1 Infrastructure Asset Management in a Large Scale European PPP Project AgileAssets Article

2 Page 2

3 Infrastructure Asset Management in a Large Scale European PPP Project How European PPP (Public-Private Partnership) Consortia are Utilizing Advanced Infrastructure Asset Management Software Systems to Facilitate Decisions, Minimize Risk and Enhance Profits Abstract AgileAssets has joined a significant European Public-Private Partnership (PPP) project as the supplier of infrastructure asset management software solutions for the next 30 years. The project concerns one of the world s most traveled highway systems, serving a major European capital. The project partners are responsible for all levels of design, building, financing and operation of the infrastructure, including all assets such as road, bridges, tunnels, signs and guardrails to name a few. This PPP is a current example of the European development in PPP, where consortia are gradually taking over the responsibility of road and rail infrastructure from the road agencies. This paper provides an example of how a large-scale consortium utilizes an integrated and comprehensive asset management software system to monitor, analyze and plan operations. Maintenance operations are planned, scheduled and recorded in the system, along with inspections on the various structures and condition assessments of the assets. This important data is in turn used in the decision support component of the process to evaluate individual asset performance, along with the performance of the network, over the life of the contract and beyond. (Specific examples are presented in this paper.) Finally, the added value of using state-of-the-art road asset management software tools in PPPs, especially in highly populated areas (urban highways), is discussed. This includes calculations on financial as well as social impacts (congestion, road closure, etc.) and focuses on hand-back criteria, making sure that the risks from a consortia standpoint are minimized through what-if scenarios as well as through various mitigation strategies. The article also discusses how decision support tools can be used for pre-contract bids, as well as post-contract awards to minimize liability and risk and to enhance profits. Monitoring Minimization of Risk Infrastructure Asset Management Software System Analysis Decision Support Enhanced Profits Operation Planning Figure 1: Infrastructure Asset Management Software System Utilization in a PPP Environment Page 3

4 Introduction AgileAssets, Inc. is a thought-leading global software company based in Austin, Texas with a wholly owned subsidiary, AgileAssets Ltd., based in London, UK. The AgileAssets suite of products includes highly advanced solutions for managing infrastructure assets, like roads and bridges as well as sub-assets like signs, signals, vehicle fleets, equipment, facilities and safety programs. The company s key to success has been its comprehensive approach towards infrastructure asset management that recognizes not only the need for constructing and maintaining the best possible infrastructure, but which also considers the requirements of administrations, suppliers and the public to maximize service quality, mobility, co-modality and safety at the lowest cost possible. The complexity of modern infrastructure calls for the most advanced, comprehensive and adaptable software, which makes AgileAssets solutions ideal for Public-Private Partnership contracts that require concurrent support for many parameters. While fully consolidated in the U.S. and abroad, AgileAssets has recently expanded operations to the European market, which itself is seeing increased use of the PPP model. European infrastructure PPP contracts have been around for quite some time, gaining popularity as practical and political reasons have spurned major investments in the TEN-T (Trans-European Transport Network). The network is a collection of infrastructure assets, representing all four transport modes; air, water, rail and roads and is backed politically by the European Commission (EC) and financially by the European Investment Bank with the goal of providing the safe and speedy transport of goods and people across Europe. In 2013, the TEN-T network was assigned a new set of guidelines from the EC that specifically asked for more public-private partnering, and the EC is backing these guidelines with promises of co-funding 26 billion EUR from or just about one tenth of the overall estimated budget for realizing the TEN-T network s goal. This means that more than 328 Billion USD will be bound in Europe s transport infrastructure until 2020, mostly paid for by the national states and mostly used on road transport infrastructure. Adding to this total are the national transport investments at the state, regional, municipal and city levels. TRANS-EUROPEAN TRANSPORT NETWORK TEN-T CORE NETWORK CORRIDORS BASED ON THE OUTCOME OF THE INFORMAL TRILOGUE OF 27th JUNE 2013 Page 4

5 The value bound in infrastructure assets is immense, and the need for re-building and expanding the postwar infrastructure in Europe is great. Huge investments are needed to achieve the best possible results. It can be argued that the public entities involved neither have the necessary funds, nor the work force or specialization to perform all aspects of the infrastructure operations themselves. These points form the central argument in favor of infrastructure PPPs, where the private partner undertakes design, planning, financing, building and maintenance of a given asset over a period of time, typically years. The private partner assumes most of the risks, while having the freedom to make decisions for the asset, as long as the performance standards set by the public agency with oversight responsibility are complied with. To cope with the challenge of managing very large infrastructure projects, tenders are often answered by large consortia, which consist of sizable construction companies, advisors and investors (banks). Depending on the tendered assignment, a PPP can range from a toll-paid solution (typically bridges, tunnels and private highways), where the private company actually owns the infrastructure, to a tax-financed construction (Design, Build, Operate), where the private company is paid to manage, but does not own, the infrastructure in question. As a matter of reference, several PPP models exist (Public Private Partnership (PPP) Review, Finnish Road Administration, 2013), such as: The Irish model: The client funds approximately half of the project s capital costs directly during the construction phase and private financing is used for the other half. As a result, more affordable public sector financing and PPP risk allocation are both being used. The French model: The client guarantees a proportion of the availability payment thus leaving approximately 70 percent of it protected. This allows the protected part of the payment to be financed at a cost close to public sector borrowing. The Danish model: The client refinances the project using public sector funds post construction. This brings more affordable financing to the project at the time when most of the project risks have passed. A typical contract approach is the Design, Build, Finance and Operate (DBFO), which is undertaken by a consortium and which works with a set of hand-back criteria in terms of service levels as well as condition levels. With a DBFO contract, the public entity involves the contractor in the planning and design phase, and also allocates the building, financing and operation of the road to the contractor. Conditions of an Infrastructure PPP Contract Criteria Types Not surprisingly, PPP contracts differ from country to country in Europe, depending on needs, experiences, tradition, size and political climate. The East European countries, some of them new to the European Union, are seeing a big increase in investor-funding from banks and from the European Commission, enabling large tenders for projects and attracting big consultancies, construction companies and other players in the field of infrastructure. Some countries are pleased with their current procurement methods and some countries have practically transferred overall management of roads and bridges to the private sector. In the UK, the Private Finance Initiative (PFI) was established in 1992 and has since signed more than 600 projects, including 43 transport projects and over 300 other operational projects in sectors such as defense, leisure, culture, housing and waste. Basically a PPP contract entails that the infrastructure assets should be handed back in a condition, following a set of criteria, agreed upon by the partners. These criteria can vary from a simple set of performance conditions which can be measured fairly easily in terms of the life expectancy of assets in relation to different kinds of structures, paired with collected data on parameters such as bearing capacity, cracks, and wear and tear. This data can be collected more or less automatically or by visual inspection and be more or less objective. Using sound judgment, common experiences and standards (key performance indicators, equipment, models), the parties agree upon the hand-back condition of the assets in question. An independent mediator might be chosen to evaluate the criteria at the end of the contract period. Page 5

6 On top of this comes a set of criteria for the contract period, which includes the level of service (LoS) of the infrastructure. LoS relates to the service quality that users of the infrastructure might expect when using the road, bridge, tunnel, rail, etc. A big part of this service relates to the mobility and safety of the users, i.e., travel time and congestion, some of which is measurable (traffic speeds, statistics) and some of which is more subjective, and may be more in the realm of preventing bad publicity/retaining happy clients on the specific asset. Environmental aspects such as noise and air pollution from the asset might also be an issue to consider. This includes the materials used for building, methods for maintenance and preventive actions (noise barriers, etc.). Additionally, there is a very large financial aspect to PPP contracts. The more complex a project (for instance a sizeable, highly used highway), the more money used for managing the assets and the more money bound in the project, both in the assets themselves and in the contribution to society keeping wheels turning, so to speak. There is a direct correlation between the effectiveness of our infrastructure and the benefit of movement of goods and people. So each unnecessary lane closure is very costly and will be subject to a penalty (from the road owner, in this case). Equally, all assets, which require interruption of traffic for maintenance, should be monitored and managed wisely. Finally there is the cross asset management aspect, not only in terms of building and maintaining the assets, but also to support the financial side of the house by accumulating all relevant data on assets, sub-assets, conditions, service levels and budgets to produce an overview of all elements of the project and to plan and act with due diligence. shareholders. After the contract award, the contracting agency and the consortium realized a review of all the assets and defined a performance baseline. This baseline defined the level at which the assets have to be returned to the contracting agency in 30 years at the end of the contracting period. The following asset classes are present in the contract: Linear Assets Types: Condition scores were applied based on machine and visual data and a set of criteria. Each asset was assigned a score of A (as new), B, C, D or E (life expired). At the end of the contract, the percentage of each linear type asset with condition score A must be between 80% and 120% of the percentage of assets with condition score A at the start of the contract. The same rule applies for assets of condition B and C. The number of assets with condition score D cannot exceed 120%. In the case of condition E, in 2039 there cannot be more than the percentage of E assets at the start of the contract. Structures: At the start of the contract, for each structure on the network, a condition score was given (0-100, with 0 being good and 100 being poor). The score for each structure is generated from element condition scores (with different weightings for element importance). Each structure falls into one of the 5 categories (retaining walls, signed gantries, high masts, small span structures, bridges and large culverts). At the end of the contract, the consortium has to hand each sub-classification group of structures back with an overall condition score and element grouping score that is equal to or better than the condition score that was calculated at the start of the contract (including the scores applied to element groupings). This exercise requires not only precise measurement data, but also highly advanced and reliable software systems that can handle complex data and support strategic and practical decisions during the full lifetime of a PPP project. Integrated Asset Management In the present example, the European PPP consortium has fairly complex hand-back criteria for each asset type it is responsible for. In order to minimize the risks to the consortium, it had developed, during the prebid process, several models in order to predict the expenditures and to limit the financial exposure of the Tunnels: For condition scoring, each tunnel is made up of two components (civil and M&E). These two components are combined using a weighting to generate a score for each tunnel (0-100). Condition scores were calculated using this methodology for each tunnel and the start of the contract. At the end of the contract, the consortium should hand back each of the tunnels with an equal or better overall condition score and element grouping score than was calculated at the start of the contract. Page 6

7 There are a few more very demanding conditions on the contracted consortium such as: Expenditure Profiles: The expenditures in the 15 years post contract (during year 30-45) have to be between 80% and 120% of the expenditures during the years of the contract. This in effect is an obligation to the consortium to maintain the assets at a certain level including necessary preventative maintenance. This is true for all asset types combined. Lane Closures: Lane closures occur when interventions need to be conducted during the day time (generally between 5AM and 10PM) and anything from a part lane to a full carriageway is closed to traffic. This results in a financial penalty dependent on the number of lanes closed, duration, road, location, closure type and time of the year. Figure 2 below shows the overall simplified timeline of the contract. The Maintenance and Operations window spans from 2009 to However, it is important to note that the expenditure profile penalties could still be imposed to the consortium 15 years after the contract ends. Figure 3 below represents the traditional asset management life-cycle. In this DBFO contract and this paper specifically, the Operations stage is the focus. In our particular example, the Operations and Management stage represents a 30 year budget of more than 3 billion EUR or more than 100 million EUR per year. For approximately 440 km of roads and 1800 structures (considering equal allocation 50% pavement and 50% structures), this represents 120,000 GBP per year per km and 29,000 GBP per year per structure. Contract Award Construction Asset Condition Baseline Widening Maintenance Operations Contract End Potential Penalties Figure 2: PPP Contract Timeline Establish Needs Finance Design Disposal Procure Operations Build Figure 3: Infrastructure Asset Management Life Cycle Page 7

8 9:41 AM 100% 9:41 AM 100% In order to facilitate the Maintenance and Operations phase of the contract, the consortium decided to adopt AgileAssets infrastructure asset management system, a state-of-the-art solution that enables greater visibility into and efficiencies in managing day-to-day operations (inspections, defects, maintenance work, asset condition recording, reporting, etc.) as well as in the development of short, medium, and long-term work plans that ensure that the various criteria are met during and at the end of the contracting period (and beyond). Figure 4 represents the AgileAssets system as implemented. It consists of a comprehensive, integrated modular system that supports all facets of asset management, from operational to strategic. The web-based system enables multiple users to perform their functions in a Commercial Off-The- Shelf (COTS) environment that is configured to the consortium s specific requirements. The following AgileAssets modules were implemented: The Foundation TM module enables management of the business rules and users, as well as configuration of the system. It also supports the creation of data models for each asset type and includes a comprehensive Extract Transform and Load (ETL) tool. For the consortium, it is used to tailor the data model of each asset to its specific requirements. The Bridge Inspector TM module enables advanced inspection and condition data capture for structure inventory including bridges, culverts, small span structures, masts, sign gantries, retaining walls, tunnels, mechanical and equipment. The consortium performs approximately 800 inspections annually and has several inspectors and contractors carrying out the scheduled and ad-hoc inspections. Inspections Defects Central Desk Foundation (Core Set of System Capabilities) Inspection Management KPIs Bridge Inspector AgileAssets Integrated Infrastructure Asset Management System Maintenance Manager Warehouse Management Key Performance Indicators Bridge Analyst Pavement Analyst Field Maintenance Operators What-If Scenarios Forward Plans What-If Scenarios Forward Plans Survey Equipment Figure 4: Example of Integrated Asset Management in a PPP Consortium Page 8

9 The Maintenance Manager TM module enables management of day-to-day maintenance operations including planning, scheduling, work recording and reporting on network assets. The module helps optimize available resources, eliminate redundant work and provide reliable information that enables better decisions. The Pavement Analyst TM module is a decision support tool for comprehensive pavement management. It produces short, medium and long-term work plans. The work plans are the output of what-if scenarios analyses based on specific objectives and constraints. The solution supports multiple analysis types that range from simple methods like worst first and prioritization to complex multi-year, multiobjective, multi-constraint optimizations. It supports the definition of engineering rules such as decision trees and treatments, deterioration models, objectives and constraints. The consortium is able to run level of service scenarios and determine the budget levels required to meet specific level of service goals. The Bridge Analyst TM module is a decision support tool for comprehensive bridge management. It produces short, medium and long-term work plans detailed at the element level. The work plans are output of whatif scenarios analyses based on specific objectives and constraints. The solution supports multiple analysis types that range from simple methods like worst first and prioritization to complex multi-year, multi-objective, multi-constraint optimizations. It supports the definition of engineering rules such as decision trees and treatments, deterioration models, objectives and constraints at the element level. The consortium is able to run level of service scenarios and determine the budget levels required to meet specific level of service goals. In addition to performing specific, crucial functions, the integrated design of the AgileAssets system provides additional benefits. Table 1 below summarizes these benefits. It is interesting to note that each benefit can correspond to significant financial benefits for the consortium. Each benefit can be summed up and used to help justify the acquisition of such a system, without even considering the actual improvements in terms of efficiency, accuracy, quality or software maintenance. To Module Maintenance Manager TM Bridge Inspector TM Bridge Analyst TM Pavement Analyst TM Maintenance Manager TM Work realized to address identified defects Maintenance history on structures Maintenance impact and costs on structures and elements Maintenance history on pavement sections and linear assets Maintenance impact and costs on pavement sections and linear assets From Module Bridge Inspector TM Bridge Analyst TM Defects identified during inspections Structure Work Plans (actionable down to structure element level) Structure Work Plans (actionable down to structure element level) Accurate and up-to-date structure data inventory Accurate and up-todate condition data Structures inventory and condition data on pavement section (Can be rolled up to have trend indicators) Projected structures conditions and expenditures Pavement Work Plans (actionable) Roadway and right-of-way Roadway and right-of-way conditions Pavement Analyst TM Traffic volumes Roadway and right-of-way inventory Traffic volumes and projections Roadway and right-of-way inventory Projected roadway conditions and budgets Table 1: Benefits of an Integrated Asset Management System Page 9

10 Analytical Decision Support Tools During the Operations Phase of a PPP Contract In the example presented above, the contract duration is 30 years with potential penalties after the life of the contract. It is important to keep in mind that the Design and Build phases are not the focus of this paper. This paper focuses on the Operations phase. During the 30 years of the contract, the assets will need to be at least partially maintained so as to meet the contractual hand-back requirements. In order to achieve the most efficient management, it is important to have some robust asset management capabilities and to apply a systematic approach. The Consortium has decided that having an integrated system would present a significant potential for mid to long-term return on investment. It is indeed conceivable that potential budget reductions between 5% and 20% can be achieved, which could potentially result in valuable returns to the Consortium s shareholders. In Figure 5, the anticipated workflow for most of the asset types is presented. It is important to note that the feedback cycles are built into the process in order to refine the engineering rules during the life of the contract. It is also important to note that every major process is fed by another process and that no process works in isolation. A PPP consortium should therefore function in a very similar manner and adopt a solution that allows for all components and teams to work seamlessly in a single system. At any point in time, the engineering or asset management teams should have feedback loops from the commercial teams and inspection teams in order to run effective scenarios and produce meaningful proposed work plans. All the engineering rules inputted in what-if scenarios should allow rapid modifications in order to evaluate different maintenance strategies. Inventory and Conditions Condition Updates Treatment Library Deterioration Models Engineering Rules Decision Trees Level-of Service Constraints Budget Constraints What-If Scenarios Penalties Constraints Inspections (Manual and Automated) Existing Maintenance Projects Executed Maintenance Updated Treatment Costs Approved Projects Commercial Team and Maintenance Team Proposed Projects Short Medium Strategic Proposed Work Plans Figure 5: Life-Cycle of an Integrated Asset Management System Page 10

11 The solution adopted by the consortium contains all the built-in loops and allows for rapidly modifying any engineering rule in order to evaluate new maintenance strategies. The decision support components (Bridge Analyst TM and Pavement Analyst TM ) contain one of the most advanced analytical frameworks in the industry and therefore supports extremely complex what-if scenarios that can model contract objectives and constraints as closely as possible. Galenko and Garvey (2014) as well as Laumet and Galenko (2014) discussed the different analytical frameworks and their advantages. It is important to note that using a solution that utilizes advanced analytical methods can offer a potential gain between 20% and 25% on maintenance budgets to achieve identical network level of service goals. Figure 6 summarizes the application of two analytical methods available in the adopted solution and demonstrate the potential for savings using the pavement network of four different clients both large and small. Before the Contract: Asset Management Reduces the Risks Decision Support Tools and Risk Mitigation A decision support tool is not only a tool that can be used during the life of the contract, it can also be used before any contract bids. It should be used by the potential bidder to evaluate the financial profiles required during the life of the contract to maintain the appropriate level of service. Asset conditions can be obtained from the contracting agency, or they can be simulated. Decision support tools can evaluate the budget required to maintain several levels of service. Example of Pre-Bid Scenarios on a Small Pavement Network In Table 2, a small pavement network of 200 km is simulated. The network is simplistically divided in 1 km sections (200 sections of 1 lane) and a single performance indicator (PI) is used (scale of 100-0; 100 is perfect). The condition of each section of the network at the beginning of the contract is randomly generated in order to obtain an overall network condition (see column Starting Network Condition in table 2). Table 2 contains the various starting network conditions, and the various constraints and objectives considered during the simulation runs. The following decision criteria is used to recommend treatments on the network: If PI < 40: Aggressive treatment is a candidate ($213/m) If 40 < PI < 75: Medium treatment is a candidate ($126/m) If 75 < PI < 85: Light treatment is a candidate ($40/m) If PI > 85: Do nothing Reasonably aggressive deterioration models are applied (26 years for the Performance Index to reach 50 and 16 years for the Performance Index to reach 50). $ % Budget Requirements, Billions $2.50 $2.00 $1.50 $1.00 $0.50 Multi-Year Analysis Single-Year Analysis Difference % Difference 25% 20% 15% 10% 5% $ Sections Client Sections Client Sections Client Sections Client 4 0% Figure 6: Budget Comparison Between Analytical Approaches (Galenko 2014)) Page 11

12 Starting Network Condition Constraint(s) Deterioration Number of Years Inflation Total Optimized Budget (Million $) Scenario #1 70 Maintain 80% of 26 Years to Reach 20 0% Scenario #2 70 Maintain 80% of 26 Years to Reach 20 3% Scenario #3 70 Maintain 90% of 26 Years to Reach 20 0% Scenario #4 70 Maintain 90% of 26 Years to Reach 20 3% Scenario #5 78 Maintain 80% of 26 Years to Reach 20 0% Scenario #6 78 Maintain 80% of 26 Years to Reach 20 3% Scenario #7 78 Maintain 80% of 16 Years to Reach 20 0% Scenario #8 78 Maintain 80% of 16 Years to Reach 20 3% Table 2: Pre-Bid Scenarios on Simple Pavement Network As expected, Table 2 shows that the condition of the network at the beginning of the contract is important when it comes to developing long-term maintenance budgets. However, inflation appears to be even more important when estimating the financial envelopes and should not be overlooked. Finally, the rate of deterioration of the network is an important factor in terms of sensitivity analysis when considering a bid for a PPP contract. and strategic issues into one systematic approach, asset managers are better able to meet the many challenges that come with long-term infrastructure asset management contracts. References Paper authors include: Dr. Pascal Laumet and Mikkel Bruun. Conclusion Public-Private Partnerships are not new to Europe. Focusing on the win-win situation of having schools, hospitals and other infrastructure built to the mutual benefit of investors, stakeholders, private companies and end users, the methodical use of PPP has become increasingly popular. In the UK and France, PPP has proven valuable to accomplish projects that require significant investment and which feature complex infrastructures, including highways and bridges. With some contracts, spanning years, high standards in quality management and asset management are expected. In the end, the condition and usability of the assets are crucial values to modern society and there is an expectation for private operators to perform their tasks in the least disruptive and most efficient manner. Cross-asset management is a means to reach that end. By centralizing financial, practical Public Private Partnership (PPP) Review, Finnish Road Administration, 2013 Galenko Alexander and Joe Garvey (2014). Pavement Analyst TM : Theoretical Models and Practical Applications. In Proceedings of OPT-I An International Conference on Engineering and Applied Sciences Optimization. Laumet Pascal and Alexander Galenko (2014). Bridge Management: Optimization Model Reduced Formulations and Practical Applications. In Proceedings of OPT-I An International Conference on Engineering and Applied Sciences Optimization. Page 12

13 Page 13

14 Copyright 2015 AgileAssets Inc. AgileAssets is a registered trademark of AgileAssets Inc. All other trademarks are the property of their respective owners.

Asset Management Policy for Major PFI Projects

Asset Management Policy for Major PFI Projects Asset Management Policy for Major PFI Projects Agenda Asset Management Drivers Typical AM positioning in Motorway PFI Asset management Strategy Works Planning and Scheduling Innovation & Risk Mitigation

More information

Active Asset Management in State DOTs

Active Asset Management in State DOTs Active Asset Management in State DOTs Stuart Hudson, P.E. Charles Pilson, PhD, and Eric Perrone AgileAssets Inc. Prepared for : 9 th National Conference on Transportation Asset Management San Diego, CA

More information

The World s Most Advanced Infrastructure Asset Management Software

The World s Most Advanced Infrastructure Asset Management Software The World s Most Advanced Infrastructure Asset Management Software Solutions for Cities and Counties The Leading Global Provider of Integrated Infrastructure Asset Management Software Solutions Advanced

More information

Slough Borough Council. Highway Asset Management Strategy

Slough Borough Council. Highway Asset Management Strategy Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand

More information

Integrated Asset Management Tool for Highway Infrastructure

Integrated Asset Management Tool for Highway Infrastructure Integrated Asset Management Tool for Highway Infrastructure Robert VEITEGERER Head of Department Vienna Consulting Engineers Vienna, Austria veitegerer@vce.at Rui LIMA Civil Engineer Vienna Consulting

More information

About ERP Software Whitepaper

About ERP Software Whitepaper About ERP Software Whitepaper Many people have heard the term ERP used in a conversation but don t fully understand what it means. This whitepaper will provide information about the processes and advantages

More information

PPP Basics and Principles of a PPP Framework

PPP Basics and Principles of a PPP Framework Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership

More information

Defining Contract Management

Defining Contract Management Defining Contract Management Government must anticipate the contract management needs over the contract period. The main aspect to be emphasized under contract management is that this vital activity must

More information

Highway Infrastructure Asset Management Strategy

Highway Infrastructure Asset Management Strategy Highway Infrastructure Asset Management Strategy City Development Highways and Transportation Highways Asset Management Page i Asset Management Strategic Documents Contents Page Foreword 4. 1 Introduction)...)))))))))))))))))))))))...

More information

Chapter 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK CHAPTER 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK PAGE 11

Chapter 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK CHAPTER 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK PAGE 11 Chapter 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK CHAPTER 2 ASSET MANAGEMENT PLANNING AND PROGRAMMING FRAMEWORK PAGE 11 This page intentionally left blank. PAGE 12 MINNESOTA GO MNDOT TRANSPORTATION

More information

Maintenance Management and Asset Management

Maintenance Management and Asset Management Defining and Understanding the Difference Between Maintenance Management and Asset Management Dr. Simon Lewis AgileAssets, Inc. 12th AASHTO-TRB Maintenance Management Conference Annapolis Maryland, July

More information

Asset Management Plan Final Report

Asset Management Plan Final Report AssetManagementPlan FinalReport DillonConsultingLimited 10FifthStreetSouth Chatham,ONN7M4V4 T:519-352-7802 F:519-354-2050 May,2014 www.dillon.ca EXECUTIVE SUMMARY Public infrastructure is central to our

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption.

Page 1 of 24. To present the Asset Management Policy 2014 for Council adoption. Page 1 of 24 COMMUNITY AND SERVICES SPECIAL COMMITTEE REPORT 9 DECEMBER 2104 AGENDA ITEM 6.1 ASSET MANAGEMENT POLICY 2014 REVIEW Director: Manager: Ian Butterworth Director Infrastructure and Engineering

More information

Plymouth Council & Asset Management

Plymouth Council & Asset Management Plymouth Council & Asset Management Plymouth City Council is committed to improving the condition of its carriageways and has demonstrated this graphically by pledging to spend 20m over and above any DfT/central

More information

The City of Owen Sound Asset Management Plan

The City of Owen Sound Asset Management Plan The City of Owen Sound Asset Management Plan December 013 Adopted by Council March 4, 014 TABLE OF CONTENTS 1 EXECUTIVE SUMMARY... 1 INTRODUCTION....1 Vision.... What is Asset Management?....3 Link to

More information

Design quality and the private finance initiative

Design quality and the private finance initiative Design quality and the private finance initiative This paper sets out CABE s perspective on the ability of the private finance initiative (PFI) to deliver well-designed public buildings, and considers

More information

SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE

SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE Business Value Guide SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE INTRODUCTION What if it were possible to tightly link sales, marketing, supply chain, manufacturing and finance, so that

More information

Enabling safer, more efficient and environmentally friendly fleets. Zurich Fleet Intelligence

Enabling safer, more efficient and environmentally friendly fleets. Zurich Fleet Intelligence Enabling safer, more efficient and environmentally friendly fleets Zurich Fleet Intelligence Zurich Fleet Intelligence: enabling safer, more efficient and environmentally friendly fleets Whether you operate

More information

IBM asset and service management solutions White paper. Asset and service management for Departments of Transportation.

IBM asset and service management solutions White paper. Asset and service management for Departments of Transportation. IBM asset and service management solutions White paper Asset and service management for Departments of Transportation. March 2007 Page 2 Contents 2 Executive summary 3 Introduction 4 Unifying asset management

More information

Coca-Cola Enterprises Inc. Case Study. Coca-Cola Enterprises leverages output strategy to consolidate vendors and devices and reduce costs

Coca-Cola Enterprises Inc. Case Study. Coca-Cola Enterprises leverages output strategy to consolidate vendors and devices and reduce costs Case Study Manufacturing & Distribution Coca-Cola Enterprises leverages output strategy to consolidate vendors and devices and reduce costs The Organization Coca-Cola Enterprises Inc. (CCE) is the world

More information

Pavement Engineering & Asset Management. Meeting the requirements of our existing & future diverse road networks

Pavement Engineering & Asset Management. Meeting the requirements of our existing & future diverse road networks Pavement Engineering & Asset Management Meeting the requirements of our existing & future diverse road networks 3 Introduction Pavement Engineering Services Jean Lefebvre (UK) are able to provide analysis

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

RedPrairie Transportation Management

RedPrairie Transportation Management RedPrairie Transportation Management All your global and local transport needs on one easy-to-use platform Whether your world involves orchestrating shipments across complex global supply and demand networks,

More information

The Town of Fort Frances POLICY SECTION ACCOUNTING FOR TANGIBLE CAPITAL ASSETS. ADMINISTRATION AND FINANCE NEW: May 2009 1. PURPOSE: 2.

The Town of Fort Frances POLICY SECTION ACCOUNTING FOR TANGIBLE CAPITAL ASSETS. ADMINISTRATION AND FINANCE NEW: May 2009 1. PURPOSE: 2. The Town of Fort Frances ACCOUNTING FOR TANGIBLE CAPITAL ASSETS SECTION ADMINISTRATION AND FINANCE NEW: May 2009 REVISED: POLICY Resolution Number: 05/09 Consent 156 Policy Number: 1.18 PAGE 1 of 11 Supercedes

More information

2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation

2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation 2014 ASSET MANAGEMENT PLAN Building, Stormwater & Linear Transportation Version 1 Table of Contents Executive Summary... 5 1.1 Background... 5 1.2 State of Local Infrastructure... 5 1.3 Desired Levels

More information

How To Manage Transportation Asset Management

How To Manage Transportation Asset Management 1 TRANSPORTATION ASSET MANAGEMENT THE NEW BUSINESS MODEL FOR TRANSPORTATION AGENCIES Presented at the AASHTO Subcommittee on Transportation Finance Policy Business Meeting Irvine, California June 26, 2012

More information

Highway Asset Management Strategy

Highway Asset Management Strategy 1. Introduction 1.1. Cheshire East Council (CEC) recognises the importance of its highway infrastructure and how an effectively maintained and managed network contributes to the achievement of its corporate

More information

Extend the value of your core business systems.

Extend the value of your core business systems. Legacy systems renovation to SOA September 2006 Extend the value of your core business systems. Transforming legacy applications into an SOA framework Page 2 Contents 2 Unshackling your core business systems

More information

Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.

Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing

More information

Agile Manufacturing for ALUMINIUM SMELTERS

Agile Manufacturing for ALUMINIUM SMELTERS Agile Manufacturing for ALUMINIUM SMELTERS White Paper This White Paper describes how Advanced Information Management and Planning & Scheduling solutions for Aluminium Smelters can transform production

More information

CITY OF GREATER SUDBURY. Municipal Roads, Structures and Related Infrastructure. Final Report. July 10, 2012

CITY OF GREATER SUDBURY. Municipal Roads, Structures and Related Infrastructure. Final Report. July 10, 2012 CITY OF GREATER SUDBURY Financial Planning for Municipal Roads, Structures and Related Infrastructure Final Report July 10, 2012 Financial Planning for Roads Table of Contents I. Financial Planning for

More information

Improved Decision-Making Through Effective Asset Management

Improved Decision-Making Through Effective Asset Management Improved Decision-Making Through Effective Asset Management Rob Corazzola, P.Eng., Hansen Canada Co-authored by Jon Poli, PE, Hansen Paper prepared for presentation At the Roadway Inventory and Condition

More information

How to Use Supply Chain Design to Craft Successful M&A Activities

How to Use Supply Chain Design to Craft Successful M&A Activities How to Use Supply Chain Design to Craft Successful M&A Activities Mergers and acquisitions (M&A) present an incomparable number of options for the design of the new organization s supply chain; a staggering

More information

Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level

Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level Implementing Pavement Management Systems, Do's and Don ts at the Local Agency Level Roger E. Smith, P.E., Ph.D. Zachry Department of Civil Engineering Texas A&M University 1 Do Understand Basic Pavement

More information

ASSET MANAGEMENT STRATEGY

ASSET MANAGEMENT STRATEGY ASSET MANAGEMENT STRATEGY Transport and Highways June 2013 Asset Management Strategy (June 2013) Page 1 of 10 CONTENTS INTRODUCTION 3 SECTION 1: WHY ASSET MANAGEMENT 4 1.1 Background 4 1.2 Strategic Framework

More information

Asset Management for MAP-21. Gary Lasham, P.E. Jonathan Pollack

Asset Management for MAP-21. Gary Lasham, P.E. Jonathan Pollack Asset Management for MAP-21 Gary Lasham, P.E. Jonathan Pollack Replaced Intermodal Surface Transportation Efficiency Act (ISTEA) MAP-21 is transforming the policy and programmatic framework for investments

More information

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

Achieve greater efficiency in asset management by managing all your asset types on a single platform. Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. When you use Maximo Asset Management to help maximize the

More information

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

Achieve greater efficiency in asset management by managing all your asset types on a single platform. Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company

More information

LBJ Freeway in Dallas

LBJ Freeway in Dallas LBJ Freeway in Dallas Texas/USA Ferrovial Agroman is redeveloping the LBJ Freeway to increase capacity and relieve severe congestion in one of the fastest growing areas in the United States. Ribera del

More information

IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution

IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution IBM Sensor Solutions IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution Highlights Transforms your supply chain by automating and error-proofing business processes Provides real-time

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Date: 10/10/2014 Initiated by: AAS-100

Date: 10/10/2014 Initiated by: AAS-100 U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Airport Pavement Management Program (PMP) Date: 10/10/2014 Initiated by: AAS-100 AC No: 150/5380-7B Change:

More information

DRAFT Freight Performance Measures

DRAFT Freight Performance Measures DRAFT Freight Performance Measures The purpose of the Industrial Areas Freight Access Project is to conduct a focused and pragmatic technical evaluation to identify and assess current and future freight

More information

CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM

CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM CHAPTER 2 PAVEMENT MANAGEMENT SYSTEM 2.1. INTRODUCTION TO PAVEMENT MANAGEMENT The ability of a pavement system to serve a society is largely a function of planning. Planning is the intersection between

More information

Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured.

Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured. Testing Platform-as-a-Service Get Significant Application Quality Improvement Without Major Investment. Performance driven. Quality assured. TPaaS a complete testing service, on demand, using the Capgemini

More information

Trapeze Rail System Simulation and Planning

Trapeze Rail System Simulation and Planning trapeze Rail System English Software for Rail Modelling and Planning Trapeze Rail System Simulation and Planning www.trapezegroup.com Enabling future railway plans Cost reductions through integrated planning

More information

Road Asset Management Research Program In Finland

Road Asset Management Research Program In Finland Langfassung / long version Road Asset Management Research Program In Finland Abstract Mr. Vesa Männistö, M.Sc. (Statistics) Inframan Ltd Länsituulentie 10, 02100 Espoo, Finland Tel +358-9-8567 7715, fax

More information

11. Managing our Transport Assets

11. Managing our Transport Assets 11. Managing our Transport Assets 11.1 The Need for an Asset Management Plan 11.1.1 A key challenge is to make transport assets work for the city in a way which fully contributes to the delivery of corporate

More information

Predictive Intelligence: Moving Beyond the Crystal Ball BEST PRACTICES WHITE PAPER

Predictive Intelligence: Moving Beyond the Crystal Ball BEST PRACTICES WHITE PAPER Predictive Intelligence: Moving Beyond the Crystal Ball BEST PRACTICES WHITE PAPER Table of Contents Introduction...1 Business Challenge...1 A Solution: Predictive Intelligence...1 > Dynamic Thresholding...2

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SAFETY DATA PROCESSES AND GOVERNANCE PRACTICES

MICHIGAN DEPARTMENT OF TRANSPORTATION SAFETY DATA PROCESSES AND GOVERNANCE PRACTICES MICHIGAN DEPARTMENT OF TRANSPORTATION SAFETY DATA PROCESSES AND GOVERNANCE PRACTICES CASE STUDY FHWA-SA-15-059 Prepared for Federal Highway Administration Office of Safety November 2015 (Page intentionally

More information

Predictive Intelligence: Identify Future Problems and Prevent Them from Happening BEST PRACTICES WHITE PAPER

Predictive Intelligence: Identify Future Problems and Prevent Them from Happening BEST PRACTICES WHITE PAPER Predictive Intelligence: Identify Future Problems and Prevent Them from Happening BEST PRACTICES WHITE PAPER Table of Contents Introduction...1 Business Challenge...1 A Solution: Predictive Intelligence...1

More information

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

Achieve greater efficiency in asset management by managing all your asset types on a single platform. Asset solutions To support your business objectives Achieve greater efficiency in asset by managing all your asset types on a single platform. Obtain an entirely new level of asset awareness Every company

More information

Transit Asset Management MBTA Initiatives

Transit Asset Management MBTA Initiatives Transit Asset Management MBTA Initiatives Standing Committee on Audit and Finance March 3, 2015 1 Agenda TAM overview MAP 21 requirements MBTA TAM initiatives: Asset Management Plan Decision Support Tool

More information

REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information

REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information REAL PROPERTY MANAGEMENT: Applying Best Practices Can Improve Real Property Inventory Management Information Report No. OIG-A-2013-015 June 12, 2013 NATIONAL RAILROAD PASSENGER CORPORATION The Inspector

More information

1. RECOMMENDATIONS. It is recommended that:

1. RECOMMENDATIONS. It is recommended that: Clause No. 7 in Report No. 3 of was adopted, without amendment, by the Council of The Regional Municipality of York at its meeting held on February 20, 2014. (Mayor Hackson declared an interest in this

More information

Transportation Asset Management Systems and Pavement Preservation. Southeast Pavement Preservation Partnership San Antonio, Texas May 29, 2013

Transportation Asset Management Systems and Pavement Preservation. Southeast Pavement Preservation Partnership San Antonio, Texas May 29, 2013 Transportation Asset Management Systems and Pavement Preservation Southeast Pavement Preservation Partnership San Antonio, Texas May 29, 2013 Today s Discussion Topics Asset Management Systems Overview

More information

The Development of Practical Asset Management System for an Urban Expressway Network

The Development of Practical Asset Management System for an Urban Expressway Network The Development of Practical Asset Management System for an Urban Expressway Network Motohiko Nishibayashi, Hanshin Expressway Company Limited 1. Introduction Hanshin Expressway is an urban expressway

More information

Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49

Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49 Chapter 5 RISK MANAGEMENT ANALYSIS CHAPTER 5 RISK MANAGEMENT ANALYSIS PAGE 49 This page intentionally left blank. PAGE 50 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN RISK MANAGEMENT ANALYSIS

More information

HP Service Manager software

HP Service Manager software HP Service Manager software The HP next generation IT Service Management solution is the industry leading consolidated IT service desk. Brochure HP Service Manager: Setting the standard for IT Service

More information

Technology management in warship acquisition

Technology management in warship acquisition management in warship acquisition A J Shanks B.Eng(Hons) MIET BMT Defence Services Limited SYNOPSIS Today s warship designers and engineers look to technology to provide warships and systems better, cheaper

More information

MSD Supply Chain Programme Strategy Workshop

MSD Supply Chain Programme Strategy Workshop MSD Supply Chain Programme Strategy Workshop Day 2 APPENDIX Accenture Development Partnerships Benchmarking MSD s Current Operating Supply Chain Capability 1.0 Planning 2.0 Procurement 3.0 Delivery 4.0

More information

ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY

ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY ENTERPRISE MANAGEMENT AND SUPPORT IN THE TELECOMMUNICATIONS INDUSTRY The Telecommunications Industry Companies in the telecommunications industry face a number of challenges as market saturation, slow

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON

STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON STANDARDIZED CLASSIFICATION SYSTEM TO ASSESS THE STATE AND CONDITION OF INFRASTRUCTURE IN EDMONTON Theresa Cloake, P.Eng. Infrastructure Analyst and K.L. Siu, P.Eng. Senior Infrastructure Officer Office

More information

Evaluation Guide. Sales and Operations Planning Performance Blueprint

Evaluation Guide. Sales and Operations Planning Performance Blueprint Evaluation Guide Sales and Operations Planning Performance Blueprint Introduction What if it were possible to tightly link sales, marketing, supply chain, manufacturing and finance, so that executives

More information

OPTIMIZING YOUR WORLD REVENUE TECHNOLOGY SERVICES. Revenue Management. for. Cruise Ferries

OPTIMIZING YOUR WORLD REVENUE TECHNOLOGY SERVICES. Revenue Management. for. Cruise Ferries OPTIMIZING YOUR WORLD REVENUE TECHNOLOGY SERVICES Revenue Management for Cruise Ferries Revenue Management in Cruise Ferry Industry Revenue Management in the cruise ferry industry is beginning to get recognition

More information

Introduction to Strategic Supply Chain Network Design Perspectives and Methodologies to Tackle the Most Challenging Supply Chain Network Dilemmas

Introduction to Strategic Supply Chain Network Design Perspectives and Methodologies to Tackle the Most Challenging Supply Chain Network Dilemmas Introduction to Strategic Supply Chain Network Design Perspectives and Methodologies to Tackle the Most Challenging Supply Chain Network Dilemmas D E L I V E R I N G S U P P L Y C H A I N E X C E L L E

More information

Managing the Product Value Chain for the Industrial Manufacturing Industry

Managing the Product Value Chain for the Industrial Manufacturing Industry An Oracle White Paper June 2011 Managing the Product Value Chain for the Industrial Manufacturing Industry Contributing Authors: John DaDamio, Oracle PLM/PIM Applications Pre-Sales Kerrie Foy, Oracle PLM/PIM

More information

AMS Asset Management Redkite Asset Management System When only the best will do.

AMS Asset Management Redkite Asset Management System When only the best will do. Defects AMS Asset Management Redkite Asset Management System When only the best will do. Redkite Systems Ltd 2014 AMS Overview You ll wonder how you managed without it! What can I record on Redkite AMS?

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

How To Create A Help Desk For A System Center System Manager

How To Create A Help Desk For A System Center System Manager System Center Service Manager Vision and Planned Capabilities Microsoft Corporation Published: April 2008 Executive Summary The Service Desk function is the primary point of contact between end users and

More information

What makes a good process?

What makes a good process? Rob Davis Everyone wants a good process. Our businesses would be more profitable if we had them. But do we know what a good process is? Would we recognized one if we saw it? And how do we ensure we can

More information

Scrim And Texture Data Collection Contract Management S Chamberlain

Scrim And Texture Data Collection Contract Management S Chamberlain Scrim And Texture Data Collection Contract Management S Chamberlain Introduction Transit New Zealand (Transit) has been successfully managing SCRIM and texture data collection through external suppliers

More information

Managing Linear Assets with Ventyx Ellipse

Managing Linear Assets with Ventyx Ellipse A Ventyx Whitepaper: Managing Linear Assets with Ventyx Ellipse Discover How Ventyx solutions Uniquely Meet the Requirements for Linear Asset Management Copyright 2012 Ventyx, An ABB Company. All rights

More information

Logistics Solutions. Intimate Involvement for Personalized Solutions

Logistics Solutions. Intimate Involvement for Personalized Solutions Logistics Solutions Intimate Involvement for Personalized Solutions Close Collaboration for Total Understanding When you have a committed logistics partner planning and implementing a supply chain solution

More information

SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN

SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN SUMMARY: LAND TRANSPORT ASSET MANAGEMENT PLAN Introduction This Asset Management Plan (AMP) for Land Transport Network 2012 describes in detail how the District s land transport network will be managed

More information

A new paradigm for EHS information systems: The business case for moving to a managed services solution

A new paradigm for EHS information systems: The business case for moving to a managed services solution White Paper A new paradigm for EHS information systems: The business case for moving to a managed services solution Business solutions through information technology TM Entire contents 2005 by CGI Group

More information

CHAPTER 20 Project Development Cost Estimates Table of Contents

CHAPTER 20 Project Development Cost Estimates Table of Contents Chapter 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates Table of Contents CHAPTER 20 Project Development Cost Estimates... 20-3 SECTION 1 Project Cost

More information

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1

More information

Procurement & Supply Chain Management

Procurement & Supply Chain Management New Skills. New Thinking Procurement & Supply Chain Management Supply Chain Effectiveness Audit - Implementing lean processes in your supply chain 20 September 2012 Auckland 24 September 2012 Wellington

More information

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33

Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 Chapter 4 ASSET INVENTORY AND CONDITION CHAPTER 4 ASSET INVENTORY AND CONDITION PAGE 33 This page intentionally left blank. PAGE 34 MINNESOTA GO MNDOT TRANSPORTATION ASSET MANAGEMENT PLAN ASSET INVENTORY

More information

TestScape. On-line, test data management and root cause analysis system. On-line Visibility. Ease of Use. Modular and Scalable.

TestScape. On-line, test data management and root cause analysis system. On-line Visibility. Ease of Use. Modular and Scalable. TestScape On-line, test data management and root cause analysis system On-line Visibility Minimize time to information Rapid root cause analysis Consistent view across all equipment Common view of test

More information

WHITE PAPER December 2009. TMS Transportation Management Systems & Supply Chain Sustainability

WHITE PAPER December 2009. TMS Transportation Management Systems & Supply Chain Sustainability WHITE PAPER December 2009 TMS Transportation Management Systems & Supply Chain Sustainability Introduction >>> Today, more than ever, transportation executives are focused on driving efficiencies within

More information

A Common-Sense Approach to Information Management for Corporate Greenhouse Gas Inventory

A Common-Sense Approach to Information Management for Corporate Greenhouse Gas Inventory A Common-Sense Approach to Information Management for Corporate Greenhouse Gas Inventory Kyle M. Tanger and Ebitari E. Isoun Project Performance Corporation 1760 Old Meadow Rd. 4th Floor, McLean, Virginia

More information

The Design and Improvement of a Software Project Management System Based on CMMI

The Design and Improvement of a Software Project Management System Based on CMMI Intelligent Information Management, 2012, 4, 330-337 http://dx.doi.org/10.4236/iim.2012.46037 Published Online November 2012 (http://www.scirp.org/journal/iim) The Design and Improvement of a Software

More information

Digital Continuity in ICT Services Procurement and Contract Management

Digital Continuity in ICT Services Procurement and Contract Management Digital Continuity in ICT Services Procurement and Contract Management This guidance relates to: Stage 1: Plan for action Stage 2: Define your digital continuity requirements Stage 3: Assess and manage

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

Project Management Terms

Project Management Terms FDM 2-1 Attachment 1.1 Terms Terms Baseline Term Baseline Budget Baseline Schedule Baseline Scope Budget Budget Change Control Communication Corrective Action Cost-Benefit Analysis Critical Path Decision

More information

Choosing the Right Project and Portfolio Management Solution

Choosing the Right Project and Portfolio Management Solution Choosing the Right Project and Portfolio Management Solution Executive Summary In too many organizations today, innovation isn t happening fast enough. Within these businesses, skills are siloed and resources

More information

SIAMA. SIAMA Asset Management Technologies Advanced Inspection Technology

SIAMA. SIAMA Asset Management Technologies Advanced Inspection Technology Prolonging Infrastructure Assets Life Asset Management Technologies Advanced Inspection Technology Smart Infrastructure Asset Management Australia () Research and Development Research & Development company

More information

Sub-Saharan Africa Transport Policy Program (SSATP) Output- and Performance-based Road Contracts (OPRC)

Sub-Saharan Africa Transport Policy Program (SSATP) Output- and Performance-based Road Contracts (OPRC) Sub-Saharan Africa Transport Policy Program (SSATP) Work in Progress and New Developments in RMF Output- and Performance-based Road Contracts (OPRC) (Based on presentations by Schliessler/Gericke WB) Olav

More information

Advanced Analytics for Financial Institutions

Advanced Analytics for Financial Institutions Advanced Analytics for Financial Institutions Powered by Sybase IQ on HP Servers product brochure www.sybase.com Over the past 18 months the global financial industry has gone through a huge transformation.

More information

Strategy management systems for collections. White paper

Strategy management systems for collections. White paper Strategy management systems for collections White paper Introduction to strategy management A strategy management solution for debt collections offers the potential for significantly improving operational

More information

Sustainability + Resilience

Sustainability + Resilience Sustainability + Resilience Fredericton s Journey By Tina Tapley The City of Fredericton, New Brunswick, has managed to not only see its way successfully through the economic turbulence of the last seven

More information

Combining Financial Management and Collections to Increase Revenue and Efficiency

Combining Financial Management and Collections to Increase Revenue and Efficiency Experience the commitment SOLUTION BRIEF FOR CGI ADVANTAGE ERP CLIENTS Combining Financial Management and Collections to Increase Revenue and Efficiency CGI Advantage ERP clients have a unique opportunity

More information

LONDON CORPORATE ASSET MANAGEMENT PLAN 2014

LONDON CORPORATE ASSET MANAGEMENT PLAN 2014 LONDON CORPORATE ASSET MANAGEMENT PLAN 2014 ACKNOWLEDGEMENT Acknowledgement The Corporate Asset Management office would like to acknowledge the efforts of the staff of the individual City of London Service

More information

Contract management's effect on in house counsel

Contract management's effect on in house counsel IBM Software Industry Solutions Industry/Product Identifier Contract management's effect on in house counsel Impacting contract visibility, analysis and compliance Emptoris Contract Management Solutions

More information

Integrated global treasury management

Integrated global treasury management FusionBanking KTP Software overview Integrated global treasury management Unifying treasury operations to optimise cashflow We needed to put in place a global solution to manage cash positions resulting

More information

2016-2021 Highway Asset Management Strategy

2016-2021 Highway Asset Management Strategy 2016-2021 Highway Asset Management Strategy Barnsley MBC 2016-2021 v0.1 0 BARNSLEY COUNCIL ASSET MANAGEMENT IMPLEMENTATION STRATEGY Contents 1.0 Introduction 2 Page 2.0 Legislative Requirements 2 3.0 Planning

More information