The To Complete Performance Index
|
|
|
- Loren George
- 10 years ago
- Views:
Transcription
1 The To Complete Performance Index transforming project performance Walt Lipke 1.1 PMI - Oklahoma City Chapter [email protected] Index TCPI vs CPI TCPI CPI Threshold Fraction Complete
2 Abstract The To Complete Performance Index (TCPI) from Earned Value Management describes the performance efficiency required to achieve a cost objective. Beyond its usual application, the TCPI indicator has a significant role in transforming project performance to effect a project recovery. This virtually unknown aspect is the focus of this presentation. 2
3 Overview Introduction Evaluation of EAC Further Examination Application to Project Recovery Evaluating the Recovery Strategy Schedule Analysis Summary & Conclusions 3
4 Introduction EVM provides a method of describing project performance numerically a significant improvement for assessing & reporting project status The most often used and best understood indicator from EVM is the Cost Performance Index, CPI = EV / AC CPI is a description of the efficiency of achieving the accomplishment with respect to the cost investment made 4
5 Introduction Whereas CPI describes the past, TCPI provides information about the future TCPI is defined as the work remaining to be accomplished divided by the amount of unspent funding TCPI = (BAC EV)/(TC AC) where TC = Target Cost or Desired Cost Outcome What does TCPI tell us? The index value describes the cost performance efficiency required for the remainder of the project to achieve the desired final cost 5
6 Evaluation of EAC Traditionally, TCPI is used by customers or oversight organizations to assess the reasonableness of an estimated final cost or Estimate at Completion (EAC) For this application, TCPI = (BAC EV) / (EAC AC) The customer evaluates the EAC provided by the PM from the value of the TCPI computed 6
7 Evaluation of EAC TCPI Value Predicted Outcome Achievable > 1.10 Not Achievable 7
8 Evaluation of EAC When TCPI is equal to or less than 1.00, there is confidence that the EAC can be achieved Conversely, when TCPI is equal to or greater than 1.10 the project is considered to be out of control; the EAC is very likely unachievable Between the two declarative values, 1.00 and 1.10, the PM s actions become ever more critical to project success. Management intervention to improve cost performance very probably will be required to achieve the EAC 8
9 Evaluation of EAC TCPI vs CPI TCPI CPI Threshold Index Exceed TCPI CPI = Fraction Complete 9
10 Evaluation of EAC The planned final cost (BAC) will not be achieved if this performance, CPI = 0.850, continues TCPI continually increases as the project progresses, exceeding the threshold value of 1.10 at fraction complete of approximately 0.35 The rate of TCPI increase becomes ever larger as fraction complete increases. 10
11 Further Examination What is the evidence that when TCPI > 1.10, the project is irrecoverable? As far as I know, there have not been any empirical or theoretical studies to validate the claim. In the next few slides, we ll look at the behavior of TCPI in more detail and state my opinion 11
12 Further Examination A revealing view can be obtained using calculus from TCPI in a different form: TCPI = (1 EV%)/(CR CPI -1 EV%) where CR (Cost Ratio) = TC / BAC EV% = EV / BAC For notation simplicity: y = TCPI, x = EV%, a = CR, b = CPI -1 The equation to examine becomes: y = (1 x)/(a bx) 12
13 Further Examination As an example, let us analyze a project having cost performance which will not achieve the cost objective: CPI -1 = , CR= The point of interest is when TCPI equals the threshold value (1.10) x = (ya 1)/(yb -1) = (( ) 1)/(( ) -1) =
14 Further Examination What is the rate of increase of TCPI at the threshold value (1.10)? TCPI rate of increase with respect to fraction complete can be examined using the first calculus derivative: dy/dx = (b a)/(a bx) 2 At the point of interest (TCPI = 1.10), the derivative can be evaluated: dy/dx = ( )/(1.11)/(1 1 ( )) 2 = (0.1)/( ) 2 =
15 Further Examination What happens to the rate of increase of TCPI when performance continues and fraction complete increases? EV% dy/dx
16 Further Examination For modest increases in EV%, it is seen from the numbers in the table that dy/dx (i.e. the TCPI rate) has larger and larger rates of change Once the threshold is exceeded, there is little hope that management intervention can have positive impact the project is very rapidly becoming out of control Thus, the threshold value of for TCPI appears to be a reasonable criterion for making the assertion that the EAC put forth by the PM in the project status report is unachievable 16
17 Application to Project Recovery PMs applying EVM possess early warning tools Forecast of final cost, IEAC = BAC / CPI As an example, let s examine a project using the following data: CPI = 0.850, BAC = $1000, MR = $100 What is projected for the future? If CPI does not improve, BAC will be exceeded IEAC = 1000 / = $1176 MR will be consumed, IEAC > TAB The project is headed for a budget overrun 17
18 Application to Project Recovery What is the PM s prerogative when the project is 80 percent complete? By calculating TCPI using TAB as the desired final cost and graphing it as shown previously, the answer is readily seen As observed in the next slide, the value of TCPI is so large it is nearly off the chart; the computed value is
19 Application to Project Recovery TCPI vs CPI TCPI CPI Threshold Index TCPI = CPI = Fraction Complete 19
20 Application to Project Recovery From our previous discussion, the PM knows that when TCPI 1.10 the project is regarded as irrecoverable and that additional funding is very likely needed In this instance, as uncomfortable as it may be, negotiation with the customer cannot be avoided Does the PM make the same decision when the project is 30 percent complete? 20
21 Application to Project Recovery The simple answer is No At 30 percent complete, TCPI = 0.937, a good number, yet the PM knows from IEAC that if the current performance does not improve the project will overrun the funding available (TAB) However, with this value for TCPI, the PM has an opportunity to take action thereby avoiding the overrun and the embarrassment of the impending negotiation if the present cost performance continues 21
22 Application to Project Recovery What is the period of opportunity for the PM to make a positive performance change? The PM has from the present status point until TCPI exceeds 1.10 to recover the project Is the period of opportunity sufficient for recovery to be successful? For our example, let s look at the graph 22
23 Application to Project Recovery TCPI vs CPI TCPI CPI Threshold Index TCPI = 0.30 TCPI > 0.72 ΔEV% = Fraction Complete 23
24 Application to Project Recovery For a project of reasonable size, having more than 40 percent of the period of performance to create and make an effective change, the PM has a very good chance for being successful with the recovery action 24
25 Evaluating the Recovery Strategy The TCPI has application, as well, in creating a viable recovery strategy a trade-off between cost and schedule performance to achieve the commitments to the customer (TAB & negotiated product delivery date) To resolve the condition of unsatisfactory cost performance, the PM creates a plan for transforming the cost performance from the present value of CPIa (actual value) to an improved efficiency, CPIs (strategy value) 25
26 Evaluating the Recovery Strategy TCPI plays a role in evaluating whether the change desired can realistically be achieved. For this purpose, the following formula for TCPI is used: TCPI = (1 EV%) / (CPIs -1 CPIa -1 EV%) As a rule of thumb, the envisioned performance change has a good likelihood of being achievable when the calculated value for TCPI is less than or equal to 1.00 indicating whether there is sufficient opportunity for the improvement to succeed 26
27 Schedule Analysis The To Complete Schedule Performance Index (TSPI) facilitates analysis similar to the TCPI TSPI is equal to the planned duration for the work remaining divided by the duration available: TSPI = (PD ES) / (TD AT) 27 where PD is the planned duration ES is the Earned Schedule TD is the total duration desired generally: PD, the negotiated duration (ND), or estimated duration (ED) AT is the actual time or duration at the time of computation
28 Schedule Analysis The use of TSPI is available for schedule management and control in a parallel manner to cost and TCPI Is the project schedule recoverable? What is the period of opportunity for the PM to make a positive schedule performance change? Is the period of opportunity sufficient for schedule recovery to be successful? Both TCPI & TSPI are needed to have complete capability for the cost schedule performance trade-off necessary for project recovery 28
29 Summary TCPI is definitely more than the simple calculation for determining the performance rate needed for the remaining work TCPI has application in evaluating the realism of the bottom up derived EAC it was shown that the value of 1.10 is a reasonable criterion for determining when a project is not recoverable and is out of control 29
30 Summary Use of TCPI was extended to the evaluation of the opportunity and the performance transformation envisioned for project recovery TCPI may also be used in creating the tactical changes of personnel and overtime adjustments Through Earned Schedule the methods described for TCPI are made applicable to schedule analysis, as well TCPI & TSPI have much to offer to the PM in his/her efforts for controlling and managing the project 30
31 References The To Complete Performance Index an expanded view, The Measurable News, 2009 Issue 2: [W. Lipke] Project Recovery It Can Be Done, CrossTalk, January 2002: [W. Lipke] Practice Standard for Earned Value Management. Newtown Square, PA: Project Management Institute Earned Schedule website: com 31
Earned Schedule application to Project Management
Earned Schedule application to Project Management Walt Lipke PMI - Oklahoma City +1 405 364 1594 [email protected] www.earnedschedule.com $$ The ES idea is to determine the time at which the EV accrued
Earned Value Formulae
Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue
The Two Most Useful Earned Value Metrics: the CPI and the TCPI
PM WORLD TODAY SECOND EDITIONS JUNE 2009 Editor s note: Second Editions are papers that have been previously published that have continued relevance and deserve additional visibility. The paper below was
Since 1985, the Test Program Set (TPS) development
Applying Management Reserve to Software Project Management Walter H. Lipke Oklahoma City Air Logistics Center, Directorate of Aircraft Maintenance, Software Division Today s standard of practice for managing
Schedule Adherence. and Rework Walt Lipke, PMI Oklahoma City Chapter. PUBLISHER s CHOICE
Schedule Adherence and Rework Walt Lipke, PMI Oklahoma City Chapter Abstract. When project performance is such that the product is delivered with expected functionality at the time and price agreed between
700 Analysis and Reporting
Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how
Earned Schedule Leads to Improved Forecasting
Lipke, Walt Norman, Oklahoma, USA Earned Schedule Leads to Improved Forecasting Abstract For project cost, analysts can predict the final value with some confidence using the Independent Estimate at Completion
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques
IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 [email protected]
PROJECT MONITORING AND CONTROL USING BURNDOWN CHARTS
The 4 th edition of the Interdisciplinarity in Engineering International Conference Petru Maior University of Tîrgu Mureş, Romania, 2009 PROJECT MOITORIG AD COTROL USIG BURDOW CHARTS Attila Vajda Sysgenic
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT
EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT Assoc. Prof. Anca Mehedintu Ph. D University of Craiova Faculty of Economics and Business Administration Craiova, Romania Prof. Cerasela Pirvu
Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.
About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule
Project Duration Forecasting a comparison of Earned Value Management methods to Earned Schedule Walt Lipke Member of Oklahoma City Chapter Project Management Institute (USA) Abstract: Earned Value Management
Schedule Adherence a useful measure for project management
Schedule Adherence a useful measure for project management Walt Lipke PMI Oklahoma City Chapter Abstract: Earned Value Management (EVM) is a very good method of project management. However, EVM by itself
Project Cost Management
Project Cost Management Guide to Mathematical Questions PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Present
Project Cost Management
Project Cost Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points To Note Please
Project Control with ProTrack
Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS
Simple Earned Value (Using MS Project 2010)
Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained
Assessing Schedule Performance with Earned Value
FEATURED PAPER OCTOBER 2007 Time Is Up: Assessing Schedule Performance with Earned Value By Robert Van De Velde Time drives projects. Quick and accurate evaluation of schedule performance is crucial. Quantitative
Rules on using templates. MECH 896 Professional Development for MEng Students. Assignment #6A: Questions. Homework Discussion
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor ([email protected] and [email protected]) Rules on using templates 1) Must reference the template used 2) Use
Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1
Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control
Abstract. Earned Value Management Basics
Earned Schedule: A Breakthrough Extension to Earned Value Management Kym Henderson Education Director, Project Management Institute, Sydney Australia Chapter Abstract Earned Schedule (ES) analysis is a
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION
LEADING EDGE FORUM CSC PAPERS 2012 EARNED SCHEDULE: FROM EMERGING PRACTICE TO PRACTICAL APPLICATION Author Bill Mowery MPM, PMP Keywords Earned Value Management, Earned Schedule, Project Management, Cost
How To Manage A Project
Project Management Institute Practice Standard for EARNED VALUE MANAGEMENT Global Project Management Institute Practice Standard for Earned Value Management Practice Standard for Earned Value Management
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Brainstorm. What is Cost and Project Cost Management?
Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.
Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C07_01
PMP Test C07_01 01. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI. B. Multiply by SPI. C. Multiply by CPI. D. Divide by CPI. 02.
Using Earned Value Management for Improving Processes. By Cynthia K. West
Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.
A Gentle Introduction to Earned Value Management Systems
A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com
Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman
Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government
TIME FORECASTING USING EARNED SCHEDULE
TIME FORECASTING USING EARNED SCHEDULE THE EUROPEAN EXPERIENCE (WITH THE HELP OF THE US) By Ing. Stephan Vandevoorde Manager Airport Systems, CofelyFabricom Director, EVM Europe Agenda The Start The beginnings
Introduction to earn value management in Civil Engineering
3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )
Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:
Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting Prepared by: Module 6: Metrics, Performance Measurements and Forecasting Welcome to Module 6. The objective
Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP
Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:
IST 302 : Project Cost Management
IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects. Abstract. Introduction
Integration of Income Management and Cost Management: A Complementary for Financial Analysis of Projects Puian Masudifar, Deputy CEO, VIRA Consulting Engineers Fereydoun Fardad, Aryana Project Management
An introduction to Earned Value Analysis
An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:
Earned Value Management Tutorial Module 1: Introduction to Earned Value Management Prepared by: Module1: Introduction to Earned Value Welcome to Module 1. The objective of this module is to introduce you
L10: Budgeting and Cost Control. Olivier de Weck
ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen
CVR/IT Consulting LLC
2011 CVR/IT Consulting LLC All Rights Reserved 1 www.cvr-it.com [email protected] Overview Easy Earned Value CVR/IT Consulting LLC 2011 CVR/IT Consulting LLC All Rights Reserved 2 Introduction Earned Value
performance management system that is based on Earned Schedule Management.
The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created
Unit 5: Cost Management (PMBOK Guide, Chapter 7)
(PMBOK Guide, Chapter 7) The questions on this topic have historically been more difficult than average for some exam takers because of unfamiliarity with some of the math. You will be responsible for
Project Management Using Earned Value
Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No
EVM.01. Earned Value Analysis Why it Doesn't Work
EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects
Forecasting Project Schedule Completion by Using Earned Value Metrics
Forecasting Project Schedule Completion by Using Earned Value Metrics Ing. Stephan Vandevoorde Sr. Project Manager Fabricom Airport Systems [email protected] 1 Agenda Introduction Schedule performance indicators
Agile Project Management Controls
0 Agile Project Management Controls Issues with EVM and a Viable Alternative: Agile Project Management (PM) Tool ICEAA Conference, June 2015 San Diego, CA Blaze Smallwood, Booz Allen Hamilton Omar Mahmoud,
Earned Value Management Guidelines
Effective Date: April 21, 2009 Status: Revision 1 Supersedes: NA Document Owner: Director, Environmental and Engineering Program Introduction This paper provides guidance and recommendations for the application
A Guide to Managing Programs Using Predictive Measures
National Defense Industrial Association Integrated Program Management Division A Guide to Managing Programs Using Predictive Measures September 17, 2014 National Defense Industrial Association (NDIA) 2111
Pune, MH, India. 2 P.G. Student, Imperial College of Engineering & Research, Wagholi, Pune, MH, India. [email protected]
COST CONTROL AND TRACKING OF A BUILDING BY EARNED VALUE METHOD Dr. Arun Dhawale 1 Vaishnavi Tuljapurkar 2 1 Head of Department, Associate Professor, Department of Civil Engineering, Imperial College of
Project Cost Management
Project Cost Management Martin Pazderka [email protected] INSO - Industrial Software Institut für Rechnergestützte Automation Fakultät für Informatik Technische Universität Wien Agenda
Project Management Center
Project Management Center Overview - 1 - OMNITRACKER Project Management Center Application to support an efficient management of projects, from initiation until closure Planning and administration of projects
PMP 2013 Exam Prep. Course Overview
PMP 2013 Exam Prep Course Overview This course has been designed to prepare participants to take the Project Management Institute's Project Management Professional (PMP) Exam, 2013 edition and is based
Ź Ź ł ź Ź ś ź ł ź Ś ę ż ż ł ż ż Ż Ś ę Ż Ż ę ś ź ł Ź ł ł ż ż ź ż ż Ś ę ż ż Ź Ł Ż Ż Ą ż ż ę ź Ń Ź ś ł ź ż ł ś ź ź Ą ć ś ś Ź Ś ę ę ć ż Ź Ą Ń Ą ł ć ć ł ł ź ę Ś ę ś ę ł ś ć ź ś ł ś ł ł ł ł ć ć Ś ł ź Ś ł
Earned Value and Agile Reporting
Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,
PROJECTS SCHEDULING AND COST CONTROLS
Professional Development Day September 27th, 2014 PROJECTS SCHEDULING AND COST CONTROLS Why do we need to Control Time and Cost? Plans are nothing; Planning is everything. Dwight D. Eisenhower Back to
DCMA DCMA-EA PAM 200.1. October 2012
DCMA Earned Value Management System (EVMS) Program Analysis Pamphlet (PAP) DCMA-EA PAM 200.1 October 2012 THE DCMA ENGINEERING AND ANALYSIS EXECUTIVE DIRECTOR IS RESPONSIBLE FOR ISSUANCE AND MAINTENANCE
INSE 6230 Total Quality Project Management
Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost
Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes
Lecture Slides for Managing and Leading Software Projects Chapter 8: Measuring and Controlling Work Processes developed by Richard E. (Dick) Fairley, Ph.D. to accompany the tet Managing and Leading Software
Project Management: Tracking Progress and Earned Value with MS Project 2003
Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain
Managing Project Budgets with MS Project. Sonja Streuber, PMP, SSBB
Managing Project Budgets with MS Project Sonja Streuber, PMP, SSBB Sonja Streuber Project Mgmt & Engineering, Six Sigma, Risk Mgmt & Risk Analysis: 2000 2003 Agilent Technologies 2003 2009 Lockheed Martin
Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP
PMP Formulae & Tips Cheat Sheet P a g e Integration Management Develop Project Charter process Project Selection Methods (>> Benefit Measurement Methods >> Economic Models -7) Present Value (PV) FV The
earned value management
earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project
Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded?
Resource Loading: who and/or what needed where and when. Adjust MS Project default settings to meet the needs of your project. Loading Analysis is an iterative process. Where are you overloaded? Resource
Earned value method as a tool for project control
Budownictwo i Architektura 3 (2008) 15-32 Earned value method as a tool for project control Institute of Construction, Faculty of Civil and Sanitary Engineering, Lublin University of Technology, 20-618
Estimating Cost at Completion - Judgment & EV Information
Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number
A Framework for Project Metrics
A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics
Tracking Software Development Progress with Earned Value and Use Case Point
ISBN 978-952-5726-06-0 Proceedings of the 2009 International Workshop on Information Security and Application (IWISA 2009) Qingdao, China, November 21-22, 2009 Tracking Software Development Progress with
Project Cost Management - 2 Days
Project Cost Management - 2 Days Course Description: The Cost Management course addresses the identification, elaboration, planning, and management of the project budget. Including selected processes from
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Management, Sixth Edition Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project cost management Explain basic project cost management principles,
Algebra Practice Problems for Precalculus and Calculus
Algebra Practice Problems for Precalculus and Calculus Solve the following equations for the unknown x: 1. 5 = 7x 16 2. 2x 3 = 5 x 3. 4. 1 2 (x 3) + x = 17 + 3(4 x) 5 x = 2 x 3 Multiply the indicated polynomials
Tracking Budgets and Schedules
Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Training Seminars. Description. Core Courses: The core courses consist of the following:
Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals
GPMCEP GLOBAL PROJECT MANAGEMENT, LLC C O U R S E
C O U R S E C E GPMCEP GLOBAL PROJECT MANAGEMENT, LLC Project Management Professional (PMP) Certification Exam Prep Global Project Management, LLC is a Global Registered Education Provider (R.E.P.) of
Project Cost Management - 2 Days
Project Cost Management - 2 Days Course Description: The Cost Management course addresses the identification, elaboration, planning, and management of the project budget. Including selected processes from
PMP Exam Preparation Answer Key
Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.
COINS EVA Earned Value Analysis
COINS EVA Earned Value Analysis Nigel Cope July 2006 Earned Value Analysis The most widely used method for performance measurement of projects Combines scope, cost and schedule patterns Informs project
Chapter 5: Project Cost Management
Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource
Module 5 Cost Management PMP Exam Questions
Module 5 Cost Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc Question 1 A company, which provides professional
AACE International Recommended Practice No. 86R 14
AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment
Predicting progress on your project
www.nonsuch.co [email protected] Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant
PMI Lexicon of Project Management Terms
Project Management Institute PMI Lexicon of Project Management Terms Version 3.0 Published by: Project Management Institute, Inc. 14 Campus Boulevard Newtown Square, Pennsylvania 19073-3299 USA Phone:
What is the Health of my Project?
WHITE PAPER What is the Health of my Project? The Use and Benefits of Earned Value Table of Contents How s My Project Doing?...1 Need a Solution? Earned Value to the Rescue!...1 My actual costs are less
Chapter 7: Project Cost Management. Munawar [email protected]
Chapter 7: Project Cost Management Munawar [email protected] Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.
Brief Introduction to Earned Value Management (EVM)
Brief Introduction to Earned Value Management (EVM) 12/25/06 EVM Introduction 1 12/25/06 EVM Introduction 1 Outline Introduction to the basic rationale and elements of EVM Issues of actually implementing
Simulation Exercises to Reinforce the Foundations of Statistical Thinking in Online Classes
Simulation Exercises to Reinforce the Foundations of Statistical Thinking in Online Classes Simcha Pollack, Ph.D. St. John s University Tobin College of Business Queens, NY, 11439 [email protected]
plans based on actual cost, schedule and technical progress of work [1, 9].
An Analysis on Resource Planning, Estimation and Tracking of Project by Earned Value Management SHAIK MOHAMMAD MASOOD, DEVANAND.R, HARSHA H.N PG Student, Department of Civil Engineering, G.E.C, Hassan
What are the place values to the left of the decimal point and their associated powers of ten?
The verbal answers to all of the following questions should be memorized before completion of algebra. Answers that are not memorized will hinder your ability to succeed in geometry and algebra. (Everything
a 11 x 1 + a 12 x 2 + + a 1n x n = b 1 a 21 x 1 + a 22 x 2 + + a 2n x n = b 2.
Chapter 1 LINEAR EQUATIONS 1.1 Introduction to linear equations A linear equation in n unknowns x 1, x,, x n is an equation of the form a 1 x 1 + a x + + a n x n = b, where a 1, a,..., a n, b are given
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
DICK BRODKORB 714.235.1485 FAX ( ) 3 THEN CHECK THE LOCATION YOU LL BE ATTENDING.
Instructors VENUE INFORMATION PROJECT SCHEDULING & EVMS LAS VEGAS, NV August 23-27, 2010 The M Resort, Spa and Casino 12300 Las Vegas Blvd. South Henderson, NV 89044 (877) 673-7678 Group block expires:
Over Target Baseline and Over Target Schedule Guide
Over Target Baseline and Over Target Schedule Guide OUSD AT&L (PARCA) December 5, 2012 1 Table of Contents Section Page No. Introduction 4 Chapter 1. What is Formal Reprogramming? 5 1.1 Formal Reprogramming
Project Management Institute (PMBOK 2000) PMP Preparation Worksheet
Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning
Project Management Planning
Overview of Resource Planning Every organization has a limited number of resources to perform tasks. A project manager's primary role is to find a way to successfully execute a project within these resource
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Project Execution, Monitoring and Control (IS PM 8. Lecture; 2012 Spring)
Project Execution, Monitoring and Control Topics of the lecture as follows: PDCA cycle Project execution processes by PMBOK Project monitoring and controlling processes by PMBOK Project monitoring and
