Modeling Quality Assurance Project Plans (QAPPs) Sandra Arismendez TCEQ Laboratory and Quality Assurance Section July 8, 2015
|
|
- Betty Carson
- 8 years ago
- Views:
Transcription
1 Modeling Quality Assurance Project Plans (QAPPs) Sandra Arismendez TCEQ Laboratory and Quality Assurance Section July 8, 2015
2 QAPPs: Why Write Them? Because they are required EPA Order CIO (formerly A2) sets forth requirement for all organizations conducting environmental data operations on EPA s behalf State agencies (including TCEQ and TSSWCB) and TCEQ contractors follow suit So that projects can be planned and implemented effectively
3 Importance of Modeling QAPPs Helps ensure that the model(s) (and underlying data) are sufficient for achieving project objectives Provides documentation of specifications and activities
4 QAPP Requirements Graded Approach Level of detail commensurate with nature of the work and intended use of data
5 Tools for QAPP Development EPA Requirements for Quality Assurance Project Plans (EPA QA/R-5) is governing requirement ( EPA Guidance for Modeling QAPPs (EPA QA/G-5M) ( QAPP Program Shells Other QAPPs
6 QAPP Content Section A Project Management Section B Measurement and Data Acquisition Section C Assessment and Oversight Section D Data Validation and Usability
7 Section A Project Management A1, A2, A3 Title Page, Signature Page, TOC, Distribution List A4 Project/Task Organization A5 Problem Definition/Background A6 Project/Task Description and Schedule A7 Quality Objectives and Criteria A8 Special Training/Certification A9 Documents and Records
8 A5 Problem Definition/Background Define problem, place modeling activities into overall context with the project, and explain why modeling is being conducted Provide justification for model(s) to be used Summarize what questions will be answered and/or what decisions will be made
9 A6 Project/Task Description and Schedule Summarize work to be done Detail project tasks, schedule, and milestones Development, verification, and validation of code or software is a task (if applicable) Provide enough detail so it is clear as to what versions and implementations of packaged models will be used If multiple models are being used, any linkages should be discussed (preferably diagrammed)
10 A7 Quality Objectives and Criteria for Model Inputs/Outputs Inputs: Quantity, quality, and data type are relevant Quantity and quality: Precision, Bias, Accuracy, Sensitivity, Representativeness, Comparability, Completeness Type: data collection technique Outputs: Qualitative and quantitative criteria and measures Quantitative: Goodness of fit, error and other forms of uncertainty, sensitivity, graphical analysis Qualitative: Reasonableness (what is reasonable should be defined)
11 Sensitivity and Uncertainty Analyses Sensitivity analysis evaluates the effect of changes in input values or assumptions on a model s results Uncertainty analysis investigates the effects of a lack of knowledge or other potential sources of error in the model When used in combination, sensitivity and uncertainty analysis allow model users to be more informed about the confidence that can be placed in model results * Text above copied directly from Guidance on the Development, Evaluation, and Application of Environmental Models, Council for Regulatory Environmental Modeling (EPA/100/K-09), USEPA, 2009.
12 A9 Documents and Records Specify records, their contents, storage location, retention period, formats, and backup protocols Examples: QAPPs, User s Manual(s), various reports, raw files, code, calibration records, verification/validation records
13 Section B Measurement and Data B7 Calibration Acquisition B9 Non-direct Measurements (Data Acquisition Requirements) B10 Data Management and Hardware/Software Configuration
14 B7 Calibration Identify calibration parameters (including literature values) If calibration process is iterative and/or stepwise, spell out calibration steps Specify criteria/guidelines used to determine whether calibration is successful Also, state what will be done if minimum requirements are not met (e.g., recalibration with additional data, consideration of different modeling approach, etc.)
15 Section B9 Non-Direct Measurements (Secondary Data) This section is critical as primary data collection is rarely described in modeling QAPPs Tables can be extremely helpful Don t forget the graded approach! If some data will be acquired that are not yet known, this may be built into the QAPP In this case, it is especially important to specify criteria for acceptance and use of those data
16
17 B10 Data Management Details about data storage, production, management, storage, and archival should be provided If SOPs already exist, these may be referenced instead If data coding or software development is taking place, some reference to these procedures should be provided Hardware and software requirements/specifications should be included Flow diagrams can be very instructive
18 Section C Assessment and Oversight C1 Assessments and Response Actions C2 Reports to Management
19 C1 Assessments and Response Actions Describe surveillance activities, audits, and the process for identifying, documenting, and correcting problems Also, describe assessments of the model performance, and the schedule for these activities
20 Section D Data Validation and Usability D1 Departures from Validation Criteria D2 Validation Methods D3 Reconciliation with User Requirements
21 Section D D1: Describe how results are evaluated and departures from procedures presented D2: Describe steps in the validation process Performance criteria from A7 should be referenced D3: Describe uses of data and how limitations will be reported
22 Questions?
Elements A7 Project Plan - Modeling Needs and Requirements
United States Office of Environmental EPA/240/R-02/007 Environmental Protection Information Agency Washington, DC 20460 Guidance for Quality Assurance Project Plans for Modeling EPA QA/G-5M Quality Quality
More informationCOPY. Revision History
Revision History COPY The top row of this table shows the most recent changes to this controlled document. For previous revision history information, archived versions of this document are maintained by
More information4 PROJECT PLAN DOCUMENTS
1 4 PROJECT PLAN DOCUMENTS 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 4.1 Introduction The project plan documents are a blueprint for how a particular project
More informationGreat Lakes National Program Office and Office of Water Quality Management Training Modules
GLOSSARY Assessment - the evaluation process used to measure the performance or effectiveness of a system and its elements. As used here, assessment is an all-inclusive term used to denote any of the following:
More informationEPA GUIDANCE FOR QUALITY ASSURANCE PROJECT PLANS EPA QA/G-5
United States Office of Research and EPA/600/R-98/018 Environmental Protection Development February 1998 Agency Washington, D.C. 20460 EPA GUIDANCE FOR QUALITY ASSURANCE PROJECT PLANS FOREWORD The U.S.
More informationGuidance for Geospatial Data Quality Assurance Project Plans
United States Environmental Protection Agency Guidance for Geospatial Data Quality Assurance Project Plans EPA QA/G-5G Office of Environmental Information Washington, DC 20460 EPA/240/R-03/003 Quality
More informationOverview of EPA Quality System Requirements
Overview of EPA Quality System Requirements Course Goals At the completion of this course, you will: Understand EPA's quality system requirements Understand the roles and responsibilities in implementing
More informationUS EPA REGION III QUALITY MANAGEMENT PLAN REVIEW CHECKLIST
US EPA REGION III Organization: EPA Organization: EPA Program: Contact: EPA Contact: EPA Contract/Grant/IAG Number: Phone Number: Phone Number: Reviewer: Date Reviewed: Reviewer Organization: Check New
More informationDeveloping Quality Assurance Project Plans using Data Quality Objectives and other planning tools. Developing QAPPs 5/10/2012 1
Developing Quality Assurance Project Plans using Data Quality Objectives and other planning tools 1 Introductions 2 Agenda I. Developing a QAPP II. Systematic Planning using Data Quality Objectives III.
More informationHelp Desk Review of Quality Assurance Project Plans
Help Desk Review of Quality ssurance Project Plans May 2, 2011 pproved by Beverly H. van Buuren, Surface Water mbient Monitoring Program Quality ssurance Officer, on May 2, 2011 1. Purpose This document
More information3.3 Data Collection Systems Design... 22 3.4 Planning Documents... 23 3.4.1 Work Plan... 23 3.4.2 Field Sampling Plan (FSP)... 24 3.4.
TABLE OF CONTENTS 1 INTRODUCTION... 1 1.1 Commitment to Quality... 1 1.2 QA Program Principles... 1 1.2.1 Client Satisfaction... 1 1.2.2 Employee Participation... 2 1.2.3 Problem Prevention... 2 1.2.4
More informationAPPENDIX E THE ASSESSMENT PHASE OF THE DATA LIFE CYCLE
APPENDIX E THE ASSESSMENT PHASE OF THE DATA LIFE CYCLE The assessment phase of the Data Life Cycle includes verification and validation of the survey data and assessment of quality of the data. Data verification
More informationAPPENDIX N. Data Validation Using Data Descriptors
APPENDIX N Data Validation Using Data Descriptors Data validation is often defined by six data descriptors: 1) reports to decision maker 2) documentation 3) data sources 4) analytical method and detection
More informationHaulsey Engineering, Inc. Quality Management System (QMS) Table of Contents
Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents 1.0 Introduction 1.1 Quality Management Policy and Practices 2.0 Quality System Components 2.1 Quality Management Plans 2.2 Quality
More informationData Quality. Tips for getting it, keeping it, proving it! Central Coast Ambient Monitoring Program
Data Quality Tips for getting it, keeping it, proving it! Central Coast Ambient Monitoring Program Why do we care? Program goals are key what do you want to do with the data? Data utility increases directly
More informationAPPENDIX 7-B SUGGESTED OUTLINE OF A QUALITY ASSURANCE PROJECT PLAN
APPENDIX 7-B SUGGESTED OUTLINE OF A QUALITY ASSURANCE PROJECT PLAN This outline is recommended for use by UST consultants/contractors in preparing a generic Quality Assurance Project Plan (QAPP) for use
More informationEcology Quality Assurance Glossary
Ecology Quality Assurance Glossary Edited by William Kammin, Ecology Quality Assurance Officer Accreditation - A certification process for laboratories, designed to evaluate and document a lab s ability
More informationSoftware Project Management Plan (SPMP)
Software Project Management Plan (SPMP) The basic template to be used is derived from IEEE Std 1058-1998, IEEE Standard for Software Project Management Plans. The following is a template for the SPMP.
More informationBuilding Credibility: Quality Assurance & Quality Control for Volunteer Monitoring Programs
Building Credibility: Quality Assurance & Quality Control for Volunteer Monitoring Programs Elizabeth Herron URI Watershed Watch/ National Facilitation of CSREES Volunteer Monitoring Ingrid Harrald Cook
More informationDAIDS Appendix 2 No.: DWD-POL-DM-01.00A2. Data Management Requirements for Central Data Management Facilities
DAIDS Appendix 2 No.: DWD-POL-DM-01.00A2 Data Management Requirements for Central Data Management Facilities The following clinical trial data management requirements must be met in order to ensure the
More informationTASK 2: QUALITY ASSURANCE
TASK 2: QUALITY ASSURANCE Contents Introduction 2-3 Contract Provisions 2-3 Approval to Conduct Work 2-4 QAPP Extensions 2-4 Quality Assurance Project Plans 2-4 Biennial Submittal of Basin-Wide QAPPs 2-4
More informationMinnesota Pollution Control Agency. Quality Assurance Project Plan Guidance
www.pca.state.mn.us Minnesota Pollution Control Agency Quality Assurance Project Plan Guidance Overview The following guidance is for use in building Quality Assurance Project Plans (QAPPs) for the Minnesota
More informationQUALITY ASSURANCE PROJECT PLAN FOR BROWNFIELDS/VOLUNTARY CLEANUP PROGRAM SITES
QUALITY ASSURANCE PROJECT PLAN FOR BROWNFIELDS/VOLUNTARY CLEANUP PROGRAM SITES Prepared by the Missouri Department of Natural Resources Division of Environmental Quality Hazardous Waste Program Brownfields/Voluntary
More informationMontana Ambient Air Monitoring Program Quality Management Plan
Montana Ambient Air Monitoring Program Quality Management Plan September 15, 2015 State of Montana Ambient Air Monitoring Program Montana Department of Environmental Quality Air Quality Bureau 1520 E.
More informationOPERATIONAL STANDARD
1 of 11 1. Introduction The International Safe Transit Association (ISTA), a non-profit association whose objective is to prevent product damage and excess packaging usage within the distribution environment.
More informationunless the manufacturer upgrades the firmware, whereas the effort is repeated.
Software Validation in Accredited Laboratories A Practical Guide Gregory D. Gogates Fasor Inc., 3101 Skippack Pike, Lansdale, Pennsylvania 19446-5864 USA g.gogates@ieee.org www.fasor.com Abstract Software
More informationR9QA/03.2. U.S. Environmental Protection Agency Region 9 Quality Assurance Office 75 Hawthorne Street San Francisco, CA 94105.
1 EPA REGION 9 GUIDANCE FOR QUALITY ASSURANCE PROGRAM PLANS R9QA/03.2 U.S. Environmental Protection Agency Region 9 Quality Assurance Office 75 Hawthorne Street San Francisco, CA 94105 March 2012 FOREWORD
More informationInformation Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
More informationData Management Implementation Plan
Appendix 8.H Data Management Implementation Plan Prepared by Vikram Vyas CRESP-Amchitka Data Management Component 1. INTRODUCTION... 2 1.1. OBJECTIVES AND SCOPE... 2 2. DATA REPORTING CONVENTIONS... 2
More informationQuality Assurance For Environmental Laboratories
Quality Assurance for Environmental Laboratories Gary L. Johnson - U.S. EPA Raymond G. Merrill, Jr. ERG September 15, 2008 1 Session Objectives This Session will discuss: Concept of Quality for Environmental
More informationA. PROJECT MANAGEMENT
Quality Assurance Project Plan (QAPP) for Analysis of Data Received from Nine Hydraulic Fracturing (HF) Service Companies A. PROJECT MANAGEMENT This section addresses project management, including project
More information4 QUALITY ASSURANCE 4.1 INTRODUCTION
4 QUALITY ASSURANCE 4.1 INTRODUCTION BNL has an established Quality Assurance/Quality Control (QA/QC) Program to ensure that the accuracy, precision, and reliability of environmental monitoring data are
More informationDRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I 050 07010 002
DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN April 2009 SLAC I 050 07010 002 Risk Management Plan Contents 1.0 INTRODUCTION... 1 1.1 Scope... 1 2.0 MANAGEMENT
More informationQUALITY MANAGEMENT PLAN
QUALITY MANAGEMENT PLAN August 2010 EQR 10-04 Revised 11-2014 ARIZONA DEPARTMENT OF ENVIRONMENTAL QUALITY QUALITY MANAGEMENT PLAN Approval and Concurrences 2 ARIZONA DEPARTMENT OF ENVIRONMENTAL QUALITY
More informationDRY CLEANING PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN
DIVISION OF ENVIRONMENT QUALITY MANAGEMENT PLAN PART III: DRY CLEANING PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN Revision 3 January 8, 2013 Kansas Department of Health and Environment Division of Environment
More informationGuidance for Industry: Quality Risk Management
Guidance for Industry: Quality Risk Management Version 1.0 Drug Office Department of Health Contents 1. Introduction... 3 2. Purpose of this document... 3 3. Scope... 3 4. What is risk?... 4 5. Integrating
More informationTEMPLATE DATA MANAGEMENT PLAN
TEMPLATE DATA MANAGEMENT PLAN ICRIN (QM sub group) Version: XX Date: XXXXXXX Page 1 of 6 1.0 Document Ownership The Data Management Plan (DMP) will be initiated and subsequently owned by the Data Manager
More informationTesting Automated Manufacturing Processes
Testing Automated Manufacturing Processes (PLC based architecture) 1 ❶ Introduction. ❷ Regulations. ❸ CSV Automated Manufacturing Systems. ❹ PLCs Validation Methodology / Approach. ❺ Testing. ❻ Controls
More informationDIVISION OF ENVIRONMENT QUALITY MANAGEMENT PLAN VOLUNTARY CLEANUP AND PROPERTY REDEVELOPMENT PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN
DIVISION OF ENVIRONMENT QUALITY MANAGEMENT PLAN PART III: VOLUNTARY CLEANUP AND PROPERTY REDEVELOPMENT PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN January 29, 2015 Kansas Department of Health and Environment
More informationWhat methods are used to conduct testing?
What is testing? Testing is the practice of making objective judgments regarding the extent to which the system (device) meets, exceeds or fails to meet stated objectives What the purpose of testing? There
More informationDIVISION OF ENVIRONMENT QUALITY MANAGEMENT PLAN PART III: SUPERFUND (MACA) PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN
DIVISION OF ENVIRONMENT QUALITY MANAGEMENT PLAN PART III: SUPERFUND (MACA) PROGRAM QUALITY ASSURANCE MANAGEMENT PLAN Revision 3 February 21, 2012 Kansas Department of Health and Environment Division of
More informationPOLICY AND PROGRAM REQUIREMENTS FOR THE MANDATORY AGENCY-WIDE QUALITY SYSTEM
Classification No.: CIO 2105.0 (formerly ) Approval Date: May 5, 2000 POLICY AND PROGRAM REQUIREMENTS FOR THE MANDATORY AGENCY-WIDE QUALITY SYSTEM 1. PURPOSE. This Order re-affirms the policy defined by
More informationCHAPTER ONE TABLE OF CONTENTS 1.0 INTRODUCTION... 1
CHAPTER ONE TABLE OF CONTENTS Section Page 1.0 INTRODUCTION... 1 2.0 QA PROJECT PLAN... 1 2.1 DATA QUALITY OBJECTIVES... 2 2.2 PROJECT OBJECTIVES... 2 2.3 SAMPLE COLLECTION... 3 2.4 ANALYSIS AND TESTING...
More informationINTRODUCTION. This book offers a systematic, ten-step approach, from the decision to validate to
INTRODUCTION This book offers a systematic, ten-step approach, from the decision to validate to the assessment of the validation outcome, for validating configurable off-the-shelf (COTS) computer software
More informationFinal Plan. Revision No. 1.0 Effective September 5, 2014
UTAH DIVISION OF WATER QUALITY QUALITY ASSURANCE PROGRAM PLAN FOR ENVIRONMENTAL DATA OPERATIONS Final Plan Revision No. 1.0 Effective September 5, 2014 Utah Division of Water Quality Utah Department of
More informationEUROPEAN COMMISSION HEALTH AND CONSUMERS DIRECTORATE-GENERAL. EudraLex The Rules Governing Medicinal Products in the European Union
EUROPEAN COMMISSION HEALTH AND CONSUMERS DIRECTORATE-GENERAL Public Health and Risk Assessment Pharmaceuticals Brussels, SANCO/C8/AM/sl/ares(2010)1064587 EudraLex The Rules Governing Medicinal Products
More informationTEST PLAN APPLICATION TEMPLATE for Field Verification of Advanced Onsite Pretreatment Units for Nitrogen Reduction Chesapeake Bay Watershed States
TEST PLAN APPLICATION TEMPLATE for Field Verification of Advanced Onsite Pretreatment Units for Nitrogen Reduction Chesapeake Bay Watershed States This document is a template to be used by applicants seeking
More information6.b Quality Management Plan
6.b Quality Management Plan 6.b.1. Summary: The researchers participating in this Center are strongly committed to good science and aggressive quality management (QM) practices. Our commitment is documented
More informationPROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
More informationSUPPLIER QUALITY PROGRAM, V (U)
FEDERAL MANUFACTURING & TECHNOLOGIES PQR 1060 PAGE 1 OF 17 SUPPLIER QUALITY PROGRAM, V (U) CHANGE HISTORY ISSUE DESCRIPTION OF CHANGE AUTHOR DATE E CORRECTED CHANGE HISTORY S. L. HALTER 10/18/2000 F UPDATED
More informationPHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
More informationOECD DRAFT ADVISORY DOCUMENT 16 1 THE APPLICATION OF GLP PRINCIPLES TO COMPUTERISED SYSTEMS FOREWARD
OECD DRAFT ADVISORY DOCUMENT 16 1 THE APPLICATION OF GLP PRINCIPLES TO COMPUTERISED SYSTEMS FOREWARD 1. The following draft Advisory Document will replace the 1995 OECD GLP Consensus Document number 10
More informationQuality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
More informationCONTENTS. List of Tables List of Figures
Prelims 13/3/06 9:11 pm Page iii CONTENTS List of Tables List of Figures ix xi 1 Introduction 1 1.1 The Need for Guidance on ERP System Validation 1 1.2 The Need to Validate ERP Systems 3 1.3 The ERP Implementation
More informationINSERT COMPANY LOGO/HEADER
LICENCE REFERENCE No. Insert licence reference number RISK ASSESSMENT METHODOLOGY STAGE & STEP Insert methodology stage and step, e.g. Stage 3 Step 1 REPORT VERSION Insert report version no., e.g. Draft,
More informationSoftware Test Plan (STP) Template
(STP) Template Items that are intended to stay in as part of your document are in bold; explanatory comments are in italic text. Plain text is used where you might insert wording about your project. This
More information9. Quality Assurance 9.1 INTRODUCTION 9.2 FIELD SAMPLING QUALITY ASSURANCE 9.3 ANALYTICAL QUALITY ASSURANCE. 9.3.1 Internal Quality Control
9. Quality Assurance Setting The overall goal of a well-designed and well-implemented sampling and analysis program is to measure accurately what is really there. Environmental decisions are made on the
More informationTABLE OF CONTENTS. NJDEP and EPA Approvals...i. NJDEP Organizational Structure Flow Chart (Figure1)...3
TABLE OF CONTENTS NJDEP and EPA Approvals......i NJDEP Senior Staff Approvals......iii I. Introduction and Purpose...1 II. NJDEP Organizational Structure...2 III. Quality System Organizational Structure...2
More informationU. S. Department of Energy Consolidated Audit Program Checklist 5 Laboratory Information Management Systems Electronic Data Management
U. S. Department of Energy Consolidated Audit Program Checklist 5 Laboratory Information Management Systems Electronic Data Management Revision 4.0 February 2014 Use of this DOECAP checklist is authorized
More informationQuality Management Plan
Quality Management Plan 6666 West Quincy Avenue Denver, Colorado 80235-3098 Telephone (303) 347-6100 September 1, 2011 CONTENTS Page APPROVALS ACRONYMS AND ABBREVIATIONS ii vi 1 INTRODUCTION 1 2 FOUNDATION
More informationOverview of the Remedial Action Cost Engineering Requirements (RACER ) Software
Overview of the Remedial Action Cost Engineering Requirements (RACER ) Software For More Information, Please Contact: Andrew Schleppi RACER Product Line Manager 717 17th Street, Suite 2600 Denver, CO 80202
More informationQuality Assurance Program Plan. July 2006. U.S. Department of Energy Office of Legacy Management
U. S. Department of Energy Office of Legacy Management July 2006 July 2006 Page i DOE-LM Policy Statement The U.S. Department of Energy (DOE) Office of Legacy Management (LM) performs long-term surveillance
More informationPERFORMANCE-BASED EVALUATION OF LABORATORY QUALITY SYSTEMS An Objective Tool to Identify QA Program Elements that Actually Impact Data Quality
PERFORMANCE-BASED EVALUATION OF LABORATORY QUALITY SYSTEMS An Objective Tool to Identify QA Program Elements that Actually Impact Data Quality ABSTRACT Sevdâ K Aleckson, Western Region Quality Assurance
More informationData Validation for Smart Grid Analytics
Key Concepts This white paper presents several key concepts behind quality and validation as implemented in the industry. Typical validation mechanisms and workflow targeting automatically and manually
More informationHow To Write A Contract For Software Quality Assurance
U.S. Department of Energy Washington, D.C. NOTICE DOE N 203.1 Approved: Expires: 06-02-01 SUBJECT: SOFTWARE QUALITY ASSURANCE 1. OBJECTIVES. To define requirements and responsibilities for software quality
More informationElectronic Raw Data and the Use of Electronic Laboratory Notebooks
7th WRIB- M-2 Workshop Electronic Raw Data and the Use of Electronic Laboratory Notebooks Ron Shoup Outline for Today Raw Data- defining it, creating it, and keeping it for posterity Hybrid Data- paper,
More informationGood Research Practice
Page 1 of 8 The Royal Veterinary College Introduction Preface Good Research Practice Funding bodies need to be assured of the quality and validity of research they fund and ensure their contractors are
More informationPERFORMANCE EVALUATION AUDIT CHECKLIST EXAMPLE. EIIP Volume VI
Final 7/96 APPENDIX E - PERFORMANCE EVALUATION AUDIT APPENDIX E PERFORMANCE EVALUATION AUDIT CHECKLIST EXAMPLE APPENDIX E - PERFORMANCE EVALUATION AUDIT Final 7/96 This page is intentionally left blank.
More informationValidating Enterprise Systems: A Practical Guide
Table of Contents Validating Enterprise Systems: A Practical Guide Foreword 1 Introduction The Need for Guidance on Compliant Enterprise Systems What is an Enterprise System The Need to Validate Enterprise
More informationOECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT
GENERAL DISTRIBUTION OCDE/GD(95)115 OECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT THE APPLICATION OF THE PRINCIPLES OF GLP TO COMPUTERISED
More informationTest/QA Plan for Selective Catalytic Reduction Systems at SwRI Version 1.0 November 2006
TEST/QA PLAN FOR THE VERIFICATION TESTING OF SELECTIVE CATALYTIC REDUCTION CONTROL TECHNOLOGIES FOR HIGHWAY, NONROAD, AND STATIONARY USE DIESEL ENGINES EPA Cooperative Agreement No. CR83191101 Southwest
More informationMethods of Data Collection and Field Planning
Quality Assurance and Quality Control Tools for Monitoring Projects Beverly H. van Buuren,, SWAMP QA Officer Amara Vandervort, SWAMP QA Coordinator Megan Kilner, SWAMP QA Specialist The Quality Assurance
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationPHASE 3: PLANNING PHASE
PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning
More informationDraft. Quality Assurance Project Plan. Haul Road Fugitive Dust Study. Red Dog Mine, Alaska. Prepared for. Teck Cominco Alaska Inc.
Draft Quality Assurance Project Plan Haul Road Fugitive Dust Study Red Dog Mine, Alaska Prepared for Teck Cominco Alaska Inc. Anchorage, Alaska Draft Quality Assurance Project Plan Haul Road Fugitive Dust
More information1.0 INTRODUCTION 1.1 Overview
Guidance document for the writing of standard operating procedures (Taken from United States Environmental Protection Agency Guidance for Preparing Standard Operating Procedures (SOPs) EPA QA/G- 6 [EPA/600/B-
More informationIT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
More informationMDEP/RCRA Quality Assurance Plan Revision 6 Date: November 21, 2012 Page 0 of 19
Page 0 of 19 Page 1 of 19 TABLE OF CONTENTS Title Page 1.0 Introduction 3 1.1 Project Description 3 1.2 QAP Implementation 4 2.0 Quality Assurance Statement 4 3.0 MDEP/RCRA Program Organization 5 3.1 Organizational
More informationEagle Machining, Inc. Quality Management System
Eagle Machining, Inc. Quality Management System 1 of 10310 Antoine Drive Bldg D, Houston, Texas 77086 BUSINESS OPERATING MANUAL (QUALITY MANUAL) Revision Date: 08/01/2014 Approved By: Joseph Vu Date: 08/01/2014
More informationMHRA GMP Data Integrity Definitions and Guidance for Industry January 2015
MHRA GMP Data Integrity Definitions and Guidance for Industry Introduction: Data integrity is fundamental in a pharmaceutical quality system which ensures that medicines are of the required quality. This
More informationSoftware Quality Assurance Plan
For Database Applications Document ID: Version: 2.1a Planning Installation & Acceptance Integration & Test Requirements Definition Design Development 1 / 54 Copyright 2000-2006 Digital Publications LLC.
More informationMHRA GMP Data Integrity Definitions and Guidance for Industry March 2015
MHRA GMP Data Integrity Definitions and Guidance for Industry Introduction: Data integrity is fundamental in a pharmaceutical quality system which ensures that medicines are of the required quality. This
More information2.2 INFORMATION SERVICES Documentation of computer services, computer system management, and computer network management.
3 Audit Trail Files Data generated during the creation of a master file or database, used to validate a master file or database during a processing cycle. GS 14020 Retain for 3 backup cycles Computer Run
More informationSoftware Verification and Validation
Software Verification and Validation Georgia L. Harris Carol Hockert NIST Office of Weights and Measures 1 Learning Objectives After this session, using resources and references provided, you will be able
More informationProcedure for Writing Technical Procedures
Procedure for Writing Technical Procedures 1.0 Purpose This procedure specifies when a technical procedure is needed and outlines the required elements for writing the technical procedure. 2.0 Scope This
More informationIMPLEMENTATION FRAMEWORK
IMPLEMENTATION FRAMEWORK Credit unions not members of a federation, trust companies and savings companies wishing to adopt a standardized approach for calculating operational risk capital charges January
More informationUniform Federal Policy for Implementing Environmental Quality Systems
Publication Numbers: EPA: EPA-505-F-03-001 DoD: DTIC ADA 395303 DOE: DOE/EH-0667 Intergovernmental Data Quality Task Force Uniform Federal Policy for Implementing Environmental Quality Systems Evaluating,
More informationNova Southeastern University Standard Operating Procedure for GCP. Title: Electronic Source Documents for Clinical Research Study Version # 1
Nova Southeastern University Standard Operating Procedure for GCP Title: Electronic Source Documents for Clinical Research Study Version # 1 SOP Number: OCR-RDM-006 Effective Date: August 2013 Page 1 of
More informationCalifornia Department of Mental Health Information Technology Attention: MHSA-IT 1600 9 th Street, Room 141 Sacramento, CA 95814
IT Project Status Report For an MHSA-Funded IT Project Please send the Signed Original to the following address: California Department of Mental Health Information Technology Attention: MHSA-IT 1600 9
More informationFAIR Act Inventory Functions and Service Contract Inventory Product Service Codes Crosswalk Attachment I
Product Service Code (PSC) Recommended PSC Definition FAIR Function Codes and Definitions 1 B510 Study/Environmental Assessments - Organized, analytical assessments/evaluations in support of policy development,
More informationNABL NATIONAL ACCREDITATION
NABL 160 NABL NATIONAL ACCREDITATION BOARD FOR TESTING AND CALIBRATION LABORATORIES GUIDE for PREPARING A QUALITY MANUAL ISSUE NO. : 05 AMENDMENT NO : 00 ISSUE DATE: 27.06.2012 AMENDMENT DATE: -- Amendment
More informationKnowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
More informationQuality Assurance Program Quality Assurance Plan Periodic Audits Standard Operating Procedures Preventive Maintenance Outline Quality Assurance Plan (QAP) What is a QAP Why is a QAP required? What does
More informationGAMP 4 to GAMP 5 Summary
GAMP 4 to GAMP 5 Summary Introduction This document provides summary information on the GAMP 5 Guide and provides a mapping to the previous version, GAMP 4. It specifically provides: 1. Summary of Need
More informationOVERVIEW OF STANDARD 7E & STANDARD 20
Standard for Thermal Transport Packaging Used in Parcel Delivery System Shipment 7E 2 010 ISTA 7E Usage Modes VERSION DATE OCTOBER 2010 Initial Release ISTA, Distributing Confidence, Worldwide ISTA 7-Series
More informationRequest for Records Disposition Authority
/......:- NATIONAL ARCHIVES AND RECORDS ADMINISTRATION Records Schedule: DAA-0412-2013-0009 Records Schedule Number Schedule Status DAA~041'2-2013-0009 Approved Agency or Establishment Record Group I Scheduling
More informationQUALITY CONTROL AND QUALITY ASSURANCE IN CLINICAL RESEARCH
QUALITY CONTROL AND QUALITY ASSURANCE IN CLINICAL RESEARCH Martin Valania, Executive Director, Corporate QA and Compliance Introduction Pharmaceutical companies recognize the benefits of carefully managing
More informationBusiness Management System Manual. Context, Scope and Responsibilities
Business Management System BMS Manual Page 1 of 11 Business Management System Manual Context, Scope and Responsibilities ISO 9001:2015 BMS.0100 R1 MAS Solutions LLC 29810 FM 1093 Suite C Fulshear, TX 77441
More informationALACC Frequently Asked Questions (FAQs)
Updated October 17, 2012 ALACC Contents Web Introduction to FAQ... 2 FAQ #6... 3 ALACC Section: How to Meet ISO 17025 Requirements for Method Verification (Page 9)... 3 FAQ #13... 4 ALACC Section ALACC
More informationDecember 21, 2012. The services being procured through the proposed amendment are Hosting Services, and Application Development and Support for CITSS.
Justification for a Contract Amendment to Contract 2012-01: Interim Hosting and Jurisdiction Functionality for the Compliance Instrument Tracking System Service (CITSS) December 21, 2012 Introduction WCI,
More information