1 Solving Fundamental Problems in Model Based, Semi-Automated Building Project Scheduling Can Ersen FIRAT Construction Management and Economics, TKK Helsinki University of Technology Juhani KIIRAS Construction Management and Economics, TKK Helsinki University of Technology Pekka HUOVINEN International Construction Business, TKK Helsinki University of Technology ABSTRACT The main aim of the paper is to explore and to understand fundamental problems in the modeling of the master schedules of building projects and to suggest viable solutions for those problems. Project management and construction management staff is mainly relying on their own tacit experience in planning and scheduling. It is proposed here that combined product and process modeling is a viable way of solving these problems. Fundamental problems in scheduling are here addressed through five questions: (i) How to handle size variety? (ii) How to handle activity scope variety? (iii) How to manage work order, dependencies, and overlapping? (iv) How to dimension activities or to calculate their durations? (v) How to integrate a product model and a resource model with a process model to get enough data? The location based Advanced Line of Balance (ALoB) is herein used as a means for demonstrating and solving the fundamental problem. A building construction information model is suggested to provide enough data for developing viable solutions. Finally, the validity of model based scheduling is initially tested in eight building projects by comparing the model based schedules to the actual planned schedules. Keywords: Advanced line of balance, Building information models, Master schedule and Model based scheduling. INTRODUCTION Building projects are primarily planned based on accumulated, individual tacit experience. All data needed in scheduling such as activities, man-hours, durations, and dependencies are not collected and used in systematic ways. So the outcomes of project planning processes, i.e. schedules are of ad hoc type. Most textbooks on construction scheduling deal only with an activity based procedure for planning a schedule. Network techniques such as Critical Path Method (CPM) are predominantly used among practitioners and scholars. There are numerous ICT-enabled programs and systems based on performing schedules from bottom up i.e. from an activity level to a phase level and further to a project level. Thus, our aims are as follows: (i) to recall the traditional and practice-born problems in scheduling in building projects, (ii) to advance model based building project scheduling, (iii) to solve five fundamental problems in model based, semi-automated scheduling, and (iv) to report on the promising initial test results. Our model based approach includes the semi-automated or iterative processing of project information that is retrieved from building construction information models, i.e. product models and resource and cost models. In other words, we argue that it is possible to obviate the traditional scheduling logic with its practice-born weaknesses by the adoption of model based scheduling. 2. MODELING OF BUILDING PROJECT SCHEDULES IN LITERATURE It seems that there is a slow movement in literature from tacit knowledge based planning systems toward the model based ones in the case of building projects. For example, this kind of a migration has taken place in the sequencing of activities from tacit knowledge based scheduling (e.g. [], [2]) to the model based one (e.g. [3]). Some researchers have suggested improvements [4] in terms of advanced visualization techniques such as 4D [5] and virtual reality [6] for the more effective evaluation of scheduling information.

2 Jongeling [7] combines workflows and location based scheduling. He reports upon the satisfactory results when the 4D models and the line of balance technique were used together to plan the workflows. Recently, Porkka and Kähkönen [8] compiled the best known 4D applications and addressed challenges and future trends in 4D applications. However, there is no published research on interrelatedness between 4D applications and automated planning systems. There are some computer tools using linear scheduling methods and in particular a location based scheduling methodology, the repetitive Line of Balance (LoB) method, such as VicoControl (formerly Graphisoft Control ). Software vendors have been developing 4D modeling tools and 4D models such as Virtual Product Chronology (VPS), Navisworks (Jet Stream), and CommonPoint with Project 4D [9]. So far, commercialized software is based on the bottom-up principle of planning schedules, which requires all information of every activity before a complete schedule is at hand. Some templates of commercial software can readily be used in model based scheduling presuming that the recognized fundamental problems will be solved first. 3. TOWARDS AUTOMATED SCHEDULING - WHAT THEORIES AND WHEREFROM DATA? The nature of building works is in part that of serial production. Same activities are done in a same order in the consecutive sections (locations) of a building. Serial production can be modeled fairly easily. An optimum process is a balanced production, i.e. all activities have same durations (synchronized). The Line of Balance (LoB) technique has been developed for this balanced serial construction. The LoB is a graphical scheduling technique and a location and resources based management system to plan and to manage continuous work flows in specified locations with balanced resource uses. The LoB has turned out to be more effective than the CPM and other traditional network scheduling systems in particular in repetitive construction like housing projects. Herein, we apply the advanced principles of the line of balance techniques to solving an automatic scheduling problem. The Advanced Line of Balance (ALoB) differs from the traditional one so that the sections need not to be equal in size or even in their activity content. In a so called time-place diagram, a workflow of each activity is shown through the sections of a project. In Figure, an example of a flow-line view of a sample location based schedule is given in the case of a building with three locations (A, B, C). y C B A EFSubS FRSuperS Partition Walls EFSubS=Earthwork+Foundations substructure FRSuperS=Framework+Roof Superstructure Interior Works Figure : Example of the application of the ALoB. Key: A flow-line view on () the LBS and hierarchy levels, sectioning, (2) an example of a balanced workflow, and (3) an example of a deviation, non-continuous workflow. So far, no viable total solutions are available for supplying all data needed for automatic scheduling. Thus, we propose combined product and process modeling as a novel way of handling data in model based scheduling. A Building Construction Information Model (BCIM) is offered as an environment, where data are stored, updated, and reused via the evolving project libraries of a building contractor [0]. A BCIM consists of three sub-models as follows: (i) a building product model targets a finished building as a design object, containing building elements and their receipts of building products. (ii) a building project resource and cost model targets a building project as a resource object, retrieving the amounts of building products from a building product model and relying on their installation resource receipts. (iii) a building construction process model targets a building project as a process object, retrieving the activity receipts of elements and resources from the product and resource and cost models and relying on duration calculation rules (dimensioning formulas) []. Moreover, a building product model produces the technical sequence dependencies of activities and a resource model complements them with man-hours to enable the duration calculations of activities. 4. SOLUTIONS TO FIVE FUNDAMENTAL PROBLEMS IN BUILDING PROJECT SCHEDULING Five fundamental problems in model based project scheduling are herein recognized as follows. The fundamental problems are addressed through five investigative questions: (i) How to handle size variety? (ii) How to handle activity scope variety? (iii) How to manage work order, dependencies, and overlapping? A 3 B C x

3 (iv) How to dimension activities or to calculate their durations? and (v) How to integrate a product model and a resource model with a process model to get enough data. Each fundamental question is being explored and initially solved as follows. (i) How to handle a variation of sizes in building projects? A possible solution to this problem is a sectioning by a location breakdown structure (LBS). Sections are specified as so small that activities form a chain without overlapping. A basic process model contains only this chain for one section. Thereafter, all sections are balanced. The sectioning function of the ALoB enables the controlling of various projects. Through a sectioning and LBSs, all dependencies in one section model can be of a finish-to-start (FS) type. The sectioning makes then all overlapping. (ii) How to handle a variation of scopes of building projects as activities? Building elements and their building products in a product model contain model library activity information where this relatedness is specified. So a list of project specific activities can be produced with all data from previous BCIM models. (iii) How to manage a work order (sequencing), dependencies, and an overlapping in building projects? A technical sequence of activities is retrieved from a building product model. No overlapping is needed in any of basic section models. The sequencing of activities (work order) is modeled without time involvement and the checking of a project model is performed by a 4D animation. (iv) How to calculate activity durations, i.e. how to dimension activities in building projects? The dimensioning of activities proceeds from top to down. The total duration of a project in one section is divided between phases and such phase durations between balanced activities. A duration of each activity is calculated by a phase specific duration model or rule. A process model contains dimensioning rules for activities. In Figure 2, the dependencies between the project phases in one section of a typical housing project schedule are given. An interior phase has been divided into two phases: partitioning and interior works. (The same phasing can be seen in Figure, section A.) Location A y EF SubS EF SubS F SuperS F SuperS R SuperS R SuperS F SuperS =Framework Superstructure R SuperS =Roof Superstructure EF SubS = Earthwork+Foundations substructure Partition Walls -PW PW Interior Works Interior Works-IW Figure 2: Phasing of a housing project schedule in terms of dependencies between phases. (v) How to retrieve data from a product model as well as from a resource and cost model in integrated ways for scheduling? This involves a solution of an integration problem of sub-models: product, resource, and cost models. A BCIM serves as an information system to manage building projects. In turn, the targeted novel outcomes of a building construction process model are semi-automated schedules. All the parameters of the models are stored in the libraries and the parameters are then updated based on the actual results in the real projects. So this integrated set of three models makes true learning possible. 5. INITIAL RESULTS OF THE PILOT TESTING IS AUTOMATED SCHEDULING VIABLE? By the year 2008, we have completed the multiple pilot tests in the case of eight residential projects in Finland. In these pilot tests, the VicoControl TM [9] program has been relied upon. It has all features of product and resource models and template for scheduling. In these tests, the real planned schedules were compared to the model based ones. We posit that no comparison should be made to the actual schedules of the executed projects, because actual timing contains always many random delaying events. The effects of such events should be dealt with buffers as part of schedules and not as the goal-oriented durations of activities and phases. A comparison between the model based schedule and the planned one reveals the model s viability and a comparison between the planned schedule and the actual executed times of activities reveals a level of project management performance (Figure 3). IW Interior Works X Model schedule Planned schedule Actual timing Figure 3: Comparison chain, model versus planned and planned versus actual executed project.

4 Our tentative model is started by creating location breakdown structure (LBS) with proper sections. The sectioning function of the Advanced Line of Balance (ALoB) enables the planning and controlling of various building construction projects [2]. The dimensioning of activity durations are done for one section. Dimensioning in other sections is then created automatically in scheduling software. Dimensioning in one section is based on activities on critical path. In the model schedule critical combined activities is used to simplify the list of the activities. Project specific dimensioning information is retrieved from a contractor s resource model. In the current model, some additional information is handled manually, e.g. the volumes of earth excavation and building area. After the calculation of a production rate for building frame work, all interior work is synchronized to the frame work in order to manage a continuous workflow. Duration information is fed in VicoControl TM [9]. After the feeding, a complete schedule is created automatically so that the template file includes all needed dependencies and start delays. Hence, a model based schedule is ready for testing. The test results are presented in Table. Moreover same results can be seen in a graphical form in Figure 4, which is showing the average delays versus the numbers of the sections of the buildings. Moreover, an example of one two section test case is presented in Figure 5, i.e. a projection of the actually planned schedules (dashed lines) onto the model based schedules (continuous lines). Table : Pilot test results of the eight residential projects. The projects are presented in the order of the numbers of the sections. The delays are the differences between the real planned schedule and the model based one. Test project Sections max. delay min. delay av. delay NB Test High rise Test High rise Test Test Test Test Test Test average delay (days) number of sections vs average delay number of sections Figure 4: Graphical illustration of the number of the sections versus the average delays in days in the eight residential projects. This projection serves as a way to measure differences (delays) between the model based schedule and the planned one. Hence, the differences between the dashed lines and the continuous lines are the delays in the calculations presented in Table. 6. CONCLUSIONS WHAT NEXT The main findings are that it is possible (i) to model a master schedule up to some extent and (ii) to form fairly viable and uniform models. (iii) In the eight test projects, the actual schedules were even work shifts (mostly in the interior works phases) longer than the model based schedules. So the model should be calibrated. (iv) One section high rise building differs from the basic model and should be treated differently. (v) Each of the eight actual planned schedules was different and scattered, which implies that no case company-specific way of scheduling exists. (vi) The use of a test model was partly iterative and manual and it seems that iterative planning processes are viable in any future developments. Besides the five fundamental problems, we have also discerned two calibration and updating problems, but they are not presented here. Each of these problems is initially addressed and being solved by applying the principles of model based, semi-automated scheduling.

5 Delay Figure 5: An example of the test case project schedule. The dashed lines indicate a flow-line of the actual planned schedules and the continuous lines indicate the model based ones. 7. REFERENCES [] M. Stefik, Planning with constraints (MOLGEN Part ), Artificial Intelligence, Vol.6, No. 2, pp (Reprinted in E.A. Feigenbaum, Building Blocks of Artificial Intelligence, Reading, MA: Addison-Wesley, 987. [2] K. Kähkönen, Modeling Activity Dependencies for Building Construction Project Scheduling, Espoo: VTT, Publication No. 53, 993. [3] A. Darwiche, R. Levitt, & B. Hayes-Roth, OARPLAN: Generating Project Plans in a Blackboard System by Reasoning about Objects, Actions, and Resources, Stanford, CA: Stanford University, CIFE Technical Report No. 2., 989. [4] E. Sriprasert & N. Dawood, Requirements identification for 4D constraint-based construction planning and control system, Proceedings of CIB W78 Conference. Aarhus, Denmark: Aarhus School of Architecture, [5] K. McKinney & M. Fischer, Generating, evaluating and visualizing construction schedule with CAD tools, Automation in Construction, Vol.7, No. 6, 998, pp [6] A. Retik & A. Shapira, VR-based planning of construction site activities, Automation in Construction, Vol.8, No.6, 999, pp [7] R. Jongeling, A Process Model for Work-Flow Management in Construction. Lulea, Sweden: Lulea University of Technology, PhD Thesis, [8] J. Porkka & K. Kähkönen, Software development approaches and challenges of 4D product models, Proceedings of 24th CIB W78 Conference. Maribor, Slovenia: CIB, [9] Commercial Software Links com; www. commonpointinc.com; com; (accessed 20 May 2008). [0] C. E. Firat, J. Kiiras & P. Huovinen, A Building Construction Information Model for Managing Projects Virtually Innovation in Architecture, Engineering and Construction (AEC) June 23-25, 2008 Antalya Turkey, [] W. Alsakini, J. Kiiras & P. Huovinen,. Management of a virtual construction management services company In Putnik, G. D. and Cunha, M.M. eds., Encyclopedia of Networked and Virtual Organizations. IGI Globa, Vol. II, [2] C. E. Firat, J. Kiiras, K. Kähkönen & P. Huovinen, Model based scheduling in building projects: Is it oxymoron? Proceedings of 24th CIB W78 Conference. Maribor, Slovenia: CIB, 2007.

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.

More information

Virtual Reality Applications in Project Management Scheduling

Virtual Reality Applications in Project Management Scheduling 71 Virtual Reality Applications in Project Management Scheduling Wael A. Abdelhameed University of Bahrain, wael.abdelhameed@gmail.com ABSTRACT This study concentrates on management of construction projects

More information

A Pattern-Based Approach for Facilitating Schedule Generation and Cost Analysis in Bridge Construction Projects

A Pattern-Based Approach for Facilitating Schedule Generation and Cost Analysis in Bridge Construction Projects A Pattern-Based Approach for Facilitating Schedule Generation and Cost Analysis in Bridge Construction Projects I.C. Wu, A. Borrmann & E. Rank Computation in Engineering, Technische Universität München,

More information

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses

BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction

More information

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)

Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Takeoff and Estimating for Design-Build Contractors

Takeoff and Estimating for Design-Build Contractors Takeoff and Estimating for Design-Build Contractors Design-build contractors specialize in turnkey projects that vary from one-of-a-kind office buildings to custom residential properties. Each project

More information

Location Based Scheduling In The Form Of Flow Line and Its Comparison to Cpm/Bar Chart Scheduling - doi: 10.17932/ IAU.IJEMME

Location Based Scheduling In The Form Of Flow Line and Its Comparison to Cpm/Bar Chart Scheduling - doi: 10.17932/ IAU.IJEMME Location Based Scheduling In The Form Of Flow Line and Its Comparison to Cpm/Bar Chart Scheduling - doi: 10.17932/ IAU.IJEMME.m.21460604.2015.5/1.891-903 Alireza Rezaei 1 Abstract Time Management is a

More information

Integrating Software Services for Preproject-Planning

Integrating Software Services for Preproject-Planning Integrating Software Services for Preproject-Planning Edward L DIVITA M.Sc., Ph.D. Candidate divita@stanford.edu Stanford University Stanford, CA 94305-4020 Martin FISCHER Associate Professor fischer@ce.stanford.edu

More information

PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING

PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING Downloaded from orbit.dtu.dk on: Feb 01, 2016 PRACTICAL IMPLICATIONS OF LOCATION-BASED SCHEDULING Andersson, Niclas; Christensen, Knud Published in: CME25:Construction Management and Economics: past, present

More information

CIFECENTER FOR INTEGRATED FACILITY ENGINEERING

CIFECENTER FOR INTEGRATED FACILITY ENGINEERING CIFECENTER FOR INTEGRATED FACILITY ENGINEERING Potential Benefits of Internet-Based Project Control Systems A Study On Monthly Progress Billings Processing By Alex Barrón, Martin Fischer CIFE Technical

More information

CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT

CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT 664 CASE STUDY OF USING AN INTEGRATED 5D SYSTEM IN A LARGE HOSPITAL CONSTRUCTION PROJECT Tanmaya Kala 1, Olli Seppänen 2, Claire Stein 3 ABSTRACT 3D models for constructability analysis, quantity takeoff,

More information

Component Based Development in Software Engineering

Component Based Development in Software Engineering Component Based Development in Software Engineering Amandeep Bakshi, Rupinder Singh Abstract--In today s world, Component Based development is an active research area for more than a decade in software

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS

NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS Ricardo Mendes Jr 1., Luiz Fernando, M. Heineck and Oscar L. Vaca Dep. de Engenharia de Produção e Sistemas, Laboratório de Gerenciamento

More information

Automated construction schedule creation using project information model

Automated construction schedule creation using project information model Automated construction schedule creation using project information model Aleš Mrkela Faculty of civil engineering, University of Maribor, Maribor, Slovenia Danijel Rebolj Faculty of civil engineering,

More information

IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY

IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY IMPLEMENTATION OF LINE-OF-BALANCE BASED SCHEDULING AND PROJECT CONTROL SYSTEM IN A LARGE CONSTRUCTION COMPANY Mika Soini\ Ilkka LeskeHi 2, Olli Seppanen 3 ABSTRACT Line-of-Balance has been successfully

More information

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry

A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry A Comparison Study Between Event Chain Methodology And Critical Path Method In The Construction Industry Pranam B 1, Madhusudan G Kalibhat 2, Sudharshan KR 3 1 Student, Master of Technology (Construction

More information

risks in the software projects [10,52], discussion platform, and COCOMO

risks in the software projects [10,52], discussion platform, and COCOMO CHAPTER-1 INTRODUCTION TO PROJECT MANAGEMENT SOFTWARE AND SERVICE ORIENTED ARCHITECTURE 1.1 Overview of the system Service Oriented Architecture for Collaborative WBPMS is a Service based project management

More information

Linear Schedules for Tunnel Projects

Linear Schedules for Tunnel Projects Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear

More information

Technique (LOBST) for a Real estate sector

Technique (LOBST) for a Real estate sector Journal Paper: Application of Line of Balance Scheduling Technique (LOBST) for a Real estate sector Authors: 1. Prof: Siddesh K Pai Assistant professor National Institute of construction Management & Research(NICMAR)

More information

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING

CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can

More information

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain * TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited

More information

MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009. Timo Hartmann t.hartmann@ctw.utwente.nl

MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009. Timo Hartmann t.hartmann@ctw.utwente.nl Technical Paper #5 MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT 2009 Timo Hartmann t.hartmann@ctw.utwente.nl COPYRIGHT 2009 VISICO Center, University of Twente visico@utwente.nl Integrated

More information

HEURISTIC SOLUTION FOR RESOURCE SCHEDULING FOR REPETITIVE CONSTRUCTION PROJECTS

HEURISTIC SOLUTION FOR RESOURCE SCHEDULING FOR REPETITIVE CONSTRUCTION PROJECTS Management and Innovation for a Sustainable Built Environment ISBN: 9790299 20 2 June 2011, Amsterdam, The Netherlands HEURISTIC SOLUTION FOR RESOURCE SCHEULING FOR REPETITIVE CONSTRUCTION PROJECTS MARCO

More information

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling. Planning & Scheduling CSTM 462 Managing a project through time and resources. The need for proper planning and scheduling. Project Management Objectives 1. Eliminate or reduce project RISK. 2. Obtain a

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

Scheduling Glossary Activity. A component of work performed during the course of a project.

Scheduling Glossary Activity. A component of work performed during the course of a project. Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the

More information

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management

Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute

More information

Module 3: The Project Planning Stage

Module 3: The Project Planning Stage Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you

More information

Priority rules and relationships in micro-scheduling of construction wood-framing tasks

Priority rules and relationships in micro-scheduling of construction wood-framing tasks Priority rules and relationships in micro-scheduling of construction wood-framing tasks Marcel Maghiar, M.S. and Sunitha Jain, M.S. and Avi Wiezel, Ph.D, P.E. Arizona State University Tempe, Arizona This

More information

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014

Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method

More information

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY By Mohammad A. Ammar 1 and Emad Elbeltagi 2 ABSTRACT: Scheduling of construction projects that have multiple units, wherein activities

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

Scheduling Best Practices

Scheduling Best Practices In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project

More information

CHAPTER 24 SOFTWARE PROJECT SCHEDULING. Overview

CHAPTER 24 SOFTWARE PROJECT SCHEDULING. Overview CHAPTER 24 SOFTWARE PROJECT SCHEDULING Overview The chapter describes the process of building and monitoring schedules for software development projects. To build complex software systems, many engineering

More information

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY

BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY BETTER BY 3D DESIGN AND COORDINATION IN BUILDING SERVICES INDUSTRY MR. ALVIN WONG-KAM MAN Building Services Engineering Graduate Gammon Skanska Limited E-mail: alvin.wong@gammonskanska.com Do a 2-Dimensional

More information

Constraint-Directed Scheduling for Multi-Storey Building Projects

Constraint-Directed Scheduling for Multi-Storey Building Projects Constraint-Directed Scheduling for Multi-Storey Building Projects Pasit Lorterapong* and Osama Moselhi** ** Department of Civil Engineering, King Mongkut ' s Institute of Technology Thonburi, Pracha u-tid

More information

Network Calculations

Network Calculations Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks

More information

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry

Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry Line of Balance Scheduling: Software Enabled Use in the U.S. Construction Industry Meena R. Nageeb, MS Texas A&M University College Station, Texas Bradly T. Johnson, PhD Colorado State University Fort

More information

Practical Aspects of Construction Scheduling

Practical Aspects of Construction Scheduling Practical Aspects of Construction Scheduling AACE Atlanta, GA April 16, 2013 Mark G Cundiff, PSP Vice President, Hill International The Preparation of the Estimate involves planning and consideration of

More information

Elite: A New Component-Based Software Development Model

Elite: A New Component-Based Software Development Model Elite: A New Component-Based Software Development Model Lata Nautiyal Umesh Kumar Tiwari Sushil Chandra Dimri Shivani Bahuguna Assistant Professor- Assistant Professor- Professor- Assistant Professor-

More information

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY ISTANBUL TECHNICAL UNIVERSITY FACULTY OF ARCHITECTURE DEPARTMENT OF DESIGN COMPUTING BIM 2037 / BUILDING INFORMATION MODELS INSTRUCTOR: Salih OFLUOĞLU A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL

More information

CRASHING-RISK-MODELING SOFTWARE (CRMS)

CRASHING-RISK-MODELING SOFTWARE (CRMS) International Journal of Science, Environment and Technology, Vol. 4, No 2, 2015, 501 508 ISSN 2278-3687 (O) 2277-663X (P) CRASHING-RISK-MODELING SOFTWARE (CRMS) Nabil Semaan 1, Najib Georges 2 and Joe

More information

Devising new Software Project Risk Management Model: MARUNA

Devising new Software Project Risk Management Model: MARUNA Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the

More information

CIFECENTER FOR INTEGRATED FACILITY ENGINEERING

CIFECENTER FOR INTEGRATED FACILITY ENGINEERING CIFECENTER FOR INTEGRATED FACILITY ENGINEERING Practical and Research Issues in using Industry Foundation Classes for Construction Cost Estimating By Sheryl Staub-French Martin Fischer CIFE Working Paper

More information

Simulating the Structural Evolution of Software

Simulating the Structural Evolution of Software Simulating the Structural Evolution of Software Benjamin Stopford 1, Steve Counsell 2 1 School of Computer Science and Information Systems, Birkbeck, University of London 2 School of Information Systems,

More information

BIM based Schedule Control for Precast Concrete Supply Chain

BIM based Schedule Control for Precast Concrete Supply Chain BIM based Schedule Control for Precast Concrete Supply Chain J. Nissilä a, R. Heikkilä b, I. Romo a, M. Malaska b and T. Aho b a Skanska Oy, Helsinki, Finland b Construction Technology Research Center,

More information

Project Management Using Earned Value

Project Management Using Earned Value Project Management Using Earned Value Third Edition Gary C. Humphreys Earned Value Management Consulting Training 2002, 2011, 2014 Gary C. Humphreys Humphreys & Associates, Inc. All rights reserved. No

More information

On Correlating Performance Metrics

On Correlating Performance Metrics On Correlating Performance Metrics Yiping Ding and Chris Thornley BMC Software, Inc. Kenneth Newman BMC Software, Inc. University of Massachusetts, Boston Performance metrics and their measurements are

More information

Ming Sun 1, Ghassan Aouad, Nick Bakis, Stuart Birchall, William Swan

Ming Sun 1, Ghassan Aouad, Nick Bakis, Stuart Birchall, William Swan The ASCE 8th International Conference on Computing in Civil and Building EngineeringStandford University California, USA, August 14-17, 2000, pp130-137 Integrated Information Management and Exchange for

More information

14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003

14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 A CASE STUDY OF THE IMPACTS OF PRELIMINARY DESIGN DATA EXCHANGE ON NETWORKED PRODUCT DEVELOPMENT PROJECT CONTROLLABILITY Jukka Borgman,

More information

An Integrated Methodology for Implementing ERP Systems

An Integrated Methodology for Implementing ERP Systems APDSI 2000 Full Paper (July, 2000) An Integrated Methodology for Implementing ERP Systems Su-Yeon Kim 1), Eui-Ho Suh 2), Hyun-Seok Hwang 3) 1) Department of Industrial Engineering, POSTECH, Korea (tomi@postech.edu)

More information

How To Program A Laser Cutting Robot

How To Program A Laser Cutting Robot Robotics ABB Robotics Laser Cutting Software High precision laser cutting made easy - Greater manufacturing flexibility at lower capital investment Robotic laser cutting Overview Allows for the increased

More information

Keywords: Programming, planning, linear work, civil engineering, time chainage, 4D, virtual reality.

Keywords: Programming, planning, linear work, civil engineering, time chainage, 4D, virtual reality. Abstract The technique for the representation of the information based on the time chainage diagrams (usually denoted as T.C.D.) is the most common approach, compared to more traditional systems such as

More information

Scheduling Best Practices

Scheduling Best Practices In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules

More information

Scheduling 101 CPM Basics. Phoenix Project Management Systems, LLC www.phoenixcpm.com

Scheduling 101 CPM Basics. Phoenix Project Management Systems, LLC www.phoenixcpm.com Scheduling 101 CPM Basics Phoenix Project Management Systems, LLC www.phoenixcpm.com Scheduling 101 CPM Basics Getting Started with CPM This guide is intended as an introduction to the Critical Path Method

More information

Unit 4: Time Management (PMBOK Guide, Chapter 6)

Unit 4: Time Management (PMBOK Guide, Chapter 6) (PMBOK Guide, Chapter 6) The questions on this topic focus heavily on scheduling techniques, network diagrams, Gantt charts, the critical path, compressing the schedule, PERT, and float. You may or may

More information

The Project Planning Process Group

The Project Planning Process Group 3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity

More information

SPACE-CENTRED INFORMATION MANAGEMENT APPROACH TO IMPROVE CAD-BASED HEALTHCARE BUILDING DESIGN

SPACE-CENTRED INFORMATION MANAGEMENT APPROACH TO IMPROVE CAD-BASED HEALTHCARE BUILDING DESIGN SPACE-CENTRED INFORMATION MANAGEMENT APPROACH TO IMPROVE CAD-BASED HEALTHCARE BUILDING DESIGN SUBMITTED: March 2006 REVISED: November 2006 PUBLISHED: January 2007 at http://itcon.org/2007/4/ EDITOR: B-C

More information

Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2

Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2 Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2 Abstract In construction scheduling, constraints among activities are vital as they govern the

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover

Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover Introduction/Purpose Graphical Project Planning Techniques: An Overview of Gantt, PERT, and CPM Charts Prepared for groups in ECE480 1/6/02, D. Grover The purpose of this brief tutorial is to present an

More information

Strategic Management System for Academic World

Strategic Management System for Academic World 2011 International Conference on Software and Computer Applications IPCSIT vol.9 (2011) (2011) IACSIT Press, Singapore Strategic Management System for Academic World Expert System Based on Composition

More information

Scheduling. Anne Banks Pidduck Adapted from John Musser

Scheduling. Anne Banks Pidduck Adapted from John Musser Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart

More information

AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS

AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS AUTOMATED CONSTRUCTION PLANNING FOR MULTI-STORY BUILDINGS Tang-Hung Nguyen 1 ABSTRACT This paper outlines a computer-based framework that can assist construction planners and schedulers in automatically

More information

DOCUMENTOS DE TRABAJO Serie Gestión

DOCUMENTOS DE TRABAJO Serie Gestión Nº 130 A Lightweight Approach for Designing Enterprise Architectures Using BPMN: an Application in Hospitals O.Barros, R.Seguel, and A. Quezada DOCUMENTOS DE TRABAJO Serie Gestión Aceptado para presentacion

More information

Oracle Data Integrator: Administration and Development

Oracle Data Integrator: Administration and Development Oracle Data Integrator: Administration and Development What you will learn: In this course you will get an overview of the Active Integration Platform Architecture, and a complete-walk through of the steps

More information

Dynamic Change Management for Fast-tracking Construction Projects

Dynamic Change Management for Fast-tracking Construction Projects Dynamic Change Management for Fast-tracking Construction Projects by Moonseo Park 1 ABSTRACT: Uncertainties make construction dynamic and unstable, mostly by creating non value-adding change iterations

More information

PROCESS OF MOVING FROM WATERFALL TO AGILE PROJECT MANAGEMENT MODEL

PROCESS OF MOVING FROM WATERFALL TO AGILE PROJECT MANAGEMENT MODEL PROCESS OF MOVING FROM WATERFALL TO AGILE PROJECT MANAGEMENT MODEL Sanja Vukićević 1, Dražen Drašković 2 1 Faculty of Organizational Sciences, University of Belgrade, vukicevicsanja@yahoo.com 2 Faculty

More information

A STRATEGIC PLANNER FOR ROBOT EXCAVATION' by Humberto Romero-Lois, Research Assistant, Department of Civil Engineering

A STRATEGIC PLANNER FOR ROBOT EXCAVATION' by Humberto Romero-Lois, Research Assistant, Department of Civil Engineering A STRATEGIC PLANNER FOR ROBOT EXCAVATION' by Humberto Romero-Lois, Research Assistant, Department of Civil Engineering Chris Hendrickson, Professor, Department of Civil Engineering, and Irving Oppenheim,

More information

Project Management Planning

Project Management Planning Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing

More information

Building flexibility management

Building flexibility management Building flexibility management Arto SAARI Dr Tech Helsinki University of Technology, Laboratory of Construction Economics and Management Espoo, Finland arto.saari@hut.fi Pekka HEIKKILÄ M Sc AIR-IX Talotekniikka

More information

Project Scheduling & Tracking

Project Scheduling & Tracking Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the

More information

Precedence Diagram Method. CSTM 462 Planning & Scheduling

Precedence Diagram Method. CSTM 462 Planning & Scheduling Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.

More information

Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education

Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Keith E. Sylvester, Ph.D. and Charlotte Dietrich, Undergraduate Student East Carolina University Greenville,

More information

A-1. Chapter 1. Project planning. Chapter 1. Festo Didactic Mechatronics

A-1. Chapter 1. Project planning. Chapter 1. Festo Didactic Mechatronics A-1 Project planning A-2 Mechatronics specialists are responsible for the complete service life of an industrial machine, from the initial planning phase through to its disassembly and disposal. This cycle

More information

Embedded/Real-Time Software Development with PathMATE and IBM Rational Systems Developer

Embedded/Real-Time Software Development with PathMATE and IBM Rational Systems Developer Generate Results. Real Models. Real Code. Real Fast. Embedded/Real-Time Software Development with PathMATE and IBM Rational Systems Developer Andreas Henriksson, Ericsson andreas.henriksson@ericsson.com

More information

Software Life-Cycle Management

Software Life-Cycle Management Ingo Arnold Department Computer Science University of Basel Theory Software Life-Cycle Management Architecture Styles Overview An Architecture Style expresses a fundamental structural organization schema

More information

CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?

CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST? EXECUTIVE SUMMARY PURPOSE: This paper is a comparison and contrast of two project management planning and execution methodologies: critical path methodology (CPM) and the critical chain project management

More information

Information Systems Analysis and Design CSC340. 2004 John Mylopoulos. Software Architectures -- 1. Information Systems Analysis and Design CSC340

Information Systems Analysis and Design CSC340. 2004 John Mylopoulos. Software Architectures -- 1. Information Systems Analysis and Design CSC340 XIX. Software Architectures Software Architectures UML Packages Client- vs Peer-to-Peer Horizontal Layers and Vertical Partitions 3-Tier and 4-Tier Architectures The Model-View-Controller Architecture

More information

CRITICAL PATH METHOD (CPM) SCHEDULES

CRITICAL PATH METHOD (CPM) SCHEDULES 96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without

More information

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS

COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Proceedings from the 2004 ASEM National Conference pp. 453-460, Alexandria, VA (October 20-23, 2004 COMPUTING DURATION, SLACK TIME, AND CRITICALITY UNCERTAINTIES IN PATH-INDEPENDENT PROJECT NETWORKS Ryan

More information

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects

Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Enterprise Resource Planning Analysis of Business Intelligence & Emergence of Mining Objects Abstract: Build a model to investigate system and discovering relations that connect variables in a database

More information

Hybrid Approach of Client-Server Model and Mobile Agent Technology to Drive an E-Commerce Application

Hybrid Approach of Client-Server Model and Mobile Agent Technology to Drive an E-Commerce Application Hybrid Approach of Client-Server Model and Mobile Agent Technology to Drive an E-Commerce Application Ajab Maheshwari PG Scholar, IT Dept, IET-DAVV, Indore (M.P.), India. Dr. Pratosh Bansal Associate Professor,

More information

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project

More information

Measuring and Monitoring the Quality of Master Data By Thomas Ravn and Martin Høedholt, November 2008

Measuring and Monitoring the Quality of Master Data By Thomas Ravn and Martin Høedholt, November 2008 Measuring and Monitoring the Quality of Master Data By Thomas Ravn and Martin Høedholt, November 2008 Introduction We ve all heard about the importance of data quality in our IT-systems and how the data

More information

SWEN 256 Software Process & Project Management

SWEN 256 Software Process & Project Management SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end

More information

Project Management Dr. James A. Bednar

Project Management Dr. James A. Bednar Project Management Dr. James A. Bednar jbednar@inf.ed.ac.uk http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce

More information

DM810 Computer Game Programming II: AI. Lecture 11. Decision Making. Marco Chiarandini

DM810 Computer Game Programming II: AI. Lecture 11. Decision Making. Marco Chiarandini DM810 Computer Game Programming II: AI Lecture 11 Marco Chiarandini Department of Mathematics & Computer Science University of Southern Denmark Resume Decision trees State Machines Behavior trees Fuzzy

More information

APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION

APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION Fitria H. Rachmat 1, Lingguang Song 2, and Sang-Hoon Lee 2 1 Project Control Engineer, Bechtel Corporation, Houston, Texas, USA 2

More information

The Project Management Plan will be used to guide, communicate and coordinate project efforts.

The Project Management Plan will be used to guide, communicate and coordinate project efforts. F.1 General Implementation Contractor Deliverables include critical system planning and development components. Sufficient deliverables have been identified at key steps in the project to guide the project

More information

Software Project Management Part 2: Work Breakdown Structures

Software Project Management Part 2: Work Breakdown Structures Software Project Management Part 2: Work Breakdown Structures Introduction into Software Engineering Lecture 20 Bernd Bruegge Applied Software Engineering Technische Universitaet Muenchen 1 Where are we?

More information

Task Characteristics, Knowledge Sharing and Integration, and Emergency Management Performance: Research Agenda and Challenges

Task Characteristics, Knowledge Sharing and Integration, and Emergency Management Performance: Research Agenda and Challenges Task Characteristics, Knowledge Sharing and Integration, and Emergency Management Performance: Research Agenda and Challenges Irma Becerra-Fernandez becferi@fiu.edu Arvind Gudi AGudi@aol.com Weidong Xia

More information

Manual on Training Preparation

Manual on Training Preparation Project on Improvement of Local Administration in Cambodia Three Steps of Training Preparation Step 1: Work Breakdown Structure Step 2: Schedule Step 3: Budget Table of Contents Three Steps of Training

More information

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many

Manufacturing. Manufacturing challenges of today and how. Navision Axapta solves them- In the current explosive economy, many Manufacturing challenges of today and how Navision Axapta solves them- the solution for change; controlled by you. Manufacturing In the current explosive economy, many manufacturers are struggling to keep

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.

MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions

More information

8. Project Time Management

8. Project Time Management 8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project

More information