Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth

Size: px
Start display at page:

Download "Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth"

Transcription

1 LHC - BOLD BEGINNING Mike Lamont Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth Lend thy fresh beams our lagging months to cheer LOOK WITH FAVOR UPON A BOLD BEGINNING Virgil

2 Reasonably good start

3 Even before the drawing-board stage, the farsighted John Adams noted in 1977 that the tunnel for a future large electron positron (LEP) collider should also be big enough to accommodate another ring of magnets. REALLY BOLD BEGINNINGS

4 Challenges Accepted High magnetic field 2-in-1 magnet design Superfluid helium (After some debate!) LEP isn t even installed yet but we re going to start work on an accelerator which needs: a magnet design we re not sure works; fields we can t yet produce; to be cooled by superfluid helium in 27 km tunnel deep underground.

5 1984 Since it is very difficult to handle more than one event per bunch crossing for experiments that can accept a higher <n>, luminosities of up to 1.5 x cm -2 s -1 could possibly be reached It took a very long time - 10 years - from this starting point for the project to be approved. During most of this time Giorgio Brianti led the LHC project study. However, we should not forget the enormous debt we owe to Carlo Rubbia in the second half of that decade for holding the community together behind the LHC against all the odds. Lyn Evans

6 Parameters through the years Giorgio Brianti

7 June 1994 first full scale prototype dipole June 2007 First sector cold ECFA-CERN workshop April 2008 Last dipole down 1994 project approved by council (1-in-2) SSC cancelled Some of us practiced on a 27 km warm version First set of twin 1 m prototypes Over 9 T 2002 String 2 Main contracts signed November delivered September 19, 2008

8 Courtesy Luca Bottura

9

10 Technology: beautiful, when well done! 25 March 2003 Lucio Rossi - Superc. Mag. 10

11

12 48 warm magnets have come from TRIUMF, Vancouver; 40 from the Institute for High Energy Physics in Protvino, near Moscow; and 65 from the Budker Institute of Nuclear Physics in Novosibirsk, Russia. Warm quadrupole magnets in IR3 and IR7 - challenging 2-in-1 design Significant international effort

13 Triplets Two separate designs: FNAL had a good field quality didn t initially reach the design gradient KEK reached the design gradient but had field quality issues Following the triplet construction was Tom Taylor and Ranko Ostojic. The upshot of the above challenges was the decision to mix the triplet magnets: KEK magnets at Q1 and Q3; FNAL magnets at Q2. Impact on the powering scheme of the triplet (both designs require different currents for the same gradient) key player here was Jean-Pierre Koutchouk.

14 Magnets++ Field quality tracking and adjustment Field quality vitally important for beam stability - good after adjustments and faithful to the tight specifications Sorting: not all magnets are created equal geometry - aperture b3 - dynamic aperture/resonance driving terms b1 closed orbit perturbations a2 coupling, vertical dispersion Magnetic measurement and modelling Characterize the important dynamic effects in anticipation of correction All important magnetic strength versus current calibration

15 Dipole Skew Dipole Quadrupole Skew Quadrupole Sextupole Skew Sextupole Octupole Skew Octupole Decapole Skew Decapole Quattuordecapole

16 b3 integral (units) 10 5 Firm 1 Firm 2 Firm 3 Collared coil 0-5 average upper limit for systematic lower limit for systematic -10 Xs1 Xs2 Xs Collared coil progressive number AT-MAS & MTM Plus: main field, magnetic length, quadrupole, octupole, decapole, skew quadupole, skew sextupole, skew octupole! Courtesy Ezio Todesco et al

17 QUALITY CONTROL Strong anomalies all along the magnet axis (-13 units of b2, -5 units of b3, 16 units of a2, 12 units of a3, 7 of a4, ). After decollaring, it has been found that a copper wedge of type 2 has been put at the place of the type 1 wedge (see Fig. 32). Courtesy Ezio Todesco et al

18 Magnet sorting - geometry Measured the curved aperture of dipoles: 3 classes: GOLD SILVER MID-CELL MQ MB MB MB MB MB MB G S SL G,S SL,SR MC G S SR MQ G S SL G,S SL,SR MC S. Fartoukh for the MEB G S SR MQ

19 Magnet sorting - b3 Very efficient flip-flop pairing: effective random b3 reduced by a factor 2-3, further improved by super-imposing p-pairing for the outliers in sectors78/81/34 Typical p-pairing + flip-flop Few Xs3 s Xs1 Noell magnets Sector 78: ap. V1 Courtesy Stephane Fartoukh

20 Magnet measurements and modeling 10 years of measurements, dedicated instrumentation R&D, 4.5 million coil rotations, 50 GB of magnetic field data, 3 Ph.D.s and a few Masters Theses on the subject, 2 years of data pruning and modeling, collaborations and participation in runs in Tevatron and RHIC today we have the most complex and comprehensive forecast system ever implemented in a superconducting accelerator Luca Bottura 2008 for the FIDEL team

21 CRYOGENICS

22 24 km of superconducting K 88 tons of superfluid helium at 1.9 K 8 x 4.5 K superconducting magnets Courtesy Serge Claudet

23 Cryogenic vacuum Good beam lifetime in a cryogenic system where heat input into the 1.9 K helium circuit must be minimized and where significant quantities of gas can be condensed on the vacuum chamber Constraints: heat input (beam screen); resistivity (copper layer); beam stability (impedance); Beam screen as seen by the beam BS cooling pipes Slots (3% surface) Cold Bore (2K)

24 Room temperature vacuum ~6 km of room temperature vacuum chambers Same requirements in terms of beam lifetime and stability as the cold sectors, but do not benefit from cryo-pumping. A new technology: sputtered non-evaporable getter, was developed for the LHC

25 Foreseen limitations At low energy the main limitation for the beam lifetime comes from the machine non-linearities, i.e. the magnetic field errors At collision energy the limiting effects are caused by the beam-beam interaction Head-on conservative approach based on previous experience long range interactions - limiting factor performance. Electron cloud only identified as a problem for the LHC in the late 90ies Pioneering work by Francesco Ruggiero & Frank Zimmermann

26 Optics and beam dynamics Major effort to optimize the optics: Which crossing scheme is preferred? What is the effect of triplet errors? Which is the preferred working point? What are the best integer tunes? Major simulation effort to study: Particle stability (dynamic aperture), beam instabilites Effect of triplet errors, head-on beam-beam, long-range beam-beam development of simulation tools (MAD and SIXTRACK) and the build up of computing resources (Frank Schmidt and Eric McIntosh) Specification of corrector circuits and strategy Jean-Pierre Koutchouck et al

27 Jacques Gareyte

28 Dynamic aperture In collisions, dynamic aperture largely constrained by the long range beam-beam effects and the field errors in the low beta triplets Phase-space plot simulated using a 2- dimensional model of the long-range beambeam force Y. Papaphilippou & F. Zimmermann

29 Long range encounters give rise to a well defined border of stability at the diffusive aperture Diffusion rate Particle amplitude Y. Papaphilippou & F. Zimmermann

30 POWERING TESTS INTERCONNECTION And then a miracle occurred QRL COOL DOWN

31 Alignment HLS linked by two hydraulic networks Beam through Alice and to the end of sector 23 first shot 8/8/2008

32 Preparation: beam tests through the years 2003:TT :TI8 CNGS 2005: FIRST HOLE TI2 2008: FIRST BEAM TO LHC 2008: FIRST BEAM TO IR3 2008: SEPT : FIRST IONS TO LHC 2009: Sector test 2009!

33 MAGNET CIRCUIT TESTS++ Transfer lines Injection, Extraction RF, injection sequence Timing System Beam Interlock System Collimators Vacuum Interlocks, SIS BLMs, BPMs BTV, BCT Beam dump Powering Groups of Circuits Magnet model Sequencer, alarms Controls, logging, DBs LSA, optics model, YASP Preparation: HWC and machine checkout RF frequency is nearly fixed. Just jump to the next bucket. This can only happen if the SPS is empty PSB VCO CPS Source Next SPS target bucket FREV bucket FREV Time difference to digital convertor SB-Frev jumps to the next LHC TB-Frev Jump SPS SBF Target bucket revolution frequency CPS Re-phase with beam ~20ms Target Bucket FREV + - LHC TBF Batch 1 CPS RF Reference frequency Jump LHC TBF SPS SBF Batch 2 Re-phase with beam ~50ms RF SPS SPS RF BA3 Rephase with beam: The time difference between the target bucket FREV and the source bucket FREV is measured by a TDC. The TDC value then changes the RF frequency so that they come in line. This takes time to complete, and disturbs the orbit. ABORT GAP Filling LHC Ring 1 R1 Bucket from telegram Target bucket revolution frequency In LHC RF SR4 Batch 3 Batch 4 Batch 5 Injection Kicker Batch 1 Batch 4 Out Kicker tail is to long to allow inserting batch 4 between batch 3 and batch 5 Batch number to Bucket number conversion Bucket = K + h/n h = RF Buckets n = 12 Batches K = 121 Approx (Offset) Re-phasing in the SPS: Batch 2 Batch 3

34 August 2008 First injection test November 29, 2009 Beam back August, e33, 2.6 fb bunches September 10, 2008 First beams around April 2010 Squeeze to 3.5 m October e bunches June bunches September 19, 2008 Disaster Accidental release of 600 MJ stored in one sector of LHC dipole magnets March 30, 2010 First collisions at 3.5 TeV November 2010 Ions

35 September 10 th, 2008 Bold or foolhardy? James Gillies & team: the creation of a global brand. IR7 IR3 IR6 First turn!

36

37 2009: besides massive repair and consolidation Understanding the problem Copper stabilizer issue identified Measurement campaign warm and cold Simulations Test set-up (FRESCA) Prevention Deployment of new Quench Protection System (design, prototyping, production, deployment, testing) Allows online measurement of the cold splice resistance on the nano-ohm level. Heroic effort from Knud, Reiner and team Caution Run at 3.5 TeV

38 2009: That which does not kill us Beam based systems Injectors & transfer lines Instrumentation: BPMs, BLMs Beam interlock System RF Collimators Controls & software Sequencer Injection sequencer Settings management Middleware Timing Software interlocks Magnet model On-line model Logging Dry runs, system tests and hardware commissioning (bis) RF frequency is nearly fixed. Just jump to the next bucket. This can only happen if the SPS is empty SB-Frev jumps to the next LHC TB-Frev Jump Jump LHC TBF LHC TBF SPS SBF SPS SBF Target Bucket FREV Target bucket revolution frequency Batch 1 SPS SPS RF BA3 ABORT GAP Filling LHC Ring 1 R1 Bucket from telegram Target bucket revolution frequency LHC RF SR4 Batch 1 Batch 2 Batch 3 CPS Batch 4 PSB VCO CPS Source Next SPS target bucket FREV bucket FREV Time difference to digital convertor Re-phase with beam ~20ms + - CPS RF Batch 2 Re-phase with beam ~50ms RF Rephase with beam: The time difference between the target Unprecedented state of readiness Reference frequency bucket FREV and the source bucket FREV is measured by a TDC. The TDC value then changes the RF frequency so that they come in line. This takes time to complete, and disturbs the orbit. In Batch 3 Batch 4 Batch 5 Injection Kicker Out Kicker tail is to long to allow inserting batch 4 between batch 3 and batch 5 Batch number to Bucket number conversion Bucket = K + h/n h = RF Buckets n = 12 Batches K = 121 Approx (Offset)

39 Early commissioning Marked by phenomenally swift deployment of tools to measure, correct, and verify: Optics, magnet model, polarities (!), aperture Fabulously fast turnaround on problem resolution Ramp, squeeze commissioning eased by availability of feedbacks Underpinned by instrumentation and software Experience meets youthful enthusiasm, talent, and stamina

40 Feb 27 Beam back March 30 First collisions 3.5 TeV June Commission nominal bunch intensity CONSOLIDATION November 4 Switch to lead ions February March April May June July August September October November April Commission squeeze September Crossing angles on October Luminosity production 2010

41 2010 integrated luminosity CONSOLIDATION COMMISSIONING and frantic debugging EXPLOITATION

42 Optics Optics stunningly stable and well corrected Two measurements of beating at 3.5 m 3 months apart Local and global correction at 1.5 m R. Tomas, G. Vanbavinckhove, M. Aiba, R. Calaga, R. Miyamoto

43 Reproducibility LHC magnetically reproducible with rigorous pre-cycling - set-up remains valid from month to month 7 e-3 Tune corrections made by feedback during squeeze Courtesy Stefano Redaelli

44 Nominal cycle 2011 Beam dump Squeeze Stable beams Collide Ramp down/precycle Ramp Ramp down Injection 35 mins ~30 mins Injection Ramp Squeeze 17 mins 8 mins Collide 1 mins Stable beams 0 30 hours Fastest turn around down from 3h40m in 2010 to 2h7m in 2011 after optimization

45 Transfer & injection 2011: 144 bunches of 1.4e11 ppb MJ IR8 Possibly the best studied, best optimized transfer lines in the history of accelerator physics Injection kicker Fast extraction kicker SPS 6911 m 450 GeV / 400 GeV Switching magnet CNGS Target Transfer line LHC Injection kicker IR2 Transfer line HiRadMat Fast extraction kicker 1 km

46 Injection Complex process wrestle with: Re-phasing, synchronization, transfer, capture Timing, injection sequencing, interlocks Injection Quality checks SPS and LHC Abort gap keeper Beam losses at injection, gap cleaning Full program of beam based checks performed Carefully positioning of collimators and other protection devices Aperture, kicker waveform Transfer line collimator SC magnets armed with beam loss monitors TCDD absorber TDI collimator 4 x KICKERS 5 x SEPTA

47 Ramp Power converters (all magnet circuits), magnet model, RF, collimators, beam dump, transverse damper, orbit and tune feedback, BLM thresholds etc. Reproducible and essentially without loss (after a lot of work) Ions this morning (after less than a week in the machine)

48 Current [A] Tracking between the three main circuits of sector Quadrupole Circuits (RQF, RQD) ppm Dipole Circuit (RB) 1000 Main bend power converters: tracking error between sector 12 0 & 23 in ramp to 1.1 TeV 19:00 19:30 20:00 20:30 21:00 21:30 Phenomenal performance from the power converters Courtesy Freddy Bordry & Dave Nisbet

49 Magnet model Knowledge of the magnetic machine is remarkable All magnet transfer functions, all harmonics including decay and snapback Tunes, momentum, optics remarkably close to the model Model based feed-forward reduces chromaticity swing Courtesy Luca Bottura & Ralph Steinhagen

50 Tune and orbit feedback Mandatory in ramp and squeeze Commissioning not without some issues but now fully operational Courtesy Ralph Steinhagen

51 RF Beam-induced voltage and load power dealing with over half nominal intensity RF feedback working as designed to cope with transient beam loading The broadband RF noise is reduced to a level that makes its contribution to beam diffusion in physics well below that of Intra Beam Scattering. Capture losses are also under control, at well below 0.5%. Longitudinal emittance blow-up operation needed for ramping of nominal bunch intensity 1.2 ns Courtesy Philippe Baudrenghien Bunch length in ramp with blow-up

52 Courtesy Andy Butterworth

53 Courtesy Andy Butterworth

54 Transverse position Transverse dampers Injection oscillations Working extremely well to damp the TCBI mode 0 Hump suppression Abort gap and injection gap cleaning Coherent instabilities Blow-up for loss maps Vital and working very well OFF ON Injection oscillations Turn number Courtesy Wolfgang Hofle & Daniel Valuch

55 Beam Instrumentation: brilliant the enabler Beam Position Monitors Beam loss monitors Base-Band-Tune (BBQ) Synchrotron light Longitudinal density monitor Wire scanner

56 Machine protection the challenge Beam 100 MJ Situation at 3.5 TeV (in August 2011) Not a single beam-induced quench at 3.5 TeV YET SC Coil: quench limit mj/cm 3 56 mm 11 magnet quench at 450 GeV injection kicker flash-over

57 Beam Interlock System Safe Beam Parameter Distribution Jaw Position Temperature Safe LHC Parameter Software Interlock System Operator Buttons CCC Vacuum System Screens and Mirrors beam observation RF System (f_rf + P) Access System Collimation System Special BLMs Safe Beam Flag Beam Interlock System Beam Dumping System Powering Interlocks superconducting magnets Magnet protection system (20000 channels) Powering Interlocks normal conducting magnets Magnets Power Converters ~1600 Power Converters AUG UPS Fast Magnet Current change Monitor Cryogenics some channels BPMs LHC Experiments Beam Loss Monitors BCM Beam loss monitors BLM Monitors aperture limits (some 100) Monitors in arcs (several 1000) Injection Interlock Timing System (Post Mortem Trigger) Courtesy Rudiger Schmidt, Bruno Puccio, Ben Todd

58 Beam Dump System (LBDS) Absolutely critical. Rigorous and extensive program of commissioning and tests with beam. Expected about two asynchronous dumps per year one to date with beam IR6 H Beam2, extracted

59 Collimation 1.2 m Two warm cleaning insertions IR3: Momentum cleaning 1 primary (H) 4 secondary (H,S) 4 shower abs. (H,V) IR7: Betatron cleaning 3 primary (H,V,S) 11 secondary (H,V,S) 5 shower abs. (H,V) Local IP cleaning: 8 tertiary coll. Total = 108 collimators About 500 degrees of freedom. beam

60 Collimation cleaning at 3.5 TeV Generate higher loss rates: beam across the 3rd order resonance. Beam 1 Betatron TCTs Off-momentum Dump TCTs TCTs TCTs Legend: Collimators Cold losses Warm losses Outstanding performance: No beam-induced quenches in 2010/2011

61 ns 50 ns 4. Increase bunch intensity 1. Increase number of bunches 3. Squeeze further 2. Reduce beam size from injectors

62 Total intensity At injection dynamic aperture is clearly greater than aperture defined by collimators: Excellent field quality and correction of non-linearities Dynamic effects well under control (FIDEL) Low tune modulation, low power converter ripple, low RF noise Number of issues during the ramp-up in the number of bunches: Instrumentation response Vacuum activity UFOs Beam induced heating Single Event Effects (SEE) Machine protection performing impeccably Routine collimation of 110 MJ LHC beams (50 times HERA/Tevatron) without a single quench from stored beams.

63 The LHC Success of Stored Energy factor ~50 no quench with stored beam at LHC Courtesy Ralph Assmann

64 Beam from injectors This year we ve mostly been taking the 50 ns beam. Excellent performance better than nominal bunch intensity and less than nominal beam size Years in the preparation

65 Beam stability Even with well over nominal bunch intensity instabilities under control via Landau damping (octupoles) and transverse feedback TSBI of HT mode m = -1 from machine impedance predicted without octupoles and intrinsic nonlinearities (Elias Metral) Lots of care during design to minimize the machine impedance. Lot of effort to study and simulate potential limitations. Francesco Ruggiero (impedance police) and Fritz Caspers (RF contact specifications)

66 COLLISIONS Beam-beam Can collide well over nominal bunch intensity with smaller that nominal emittances Head-on: no problem up to ~0.0075, ~0.02 total tune shift with offset collisions in LHCb and Alice Put this down to excellent field quality and sufficient long range separation 25 hours

67 Squeezing further Aperture compatible with a well-aligned machine, a well centred orbit and close to design mechanical aperture Together with collimation, this opened the way to a squeeze from 1.5 to 1.0 m. (50% increase in luminosity.) Stefano Redaelli, Massimo Giovannozzi, Jorg Wenninger et al

68 Operational robustness Injecting dangerous beams routinely vigilance always required Ramp & squeeze & collide essentially without loss Excellent reproducibility and stability Feedbacks (tune, orbit, transverse) indispensable Almost exclusive coverage by the sequencer for nominal operation Software, controls, databases, measurement and analysis tools provide rich functionality

69 Efficiency/Availability 30% efficiency for stable beams during 180 days for physics (54 days in stable beams) Other scheduled periods: 18 days technical stops 10 days scrubbing run ~17 days of MD Pretty good!

70 Availability LHC Cryo global availability Major stops: PLC-SEU: 5 Cryo: 5 EL: 4 24-Jan 21-Feb 21-Mar 18-Apr 16-May 13-Jun 11-Jul 8-Aug 5-Sep 3-Oct 31-Oct 28-Nov 2010: Nice learning curve 2011: Direct effect of high luminosity since spring, partially treated now and to be continued at Xmas break Between TS 2010 Scheduled Stops Weekly 2011 Between TS 2011 Courtesy: Serge Claudet

71 PERSONAL COMPETANCIES Leadership Teamwork Ability to relax

72 Maslow s Hierarchy of Needs Tee Shirts Experience Expertise Resources

73 We delivered 5.6 fb -1 to Atlas in 2011 and all we got was a blooming tee shirt

74

Running in 2011 - Luminosity. Mike Lamont Verena Kain

Running in 2011 - Luminosity. Mike Lamont Verena Kain Running in 2011 - Luminosity Mike Lamont Verena Kain Presentations Many thanks to all the speakers! Experiments expectations Massi Ferro-Luzzi Pushing the limits: beam Elias Métral Pushing the limits:

More information

The commissioning of the LHC: first the technical systems, then the commissioning with beam

The commissioning of the LHC: first the technical systems, then the commissioning with beam The commissioning of the LHC: first the technical systems, then the commissioning with beam Roberto Saban 4. Ulusal Parçacık Hızlandırıcıları ve Uygulamaları Kongresi 30 Ağustos 1 Eylül 2010, Bodrum -

More information

LHC MACHINE PROTECTION

LHC MACHINE PROTECTION LHC MACHINE PROTECTION Rossano Giachino, CERN, Geneva, Switzerland Abstract The energy stored in LHC magnets presents a considerable challenge for commissioning even before any beam is injected. Furthermore,

More information

LHC optics measurement & correction procedures. M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove

LHC optics measurement & correction procedures. M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove LHC optics measurement & correction procedures M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove Thanks to: I. Agapov, M. Bai, A. Franchi, M. Giovannozzi, V. Kain, G. Kruk, J. Netzel, S. Redaelli,

More information

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I) 28. High-energy collider parameters 1 HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I) Updated in early 2012 with numbers received from representatives of the colliders (contact J. Beringer, LBNL).

More information

Large Systems Commissioning

Large Systems Commissioning Large Systems Commissioning, DESY CAS Vacuum in Accelerators Platja D`Aro, May 21, 2006 Special thanks to O. Gröbner 1 Outline Introduction Pump Down and Leak Check Components Check Bake Out Interlocks/Safety

More information

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006 Tune and Chromaticity Tracking in the Tevatron C.Y. Tan 09 May 2006 Overview What is the Tevatron tune tracker? Selected results from some stores. (There are many stores with TT running). Planned chromaticity

More information

SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10

SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN ACCELERATORS AND TECHNOLOGY SECTOR CERN-ATS-2011-003 SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10 Editors : Rama Calaga, Steve Myers, Frank Zimmermann

More information

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source Frequency Map Experiments at the Advanced Light Source David Robin Advanced Light Source work done in collaboration with Christoph Steier (ALS), Ying Wu (Duke), Weishi Wan (ALS), Winfried Decking (DESY),

More information

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN Abstract BEPC Group, presented by Yingzhi Wu Institute of High Energy Physics, Beijing 100039, P.R. China The luminosity upgrades of the BEPC are briefly reviewed.

More information

Machine Protection and Interlock Systems for Circular Machines Example for LHC

Machine Protection and Interlock Systems for Circular Machines Example for LHC Published by CERN in the Proceedings of the Joint International Accelerator School: Beam Loss and Accelerator Protection, Newport Beach, US, 5 14 November 2014, edited by R. Schmidt, CERN-2016-002 (CERN,

More information

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

Brookhaven Magnet Division - Nuclear Physics Program Support Activities Brookhaven - Nuclear Physics Program Support Activities Spin Program support E-Cooling R&D RIA RHIC Operations Support Funding AGS Warm Siberian Snake AGS Warm Snake Magnetic element designed and built

More information

FCC 1309180800 JGU WBS_v0034.xlsm

FCC 1309180800 JGU WBS_v0034.xlsm 1 Accelerators 1.1 Hadron injectors 1.1.1 Overall design parameters 1.1.1.1 Performance and gap of existing injector chain 1.1.1.2 Performance and gap of existing injector chain 1.1.1.3 Baseline parameters

More information

Zero Degree Extraction using an Electrostatic Separator

Zero Degree Extraction using an Electrostatic Separator Zero Degree Extraction using an Electrostatic Separator L. Keller Aug. 2005 Take another look at using an electrostatic separator and a weak dipole to allow a zero degree crossing angle a la the TESLA

More information

Possible Upgrades and New Design. F. Velotti and B. Goddard

Possible Upgrades and New Design. F. Velotti and B. Goddard Possible Upgrades and New Design F. Velotti and B. Goddard Outline Possible system upgrade General principles TIDVG modifications needed MKDV modifications needed External beam dump study Requirements

More information

Damping Wigglers in PETRA III

Damping Wigglers in PETRA III Damping Wigglers in PETRA III WIGGLE2005, Frascati 21-22.2.2005 Winni Decking, DESY-MPY Introduction Damping Wiggler Parameters Nonlinear Dynamics with DW Operational Aspects Summary DESY and its Accelerators

More information

Lecture VI Magnetic Design

Lecture VI Magnetic Design Lecture VI Magnetic Design Field Quality Adjustment After Construction (or After the Start of Production Run) Ramesh Gupta Superconducting Brookhaven National Laboratory US Particle Accelerator School

More information

R. GIACHINO, M. ALBERT LHC MACHINE CHECKOUT 2015

R. GIACHINO, M. ALBERT LHC MACHINE CHECKOUT 2015 R. GIACHINO, M. ALBERT LHC MACHINE CHECKOUT 2015 QUENCH 2 SATURDAY PNO.b3 in RQD.A45 and RQF.A45 Tripped a few minutes after flattop 3 SATURDAY RQF.A12 tripped at while at nominal. Earth fault still present

More information

Results: Low current (2 10 12 ) Worst case: 800 MHz, 12 50 GeV, 4 turns Energy oscillation amplitude 154 MeV, where

Results: Low current (2 10 12 ) Worst case: 800 MHz, 12 50 GeV, 4 turns Energy oscillation amplitude 154 MeV, where Status Focus has shifted to a neutrino factory Two comprehensive designs of acceleration (liancs, arcs) Jefferson Lab, for Fermilab Study CERN (Keil et al.) Jefferson Lab study Low (2 10 12 ) charge per

More information

The half cell of the storage ring SESAME looks like: Magnetic length =

The half cell of the storage ring SESAME looks like: Magnetic length = 6. Magnets 6.1 Introduction SESAME will be perhaps erected in steps. The number of steps depends upon the available money. The cheapest way is to use the quadrupole and sextupoles from BESSY I. In this

More information

The accurate calibration of all detectors is crucial for the subsequent data

The accurate calibration of all detectors is crucial for the subsequent data Chapter 4 Calibration The accurate calibration of all detectors is crucial for the subsequent data analysis. The stability of the gain and offset for energy and time calibration of all detectors involved

More information

New Machine Layout in IR3 and IR7

New Machine Layout in IR3 and IR7 CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project LHC Project Document No. EDMS Document No. 474750 Engineering Change requested by ( Name & Div./Grp. ) : R. Assmann, AB/ABP Date: 2004-05-26

More information

RF SYSTEM FOR VEPP-5 DAMPING RING

RF SYSTEM FOR VEPP-5 DAMPING RING Ó³ Ÿ. 2006.. 3, º 7(136).. 60Ä64 Š 621.384.634.14 RF SYSTEM FOR VEPP-5 DAMPING RING Ye. Gusev, N. Kot, S. Krutikhin, I. Kuptsov, G. Kurkin, I. Makarov, N. Matyash, L. Mironenko, S. Motygin, V. Osipov,

More information

Minimum requirements for the 13 ka splices for 7 TeV operation

Minimum requirements for the 13 ka splices for 7 TeV operation Minimum requirements for the 13 ka splices for 7 TeV operation - type of defects - FRESCA tests and validation of the code QP3 - a few words on the RRR - I safe vs R addit plots - conclusion Arjan Verweij

More information

10 Project Costs and Schedule

10 Project Costs and Schedule II-367 10 Project Costs and Schedule 10.1 Overview The investment costs given in this chapter include all components necessary for the baseline design of TESLA, as described in chapters 3 to 9. Not included

More information

SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS *

SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS * SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS * K. C. Harkay and R. A. Rosenberg, ANL, Argonne, IL 60439, USA M. A. Furman and M. Pivi, LBNL, Berkeley, CA 94720, USA Abstract In studies

More information

Projects and R&D activities

Projects and R&D activities Projects and R&D activities J.M. Jimenez On behalf of the Vacuum, Surface and Coatings Group (VSC) Vacuum, Surface and Coatings group* Mandate Design, construction, operation, maintenance and upgrade of

More information

The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead

The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead R. Kersevan Vacuum Surfaces and Coatings Group, Technology Department, CERN, Geneva The HiLumi LHC Design Study is included in the

More information

Beam Instrumentation Group, CERN ACAS, Australian Collaboration for Accelerator Science 3. School of Physics, University of Melbourne 4

Beam Instrumentation Group, CERN ACAS, Australian Collaboration for Accelerator Science 3. School of Physics, University of Melbourne 4 Prototype tests of a wide-band Synchrotron-Light based Beam Pattern Monitor for measuring charge-couple bunch instabilities in High-Energy Particle Accelerator Beams Sophie Dawson2,3, Mark Boland2,4, David

More information

LHCC TOTEM STATUS REPORT

LHCC TOTEM STATUS REPORT LHCC TOTEM STATUS REPORT Status of Roman Pot Consolidation & Upgrade Program Physics Analysis Highlights 4/9/2013 LHCC TOTEM 13.3.2013 CERN J. Baechler 1 TOTEM Status of Roman Pot Consolidation & Upgrade

More information

Status of the SOLEIL project Commissioning from Linac to beamlines

Status of the SOLEIL project Commissioning from Linac to beamlines Status of the SOLEIL project Commissioning from Linac to beamlines On behalf of the commissioning team 2 D01-1-CX1/DT/DTC/absorption Y Axis Title 0-200 0 200 400 600 800 1000 1200 1400 X Axis Title 1 Site

More information

Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:1606.06697v1 [physics.acc-ph] 21 Jun 2016

Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:1606.06697v1 [physics.acc-ph] 21 Jun 2016 Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:606.06697v [physics.acc-ph] 2 Jun 206 Javier Resta-Lopez, James R. Hunt, Carsten P. Welsch Department of Physics,

More information

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004 DOE LHC Quarterly Review Magnet Production Cable Testing Cost to Complete issues Mike Harrison, BNL July 26, 2004 1 BNL Production Status Magnet production complete The last series of dipoles (D3 s) is

More information

Status of the HOM Damped Cavity for the Willy Wien Ring

Status of the HOM Damped Cavity for the Willy Wien Ring Status of the HOM Damped Cavity for the Willy Wien Ring Ernst Weihreter / BESSY Short Review of HOM Damped Cavity Prototype Modifications for the Willy Wien Ring Cavity Results of Low Power Measurements

More information

Calorimetry in particle physics experiments

Calorimetry in particle physics experiments Calorimetry in particle physics experiments Unit n. 8 Calibration techniques Roberta Arcidiacono Lecture overview Introduction Hardware Calibration Test Beam Calibration In-situ Calibration (EM calorimeters)

More information

Status of EVOLVE boiling flow regime experiments

Status of EVOLVE boiling flow regime experiments Status of EVOLVE boiling flow regime experiments M.H. Anderson M.L. Corradini J. Murphy I. Sviatoslavsky M. Sawan APEX TASK IV APEX ELECTRONIC MEETING Feb. 7, 2002 U- Madison of Nuclear Systems Nuclear

More information

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides The BESSY HOM Damped Cavity with Ferrite Absorbers E. Weihreter / BESSY Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides Design of a ferrite loaded ridged circular waveguide

More information

ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS

ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS D. Schulte, R. Wanzenberg 2, F. Zimmermann CERN, Geneva, Switzerland 2 DESY, Hamburg, Germany Abstract Damping rings reduce the emittances

More information

AUTOMATION OF OPERATIONS ON THE VEPP-4 CONTROL SYSTEM

AUTOMATION OF OPERATIONS ON THE VEPP-4 CONTROL SYSTEM 10th ICALEPCS Int. Conf. on Accelerator & Large Expt. Physics Control Systems. Geneva, 10-14 Oct 2005, PO1.072-7 (2005) AUTOMATION OF OPERATIONS ON THE VEPP-4 CONTROL SYSTEM A. Bogomyagkov, S. Karnaev,

More information

Machine Interlocks Systems

Machine Interlocks Systems rlocks Status for locks s Hardware readiness and plans State of the supervision Bruno Puccio Pierre Dahlen Benjamin Todd Markus Zerlauth 1 Outline locks = 5 systems managed by AB/CO Hardware readiness

More information

Francesco Ruggiero My Dear Friend and Colleague

Francesco Ruggiero My Dear Friend and Colleague Francesco Ruggiero My Dear Friend and Colleague Weiren Chou (Fermilab) Francesco Ruggiero Memorial Symposium, 02/10/07, CERN 1 Last E-mail from Francesco He wrote this e-mail on December 5, 2006, only

More information

Technical Specification for the Cryogenic Testing of HTS Current Leads

Technical Specification for the Cryogenic Testing of HTS Current Leads Group Ref.: AT-MEL-CF EDMS No.: 44036 The Large Hadron Collider Project IT-3303/AT/LHC Technical Specification for the Cryogenic Testing of HTS Current Leads Abstract This specification concerns the testing

More information

CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS

CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS CABLE DESIGN AND RELATED ISSUES IN A FAST-CYCLING SUPERCONDUCTING MAGNETS A.D.Kovalenko JINR, Dubna, Russia Abstract Hollow superconducting cables for a fast-cycling synchrotrons are discussed. The essential

More information

UNIVERSITÉ CLERMONT FERRAND II BLAISE PASCAL THÈSE. pour obtenir le grade de DOCTEUR DE L UBP Discipline : Physique des Particules

UNIVERSITÉ CLERMONT FERRAND II BLAISE PASCAL THÈSE. pour obtenir le grade de DOCTEUR DE L UBP Discipline : Physique des Particules Numéro d ordre : DU 1631 EDSF : 473 PCCF T 0509 UNIVERSITÉ CLERMONT FERRAND II BLAISE PASCAL THÈSE pour obtenir le grade de DOCTEUR DE L UBP Discipline : Physique des Particules préparée au CERN/BDI/BL

More information

x = u cos z =-u sin where d~ = - ~ B(s). ds 2p 1.2 Compensation by skew guadrupoles 2,3) - 8n~ E B(s) ds

x = u cos z =-u sin where d~ = - ~ B(s). ds 2p 1.2 Compensation by skew guadrupoles 2,3) - 8n~ E B(s) ds STATUS REPORT ON ACO t) The Orsay Storage Ring Group Laboratoire de taccelerateur Lineaire, Universite de Paris-Sud, Centre dtorsay, Orsay, France. (presented by D. Potaux) Abstract 1.1 Compensation by

More information

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group Status of the Diamond Storage Ring RF Systems Morten Jensen on behalf of Diamond Storage Ring RF Group Content 1. General Operational Status 2. Main issues and causes of trips 3. 200 ma + operation Qext

More information

SOLEIL Current Performances. And. Futur Developments

SOLEIL Current Performances. And. Futur Developments SOLEIL Current Performances And Futur Developments Amor Nadji On Behalf of the SOLEIL Team A. Nadji, ESLSXVIII, Trieste, November 25-26 2010 1 Main Parameters Energy (GeV) 2.75 Emittance H (nm.rad) 3.7

More information

Activities at the University of Frankfurt (IAP)

Activities at the University of Frankfurt (IAP) Activities at the University of Frankfurt (IAP) Holger Podlech Ulrich Ratzinger Oliver Kester Institut für Angewandte Physik (IAP) Goethe-Universität Frankfurt am Main H. Podlech 1 Development of 325 MHz

More information

Cathode Ray Tube. Introduction. Functional principle

Cathode Ray Tube. Introduction. Functional principle Introduction The Cathode Ray Tube or Braun s Tube was invented by the German physicist Karl Ferdinand Braun in 897 and is today used in computer monitors, TV sets and oscilloscope tubes. The path of the

More information

SHORT STRAIGHT SECTION TYPES IN THE MATCHING SECTIONS

SHORT STRAIGHT SECTION TYPES IN THE MATCHING SECTIONS CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project LHC Project Document No. CERN Div./Group or Supplier/Contractor Document No. IN2P3-IPNO/FL/cc EDMS Document No. 420222 Date: 2005-02-23

More information

Spin Tracking with COSY INFINITY and its Benchmarking

Spin Tracking with COSY INFINITY and its Benchmarking Spin Tracking with COSY INFINITY and its Benchmarking 2015-05-05 Marcel Rosenthal for the JEDI collaboration Outline Methods Simulation toolbox New extension: Transfer maps for time-varying fields Application

More information

World-first Proton Pencil Beam Scanning System with FDA Clearance

World-first Proton Pencil Beam Scanning System with FDA Clearance Hitachi Review Vol. 58 (29), No.5 225 World-first Proton Pencil Beam Scanning System with FDA Clearance Completion of Proton Therapy System for MDACC Koji Matsuda Hiroyuki Itami Daishun Chiba Kazuyoshi

More information

Copyright. Ryoichi Miyamoto

Copyright. Ryoichi Miyamoto Copyright by Ryoichi Miyamoto 2008 The Dissertation Committee for Ryoichi Miyamoto certifies that this is the approved version of the following dissertation: Diagnostics of the Fermilab Tevatron Using

More information

Figure 1: Lattice drawing for the APS storage ring.

Figure 1: Lattice drawing for the APS storage ring. PERFORMANCE OF THE ADVANCED PHOTON SOURCE Glenn Decker Advanced Photon Source, Argonne National Laboratory 9700 South Cass Avenue, Argonne, Illinois 60439 USA Abstract The Advanced Photon Source (APS)

More information

Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities

Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities F. Marhauser Thanks also to H. Wang and K. Tian 27. August 2009 How HOMs are excited and why they are important - Wakefields- some

More information

The design and performance of Static Var Compensators for particle accelerators

The design and performance of Static Var Compensators for particle accelerators CERN-ACC-2015-0104 Karsten.Kahle@cern.ch The design and performance of Static Var Compensators for particle accelerators Karsten Kahle, Francisco R. Blánquez, Charles-Mathieu Genton CERN, Geneva, Switzerland,

More information

Industry Environment and Concepts for Forecasting 1

Industry Environment and Concepts for Forecasting 1 Table of Contents Industry Environment and Concepts for Forecasting 1 Forecasting Methods Overview...2 Multilevel Forecasting...3 Demand Forecasting...4 Integrating Information...5 Simplifying the Forecast...6

More information

TTF OPERATIONS STATISTICS

TTF OPERATIONS STATISTICS 21.Nov.01 M i n t y TTF OPERATIONS STATISTICS To direct accelerator improvements aimed at increased reliability, the operational statistics at the TTF are now logged on a per -shift basis. Initially these

More information

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator R. Gupta and M.Harrison, Brookhaven National Laboratory A. Zeller, Michigan State University

More information

CONTROL ROOM ACCELERATOR PHYSICS

CONTROL ROOM ACCELERATOR PHYSICS 1/30/14 USPAS 1 CONTROL ROOM ACCELERATOR PHYSICS Trajectory/ Applications 1/30/14 USPAS 2 Objective Maintain the beam (bunch) propagation along its design trajectory There are always errors from power

More information

C.-K. Ng. Stanford Linear Accelerator Center. and. T. Weiland. University oftechnology. FB18, Schlossgartenstr. 8. D64289, Darmstadt, Germany.

C.-K. Ng. Stanford Linear Accelerator Center. and. T. Weiland. University oftechnology. FB18, Schlossgartenstr. 8. D64289, Darmstadt, Germany. SLAC-PUB-95-7005 September, 1995 Impedance of the PEP-II DIP Screen C.-K. Ng Stanford Linear Accelerator Center Stanford University, Stanford, CA 94309, USA and T. Weiland University oftechnology FB18,

More information

Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique

Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique Uwe Niedermayer and Oliver Boine-Frankenheim 24 August 2012 TU Darmstadt Fachbereich 18

More information

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK K. Rehlich, DESY, Hamburg, Germany Abstract The next generation of large accelerators facilities will be produced and operated

More information

Information about the T9 beam line and experimental facilities

Information about the T9 beam line and experimental facilities Information about the T9 beam line and experimental facilities The incoming proton beam from the PS accelerator impinges on the North target and thus produces the particles for the T9 beam line. The collisions

More information

Tom Wilson Product Marketing Manager Delivery Systems Varian Medical Systems International AG. CERN Accelerator School, May 2015

Tom Wilson Product Marketing Manager Delivery Systems Varian Medical Systems International AG. CERN Accelerator School, May 2015 INDUSTRIAL DESIGN Tom Wilson Product Marketing Manager Delivery Systems Varian Medical Systems International AG VARIAN ONCOLOGY SYSTEMS 1 VARIAN ONCOLOGY SYSTEMS CERN Accelerator, May 2015 Industrial Design

More information

Status Overview The Australian Synchrotron. Steven Banks Control Systems Group

Status Overview The Australian Synchrotron. Steven Banks Control Systems Group Status Overview The Australian Synchrotron Steven Banks Control Systems Group Where Are We? Where Are We? Where Are We? The Building Development being managed by Major Projects Victoria (MPV) Budget is

More information

FACET First Beam Commissioning. Jerry Yocky For the FACET commissioning team 21-May-2012 IPAC 2012, New Orleans, LA

FACET First Beam Commissioning. Jerry Yocky For the FACET commissioning team 21-May-2012 IPAC 2012, New Orleans, LA FACET First Beam Commissioning Jerry Yocky For the FACET commissioning team 21-May-2012 IPAC 2012, New Orleans, LA Facility for Advanced accelerator Experimental Tests WHAT IS FACET? The FACET Facility

More information

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratory for Particle Physics SUPERCONDUCTIVITY AND CRYOGENICS FOR FUTURE HIGH-ENERGY ACCELERATORS

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratory for Particle Physics SUPERCONDUCTIVITY AND CRYOGENICS FOR FUTURE HIGH-ENERGY ACCELERATORS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH Laboratory for Particle Physics Departmental Report CERN/AT 2007-4 SUPERCONDUCTIVITY AND CRYOGENICS FOR FUTURE HIGH-ENERGY ACCELERATORS Ph. Lebrun High-energy

More information

A new extraction system for the upgraded AIC-144 cyclotron

A new extraction system for the upgraded AIC-144 cyclotron NUKLEONIKA 2001;46(2):51 57 ORIGINAL PAPER A new extraction system for the upgraded AIC-144 cyclotron Edmund Bakewicz, Krzysztof Daniel, Henryk Doruch, Jacek Sulikowski, Ryszard Taraszkiewicz, Nikolaj

More information

PERFORMANCE EVALUATION AND QUALITY ASSURANCE MANAGEMENT DURING THE SERIES POWER TESTS OF LHC MAIN LATTICE MAGNETS

PERFORMANCE EVALUATION AND QUALITY ASSURANCE MANAGEMENT DURING THE SERIES POWER TESTS OF LHC MAIN LATTICE MAGNETS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 1092 PERFORMANCE EVALUATION AND QUALITY ASSURANCE MANAGEMENT DURING

More information

AS COMPETITION PAPER 2007 SOLUTIONS

AS COMPETITION PAPER 2007 SOLUTIONS AS COMPETITION PAPER 2007 Total Mark/50 SOLUTIONS Section A: Multiple Choice 1. C 2. D 3. B 4. B 5. B 6. A 7. A 8. C 1 Section B: Written Answer Question 9. A mass M is attached to the end of a horizontal

More information

Lawrence Berkeley National Laboratory Lawrence Berkeley National Laboratory

Lawrence Berkeley National Laboratory Lawrence Berkeley National Laboratory Lawrence Berkeley National Laboratory Lawrence Berkeley National Laboratory Title: Electron-cloud simulation results for the SPS and recent results for the LHC Author: Furman, M.A. Pivi, M.T.F. Publication

More information

HIGH CURRENT OPERATION OF THE ACSI TR30 CYCLOTRON

HIGH CURRENT OPERATION OF THE ACSI TR30 CYCLOTRON HIGH CURRENT OPERATION OF THE ACSI TR30 CYCLOTRON 18 th International Conference on Cyclotrons and their Applications, Sicily, 2007 Vasile Sabaiduc, Project Manager, RF Senior Engineer Advanced Cyclotron

More information

MICE detectors and first results. M. Bonesini Sezione INFN Milano Bicocca

MICE detectors and first results. M. Bonesini Sezione INFN Milano Bicocca MICE detectors and first results M. Bonesini Sezione INFN Milano Bicocca I will speak of the installed beamline PID detectors (TOFes, CKOVs, KL) and only shortly of EMR (to be built)/ the trackers (tested

More information

Advantages of Real-time Spectrum Analyzers in High Energy Physics Applications

Advantages of Real-time Spectrum Analyzers in High Energy Physics Applications Advantages of Real-time Spectrum Analyzers in High Energy Physics Applications Introduction In High Energy Physics (HEP) applications, the fundamental challenges facing operators and researchers are sustained

More information

Status And Future Plans. Mitsuyoshi Tanaka. AGS Department.Brookhaven National Laboratory* Upton NY 11973, USA INTRODUCTION

Status And Future Plans. Mitsuyoshi Tanaka. AGS Department.Brookhaven National Laboratory* Upton NY 11973, USA INTRODUCTION 6th Conference on the Intersections of Particle & Nuclear Physics Big Sky, Montana May 27-June 2, 1997 / BNL-6 40 4 2 c0,lvf- 7 70 5 The BNL AGS Accelerator Complex Status And Future Plans Mitsuyoshi Tanaka

More information

FLASH Commissioning and Startup

FLASH Commissioning and Startup FLASH Seminar 8-May-2007, DESY FLASH Commissioning and Startup email: siegfried.schreiber@desy.de Commissioning Startup Accelerator/FEL Studies Main Commissioning Tasks Modules: RF/LLRF warm/cold coupler

More information

Top rediscovery at ATLAS and CMS

Top rediscovery at ATLAS and CMS Top rediscovery at ATLAS and CMS on behalf of ATLAS and CMS collaborations CNRS/IN2P3 & UJF/ENSPG, LPSC, Grenoble, France E-mail: julien.donini@lpsc.in2p3.fr We describe the plans and strategies of the

More information

The TOTEM experiment at the LHC: results and perspective

The TOTEM experiment at the LHC: results and perspective The TOTEM experiment at the LHC: results and perspective Edoardo Bossini Università degli studi di Siena and INFN-Pisa (on behalf of the TOTEM collaboration) Trieste, 24 Settembre 2013 OUTLINE: Detector

More information

Cryogenic Current Comparator Status at GSI/FAIR -

Cryogenic Current Comparator Status at GSI/FAIR - Cryogenic Current Comparator Status at GSI/FAIR - Outline Overview and timeline of the FAIR project at GSI Cryogenic Current Comparators as German In-Kind to FAIR CCCs in HEBT section of FAIR CCC inside

More information

Status of Radiation Safety System at

Status of Radiation Safety System at Status of Radiation Safety System at Taiwan Photon Source Joseph C. Liu Radiation and Operation Safety Division National Synchrotron Radiation Research Center, Taiwan NSRRC layout 1.5 GeV, 120m, 400 ma

More information

Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting

Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting 23 October 2011 TU Darmstadt Fachbereich 18 Institut Theorie Elektromagnetischer Felder Uwe Niedermayer 1 Contents Motivation / Overview

More information

Relativistic kinematics basic energy, mass and momentum units, Lorents force, track bending, sagitta. First accelerator: cathode ray tube

Relativistic kinematics basic energy, mass and momentum units, Lorents force, track bending, sagitta. First accelerator: cathode ray tube Accelerators Relativistic kinematics basic energy, mass and momentum units, Lorents force, track bending, sagitta Basic static acceleration: First accelerator: cathode ray tube Cathode C consist of a filament,

More information

3D SCANNERTM. 3D Scanning Comes Full Circle. s u n. Your Most Valuable QA and Dosimetry Tools A / B / C. The 3D SCANNER Advantage

3D SCANNERTM. 3D Scanning Comes Full Circle. s u n. Your Most Valuable QA and Dosimetry Tools A / B / C. The 3D SCANNER Advantage 3D SCANNERTM 3D Scanning Comes Full Circle Relative 3D Dosimetry offering the easiest setup, most objectivity, and best consistency available The 3D SCANNER Advantage Advanced Design Ring and diameter

More information

Vertical orbit-excursion fixed field alternating gradient accelerators (V-FFAGs) and 3D cyclotrons

Vertical orbit-excursion fixed field alternating gradient accelerators (V-FFAGs) and 3D cyclotrons BNL-103342-2014-CP Vertical orbit-excursion fixed field alternating gradient accelerators (V-FFAGs) and 3D cyclotrons S.J. Brooks Presented at the 5th International Particle Accelerator Conference (IPAC14)

More information

Study of electron cloud at MI and slip stacking process simulation

Study of electron cloud at MI and slip stacking process simulation Study of electron cloud at MI and slip stacking process simulation Alexandr S. Valkovich Purpose 1.Understand the slip stacking process which happens in the Main Injector. 2. Calculation of bunch distortion

More information

The OPERA Emulsions. Jan Lenkeit. Hamburg Student Seminar, 12 June 2008. Institut für Experimentalphysik Forschungsgruppe Neutrinophysik

The OPERA Emulsions. Jan Lenkeit. Hamburg Student Seminar, 12 June 2008. Institut für Experimentalphysik Forschungsgruppe Neutrinophysik The OPERA Emulsions Jan Lenkeit Institut für Experimentalphysik Forschungsgruppe Neutrinophysik Hamburg Student Seminar, 12 June 2008 1/43 Outline The OPERA experiment Nuclear emulsions The OPERA emulsions

More information

RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure

RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure PEI Shi-Lun( 裴 士 伦 ) 1) CHI Yun-Long( 池 云 龙 ) ZHANG Jing-Ru( 张 敬 如 ) HOU Mi( 侯 汨 ) LI Xiao-Ping( 李 小

More information

ADONE THE FRASCATI 1.5 GeV ELECTRON POSITRON STORAGE RING

ADONE THE FRASCATI 1.5 GeV ELECTRON POSITRON STORAGE RING 703 ADONE THE FRASCATI 1.5 GeV ELECTRON POSITRON STORAGE RING F. Amman, R. Andreani, M. Bassetti, M. Bernardini, A. Cattani, V. Chimenti, G. Corazza, D. Fabiani, E. Ferlenghi, A. Massarotti, C. Pellegrini,

More information

Insertion Devices Lecture 4 Permanent Magnet Undulators. Jim Clarke ASTeC Daresbury Laboratory

Insertion Devices Lecture 4 Permanent Magnet Undulators. Jim Clarke ASTeC Daresbury Laboratory Insertion Devices Lecture 4 Permanent Magnet Undulators Jim Clarke ASTeC Daresbury Laboratory Introduction to Lecture 4 So far we have discussed at length what the properties of SR are, when it is generated,

More information

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet ABB Instruction Leaflet 41-161J Effective: May 1997 Supersedes I.L. 41-161H Dated July 1984 ( ) Denotes Change Since Previous Issue Type COQ Negative Sequence Generator Relay (50/60 Hertz)! CAUTION Before

More information

LLRF. Digital RF Stabilization System

LLRF. Digital RF Stabilization System LLRF Digital RF Stabilization System Many instruments. Many people. Working together. Stability means knowing your machine has innovative solutions. For users, stability means a machine achieving its full

More information

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson FERMILAB-CONF-11-258-AD FERMILAB SRF CRYOMODULE OPERATIONAL EXPERIENCE A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson Fermi National Accelerator Laboratory Batavia,

More information

Digital vs. Analogue Control Systems

Digital vs. Analogue Control Systems Digital vs. Analogue Control Systems Presented at the 2011 Annual Meeting of the American College of Medical Physics, Chattanooga, TN, May 1, 2011 Ivan A. Brezovich, PhD, Dept. of Rad Onc, Univ of Alabama

More information

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues 10:45 11:10 Limits to achievable stability Glenn Decker, APS 11:10 11:35 Stability and alignment of NSLS II magnet

More information

Reliability and Availability Aspects of. the IPHI Project

Reliability and Availability Aspects of. the IPHI Project Reliability and Availability Aspects of the IPHI Project Pierre-Yves Beauvais CEA/DSM/DAPNIA for the IPHI Team 18/02/2002 Pierre-Yves Beauvais, CEA Saclay 1 Table of contents Brief description of IPHI

More information

Manufacturing and Testing of Accelerator Superconducting Magnets

Manufacturing and Testing of Accelerator Superconducting Magnets Published by CERN in the Proceedings of the CAS-CERN Accelerator School: Superconductivity for Accelerators, Erice, Italy, 24 April 4 May 2013, edited by R. Bailey, CERN 2014 005 (CERN, Geneva, 2014) Manufacturing

More information

PHYSICS WITH LHC EARLY DATA

PHYSICS WITH LHC EARLY DATA PHYSICS WITH LHC EARLY DATA ONE OF THE LAST PROPHETIC TALKS ON THIS SUBJECT HOPEFULLY We may have some two month of the Machine operation in 2008 LONG HISTORY... I will extensively use: Fabiola GIANOTTI

More information