brunsbüttel Unterweser Emsland Stade Forsmark Brokdorf Grohnde Würgassen Krümmel Grafenrheinfeld Isar Gundgremmingen Ringhals Oskarshamn Barsebäck E.ON as licensee E.ON as minority owner E.ON decommissioning Fennovoima 8
9 Schedule challenge Next steps: site and vendor selection = Contracting phase Preparation Broad ownership Site and technology alternatives developed EIA Municipality, STUK and other stakeholder statements Decision in Principle Contracting Site and main supplier selections Land use plans in force Site preparatory works Construction License and other permits Construction Building the plant and site facilities Operating License Operation At least 60 years of safe and economic operation Waste disposal Decommissioning and dismantling 9
10 Initial challenge Site challenges Technology challenges Implementation challenges 10
11 Two suitable alternative greenfield sites in Northern Finland Site selection Site screening process started in 2007 with ~40 candidates Fennovoima will select the final site in early 2011 Sufficient land area acquired Planning process completed in fall 2010 Environment and safety EIA completed in Spring 2009 Both sites passed review of the nuclear regulator STUK Regions support Fennovoima Both municipalities, regions, and majority of local people support the project 11
12 Majority in the regions support the project What is your opinion about Fennovoima s plan to build a nuclear power plant in the region? Pyhäjoki and surrounding municipalities* Simo and surrounding municipalities 100 % 100 % 90 % 80 % 70 % 60 % 50 % 40 % 30 % 20 % % 80 % 70 % 60 % 50 % 40 % 30 % 20 % Strongly disagree or disagree Neither agree or disagree Agree or strongly agree 10 % 10 % 0 % 5/ /2008 5/2009 1/ / % 5/ /2008 5/2009 1/ /2010 * Kalajoki, Merijärvi, Oulainen, Raahe, Vihanti Ii, Kemi, Keminmaa, Ranua, Tervola 12
13 Pyhäjoki site Areva (EPR and Kerena) and Toshiba (ABWR) as reactor options 13
14 Simo site Areva (EPR and Kerena) and Toshiba (ABWR) as reactor options 14
15 Initial challenge Site challenges Technology challenges Implementation challenges 15
16 Plant alternatives Toshiba ABWR, Areva EPR and Areva Kerena were shortlisted for the Decision-in-Principle Preliminarily reviewed by STUK Each of these represent a balanced combination of proven technology, licensability, and advanced features Toshiba ABWR EPR Kerena Vendor, country Toshiba/WES Japan/Sweden Areva NP France/Germany Areva NP France/Germany Thermal MW Electric MW ~1600 ~1700 ~1250 Reactor type Boiling water Pressurised water Boiling water Safety system Active + Passive Active Passive + Active Reference plant Hamaoka-5 Olkiluoto 3 Gundremmingen C 16
17 STUK comments on the EPR Acceptability of reactor power level 4590 MWth 17
18 STUK comments on the Kerena 1/2 Fuel pool cooling diversification Passive systems - functional tests - periodic testing concept Containment isolation valve diversification 18
19 STUK comments on Kerena 2/2 Electrical and I&C system - separation principles - redundancy Aircraft crash protection of control building Lessons learned from Forsmark incidents 19
20 STUK comments on the ABWR Fuel pool cooling diversification Containment isolation valve diversification Independence of electrical and I&C systems for core melt accidents Core catcher qualification ECCS strainer qualification Lessons learned from Forsmark incidents Bringing the plant to safe state without computerised I&C 20
21 Further technology challenges ABWR Europeanisation in detailed design EPR lessons learned from earlier projects Kerena is first-of-a-kind Implementation of EON Fleet principles on designs Adaptation technologies to site specific conditions Northern Finland is surprisingly seismic TI challenges Optimisation for cold cooling water Meeting grid compatibility requirements, especially the NORDEL 250 ms fault ride-out capability 21
22 Initial challenge Site challenges Technology challenges Implementation challenges 22
23 The DIP Phase The first big milestone was the Decision-in-Principle (DIP) Preceded by a thorough EIA for three separate candidate sites DIP Application covered 1 to 2 reactors + all other nuclear facilities on site (storage, L/MLW disposal) STUK review covering technology candidates, site candidates, and the company itself (competence) Political process where both local and national acceptance is needed Hundreds of other authority and stakeholder comments filed on first the EIA, then the DIP 23
24 Decision in Principle provides a solid foundation Goverment decision in Fennovoima s favour on May 6, 2010: According to the decision, Fennovoima Is authorised to build one nuclear reactor up to 1800 MWe Has to apply for a Construction License within five years Has to present next waste management plans within six years Parliament approved the decision on July 1, 2010 Vote result Parliament decision contains four motions; according to one of them The Government shall bring, during 2010, Posiva and its owners into negotiations with Fennovoima aiming at one national spent fuel management solution 24
25 What next? Continuing Fennovoima organisation build-up Site selection in first half of 2011 Commercial challenge: bidding process & technology selection in 2012 Coping with the ongoing major revision of the whole set of YVL Guides presents a challenge Parallel work on CL docs for competing technologies is needed Licensing challenge: preparations for Construction License application Ample time reserved for preparation between now and CL filing, and subsequent STUK review Site preparation (road, power, water,...) Implementation challenge: construction and commissioning In 2020, MWe up and running in Northern Finland 25
26 Thank you. Dr. Juhani Hyvärinen Chief Nuclear Officer Fennovoima Oy Salmisaarenaukio 1, Helsinki
New nuclear power plant construction project
New nuclear power plant construction project Overall description This is an overall description of the Fennovoima nuclear power plant project as required in section 13 of the Nuclear Energy Act, inspected
More informationEnvironmental Impact Assessment Program for a Nuclear Power Plant. September 2013
Environmental Impact Assessment Program for a Nuclear Power Plant September 2013 1 Contact information Project Owner: Fennovoima Oy Postal address: Salmisaarenaukio 1, FI-00180 Helsinki, Finland Phone:
More informationPocket Guide. Key Figures 2014. Teollisuuden Voima Oyj Well-being with nuclear electricity. Pocket Guide 2015 1
Pocket Guide Key Figures 2014 Teollisuuden Voima Oyj Well-being with nuclear electricity Pocket Guide 2015 1 4TEOLLISUUDEN VOIMA OYJ 4 Company 6 Company shareholders 7 Financial key figures 8THE OLKILUOTO
More informationPocket Guide. Key Figures 2013. Teollisuuden Voima Oyj Well-being with nuclear electricity
Pocket Guide Key Figures 2013 Teollisuuden Voima Oyj Well-being with nuclear electricity 4Teollisuuden Voima Oyj 4 Company 5 Company shareholders 8 Financial key figures 9The Olkiluoto nuclear power plant
More informationNuclear Power Financing in Finland Past experiences and future challenges. Jean-Francois Tapprest 07.10.2010
Nuclear Power Financing in Finland Past experiences and future challenges Jean-Francois Tapprest 07.10.2010 Agenda The experience of financing OL3 Financing of new plants in Finland Case Lithuania Visaginas
More informationPocket Guide 2012. Pocket Guide 2012 1
Pocket Guide 2012 Pocket Guide 2012 1 2 Pocket Guide 2012 04 11 Teollisuuden Voima Oyj Olkiluoto nuclear power plant 4 Company 5 Shareholders and holdings 6 Important dates 10 Key figures 10 Nuclear Waste
More informationNuclear Design Practices and the Case of Loviisa 3
Nuclear Design Practices and the Case of Loviisa 3 Harri Tuomisto Fortum Power, Finland Third Nuclear Power School, 20-22 October 2010, Gdańsk, Poland 22 October 2010 Harri Tuomisto 1 Objectives The objective
More informationNUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012
NUCLEAR POWER OVERALL GOOD FOR THE SOCIETY Finnish German Energy Day, 7th November 2012 Tanhua Jarmo Teollisuuden Voima Oyj 2 EU ENERGY ROADMAP 2050 NUCLEAR POWER IN ALL SCENARIOS Consumption of electricity
More informationSwiss media visit to Olkiluoto August 15, 2014
Swiss media visit to Olkiluoto August 15, 2014 Käthe Sarparanta Senior Adviser, Project Department Teollisuuden Voima Oyj NUCLEAR POWER PLANTS IN FINLAND Olkiluoto, Eurajoki Population 5.4 million Power
More informationTeollisuuden Voima Oyj - General Presentation January 2009. Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj
Teollisuuden Voima Oyj - General Presentation January 2009 Ilkka Mikkola Senior Adviser (Former Fuel Manager) Teollisuuden Voima Oyj Nuclear Power Plants in Finland in 2008 Olkiluoto OL1 BWR 860 MW 1978
More informationRights and obligations of DSOs and suppliers in the customer interface Evaluation of responses from the public consultation
Rights and obligations of DSOs and suppliers in the customer interface Evaluation of responses from the public consultation Report 5/2011 RIGHTS AND OBLIGATIONS OF DSOs AND SUPPLIERS IN THE CUSTOMER INTERFACE
More informationNEW NUCLEAR POWER PLANT UNIT IN FINLAND ACCEPTED BY THE FINNISH PARLIAMENT
International Conference Nuclear Energy for New Europe 2002 Kranjska Gora, Slovenia, September 9-12, 2002 www.drustvo-js.si/gora2002 NEW NUCLEAR POWER PLANT UNIT IN FINLAND ACCEPTED BY THE FINNISH PARLIAMENT
More informationTHE CONSTRUCTION OF. Natural Gas 11% Coal 12% Industry 49% Nuclear 18%
THE CONSTRUCTION OF OLKILUOTO 3 IN FINLAND ND A CASE STUDY Summary The recent publication of the energy review and CoRWM s findings have ensured nuclear is currently top of the news agenda. With new build
More informationManagement of spent fuel and radioactive waste in Finland national programme in accordance with Article 12 of the Council Directive 2011/70/Euratom
Management of spent fuel and radioactive waste in Finland national programme in accordance with Article 12 of the Council Directive 2011/70/Euratom 1 Contents Preface... 4 Introduction... 5 1 Overall objectives
More informationAREVA: supply chain network principles and company s vision
AREVA: supply chain network principles and company s vision Virginie MOUCQUOT-LAIHO AREVA Finland Communications Director & Vice Country Manager Oulu, Finland 18.09.2012 1 AREVA & nuclear industry The
More informationTVO and Nuclear Waste Management at Olkiluoto. Corporate Adviser
Olkiluoto, 28 October 2008 TVO and Nuclear Waste Management at Olkiluoto Corporate Adviser Nuclear Power Plants in Finland Olkiluoto OL1 BWR 860 MW 1979 OL2 BWR 860 MW 1982 Population 5.3 million Power
More informationOnkalo: Recent policies on the disposal of nuclear waste in Finland
Onkalo: Recent policies on the disposal of nuclear waste in Finland Burkhard Auffermann, Finland Futures Research Centre Climate Policy Strategies and Energy Transition, session on Nuclear Waste Governance
More informationNew nuclear project financing Warsaw, June 26, 2013 p. 1
New nuclear project financing Warsaw, June 26, 2013 p. 1 The EPR design: a reference technology Loïc ELOY Director of New Builds Offers Poland Platts Conference Warsaw, 26 June 2013 EPR reactor design
More informationPOHJOLAN VOIMA COMBINES RESOURCES
POHJOLAN VOIMA COMBINES RESOURCES POHJOLAN VOIMA COMBINES RESOURCES Pohjolan Voima s joint resources increase our customers competitive advantage through providing efficient and innovative energy services
More informationE.ON Nordic: Steady Value Growth
E.ON Nordic: Steady Value Growth Lars Frithiof Chief Executive Officer, E.ON Nordic E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Topics for the day Introduction to E.ON Nordic Our achievements
More informationAREVA, an unparalleled experience in building nuclear reactors
AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European
More informationNuclear Waste Management in Finland
Nuclear Waste Management in Finland Facts about Finland Independent Republic since 1917 Member State of the European Union since 1995 Capital: Helsinki Neighbouring countries: Estonia, Norway, Russia and
More informationRADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND
RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND 1. NATIONAL FRAMEWORK FOR MANAGEMENT AND REGULATION OF RADIOACTIVE WASTE AND DECOMMISSIONING 1.1 National framework 1.1.1 Overview of national
More informationGovernment Degree on the Safety of Nuclear Power Plants 717/2013
Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and
More informationCO 2 emissions, energy efficiency and renewables are in the focus. A carbon neutral future as a goal
RESPONSIBLE ENERGY A carbon neutral future as a goal The Finnish Energy Industries goal is to achieve carbon neutral production of electricity and district heat in Finland by 2050. We have answered the
More informationOlkiluoto 3 Basic Facts
Olkiluoto 3 Basic Facts TVO a world-class nuclear power company Teollisuuden Voima Oy (TVO) is a Finnish limited liability company established in 1969. The operating idea of the Company is to produce electricity
More informationOutlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012
Outlook for RWE s nuclear operations Prof. Dr. Gerd Jäger London, 16 January 2012 Overview of German nuclear power plants Power plant Net capacity MW Commercial commissioning Shutdown German nuclear power
More information46 000 m 2 of business space in the best commercial spot! Raahen Portti Trade and Services RAAHEN PORTTI
46 000 m 2 of business space in the best commercial spot! Raahen Portti Trade and Services www.raahenportti.fi The Gateway of Raahe www.raahenportti.fi The Gateway of Raahe Trade and Services 46 000 m
More informationHåkan Lorentz Barsebäck Kraft AB Box 524, SE-246 25 Löddeköpinge, Sweden
WM2009 Conference, March 1-5, 2009, Phoenix, AZ Barsebäck NPP in Sweden Transition to Decommissioning Socio-Economic Aspects of Decommissioning What Did We Achieve During the Transition 1997-2008? 9092
More informationPower Generation Portfolio
Power Generation Portfolio Håkan Bushke Senior Vice President Electricity Production E.ON Capital Market Day Nordic Stockholm, July 3, 2006 Agenda Nordic and the Swedish power situation E.ON Sverige generation
More informationNew legislation in the nuclear field in Sweden
1 New legislation in the nuclear field in Sweden A presentation at INLA Congress 2012 (Manchester) - 11 October 2012 by Ingvar Persson, Swedish National Council for Nuclear Waste and PP 1 Presentation
More informationELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY
ELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Requirement specification, selection, and procurement of electrical and I&C equipment and cables 7 3.1 General
More informationEPV Energy Ltd Kirkkopuistikko 0 Tel. +358 (0)10 505 5000 65100 Vaasa Fax +358 (0)10 505 5001 www.epv.fi Annual report 2014
Annual report 2014 EPV ENERGY LTD 2014 2 TABLE OF CONTENTS EPV Energy Ltd...2 An unprejudiced pioneer...3 The CEO s statement....4 Towards low-emission energy generation...6 Group structure and business
More informationOlkiluoto 3 Project June 2010
Olkiluoto 3 Project June 2010 Author: R&S Communications Department, La Défense, France. The reproduction, transmission or use of this document or its contents is not permitted without express written
More information7.1 General 5 7.2 Events resulting in pressure increase 5
GUIDE YVL 2.4 / 24 Ma r ch 2006 Primary and secondary circuit pressure control at a nuclear power plant 1 Ge n e r a l 3 2 General design requirements 3 3 Pressure regulation 4 4 Overpressure protection
More informationManagement of Radioactive Waste and Spent Fuel, Balance of Reprocessing
Management of Radioactive Waste and Spent Fuel, Balance of Reprocessing Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Second Review Meeting May
More informationWORKING PAPER Identifying remaining socio-technical challenges at the national level: Finland (WP 1 MS 5)
WORKING PAPER Identifying remaining socio-technical challenges at the national level: Finland (WP 1 MS 5) Nurmi, Anna, University of Jyväskylä Kojo, Matti, University of Tampere Litmanen, Tapio, University
More informationElectrical Systems. Emergency Diesel Generator Solutions
Electrical Systems Emergency Diesel Generator Solutions AREVA Competence in Emergency Power Supply Emergency Diesel Generators (EDGs) Business Areas e Modernization of existing EDGs p Customer support
More informationInvesting in our common future
Investing in our common future PRODUCTION LOCATIONS Hydropower plants Thermal power plants Nuclear power plant * under construction Jolmankoski Kaaranneskoski Portimokoski Jumisko Isohaara Kierikki Raasakka
More informationSolutions for Nuclear & Renewable Power Generation
Solutions for Nuclear & Renewable Power Generation Integrated Business Model Luc Oursel AREVA CEO AREVA has become the undisputed global leader in low carbon power generation solutions through its unique
More informationNuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3
GUIDE 26 June 2000 YVL 2.1 Nuclear power plant systems, structures and components and their safety classification 1 General 3 2 Safety classes 3 3 Classification criteria 3 4 Assigning systems to safety
More informationOlkiluoto 3 Project. AREVA Suppliers Day Warsaw October 4, 2011
Olkiluoto 3 Project AREVA Suppliers Day Warsaw October 4, 2011 Virginie MOUCQUOT-LAIHO AREVA OL3 Project Management Office & Communications Manager AREVA Reactor & Services - New Builds EPR Project Fleet
More informationThe new waste burning investment in the Helsinki Metropolitan Area
The new waste burning investment in the Helsinki Metropolitan Area Vantaa Energy, Project Director Pekka Karjalainen 15.1.2010 / PK The Vantaa Energy Group Vantaa Energy Ltd Vantaa Energy Electricity Networks
More informationThe Price-Anderson Act and the Three Mile Island Accident
The Price-Anderson Act and the Three Mile Island Accident OECD/NEA Workshop Nuclear Damages, Liability Issues, and Compensation Schemes Overview Overview of Nuclear Liability in U.S. Three Mile Island
More informationEnvironmental Impact Assessment Report for a Nuclear Power Plant. February 2014
Environmental Impact Assessment Report for a Nuclear Power Plant February 2014 Contact information Party responsible for the project: Fennovoima Oy Postal address: Salmisaarenaukio 1, FI-00180 Helsinki,
More informationDrivers and approach for the design of the EPR reactor
Drivers and approach for the design of the EPR reactor Martine Mayousse Reactor & Services / Safety & Licensing IAEA Vienna June 27, 2013 1 Agenda 1. Introduction 2. EPR design objectives and principles
More informationSafety of New Nuclear Power Plants
Safety of New Nuclear Power Plants Example: VVER-1200/V491 H. Hirsch A. Y. Indradiningrat Workshop on the Paks II NPP Project Budapest, Energiaklub, 08.10.2014 New NPP in Paks: Reactor Type In the EIA
More informationSPANISH NUCLEAR INDUSTRY. Antonio Cornadó Quibus President Spanish Nuclear Industry Forum
SPANISH NUCLEAR INDUSTRY Antonio Cornadó Quibus President Spanish Nuclear Industry Forum WHAT IS SPANISH NUCLEAR IDUSTRY FORUM? An association of companies that support activities related to nuclear energy:
More informationLoviisa 3 unique possibility for large scale CHP generation and CO 2 reductions. Nici Bergroth, Fortum Oyj FORS-seminar 26.11.
Loviisa 3 unique possibility for large scale CHP generation and CO 2 reductions Nici Bergroth, Fortum Oyj FORS-seminar 26.11.2009, Otaniemi Loviisa 3 CHP Basis for the Loviisa 3 CHP alternative Replacement
More informationAREVA. Solutions for Nuclear & Renewable Power Generation
AREVA Solutions for Nuclear & Renewable Power Generation 1 AREVA Group Arlit, Niger Melox, France La Hague, France Lynchburg, U.S.A. Alpha Ventus, Germany 2 AREVA Group 2011 Key Figures 8.872Bn in Annual
More informationThe EPR reactor the reference for New Build
The EPR reactor the reference for New Build The reference for New Build The Reference for Safety The EPR design offers the highest level of safety: Already licensed in France, Finland and China Strong
More informationNuclear Safety. Policy 2013-2016
Nuclear Safety Policy 2013-2016 Nuclear Safety Policy 2013-2016 T he organisational principles and actions defined in the Nuclear Safety Charter and applied within the group have achieved significant improvements
More informationFINNGULF LNG LNG IMPORT TO FINLAND
FINNGULF LNG LNG IMPORT TO FINLAND CLEANLY WITH NATURAL ENERGY GASES Gasum is a Finnish expert in natural energy gases. We import natural gas to Finland, and transmit and supply it for energy production,
More informationAREVA Advanced nuclear power plants
AREVA Advanced nuclear power plants Bernard Bastide AREVA Brazil and South America VP University of Rio de Janeiro III Semana da Engenharia Nuclear UFRJ August 2013 AREVA presentation AREVA EPR projects
More informationDRAFT Milestones and Recommendations: Fuel Cycle OECD/IEA 2010
DRAFT Milestones and Recommendations: Fuel Cycle 1 OECD/IEA 2010 Fuel cycle: - established technologies for all steps of the NFC, though R&D can help improve technologies, reduce costs, Front end: uranium
More informationNuclear Consultancy & Engineering Services
Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION
More informationWind energy statistics in Finland 2012 Public version. [Source: Tuuliwatti Oy (Simo wind plant)]
Wind energy statistics in Finland 2012 Public version [Source: Tuuliwatti Oy (Simo wind plant)] Click Wind to energy edit Master year 2012 title style Click End of to year edit capacity Master in text
More informationGlobal Nuclear Power Developments Asia Leads The Way
Global Nuclear Power Developments Asia Leads The Way Edward Kee Nuclear Energy Asia 2010 - Hong Kong (1400 1430) Global Nuclear Power Developments - Asia Leads The Way What is the competitive global position
More informationMANAGEMENT SYSTEM FOR A NUCLEAR FACILITY
GUIDE YVL A.3 / 2 June 2014 MANAGEMENT SYSTEM FOR A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Management system 6 3.1 Planning, implementation, maintenance, and improvement of the management
More informationTOSHIBA s Nuclear Energy Activities
December 12, 2010 IGARASHI, Yasuharu Toshiba Corporation, Executive Officer Corporate Senior Vice President President & CEO, Power Systems Company Export Control No. PSN-2010-1406 Document No. G3-1109
More informationBuilding New Generation Nuclear Plants Worldwide : AREVA's Experience
Building New Generation Nuclear Plants Worldwide : AREVA's Experience Philippe Guay Senior Vice President, New Builds Offers AREVA 37 th WNA Symposium 12-14 September 2012 LONDON Projects status The value
More informationTeollisen ekologian soveltaminen Perämerenkaaren metallurgiseen teollisuuteen - Kommenttipuheenvuoro
Teollisen ekologian soveltaminen Perämerenkaaren metallurgiseen teollisuuteen - Kommenttipuheenvuoro Juho Mäkinen, VTT Business Solutions Industrial Ecosystem A system where the industrial actors use the
More informationWind energy statistics in Finland 2014 Version: Public. Foto: Puhuri Oy, Kopsa wind plant
Wind energy statistics in Finland 2014 Version: Public Foto: Puhuri Oy, Kopsa wind plant Click Wind to energy edit Master year 2014 title style End of year capacity in Finland: 631 MW (268 turbines)* Average
More informationTechnical concepts for storing HLW - Monitoring, renewal and refurbishment of storage facilitites
Technical concepts for storing HLW - Monitoring, renewal and refurbishment of storage facilitites Dipl.-Ing. Dennis Köhnke Dipl.-Ing. Manuel Reichardt Institute for Building Materials, Concrete Construction
More informationOVERVIEW OF THE OPERATING REACTORS BUSINESS LINE. July 7, 2016 Michael Johnson Deputy Executive Director for Reactor and Preparedness Programs
OVERVIEW OF THE OPERATING REACTORS BUSINESS LINE July 7, 2016 Michael Johnson Deputy Executive Director for Reactor and Preparedness Programs Program Overview Bill Dean Director Office of Nuclear Reactor
More informationHow To Make Money In Sweden
Future challenges in the Swedish electricity production Presentation at The Finnish Nuclear Society s 40th Anniversary Helsinki, October 13, 2006 Bo Källstrand, Managing Director Svensk Energi Sweden,
More informationSAFETY DESIGN OF A NUCLEAR POWER PLANT
GUIDE YVL B.1 / 15 November 2013 SAFETY DESIGN OF A NUCLEAR POWER PLANT 1 Introduction 5 2 Scope 5 3 Management of design 5 3.1 Organisations responsible for design 5 3.2 Design processes 6 3.3 Configuration
More informationSafety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland
Safety culture in the construction phase lessons learned from Olkiluoto 3 Pia Oedewald, Senior scientist VTT Technical Research Centre of Finland IAEA Technical meeting on Safety culture in pre-operational
More informationPRESS RELEASE. At September 30, 2015: Progress on the transformation plan in the third quarter:
At September 30, 2015: Rise in revenue to 2.947bn: +10.3% vs. September 2014 (+8.7% like for like) Backlog of 31.595bn Discontinued operations, including AREVA NP: Revenue of 2.732bn: -7.5% vs. September
More informationFINANCIAL INSTITUTIONS ENERGY INFRASTRUCTURE, MINING AND COMMODITIES TRANSPORT TECHNOLOGY AND INNOVATION PHARMACEUTICALS AND LIFE SCIENCES
Nuclear Finance Basics FINANCIAL INSTITUTIONS Offtakers Regulators Developers People International Stakeholders Government Operators Suppliers Public Legacy Managers Financers Insurers 2 NEPIO Government
More informationA short history of reactors
A short history of reactors Janne Wallenius Reactor Physics, KTH Objectives of this meeting The origin of nuclear power was considerably more diversified than the existing variation in commercial reactor
More informationREPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL
EUROPEAN COMMISSION Brussels, 3.3.2015 COM(2015) 78 final REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL on the implementation of the work under the nuclear decommissioning assistance
More informationDESIGN OF EPR. Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com. AREVA FRAMATOME ANP Plants Sector Nuclear Engineering
DESIGN OF EPR Bernard DEBONTRIDE France, bernard.debontride @framatome-anp.com AREVA FRAMATOME ANP Plants Sector Nuclear Engineering Key Words: EPR, Design Abstract: At the origin was the common decision
More informationReport of the Committee for Nuclear Energy Competence in Finland
Report of the Committee for Nuclear Energy Competence in Finland Publications of the Ministry of Employment and the Economy Energy and the Climate 14/2012 Report of the Committee for Nuclear Energy Competence
More informationHOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY
HOISTING AND TRANSFER EQUIPMENT OF A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Equipment requirement specifications for hoisting device units 7 4 Manufacturer 7 4.1 General 7 4.2 Obligations
More informationStructural Integrity and NDE Reliability II
Structural Integrity and NDE Reliability II Preparing for EPR TM Reactor Vessel Inspection J. Laube, AREVA NDE Solutions / intelligendt, Germany Y. Bouveret, AREVA NDE Solutions / Intercontrole, France
More informationPGE - Polish Energy Group. Nuclear power development in Poland - we need decision today. Organisation of the Polish Power Sector After Consolidation
Nuclear power development in Poland - we need decision today Hanna Trojanowska Director of International Affairs and New Technologies Department PGE Polska Grupa Energetyczna S.A. Organisation of the Polish
More informationNGV / CNG Market Finland Jussi Vainikka, Gasum Oy Malmö, Sweden, 28.01.2010. 01/05/2009 30/04/2012, IEE/08/545/SI2.528537, www.gashighway.
NGV / CNG Market Finland Jussi Vainikka, Gasum Oy Malmö, Sweden, 28.01.2010 01/05/2009 30/04/2012, IEE/08/545/SI2.528537, www.gashighway.net AGENDA Finnish natural gas market and Gasum (short overview)
More informationNational Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission
Ref: 1602/601/2014 10.7.2014 National Report 2014 to the Agency for the Cooperation of Energy Regulators and to the European Commission Finland National Report 2014 - Energy Authority, Finland 1 CONTENT
More informationPROBABILISTIC RISK ASSESSMENT AND RISK MANAGEMENT OF A NUCLEAR POWER PLANT
PROBABILISTIC RISK ASSESSMENT AND RISK MANAGEMENT OF A NUCLEAR POWER PLANT 1 Introduction 3 2 Scope of application 3 3 Development and use of the PRA 4 3.1 General requirements 4 3.2 PRA during the design
More informationFlamanville 3 Nuclear Power Plant
Flamanville 3 Nuclear Power Plant Prepared by: Giorgio Locatelli (University of Lincoln) and Mauro Mancini (Politecnico di Milano) Contacts: Giorgio Locatelli University of Lincoln Lincoln School of Engineering
More informationFinnish wind power from an investor perspective
Finnish wind power from an investor perspective Talking about Invest in Finland Current status Opportunities Key questions 2 3/27/2015 Finpro Invest in Finland Invest in Finland Mission what we do Assist
More informationOULU UNIVERSITY HOSPITAL. P romoting better health
OULU UNIVERSITY HOSPITAL P romoting better health Top healthcare provider Oulu University Hospital (OYS) is an innovative, research and development-oriented provider of high-quality healthcare. The five
More informationReconciling Electricity Markets and New Nuclear Build. Platts 3rd Annual European Nuclear Power Conference
Reconciling Electricity Markets and New Nuclear Build Presentation at: Platts 3rd Annual European Nuclear Power Conference July 1, 2008 London Steve Thomas (stephen.thomas@gre.ac.uk) PSIRU (www.psiru.org),
More informationVATTENFALL Q1 2016 RESULTS
VATTENFALL Q1 2016 RESULTS Magnus Hall, CEO and Ingrid Bonde, CFO Presentation 28 April 2016 1 HIGHLIGHTS AND KEY FIGURES Stable results in Q1 due to higher production volumes and lower costs Good water
More informationWaste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010
Waste Volume Reduction by Studsvik Nuclear AB Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Streams from Industry The Nuclear Industry generates operational waste during its lifetime as well
More informationHybrid system. Energy-efficient and environmentally friendly
Hybrid system Energy-efficient and environmentally friendly Hybrid solutions Hybrid heating systems utilise several different energy sources for heating and hot water supply during the different seasons
More informationFortum Corporation. Financial Statements Bulletin 2011. 1 February 2012. Fortum Corporation. Domicile Espoo Business ID 1463611-4
Financial Statements Bulletin 1 February 2012 Fortum Corporation Domicile Espoo Business ID 1463611-4 Financial Statements Bulletin 1 February 2012 at 9:00 EET Overall good year in a challenging environment
More informationTowards a French Nuclear Phase-Out?
Towards a French Nuclear Phase-Out? New Directions in the Energy Debate Yves Marignac Director of Nuclear Energy Conference 2015 Europe without nuclear - What does Europe's energy future look like? 19
More informationThe EPR design: the European reference
The EPR design: the European reference Jean-Bernard Ville Executive Vice-President, New Builds June 25 th, London 1 EPR Design safety 2 EPR project delivery 3 A partnership-based approach Platts 7 th European
More informationMDEP Generic Common Position No DICWG 02
MDEP Generic Common Position No DICWG 02 Related to: Digital Instrumentation and Controls Working Group activities COMMON POSITION ON SOFTWARE TOOLS FOR THE DEVELOPMENT OF SOFTWARE FOR SAFETY SYSTEMS 1
More informationEUROPEAN ELECTRICITY MARKET INTEGRATION: THE NORDIC EXPERIENCES
EUROPEAN ELECTRICITY MARKET INTEGRATION: THE NORDIC EXPERIENCES Lars Bergman Stockholm School of Economics Box 6501 SE-113 83 Stockholm, Sweden Abstract During the 1990s the electricity markets in Norway,
More informationSilver Mine Project Investment Opportunity in Scandinavia
Silver Mine Project Investment Opportunity in Scandinavia KPMG Corporate Finance ( KPMG ) has been retained by Sotkamo Silver as exclusive Financial and Strategic adviser in connection with the Project
More informationEPV Energy Ltd Frilundintie 7 Tel. +358 (0)10 505 5000 FI-65170 Vaasa Fax +358 (0)10 505 5001 www.epv.fi Annual Report 2013 1
1 Annual Report 2013 Table of contents EPV Energy Ltd................................... 2 Towards low-emission energy generation...... The CEO s statement............................. Group structure
More informationPresentation: June 2010. Enabling change combining competencies
Presentation: June 2010 Enabling change combining competencies Empower in Brief Empower is a multinational service group delivering construction, and professional services within energy, telecom and industry
More informationFinnish Institute of Occupational Health. Finnish Institute of Occupational Health - Annual Report
Page 1 of 5 Search: fioh annual report Instructions Main Page Contact Us Organization Thematic Pages Research Information Training Advisory services Organization About FIOH Strategy Annual Report Organization
More informationRepublic of Turkey. Date of acceptance: 9 November 2007 PART 1. Goal, scope, definitions and abbreviations. Goal and scope.
Republic of Turkey Unofficial Translation 1 of the Turkish Law No. 5710 2 Concerning the Construction and Operation of Nuclear Power Plants and the Sale of Energy Generated from Those Plants Date of acceptance:
More informationIntroductions: Dr. Stephen P. Schultz
Introductions: Dr. Stephen P. Schultz Vienna, Austria 1 3 September 2015 Work Experience Current Member Advisory Committee on Reactor Safeguards, U.S. Nuclear Regulatory Commission, 12/2011 Chair, Fukushima
More informationNational Report 2015 to the Agency for the Cooperation of Energy Regulators and to the European Commission
Ref: 1842/601/2015 10.7.2015 National Report 2015 to the Agency for the Cooperation of Energy Regulators and to the European Commission Finland National Report 2015 - Energy Authority, Finland 1 CONTENT
More information