E- Materials - ESBN and Public Lighting Safety

Size: px
Start display at page:

Download "E- Materials - ESBN and Public Lighting Safety"

Transcription

1 Public Lighting & ESBN LV Network Asset Ownership and Unbundling Proposals Proposals for presentation to CER & Local Authorities October

2 Topics Background Proposals Key Points Actions required 2

3 Background Historic practice of erecting public lighting on low voltage public electricity distribution network. ESB provides installation and maintenance/repair service for local authorities for these and other types of PL installations via a separate company within the ESB Group know as ESB Contracts. ESBC is a commercial company operating in the electrical contracting industry in competition with other companies The LV public distribution network is managed and operated by a different and separate company within ESB know as ESB Networks. ESBN s activities and revenues are dictated by CER based on legislation passed by the DAIL to implement Competition in Electricity Supply. ESBN has no statutory requirement to make the public electricity distribution network available to physically support public lighting equipment. 3

4 ESB Power Generation ESB Networks ESB Customer Supply & ESB Contracts ESB International & ESB Independent Energy 4

5 Background No existing agreement on ownership of assets No existing agreement covering the sharing of network ESBN responsible for provision of electricity connection L.A.s responsible for provision of lighting L.A.s wish to increase access for contractors on PL work Much of the LV network is over 50 years old and is at the end of its useful/economic life. Accordingly ESBN has no choice but to undertake refurbishment of LV networks for public safety and economic reasons. This will require replacement of poles on which PL equipment including control gear is currently mounted, retirement of switchwires, regularise interface arrangements and decisions on networks that are only for PL and therefore should not be refurbished by ESBN 5

6 Background Issue first raised at LA conference on UMS in Feb 2005 ESBN wrote to CCMA Transport Sub committee in May 2005 and LGMSB in September 2005 requesting the formation of a joint working group to address emerging issues. CER UMS Workshop in June 2005 set up industry group to look at all UMS issues. Following second meeting of this group in February 2006, LAs were requested to send reps to a Technical Workshop for discussion of safety and asset ownership & unbundling issues. This workshop took place in March 2006 and the agreed actions included the following Briefing on ESBN Safety Rules requirements for LA contractors/staff working in proximity of LV networks ESBN to draft Asset Ownership to Unbundling proposals LA reps to obtain agreement from CCMA to participate in joint investigations of work and cost involved in unbundling in two pilot locations 6

7 Background Unbundling proposals were presented formally to the Group in October. In order to obtain wider consultation. No mandated LA group has yet come forward to engage with ESBN on the issues. Current Ad Hoc arrangements need to be regularised in order for ESBN to ramp up LVR work from the second quarter of

8 No difficulty in principle! Access for PL Contractors? Requires agreement and implementation of asset unbundling proposals L.A. responsibility to develop safety management and training requirements etc for their contractors/staff. ESBN will provide input in relation to procedures and training required where L.A. s want contractor/staff to work on PL or other LA assets located in the vicinity of or on ESBN networks. 8

9 Unbundling of Public Lighting and Public Electricity Distribution Assets Proposals: All LAs to be briefed on current Safety and Operation issues 9

10 Work on or in Work on or in the vicinity of network; Training Certification Assessment & Approvals Work Methods & procedures 10 Auditing

11 ESB LV & Public Lighting Switch-wire System Safety and operational control of electrical systems ESB Connection to PL Control Box 11

12 Unbundling of Public Lighting and Public Electricity Distribution Assets Proposals: - All LAs to be briefed on current Safety and Operation issues Agree ownership and boundary points for existing assets 12

13 1 13

14 2 14

15 Public Lighting Switch-wire System 3 ESB Connection to PL Control Box 15

16 4 16

17 5 17

18 18

19 6 7 19

20 8 20

21 Floodlighting for church? 9 21

22 Unbundling of Public Lighting and Public Electricity Distribution Assets Proposals: - All LAs to be briefed on current Safety and Operation issues - Agree ownership and boundary points for existing assets Agree identification and labelling of respective assets 22

23 23

24 24

25 L.A. 25

26 Unbundling of Public Lighting and Public Electricity Distribution Assets Proposals: - All LAs to be briefed on current Safety and Operation issues - Agree ownership and boundary points for existing assets - Agree identification and labelling of respective assets Agree basis for sharing network now and in the future 26

27 27

28 Unbundling of Public Lighting and Public Electricity Distribution Assets Proposals: All LAs to be briefed on current Safety and Operation issues Agree ownership and boundary points for existing assets Agree identification and labelling of respective assets Agree basis for sharing network now and in the future For existing installations agree plan for installation of isolation/protection equipment at boundary points in line with National Code of Practice for Customer Interface Installation of Customer Interface for all new installations. Provision of Wiring Completion Certificates in line with ETCI rules for new/refurbished installations Agree plan for removal of switch-wire Agree plan for removal of PL equipment from MP s and Subs Application and payment required for all new connections to ESBN network 28

29 Public Lighting & ESBN LV Network(1) Key Points Transfer of ownership of PL (only) networks to LAs (approx. 9,000 poles) Continue to allow LAs to erect new or retain PL on existing OH networks subject to unbundling No extension of ESBN OH LV network purely to cater for PL No objection to LAs erecting wood poles and overhead conductors for their own OH PL installations which can be connected via aerials and interface Costs associated with retaining PL assets on ESBN networks, removal of switchwire, transfer of PL equipment and provision of interfaces (OH & UG), during refurbishment or other work carried out by either LA or ESBN, to be fully attributable to LAs. Installation of interface requirements at boundary points for all new or refurbished installations L.A. cost Cost recovery mechanism for ESBN unbundling work Interim control of system (incl. sw./w.) ESBN Access for PL Contr. Competency, training, approval & unbundling 29

30 Public Lighting & ESBN LV Network(3) Actions Brief LAs on safety, operational and ownership issues Formation of mandated LA group to engage with ESBN during March with a view to reaching agreement in April. In absence of agreement, ESBN will seek agreement with CER on basis for proceeding with LVR and future position on sharing of network. All future PL work to be consistent with safety and unbundling requirements. 30

31 END 31

32 Assessment of Contractors Contractors working on ESB Networks as PSCS are assessed on the following items:- Safety Documentation Risk Assessments and Control of Risks Safety management System & resources Knowledge and Experience 32

33 Assessment of Contractors Effectiveness of Site management in implementing a Safety & Health Plan Demonstration of Competence in carrying out work in safe manner Examples of investigations, follow up on incidents, near misses 33

34 Assessment of Persons to Work on ESB Network For the Nominated Person:- Attend an ESB Induction Course Must have successfully attended a recognised training course for the activity being undertaken Outline involvement in LV operations with any other utility Must complete training in Knowledge of Proximity Limits Must understand safe or protected working zone 34

35 Assessment of Persons to Work on ESB Network Must understand ESB Safety Rules as they apply to OH PL Network Knowledge of Role and responsibilities of personnel with authority under the Safety Rules Understand precautions to be taken before working on apparatus,viz. identify, disconnect, earth, safety of public Cary out On Site Assessment if required 35

36 Approvals Process Candidate receives Approval to work on ESB LV Single and three phase tail fed and interconnected network subject to:- Certification of training On Site assessment (if required) Assessment by ESB operations personnel 36

High Voltage. Hazards

High Voltage. Hazards High Voltage Hazards HV Hazards Substations, Overhead Lines, Cables Safety Incidents Requirements for Designers, Constructors Construction Regs 2013 and other Legislation Codes of Practice Other Guidance

More information

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Company Policy MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS. Page 1 of 11

Company Policy MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS. Page 1 of 11 MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS Page 1 of 11 MANAGEMENT OF OVERHEAD PRIVATE AND SHARED MAINS 2015 Contents 1.0 POLICY STATEMENT... 3 2.0 PURPOSE... 4 3.0 REFERENCES... 4 4.0 DEFINITIONS...

More information

Information Governance Strategy. Version No 2.0

Information Governance Strategy. Version No 2.0 Plymouth Community Healthcare CIC Information Governance Strategy Version No 2.0 Notice to staff using a paper copy of this guidance. The policies and procedures page of PCH Intranet holds the most recent

More information

Customer Installation Safety Plan. March 2015

Customer Installation Safety Plan. March 2015 Customer Installation Safety Plan March 2015 Document History Issue No. Date Approved By Summary of Changes 1 June 2014 Chief Engineer Updated and revised in line with requirement for biennial review under

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)

More information

ESB Telecoms Ltd Contractor Safety Guidelines

ESB Telecoms Ltd Contractor Safety Guidelines ESB Telecoms Ltd Contractor Safety Guidelines Version Date Issued by Reason for Change 1 27 th January 2003 P Gregg 2 24 th June 2003 P Gregg Addition of contents 3 18 th May 2007 P Gregg Revision of section

More information

Distribution Business Electrical Safety Performance Reporting Guidelines

Distribution Business Electrical Safety Performance Reporting Guidelines Distribution Business Electrical Safety Performance Reporting Guidelines 1. General The Electricity Safety Act 1998 (the Act) specifies that Energy Safe Victoria (ESV) has eleven functions. Two of the

More information

Networks. Code of Practice for Avoiding Danger from Overhead Electricity Lines

Networks. Code of Practice for Avoiding Danger from Overhead Electricity Lines Networks Code of Practice for Avoiding Danger from Overhead Electricity Lines CODE OF PRACTICE FOR AVOIDING DANGER FROM OVERHEAD ELECTRICITY LINES (FIRST EDITION SEPTEMBER 2008) Approved by the Health

More information

Asbestos Management Policy (Version 3)

Asbestos Management Policy (Version 3) Asbestos Management Policy (Version 3) Contents Page Introduction 3 College Policy Statement for Asbestos Management 3 Objectives (of this Policy and Procedure) 3 Application of Policy 4 Licensed Asbestos

More information

The Electrical Safety Regulation (pre and post 1 January 2014)

The Electrical Safety Regulation (pre and post 1 January 2014) The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013

More information

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design

More information

INJURY PREVENTION AND MANAGEMENT

INJURY PREVENTION AND MANAGEMENT INJURY PREVENTION AND MANAGEMENT PERFORMANCE MEASUREMENT FOR SENIOR OFFICERS KEY ACCOUNTABILITY ACTPS and Agency injury prevention and injury management policies and procedures are implemented and operating

More information

Contestability on the Distribution System ESB Networks Key Principles and Processes Paper

Contestability on the Distribution System ESB Networks Key Principles and Processes Paper Contestability on the Distribution System ESB Networks Key Principles and Processes Paper Revision Date: 01/09/2010 Revision No.: 0 Document No: DOC-090211-BGY Issued by: ESB Networks Ltd. Approved by:

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

Information Governance Strategy. Version No 2.1

Information Governance Strategy. Version No 2.1 Livewell Southwest Information Governance Strategy Version No 2.1 Notice to staff using a paper copy of this guidance. The policies and procedures page of LSW Intranet holds the most recent version of

More information

Health & Safety Management System Manual

Health & Safety Management System Manual Health & Safety Management System Manual Document Information Document Number Description HSMSM This manual describes the Health & Safety Management System elements of the Integrated Management System

More information

SERVICE - GENERAL Residential, Commercial, Industrial

SERVICE - GENERAL Residential, Commercial, Industrial PAGE 1 OF 9 USE: Rules and procedures for overhead or underground services. PREVIOUS REVISION 10-01-01 ORIGINATED 03-94 PREVIOUS NUMBER ER 1-290-B, 07-15-93 LATEST REVISION: Remove details of Facility

More information

Corporate Health and Safety Policy

Corporate Health and Safety Policy Corporate Health and Safety Policy Publication code: ED-1111-003 Contents Foreword 2 Health and Safety at Work Statement 3 1. Organisation and Responsibilities 5 1.1 The Board 5 1.2 Chief Executive 5 1.3

More information

Printed Copies of this Document are Uncontrolled Refer to the Portal for the Latest Version TABLE OF CONTENTS

Printed Copies of this Document are Uncontrolled Refer to the Portal for the Latest Version TABLE OF CONTENTS Printed Copies of this Document are Uncontrolled Refer to the Portal for the Latest Version TABLE OF CONTENTS 1 PURPOSE 3 2 SCOPE 3 3 ABBREVIATIONS 3 4 DEFINITIONS 3 5 SPECIFIC RESPONSIBILITIES 3 5.1 Executive

More information

SITE CONTRACTOR PROCEDURES

SITE CONTRACTOR PROCEDURES SITE CONTRACTOR PROCEDURES Asset Collection Type B Assets are considered High risk ; the site activities must be in accordance with Graysonline contractor procedures and are to be collected by appointment

More information

MANAGEMENT OF ASBESTOS POLICY

MANAGEMENT OF ASBESTOS POLICY MANAGEMENT OF ASBESTOS POLICY The application of this policy and procedure ensures that no employee receives less favourable treatment on grounds of sex, trans-gender status, sexual orientation, religion

More information

GLASGOW SCHOOL OF ART OCCUPATIONAL HEALTH AND SAFETY POLICY. 1. Occupational Health and Safety Policy Statement 1

GLASGOW SCHOOL OF ART OCCUPATIONAL HEALTH AND SAFETY POLICY. 1. Occupational Health and Safety Policy Statement 1 GLASGOW SCHOOL OF ART OCCUPATIONAL HEALTH AND SAFETY POLICY CONTENTS PAGE 1. Occupational Health and Safety Policy Statement 1 2. Occupational Health and Safety Management System 2 3. Organisational Management

More information

Report for Agenda Item: 19. QLDC Organisational Health Safety and Wellbeing Performance

Report for Agenda Item: 19. QLDC Organisational Health Safety and Wellbeing Performance QLDC Council 3 June 216 Department: Corporate Services Report for Agenda Item: 19 QLDC Organisational Health Safety and Wellbeing Performance Purpose The purpose of this report is to provide Councillors

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

South Norfolk Council Business Continuity Policy

South Norfolk Council Business Continuity Policy South Norfolk Council Business Continuity Policy 1 Title: Business Continuity Policy Date of Publication: TBC Version: 2 Published by: Emergency Planning Team Review date: April 2014 Document Owner: Document

More information

Electrical Services Engineering, School of Electrical and Electronic Engineering, Dublin Institute of Technology, Kevin St., Dublin 8.

Electrical Services Engineering, School of Electrical and Electronic Engineering, Dublin Institute of Technology, Kevin St., Dublin 8. Electrical Services Engineering, School of Electrical and Electronic Engineering, Dublin Institute of Technology, Kevin St., Dublin 8. Tuesday, Ms. Tara O Beirne, Commission for Energy Regulation, The

More information

How To Manage Risk In Ancient Health Trust

How To Manage Risk In Ancient Health Trust SharePoint Location Non-clinical Policies and Guidelines SharePoint Index Directory 3.0 Corporate Sub Area 3.1 Risk and Health & Safety Documents Key words (for search purposes) Risk, Risk Management,

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

OCCUPIERS DUTIES SITE ACCESS

OCCUPIERS DUTIES SITE ACCESS OCCUPIERS DUTIES SITE ACCESS Health and Safety at Work Act 1974 - Section 4 - Persons in control of premises Must ensure as far as they are in control that the premises are so as is reasonably practicable

More information

School or service safety advisor (SSA) role

School or service safety advisor (SSA) role School or service safety advisor (SSA) role Document control information Published document name: ssa-role-gn Date issued: January 2012 Version: 1.0 School or service safety advisor (SSA) role Previous

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety

More information

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

Policy 7 Management of Asbestos

Policy 7 Management of Asbestos Policy 7 Management of Asbestos 1.0 Introduction Development & Infrastructure recognise both the need to protect their employees from the risks associated with encountering asbestos and the potential for

More information

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy

Asbestos Policy ASBESTOS POLICY. Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy ASBESTOS POLICY Version 2 / Jun 2015 Page 1 of 11 Asbestos Policy This is a controlled document. It should not be altered in any way without the express permission of the author or their representative.

More information

The Management of Asbestos containing Materials

The Management of Asbestos containing Materials The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...

More information

Health and Safety Policy Part 1 Policy and organisation

Health and Safety Policy Part 1 Policy and organisation Health and Safety Policy Part 1 Policy and organisation ICO H&S Policy Policy and organisation, June 2014 Page 1 of 6 1. Scope 1.1 The Health and Safety policy applies to all employees of the Information

More information

RISK MANAGEMENT FRAMEWORK

RISK MANAGEMENT FRAMEWORK RISK MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Manager Organisational Development

More information

REPORT 4 FOR DECISION. This report will be considered in public

REPORT 4 FOR DECISION. This report will be considered in public REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director

More information

ELECTRIC SCHEDULE LS-2 Sheet 1 CUSTOMER-OWNED STREET AND HIGHWAY LIGHTING

ELECTRIC SCHEDULE LS-2 Sheet 1 CUSTOMER-OWNED STREET AND HIGHWAY LIGHTING Revised Cal. P.U.C. Sheet No. 33883-E Cancelling Revised Cal. P.U.C. Sheet No. 28182-E ELECTRIC SCHEDULE LS-2 Sheet 1 APPLICABILITY: TERRITORY: RATES: This schedule is applicable to services for lighting

More information

SAFETY OF SOLAR PANEL INSTALLATIONS IN VICTORIA REPORT

SAFETY OF SOLAR PANEL INSTALLATIONS IN VICTORIA REPORT SAFETY OF SOLAR PANEL INSTALLATIONS IN VICTORIA REPORT July 2010 Table of Contents Executive Summary... 3 Glossary of Acronyms and Phrases.....4 Introduction...5 Background 6 Electricity safety requirements

More information

BEFORE USING THIS GUIDANCE, MAKE SURE YOU HAVE THE MOST UP TO DATE VERSION GUIDANCE 2 POLICY AREA: INFORMATION GOVERNANCE

BEFORE USING THIS GUIDANCE, MAKE SURE YOU HAVE THE MOST UP TO DATE VERSION GUIDANCE 2 POLICY AREA: INFORMATION GOVERNANCE GUIDANCE 1 TITLE: INFORMATION GOVERNANCE FRAMEWORK 2 POLICY AREA: INFORMATION GOVERNANCE 3 ACCOUNTABLE DIRECTOR FOR POLICY AREA: DIRECTOR OF QUALITY AND GOVERNANCE 4 GUIDANCE DRAFTED BY: INTEGRATED GOVERNANCE

More information

As corresponding author, if I can be of further assistance, please do not hesitate to contact me.

As corresponding author, if I can be of further assistance, please do not hesitate to contact me. Department of Electrical Services Engineering (DESE) Dublin Institute of Technology Kevin Street Dublin 8 Friday, 27 May 2011 Mr David Egan Commission for Energy Regulation The Exchange, Belgard Square

More information

Building Electrical Infrastructure

Building Electrical Infrastructure Building Electrical Infrastructure Industrial & Commercial Connections, Industrial / Urban Residential Development, Asset Relocation, Street Lighting Our Company Our vision is to combine electrical engineering

More information

Information Governance Strategy

Information Governance Strategy Information Governance Strategy ONCE PRINTED OFF, THIS IS AN UNCONTROLLED DOCUMENT. PLEASE CHECK THE INTRANET FOR THE MOST UP TO DATE COPY Target Audience: All staff employed or working on behalf of the

More information

38. Project Management

38. Project Management Draft 1 - RGU: Master Retention Schedule (MaRS) November 2008 38. Project Management The function of managing projects. The original copy of the records in this section will be held by and. Some records

More information

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation

More information

EAST AYRSHIRE COUNCIL. No Goals Target Date Progress & Comments

EAST AYRSHIRE COUNCIL. No Goals Target Date Progress & Comments Page 1 of 18 No Goals Target Date Progress & Comments OBJECTIVE 1 - ENCOURAGING A POSITIVE SAFETY CULTURE INVOLVING ALL EMPLOYEES ACTION AREA 1.1 - Services will ensure the implementation of corporate

More information

Diploma of Practice Management

Diploma of Practice Management Diploma of Practice Management Assessment Tasks Module 3 Part A Covering Units: HLTIN301A HLTIN403B Comply with Infection Control Policies and Procedures in Health Work (Prerequisite) Implement and Monitor

More information

TECHNICAL DESCRIPTION OF THE DISTRIBUTION SUBSTATION REMOTE MONITORING SYSTEM

TECHNICAL DESCRIPTION OF THE DISTRIBUTION SUBSTATION REMOTE MONITORING SYSTEM HELLENIC ELECTRICITY DISTRIBUTION NETWORK OPERATOR S.A. NOTICE OF CALL FOR TENDERS No ND-xxx PROJECT: Pilot Telemetering and Management System for the Electric Power Supply Demand by Residential and Small

More information

OHS Contractor Management Procedure

OHS Contractor Management Procedure The Wudinna District Council will through this procedure seek to ensure that Contractors they engage have an adequate understanding and a commitment to Occupational Health, Safety and Welfare as well as

More information

Service & Installation Rules 2014

Service & Installation Rules 2014 Victorian Electricity Distributors Service & Installation Rules 2014 These Service & Installation Rules form the following Distributors Reasonable Technical Requirements for the connection of electrical

More information

Rolls Royce s Corporate Governance ADOPTED BY RESOLUTION OF THE BOARD OF ROLLS ROYCE HOLDINGS PLC ON 16 JANUARY 2015

Rolls Royce s Corporate Governance ADOPTED BY RESOLUTION OF THE BOARD OF ROLLS ROYCE HOLDINGS PLC ON 16 JANUARY 2015 Rolls Royce s Corporate Governance ADOPTED BY RESOLUTION OF THE BOARD OF ROLLS ROYCE HOLDINGS PLC ON 16 JANUARY 2015 Contents INTRODUCTION 2 THE BOARD 3 ROLE OF THE BOARD 5 TERMS OF REFERENCE OF THE NOMINATIONS

More information

Operating Instructions. Room temperature controller

Operating Instructions. Room temperature controller Operating Instructions 1. Area of application The room temperature controller is used to regulate the temperature in closed rooms such as flats, schools, function suites, workshops, etc. Safety instructions

More information

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY

CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY AND POLICY Zurich Management Services Limited Registered in England: No 2741053 Registered Office The Zurich Centre, 3000 Parkway Whiteley, Fareham Hampshire, PO15 7JZ CHAPTER 1: BUSINESS CONTINUITY MANAGEMENT STRATEGY

More information

HP1265, LD 1778, item 1, 124th Maine State Legislature An Act To Enable the Installation of Broadband Infrastructure

HP1265, LD 1778, item 1, 124th Maine State Legislature An Act To Enable the Installation of Broadband Infrastructure PLEASE NOTE: Legislative Information cannot perform research, provide legal advice, or interpret Maine law. For legal assistance, please contact a qualified attorney. Emergency preamble. Whereas, acts

More information

OH&S Management Systems Audit Checklist (NAT, E3)

OH&S Management Systems Audit Checklist (NAT, E3) 3.1.2 3.1.1 Introduction OH&S Management Systems Audit Checklist (NAT, E3) This audit checklist is based on Element 3 (Implementation) of the National Self-Insurers OHS Audit Tool. For a full copy of the

More information

Contractor Training Courses & Pre-requisites. January 2016

Contractor Training Courses & Pre-requisites. January 2016 Contractor Training Courses & Pre-requisites January 2016 Available courses and pre-requisites It is very important that all participants have completed the course pre-requisites before attending our training.

More information

Ausgrid s Policy on Public Lighting - Contestable Projects. AUSPL CONPOL01 September 2012

Ausgrid s Policy on Public Lighting - Contestable Projects. AUSPL CONPOL01 September 2012 Ausgrid s Policy on Public Lighting - Contestable Projects AUSPL CONPOL01 September 2012 Ausgrid s Policy on Public Lighting - Contestable Projects September 2012 Contents 1 OBJECTIVE... 3 2 SCOPE AND

More information

West Dunbartonshire Council. Follow-up data protection audit report

West Dunbartonshire Council. Follow-up data protection audit report West Dunbartonshire Council Follow-up data protection audit report Auditors: Lee Taylor (Audit Team Manager) Jonathan Kay (Engagement Lead Auditor) Data controller contacts: Michael Butler (Data Protection/Information

More information

CUSTOMER CONNECTION GUIDE

CUSTOMER CONNECTION GUIDE CUSTOMER CONNECTION GUIDE A GUIDE TO CONNECTING ELECTRICITY SUPPLY TO YOUR PROPERTY IN UNITED ENERGY S AREA Document No: UE4309 Issue: 4 Issue Date: 1 April, 2014 1 CUSTOMER CONNECTION GUIDE A GUIDE TO

More information

Information Governance Strategy :

Information Governance Strategy : Item 11 Strategy Strategy : Date Issued: Date To Be Reviewed: VOY xx Annually 1 Policy Title: Strategy Supersedes: All previous Strategies 18/12/13: Initial draft Description of Amendments 19/12/13: Update

More information

INFORMATION TECHNOLOGY SECURITY STANDARDS

INFORMATION TECHNOLOGY SECURITY STANDARDS INFORMATION TECHNOLOGY SECURITY STANDARDS Version 2.0 December 2013 Table of Contents 1 OVERVIEW 3 2 SCOPE 4 3 STRUCTURE 5 4 ASSET MANAGEMENT 6 5 HUMAN RESOURCES SECURITY 7 6 PHYSICAL AND ENVIRONMENTAL

More information

Technical Trial of Broadband IP/Internet over ESB Power Networks. Engineers Ireland. October 2006

Technical Trial of Broadband IP/Internet over ESB Power Networks. Engineers Ireland. October 2006 Technical Trial of Broadband IP/Internet over ESB Power Networks Engineers Ireland October 2006 Outline of Presentation 1. Introduction to Broadband Power Line Carrier 2. Trial start up 1. Objectives 2.

More information

DRAFT SERVICE LEVEL AGREEMENT FOR THE PROVISION OF TEMPORARY AGENCY WORKERS

DRAFT SERVICE LEVEL AGREEMENT FOR THE PROVISION OF TEMPORARY AGENCY WORKERS DRAFT SERVICE LEVEL AGREEMENT FOR THE PROVISION OF TEMPORARY AGENCY WORKERS VERSION 1 21 MAY 2008 PREPARED BY CHARMIAN HICKMAN CONTENTS 1. INTRODUCTION... 3 1.1. SERVICES TO BE PROVIDED by the Agency 4

More information

Information Governance Strategy & Policy

Information Governance Strategy & Policy Information Governance Strategy & Policy March 2014 CONTENT Page 1 Introduction 1 2 Strategic Aims 1 3 Policy 2 4 Responsibilities 3 5 Information Governance Reporting Structure 4 6 Managing Information

More information

Business Continuity Management Policy and Framework

Business Continuity Management Policy and Framework Management Policy and Framework Version: Produced by: Date Produced: Approved by: Updated: 7 University Manager with the assistance of the Operational Group 11 th March 2010 Steering Group (14 December

More information

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13

Interfacing electrification and system reliability. Earthing of AC and DC railways 4,10,13 Interfacing electrification and system reliability Roger White Professional Head of Electrification and Plant Rail Abstract Integration is the term given to ensuring that the different elements of an electrified

More information

Lifecycle Strategy DISPOSAL AND DIVESTMENT

Lifecycle Strategy DISPOSAL AND DIVESTMENT Lifecycle Strategy DISPOSAL AND DIVESTMENT Document 07/10/2013 Page 1 of 19 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D This document

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

Overhead Power Line Safety for Contractors

Overhead Power Line Safety for Contractors Overhead Power Line Safety for Contractors By following simple procedures, you can save lives and prevent accidents. Working Safely As a contractor, before you can even break ground on a construction project,

More information

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to

More information

ESB Networks Perspective on Microgeneration

ESB Networks Perspective on Microgeneration ESB Networks Perspective on Microgeneration Presentation to DIT Seminar 13 th November 2009 Tony Hearne Manager, Generation Planning ESB networks Brendan O Connor Commercial Policy ESB networks Micro-generation

More information

Electrical Safety Policy

Electrical Safety Policy Electrical Safety Policy Version Number: V2 Name of originator/author: Director of Estates and Facilities Name of responsible committee: Estates and Facilities Committee Name of executive lead: Chief Operating

More information

Contract Relationship Management DRAFT

Contract Relationship Management DRAFT Contract Relationship Management Index Introduction 3 Who is a principal? Who is a contractor? 3 For gain or reward 3 What is the duty? 3 Contractor or Employee? 4 Indications of being an employee 4 Indications

More information

Member Development Strategy 2012-2014. Draft: March 2012

Member Development Strategy 2012-2014. Draft: March 2012 Member Development Strategy 2012-2014 Draft: March 2012 Member Development Strategy 2012-2014 Appendix 1 to Item 3 Contents 1. Introduction 2. Aims of the Strategy 3. Key Objectives 3.1 Members Personal

More information

JOB TITLE: Data Quality/IT Manager

JOB TITLE: Data Quality/IT Manager JOB DESCRIPTION JOB TITLE: Data Quality/IT Manager RESPONSIBLE TO: PRACTICE MANAGER PARTNERS SALARY: Starting From 25000 HOURS: 35 Hours The post-holder will need to become familiar with all functions

More information

Electrical and Communications Industry comment on proposed Work Health and Safety regulations and codes

Electrical and Communications Industry comment on proposed Work Health and Safety regulations and codes Electrical and Communications Industry comment on proposed Work Health and Safety regulations and codes BACKGROUND The National Electrical and Communications Association WA (NECA WA) support the business

More information

Guideline for preparing an Environmental and Social Management Plan

Guideline for preparing an Environmental and Social Management Plan Guideline for preparing an Environmental and Social Management Plan NZ Transport Agency www.nzta.govt.nz Version 1: April 2014 ISBN 978-0-478-41934-4 (online) Copyright information This publication is

More information

Health and Safety Policy

Health and Safety Policy Health and Safety Policy October 2014 1 October 2014 Contents: Introduction 1. STATEMENT OF INTENT AND POLICY OBJECTIVES 2. RESPONSIBILITIES AND ACCOUNTABILITIES FOR HEALTH AND SAFETY 2.1 The Director

More information

Mapping Document. BSBOHS201A Participate in OHS Processes. Version: 1.0 Issue Date: 1/02/2010. Updated to Version: 3.0 Issue Date: 28/07/2013

Mapping Document. BSBOHS201A Participate in OHS Processes. Version: 1.0 Issue Date: 1/02/2010. Updated to Version: 3.0 Issue Date: 28/07/2013 Mapping Document Version: 1.0 Issue Date: 1/02/2010 Updated to Version: 3.0 Issue Date: 28/07/2013 Copyright Peter Alderson 2013 Mapping Document Unit Descriptor This unit describes the performance outcomes,

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS

11. Assessment of service 12. S-phase supply 13. Water heaters NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS NORTHERN TERRITORY OF AUSTRALIA ELECTRICITY BY-LAWS T ABLE OF PROVISIONS By-law PART I - PRELIMINARY 1. Citation 2. Repeal 3. Interpretation 4. Qualifications of inspector PART II - INSPECTORS PART III

More information

Accident/Incident Investigation & Reporting Procedure

Accident/Incident Investigation & Reporting Procedure Accident/Incident Investigation & 1. Overview The recognises its obligation to ensure that all accidents and incidents are reported, recorded and investigated. We are committed to identifying corrective

More information

iso20000templates.com

iso20000templates.com iso20000templates.com Public IT Limited 2011 IT Service Policy Document Ref. ITSM01001 Version: 1.0 Draft 1 Document Author: Document Owner: V 1.0 Draft 1 Page 1 of 11 Revision History Version Date RFC

More information

Procedure: OHS CONTRACTOR MANAGEMENT

Procedure: OHS CONTRACTOR MANAGEMENT Procedure: OHS CONTRACTOR MANAGEMENT. Purpose This procedure outlines the occupational health and safety (OHS) requirements for the management of contractors engaged to perform tasks or services for Greater

More information

SALISBURY NHS FOUNDATIONTRUST

SALISBURY NHS FOUNDATIONTRUST SALISBURY NHS FOUNDATIONTRUST PAPER SHC 1738 TITLE Information Governance Policy PURPOSE OF PAPER The Information Governance Policy was first approved in April 2005. It is currently due for review to ensure

More information

SICKNESS ABSENCE REPORT

SICKNESS ABSENCE REPORT AGENDA ITEM No. 12 MEETING : TRUST BOARD DATE : 28 APRIL 2010 REPORT OF : WORKFORCE & OD DIRECTORATE Contact : Jo Davies, Director of HR & Development Officer Tel: 01792 562940 Email: jo.davies@ambulance.wales.nhs.uk

More information

La Trobe University is committed to maintaining a comprehensive and effective Compliance Framework.

La Trobe University is committed to maintaining a comprehensive and effective Compliance Framework. La Trobe University Compliance Framework Introduction The Compliance Framework documents the system and Compliance Process through which La Trobe University can monitor, review and comply with its legislative

More information

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers Appendix 1 RISK MANAGEMENT POLICY AND STRATEGY Document Status: Draft Originator: A Struthers Updated: A Struthers Owner: Executive Director Corporate Services Version: 01.01.03 Date: 30/3/14 Approved

More information

OHS Training Guidelines

OHS Training Guidelines 1. Introduction... 2 2. Legislative Requirements... 2 3. Definitions... 2 4. Responsibilities... 2 4.1. Senior Executive, Deans and Directors... 2 4.2. Management of Academic/Administrative Units... 3

More information

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network A GUIDE TO Connecting Renewable and CHP Electricity Generators to the Electricity Network A Guide to Connecting Renewable and CHP Electricity Generators to the Electricity Network October 2008 Guide prepared

More information

HISTORIC SCOTLAND BOARD MEETING 25-27 JUNE: ORKNEY HSB 10/06 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006

HISTORIC SCOTLAND BOARD MEETING 25-27 JUNE: ORKNEY HSB 10/06 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006 1 INTRODUCTION 1.1 Managing corporate risks is a key issue for all organisations. One key risk is the health and safety of our staff and others such as visitors

More information

Position Description

Position Description Position Description Title Contracts Administration Officer Directorate Corporate Services Department Commercial and Property Services Location Camberwell Classification Band 5 Position code CRPRPPXXCAO

More information

Approved Meter Sockets and Cabinets

Approved Meter Sockets and Cabinets Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4

More information