SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10

Size: px
Start display at page:

Download "SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10"

Transcription

1 EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH CERN ACCELERATORS AND TECHNOLOGY SECTOR CERN-ATS SUMMARY OF THE 4TH LHC CRAB CAVITY WORKSHOP LHC-CC10 Editors : Rama Calaga, Steve Myers, Frank Zimmermann Abstract The 4 th workshop on crab cavities for the LHC high-luminosity upgrade project HL-LHC (LHC- CC10) was held from 15 to 17 December 2010 at CERN, Geneva, Switzerland. This document outlines the key conclusions from the LHC-CC10 workshop and summarizes each individual session based on the final presentations by the session conveners and on the subsequent discussions. At LHC-CC10, local crab crossing with the aid of 400 MHz deflecting SRF cavities was identified as the baseline tool for geometric luminosity-loss compensation and luminosity levelling for the HL-LHC. Associated key issues such as machine protection and robust operational scenarios still have to be studied in detail, so as to identify and mitigate potential beam-dynamics or technology limits on implementing and fully exploiting crab crossing at the LHC. Also at LHC-CC10, the decision was taken not to install a KEK-B crab cavity in the SPS. However, it was recommended that all measures to test future LHC prototype cavities with and without beam outside the LHC be taken in order to ensure robust operation of the crab RF structures in the LHC. The 4 th workshop on the crab cavities (LHC-CC10) for the LHC luminosity upgrade project (HL-LHC) was held from 15 to 17 December 2010 at CERN, Geneva, Switzerland. Geneva, Switzerland, March 2011

2 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY INTRODUCTION WORKSHOP CHARGE AND OBJECTIVES SESSION SUMMARIES LHC-CC STATUS & REVIEW OPTICS & BEAM PHYSICS ASPECTS CAVITY TECHNOLOGY AND CRYOMODULES CRAB CAVITY BEAM STUDIES AND INSTRUMENTATION MACHINE PROTECTION RF CONTROLS & TESTING SCHEDULE & FUTURE OUTLOOK ADVISORY BOARD MEETINGS AND COMMENTS PARTICIPANTS MEETING COMMENTS OPEN ISSUES AND ACTION ITEMS

3 1 EXECUTIVE SUMMARY 1. Crabs are the *baseline* tool for geometric compensation and luminosity levelling for the HL-LHC. The nominal scheme for HL-LHC is a local crab crossing scheme with 400 MHz superconducting cavities independent of each IP (IP1 and IP5). Other options are pursued as backup if technology limits or machine protection issues are identified. 2. A refined roadmap should be sketched by the RF group and presented at the LMC before summer 2011 showing the overall effort and resources needed, including the prototyping. 3. No cavity down selection will be made now. A cavity down selection should be foreseen after the results from prototyping yield conclusive reasons to pick the best candidate for the LHC, which is expected by the end of The RF group will identify available resources within CERN to support prototyping effort while synchronizing with the US and UK efforts. 4. Identical systems for both IPs are preferable but this is not an absolute requirement. Therefore, one should pursue the best candidate satisfying the appropriate crossing scheme. 5. KEK-B crab cavities will not be installed in the SPS due to several reasons such as cost, difficulty, extrapolation to LHC, risk etc. 6. No synergies with CLIC crab cavities have been identified except for the low-level RF and cavity controls. 7. Machine protection with crab cavities needs detailed investigation with realistic RF failure signals in conjunction with the upgraded collimation system to arrive at a clear conclusion. 8. No show stoppers have been identified for the compact cavity designs presented. Three to four promising designs compatible with the LHC footprint exist. Cavity engineering design and prototyping should follow. A common platform for couplers, tuner systems and cryomodule equipment should be studied. 9. Detailed specifications for the cavities should be given, addressing the requirements on transparency, impedance, field quality, fundamental mode damping, trip rate, synchrobetatron resonances, plane of crabbing, etc. 10. A clear timeline for cryomodule development and prototype testing needs to be put in place. A generic cryostat could be used for testing all compact candidates. 11. A clear program for beam tests in the SPS and LHC, associated with their benefits, needs to be defined with a consistent timeline, taking into the account the regular operation and shutdowns of the LHC and its injectors. Critical issues such as machine protection, cavity transparency, impact on collimation system, emittance growth, low-level RF and cavity controls, and cavity impedance should be prioritized and addressed with a detailed experimental program 12. Other applications of crab cavities in the LHC or SPS such as the compensation of beamloading effects, momentum cleaning, bunch compression, etc.. should be investigated. 3

4 2 INTRODUCTION The 4 th workshop on the crab cavities (LHC-CC10) for the LHC luminosity upgrade project (HL- LHC) was held from 15 to 17 December 2010 at CERN, Geneva, Switzerland. The workshop was organized by a joint collaboration of CERN, EUCARD, KEK and US-LARP. Approximately 50 participants from 3 continents and several institutions participated in the workshop to discuss the future implementation of the crab cavities in the LHC and related issues. The detailed participation list, scientific program along with the associated contributions are available at: WORKSHOP CHARGE AND OBJECTIVES The charge of the workshop was as follows: 1. Can compact cavities for the LHC be realized and made robust with the complex damping schemes? 2. Are crab cavities compatible with LHC machine protection, or can they be made to be so? 3. Should a KEKB crab cavity be installed in the SPS for test purposes? A scientific program committee of 17 members from 10 institutes around the world compiled a comprehensive two-day program spanning various subjects related to the need, technologies, beam aspects and precise implementation of crab crossing in the LHC. The program was divided into 7 sessions with dedicated session conveners. The session conveners prepared individual summaries which were presented to an advisory board chaired by S. Myers with representatives from most of the major collaborating institutes. The session conveners were specifically requested to focus on the open issues and to trigger discussions addressing the charge of the workshop. 4

5 3 SESSION SUMMARIES Notes from the session summaries prepared by their respective conveners and additional material from the discussions during the workshop are detailed in this section. 3.1 LHC-CC STATUS & REVIEW Session Convener: Jean-Pierre Koutchouk As an initial disclaimer, it was mentioned that this session was not geared to address the charge, but to set the scene for the need of crab crossing in the LHC. KEK-B has established the proof of principle for crab crossing in a short period, but the expected performance of factor 2 increase in beam-beam parameter was not reached. This issue is specific to the strong beam-beam regime at which KEK-B operated, with very large dynamic beta changes, and less relevant to the LHC. Approximately 13 years for R&D, 2.5 years for commissioning and 1 year to achieve improvement was spent. In addition to crab cavities, skew sextupoles were needed to realize the full gain in beam-beam parameter that was finally achieved with crab crossing at KEK-B. A 4- mm orbit bump and a 10 degree RF phase shift were introduced to stabilize an observed instability which was caused by a coupling of the crab cavities of the two rings through the beam-beam interaction. The KEK-B crab cavities were sufficiently mature for operational purposes. However, the voltage performance was 30% lower than on the test bench. A high trip observed was mainly related to either the cavity fields or the coaxial couplers. Reducing the surface field had a strong impact on reducing the trip rate. No strong dependence of the trip rate on the beam current was evident. The KEK experience justifies using crab cavities for LHC. Strong performance during 2010 run was the highlight for the LHC. It was indicated that the speed of the LHC performance increase had been dictated by MPS considerations. Beam instrumentation was working extremely well. The transverse emittance had been 30% to 50% lower than the design value, which was promising for the future. The beam-beam tune shift had been twice the nominal value. No evidence had been observed of any issues related to operating at such a high beam-beam tune shift, which also bodes well for the upgrade. However, operation with much less than the nominal emittance would be very difficult for collimation. A common scenario and a coordinated shutdown calendar for the accelerator and the detectors are essential to reaching the LHC physics goals. It is extremely difficult if not impossible to integrate accelerator elements into the detector and such elements will clearly limit the physics reach. Since CCs do not interfere with the detector, they could be very important as upgrade ingredients which do not to perturb the physics reach of the experiments. HL-LHC is a project with a clear target for the upgrade to reach the LHC performance goal including luminosity levelling. Validation of a 400-MHz crab cavity with beam in the LHC circa 2016 is envisioned, which leaves a total 5 years for R&D and prototyping. This challenging time scale calls for vigorous R&D rather immediately. LHC challenges could be very different from 5

6 those at KEKB. Therefore detailed simulations and experiments are vital to the development of LHC crab hardware, but the hardware may not be the only challenge. 3.2 OPTICS & BEAM PHYSICS ASPECTS Session Convener: Massimo Giovannozzi An optics with beta* of 15cm based on the slhcv3 layout was designed. A crossing angle of 0.58 mrad is required with this optics to retain the 10sigma separation in the common aperture. The principle of the optics design is based on the off-momentum beat-beating correction using adjacent IR insertion regions resulting in larger than nominal beta s in the arc. A scheme of alternating crossing at IR1 and IR5 is still considered as nominal separation scheme for HL-LHC. Therefore, the crab cavity designs should envision providing dual plane kicks but with the same horizontal constraint for the beam pipe separation. Two cavities per beam per side of the IP placed after the D2 starting from the IP is ideal to profit from the large beta functions. About 10 MV of total voltage for 400-MHz crab cavities is required per side, per beam and per IP at 15 cm beta* and the current baseline crab location. Studies are ongoing to determine the dynamic aperture and field quality tolerance at top energy. Synchro-betatron resonances and the nonlinearity of the RF kick voltage as a function of transverse offset should be carefully considered. The local bump between the cavities is not absolutely closed due to imperfect phase advance between the cavities, but this non-closure is at the 2% level. Large orbit variations may be needed for luminosity scans. However, the crab cavities themselves could also be used to perform the luminosity scans, at least in the plane of crossing. The crab cavities may require transverse re-alignment in case of systematic large crossing angle changes requested by the experiments. Mitigation of static offsets for operational flexibility with remote alignment needs to be studied. In addition, the placement of the cavities on the IP side of the D2 in order to increase the beta function at the crab cavities has to be studied and compared with the non-ip side placement. An 8-mrad optics was initially proposed in 2006, triggered by a large crossing angle scheme. The present separation dipoles based on Nb-Ti magnets are relatively moderate from the aperture field plots. Therefore one solution for twin aperture magnets with smallest crossing would be to shorten D1. Additional gain in strength and in space between the dipole twin apertures is possible. For quadrupoles, there is less flexibility with regards to larger field gradient or larger aperture. Exotic designs are available, but need to be investigated more closely. Luminosity leveling in the presence of IBS and proton-burn off was studied for the nominal LHC and for LHC upgrade options. The assumptions on the machine availability used the simulations were optimistic, but the observed scaling is useful. Cross checks with one fill were performed and more cross checks are needed, e.g. benchmarking the model with a number of fills. We are far from the integrated luminosity goals set by the experiments even at ultimate intensities. Adding crab crossing significantly increases the reach of the upgrade. Adding luminosity leveling will help towards better integrated luminosity and reach the expected goal of 3000 fb -1. There is 6

7 also one scenario with crab crossing and 50-ns bunch spacing which comes close to the goal set by the experiments. RF feedback and feed-forward at 400 MHz with 1 MHz bandwidth available are currently available in the LHC. Im Z/n leads to loss of Landau damping. Controlled longitudinal emittance blow up during the ramp is performed to make the beams stable. For stability, the longitudinal shunt impedance is limited to a total of 60 kohm at 0.45 TeV determined for the anticipated 200 MHz RF system at nominal intensity. At 7 TeV the shunt impedance is limited to 300 kohm determined for the 400 MHz RF system assuming a longitudinal emittance of 2.5 evs. The exact impedance budget is strongly dependent on the frequency of the HOMs. Transverse feedback with 20 MHz bandwidth is also available with a damping time down to less than 1.8 ms achieved already in the 2010 run. The damping specification at 0.45 TeV is 3.6 ms which corresponds to 40 turns. At 7 TeV the damping specification is expected to be about 60 ms. The transverse impedance budget for crab cavities is limited to 0.8 MOhm/m/#cc at 800 MHz for ultimate intensities using a pessimistic scenario. Rama Calaga remarked that one might need updated impedance curve for 400 (or 800) MHz crab cavities that can be used by the cavity designers. Elena Shaposhnikova replied that there were two curves: the second, lower curve assumed that the beam was captured by a 200-MHz system; if the 200 MHz capture system was not installed the crab-cavity designers could use the upper curve. Summary: The 2010 experience is already folded into some of the studies. A promising first HL- LHC optics solution for a low-beta lattice with local crab cavities is available. Some margin exists in the parameters of the separation dipoles. The impact of leveling on overall performance was shown. The impedance bounds were discussed. The question was raised whether these bounds are realistic. Steve Myers asked how the field quality would be specified. Massimo Giovannozzi responded that the specification would come from simulations. 3.3 CAVITY TECHNOLOGY AND CRYOMODULES Session Convener: Edmond Ciapala Several talks spanning compact cavity designs, cryomodule, tuners and ancillaries were given. The abstracts for the talks had been geared to move forward on realizing the four major contenders from LHC-CC09. The recommendations in 2009 had been to develop compact cavities suitable for both local and global schemes. Complete conceptual designs, followed by a down select to 1 or 2 candidates with full specifications and engineering drawings were requested in This is now foreseen for the end of In the HL-LHC plan, 2 major milestones are defined, 1) compact cavity technology validation and 2) later implementation into a prototype cryomodule by Tuning systems are not yet ready for design specification as they are highly dependent on the cavity topology. A common platform might be impossible. An initial layout of the cryostat has 7

8 started for some of the designs. Baseline for local CC is to accommodate the second beam inside the He tank. At present four compact contenders satisfying the LHC constraints at 400 MHz are available, and a new one has been proposed at the LHC-CC10 workshop. The SLAC design is well advanced and robust with some complicated coupler designs. The JLab-ODU parallel bar cavity with an improved design is much more efficient than the previous version, with fewer higher order modes and a larger separation from the operating mode. The 4-rod design is cell optimized for surface fields, and higher order mode damping concepts are also well advanced with LEP type hook couplers on the top and bottom of the cavities. Kota cavities from KEK were not discussed. A new idea on a ¼-wave cavity was presented by BNL. The possible side effect of residual acceleration needs to be addressed. A slim cavity at 800 MHz also seems as a viable option. Cavity characteristics are well advanced and defined. The non-linearity of the deflecting voltage is below the percent level as has been calculated from a numerical fit at 17mm reference radius for atleast two of the designs. Further optimization is possible when specifications are given. Multipacting and tuning concepts need to be studied in greater detail. Other issues such as fabrication, cleaning, assembly, He vessel etc... also need detailed studies. No fundamental show stopper for embarking on compact cavity technology and hardware prototypes were identified. Excellent progress since the goals set from the last workshop. Fairly advanced engineering designs exist for some of the designs. Therefore, the plan to reach HL-LHC milestone 1 is defined and awaiting cavity prototype validation. Designs of the cryomodules and ancillaries should continue to be finalized after the 1 st milestone is reached. In summary, clear set of specifications are needed for both vertical and horizontal cavities. Engineering complications arising from the need to crab in either plane need to be addressed immediately. Couplers were discussed see later. Steve Myers asked how one would decide which of the proposed designs should be prototyped, or if several designs should all be prototyped. Ed Ciapala commented that most likely three designs would be prototyped by the respective promoters. Frank Zimmermann suggested to also include the QWR of Ilan Ben-Zvi in this list. Ilan Ben-Zvi commented that the QWR cavity had already been tested with beam in the other direction. Important action items were identified: Establish precise impedance budget for beam stability with the current baseline of 8 cavities per beam. Experimental verification of dynamic failures (multipacting and fast quenches). Early construction of a full prototype CC for early test in the SPS? 8

9 Steve Myers observed that the cryomodule was not independent of the cavity. Ed Ciapala commented that a first stage test of all cavities could be performed in the same vertical test stand, and that some work could go on in parallel for the different designs. Steve Myers expressed a concern about the cavity field quality. Stephane Fartoukh highlighted the question of cavity alignment. Ali Al-Nassiri reported that 100 micron cavity alignment had been achieved for light sources; some pertinent work was ongoing in collaboration with JLAB. Jean Delayen pointed out that the crab-cavity design had progressed beyond the point that had been specified, and that, therefore, a more complete set of specifications was required. Steve Myers asked if the frequency had been decided. The answer was yes. The frequency agreed upon for all compact designs is 400 MHz. Graeme Burt clarified that there was no overlap of the LHC crab-cavity design with the CLIC crab cavity. Riccardo De Maria observed that not all the cavities presented could be integrated for both vertical and horizontal crossing. Philippe Lebrun inquired if an extended specification would favor one or the other design. Erk Jensen replied that the cavity designers had not yet taken into account the field linearity requirements, but could do so if required. Ali Al-Nassiri suggested publishing complete specification in order to arrive at a final design. Frank Zimmermann commented that the maximum voltage and the trip rate should be an important part of the specification, though the trip rate might not be predictable in the design process. Tor Raubenheimer suggested that the engineering demonstration would be very important. Steve Myers reiterated his earlier question if 3 cavities were too many. Graeme Burt answered that two of these designs would move forward anyway. Steve Myers added that Ilan Ben-Zvi would build one, too. CERN could construct the fourth one. Ed Ciapala stressed that there was significant synergy with other projects. 3.4 CRAB CAVITY BEAM STUDIES AND INSTRUMENTATION Session Convener: Paul Collier Results from the KEK noise experiments are very interesting. Little or no problem was observed when the noise spectrum remained outside the beam spectrum. Small amounts of noise close to the betatron tunes could be catastrophic, on the other hand. An instability driven by beambeam in the presence of noise excitation at frequencies between the sigma and pi mode was observed. Approximately deg of phase noise control seemed ok from preliminary simulations for the LHC using a rigid model. The LHC hump is 10 times smaller than this number. Concerning the installation of a KEK cavity in the SPS, the available space in LSS4 is sufficient but integration appears complicated. In addition the frequency is non-ideal and therefore forcing a special configuration in the SPS for beam test. The full installation including the refurbishment 9

10 and transport to CERN is not cheap. In 2010, two beam experiments had been performed in the SPS in coast to prepare for a possible experiment with a KEK cavity. The main observation was a significant emittance growth at least in the horizontal plane without any external excitation. To study the effects of crab cavities on emittance growth in the SPS, the natural emittance growth needs more investigation and mitigation measures. Else it may require a vertical crab cavity for an SPS test and potentially higher voltages to kick at higher energy coasts. Synchronization between main RF and KEK cavity frequency may be difficult and may introduce noise which will be difficult to separate from the actual crab cavity phase noise. Measuring all relevant quantities will be challenging with KEK cavities and will need a lot of resources. Validity tests of the LHC prototype compact crab-cavities in the SPS should be performed at the latest by the end of 2016 before the final decision on the construction for the HL-LHC crab cavities is taken. An SPS test cannot access beam-beam driven noise instabilities. Therefore, an LHC test before a full installation in the LHC is obligatory. In addition the LHC has better instrumentation, for example, a head-tail monitor with 4 GHz bandwidth (versus 2.5 GHz in the SPS). It is recommended to test crab cavities that are as close as possible to final design as the schedule towards final implementation is tight. Therefore, the idea of testing a KEKB crab cavity at the SPS has been abandoned and it was suggested to focus all efforts on a real LHC cavity. A decision on an elliptical or compact cavity for the SPS tests should be taken soon. Measures to address the SPS emittance growth problem should be pursued in the coming years, in order to enhance the usefulness of future crab-cavity tests. Steve Myers commented on specifications with respect to the possible impact of the crab-cavity prototype on the LHC. In the case of the SPS test, the proposed bypass should solve this problem. Ilan Ben-Zvi quoted the example of the 56 MHz frequency cavity for RHIC, where an FOM damper makes it look like the cavity is not there (Q value reduced down to 300). In the meantime one will need to spend time understanding SPS without crab cavities Elena Shaposhnikova commented that at the time of ppbar collisions there had been a single bunch operation, while the SPS crab-cavity tests were performed with bunch trains. Bunches of smaller intensity and higher energy should be tried. Specifications on crab-cavity field quality will be provided by Massimo Giovannozzi. Rama Calaga suggested that the solution proposed by Philippe Baudrenghien for injection & ramp should be tested in the SPS Wolfgang Hofle commented that regarding LLRF, feedback, etc., many items could be tested in the SPS. An SPS test would reduce the risk of a long commissioning in the LHC. 10

11 3.5 MACHINE PROTECTION Session Convener: Jörg Wenninger Machine protection and criticality are strongly correlated to the luminosity gain. Up to 4 sigma kicks with 15 cm beta* can be expected due to a crab-cavity failure with the proposed optics. Simulations have been only very preliminary, and more detailed studies are needed. Realistic models of the beam distribution and of the RF failure dynamics are essential for correctly modeling and understanding the impact on machine protection. Tail distributions could/should be adjusted to what had been measured in 2010 (1-3% of the beam in last beam sigma). In addition, the upgrade collimation with cryo-collimators should be included in the simulations for a complete understanding. MP considerations also need as input the maximum acceptable losses on specific collimators (latest) for a worst case scenario with beam loss between 1-10 turns. No show stoppers from the collimation simulations using halo tracking have been found for the nominal LHC, but the same analysis still has to be done with the SLHC optics. As a reference, all electrical circuits in the LHC had been analyzed for criticality to adjust interlocking. It is crucial to understand the quench and multipacting processes that were highlighted as possible failure modes of interest. KEK has observed a wide range of failures. Are these failures specific to each cavity design? One should agree on reference failure scenarios for simulations of realistic failures. Input from RF experts for this topic is highly desired. A decision on using multiple cavities to help alleviate MP should be taken. The final frequency choice is also important in order to focus the simulations. There still exists an 800 MHz option. The collimation system needs further optimization for the best possible protection and performance in conjunction with crabbed beams. Possible issues along the LHC cycle of operation need to be studied. Operation with a prototype crab-cavity in the SPS will be extremely interesting for MP studies. First simulations indicate that a test in the LHC with the nominal optics cannot lead to catastrophic failures, which was an interesting outcome. Several possible paths have been proposed for optimizing machine protection with crab cavities. Critical is the operation with crab cavities all along the cycle. Installing proto-type cavity in the SPS for beam tests should be given adequate priority Oliver Brüning suggested that when optimizing the collimation system the absolute collimator gaps in number of mm should be maintained. Eric Prebys did not see how testing a crab cavity different from the one ultimately installed in the LHC, such as the KEKB crab cavity, could provide any information. Jean-Pierre Koutchouk recommended establishing a calendar of failure scenarios. 11

12 3.6 RF CONTROLS & TESTING Session convener: Jean Delayen The scheme developed at KEKB to determine the cavity center is innovative and will also be useful for cavity alignment in the LHC. Several discussions on the instabilities at KEK took place. For example a large betatron amplitude oscillation at high currents with colliding beam was observed.. The instability was only seen only in the presence of beam-beam collisions, and depended on the crabbing phase and was concluded to be beam loading related effect. It was remedied with static shift of the crabbing phase. Cavity trips were reduced to the order of 1/day. It appeared that the trips were caused predominantly by the couplers and not by the cavities proper. A weak correlation of the trip rate with the beam current, but a strong correlation with the cavity voltage has been observed. Preparation and assembly are well known. Facilities suitable for crab-cavity power tests are available at a number of places. In particular, high-power tests are possible and the required facilities are available at CERN. A cryogenic upgrade of SM18 is necessary for both SPL R&D and crab cavities. 400 MHz at 4.5K is a logical combination, but 4.5 K would be difficult at 800 MHz. However, 2K is difficult in the LHC tunnel at 30 mbar. A temperature decision needs to be finalized soon. The design of the cavity, couplers and ancillaries should include different cooling circuits at different operating temperatures. An operational scenario for making the crab cavities invisible during injection and ramp should be defined and tested. No show stoppers were seen, but several issues related to failure scenarios need more detailed investigation. Loaded Q specifications must be determined taking into account technology and machine protection constraints. A complete set of specifications and requirements are needed as soon as possible including crossing planes, field quality, impedance and other relevant information. A real LHC cavity is preferable for the tests. Vertical cryostats are also available at other places around the world. For the LLRF operational scenario a number of open questions need to be addressed. Philippe Lebrun commented on the SPS test, highlighting space constraints and cryogenics limitations. 3.7 SCHEDULE & FUTURE OUTLOOK Session Convener: Roland Garoby The summary of this session started with a review of the HL-LHC project, which is aiming at improving the LHC luminosity beyond the nominal reach. The high-luminosity LHC design study is only a small part of the HL-LHC project. The total cost of project and study are estimated at 500 ME and 27 ME respectively. An overall cost estimate of 80 MCHF for the crab project and an associated 150 FTE man years was given. Other applications and projects requiring crab cavities were also discussed. For example, crab-cavity can removing the effect of the transient beam loading at the collision point, and momentum cleaning were two LHC 12

13 applications being highlighted. Several electron ion colliders anticipate the use of crabs with required crab voltages between 2 MV and 200 MV. To address the field quality for the RF cavity a specification is needed from optics and beam simulations. Development and implementation of LHC crab cavities needs a consistent global planning. The precise purpose of the SPS tests should be outlined. Requirements such as deflecting field, direction of kick, dimensions, acceptable non-linearities, impedance, and constraints from machine protection need all be specified The question was raised whether one could run for physics if one cavity was not operational. 4 ADVISORY BOARD MEETINGS AND COMMENTS 4.1 PARTICIPANTS T. Baer, I. Ben Zvi, C. Bhat, O. Bruning, G. Burt, J. Byrd, R. Calaga, E. Ciapala, P. Collier, J. Delayen, R. De Maria, S. De Silva, T. Ekelof, S. Fartoukh, Y. Funakoshi, L. Ficcadenti, R. Garoby, M. Giovannozzi, W. Hofle, K. Hosoyama, E. Jensen, H. Kim, J.-P. Koutchouk, P. Lebrun, Z. Li, E. Metral, S. Myers (Chair), K. Nakanishi, A. Nassiri, V. Parma, E. Prebys, T. Raubenheimer, E. Shaposhnikova, B. Strauss, J. Tuckmantel, W. Weingarten, J. Wenninger, A. Yamamoto, F. Zimmermann 4.2 MEETING COMMENTS Steve Myers summarized the main conclusions of the LHC-CC 10 workshop and the subsequent advisory board session. 1. For the KEK-B crab-cavity test, the answer was no. Such test was discarded for a number of reasons. 2. The final LHC crab-cavity scheme should be the local scheme only. 3. The crab-cavity frequency was set to be 400 MHz. 4. Whether machine protection could be a possible showstopper was still not absolutely clear. No hard obstacle had been found in preliminary studies, but a lot more work was required on this topic. 5. There was almost no synergy with CLIC crab-cavity technology, the sole exception being the LLRF. 6. No show stoppers had been encountered for compact crab cavities. At least 3-4 mature designs were available now. Stephane Fartoukh asked for the consequences if no local solution would be found. Steve Myers answered that the choice of local scheme could be reconsidered later if the development of compact crab cavities or the associated optics were unsuccessful, and/or if strong new arguments would favour a global or hybrid scheme. The original workshop charge had been threefold: 13

14 1. Can compact cavities for the LHC be realized and made robust with the complex damping schemes? 2. Are crab cavities compatible with LHC machine protection, or can they be made to be so? 3. Should a KEKB crab cavity be installed in the SPS for test purposes? The answers for points 1 and 3 had been given. There had been progress on point 2, but this was still an open issue. Complete specifications for further optimization were stressed to be of uttermost importance to the crab-cavity designers. 4.3 OPEN ISSUES AND ACTION ITEMS Steve Myers and the other advisory board members plus meeting participants compiled the following points for further follow up. (1) Specifications One wants to be able to make cavity invisible for many reasons (ramping, testing, when not operational) this possibility was a sine qua non. Specifications could come from Massimo Giovannozzi and his team; the crab cavities should be transparent with regard to optics and beam operation. Impedance and field quality had to be specified. Could one damp the fundamental mode? The need for a dynamic alignment of the crab cavities in-situ has be first clarified and appropriate specification should be derived. Is this dynamic alignment easily feasible at cold temperature and to what level? The trip rate should be part of the specification, as a function of voltage, and its effect on impedance on the beam has to be studied. Horizontal and vertical crossing might need two types of cavities. A single system is preferable for ease of technical maintenance among other reasons but not a requirement if specific cavities if different cavities are more efficient for different planes while maintaining the same horizontal space constraint of 192 mm separation. (2) Testing, SPS and/or LHC What do we need to test? Machine protection, making the cavities invisible, etc The final collimation system, different from the present one, may have an impact on the cavity qualification. Concerning a test with an LHC prototype cavity in the SPS, what could be learnt from an SPS test? 14

15 (3) Prototypes Prototyping of compact crab cavities should continue Also power couplers should be tested. Each cavity needed a special power coupler, but a common platform for power coupler development is highly desirable to focus the R&D. Cryomodule time line should be defined. Paul Collier suggested using a generic cryomodule for the tests of all cavities. Erk Jensen confirmed that it would indeed be possible to perform the first test in identical cryostat for all cavities. Ed Ciapala, Erk Jensen and Wolfgang Weingarten reported that a suitable cryostat already existed at CERN. The development of the cryomodules for the final LHC compact crab cavities was included in the HL-LHC design study, which was considered to be sufficient. (4) Other issues Steve Myers stressed that other potential applications of crab cavities should be looked at, such as off-momentum cleaning, compensation of beam loading, emittance exchange, beam instrumentation and use towards future projects such as LHeC and HE- LHC. (5) Roadmap The CERN-RF group will sketch a roadmap with milestones and resources to be presented to LMC before the end of summer Erk Jensen reported that together with Ed Ciapala and Rama Calaga he had described the overall crab-cavity project. He proposed to distribute this draft document to the community. Concerning the machine-protection issues, Ilan Ben-Zvi suggested developing a dynamic model of cavity breakdown and the exact time dependence, based on the physics of cavities. Jean- Pierre Koutchouk added that this model should then be combined with a beam tracking model. Oliver Bruning remarked that the most pessimistic case simulation looked challenging from the machine-protection point of view. However, it is unclear if this is a realistic scenario. Frank Zimmermann commented that an early crab-cavity quench detection system was needed, in analogy to the quench protection system of the LHC SC magnets. Ilan Ben-Zvi reported that RHIC will install a 56 MHz SRF cavity which heavily damps the operating mode when not required. One response to a detected trip onset would be to turn off two cavities simultaneously. Philippe Baudrenghien observed that segmenting into several independent systems was another mitigation measure. 15

16 Protection might need to be balanced against reliability. However, more modules (of lower voltage each) could also lead to higher reliability. Eric Prebys inquired about the need of both horizontal and vertical crab cavities. The response was that the crab cavities would assist in leveling, and that the standard LHC had alternating planes of crossing. The proposed crab-cavity system should therefore work in both planes. Tor Raubenheimer commented that other activities besides the RF designers needed a list of final specifications to focus the development. Paul Collier asked if 1.9 K was needed to reach the target field, or if the cavities could be operated at 4.5 K as well, for the SPS test or LHC IP4 test. This was not excluded. One would need to know how the cavities behaved at 4.5 K. Philippe Lebrun commented that when operating the cavities in boiling gas one needed to get vapor out. Superfluid helium at 1.9 K did not only provide a higher field, but also cooling without bubbles. Rama Calaga suggested that higher temperature could be possible, at least for the tests. Jean Delayen pointed out that spoke cavities were running at higher temperature. Wolfgang Weingarten estimated that the power dissipation at 4.5 K would be W per cavity. The exact dynamic load should be calculated with appropriate cavity designs and heat loads, the KEK-B requires about 100 W of dynamic heat load. Paul Collier observed that this might possibly exclude the SPS tests. Responding to a question by Stephane Fartoukh, it was clarified that beam-beam simulations by Kazuhito Ohmi (KEK) had demonstrated that a perfect cavity was very good for the LHC (increasing the beam-beam lifetime by a factor of 10). 16

Running in 2011 - Luminosity. Mike Lamont Verena Kain

Running in 2011 - Luminosity. Mike Lamont Verena Kain Running in 2011 - Luminosity Mike Lamont Verena Kain Presentations Many thanks to all the speakers! Experiments expectations Massi Ferro-Luzzi Pushing the limits: beam Elias Métral Pushing the limits:

More information

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN

BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN BEPC UPGRADES AND TAU-CHARM FACTORY DESIGN Abstract BEPC Group, presented by Yingzhi Wu Institute of High Energy Physics, Beijing 100039, P.R. China The luminosity upgrades of the BEPC are briefly reviewed.

More information

LHC MACHINE PROTECTION

LHC MACHINE PROTECTION LHC MACHINE PROTECTION Rossano Giachino, CERN, Geneva, Switzerland Abstract The energy stored in LHC magnets presents a considerable challenge for commissioning even before any beam is injected. Furthermore,

More information

Zero Degree Extraction using an Electrostatic Separator

Zero Degree Extraction using an Electrostatic Separator Zero Degree Extraction using an Electrostatic Separator L. Keller Aug. 2005 Take another look at using an electrostatic separator and a weak dipole to allow a zero degree crossing angle a la the TESLA

More information

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I)

HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I) 28. High-energy collider parameters 1 HIGH-ENERGY COLLIDER PARAMETERS: e + e Colliders (I) Updated in early 2012 with numbers received from representatives of the colliders (contact J. Beringer, LBNL).

More information

FCC 1309180800 JGU WBS_v0034.xlsm

FCC 1309180800 JGU WBS_v0034.xlsm 1 Accelerators 1.1 Hadron injectors 1.1.1 Overall design parameters 1.1.1.1 Performance and gap of existing injector chain 1.1.1.2 Performance and gap of existing injector chain 1.1.1.3 Baseline parameters

More information

LHC optics measurement & correction procedures. M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove

LHC optics measurement & correction procedures. M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove LHC optics measurement & correction procedures M. Aiba, R. Calaga, A. Morita, R. Tomás & G. Vanbavinckhove Thanks to: I. Agapov, M. Bai, A. Franchi, M. Giovannozzi, V. Kain, G. Kruk, J. Netzel, S. Redaelli,

More information

Brookhaven Magnet Division - Nuclear Physics Program Support Activities

Brookhaven Magnet Division - Nuclear Physics Program Support Activities Brookhaven - Nuclear Physics Program Support Activities Spin Program support E-Cooling R&D RIA RHIC Operations Support Funding AGS Warm Siberian Snake AGS Warm Snake Magnetic element designed and built

More information

Large Systems Commissioning

Large Systems Commissioning Large Systems Commissioning, DESY CAS Vacuum in Accelerators Platja D`Aro, May 21, 2006 Special thanks to O. Gröbner 1 Outline Introduction Pump Down and Leak Check Components Check Bake Out Interlocks/Safety

More information

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides

The BESSY HOM Damped Cavity with Ferrite Absorbers. Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides The BESSY HOM Damped Cavity with Ferrite Absorbers E. Weihreter / BESSY Review of prototype cavity test results, taperedwaveguidesvshomogenouswaveguides Design of a ferrite loaded ridged circular waveguide

More information

10 Project Costs and Schedule

10 Project Costs and Schedule II-367 10 Project Costs and Schedule 10.1 Overview The investment costs given in this chapter include all components necessary for the baseline design of TESLA, as described in chapters 3 to 9. Not included

More information

Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities

Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities Investigations on Critical Higher Order Modes in CEBAF Upgrade Cavities F. Marhauser Thanks also to H. Wang and K. Tian 27. August 2009 How HOMs are excited and why they are important - Wakefields- some

More information

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES

THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES THE ALIGNMENT STRATEGY FOR THE SPIRAL2 SUPERCONDUCTING LINAC CRYOMODULES R. Beunard, GANIL, BP 55027, 14076 CAEN, CEDEX 5, France Abstract The SPIRAL2* project, located at the GANIL** facility in Caen,

More information

Projects and R&D activities

Projects and R&D activities Projects and R&D activities J.M. Jimenez On behalf of the Vacuum, Surface and Coatings Group (VSC) Vacuum, Surface and Coatings group* Mandate Design, construction, operation, maintenance and upgrade of

More information

Possible Upgrades and New Design. F. Velotti and B. Goddard

Possible Upgrades and New Design. F. Velotti and B. Goddard Possible Upgrades and New Design F. Velotti and B. Goddard Outline Possible system upgrade General principles TIDVG modifications needed MKDV modifications needed External beam dump study Requirements

More information

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source

Frequency Map Experiments at the Advanced Light Source. David Robin Advanced Light Source Frequency Map Experiments at the Advanced Light Source David Robin Advanced Light Source work done in collaboration with Christoph Steier (ALS), Ying Wu (Duke), Weishi Wan (ALS), Winfried Decking (DESY),

More information

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group

Status of the Diamond Storage Ring RF Systems. Morten Jensen on behalf of Diamond Storage Ring RF Group Status of the Diamond Storage Ring RF Systems Morten Jensen on behalf of Diamond Storage Ring RF Group Content 1. General Operational Status 2. Main issues and causes of trips 3. 200 ma + operation Qext

More information

Lecture VI Magnetic Design

Lecture VI Magnetic Design Lecture VI Magnetic Design Field Quality Adjustment After Construction (or After the Start of Production Run) Ramesh Gupta Superconducting Brookhaven National Laboratory US Particle Accelerator School

More information

Results: Low current (2 10 12 ) Worst case: 800 MHz, 12 50 GeV, 4 turns Energy oscillation amplitude 154 MeV, where

Results: Low current (2 10 12 ) Worst case: 800 MHz, 12 50 GeV, 4 turns Energy oscillation amplitude 154 MeV, where Status Focus has shifted to a neutrino factory Two comprehensive designs of acceleration (liancs, arcs) Jefferson Lab, for Fermilab Study CERN (Keil et al.) Jefferson Lab study Low (2 10 12 ) charge per

More information

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006

Tune and Chromaticity Tracking in the Tevatron. C.Y. Tan 09 May 2006 Tune and Chromaticity Tracking in the Tevatron C.Y. Tan 09 May 2006 Overview What is the Tevatron tune tracker? Selected results from some stores. (There are many stores with TT running). Planned chromaticity

More information

The commissioning of the LHC: first the technical systems, then the commissioning with beam

The commissioning of the LHC: first the technical systems, then the commissioning with beam The commissioning of the LHC: first the technical systems, then the commissioning with beam Roberto Saban 4. Ulusal Parçacık Hızlandırıcıları ve Uygulamaları Kongresi 30 Ağustos 1 Eylül 2010, Bodrum -

More information

Development of a Low Frequency Superconducting RF Electron Gun. September 2010

Development of a Low Frequency Superconducting RF Electron Gun. September 2010 Development of a Low Frequency Superconducting RF Electron Gun Contract DE-FG02-07ER84861 07ER84861 Terry Grimm September 2010 Outline Collaboration Concept Scientific justification Design electromagnetic

More information

Status of IP FB system design

Status of IP FB system design Status of IP FB system design Philip Burrows Douglas Bett, Glenn Christian, Michael Davis, Alexander Gerbershagen*, Colin Perry John Adams Institute Oxford University Robert Apsimon, Ben Constance CERN

More information

Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:1606.06697v1 [physics.acc-ph] 21 Jun 2016

Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:1606.06697v1 [physics.acc-ph] 21 Jun 2016 Beam Dynamics Studies and Design Optimisation of New Low Energy Antiproton Facilities arxiv:606.06697v [physics.acc-ph] 2 Jun 206 Javier Resta-Lopez, James R. Hunt, Carsten P. Welsch Department of Physics,

More information

Calculation of Eigenmodes in Superconducting Cavities

Calculation of Eigenmodes in Superconducting Cavities Calculation of Eigenmodes in Superconducting Cavities W. Ackermann, C. Liu, W.F.O. Müller, T. Weiland Institut für Theorie Elektromagnetischer Felder, Technische Universität Darmstadt Status Meeting December

More information

Activities at the University of Frankfurt (IAP)

Activities at the University of Frankfurt (IAP) Activities at the University of Frankfurt (IAP) Holger Podlech Ulrich Ratzinger Oliver Kester Institut für Angewandte Physik (IAP) Goethe-Universität Frankfurt am Main H. Podlech 1 Development of 325 MHz

More information

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson

A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson FERMILAB-CONF-11-258-AD FERMILAB SRF CRYOMODULE OPERATIONAL EXPERIENCE A. Martinez, A. L. Klebaner, J. C. Theilacker, B. D. DeGraff, M. White and G. S. Johnson Fermi National Accelerator Laboratory Batavia,

More information

MYRRHA Injector Design

MYRRHA Injector Design MYRRHA Injector Design Horst Klein Dominik Mäder, Holger Podlech, Ulrich Ratzinger, Alwin Schempp, Rudolf Tiede, Markus Vossberg, Chuan Zhang Institute for Applied Physics, Goethe-University Frankfurt

More information

Calorimetry in particle physics experiments

Calorimetry in particle physics experiments Calorimetry in particle physics experiments Unit n. 8 Calibration techniques Roberta Arcidiacono Lecture overview Introduction Hardware Calibration Test Beam Calibration In-situ Calibration (EM calorimeters)

More information

RF SYSTEM FOR VEPP-5 DAMPING RING

RF SYSTEM FOR VEPP-5 DAMPING RING Ó³ Ÿ. 2006.. 3, º 7(136).. 60Ä64 Š 621.384.634.14 RF SYSTEM FOR VEPP-5 DAMPING RING Ye. Gusev, N. Kot, S. Krutikhin, I. Kuptsov, G. Kurkin, I. Makarov, N. Matyash, L. Mironenko, S. Motygin, V. Osipov,

More information

Machine Protection and Interlock Systems for Circular Machines Example for LHC

Machine Protection and Interlock Systems for Circular Machines Example for LHC Published by CERN in the Proceedings of the Joint International Accelerator School: Beam Loss and Accelerator Protection, Newport Beach, US, 5 14 November 2014, edited by R. Schmidt, CERN-2016-002 (CERN,

More information

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK

THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK THE TESLA TEST FACILITY AS A PROTOTYPE FOR THE GLOBAL ACCELERATOR NETWORK K. Rehlich, DESY, Hamburg, Germany Abstract The next generation of large accelerators facilities will be produced and operated

More information

Status of the HOM Damped Cavity for the Willy Wien Ring

Status of the HOM Damped Cavity for the Willy Wien Ring Status of the HOM Damped Cavity for the Willy Wien Ring Ernst Weihreter / BESSY Short Review of HOM Damped Cavity Prototype Modifications for the Willy Wien Ring Cavity Results of Low Power Measurements

More information

Damping Wigglers in PETRA III

Damping Wigglers in PETRA III Damping Wigglers in PETRA III WIGGLE2005, Frascati 21-22.2.2005 Winni Decking, DESY-MPY Introduction Damping Wiggler Parameters Nonlinear Dynamics with DW Operational Aspects Summary DESY and its Accelerators

More information

Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth

Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth LHC - BOLD BEGINNING Mike Lamont Thanks for discussion and input to: Oliver Bruning, Stephane Fartoukh, Ray Veness, Serge Claudet, Roberto Saban, Ralph Assmann, Andy Butterworth Lend thy fresh beams our

More information

LLRF. Digital RF Stabilization System

LLRF. Digital RF Stabilization System LLRF Digital RF Stabilization System Many instruments. Many people. Working together. Stability means knowing your machine has innovative solutions. For users, stability means a machine achieving its full

More information

Status of the SOLEIL project Commissioning from Linac to beamlines

Status of the SOLEIL project Commissioning from Linac to beamlines Status of the SOLEIL project Commissioning from Linac to beamlines On behalf of the commissioning team 2 D01-1-CX1/DT/DTC/absorption Y Axis Title 0-200 0 200 400 600 800 1000 1200 1400 X Axis Title 1 Site

More information

The design and performance of Static Var Compensators for particle accelerators

The design and performance of Static Var Compensators for particle accelerators CERN-ACC-2015-0104 Karsten.Kahle@cern.ch The design and performance of Static Var Compensators for particle accelerators Karsten Kahle, Francisco R. Blánquez, Charles-Mathieu Genton CERN, Geneva, Switzerland,

More information

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS*

FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS* FIVE PROJECTS OF HIGH RF POWER INPUT COUPLERS & WINDOWS FOR SRF ACCELERATORS* Quan-Sheng Shu, Joe Susta, Guangfeng Cheng AMAC International Inc., 12050 Jefferson Ave, Newport News, VA 23606 Abstract Various

More information

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues

FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues FLS 2010 Storage Ring Working Group Session 4: Future ring technology and design issues 10:45 11:10 Limits to achievable stability Glenn Decker, APS 11:10 11:35 Stability and alignment of NSLS II magnet

More information

C.-K. Ng. Stanford Linear Accelerator Center. and. T. Weiland. University oftechnology. FB18, Schlossgartenstr. 8. D64289, Darmstadt, Germany.

C.-K. Ng. Stanford Linear Accelerator Center. and. T. Weiland. University oftechnology. FB18, Schlossgartenstr. 8. D64289, Darmstadt, Germany. SLAC-PUB-95-7005 September, 1995 Impedance of the PEP-II DIP Screen C.-K. Ng Stanford Linear Accelerator Center Stanford University, Stanford, CA 94309, USA and T. Weiland University oftechnology FB18,

More information

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator

Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator Development of Radiation Resistant Quadrupoles Based on High Temperature Superconductors for the Fragment Separator R. Gupta and M.Harrison, Brookhaven National Laboratory A. Zeller, Michigan State University

More information

Robot Perception Continued

Robot Perception Continued Robot Perception Continued 1 Visual Perception Visual Odometry Reconstruction Recognition CS 685 11 Range Sensing strategies Active range sensors Ultrasound Laser range sensor Slides adopted from Siegwart

More information

RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure

RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure RF-thermal-structural-RF coupled analysis on the travelling wave disk-loaded accelerating structure PEI Shi-Lun( 裴 士 伦 ) 1) CHI Yun-Long( 池 云 龙 ) ZHANG Jing-Ru( 张 敬 如 ) HOU Mi( 侯 汨 ) LI Xiao-Ping( 李 小

More information

Development and optimization of a hybrid passive/active liner for flow duct applications

Development and optimization of a hybrid passive/active liner for flow duct applications Development and optimization of a hybrid passive/active liner for flow duct applications 1 INTRODUCTION Design of an acoustic liner effective throughout the entire frequency range inherent in aeronautic

More information

Understanding Power Impedance Supply for Optimum Decoupling

Understanding Power Impedance Supply for Optimum Decoupling Introduction Noise in power supplies is not only caused by the power supply itself, but also the load s interaction with the power supply (i.e. dynamic loads, switching, etc.). To lower load induced noise,

More information

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES*

OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES* FERMILAB-CONF-06-213-AD OVERVIEW OF PROTON DRIVERS FOR NEUTRINO SUPER BEAMS AND NEUTRINO FACTORIES* W. Chou #, Fermilab, Batavia, IL 60510, U.S.A. Abstract There has been a world-wide interest in Proton

More information

The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead

The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead The High Luminosity LHC (HL-LHC) Project at CERN: The Challenge Ahead R. Kersevan Vacuum Surfaces and Coatings Group, Technology Department, CERN, Geneva The HiLumi LHC Design Study is included in the

More information

Robotic motion planning for 8- DOF motion stage

Robotic motion planning for 8- DOF motion stage Robotic motion planning for 8- DOF motion stage 12 November Mark Geelen Simon Jansen Alten Mechatronics www.alten.nl rosindustrial@alten.nl Introduction Introduction Alten FEI Motion planning MoveIt! Proof

More information

& Tunnel Cross Section

& Tunnel Cross Section CLIC workshop Working group: Two beam hardware and Integration ti CLIC Civil Engineering Layouts & Tunnel Cross Section John Osborne TS-CE Acknowledgements : C.Wyss, J-L Baldy, N.Baddams 17 October 2007

More information

Dual H&D Cavity for the PAX Target Polarimeter

Dual H&D Cavity for the PAX Target Polarimeter Dual H&D Cavity for the PAX Target Polarimeter M. Capiluppi a, V. Carassiti a, G. Ciullo a, P. Lenisa a, A. Nass b, and E. Steffens c a INFN Ferrara, Italy b IKP, Research Center Jülich, Germany c Univ.

More information

DDX 7000 & 8003. Digital Partial Discharge Detectors FEATURES APPLICATIONS

DDX 7000 & 8003. Digital Partial Discharge Detectors FEATURES APPLICATIONS DDX 7000 & 8003 Digital Partial Discharge Detectors The HAEFELY HIPOTRONICS DDX Digital Partial Discharge Detector offers the high accuracy and flexibility of digital technology, plus the real-time display

More information

(Refer Slide Time: 01:52)

(Refer Slide Time: 01:52) Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This

More information

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004

DOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004 DOE LHC Quarterly Review Magnet Production Cable Testing Cost to Complete issues Mike Harrison, BNL July 26, 2004 1 BNL Production Status Magnet production complete The last series of dipoles (D3 s) is

More information

Understanding Mixers Terms Defined, and Measuring Performance

Understanding Mixers Terms Defined, and Measuring Performance Understanding Mixers Terms Defined, and Measuring Performance Mixer Terms Defined Statistical Processing Applied to Mixers Today's stringent demands for precise electronic systems place a heavy burden

More information

Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting

Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting Coupling Impedance of SIS18 and SIS100 beampipe CERN-GSI-Webmeeting 23 October 2011 TU Darmstadt Fachbereich 18 Institut Theorie Elektromagnetischer Felder Uwe Niedermayer 1 Contents Motivation / Overview

More information

Reliability and Availability Aspects of. the IPHI Project

Reliability and Availability Aspects of. the IPHI Project Reliability and Availability Aspects of the IPHI Project Pierre-Yves Beauvais CEA/DSM/DAPNIA for the IPHI Team 18/02/2002 Pierre-Yves Beauvais, CEA Saclay 1 Table of contents Brief description of IPHI

More information

E. K. A. ADVANCED PHYSICS LABORATORY PHYSICS 3081, 4051 NUCLEAR MAGNETIC RESONANCE

E. K. A. ADVANCED PHYSICS LABORATORY PHYSICS 3081, 4051 NUCLEAR MAGNETIC RESONANCE E. K. A. ADVANCED PHYSICS LABORATORY PHYSICS 3081, 4051 NUCLEAR MAGNETIC RESONANCE References for Nuclear Magnetic Resonance 1. Slichter, Principles of Magnetic Resonance, Harper and Row, 1963. chapter

More information

CAVITY DESIGN REPORT

CAVITY DESIGN REPORT 1. Means CAVITY DESIGN REPORT V. Serrière, A. K. Bandyopadhyay, A. Triantafyllou, J. Jacob This work constitutes the first deliverable WP13.1 of Working Package WP13, carried out within the framework of

More information

The accurate calibration of all detectors is crucial for the subsequent data

The accurate calibration of all detectors is crucial for the subsequent data Chapter 4 Calibration The accurate calibration of all detectors is crucial for the subsequent data analysis. The stability of the gain and offset for energy and time calibration of all detectors involved

More information

Anatech Electronics, Inc.

Anatech Electronics, Inc. Like all types of RF and microwave filters, ceramic filters have unique characteristics that differentiate them from their counterparts and make them useful for specific applications. Ceramic filters are

More information

AN-837 APPLICATION NOTE

AN-837 APPLICATION NOTE APPLICATION NOTE One Technology Way P.O. Box 916 Norwood, MA 262-916, U.S.A. Tel: 781.329.47 Fax: 781.461.3113 www.analog.com DDS-Based Clock Jitter Performance vs. DAC Reconstruction Filter Performance

More information

Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique

Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique Numerical Calculation of Beam Coupling Impedances in the Frequency Domain using the Finite Integration Technique Uwe Niedermayer and Oliver Boine-Frankenheim 24 August 2012 TU Darmstadt Fachbereich 18

More information

CONTROL ROOM ACCELERATOR PHYSICS

CONTROL ROOM ACCELERATOR PHYSICS 1/30/14 USPAS 1 CONTROL ROOM ACCELERATOR PHYSICS Trajectory/ Applications 1/30/14 USPAS 2 Objective Maintain the beam (bunch) propagation along its design trajectory There are always errors from power

More information

Track Trigger and Modules For the HLT

Track Trigger and Modules For the HLT CMS L1 Track Trigger for SLHC Anders Ryd for the CMS Track Trigger Task Force Vertex 2009 Sept. 13-18, 2009 L=1035 cm-2s-1 Outline: SLHC trigger challenge Tracking triggers Track trigger modules Simulation

More information

New Machine Layout in IR3 and IR7

New Machine Layout in IR3 and IR7 CERN CH-1211 Geneva 23 Switzerland the Large Hadron Collider project LHC Project Document No. EDMS Document No. 474750 Engineering Change requested by ( Name & Div./Grp. ) : R. Assmann, AB/ABP Date: 2004-05-26

More information

RF Measurements Using a Modular Digitizer

RF Measurements Using a Modular Digitizer RF Measurements Using a Modular Digitizer Modern modular digitizers, like the Spectrum M4i series PCIe digitizers, offer greater bandwidth and higher resolution at any given bandwidth than ever before.

More information

Beam Instrumentation Group, CERN ACAS, Australian Collaboration for Accelerator Science 3. School of Physics, University of Melbourne 4

Beam Instrumentation Group, CERN ACAS, Australian Collaboration for Accelerator Science 3. School of Physics, University of Melbourne 4 Prototype tests of a wide-band Synchrotron-Light based Beam Pattern Monitor for measuring charge-couple bunch instabilities in High-Energy Particle Accelerator Beams Sophie Dawson2,3, Mark Boland2,4, David

More information

LEReC Engineering. J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer)

LEReC Engineering. J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer) LEReC Engineering J. Tuozzolo, C-AD Chief Mechanical Engineer (LEReC Project Engineer) Layout, Infrastructure, and Engineering IP 2:00 location - available. Engineering interface issues. Engineering support

More information

Harmonics and Noise in Photovoltaic (PV) Inverter and the Mitigation Strategies

Harmonics and Noise in Photovoltaic (PV) Inverter and the Mitigation Strategies Soonwook Hong, Ph. D. Michael Zuercher Martinson Harmonics and Noise in Photovoltaic (PV) Inverter and the Mitigation Strategies 1. Introduction PV inverters use semiconductor devices to transform the

More information

Cathode Ray Tube. Introduction. Functional principle

Cathode Ray Tube. Introduction. Functional principle Introduction The Cathode Ray Tube or Braun s Tube was invented by the German physicist Karl Ferdinand Braun in 897 and is today used in computer monitors, TV sets and oscilloscope tubes. The path of the

More information

A NEAR FIELD INJECTION MODEL FOR SUSCEPTIBILITY PREDICTION IN INTEGRATED CIRCUITS

A NEAR FIELD INJECTION MODEL FOR SUSCEPTIBILITY PREDICTION IN INTEGRATED CIRCUITS ICONIC 2007 St. Louis, MO, USA June 27-29, 2007 A NEAR FIELD INJECTION MODEL FOR SUSCEPTIBILITY PREDICTION IN INTEGRATED CIRCUITS Ali Alaeldine 12, Alexandre Boyer 3, Richard Perdriau 1, Sonia Ben Dhia

More information

SpectraTec II. Polarized Multi-Laser Source BLUE SKY RESEARCH WAVELENGTHS. The SpectraTec II

SpectraTec II. Polarized Multi-Laser Source BLUE SKY RESEARCH WAVELENGTHS. The SpectraTec II BLUE SKY RESEARCH The SpectraTec II, two wavelength laser module is a highly integrated system comprised of two lasers, individual driving and temperature control electronics, wavelength combining, and

More information

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH THE INFORMATION SYSTEM FOR LHC PARAMETERS AND LAYOUTS

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH THE INFORMATION SYSTEM FOR LHC PARAMETERS AND LAYOUTS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN EST/98-05 (ISS) THE INFORMATION SYSTEM FOR LHC PARAMETERS AND LAYOUTS S. Mallon, M. Mottier, Th. Pettersson, T.

More information

ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS

ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS ELECTRON-CLOUD EFFECTS IN THE TESLA AND CLIC POSITRON DAMPING RINGS D. Schulte, R. Wanzenberg 2, F. Zimmermann CERN, Geneva, Switzerland 2 DESY, Hamburg, Germany Abstract Damping rings reduce the emittances

More information

Pre-Compliance Test Method for Radiated Emissions of Automotive Components Using Scattering Parameter Transfer Functions

Pre-Compliance Test Method for Radiated Emissions of Automotive Components Using Scattering Parameter Transfer Functions PreCompliance Test Method for Radiated Emissions of Automotive Components Using Scattering Parameter Transfer Functions D. Schneider 1*, S. Tenbohlen 1, W. Köhler 1 1 Institute of Power Transmission and

More information

Wireless Technologies for the 450 MHz band

Wireless Technologies for the 450 MHz band Wireless Technologies for the 450 MHz band By CDG 450 Connectivity Special Interest Group (450 SIG) September 2013 1. Introduction Fast uptake of Machine- to Machine (M2M) applications and an installed

More information

CMS Tracker module / hybrid tests and DAQ development for the HL-LHC

CMS Tracker module / hybrid tests and DAQ development for the HL-LHC CMS Tracker module / hybrid tests and DAQ development for the HL-LHC S. Mersi, G. Auzinger georg.auzinger@cern.ch 1 Outline Reminder: the Ph2 CMS Tracker upgrade pt Modules: principle, elements, electronics

More information

Experiment 7: Familiarization with the Network Analyzer

Experiment 7: Familiarization with the Network Analyzer Experiment 7: Familiarization with the Network Analyzer Measurements to characterize networks at high frequencies (RF and microwave frequencies) are usually done in terms of scattering parameters (S parameters).

More information

Spin Tracking with COSY INFINITY and its Benchmarking

Spin Tracking with COSY INFINITY and its Benchmarking Spin Tracking with COSY INFINITY and its Benchmarking 2015-05-05 Marcel Rosenthal for the JEDI collaboration Outline Methods Simulation toolbox New extension: Transfer maps for time-varying fields Application

More information

Minimum requirements for the 13 ka splices for 7 TeV operation

Minimum requirements for the 13 ka splices for 7 TeV operation Minimum requirements for the 13 ka splices for 7 TeV operation - type of defects - FRESCA tests and validation of the code QP3 - a few words on the RRR - I safe vs R addit plots - conclusion Arjan Verweij

More information

Should SMTF Include RIA?

Should SMTF Include RIA? Should SMTF Include RIA? J.D. Fuerst, M. Kedzie, M.P. Kelly, K.W. Shepard, Z.A. Conway Speakers: Ken Shepard Mike Kelly SMTF Meeting at TJNAF September 30, 2004 Argonne National Laboratory A Laboratory

More information

Cable Analysis and Fault Detection using the Bode 100

Cable Analysis and Fault Detection using the Bode 100 Cable Analysis and Fault Detection using the Bode 100 By Stephan Synkule 2014 by OMICRON Lab V1.3 Visit www.omicron-lab.com for more information. Contact support@omicron-lab.com for technical support.

More information

RARE ISOTOPE ACCELERATOR (RIA) PROJECT*

RARE ISOTOPE ACCELERATOR (RIA) PROJECT* RARE ISOTOPE ACCELERATOR (RIA) PROJECT* R.C. York#, Michigan State University, East Lansing, MI 48824 U.S.A. Abstract The proposed Rare Isotope Accelerator (RIA) Project will provide world-class intensities

More information

ELECTRICAL ENGINEERING

ELECTRICAL ENGINEERING EE ELECTRICAL ENGINEERING See beginning of Section H for abbreviations, course numbers and coding. The * denotes labs which are held on alternate weeks. A minimum grade of C is required for all prerequisite

More information

Project X: A multi-mw Proton Source at Fermilab. Steve Holmes Extreme Beam Lecture Series

Project X: A multi-mw Proton Source at Fermilab. Steve Holmes Extreme Beam Lecture Series Project X: A multi-mw Proton Source at Fermilab Steve Holmes Extreme Beam Lecture Series June 11, 2009 Outline Strategic Context/Evolution of the Fermilab Complex Project X Goals and Initial Configuration

More information

SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS *

SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS * SIMULATIONS OF ELECTRON CLOUD BUILD-UP AND SATURATION IN THE APS * K. C. Harkay and R. A. Rosenberg, ANL, Argonne, IL 60439, USA M. A. Furman and M. Pivi, LBNL, Berkeley, CA 94720, USA Abstract In studies

More information

STUDY OF THE TRANSVERSE BEAM EMITTANCE OF THE BERN MEDICAL CYCLOTRON

STUDY OF THE TRANSVERSE BEAM EMITTANCE OF THE BERN MEDICAL CYCLOTRON Proceedings of IBIC15, Melbourne, Australia - Pre-Release Snapshot 17-Sep-15 1:3 MOPB41 STUDY OF THE TRANSVERSE BEAM EMITTANCE OF THE BERN MEDICAL CYCLOTRON K. P. Nesteruka,, M. Augera, S. Braccinia, T.

More information

DEVELOPMENT OF BUTTON ELECTRODES FOR SUPERKEKB RINGS

DEVELOPMENT OF BUTTON ELECTRODES FOR SUPERKEKB RINGS DEVELOPMENT OF BUTTON ELECTRODES FOR SUPERKEKB RINGS M. Tobiyama*, H. Fukuma, K. Shibata, M. Tejima, S. Hiramatsu, K. Mori, H. Ishii, T. Obina KEK Accelerator Laboratory, 1-1 Oho, Tsukuba 35-81, Japan

More information

14.5GHZ 2.2KW CW GENERATOR. GKP 22KP 14.5GHz WR62 3x400V

14.5GHZ 2.2KW CW GENERATOR. GKP 22KP 14.5GHz WR62 3x400V 14.5GHZ 2.2KW CW GENERATOR GKP 22KP 14.5GHz WR62 3x400V UTILIZATION OF GKP 22KP GENERATOR With its characteristics of power stability whatever the load, very fast response time at a pulse, low ripple,

More information

Electronics GRETINA Project

Electronics GRETINA Project Electronics GRETINA Project Requirement Document Sergio Zimmermann July 24, 2004 ANL Electronics Workshop, Schedule 1 Outline Doc Data Base Justification Document types Functional requirements List of

More information

EM Noise Mitigation in Circuit Boards and Cavities

EM Noise Mitigation in Circuit Boards and Cavities EM Noise Mitigation in Circuit Boards and Cavities Faculty (UMD): Omar M. Ramahi, Neil Goldsman and John Rodgers Visiting Professors (Finland): Fad Seydou Graduate Students (UMD): Xin Wu, Lin Li, Baharak

More information

Digital vs. Analogue Control Systems

Digital vs. Analogue Control Systems Digital vs. Analogue Control Systems Presented at the 2011 Annual Meeting of the American College of Medical Physics, Chattanooga, TN, May 1, 2011 Ivan A. Brezovich, PhD, Dept. of Rad Onc, Univ of Alabama

More information

Coaxial Cable Feeder Influence on Yagi Antenna Dragoslav Dobričić, YU1AW dragan@antennex.com

Coaxial Cable Feeder Influence on Yagi Antenna Dragoslav Dobričić, YU1AW dragan@antennex.com Coaxial Cable Feeder Influence on Yagi Antenna Dragoslav Dobričić, YU1AW dragan@antennex.com Introduction o far, in several previous articles [1, 2, 3], we investigated how boom radius and its S distance

More information

CALIBRATION OF A ROBUST 2 DOF PATH MONITORING TOOL FOR INDUSTRIAL ROBOTS AND MACHINE TOOLS BASED ON PARALLEL KINEMATICS

CALIBRATION OF A ROBUST 2 DOF PATH MONITORING TOOL FOR INDUSTRIAL ROBOTS AND MACHINE TOOLS BASED ON PARALLEL KINEMATICS CALIBRATION OF A ROBUST 2 DOF PATH MONITORING TOOL FOR INDUSTRIAL ROBOTS AND MACHINE TOOLS BASED ON PARALLEL KINEMATICS E. Batzies 1, M. Kreutzer 1, D. Leucht 2, V. Welker 2, O. Zirn 1 1 Mechatronics Research

More information

Application Note SAW-Components

Application Note SAW-Components Application Note SAW-Components Principles of SAWR-stabilized oscillators and transmitters. App: Note #1 This application note describes the physical principle of SAW-stabilized oscillator. Oscillator

More information

Technical Specification for the Cryogenic Testing of HTS Current Leads

Technical Specification for the Cryogenic Testing of HTS Current Leads Group Ref.: AT-MEL-CF EDMS No.: 44036 The Large Hadron Collider Project IT-3303/AT/LHC Technical Specification for the Cryogenic Testing of HTS Current Leads Abstract This specification concerns the testing

More information