Connection of micro-generation to the electricity distribution network

Size: px
Start display at page:

Download "Connection of micro-generation to the electricity distribution network"

Transcription

1 Connection of micro-generation to the electricity distribution network Network recommendation YA9:09 Sivu 1(20)

2 CONTENTS INTRODUCTION MARKINGS AND DEFINITIONS DEFINITION OF MICRO-GENERATION AND RESTRICTION ON SINGLE-PHASE PRODUCTION Definition of micro-generation Restriction of single-phase generation Quantity of micro-generation in the place of use DISCONNECTION OF THE INSTALLATION AND OCCUPATIONAL SAFETY IN THE NETWORK Disconnection of the installation and safe working in the electricity network Taking account of the rear feed risk Marking of micro-generation sites QUALITY OF ELECTRICITY FED BY THE INSTALLATION EMC requirements Quality of electricity NETWORK CONNECTION OF THE INSTALLATION AND TRIPPING IN NETWORK FAULT SITUATIONS Protection properties of the generation installation The set values and operating times of parameters Synchronisation with the network Loss of Mains protection High-speed autoreclosers Use of reserve power SHORT-CIRCUIT CURRENTS FED INTO THE NETWORK BY THE INSTALLATION Fault trip Fault in protection SITES WITH NO BUYERS FOR ELECTRICITY METERING OF MICRO-GENERATION Sites with no electricity sold on the market Sites with a maximum of 3x63 A with electricity sold on the market Sites of over 3x63 A with electricity sold on the market On meter properties Registration and transmission of metering data CONTRACTS ON GENERATION Technical information on the micro-generation equipment to be notified to the network company Sites not selling to the market PRICING PRINCIPLES Connection fee Amount of connection fee when the site s consumption is greater than its generation Amount of connection fee when the site s consumption is smaller than its generation Network service fee Metering costs...19 Sivu 2(20)

3 INTRODUCTION There has been growing interest in distributed, local electricity generation along with the EU targets on the climate and increasing the use of renewable energy, lower prices of small-scale energy production plants, consumers interest in lowering their energy bills, and environmental awareness that is having an increasing impact on consumption decisions. It is the system operator s task to offer a reliable network for electricity generation and to guarantee the operation and safety of electricity distribution even after connection to the grid. The purpose of this network recommendation is to facilitate the connection process of micro-generation for all parties concerned. This recommendation includes the technical requirements of connection, and it also provides information about the necessary contracts, metering, division of costs and entry to the micro-generation market. It only focuses on very small-scale generation, so-called micro-generation. The recommendation is based on a study commissioned by the Finnish Energy Industries entitled Mikrotuotannon liittäminen yleiseen sähkönjakeluverkkoon (Connecting very small-scale electricity generation to the public distribution network in Finland), and on the standard EN Requirements for the connection of microgenerators in parallel with public low-voltage distribution networks. 1. MARKINGS AND DEFINITIONS Micro-generation plant = An electricity generation plant connected to the low-voltage network at the consumption site, with the primary purpose of generating electricity to the consumption site. Feeding into the network is only occasional or insignificant. The size limit of single-phase production is 16 A (highest current fed by the plant). ROCOF relay = Rate Of Change Of Frequency relay, i.e. a relay measuring the change of the frequency rate Rear feed/reverse current = Rear feed means that a micro-generation plant can feed electricity into the network even when the feeding network is de-energised. Loss of Mains situation = A situation where the network or part of a network unexpectedly becomes de-energised. In such a situation, the micro-generation plant feeding to the site will not necessarily detect the shut-down of the network, but may continue to feed an isolated network of one or more sites. EMC = Electromagnetic compatibility 2. DEFINITION OF MICRO-GENERATION AND RESTRICTION ON SINGLE-PHASE PRODUCTION Micro-generation is electricity generation that is primarily meant for own use at the consumer s installation, and feeding to the network is occasional or insignificant. In these generation installations, feeding to the network is not the primary reason for electricity generation. Therefore, micro-generation mainly refers to small-scale electricity generation installations acquired by individual consumers or small-scale Sivu 3(20)

4 enterprises, connected to the electricity system of their own place of consumption. Currently, the most common types of generation installations are wind farms, solar installations and very small biofuel plants Definition of micro-generation This network recommendation focuses on generation installations, which are primarily meant to generate electricity for the installation s own use and for which feeding to the network is only a secondary motive. The recommendation is based on a study commissioned by the Finnish Energy Industries entitled Mikrotuotannon liittäminen yleiseen sähkönjakeluverkkoon (Connecting very small-scale electricity generation to the public distribution network in Finland), and on the standard EN Requirements for the connection of micro-generators in parallel with public lowvoltage distribution networks. Both of these primarily deal with installations rated up to 3x16 A. Therefore, the maximum output of a micro-generation installation can be defined at approximately 11 kw. However, a network company may also use this recommendation to connect generation that is a grade higher Restriction of single-phase generation Single-phase generation that is too high will cause an imbalance in the network, jeopardising the safety and reliability of the network. Connection is permitted for a single-phase generation rated up to 16 A. Therefore, the maximum output of a singlephase micro-generation installation may be approximately 3.7 kva. The nominal rated capacity of the installation is smaller and depends on the properties of the installation. The micro-generator must notify the system operator to which phase the single-phase generation will be connected, and the system operator must be able to have an impact on the phase if it so wishes Quantity of micro-generation in the place of use Generation may be connected to the place of electricity use in accordance with the output defined in the connection contract if the installation s start-up or falling off the grid will not result in a change in voltage of over 4% and the quality of electricity in the connection point always remains within the limits of SFS-EN Moreover, the start-up current of the micro-generation installation must not exceed the peak value of current in accordance with the maximum output in the connection contract. It should be noted as background information that, according to Sener s instruction (2001), connecting a small-scale power plant to the grid may normally be permitted if the short-circuit output S k of the connection point satisfies the equation S k 25 iratio S N. The limit is based on the fact that this design value can guarantee that connection of the small-scale power plant to the grid will not result in a voltage change of over 4%. This design principle is presented in the Tuuliverkko final report of the University of Vaasa and VTT. Sivu 4(20)

5 Sener s instruction has been given to all small-scale power plants, and it cannot necessarily be applied to the management of micro-generation. There is still such a small amount of experience in the impact of micro-generation on the grid that it is not possible to give an absolute ratio for its quantity and the size of the installation. The following is an example of what following the Sener instruction (2001) would mean in practical terms for the quantity of micro-generation. S k According to Sener s instruction, an installation with a maximum output of S N = 25 may be connected to the grid if it is assumed to that the i ratio is almost 1, i.e. the installation is not obtaining considerably higher switching current than its rated current. Based on the protection terms of the grid, the design value of the short-circuit output of low-voltage network connections is currently regarded to be at least 250 amperes ( I k = 250A ). In some older connections, the short-circuit current is even smaller than this. Short-circuit current I k = 250A corresponds with short-circuit output S k = 3 I k U v = 3 250A 230V = 172, 5kVA as three-phase output of the low-voltage network. This would mean that only a generation installation of a maximum of 172,5kVA S N = = 6, 9kVA could be connected to an installation with a short-circuit 25 current of 250 A. 3. DISCONNECTION OF THE INSTALLATION AND OCCUPATIONAL SAFETY IN THE NETWORK This chapter deals with the occupational safety requirements for the operations of a micro-generation installation and safe working methods Disconnection of the installation and safe working in the electricity network According to the electrical safety standards, it must be possible to disconnect a generation plant from the network, the disconnecting device must have a visible air clearance, and it must be possible to lock the operating mechanism of the disconnecting device (SFS6002). Moreover, the distribution system operator must have either unrestricted access to the disconnecting device or a possibility for remote disconnection (SFS6000). In network maintenance and repair situations, it is important that the micro-generation installation does not maintain the network voltage. The micro-generation installation s own protection must ensure that the installation does not feed into a zero-voltage network. However, the standards require an additional disconnecting device in order to ensure installation safety during work on the network. A separate disconnecting device installed in connection with the micro-generation plant can be used as a disconnecting device if it has a visible air clearance or a reliable Sivu 5(20)

6 mechanical position indicator, or the main fuses of the power room of the site can be detached. In repair and maintenance of the network, it must be ensured that the disconnectors are used appropriately. The disconnecting device may also be a switch located before the connection point in the system operator s network. For example, a pole mounting fuse-switch in an overhead line network or a HRC fuse switch in a cable branching board in the cable network. The micro-generator can be invoiced for the installation of this kind of a switching device only if this kind of a switch would not have otherwise been installed in the network and if the micro-generator had not installed an appropriate disconnector in connection with its generation installation. An alternative for using disconnectors is to carry out the work as appropriate voltage work or otherwise in an equally safe way Taking account of the rear feed risk As micro-generation becomes more common, generation installations that have been connected to the grid without the system operator s permission will pose a possible hazard. The system operator is not aware of the location or protection of these installations. Due to the rear feed risk, it is important to establish zero voltage and to earth the place of installation on the side of any micro-generation installation. In a low-voltage network, it is also advisable to carry out earthing on both sides of the work site whenever there is a possibility that small-scale generation has been connected to the network, and earthing on the side of the site is possible Marking of micro-generation sites Micro-generation outputs must be marked appropriately on the side of both the installation and the network. In practice, all sites that can be made live by the micro-generation installation must be marked. These sites include transformer outputs and any branching boards. The customer s own power room must also be appropriately marked with a warning that micro-generation has been connected to it. The texts of the warning signs must be informative and in an appropriated place, and they must be in Finnish. It is also advisable that the system operator marks each micro-generation installation in its own systems so that an electrician may be provided with advance information regarding which connection sites have micro-generation. The network data systems must be developed so that these markings can be carried out. The warning signs must be positioned so that any electrician or layman on site will definitely see them. Furthermore, it is important to provide installation personnel with instructions on the meaning of the warning signs, how the risk posed by the microgeneration installation must be taken into account in practical work and how to ensure zero voltage of the site. Warning is given on the existence of small-scale and micro-generation installations in the distribution network by adding the marking in connection with the transformer substation Sivu 6(20)

7 or branching board output. If necessary, warning of generation may be given with a written sign with a yellow background. The text of the warning sign may be as follows: Electricity generation installation. Beware of reverse current. 4. QUALITY OF ELECTRICITY FED BY THE INSTALLATION Micro-generation operating in parallel with the network must not cause any disturbance in the network or in other electrical installations. If a micro-generation installation connected to the network causes disturbances elsewhere in the electricity network, the system operator must take measures and, if necessary, have the installation removed from the network EMC requirements The following is a list of standards on EMC requirements, which can be applied to micro-generation installations. Interference immunity: EN Electromagnetic compatibility (EMC) Generic standards Immunity for residential, commercial and light-industrial environments Electromagnetic emission: EN Electromagnetic compatibility (EMC) Generic standards Emission standard for residential, commercial and lightindustrial environments (also Appendix A11) Harmonic current emissions: EN Limits for harmonic current emissions (equipment input current up to and including 16A per phase) Voltage fluctuations and flicker: EN Electromagnetic compatibility (EMC). Limits. Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current up to and including 16 A per phase and not subject to conditional connection Moreover, requirements for micro-generation have been gathered in a technical report currently under preparation: EN Electromagnetic compatibility (EMC) Limits Assessment of low frequency electromagnetic immunity and emission requirements for dispersed generation systems in LV network Quality of electricity When a micro-generation installation is added to a metering point, the quality of voltage in the connection point must still comply with the standard SFS-EN Voltage characteristics of electricity supplied by public distribution systems. The total harmonic distortion may be a maximum of 8% in the connection point. The amount of total distortion must not be exceeded even if micro-generation is connected to the connection point. Furthermore, the standard provides limits to individual harmonic current emissions, flicker and fluctuations of voltage levels. Sivu 7(20)

8 5. NETWORK CONNECTION OF THE INSTALLATION AND TRIPPING IN NETWORK FAULT SITUATIONS The micro-generation equipment must be fitted up with protection devices that switch off the equipment from the public network if the network feed is disconnected or if the voltage or frequency in the poles of the generator equipment deviates from the voltage and frequency values set for the permitted operation of the micro-generation installation. The micro-generation equipment must never be connected to the network when the network voltage or frequency is not within the given limits. The protection of the installation must ensure that the micro-generation installation stops feeding to the network when any of the parameters listed in section 5.2 exceed or fall short of the set value. The installation must be disconnected in all equipment faults, and it must never start feeding electricity to a network if it does not meet the requirements of the set values presented in section 5.2. The equipment suppliers must always guarantee that the protection of the equipment meets the disconnection requirements laid down in legislation and standards. The protection equipment may be connected to the equipment of the micro-generation installation or it may consist of separate sets of equipment. The standard EN Requirements for the connection of micro-generators in parallel with public low-voltage distribution networks sets out the requirements for a micro-generator to be connected to the network. A recommendation for the terms and conditions for connection to and disconnection from the network is presented in the following. With regard to standard EN 50438, it must be noted that the parameters defined in the standard vary to a great extent in different countries. Therefore, an installation meeting the general section of standard EN does not necessarily meet the requirements set especially for Finland in the standard Protection properties of the generation installation The protection equipment to be connected to the micro-generation installation must disconnect the installation from the network with appropriate mechanical contactors or electronic switches. If an electronic switch is not working, the installation must stop generating electricity or disconnect itself from the network in another way. An electronic switching device must be specified according to the overvoltage classification specified by the manufacturer, and the out-switched bleed current must not exceed 0.1 ma regardless of the terminal voltage The set values and operating times of parameters The micro-generation installation must disconnect from the network if the network voltage or frequency do not remain within the given limits. These limits are given in standard EN and presented in Table 5.1. Sivu 8(20)

9 Table 5.1. The set values for the protection of the connection point, two-stage protection U n is the rated voltage. Parameter Operating time Set value Overvoltage -level s U n + 10% Overvoltage -level s U n + 15% Undervoltage-level 1 5 s U n - 15% Undervoltage-level s U n - 50% Overfrequency 0.2 s 51 Hz Underfrequency 0.5 s 48 Hz Loss of Mains* 0.15 s *Loss of Mains protection, i.e. protection to prevent island use must use detection technologies suitable for the distribution network. If it is not possible to implement two sets of over- or undervoltage limits with the protection equipment, one set of limits must be combined from the limits of the table. Thus, the requirements are stricter if there is only one set of voltage limits in use. These limits are presented in Table 5.2. Table 5.2. The set values for the protection of the connection point, single-stage protection U n is the rated voltage. Parameter Operating time Set value Overvoltage 0.15 s U n + 10% Undervoltage 1.5 s U n - 15% Overfrequency 0.2 s 51 Hz Underfrequency 0.5 s 48 Hz Loss of Mains* 0.15 s *Loss of Mains protection, i.e. protection to prevent island use must use detection technologies suitable for the distribution network Synchronisation with the network The installation s synchronisation with the network must be fully automated. The protection of the connection point must guarantee that the power feed to the network will not start until the voltage and frequency have stayed within the limits permitted by the protection settings at least for a certain minimum period, which is 3 minutes for generators and 20 seconds for systems connected with a frequency converter. Sivu 9(20)

10 It is recommended to perform re-synchronisation with the network after the fault in a staggered way, especially if there are several micro-generation installations behind the connection point. Staggering is possible to be carried out, for example, so that after the network voltage and frequency have returned to the permitted limits the frequency converter is synchronised with the network with a random delay of 0 15 seconds. This means that the synchronisation time after the return of the voltage would be seconds Loss of Mains protection A micro-generation installation must always disconnect from the network in a Loss of Mains (LoM) situation, i.e. when the network voltage is lost. A micro-generation installation must never remain alone to feed an isolated network. Some of the network connection devices feed power to the network in pulses and not as alternating current. In such a case, the network connection devices will not be able to remain in isolated network operation, but need constant network voltage for synchronisation. These device solutions do not need separate LoM protection. However, the devices must also be type tested in a LoM situation. On the other hand, it is possible with some network connection devices that if the loads of the isolated network are, by coincidence, very close to the combined production of one or several micro-generation installations, the installation will not be able to detect a LoM situation with voltage and frequency relays alone, but remains to feed the isolated network. In such a case, the devices must be equipped with LoM protection. The LoM protection must disconnect the installation sufficiently quickly. The operating time must be as quick as in a situation U n 50%. The operating time of LoM protection is 0.15 s. Some of the so-called active LoM protection methods cannot necessarily be trusted to operate sufficiently quickly. Furthermore, some protection methods have been noticed to cause unnecessary tripping of installations from the network when large reactive loads are connected to the network. For these reasons, some of the active LoM protection methods are banned, for example, in Denmark. Therefore, a ROCOF relay with an operating time of 0.15 s or another protection method that is as fast and reliable as the ROCOF relay are recommended as LoM protection. The protection method must not cause extra problems in the network, such as unnecessary disconnection of generation High-speed autoreclosers In certain cases, micro-generation may have an impact on the high-speed autorecloser automation in the network. The operating time of the installation s disconnection is 0.15 s. If the high-speed autorecloser time is, for example, 0.5 seconds, it is possible that the zero voltage time preceding the high-speed autorecloser will remain at 0.35 seconds (0.5 s 0.15 s). If the micro-generation is found to cause problems in high- Sivu 10(20)

11 speed autoreclosers, the high-speed autoreclosers in the network can be prolonged by 0.15 seconds in network sections with micro-generation and where high-speed autoreclosers are in use. 5.6 Use of reserve power If a consumer wants to use a micro-generator as reserve power in parallel with the network, the possibility of a dual connection mode must be installed, with one connection to work in parallel with the network and the other in an isolated network that is completely separated from the network. This requires a separate switch and additional devices. It is of utmost importance that the installation may under no circumstances concurrently feed both the network and the isolated network. 6. SHORT-CIRCUIT CURRENTS FED INTO THE NETWORK BY THE INSTALLATION A micro-generation plant may feed short-circuit currents into the network, thus increasing the overall short-circuit currents close to the fault location. High short-circuit currents in the vicinity of a distributed generation plant may result in exceeding the thermal limits in the network components. Especially cable connections, transformers and switching devices are problematic in a situation with increased fault currents. If the above-mentioned problems appear due to micro-generation, the problem may be managed, for example, by replacing components with better ones or by diminishing short-circuit currents by dividing the network into smaller sections. Resetting of transformer values may also reduce short-circuit currents. In some cases, fault current limiters may also be used. The fault current fed by the micro-generation installation depends on the installation s properties. The fault current of an installation connected to the network with a frequency converter is limited by the properties of the frequency converter. The fault current fed by micro-generation installations is usually only slightly higher than its rated current. The amount of maximum fault current of the equipment should be entered in the type testing documents of the installation. This value can be used when calculating the installation s network impacts. The customer must notify the network company of the maximum amount of fault current fed by the installation. Two possible cases where the fault currents of micro-generation may result in faulty functioning of network protection are presented in the following. The cases are fault trip and fault in protection. Neither case is very likely when the amounts of micro-generation are small. However, the situation may change if the amounts of micro-generation increase considerably. The situation will become increasingly likely if micro-generation is produced by an asynchronous machine. The feeding ability of fault current in production connected with a frequency converter is restricted by the internal properties of the frequency converter, but an asynchronous machine may feed large amounts of short-circuit current. Sivu 11(20)

12 6.1. Fault trip A problematic situation in terms of network protection may arise in a case presented in Figure 6.1 where a micro-generation installation causes an unnecessary disconnection of a certain network section from the feed. Figure 6.1. Fault trip. The fault current fed by a micro-generation installation is marked with red. When a short-circuit fault takes place in a feed of a transformer substation that has another feed connected to distributed generation, the operation of over-current protection may be disturbed. In a fault such as in Figure 6.1, the feeding transformer feeds the fault current to the place of fault. The micro-generation installation also takes part in the feed of fault current. In such a case, fault current also flows through the over-current protection (fuse or relay) on the left-hand side. If the amount of fault current exceeds the capacity of over-current protection and the protection does not recognise the direction of fault current, it will operate and cut off the feed from the section of network on the side of the micro-generation installation Fault in protection Another problematic situation in terms of network protection may arise in a case presented in Figure 6.2 where the fault currents fed by a micro-generation installation disturb the operation of network protection. Sivu 12(20)

13 Figure 6.2. Fault in protection. The fault current fed by a micro-generation installation is marked with red. When a fault occurs in a location where there are one or more micro-generation installations between the fault location and feed, the protection may become faulty. A situation where short-circuit current is fed to the place of fault is presented in Figure 6.2. However, the micro-generation installation in the figure also feeds fault current, in which case the fed fault current will diminish. If there is a sufficient amount of microgeneration, the fed short-circuit current may diminish to such a level that the overcurrent protection of the transformer output will no longer react. 7. SITES WITH NO BUYERS FOR ELECTRICITY It may be difficult to find a buyer for the electricity produced by micro-generation installations. Legislation does not impose a purchase obligation on any market party, Sivu 13(20)

14 and the system operator s role as the buyer of electricity is in conflict with the operating principles of the electricity market and the roles and areas of responsibility laid down for various players. According to the current terms of contract, feed to the network should be prevented if no buyer is found for the electricity. However, the system operator can be flexible in this matter until the producer finds a market partner or the matter is solved, for example, with an amendment to legislation. When the producer finds a market partner, normal obligations concerning the producer enter into force. If a producer wants to connect a generation installation to the network even if there is no buyer for the electricity, the producer must conclude a separate contract with the network company. This kind of a contract model is dealt with in section METERING OF MICRO-GENERATION Metering practices and legislation on metering are different in various sites depending on the size of the facility and whether the electricity transmitted to the network is sold on the market. The different situations are dealt with in this section. The costs arising from the metering are dealt with in section 10. Pricing principles Sites with no electricity sold on the market A site, the electricity of which is fed into the network but not sold on the market, can be compared to a pure electricity consumption place. Legislation does not recognise a situation where the electricity fed to the network is not sold on the market. In these sites, it is possible to use the traditional rotating meter that measures only consumption, i.e. it measures only in one direction. It is not permitted to use a net meter. However, it is also recommended to install hourly metering equipment in these sites. If these sites want to sell electricity fed into the network on the market at a later date, the equipment will have to be changed in any case. It is not recommended to charge the customer for this kind of a change of meter because, in practice, electricity transmitted to the network is metered only to meet the needs of the system operator Sites with a maximum of 3x63 A with electricity sold on the market The electricity generation must be metered with a remotely read electricity meter that is read by the hour. All existing generation sites from where electricity is also transmitted to the public distribution network must be equipped with hourly metering by the end of 2010 at the latest. New generation sites must be equipped with hourly metering with immediate effect. When a small-scale generation site has both electricity generation and consumption, they can be metered with a single meter. An electricity generation plant connected to a metering site that is equipped with main fuses of a maximum of 3 x 63 A does not require a separate metering device, as it is enough that electricity acquired from the network and electricity fed into the network are metered separately at the site. Sivu 14(20)

15 Network input and output must not be netted, but the metering device must have separate registers for these Sites of over 3x63 A with electricity sold on the market If a generation plant is located at a metering point exceeding 3 x 63 A, generation and consumption can no longer be metered with just one meter. In addition to network input and output, consumption of own generation must be metered at a metering point with network input and output. Consumption of own generation is obtained by deducting from the generated electricity the production plant s electricity for own use and the electricity fed into the network. Electricity for own use is electricity consumed by the production plant system itself. Figure 8.1. Metering of generation. The system operator is responsible for the metering of network input and output. The meter is owned by the system operator who also conducts its reading. The electricity generator is responsible for metering the consumption of its own generation On meter properties Various remotely read meters deal with phase-specific power transmission in different ways. There are remotely read meters that turn the readings processed by the meter into intrinsic values before sending them on. This kind of a meter is useless at a generation site because then the energy fed into the network is seen in the meter as energy obtained from the network. A net meter, which meters both ways and sums up the metering data, must not be used under any circumstances when the site has both consumption and generation. It is also not recommended to use a meter that sums up the generation and consumption metering results in different phases Registration and transmission of metering data When one metering point has both consumption and generation, they must be metered separately. The meter must record network input and output in different registers. Data management is carried out so that two metering point IDs are created for the site in the Sivu 15(20)

16 network company s system, one for the consumption site and the other for the generation site. 9. CONTRACTS ON GENERATION When generation is connected to a place of consumption, a separate contract is drawn up for the generation. For consumption, the Terms of Network Service (VPE) are complied with. All connection points where feeding of electricity into the distribution network has not been prevented must comply with the terms of connection and network services concerning places of electricity generation. According to the Terms of Network Connection for Production (Sähköntuotannon liittymisehdot, TLE) and the Terms of Network Service for Production (TVPE), the customer must conclude generationrelated contracts on connection and electricity network with the distribution network operator when the customer feeds electricity into the public distribution network. This applies to sites feeding electricity that is sold on the market Technical information on the micro-generation equipment to be notified to the network company The producer of micro-generation must deliver information on the technical properties of the generation equipment to the system operator. The producer must provide the following information before the connection is carried out. The system operator will grant the connection permit on the basis of this information, inter alia. Information recorded in the nameplates of the production equipment, network connection device and any auxiliary equipment, and the maximum fault current fed by the equipment Testing record showing that the production installation meets the protection requirements presented in subsection 5.2. Generation installation s method of connection to the network (automatic/manual) and date of connection Information about the installation s disconnection solution and disconnector data Testing records showing that the equipment meets the EMC requirements presented in section 4 When the device is connected to the network, the producer must provide the system operator with an appropriate commissioning inspection record. If the installation has a single phase, it must be indicated to which phase it is connected. The generation plant may not be used until the commissioning inspection record has been delivered to the system operator and the system operator has given permission for the use of the plant. Sivu 16(20)

17 9.2. Sites not selling to the market When so-called surplus electricity, i.e. electricity without a buyer, is transmitted to the network, normal contracts concerning the place of electricity use is drawn up on the use of the electricity at the site, and a separate contract is drawn up with respect to generation. In this subsection, it is recorded how to apply existing contractual terms in these contracts and what kinds of extra notes can be made in the contracts. Section 4 of the Terms of Network Service for Production (TVPE) may be applied to the surplus electricity contract, with definitions of technical terms and for the generation installation and its use. The Terms of Network Service (VPE) may also be used where applicable. If applied, section 4 of TVPE should be attached to the contract. An alternative is to apply TVPE only, where applicable. A separate contract on surplus electricity only applies to a generation site with no buyer for the electricity transmitted to the network. The contract is terminated if the electricity transmitted to the network is sold on the market. In such a case, a contract on the network service of generation is concluded with the system operator, applying the contractual terms of generation. For example, the following matters may be recorded in the contract. No compensation will be paid for electricity transmitted into the network, and no network service fee for production will be charged with respect to electricity transmitted into the network. Normal network service fees will be charged for network input, i.e. consumption. The generation installation may not be connected until the producer has delivered to the system operator the technical data of the generation installation and the appropriate commissioning inspection record, and the system operator has given permission for the connection of equipment. The system operator must be informed of the connection or removal of equipment. If the equipment or connections are changed, it can be regarded as a new installation, and information on a commissioning inspection carried out after the change must be delivered before commissioning. The arrangement of metering may be mentioned in the contract, for example, as follows: The system operator shall be responsible for arranging the metering and the metering of electricity at the site. The site is metered with a unidirectional meter that meters consumption only. Electricity fed into the network is not metered separately. The system operator is entitled to replace the meter with a bi-directional, remotely read metering device at a later date (without a charge). The system operator is entitled to terminate the contract at three months notice if it is unreasonable to keep the contract in force due to an amendment to legislation or an essential change in circumstances (TVPE 14.6). Sivu 17(20)

18 Furthermore, the system operator is entitled to terminate the contract with a period of notice it deems suitable if the standardisation or generally accepted guidelines on the matter are changed. The producer is obliged to notify the system operator if he concludes a contract on selling the energy fed into the network. The producer is obliged to notify the system operator of any changes to be made to the generation installation or its connection and of any other changes that may have an impact on the contract. It is advisable to record in the contract as information for the microgenerator that if the micro-generation installation keeps on feeding an isolated network due to faulty operations and equipment connected to the network becomes faulty as a result of isolated network operation, the producer who has fed electricity into the isolated network is liable to pay compensation to the system operator for any damages to be compensated for by the system operator. Correspondingly, the producer himself is liable to the producer of isolated network use for the damages caused. Section 4 of the Terms of Network Service for Production (Sähköntuotannon verkkopalveluehdot, TVPE) deals with the terms and conditions related to the use of electrical equipment and electricity generation equipment. This section may be applied in the contract. The issues included in the section are listed in the following: o Compliance of regulations concerning electrical equipment o Electrical safety of electrical equipment o Commissioning of electricity generation equipment o Use, guidance and protection of electrical equipment o Quality requirements for electricity o Fault, disturbance and damage situations of electrical equipment 10. PRICING PRINCIPLES This chapter specifies the pricing of connection fees and network service charges for micro-generation sites Connection fee The system operator must connect the metering sites and electricity generation plants that meet the technical requirements in its area at request and for a reasonable charge. According to Section 14 b of the Electricity Market Act, the connection fees for generation by a maximum of 2 MVA plants must not include costs resulting from the strengthening of the electricity network. Therefore, it is permitted to charge only for the costs arising from the section of network serving the site itself. If the connection of the Sivu 18(20)

19 generation installation causes protection changes in the network, the customer is also responsible for these costs Amount of connection fee when the site s consumption is greater than its generation If the site s consumption (network input) is greater than the generation of the site (network output), the normal connection fees for the place of use shall be charged. This situation usually applies to small-scale generation Amount of connection fee when the site s consumption is smaller than its generation If the site s consumption (network input) is smaller than its generation (network output), the size of the connection required for consumption only shall be estimated, and a connection fee for a place of consumption of a similar size shall be charged. For the exceeding part, it is possible to charge an imputed proportion corresponding to the principles of the connection fee for generation. The above-mentioned imputed proportion may be determined, for example, as follows: Its amount corresponds to the construction costs of a network serving a customer of a connection with a size corresponding to the customer s generation, deducted by the construction costs of a connection corresponding to the customer s consumption with respect to the network serving the customer Network service fee According to the Electricity Market Decree (Government decree on the electricity market), a maximum network service fee for production at 0.07 cents/kwh (VAT 0%) may be charged for generation connected to a low- and medium-voltage network. Moreover, metering services and other additional services may also be subject to a fee. Normal fees will be charged for consumption (network input). Consumption of own generation is usually subject to a fee only in installations of more than 1 MVA. This is due to the definition principles for grid fees. Sites whose generation is not sold on the market cannot be charged for a network service fee for production or a fee for the metering of generation Metering costs When a meter has to be replaced with a new one at a site due to micro-generation, the system operator may charge the site for the costs arisen from the replacement, i.e. a one-off metering fee. The meter itself is paid for by the system operator because it is the system operator s property. With regard to sites with an existing hourly meter, the system operator may charge a so-called programming fee, a fee for the introduction for the bi-directional metering facility. The system operator may also invoice the site for a so-called constant metering fee, which may be different from the metering fee of the consumption site alone. The metering fee or the basic fee for the network service charged from sites with both consumption and generation sold to the market may justifiably be slightly higher than Sivu 19(20)

20 those of the consumption site alone because in such a case, e.g. the balancing data of the sites will be doubled. It is not justifiable to charge metering fees for generation from sites where the electricity transmitted to the network is not sold on the market. Sivu 20(20)

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries TERMS OF ELECTRICITY SALES 2010 as recommended by Finnish Energy Industries Content: A. General, concluding an electricity sale contract, the prerequisites for electricity sales, commencement of electricity

More information

Nuclear Power Plant Electrical Power Supply System Requirements

Nuclear Power Plant Electrical Power Supply System Requirements 1 Nuclear Power Plant Electrical Power Supply System Requirements Željko Jurković, Krško NPP, zeljko.jurkovic@nek.si Abstract Various regulations and standards require from electrical power system of the

More information

Power transformers. Special transformers Railway

Power transformers. Special transformers Railway Power transformers Special transformers Railway A leader in railway systems Our compact and low-weight transformers fully comply with the customer s specifications. The products are developed together

More information

Rule 5.500 Fast Track Analysis for National Life Insurance Co.

Rule 5.500 Fast Track Analysis for National Life Insurance Co. Rule 5.500 Fast Track Analysis for National Life Insurance Co. For a 500 kw Solar array to be located at 155 Northfield Street in Montpelier, Vermont Green Mountain Power Pam Allen Date: 5/31/13 SECTION

More information

ESB Networks Perspective on Microgeneration

ESB Networks Perspective on Microgeneration ESB Networks Perspective on Microgeneration Presentation to DIT Seminar 13 th November 2009 Tony Hearne Manager, Generation Planning ESB networks Brendan O Connor Commercial Policy ESB networks Micro-generation

More information

Electrical Shore Connections / Cold Ironing

Electrical Shore Connections / Cold Ironing STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

CE Marking and Technical Standardisation

CE Marking and Technical Standardisation GAMBICA Technical Guide CE Marking and Technical Standardisation Guidelines for application to Electrical Power Drive Systems Edition 4 : 2015 CE Marking and Technical Standardisation Guidelines for application

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

Solar Power Plant Design and Interconnection

Solar Power Plant Design and Interconnection Solar Power Plant Design and Interconnection Wind & Solar Super Session July 27, 2011 E.H. Camm, S.E. Williams S&C Electric Company Outline Introduction Utility-scale PV power plant Grounding Reactive

More information

Advanced Protection of Distribution Networks with Distributed Generators

Advanced Protection of Distribution Networks with Distributed Generators Date:- 8 10 March 2011 Venue: University of Manchester EES-UETP Course title Advanced Protection of Distribution Networks with Distributed Generators Peter Crossley Director of the Joule Centre School

More information

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme

Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme Model Renewable Energy Wheeling Agreement under Renewable Energy Certificate (REC) scheme This agreement made at on this day of two thousand between M/s. (Renewable Energy Generator name and address) hereinafter

More information

NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana

NET METERING SUB-CODE. for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana for Connecting Renewable Energy Generating Systems to the Distribution Network in Ghana JANUARY 2015 1 Table of Contents PART A: BACKGROUND... 1 1 Introduction... 1 1.1 Objective... 1 1.2 Status... 1 2

More information

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014

Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables. Bob Yinger Southern California Edison April 15, 2014 1 Distribution Operations with High-penetration of Beyond the Meter Intermittent Renewables Bob Yinger Southern California Edison April 15, 2014 Southern California Edison SCE provides power to: Nearly

More information

ELECTRICITY MARKET ACT

ELECTRICITY MARKET ACT 1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System

General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System General Validation Test Program for Wind Power Plants Connected to the Hydro-Québec Transmission System Direction Planification des actifs et expertise de transport February 2011 TABLE OF CONTENTS 1. CONDUCTING

More information

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...

More information

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS

DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS DC TRANSMISSION BASED ON VOLTAGE SOURCE CONVERTERS by Gunnar Asplund, Kjell Eriksson, Hongbo Jiang, Johan Lindberg, Rolf Pålsson, Kjell Svensson ABB Power Systems AB Sweden SUMMARY Voltage Source Converters

More information

Electricity Terminology. Simplifying energy management

Electricity Terminology. Simplifying energy management Simplifying energy management AMR Automated Meter Reading - automatic collection of data from meters which is transferred to a central database for billing and/or analysis. Balancing Mechanism The mechanism

More information

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw

Current valve. for AC 24 V pulse/pause control of electrical loads up to 30 kw 4 937 DESIO Current valve for AC 24 V pulse/pause control of electrical loads up to 30 kw SEA45.1 Use The current valve is used for the control of electric heating elements in heating, ventilation and

More information

Brake module AX5021. Documentation. Please read this document carefully before installing and commissioning the brake module!

Brake module AX5021. Documentation. Please read this document carefully before installing and commissioning the brake module! Documentation Brake module AX5021 Please read this document carefully before installing and commissioning the brake module! Version : 1.2 : 2012.03.05 Date Article-no. : TDmlAX-5021-0000-0200 Page 2/8

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

SELECTION OF FINAL CIRCUIT PROTECTION

SELECTION OF FINAL CIRCUIT PROTECTION SELECTION OF FINAL CIRCUIT PROTECTION By Phil Williams, Product Marketing Manager, Power Distribution Components, Eaton Executive summary The selection of devices for final circuit protection in electrical

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS

N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS N.J.A.C. 14:8-4 NET METERING FOR CLASS I RENEWABLE ENERGY SYSTEMS 14:8-4.1 Scope This subchapter sets forth net metering requirements that apply to electric power suppliers, basic generation service providers

More information

Specification guide no. 9 Active harmonic conditioner from 20 to 480 A

Specification guide no. 9 Active harmonic conditioner from 20 to 480 A Active harmonic conditioner from 20 to 480 A Contents 1 - Installations concerned... 2 1.1 - New installations... 2 1.2 - Existing installations... 2 2 - General... 2 2.1 - Scope... 2 2.2 - Applicable

More information

TERMS AND CONDITIONS

TERMS AND CONDITIONS Virginia Electric and Power Company TERMS AND CONDITIONS XXIV. GENERATOR INTERCONNECTION STANDARD Electric generator interconnection service includes only the ability to interconnect an electric generator

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

ATTACHMENT G. Network Operating Agreement

ATTACHMENT G. Network Operating Agreement ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Anti-blackout system for grid connected solar installations (Solsafe concept)

Anti-blackout system for grid connected solar installations (Solsafe concept) Anti-blackout system for grid connected solar installations (Solsafe concept) General description The Solsafe concept is a system which will automatically switch from a grid feeding inverter connected

More information

Make your electric distribution network safe

Make your electric distribution network safe Make your electric distribution network safe Increase security and quality of electric distribution system Think energy From your problems... Why do you pay too much for bad power quality, insecurity and

More information

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH

Requirements for Offshore Grid Connections. in the. Grid of TenneT TSO GmbH Requirements for Offshore Grid Connections in the Grid of TenneT TSO GmbH Bernecker Straße 70, 95448 Bayreuth Updated: 21 December 2012 1/10 Requirements for Offshore Grid Connections in the Grid of TenneT

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

Cahier technique no. 196

Cahier technique no. 196 Collection Technique... Cahier technique no. 196 Integration of local power generation in industrial sites and commercial buildings T. Hazel "Cahiers Techniques" is a collection of documents intended for

More information

Earth Fault Detection Basics in Theory

Earth Fault Detection Basics in Theory Earth Fault Detection Basics in Theory Author: Dipl.-Ing. Ingo Kühnen Woodward Power Solutions Krefelder Weg 47 47906 Kempen, Germany Kempen, 16.04.2010 Earth_Fault_Detection_20100416.doc page 1 1. Star

More information

Grid Code - High and extra high voltage - Tennet TSO GmbH Bernecker Straße 70, 95448 Bayreuth

Grid Code - High and extra high voltage - Tennet TSO GmbH Bernecker Straße 70, 95448 Bayreuth Grid Code - High and extra high voltage - Tennet TSO GmbH Bernecker Straße 70, 95448 Bayreuth Status: 1. December 2012 1/45 Contents 1 Introduction... 3 1.1 Legal framew ork... 3 1.2 Technical framew ork...

More information

Fundamentals of Power

Fundamentals of Power Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At

More information

EUROPASS DIPLOMA SUPPLEMENT

EUROPASS DIPLOMA SUPPLEMENT EUROPASS DIPLOMA SUPPLEMENT TITLE OF THE DIPLOMA Técnico Superior en Energías Renovables TRANSLATED TITLE OF THE DIPLOMA (EN) (1) Higher Technician in Renewable Energy Sources --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

More information

Context: significant penetration of DG = increased risks for system security

Context: significant penetration of DG = increased risks for system security Distributed Generation: towards an effective contribution to power system security IEEE Tampa GM 2007: Panel on Impact of Dispersed Generation on Power System structure & security Bruno Meyer Outline Context:

More information

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering

Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Brochure More information from http://www.researchandmarkets.com/reports/2171489/ Integration of Distributed Generation in the Power System. IEEE Press Series on Power Engineering Description: A forward

More information

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM

PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LONG ISLAND SMART GRID SMALL GENERATOR INTERCONNECTION SCREENING CRITERIA FOR OPERATING IN PARALLEL WITH LIPA S DISTRIBUTION SYSTEM PSEG-LI SGSGIP DG Screening Criteria 5-29-14 Table of Contents I.

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

How To Understand The Electrical Power Supply Of A Power Supply System

How To Understand The Electrical Power Supply Of A Power Supply System 17 Circuit diagram symbols E 18 CIRCUIT DIAGRAM SYMBOLS electrical network elements three-phase line or cable single-phase line or cable short circuit earth electrode outgoing feeder supply incoming feeder

More information

CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE. General purpose single phase thyristors and solid state relays Product data.

CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE. General purpose single phase thyristors and solid state relays Product data. 425 CONTROLS DATA MANAGEMENT PROCESS AUTOMATION EUROCUBE General purpose single phase thyristors and solid state relays Product data abc 425 EUROCUBE A complete range of low cost solid state relays and

More information

Voltage Regulator SPAU 341 C. Product Guide

Voltage Regulator SPAU 341 C. Product Guide Issued: July 1998 Status: Updated Version: D/25.04.2006 Data subject to change without notice Features Comprehensive voltage regulation for power transformers with on-load tapchangers in distribution substations

More information

How To Choose A Transformer

How To Choose A Transformer Consider open loop MV network as an example source 1 source 2 NC NC NC or NO main MV switchboard A B Detail design of substation NC NC NC NO NC NC switchboard 1 switchboard 2 switchboard 3 MV MV MV LV

More information

DUAL%CHANNEL BROADBAND%LINEAR%AMPLIFIER Model&A800D

DUAL%CHANNEL BROADBAND%LINEAR%AMPLIFIER Model&A800D ELECTRONICS AB DUAL%CHANNEL BROADBAND%LINEAR%AMPLIFIER Model&A800D & HIGH&VOLTAGE& FIXED&GAIN& BROADBAND & 800Vpp&60mA& 100x& DC&to&ca&200&kHz & LOW&OUTPUT&IMPEDANCE& HIGH&SLEW&RATE &

More information

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw

TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION. Micro Generation & Small Generation, 3-phase, less than 30 kw TECHNICAL INTERCONNECTION REQUIREMENTS FOR DISTRIBUTED GENERATION Micro Generation & Small Generation, 3-phase, less than 30 kw i COPYRIGHT 2010 HYDRO ONE NETWORKS INC. ALL RIGHTS RESERVED ii LIMITATION

More information

SDG&E Electric Distribution System Interconnection Handbook. <Revised as of 10/21/2015>

SDG&E Electric Distribution System Interconnection Handbook. <Revised as of 10/21/2015> TABLE OF CONTENTS 1 Introduction... 1 1.1 Purposes... 1 1.2 Applicability and Related Tariffs... 1 1.3 Interconnection Agreement Required... 1 1.4 Technical Requirement... 1

More information

DESCRIPTION DWG DESCRIPTION DWG

DESCRIPTION DWG DESCRIPTION DWG DESCRIPTION DWG DESCRIPTION DWG Ferroresonance 3451/1 3451/2 3451/3 Electro-magnetic Fields (EMF) 3462/1 HV & LV Insulators (Links) 3463/1 A ORIGINAL ISSUE B 14.07.09 APPROVED DATE J. Brooks 25.02.03 INDEX

More information

Power Meter Series 700

Power Meter Series 700 PowerLogic power-monitoring units Power Meter Series 700 Technical data sheet 2007 Functions and characteristics E90463 The PowerLogic Power Meter Series 700 offers all the measurement capabilities required

More information

/ Our accessories complement all PV systems, simplify installation and ensure that the system meets the required safety standards.

/ Our accessories complement all PV systems, simplify installation and ensure that the system meets the required safety standards. 56 / Accessories for inverters Accessories for inverters / Our accessories complement all PV systems, simplify installation and ensure that the system meets the required safety standards. FRONIUS STRING

More information

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, mcint015@fiu.edu, Armando Altamirano, araltami@fiu.edu Osama A. Mohammed, mohammed@fiu.edu Energy Systems

More information

Transfer Equipment Controls

Transfer Equipment Controls Control Types Manual Transfer Switches Nonautomatic Transfer Switches Automatic Transfer Switches The type of control system for the transfer switch will vary depending on the type of switching equipment

More information

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES 1 (6) GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES GENERAL CONDITIONS prepared by Svensk Energi 1. Introductory provisions 1.1 These general conditions

More information

AN-3 SEVEN KEY CONSIDERATIONS BEFORE YOU START YOUR SLIC OR FXS PHONE LINE INTERFACE DESIGN

AN-3 SEVEN KEY CONSIDERATIONS BEFORE YOU START YOUR SLIC OR FXS PHONE LINE INTERFACE DESIGN AN-3 SEVEN KEY CONSIDERATIONS BEFORE YOU START YOUR SLIC OR FXS PHONE LINE INTERFACE DESIGN By Joe Randolph Introduction The conventional 2-wire analog phone line that telephone companies provide to residential

More information

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems

Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems Residential Solar Service Agreement (RSSA) Customer Sited Solar Photovoltaic Systems This Agreement is made and entered into this day of, 20, ( Effective Date ) by and between the Orlando Utilities Commission

More information

POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT

POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT POWER PURCHASE AGREEMENT FOR ROOFTOP SOLAR PV PLANTS WITH NET METERING ARRANGEMENT This Power Purchase agreement is entered into at (place).. on this. day of between Electricity Supply Company Limited

More information

FIRE ALARM SYSTEM TECHNICAL SPECIFICATIONS Page 1 of 10

FIRE ALARM SYSTEM TECHNICAL SPECIFICATIONS Page 1 of 10 TECHNICAL SPECIFICATIONS Page 1 of 10 FIRE DETECTION AND ALARM SYSTEM Scope Furnish a complete 24V DC conventional, electrically supervised, zone annunciated, fire detection and alarm system as specified

More information

2.06. Version. Kinglong New Energy Technology Co.Ltd. Sunteams 1500 Sunteams 3000. Sunteams 4000 Sunteams 5000

2.06. Version. Kinglong New Energy Technology Co.Ltd. Sunteams 1500 Sunteams 3000. Sunteams 4000 Sunteams 5000 Photovoltaic Inverter Specification Version 2.06 1500 2000 3000 4000 5000 Kinglong New Energy Technology Co.Ltd. Kinglong New Energy Technology Co.Ltd. specification 1.1. Introduction... 3 1.1.1. Environment...

More information

Cam switches. Page. Overview 4-2. ON-OFF switches, main switches, maintenance switches 4-3. Changeover switches, reversing switches 4-5

Cam switches. Page. Overview 4-2. ON-OFF switches, main switches, maintenance switches 4-3. Changeover switches, reversing switches 4-5 Eaton Wiring Manual / Page Overview - ON-OFF switches, main switches, maintenance switches - Changeover switches, reversing switches - (Reversing) star-delta switches - Multi-Speed Switches - Interlock

More information

Cable Solutions for Servo and Variable Frequency Drives (VFD)

Cable Solutions for Servo and Variable Frequency Drives (VFD) Cable Solutions for Servo and Variable Frequency Drives (VFD) Electric drive systems with continuous torque and speed control are widespread today. They allow an optimal adjustment of the drive with respect

More information

ABB 1 NEW. Three-phase monitoring relay for grid feeding CM-UFS.1. Data sheet. Features. Approvals. Marks. Order data. Order data - Accessories

ABB 1 NEW. Three-phase monitoring relay for grid feeding CM-UFS.1. Data sheet. Features. Approvals. Marks. Order data. Order data - Accessories 2CDC 251 014 F0t09 Features Monitoring of three-phase mains for grid feeding Type-tested in accordance with DIN V VDE V 0126-1-1: February 2006 Neutral conductor connection configurable Can also be used

More information

CONTINUOUS MONITORING AND AVOIDANCE OF RESIDUAL CURRENTS IN DATA CENTRES WITH RCM White paper Revision 2

CONTINUOUS MONITORING AND AVOIDANCE OF RESIDUAL CURRENTS IN DATA CENTRES WITH RCM White paper Revision 2 IT Power Solutions CONTINUOUS MONITORING AND AVOIDANCE OF RESIDUAL CURRENTS IN DATA CENTRES WITH RCM White paper Revision 2 Thomas B. Jones 1 Introduction Operators and managers consider outages, operational

More information

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage

Totally Integrated Power SIESTORAGE. The modular energy storage system for a reliable power supply. www.siemens.com/siestorage Totally Integrated Power SIESTORAGE The modular energy storage system for a reliable power supply www.siemens.com/siestorage Totally Integrated Power (TIP) We bring power to the point. Our products, systems,

More information

Introduction. Harmonics and IEEE 519 Page 1 of 19

Introduction. Harmonics and IEEE 519 Page 1 of 19 Introduction In an ideal power system, the voltage supplied to customer equipment, and the resulting load current are perfect sine waves. In practice, however, conditions are never ideal, so these waveforms

More information

Current and voltage measuring relays

Current and voltage measuring relays Current and voltage measuring relays RXIK 1, RXEEB 1 and Page 1 Issued June 1999 Changed since July 1998 Data subject to change without notice RXIK 1 RXEEB 1 (SE980082) (SE980081) (SE970869) Features Application

More information

Your Power. Traction energy

Your Power. Traction energy Your Power Traction energy Table of content 1. What is traction energy? 3 1.1 From producer to train 1.2 Advantages 1.3 Energy, voltage or current 1.4 Transport and distribution 1.5 Supply of traction

More information

USER MANUAL CHARGING STATIONS FOR ELECTRIC VEHICLES

USER MANUAL CHARGING STATIONS FOR ELECTRIC VEHICLES USER MANUAL CHARGING STATIONS FOR ELECTRIC VEHICLES 204.CAxxx 204.CBxxx 204.UBxxx 204.WBxxx MP36289 1 ZP90856-GB-6 INDICE 1 SYSTEM DESCRIPTION... 4 1.1 MODES OF OPERATION... 4 2 USER INTERFACE... 6 2.1

More information

TURBOtech srl. SED-635 Digital Excitation System. Industrial Electronics Sector FEATURES

TURBOtech srl. SED-635 Digital Excitation System. Industrial Electronics Sector FEATURES SED-635 Digital Excitation System SED-635 is a complete excitation system capable of adapting to control synchronous generators of any size. The integration of the TOUCH SCREEN operator interface and a

More information

How To Develop A Smart Grid In Elenia

How To Develop A Smart Grid In Elenia GEODE Autumn Seminar in Brighton 12 th of November Utilization of Automatic Meter Management in Smart Grid Development Ville Sihvola Head of Marketing and Sales Elenia Oy Elenia Oy Turnover 220 M Employees

More information

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN 5.1 Introduction So far in the development of this research, the focus has been to estimate the available insolation at a particular location on the earth s surface

More information

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions

PMCS. Integrated Energy Management Solution. Unlock the Full Potential of Power Networks Through Integration. Complete Solution. Informed Decisions PMCS Integrated Energy Management Solution Unlock the Full Potential of Power Networks Through Integration Power Management Control System (PMCS) is a highly customizable, fully integrated end-to-end Energy

More information

SIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE WELDERS

SIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE WELDERS SIZING THE PRIMARY POWER SYSTEM FOR RESISTANCE S By Jack Farrow, May, 2004 WELDING TECHNOLOGY CORPORATION ABSTRACT Information on how to select the correct size of substation transformer and 480V bus to

More information

Power Supply Unit, Primary Switched, Narrow Design MINI-PS-12-24DC/24DC/1

Power Supply Unit, Primary Switched, Narrow Design MINI-PS-12-24DC/24DC/1 Power Supply Unit, Primary Switched, Narrow Design MINI POWER provides: Extra narrow design with widths of 22.5 mm, 45 mm, and 67.5 mm (0.886, 1.772, and 2.657 in.) Global use due to a wide-range input

More information

Three-phase monitoring relay CM-PFE

Three-phase monitoring relay CM-PFE Data sheet Three-phase monitoring relay CM-PFE The CM-PFE is a three-phase monitoring relay that monitors the phase parameter phase sequence and phase failure in three-phase mains. 2CDC 251 005 S0012 Characteristics

More information

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer

Size template. Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer Size template Grid Connection Masterclass Energex John Lansley Senior Network Solutions Engineer The average system size has doubled since 2010 Key Network Issues Reverse power on up to 12 off 11 kv feeders

More information

415V DISTRIBUTION FOR GREEN DATA CENTERS

415V DISTRIBUTION FOR GREEN DATA CENTERS White Paper: HMRP-WP001-A5 June 5, 2012 415V DISTRIBUTION FOR GREEN DATA CENTERS Prepared by: Anthony (Tony) Hoevenaars, P. Eng President and CEO Mirus International Inc. Copyright 2012 Mirus International

More information

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision

More information

Fusible Disconnect Switch

Fusible Disconnect Switch Circuit Breakers Circuit breakers are used in panelboards and switchboards to provide circuit protection and provide a means of energizing and de-energizing a circuit. Siemens Sentron molded case circuit

More information

7. Reactive energy compensation

7. Reactive energy compensation 593 7. Reactive energy compensation 594 7. REACTIVE ENERGY COMPENSATION Reactive energy compensation is an important element for reducing the electricity bill and improving the quality of the electrical

More information

SPECIFICATION COG-2007

SPECIFICATION COG-2007 Cleco Power LLC SPECIFICATION COG-2007 FOR PARALLEL OPPERATION OF CUSTOMER-OWNED GENERATION ON CLECO S ELECTRICAL SYSTEM Revised: March 7, 2014 CONTENTS ITEM NO. TITLE PAGE NO. 1.0 Scope 3 2.0 Policy On

More information

Three phase circuits

Three phase circuits Three phase circuits THREE PHASE CIRCUITS THREE-PHASE ADVANTAGES 1. The horsepower rating of three-phase motors and the kva rating of three-phase transformers are 150% greater than single-phase motors

More information

Wiring Instructions and Operating Manual 12 POINT ULTRABEAM REMOTE MONITORING SYSTEM

Wiring Instructions and Operating Manual 12 POINT ULTRABEAM REMOTE MONITORING SYSTEM Wiring Instructions and Operating Manual 12 POINT ULTRABEAM REMOTE MONITORING SYSTEM Hycontrol Limited, Larchwood House, Orchard Street, Redditch, Worcestershire, B98 7DP, UK. Tel: +44 (0)1527 406800 Fax:

More information

Commission communication in the framework of the implementation of the Council Directive 89/336/EEC (2002/C 190/03)

Commission communication in the framework of the implementation of the Council Directive 89/336/EEC (2002/C 190/03) 10.8.2002 Official Journal of the European Communities C 190/5 Commission communication in the framework of the implementation of the Council Directive 89/336/EEC (2002/C 190/03) (Text with EEA relevance)

More information

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems

LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems LEHI CITY POWER NET METERING STANDARDS For Customer-Owned Electric Generating Systems A. General This Net Metering Standard for Customer-Owned Grid Connected Electric Generating Systems sets forth the

More information

YSmart Technology Co.,Ltd

YSmart Technology Co.,Ltd YSmart Technology Co.,Ltd GWV Series Grid Tie Microinverter User Manual The copyright of this user manual belong to YSmart TechnologyCompany Limited. Without the written permission of the copyright holder,

More information

Increasing Data Center Efficiency by Using Improved High Density Power Distribution

Increasing Data Center Efficiency by Using Improved High Density Power Distribution Increasing Data Center Efficiency by Using Improved High Density Power Distribution By Neil Rasmussen White Paper #128 Executive Summary A new approach to power distribution for high density server installations

More information

Technical Requirements. For Generating Facilities Interconnecting. To The Distribution System. Salt River Project

Technical Requirements. For Generating Facilities Interconnecting. To The Distribution System. Salt River Project Technical Requirements For Generating Facilities Interconnecting To The Distribution System Salt River Project Effective June 6, 2012 1-1 TABLE OF CONTENTS 1. NOTICE OF DISCLAIMER AND USE OF REFERENCES

More information

SURGE PROTECTIVE DEVICES

SURGE PROTECTIVE DEVICES SURGE PROTECTIVE DEVICES 1. INTRODUCTION In order to ensure safety of people, protection of equipment and, to a certain extent, continuity of supply, insulation co-ordination aims at reducing the likelihood

More information

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY

TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY TRACTION NETWORK MONITORING AND PROTECTION SYSTEM SMTN-3 CITY ELECTRIC TRANSPORT RAILWAYS METRO INDUSTRY 2 TRACTION NETWORK MONITORING AND PROTECTION SYSTEM Traction network monitoring and protection system,

More information

Reverse-feed applications for circuit breakers

Reverse-feed applications for circuit breakers Technical Publication PU01200001E Contents Description Page Intoduction.......................................................................... 2 breaker classifications..........................................................

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

ATC-300 Automatic Transfer Switch Controller

ATC-300 Automatic Transfer Switch Controller ATC-300 Technical Data New Information Technical Data Page 2 Effective: May 2004 ATC-300 Introduction The Cutler-Hammer ATC-300 from Eaton s Electrical business is a comprehensive, multi-function, microprocessor-based

More information

DALI RC BASIC SO. Control unit Operating instructions

DALI RC BASIC SO. Control unit Operating instructions DALI RC BASIC SO Control unit Operating instructions Contents Safety... 4 General instructions 4 Safety instructions 4 Description... 5 Purpose and application 5 Function 5 Light control 5 Brightness

More information

Electrical safety of grid-connected solar installations in Western Australia December 2011

Electrical safety of grid-connected solar installations in Western Australia December 2011 Electrical safety of grid-connected solar installations in Western Australia December 2011 Level 1, 303 Sevenoaks Street (cnr Grose Avenue) Cannington, Western Australia 6107 PO Box 135 Cannington WA 6987

More information

Single-phase (220...240 V) voltage monitoring: Undervoltage Overvoltage Window mode (overvoltage + undervoltage) Voltage fault memory selectable

Single-phase (220...240 V) voltage monitoring: Undervoltage Overvoltage Window mode (overvoltage + undervoltage) Voltage fault memory selectable Features 70.11 70.31 70.41 Electronic voltage monitoring relays for single and three-phase applications Multifunctional types, providing the flexibility of monitoring Undervoltage, Overvoltage, Window

More information