ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

Size: px
Start display at page:

Download "ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION"

Transcription

1 ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, insurance, accessories, tools, transportation, supplies, materials, supervision, data compilation and diagnosis, meetings and technical competence to perform all operations required to conduct the closed-circuit television (CCTV) inspection of designated pipeline segments and manholes. 1.2 The Contractor shall utilize Pipeline Assessment and Certification Program (PACP) certified inspectors for this contract at all times and PACP Version 6 coding methods shall be employed for all CCTV inspections conducted under this contract. Evidence of PACP certification of the Operator shall be provided to the NBC prior to the commencement of any work. 1.3 The Contractor shall be responsible for removing his equipment from the sewers and for all associated sewer and restoration repairs necessary as a result of his work. 1.4 The Contractor will be responsible for obtaining pertinent information to safely and effectively perform all work. 1.5 The Contractor s field technicians must maintain current certifications for Confined Space Entry as defined in OSHA regulations, 29CFR1910 and all amendments. The Contractor must have and utilize all necessary safety equipment to enter a Permit Required Confined Space and maintain it in good working order. The contractor must produce OSHA 10 hour and or 30 hour cards before any work commences. 1.6 Definitions Pipe Inspection: Color television inspection by obtaining a closed circuit television camera view into a sewer line for the purpose of visual inspection of the interior portion of the sewer line structures using PACP coding methods as detailed in section 1.2 in this specification. A permanent color recording of all interceptor inspection s is produced by the contractor and submitted to the NBC Pipe Inspection: Information collected and recorded by each operator using PACP coding as detailed in section 1.2 in this specification for any pipe inspection submitted to the NBC Inspection Operator: PACP-certified inspector trained in operating inspection equipment Pipe Segment: Defined as length of pipe measured from center of upstream manhole or node point to center of downstream manhole or node point. 1.7 The intent of the pipe inspection services is to accomplish two basic functions: (1) to provide an accurate understanding of the existing pipe and its condition; (2) identify and asses the condition of all connections to the sewer. 2.0 Products 2.1 Maps and Details The NBC will provide the contractor with an Excel spreadsheet that will include pertinent information on the various pipe segments and manholes to be included 2/6/20152/4/2015 Page CCTV-1

2 in the contract The NBC will make available GIS plans showing the entire run of sewer to be inspected including aerial photographs indicating locations of various pipe segments and manholes to be included in the contract The information provided herein is the best record that the NBC has on this sewer. Actual conditions may vary from what is indicated on the information provided. 2.2 CCTV Equipment The Contractor shall select and use a CCTV system that is a self-contained system complete with closed circuit television camera, monitor, and computer system with video capture card or specialized video recording equipment capable of pausing and resuming live recordings, capable of entering a manhole cover with a minimum opening of 18 diameter clearance, and all necessary equipment for the successful completion of television inspection. The equipment shall be capable of performing inspections from manholes in various field conditions. The Contractor shall have alternative capabilities to perform inspections as specified in areas where vehicle access to manholes is limited. The contractor shall have equipment capable of viewing all pipeline connections to NBC structures in order to assess the condition at the point where the connecting pipe ties into the NBC mainline and to assess whether or not the connection to the pipe is active or sealed in the immediate area of NBC property. The inspection will be limited to the extent of available camera lighting and/or bends in the connection; no device, (such as a lateral launcher), shall enter any service connections. The purpose of this observation is to assess the condition at the point of connection to the NBC pipe and attempt to determine its current state, (abandoned or active) Contractor will locate pre-designated manholes with a utility locator comprised of a receiver and transmitter per contract specifications. The transmitter shall be capable of transmitting 16Hz, 512Hz, or 8KHz; (transmitter selection will depend upon pipe material and depth), and shall be firmly secured to the CCTV Transporter/Camera unit. The receiver must be capable of locating the transmitter in pipelines comprised of brick, clay, iron, plastic, and asbestos pipe materials and at depths up to 80 feet. The receiver must also be capable of tracing pipelines and depth determination. 2.3 Pipe Inspection Camera The Contractor shall produce a video using a pan-and-tilt, radial viewing, pipe inspection camera that pans 275 degrees and rotates 360 degrees. The camera used for the inspection shall be specifically designed and constructed for such inspection. The camera must be solid-state color and have remote control of the 360-degree rotational lens. Cameras incorporating mirrors for viewing sides or cameras using exposed rotating heads are not acceptable. The camera shall be operative in 100% humidity conditions. Lighting for the camera shall be suitable to allow a clear picture of the entire periphery of the pipe. The video camera shall 2/6/20152/4/2015 Page CCTV-2

3 be capable of showing on the video the City name, Project name, Contractor name, date, pipe size and material, line identification number (NBC GIS upstream and downstream manhole identification numbers). The inspection shall show this information in the beginning of the inspection but not proceed with this information displayed on the screen throughout the inspection. The camera, monitor and other components of the video system shall be capable of producing a minimum 460 line resolution video picture. Picture quality and definition shall be to the satisfaction of the NBC and if unsatisfactory, equipment shall be removed and replaced with adequate equipment. No payment will be made for an unsatisfactory inspection All CCTV inspections shall require a crawler transporter; floating for video inspections will NOT be allowed unless the pipe segment has been pre-approved by the NBC. 2.4 Deliverables The contractor shall provide all inspection data and files on a portable external hard drive and shall become the property of the NBC once submitted The external hard drive shall contain all video files located in a separate file folder titled Pipe Inspection Videos in standard mpg video file format burned with a current version of Microsoft Windows Media Player and individual; (not combined), PDF files of each inspection report located in a separate file folder titled Pipe Inspection Reports. The report file shall note all required header information and observations/defects per NASSCO s PACP guidelines. Individual files shall be named with its NBC GIS Unit ID and date of inspection as indicated in section A label permanently affixed to the external hard drive is required as noted in Section The external hard drive shall contain the most current NASSCO version of a PACP database which should be exported from the native software product All mpg video files and individual report PDF s contained on the hard drive shall be named as follows: upstream manhole ID-downstream manhole ID-Date- TimeStamp; (i.e.m m mmddyyyy-hhmmss.mpg: M M MMDDYYYY-HHMMSS.pdf ) Defect classifications and descriptions shall be PACP compliant as detailed in section 1.2 in this specification. 2.5 Viewing Software Software shall be PACP 6 compliant Acceptable complimentary software packages are as provided by WinCan Version 8 or approved equal. 3.0 Execution 3.1 CCTV Inspection of Sewer Lines Prepare area of pipe inspection to provide safe conditions for vehicle and 2/6/20152/4/2015 Page CCTV-3

4 pedestrian traffic throughout the inspection procedure Perform gas monitoring within manhole structure at various levels prior to opening the manhole cover and after the cover is opened to ensure safe atmospheric conditions. Monitored gasses must include but not limited to: Methane, Hydrogen Sulfide, Oxygen, Carbon Dioxide, and Carbon Monoxide Record television pipe inspections at the conclusion of any cleaning work as required in Attachment 3: Specifications for Sewer Cleaning At the discretion of the NBC or if the operator questions the accuracy of the data supplied in the database the contractor shall field verify the vertical and horizontal dimensions of the pipe Documentation of the pipe data shall be presented as detailed in section If, during the inspection operation, an inspection cannot be completed due to pipe blockages/obstructions/surcharging, the Contractor shall attempt to complete the inspection from the opposite manhole If conflicts between NBC s records/database and actual field conditions are encountered in the field, additional line segments with temporary unit identification numbers may need to be input into the database in the field in order to simulate actual field conditions. In this event, additional CCTV inspections may be required for the area in question. Any additional payments pertaining to this work will be at the agreed upon contract unit price per foot of CCTV work. The contractor shall notify and obtain approval by an authorized NBC employee prior to performing any work beyond the scope of the original contract The Contractor shall provide lighting during the CCTV inspection that fully illuminates, but does not overly illuminate the entire pipe The operator shall insure the camera and video display correctly reflect the true colors within the pipe and on the video display Flow Control: No flow control devices will be permitted. Flow level may be allowed up to but not more 25% during inspections. Where practical, the TV inspection will be conducted in a manner that provides an unobstructed view of the entire pipe. If inspections cannot be completed with appropriate flow levels, the inspection may be abandoned, as dictated in NASSCOS s PACP guidelines. In all cases of flow levels interrupting the camera view, inspections must be attempted from the upstream and downstream access points. NBC shall be provided with the video footage of the flow conditions during these inspection attempts. This item shall be paid based upon actual footage inspected. CCTV inspections shall be made during normal business hours. Exceptions may be granted to accommodate CCTV inspections with flow level disturbances. The Contractor may request to inspect pipe sections during the low flow period or during off-hours if flows conditions exceed allowable limits. No payment 2/6/20152/4/2015 Page CCTV-4

5 adjustments will be made for any work done off-hours. Inspections that fall outside normal business hours must be pre-approved at least three business days prior to the intended work. 3.2 Documentation of Inspection The Contractor must use PACP compliant software package for documenting the inspection Documentation of operator PACP certification shall be provided to the NBC Data Archive: All inspection records shall be retained by the Contractor for a minimum period of 5 years and will be made accessible by the NBC with no additional charge during this time period Digital Photographs: All defects shall be documented as digital picture files Video Recordings: The purpose of video recording shall be to supply a visual and audio record of problem areas of the lines that may be replayed. Video recordings shall include an audio track recorded by the inspector during the actual inspection work describing the parameters of the line being inspected (i.e. Manhole ID to Manhole ID, date and time, location, depth, diameter, material), as well as describing connections (service, building, storm, etc.), defects and unusual conditions and other discernible features. Video recording playback shall be at the same speed that it was recorded. Slow motion or stop-motion playback features may be supplied at the option of the Contractor. The use of the zoom feature during recordings shall be utilized only when necessary so as to properly reflect the actual position of the camera during inspections. Once recorded, the videos shall become the property of the NBC. No less than 90% of the portable hard drive capacity shall be filled. The inspection information shall note all distinguishable defects, and all other pertinent information, (infiltration/inflow quantification, roots, footages, jpegs, subsystem and manhole segment, etc.) Upon request from the NBC, interim data on a portable hard disk drive shall be submitted throughout the course of the contract for the purpose of quality control viewing and acceptance The digital video and inspection data files shall be indexed to the viewing software provided by the Contractor Permanent hard drive labels are required as detailed below. 2/6/20152/4/2015 Page CCTV-5

6 Contract Title: Contract No.: Company Info: Hard Drive No.: Date: 3.3 Digital Format Video Recordings The Contractor shall capture the inspections in digital format in color from the live video source on an external hard drive to the following requirements: i. MPEG format. ii. Picture Size: NTSC 352 x frames per second iii. Data/Bit Rate: 1.5 M-bits/sec Obtain digital video inspections from first generation recordings using video capture equipment capable of capture with no frame loss. 3.4 Coordination with Others: The Contractor shall be responsible for coordinating any efforts with local authorities, as necessary. The Contractor shall be responsible for all payments imposed by local authorities for any services provided, except as indicated in the Attachment 5: Specification for Traffic Control If applicable, the Contractor shall be responsible for coordinating any efforts with Amtrak, Providence & Worcester railroads, or any other utility company or municipality regarding access to right-of-ways. The Contractor shall pay all costs associated with this work. 4.0 Measurement 4.1 Basis of Payment: Pipe segments for CCTV Inspection shall be measured from center of manhole to center of manhole. END OF SECTION 2/6/20152/4/2015 Page CCTV-6

Section 2651 Television Inspection

Section 2651 Television Inspection Section 2651 Television Inspection PART 1: General 1.1 Description Provide all labor, materials, tools, equipment and incidentals as shown, specified, and required to perform television (TV) inspection

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing CCTV INSPECTION OF SEWER LINES PART 1 GENERAL 1.1 SECTION INCLUDES A. CCTV Inspections 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02731 Sanitary Gravity Sewer Line Testing

More information

CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) 1. Scope of Work SS7-1

CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) 1. Scope of Work SS7-1 CORPORATION OF THE CITY OF BURLINGTON SPECIFICATION INDEX FOR CCTV VIDEO INSPECTION OF PROPOSED STORM SEWERS (SPEC. NO. SS7) INDEX PAGE 1. Scope of Work SS7-1 2. Contractor Certification SS7-1 3. Flushing

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan

Section 4 Pipe and Maintenance Hole Inspection and Condition Assessment Plan and Condition Assessment Plan 4.1 Introduction 4.1.1 Purpose This addresses the requirements of Section IV.A. of the EPA Order. The plan documents the progress that each agency has made to date regarding

More information

Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT)

Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT) Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT) Utilizing CCTV equipment, equipment use training, NASSCO PACP defect coding, and infrastructure program management software

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

ITEM 40 NEW SEWER VIDEO RECORDING AND INSPECTION

ITEM 40 NEW SEWER VIDEO RECORDING AND INSPECTION ITEM 40 NEW SEWER VIDEO RECORDING AND INSPECTION DESCRIPTION OF WORK (Sec. 40.01) A. Scope of Work. The Contractor shall provide all labor, materials, and equipment necessary to perform an internal closed

More information

Presented By: Justin Cira MTech Company. Your future, Condition Assessment and Sewer Asset Management tool

Presented By: Justin Cira MTech Company. Your future, Condition Assessment and Sewer Asset Management tool Presented By: Justin Cira MTech Company Your future, Condition Assessment and Sewer Asset Management tool Digital Side Scanning Camera Digital Side Scanning WhaT is it? New generation of HD High Definition

More information

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk

ALL YOUR DRAINAGE NEEDS. Tel: 01384 482228 www.midlanddrainage.co.uk ALL YOUR NEEDS Tel: 01384 482228 www.midlanddrainage.co.uk Welcome to Midland Drainage Services Midland Drainage Services is a family owned and operated Drainage Company, based in the West Midlands and

More information

www.pawsd.org Pagosa springs, Colorado 81157

www.pawsd.org Pagosa springs, Colorado 81157 Michael Church, President/Chairman Glenn Walsh, Vice President Gordon Mclver, Secretary Paul HansEn, Treasurer Blake Brueckner SCOPE OF WORK Pagosa Water and Sanitation District (PAWSD) is a quasi-municipal

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

STANDARD OPERATING INSTRUCTION SOI-GVW-198 CCTV Inspection of Sewerage Reticulation Works 1 PURPOSE 2 REFERENCES 3 DEFINITIONS

STANDARD OPERATING INSTRUCTION SOI-GVW-198 CCTV Inspection of Sewerage Reticulation Works 1 PURPOSE 2 REFERENCES 3 DEFINITIONS 1 PURPOSE The purpose of this SOI is to provide instruction and guidance for closed circuit television survey (CCTV) inspection, which the Corporation requires to be undertaken by the constructor as part

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

City of Ridgecrest. Wastewater Treatment Facility Request for Proposal Sewer Collection System Condition Assessment

City of Ridgecrest. Wastewater Treatment Facility Request for Proposal Sewer Collection System Condition Assessment City of Ridgecrest Wastewater Treatment Facility Request for Proposal Sewer Collection System Condition Assessment Proposals Due: Wednesday March 19, 2014 2:00 pm City of Ridgecrest Wastewater Treatment

More information

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 25.1 GENERAL This section of the specifications shall form a part of the contract documents and should be read in conjunction with

More information

SPECIAL PROVISIONS - SUPPLEMENTARY CLOSED CIRCUIT TELEVISION (CCTV) SEWER INSPECTION STANDARD

SPECIAL PROVISIONS - SUPPLEMENTARY CLOSED CIRCUIT TELEVISION (CCTV) SEWER INSPECTION STANDARD SPECIAL PROVISIONS - SUPPLEMENTARY CLOSED CIRCUIT TELEVISION (CCTV) SEWER INSPECTION STANDARD Date: August 2008 Revised: February 2013 SECTION TABLE OF CONTENTS PAGE 1.0 INTRODUCTION... 1 2.0 GENERAL SURVEY

More information

VERIFICATION TESTING GUIDELINES FOR CONTRACTORS

VERIFICATION TESTING GUIDELINES FOR CONTRACTORS Public Works Department Engineering Division VERIFICATION TESTING GUIDELINES FOR CONTRACTORS CITY OF BERKELEY PRIVATE SEWER LATERAL ORDINANCE BMC Chapter 17.24 Effective November 3, 2014 A consent decree

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area. 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High

More information

Sewer System Inspection: Techniques and Resources. Presented by: Doug Severson

Sewer System Inspection: Techniques and Resources. Presented by: Doug Severson Sewer System Inspection: Techniques and Resources Presented by: Doug Severson Sewer Inspection Why should you inspect a sewer system? Preserve critical assets Confirm system integrity Peace of mind Disaster

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets

Utilizing Remaining Useful Life for Asset Management of Critical Wastewater Assets *Jessica Brown, P.E., Freese and Nichols, Inc., (817) 312-6980; Jessica.Brown@freese.com Mazen Kawasmi, Freese and Nichols, Inc. ABSTRACT The City of Fort Worth s wastewater collection system includes

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

ESRI CONFERENCE, JULY 2014, SAN DIEGO

ESRI CONFERENCE, JULY 2014, SAN DIEGO QUEBEC 'S CITY EFFICIENT DATA MAN OF THE SEWER SYSTEMS and its global approach to data m of municipal infrastructure asse ESRI CONFERENCE, JULY 2014, SAN DIEGO QUEBEC CITY 'SEFFICIENT DATA MANAGE THE SEWER

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE 1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint

More information

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe. SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price

More information

4 Steps for Quality Sewer Performance in Perpetuity

4 Steps for Quality Sewer Performance in Perpetuity 4 Steps for Quality Sewer Performance in Perpetuity By Gerhard Gerry P. Muenchmeyer, P. E. Principal Muenchmeyer Associates, LLC E-mail gerry@muenchmeyerassoc.com INTRODUCTION A well maintained and functional

More information

VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013

VIDEO INSPECTION AND LASER PROFILING IN FLORIDA. AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 VIDEO INSPECTION AND LASER PROFILING IN FLORIDA AASHTO SOC Conference Larry Ritchie, FDOT August 14, 2013 PIPE INSPECTION Over the last 5 years, the Department has spent approximately 175 million dollars

More information

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

SECTION 724 PIPE CULVERTS

SECTION 724 PIPE CULVERTS SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate

More information

UNDERGROUND INFRASTRUCTURE SPECIALISTS TABLE OF CONTENTS

UNDERGROUND INFRASTRUCTURE SPECIALISTS TABLE OF CONTENTS U UNDERGROUND INFRASTRUCTURE SPECIALISTS TABLE OF CONTENTS 3. COMPANY PROFILE A growing company excelling in the fields of infrastructure repair and maintenance. 6. MANDREL TESTING Individually approved

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology

Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology 2007 Pumper & Cleaner Environmental Expo International Wednesday February 7, 2007 Mainline Pipe Rehabilitation Using Cured-in-Place Pipe (CIPP) & Folded Pipe Technology What is Cured-In-Place Pipe (CIPP)

More information

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS PURPOSE AND SCOPE This document provides information and sets forth standards for sewer lateral closed

More information

Integrate CCTV data to enterprise GIS work flows. Otay Water District

Integrate CCTV data to enterprise GIS work flows. Otay Water District Integrate CCTV data to enterprise GIS work flows Otay Water District Introduction Background of Otay Water District GIS at Otay CCTV for Sewer Collection System Integrate CCTV and Inspection data with

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY

PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY PROVIDING THE SAFE CHOICE FOR UNDERGROUND PIPE RENEWAL, INTEGRITY MANAGEMENT AND ASSET RELIABILITY Cured-In-Place Pipe Pressure & Gravity Lines Pipe Splitting Trenchless Pipe Replacement EcoCast Advanced

More information

Sewer Line Rehabilitation

Sewer Line Rehabilitation 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing sanitary sewers using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers

Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers Guidelines for closed circuit television (CCTV) inspection of newly constructed sewers These guidelines outline inspection, reporting and acceptance requirements for newly constructed rigid and flexible

More information

SMOKE TESTING PERFORMANCE SPECIFICATION GUIDELINE FOR SANITARY SEWER. December, 2010

SMOKE TESTING PERFORMANCE SPECIFICATION GUIDELINE FOR SANITARY SEWER. December, 2010 SMOKE TESTING PERFORMANCE SPECIFICATION GUIDELINE FOR SANITARY SEWER December, 2010 Thanks to the following participants for the development of this document: Bryan Ballard - Tetra Tech Paul R. Casey -

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

Info What? Using InfoMaster to Develop a Rehabilitation and Replacement Plan

Info What? Using InfoMaster to Develop a Rehabilitation and Replacement Plan Info What? Using InfoMaster to Develop a Rehabilitation and Replacement Plan Amanda Lei - City of San Jose Alex Palmatier - HDR 2014 HDR, Inc., all rights reserved. Background Forecasting and Budget Data

More information

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines: Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections

More information

Phased Assessment Strategy for Sewers

Phased Assessment Strategy for Sewers Phased Assessment Strategy for Sewers A plan for understanding sewer system condition quicker, with fewer resources. Venay Sehgal Bhatia Digital Marketing Manager Envirosight Are deteriorating infrastructure

More information

Manhole Assessment. Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP)

Manhole Assessment. Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP) Manhole Assessment Pipeline Assessment and Certification Program (PACP) & Manhole Assessment Certification Program (MACP) Ted DeBoda, PE NASSCO Executive Director Outline NASSCO Defects and Observations

More information

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

1.3.2 Method of construction and restoration of existing water service connections. This shall include: 1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

SECTION 01 78 29 AS-BUILT DOCUMENTATION

SECTION 01 78 29 AS-BUILT DOCUMENTATION SECTION 01 78 29 AS-BUILT DOCUMENTATION PART 1: GENERAL 1.01 AS-BUILTS Where identified as a product of the Work, provide as-built drawings adhering to the criteria provided here and in the special conditions.

More information

SEWER LINE CLEANING, DEBRIS AND GREASE REMOVAL, DEBRIS AND GREASE DISPOSAL

SEWER LINE CLEANING, DEBRIS AND GREASE REMOVAL, DEBRIS AND GREASE DISPOSAL SEWER LINE CLEANING, DEBRIS AND GREASE REMOVAL, DEBRIS AND GREASE DISPOSAL This contract shall consist of cleaning, debris and grease disposal, of 7048 (+/-) feet of sewer pipe in accordance with the bid

More information

Gas Line And Sewer Crossbores. Danny Hixon & Jeff Griffiths 513-410-3301 757-353-1521

Gas Line And Sewer Crossbores. Danny Hixon & Jeff Griffiths 513-410-3301 757-353-1521 Gas Line And Sewer Crossbores Danny Hixon & Jeff Griffiths 513-410-3301 757-353-1521 GOAL OF HYDROMAX USA Hydromax USA is a Professional Services company that provides accurate and easily interpreted data,

More information

Policy Guidance Notes and Requirements

Policy Guidance Notes and Requirements Policy Guidance Notes and Requirements Building over/close to Public Sewers Domestic Extensions and Garages 1.0 Introduction Householders and developers planning to build close to or over a public sewer

More information

CDVS-7000 Series Remote Software Users Guide

CDVS-7000 Series Remote Software Users Guide CDVS-7000 Series Remote Software Users Guide Crest Electronics, Inc. Version 12.1005 Remote Surveillance Program The remote surveillance program enables users of the Crest 7000 series DVRs to connect remotely

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

WEAT Collections Conference January 22, 2014 NASSCO PACP/MACP/LACP- The Trainer s Perspective. Gerald Boman NASSCO PACP/MACP/LACP Certified Trainer

WEAT Collections Conference January 22, 2014 NASSCO PACP/MACP/LACP- The Trainer s Perspective. Gerald Boman NASSCO PACP/MACP/LACP Certified Trainer WEAT Collections Conference January 22, 2014 NASSCO PACP/MACP/LACP- The Trainer s Perspective Gerald Boman NASSCO PACP/MACP/LACP Certified Trainer What is NASSCO? National Association of Sewer Service

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

CHAPTER IV SPECIAL REGULATIONS - GAS UTILITIES ONLY. Records. Each gas utility shall maintain and keep the following records:

CHAPTER IV SPECIAL REGULATIONS - GAS UTILITIES ONLY. Records. Each gas utility shall maintain and keep the following records: CHAPTER IV SPECIAL REGULATIONS - GAS UTILITIES ONLY Section 401. Records. Each gas utility shall maintain and keep the following records: (a) Monthly record of the heating value of gas produced or purchased

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Functional Requirements of the Software

Functional Requirements of the Software Generic CCTV software Specifications for Granite XP Asset Management & Decision Support Software as provided by CUES Functional Requirements of the Software a. The inspection software shall fully support

More information

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade

More information

We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year

We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year We love the drains you hate! A partner you can depend on to deliver dedicated drainage maintenance services, 24 hours a day, 365 days a year Reactive CCTV Surveys Lining & Patch Reactive London Drainage

More information

See Appendix A for additional information, or contact ASTM directly.

See Appendix A for additional information, or contact ASTM directly. DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Sample specifications for an effective Flow Monitoring Services RFP

Sample specifications for an effective Flow Monitoring Services RFP Sample specifications for an effective Flow Monitoring Services RFP Red copy indicates areas requiring specific input Each specification is numbered for quick identification 1. Project Specifications 1.1.

More information

{ { { Meeting Date 08/03/10. City of Largo Agenda Item 24. Leland Dicus, P.E., City Engineer

{ { { Meeting Date 08/03/10. City of Largo Agenda Item 24. Leland Dicus, P.E., City Engineer City of Largo Agenda Item 24 Form Revision Date: 10/19/09: Meeting Date 08/03/10 Presenter: Leland Dicus, P.E., City Engineer Department: CD Community Development TITLE: GIS PROGRAM UPDATE The implementation

More information

SAFETY AND HEALTH PROGRAM

SAFETY AND HEALTH PROGRAM PROGRAM NUMBER NO. PAGES 05-005 10 REVISION ISSUE DATE Revision 2 11/1/2005 SAFETY AND HEALTH PROGRAM Confined Space Entry 1.0 INTRODUCTION Confined Space Entry is a serious workplace hazard, capable of

More information

REPAIRS TO DAMAGED SEWERS

REPAIRS TO DAMAGED SEWERS REPAIRS TO DAMAGED SEWERS A digout is the replacement of sewer or storm water pipes that are either broken or blocked due to tree roots, ground movement or ageing of pipes. When the use of high-pressure

More information

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials

More information

CITY OF PINOLE SEWER LATERAL ADMINISTRATIVE GUIDELINES

CITY OF PINOLE SEWER LATERAL ADMINISTRATIVE GUIDELINES CITY OF PINOLE SEWER LATERAL ADMINISTRATIVE GUIDELINES Adopted by Resolution No. 2012-132 Dated December 18, 2012 1 TABLE OF CONTENTS PURPOSE... 3 I. WHEN INSPECTION IS REQUIRED (PMC 13.20.050, 13.20.060,

More information

UVDB empowered by Achilles

UVDB empowered by Achilles UVDB empowered by Achilles DISAB Centurion: High Performance Wet/Dry Materials Handling Unit DISAB Centurion: High performance vacuum tanker that will vacuum dry or wet material The DISAB can vacuum material

More information

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542 1.0 INTENT REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES 1.01 It is the intent of this specification to provide for the reconstruction of pipelines and conduits by the installation of a resin-impregnated

More information

GIS Applications for Regulatory Compliance

GIS Applications for Regulatory Compliance 4 GIS Applications for Regulatory Compliance Uzair (Sam) M. Shamsi Many cities in the world especially in the United States and Canada are dealing with regulatory enforcement actions for sewer overflows,

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

Dhaka Water Supply and Sewerage Authority. Financial and Capacity Building Consultancy of Dhaka Water Supply Sector Development Project.

Dhaka Water Supply and Sewerage Authority. Financial and Capacity Building Consultancy of Dhaka Water Supply Sector Development Project. Draft Dhaka Water Supply and Sewerage Authority of Volume 4 Sewer Cleaning May 2010 Schedule of maintenance activities are to assist the maintenance personnel of Dhaka WASA to conduct maintenance programs

More information

PIPE VIDEO INSPECTION SERVICES (FY10)

PIPE VIDEO INSPECTION SERVICES (FY10) REQUEST FOR PROPOSALS 2009-4 FOR CITY OF CHARLOTTE PIPE VIDEO INSPECTION SERVICES (FY10) Advertise Date: April 30, 2009 The City of Charlotte (City) plans to contract with one firm to provide pipe video

More information

APPENDIX D. (Standard Notes and Signature Blocks)

APPENDIX D. (Standard Notes and Signature Blocks) APPENDIX D (Standard Notes and Signature Blocks) Use this note on all construction plans in Raleigh: ATTENTION CONTRACTORS The Construction Contractor responsible for the extension of water, sewer, and/or

More information

CONFINED SPACE ENTRY NON-MARINE FACILITES

CONFINED SPACE ENTRY NON-MARINE FACILITES CONFINED SPACE SAFETY CONFINED SPACE ENTRY NON-MARINE FACILITES EM-385 Chapter 34 CONFINED SPACE ENTRY NON- MARINE FACILITIES UFGS 013526 OSHA 29 CFR 1910.146 A space that: What is a Confined Space? Is

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES 1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other

More information

INSTALLATION OF INSITUFORM LINER

INSTALLATION OF INSITUFORM LINER PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation

More information

Using Frequent Sewer Inspection to Prioritize Asset Management. May 1, 2014. John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E.

Using Frequent Sewer Inspection to Prioritize Asset Management. May 1, 2014. John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E. Using Frequent Sewer Inspection to Prioritize Asset Management May 1, 2014 John Schroeder, P.E., BCEE Drew Richards, EI Tim Fallara, P.E. Agenda Rationale and Goals for Sewer Re-inspection How and why

More information

Beechmont Park Project

Beechmont Park Project Beechmont Park Project Foundation Drain Project Why pre -1972 homes are chosen in your neighborhood? Results of pilot study in your area showed the majority of homes built prior to 1972 within your neighborhood

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049

Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 Condition Assessment of Underground Pipes April 2015 With excerpts from: Condition Assessment of Wastewater Collection Systems, EPA/600/R-09/049 EPA New England Water Infrastructure Outreach provides tools,

More information