Coal Mine Particulate Matter Control Best Practice Management Determination

Size: px
Start display at page:

Download "Coal Mine Particulate Matter Control Best Practice Management Determination"

Transcription

1 Coal Mine Particulate Matter Control Best Practice Management Determination February 2012 Bengalla Mining Company

2 Revision Details Date Amended By A Draft Final 27/01/12 Y. Scorgie B Final 3/02/12 Y. Scorgie C Revision 1 22/02/12 Y.Scorgie Authors : Y. Scorgie Signed : Reviewer : A. Harburg Signed :... Approved by : A. Sutton Signed :... Date : 2 March 2012 Distribution: Please note that when viewed electronically this document may contain pages that have been intentionally left blank. These blank pages may occur because in consideration of the environment and for your convenience, this document has been set up so that it can be printed correctly in double-sided format

3 Contents Page number Glossary Project overview v vii 1. Introduction Background PRP U2 Coal Particulate Matter Control Best Practice Scope of Assessment Additions and Clarifications for OEH Mining Activity Categories Costing of Control Measures Overview of Operations and Management Overview of Operations Mine Activities with Potential Particulate Matter Emissions Overview of Air Quality Monitoring at Bengalla Current Emissions and Control Measures Limitations of Emission Estimation Process Existing Particulate Matter Emissions and Controls Ranking of Mine Activities Based on Controlled Emissions Top Four Mining Activities Potential Measures to Minimise Emissions Best Management Practice Measures for Top Sources Wheel Generated Dust (Unpaved Roads) Truck Loading and Dumping of Overburden Bulldozing of Overburden Wind Erosion of Overburden Emplacement Areas Potential Additional Controls for Top Four Mine Activities Wheel Generated Dust (Unpaved Roads) Truck Loading and Dumping of Overburden Bulldozing of Overburden Wind Erosion of Overburden Emplacement Areas Emission Reductions Achievable due to Additional Controls Practicability of Additional Measures Evaluation of Practicability Best Practice Measures Selected for Implementation 46 BMC BMP Determination 22 Feb 2012.docx Page i

4 6. Implementation Timeline References 50 BMC BMP Determination 22 Feb 2012.docx Page ii

5 List of tables Page number Table 1.1 Mining activities defined within the OEH Guideline 14 Table 3.1 Current control measures applied at Bengalla 22 Table 3.2 Control efficiencies applied for current controls, where quantifiable 27 Table 3.3 Partially uncontrolled emissions for base case year 2011(a) 28 Table 3.4 Emissions for base case year 2011 with current controls 29 Table 3.5 Ranking of activities based on base case year 2011 annual emissions with current controls in place 30 Table 3.6 Top four mining activities 30 Table 4.1 Control measures for wheel generated dust from material haulage along unpaved surfaces, and associated control efficiencies from the literature 32 Table 4.2 Control measures for truck loading and dumping of overburden, and associated control efficiencies from the literature 35 Table 4.3 Control measures for reducing wind-blown dust from overburden emplacement areas, and associated control efficiencies from the literature 38 Table 4.4 Control measures for truck loading and dumping of overburden, and extent to which such measures are applied at Bengalla 40 Table 4.5 Control measures for bulldozing of overburden, and extent to which such measures are applied at Bengalla 41 Table 4.6 Summary of additional control measures identified, and associated control efficiencies, where quantifiable 43 Table 4.7 Annual emission reduction estimated due to implementation of the additional control measures identified at Bengalla 44 Table 5.1 Summary of additional control measures identified, and associated control efficiencies, where quantifiable 45 Table 6.1 Tasks and implementation timelines for the application of additional control measures at Bengalla 48 List of figures Page number Figure 1.1 Bengalla Locality Map 11 Figure 2.1 Bengalla Mining Method Schematic 17 Figure 2.2 Location of Bengalla s TSP, PM 10 and Meteorological Monitoring Stations 20 BMC BMP Determination 22 Feb 2012.docx Page iii

6 Appendices Appendix A Cost Information for Best Practice Measures Appendix B Emission Estimation Method Appendix C Haul Road Dust Control Efficiency Estimation Appendix D Photographs of Bengalla Operations BMC BMP Determination 22 Feb 2012.docx Page iv

7 Glossary ACARP Australian Coal Association Research Program AEMR Annual Environmental Management Report BAM Beta Attenuation Monitor bcm Bench cubic metres - a measure of volumes mined, equal to the weight of material divided by its specific gravity. BMC Bengalla Mining Company BMP Best Management Practice BoM Australian Bureau of Meteorology CARB California Air Resources Board CHPP Coal Handling and Preparation Plant EPA Environmental Protection Authority EPL Environmental Protection Licence FEL Front end loader HVAS High Volume Air Sampler µm Micrometre or micron (metre x 10-6 ) m² Square metre m 3 Cubic metre Mt Megatonne (million tonne) MOP Mine Operating Plan NPI National Pollutant Inventory NSW EPA New South Wales Environmental Protection Authority OCE Open Cut Examiner OEH Office of Environment and Heritage PM 10 Particulate matter less than 10microns in aerodynamic diameter PM 2.5 Particulate matter less than 2.5microns in aerodynamic diameter PRP Pollution Reduction Program RTCA Rio Tinto Coal Australia RTEMS Bengalla s Real Time Environmental Management System ROM Run of Mine TSP Total Suspended Particulate USEPA United States Environmental Protection Agency BMC BMP Determination 22 Feb 2012.docx Page v

8

9 Executive Summary Bengalla Mining Company (BMC) holds an Environmental Protection Licence (EPL number 6538) under the Protection of the Environment Operations Act This licence is administered by the Office of Environment and Heritage (OEH). On 8 August 2011, BMC was issued with notice amending EPL 6538 to include a Pollution Reduction Program that requires BMC to undertake a Best Management Practice (BMP) Determination comprising the following main components: 1. Estimate baseline emissions and determine the four mining activities that currently generate the most particulate matter; 2. Estimate the reduction in emissions that could be achieved by applying best practice measures; 3. Assess the practicability of each of these measures; and 4. Propose a timetable for the implementation of any practical measures. The BMP Determination has been completed and is documented within this report. Top Four Mining Activities The top four mining activities, contributing the highest emissions of TSP, PM 10 and PM 2.5 during 2011, were identified as: wheel generated dust (unpaved roads); loading/dumping overburden; bulldozing overburden; and wind erosion of overburden emplacement area. When combined, the emissions from the above activities are estimated to contribute approximately 80 percent of the particulate matter emissions from Bengalla s operations. Additional Control Measures Best management practices were reviewed and a gap analysis undertaken considering Bengalla s current control measures, to identify additional control measures which could be applied at the site. Additional control measures identified are as follows: OEH Mining Activity Category Wheel Generated Dust (Unpaved Roads) Additional Control Measures Primary measure: Chemical suppression on unpaved haul roads Supporting measures: Documentation of the haul road management program for consistent implementation Measurement of the control effectiveness through dust monitoring Truck Loading/Dumping of Overburden Bulldozing of Overburden No additional controls identified. No additional controls identified. BMC BMP Determination 22 Feb 2012.docx Page vii

10 OEH Mining Activity Category Wind Erosion of Overburden Additional Control Measures Interim stabilisation through vegetation and/or chemical suppression All practicable measures for reducing dust emissions from bulldozer operations and overburden loading and dumping operations are currently implemented at Bengalla. The importance of continued implementation of current controls was however recognised. Annual emission reductions estimated due to the implementation of the additional control measures were estimated to be in the range of 447 to 865 tonnes per year for TSP, with PM 10 emission reductions in the range 158 to 300 tonnes per year, and PM 2.5 emission reductions of the order of 17 to 32 tonnes per year. All of the additional control measures identified were concluded by Bengalla to be practicable and an implementation timeline is provided in the report for their introduction. BMC BMP Determination 22 Feb 2012.docx Page viii

11 1. Introduction 1.1 Background The Bengalla Mining Company Pty Ltd (BMC) operates the Bengalla Coal Mine (Bengalla) in the Upper Hunter Valley of New South Wales, approximately 4 kilometres west of Muswellbrook (refer to Figure 1.1). Bengalla is generally bound by Wybong Road to the north, Overton Road to the east, the Muswellbrook to Ulan Rail Line and the Hunter River Floodplain to the south and Roxburgh Road to the west. BMC was granted a development consent (Development Application, DA, 211/93) by the then Minister for Urban Affairs and Planning on 7 August 1995 for the construction and operation of a surface coal mine, coal preparation plant, rail loop, loading facilities and associated facilities. Bengalla was originally approved to operate for a 21 year period from 1996 and to produce up to 8.7 Million tonnes per annum (Mtpa) of Run of Mine (ROM) coal. Bengalla commenced operations in October Since approval, the Bengalla development consent has been modified four times providing for an increase in the maximum extraction rate to 10.7 Mtpa of ROM coal; an increase in the maximum height of the overburden dump to RL 270 metres; an extension of the coal extraction footprint by 32 hectares (ha) in the south (Wantana Extention Area), with an approved production rate for mining in this area of 2.5 Mtpa of ROM coal; and implementation of an Overburden Emplacement Area (OEA) Strategy to alleviate the shortage of emplacement capacity. This strategy involves extending the footprint and associated landform of the existing OEA to the south-east, relocation of the already approved temporary OEA to the west of the current operations; and delay in the finalisation and rehabilitation of the existing OEA. BMC holds an Environmental Protection Licence (EPL number 6538) under the Protection of the Environment Operations Act This licence is administered by the Office of Environment and Heritage (OEH). In 2010, the Office of Environment and Heritage commissioned Katestone Environmental Pty Ltd to prepare NSW Coal Mining Benchmarking Study: International Best Practice Measures to Prevent and/or Minimise Emissions of Particulate Matter from Coal Mining (Katestone, June 2011). A conclusion of the study was that substantial reductions in particulate matter emissions from coal mines in NSW could be achieved with the application of best practice measures. A key recommendation of this study is as follows: Require. existing coal mines to conduct site specific BMP determinations to identify the most technically and economically feasible options to reduce emissions.. For existing Premises the BMP determination could be required through a pollution reduction program (PRP) and the outcomes implemented through EPL conditions. On 8 August 2011, BMC was issued with notice amending EPL 6538 to include a Pollution Reduction Program on the licence that requires BMC to follow a four step assessment process: 1. Estimate baseline emissions and determine the four mining activities that currently generate the most particulate matter; BMC BMP Determination 22 Feb 2012.docx Page 9

12 2. Estimate the reduction in emissions that could be achieved by applying best practice measures; 3. Assess the practicability of each of these measures; and 4. Propose a timetable for the implementation of any practical measures. More specific information on the BMP determination required is provided in the subsequent section. This Report documents the outcomes of the particulate matter control best practice assessment undertaken to meet regulatory requirements, including the proposed implementation timeframe for applying additional control measures identified. 1.2 PRP U2 Coal Particulate Matter Control Best Practice The Best Management Practice determination requirements are set out in PRP U2 Coal Mine Particulate Matter Control Best Practice as follows: U2.1 The Licensee must conduct a site specific Best Management Practice (BMP) determination to identify the most practicable means to reduce particle emissions. U2.2 The Licensee must prepare a report which includes, but is not necessarily limited to, the following: - identification, quantification and justification of existing measures that are being used to minimise particle emissions; - identification, quantification and justification of best practice measures that could be used to minimise particle emissions; - evaluation of the practicability of implementing these best practice measures; and - a proposed timeframe for implementing all practicable best practice measures. In preparing the report, the Licensee must utilise the document entitled Coal Mine Particulate Matter Control Best Practice Site Specific Determination Guideline - August U2.3 All cost related information is to be included as Appendix 1 of the Report required by condition U1.2 above. U2.4 The report required by condition U1.2 must be submitted by the Licensee to the Office of Environment and Heritage s Regional Manager Hunter, at PO Box 488G, NEWCASTLE by 6 February 2012 U2.5 The report required by condition U1.2 above, except for cost related information contained in Appendix 1 of the Report, must be made publicly available by the Licensee on the Licensee s website by 13 February PRP U2 makes specific reference to the OEH Coal Mine Particulate Matter Control Best Practice Site Specific Determination Guideline dated August It is however noted that this guideline was revised in November BMC BMP Determination 22 Feb 2012.docx Page 10

13 Figure 1.1 Bengalla Locality Map BMC BMP Determination 22 Feb 2012.docx Page 11

14 1.3 Scope of Assessment The BMP determination followed the process outlined in the OEH Coal Mine Particulate Matter Control Best Practice Site Specific Determination Guideline, November 2011, (hereafter referred to as the OEH Guideline ). This process requires that the following steps be followed, as a minimum: 1. Identify, quantify and justify existing measures that are being used to minimise particle emissions 1.1. Estimate baseline emissions of TSP, PM 10 and PM 2.5 (tonne per year) from each mining activity. This estimate must: - Utilise USEPA AP42 emission estimation techniques (or other method as approved in writing by the EPA) - Calculate uncontrolled emissions (with no particulate matter controls in place); and - Calculate controlled emissions (with current particulate matter controls in place). Note: These particulate matter controls must be clearly identified, quantified and justified with supporting information Using the results of the controlled emissions estimates generated from Step 1.1, rank the mining activities according to the mass of TSP, PM 10, and PM 2.5 emitted by each mining activity per year from highest to lowest Identify the top four mining activities from Step 1.2 that contribute the highest emissions of TSP, PM 10 and PM Identify, quantify and justify the measures that could be used to minimise particle emissions 2.1. For each of the top four activities identified in Step 1.3, identify the measures that could be implemented to reduce emissions taking into consideration: - The findings of Katestone (June 2011). NSW Coal Mining Benchmarking Study International Best Practice Measures to Prevent and/or Minimise Emissions of Particulate Matter from Coal Mining; - Any other relevant published information; and - Any relevant industry experience from either Australia or overseas For each of the top four activities identified in Step 1.3, estimate emissions of TSP, PM 10 and PM 2.5 from each mining activity following the application of the measures identified in Step 2.1. BMC BMP Determination 22 Feb 2012.docx Page 12

15 3. Evaluate the practicability of implementing these best practice measures 3.1. For each of the best practice measures identified in Step 2.1, assess the practicability associated with their implementation, by taking into consideration: - Implementation costs; - Regulatory requirements; - Environmental impacts; - Safety implications; and - Compatibility with current processes and proposed future developments Identify those best practice measures that will be implemented at the premises to reduce particle emissions. 4. Propose a timeframe for implementing all practicable best practice measures 4.1. For each of the best practice measures identified as being practicable in Step 3.2, provide a timeframe for their implementation. In evaluating practicability in Step 3, the following specific information is to be documented: - Estimated capital, labour, materials and other costs for each best practice measure on an annual basis for a ten year period. This information must be set out in the format provided in Appendix A and included as an attachment to the report; - The details of any restrictions on the implementation of each best practice measure due to an existing approval or licence; - Quantification of any new or additional environmental impacts that may arise from the application of a particular best practice measure, such as increased noise or fresh water use; - The details of safety impacts that may result from the application of a particular best practice measure; - The details of any incompatibility with current operational practices on the premises; and - The details of any incompatibility with future development proposals on the premises Additions and Clarifications for OEH Mining Activity Categories Mining activities are defined in the OEH Guideline as including any of the activities listed in Table 1.1. BMC BMP Determination 22 Feb 2012.docx Page 13

16 Table 1.1 Mining activities defined within the OEH Guideline Mining Activities Wheel generated particles on unpaved roads Mining Activities Loading and dumping overburden Blasting Bulldozing coal Trucks unloading overburden Bulldozing overburden Front-end loaders on overburden Wind erosion of exposed areas Wind erosion of coal stockpiles Wind erosion of overburden emplacement areas Unloading from coal stockpiles Dragline Trucks unloading coal Loading coal stockpiles Graders Drilling Coal crushing Material transfer of coal Scrapers on overburden Train loading Screening Material transfer of overburden The mining activities defined within the OEH Guidelines were extended to include trucks loading coal, specifically applicable for excavators/loaders loading coal trucks. Trucks unloading coal was specifically defined for the purpose of this BMP determination as trucks unloading ROM coal to the ROM hopper, with material transfer of coal applied for conveyor transfers. Loading and unloading of coal stockpiles was taken to refer to stacking and reclaiming operations respectively. Loading and dumping overburden was taken to mean the loading of trucks with overburden and trucks dumping overburden respectively. Whereas the handling of overburden by draglines, was accounted for under the dragline activity specified. Given that there are no other transfers of overburden, the material transfer of overburden activity category was omitted. Emission factors applied for crushing operations encompass the entire crushing circuit including screening operations. The coal crushing and screening activity categories were therefore combined for the purpose of this study Costing of Control Measures According to the NSW Environmental Protection Agency (EPA), the cost information referred to in the OEH Guideline is required to verify that a particular best practice measure is not practicable for implementation at a mine site. In subsequent advice provided, the EPA indicated that any licensee may choose not to submit cost information for best practice measures that are either currently being implemented, or that are considered by the licensee to be practicable (personal communication, Mitchell Bennett, Head, Regional Operational Unit Hunter, NSW EPA, 27 January 2012). BMC BMP Determination 22 Feb 2012.docx Page 14

17 2. Overview of Operations and Management This section provides an overview of Bengalla s mining and coal processing operations, and identifies specific mining activities which are associated with particulate matter emissions. A summary of the overall environmental management procedures and systems at Bengalla, pertinent for the control of particulate matter emissions, is also provided. 2.1 Overview of Operations An overview of recent operations at Bengalla is given in this section, referencing the BMC Annual Environmental Management Report Bengalla comprises an open pit mine, using strip mining methods, and a processing plant. Mining advances to the west based on dragline strips approximately 60 metres in width. The multi-seam coal deposit at Bengalla will include 30 strips being mined during the approved mine life. Mining operations are conducted 24 hours a day, 7 days a week. The operation consists of the following facilities and equipment necessary for the extraction, washing and distribution of coal: Infrastructure area, comprising three coal stockpiles, a coal handling and preparation plant (CHPP), workshop and nearby office complex; Rail load out facilities; Mobile plant and equipment; Dragline; ROM hopper; and Mobile equipment fleet. Figure 2.1 provides a schematic of the mining method utilised at Bengalla. Pre-strip mining (overburden removal prior to dragline excavation) is carried out by utilising three hydraulic excavators, a loader and a fleet of trucks which mine down to the Piercefield coal seam. The P&H 9020 electric powered dragline is the primary piece of machinery used for removal of interburden waste from the multi-seam coal deposits at Bengalla. The waste material is removed to the Vaux seam in the first pass and to the Broonie / Bayswater seams in the second pass, each time placing the waste in the spoil adjacent to the strip mine. Spoil (the waste overburden material) is typically dumped at an angle of repose of 37 degrees. The dragline then moves onto the spoil created by the first and second passes (the low wall) where it removes the waste to the Wynn seam and, in a second low wall pass, the waste to the lower most coal seam, the Edderton seam. The overburden and coal are accessed via haul road ramps which are formed as the mine proceeds westward. Haul trucks transport the overburden to overburden emplacement areas. Coal is hauled from the mining face to the ROM hopper which is located to the southwest of the operations next to the mining infrastructure area, where the coal is crushed to less than 250 millimetre. The crushed coal is then transported BMC BMP Determination 22 Feb 2012.docx Page 15

18 along a 300 metre conveyor to the crushing station. The coal is crushed to a top size of 50 millimetre and can be bypassed to product stockpiles, direct fed into the CHPP or transported and stockpiled on the raw coal stockpile. Where practical conveyors are enclosed to reduce both noise and dust emissions. The CHPP is located in the mine infrastructure area and houses the coal washery modules, each containing a dense medium cyclone and spirals to separate mineral contaminants. After processing, the product coal is centrifuged for the purpose of moisture reduction and then stacked onto one of two 250,000 tonne clean coal stockpiles. The product coal is then reclaimed from the stockpiles and conveyed to Bengalla s rail loading facility which is fully automated from the CHPP control room in the main administration complex, supporting a loading rate of 4,000 tonnes per hour. Product coal is loaded onto trains and taken either to the Port Waratah Coal Loader at Newcastle for export or railed directly to local power stations where it is used to produce electricity for the NSW power grid. Bengalla s CHPP has three coal stockpiles, including one raw coal stockpile and two clean coal stockpiles. The ROM coal stockpile has a capacity of 200,000 tonnes and the two product stockpiles hold a combined volume of 500,000 tonnes. The CHPP and stockpiles are surrounded by bunds to reduce visual impacts of the plant on surrounding areas. Dust from stockpile areas are managed by an automatic sequential spray system that is activated when wind speed exceeds 5.6 metres per second (m/s). Unlike conventional coal processing plants, Bengalla has no tailings dam and ultrafine material less than millimetre is thickened, dewatered on belt press filters and then combined with other reject streams for final disposal back into the spoil. Reject material is combined onto a single reject belt and stored in a reject bin prior to being hauled back to the pit area where it is dried in cells before being buried within the spoil area and capped with a minimum of five metres of inert overburden material. This external rehabilitated surface is then shaped back to a slope of 10 degrees or less. The handling of reject material is undertaken in accordance with mining operations plan commitments and operational procedures for coarse rejects and tailings disposal. BMC BMP Determination 22 Feb 2012.docx Page 16

19 Figure 2.1 Bengalla Mining Method Schematic BMC BMP Determination 22 Feb 2012.docx Page 17

20 2.2 Mine Activities with Potential Particulate Matter Emissions Bengalla s mining activities which are associated with potential particulate matter emissions are as follows: Scraper stripping topsoil; Drilling and blasting of coal and overburden; Bulldozer operations on coal and overburden (in pit); Dragline operations; Loading and dumping of overburden; Loading and unloading of coal; Hauling of overburden to OEAs; Hauling of coal to ROM hopper; Coal crushing and screening; Conveyors and conveyor transfer points (raw coal; product coal; reject); Stacking/reclaiming from coal stockpiles; Train loading; Coal stockpiles, topsoil stockpiles, active mining area, overburden emplacement areas, unsealed roads (wind erosion of exposed areas); Grader operations; and Other vehicle activity on site (light vehicles, fuel trucks, water trucks, delivery trucks). 2.3 Overview of Air Quality Monitoring at Bengalla Particulate matter monitoring at Bengalla forms an integral part of the site s operational dust management and a summary of this monitoring is therefore provided. Bengalla s monitoring network is comprised of: Five High Volume Air Samplers (HVAS) measuring TSP Four HVAS measuring PM depositional dust gauges Four real-time air monitors (E-bams) measuring PM 10, linked to the Real Time Environmental Management System (RTEMS). The real-time particulate matter monitors are used for proactive management of dust, informing the application of operational controls to reduce the potential for dust impacts. Real-time data from the PM 10 monitors located upwind and downwind of the mine (Figure 2.2), are combined with wind speed and direction data from the meteorological station, to assess potential dust impacts from the site. This enables air quality to be regularly assessed, with operations modified or ceased if impacts are deemed significant. The monitors have been integrated into the site s dispatch system to enable constant monitoring of dust impacts. Dust alarms and wind speed alarms alert pit the Open Cut Examiner (OCE) and environmental staff about operational dust impacts. BMC BMP Determination 22 Feb 2012.docx Page 18

21 Bengalla ceases operations during high dust periods (as informed by the site s real-time air quality monitoring system). When hourly average wind speeds are above 5.6 m/s the site does not operate on the elevated areas of its overburden emplacement area, prestrip area or the run of mine infill area. This system operates 24 hours a day seven days a week and the mine actively tracks its performance against results of this monitoring. BMC BMP Determination 22 Feb 2012.docx Page 19

22 Figure 2.2 Location of Bengalla s TSP, PM 10 and Meteorological Monitoring Stations BMC BMP Determination 22 Feb 2012.docx Page 20

23 3. Current Emissions and Control Measures The purpose of this section is to provide an estimate of baseline emissions and identify the four mining activities that currently generate the most particulate matter. Key components include: Estimation of TSP, PM 10 and PM 2.5 emissions (tonnes per year) from each mining activity using USEPA AP42 emission estimation techniques, including uncontrolled emissions and emissions with current controls in place. Ranking of mining activities according to the mass of TSP, PM 10, and PM 2.5 emitted by each mining activity per year. Identification of the top four mining activities that comprise the greatest contribution to emissions of TSP, PM 10 and PM Limitations of Emission Estimation Process The OEH Guideline requires that uncontrolled and controlled emissions be quantified. A significant number of management measures are integrated within the mine design and site operations which are not quantifiable, rendering it impractical to provide an accurate assessment of uncontrolled emissions. For example: air quality considerations accounted for within the selection of the haul truck fleet (trucks with larger payload capacity); ongoing practices to minimise areas of disturbance and haul distances; current progressive rehabilitation; placement of plant within more sheltered areas; wind sheltering through the use of bunds; and use of draglines to replace movement of overburden by truck and shovel. For the purpose of the current study, additional control measures, other than those of the type listed here, were excluded to provide a partial approximation of the extent of uncontrolled emissions. Furthermore, control efficiencies cannot be established for all types of management measures which are applied. For example, emission reductions realised by experienced personnel applying operational measures to reduce visible dust emissions in the field are not readily quantifiable. The practice of undertaking overburden dumping at sheltered locations during high winds provides a further example. The effectiveness of control measures for fugitive dust sources typically varies temporally and, in some instances, spatially. Control efficiencies documented in the literature are applicable for estimating annual emissions for an activity, but are less accurate in characterising changes in the control efficiency on a time-resolved basis and spatial differences in control efficiency. 3.2 Existing Particulate Matter Emissions and Controls Annual TSP, PM 10 and PM 2.5 emissions (tpa) were estimated based on USEPA AP42 emission estimation techniques and site-specific information as documented in Appendix B. To support the estimation of controlled emissions existing mitigation measures were inventoried and control efficiencies allocated, where possible. Existing particulate matter control measures being implemented at Bengalla are documented within Table 3.1. BMC BMP Determination 22 Feb 2012.docx Page 21

24 Table 3.1 Current control measures applied at Bengalla Mining Activity Category Current Control Measures Blasting Air quality impacts of blast operations are managed under the environmental procedure Environmental Procedure EP9.2 Blasting (including Air Quality and Vibration), and under other relevant safe work procedures such as PRO-0538 Drill & Blast Design Standard. EP9.2 aims to ensure that blasting operations comply with all Development Consent and EPL requirements and cause minimum dust effects at neighbouring properties. PRO-0538 aims to ensure that all blast designs and drill plans at Bengalla are to a standard and consider a number of inputs before drilling and blasting is undertaken, and to ensure that results for all blasts are collected and stored for future reference. At Bengalla blasting is restricted, only being permitted between 7 am and 5 pm, Monday to Saturday (daylight hours only), with restrictions to blasting also applied on public holidays. Individual blasts are designed to limit the potential for environmental impacts taking into account the size of individual charges, their proximity to roads and neighbouring residences, the nature of the stemming material and weather conditions. Reference is made to on-line Bureau of Meteorology forecasts during blast planning. Weekly blast scheduling references 7 day weather forecasts prior to schedule publication. During scheduling consideration is given to: - Wind direction and wind speed - Probability of rain - Temperature inversion - Blast pattern location relative to the extremities of the mining areas and the mines neighbours - Size of the blast pattern area - Material type - Expected dust and or blast fume generation potential - Sleep time - Hot or reactive ground Public roads within 500 metres of the blast site are closed during the blast and until they are confirmed clear of dust and fume affecting visibility. Blasting operations are also informed by the Blasting Permission System which integrates real-time meteorology (wind speed, inversion strength, wind direction). The potential for dust impacts is primarily addressed by the wind speed and wind direction criteria, with inversion strength specified primarily to address noise impact potentials. Detailed blasting restrictions are outlined in the document Bengalla Meteorological Restrictions for Blasting. If real-time data is not available, wind speed and direction is assessed using a hand held compass and anemometer from an elevated vantage point. Real-time meteorological data is supplied on Bengalla s Real Time Monitoring System. At least 1 hour prior to a scheduled blast time, Bengalla Environmental Services checks the real-time meteorological information for wind speed and direction before the blast is fired. Blasts are avoided under adverse meteorological conditions. 2 minutes prior to the scheduled blast time, the shot firer reconfirms the wind speed and direction. In the event that a blast needs to be delayed Environmental Services and the Superintendent Dragline Drill and Blast is notified. If the delay will extend beyond the permitted time of day for blasting then BMC Procedure PRO-077 Tie In Procedure is followed for postponing tie shots. Near neighbours are notified by phone and a Blasting Hotline provides the community with daily blast times and locations via a free-call number. The location of neighbouring properties that may be affected by blasting operations has been taken into account in the placement of particulate matter monitoring stations. The Site Environmental Advisor is responsible for checking meteorological conditions prior to blasting, ensuring all blast exceedances are analysed and confirmed, preparing blast BMC BMP Determination 22 Feb 2012.docx Page 22

25 Mining Activity Category Current Control Measures monitoring reports and notifying OEH of any exceedances. Environmental data for each blast is stored including weather (inversion strength, wind speed, wind direction) and blast monitor results (air overpressure and ground vibration). In addressing blast fume generation the following measures are implemented: - Restrictions are placed on permissible sleep times. Blasts in weathered material are not permitted to be slept any greater than 48 hours without the approval of the Drill and Blast Superintendent and no other blasts are permitted to be planned to be slept any greater than 5 days without the approval of the Drill and Blast Superintendent. - Use of blast fume scale and logging of fume incidences. Blast fumes are ranked as per Bengalla s Blast Fume Scale. - Trialling different explosives (e.g. Flexigel trials) - Blasts are filmed where practicable to provide a library of reference data for planning and problem resolution. Bulldozing Coal Bulldozing Overburden Coal Crushing and Screening Coal stockpiles Loading coal stockpiles Unloading coal stockpiles Dragline Dozers travel on watered routes between work areas. Dozers travel on watered routes between work areas. Ceasing of operations at exposed areas during high dust periods (as informed by the site s real-time air quality monitoring system). Crushing plant enclosed within internal water sprays. Dust generation from the coal stockpile area is addressed within environmental work instruction CNA-10-EWI-SITE-E Provision is made for: - Automated initiation of coal stockpile sprays when the wind exceeds 5.6 m/s. Coal stockpile spray systems are informed by on-line meteorological data. - Monitoring of the stacking machine and stockpile height, wherever possible, to minimize drop heights. - Visual triggers visible dust not to rise above the boom height of the stacker or reclaimer or leave the bounds of the stockpile being worked. - Close monitoring of reclaim operations where the machine is working raw coal or performing final cut reclaiming. - Use of stockpile sprays and/or water carts where dust cannot be controlled within the confines of the stockpile. - Bengalla uses automated stacker/reclaimers which vary their height by sensor. - Stockpiling and recovery of ROM coal is minimised as practical. ROM coal is usually trucked from the pit to the ROM hopper, with a limited ROM stockpile maintained in case of poor weather. Dragline dust controls are documented within work instruction CNA-1-EWI-SITE-E Operational measures applied are as follows: - Avoiding over-dragging and overflowing the material in the bucket, - Lift bucket cleanly away from the dig face -hoist up with minimum spillage, and - Restrict the drop height as far as practical, particularly during windy conditions - Placement of material in a manner which avoids large rocks rolling down the spoils. - Regular assessment of dust from dragline operations throughout the shift by the dragline operator and mine supervisor / team leader (or nominated representative). - Implementation of measures to ensure that visible dust from active work wares does not leave the mine site and encroach on normal private property. This is given as potentially requiring changes to operations or, during poor conditions, temporarily stopping operations. - Suspension of operations during dry, windy conditions. In 2009, by example, dragline operations ceased as a dust mitigation measure for 280 hours, including 96 hours in August. BMC BMP Determination 22 Feb 2012.docx Page 23

26 Mining Activity Category Drilling Dust-related dragline stoppages are logged. Current Control Measures The use of water cannons was investigated a number of years ago but found not to be viable at that time (personal communication, Danny Brooks, Dragline Drill & Blast Superintendent, Bengalla). All drill rigs are equipped with dust suppression systems (vacuum systems). Provision is made within environmental work instructions (CNA-10-EWI-SITE-E2-004) for the following measures: - Inspection of drill dust suppression systems to ensure they are fully operational at the start of each shift (water sprays, vacuum equipment, dust skirts to be fully operational). - Ceasing operations if systems are not operating properly resulting in visible dust. The drill is stood down pending repairs being carried out. - When moving off a drill hole, operators are required to take care not to disturb drill cuttings. - Blast crew must ensure disturbance to the crust on the drill cuttings is kept to a minimum when loading the shot. - Visible dust triggers for suspending operations (visible dust cloud rising above drill deck is unacceptable). Operators can call for a water cart if the drill bench is dusty (small water cart available for this purpose). Graders Graders travel on watered roads. Wheel Generated (Unpaved Roads) Loading/Dumping Overburden Material Transfer of Coal (Conveying; transfer points) Access roads with high traffic volumes are paved. Trafficable areas are clearly demarcated and vehicle movements largely restricted to these areas. All trafficable areas and vehicle manoeuvring areas are maintained. Fleet optimisation to reduce vehicle kilometres travelled. Bengalla s haul road fleet comprises three haul trucks with payload capacities of approximately 170 tonnes (3 Euclid R190 Rear Haul Trucks), 10 haul trucks with payloads of 280 Tonnes (1 Euclid R280 and 9 Hitachi Rear Haul Trucks) and 11 haul trucks with payloads of 209 Tonnes (11 Komatsu 830E Rear Haul Trucks). Wet suppression is applied using water carts. Levels of visible dust are assessed regularly by operators and the mine supervisor. Additional wet suppression is called for when elevated dust occurs. Interim measures taken to reduce dust levels (pending additional wet suppression) may include reduced vehicle speed or suspension of operations. Ceasing of operations during high dust periods (as informed by the site s real-time air quality monitoring system). Maximum overburden dump distances are restricted to 7 metres due to the lift height being 7 metres. Enclosure or partial enclosure of conveyors. Skirting fitted to conveyors at transfer points. Use of belt cleaning. Enclosed chutes. Scrapers Scrapers travel on watered roads. Suspension of topsoil stripping operations during dry, windy conditions. Train Loading Rail loading operations at Bengalla comprise automated loading systems, with provision made for telescopic chutes and load profiling. Such systems limit the potential for the collection of coal fines collecting on rail wagon sills and for wind entrainment during transit. Provision is made within environmental work instruction CNA-10-EWI-SITE-E2-001 for rail BMC BMP Determination 22 Feb 2012.docx Page 24

27 Mining Activity Category Trucks Loading Coal Trucks Unloading Coal (ROM Hopper) Wind Erosion of Exposed Areas Current Control Measures loading facilities to be closely monitored for the spillage of coal fines and material in the vicinity of the loading bin and rail siding. Coal spillage is required to be collected and disposed of on a regular basis to eliminate the potential for wind-blown dust. Drop heights are reduced as far as practicable by excavator operators. ROM hopper is equipped with a roof and is enclosed on 3-sides with automated water curtain. Dust generation at the ROM hopper is addressed within environmental work instruction CNA-10-EWI-SITE-E Provision is made for: Visual triggers for safety purposes (visible dust should preferably not rise above the operator cabin to ensure visibility is not compromised). Visual trigger for dust mitigation. Dust mitigation measures are called for if dust is observed to rise above the top of the tray. Application of wind speed thresholds (5.6 m/s) for defining moderate to strong winds for dust management purposes. Under such winds dust should not consistently rise over and above the operator cabin, unless other controls are in place (e.g. wind breaks or sprays) that effectively prevent dust from leaving the immediate area. Dust suppression sprays (or water cart) availability for use at all times during coal handling or dumping and in use if dust cannot be controlled below cabin height. Modification of operations (e.g. slower tipping) if dust cannot be controlled in the manner specified. Ceasing of operations when visible dust leaves the mine site. Minimisation of disturbed areas. All site disturbances are managed via the ground disturbance permit system. Topsoil stripping and topsoil stockpile volumes are tracked (and mapped) on an on going basis (topsoil stockpiled register). Topsoil stockpiles in place for longer than 3 months are revegetated to minimise dust generation. Topsoil stockpiles have gently battered slopes with heights limited to 3 metres. Topsoil stripping is not undertaken during high winds. Bengalla has no tailings dam (fine material is thickened, dewatered and then combined with other reject streams for emplacement within the spoil area and capped with a minimum of five metres of inert overburden material.) BMC BMP Determination 22 Feb 2012.docx Page 25

28 Mining Activity Category Wind Erosion of Overburden Current Control Measures Permanent rehabilitation in line with mining operation plan (MOP) targets. Bengalla rehabilitated 37.1 hectares in 2011; above its 2011 target of 36 hectares. Rehabilitation methods and procedures are undertaken in accordance with the Coal & Allied Rehabilitation Procedure and Bengalla s approved Rehabilitation and Landscape Management Plan. As rehabilitation progresses the vegetation is actively managed. This includes annual weed inspections and weed spraying programmes, vegetation control and slashing to mimic grazing and any remedial requirements such as repairing surface erosion. Rehabilitation is completed opportunistically to ensure plant establishment occurs reducing dust generation from uncovered areas. Warmer months are targeted for seeding, with increased soil temperatures that assist seed germination in native species. Rehabilitation monitoring is undertaken to assess the long term viability of rehabilitation. Monitoring methods used derive from ACARP Hunter Valley Project C13048 Development of Rehabilitation Completion Criteria for Native Ecosystem Establishment on Coal Mines in the Hunter Valley. Annual audit of rehabilitated areas to assess on going success of rehabilitation and identify areas that need remedial work. External consultants engaged to complete audits. The audit includes the review of Bengalla s initial rehabilitation completion criteria and other relevant statutory rehabilitation obligations. Specialist rehabilitation consultants are engaged to assist in rehabilitation techniques. Alternative rehabilitation techniques and soil improvement options are often trialled at Bengalla to improve the rehabilitation success of both pasture species and native tree species. Previous trials have included the use of bio solids, and the trialling of an organic growth medium (OGM) in 2010 consisting of municipal waste compost on a 2 hectare area of native seed. Hydromulch has been applied on temporarily inactive open spoils. Bengalla has applied hydromulching on a number of areas. Hydromulching is a type of rehabilitation often used for areas that topsoil cannot be applied and is commonly used for temporary rehabilitation. Hydro mulch contains a mixture of straw, seeds, water and a sticking agent so that it can be sprayed onto surfaces and will stick (then the seeds germinate). The temporary dump face facing Wybong Road was hydromulched in December 2010, increasing the visual amenity of the dump face and reducing the potential for dust from this dump face. In summary, Bengalla currently undertakes rehabilitation of areas as soon as they become available (including grass cover on windrows and temporary slopes). In addition, Bengalla will be increasing the amount of interim stabilisation of exposed areas. Control efficiencies are not readily quantifiable for all measures applied Where control efficiencies for measures exist, they have been based on published control factors or sitespecific calculations, as documented in Table 3.2. Site-specific calculations undertaken to quantify the effectiveness of Bengalla s haul road watering strategy are presented in Appendix C. Emission reductions due to rehabilitation efforts are accounted for by emission estimates only being quantified for exposed, unrehabilitated areas. BMC BMP Determination 22 Feb 2012.docx Page 26

29 Table 3.2 Control efficiencies applied for current controls, where quantifiable Mining Activity Category Coal Crushing and Screening Control Measure(s) Providing Basis for Control Efficiency Allocated(a) Crushing plant are enclosed within internal water sprays(b) Control Efficiencies (%) TSP PM 10 PM Coal Stockpiles Water sprays Drilling Water sprays Loading Coal Water sprays and variable height stacker(d) Stockpiles Material Transfer of Enclosed/partially enclosure of coal and reject Coal conveyors Train Loading Retractable chute Trucks Unloading ROM hopper is enclosed (roof, 3 sides) with Coal automated water curtain(e) Wheel Generated Wet suppression (water cart)(f) (Unpaved Roads) Wind Erosion of Wet suppression (water cart)(f) Exposed Areas Dragline Minimise drop height to within 5 metres(c) Notes: (a) Control efficiencies were derived from the NPI EETM Mining (2011), and the USEPA AP42 Emission Factor literature unless specified otherwise. (b) Crushers are enclosed with internal water sprays. A control efficiency of 75 percent was applied for enclosure, and an additional 50 percent control efficiency for water sprays, giving a combined control efficiency of 87.5 percent. (c) The control effectiveness of reducing the dragline drop height from 10m to 5m was estimated by varying the drop height within the dragline emission factor. (d) A control efficiency of 50 percent was applied for water sprays, and an additional 25 percent control efficiency for the use of variable height stackers, giving a combined control efficiency of 62.5 percent. (e) A control efficiency of 70 percent was applied for hopper enclosure (3 sides and roof), and an additional 50 percent control efficiency for the use of automated water sprays, giving a combined control efficiency of 85 percent. (f) A control efficiency of approximately 75 percent was calculated based on the site s haul road watering practices (refer to Appendix C); this coincides with the control efficiency specified in NPI EETM Mining (2011) for Level 2 watering, and with the maximum control efficiency indicated by the USEPA (2006) to be achievable through wet suppression. Annual TSP, PM 10 and PM 2.5 emissions (tpa) estimated for each OEH-defined mining activity utilising USEPA AP42 emission estimation techniques are provided for 2011 Operations for: Partially uncontrolled emissions (with no additional particulate matter controls in place) (Table 3.3); and Controlled emissions (with current particulate matter controls in place, where such controls are quantifiable and control efficiencies available) (Table 3.4). The overall control effectiveness, between the partially uncontrolled and currently control annual emission estimates, was calculated to be 65 percent for TSP, 63 percent for PM 10 and 51 percent for PM 2.5. BMC BMP Determination 22 Feb 2012.docx Page 27

MAC-ENC-PRO-057 AIR QUALITY MONITORING PROGRAM

MAC-ENC-PRO-057 AIR QUALITY MONITORING PROGRAM MAC-ENC-PRO-057 AIR QUALITY MONITORING Document Owner Donna McLaughlin, Environment Superintendent Document Approver Rob Hayes, Manager Environment Revision History Version No. Date Published Details 1.2

More information

Environmental compliance and performance report. Management of dust from coal mines

Environmental compliance and performance report. Management of dust from coal mines Environmental compliance and performance report Management of dust from coal mines Environmental compliance and performance report Management of dust from coal mines The Environmental compliance and performance

More information

MAC-ENC-MTP-040 AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN

MAC-ENC-MTP-040 AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN MAC-ENC-MTP-040 AIR QUALITY AND GREENHOUSE GAS MANAGEMENT PLAN Document Owner Donna McLaughlin, Environment Superintendent Document Approver Rob Hayes, Environment Manager Revision History Version Date

More information

WERRIS CREEK COAL PRP U1: MONITORING RESULTS WHEEL GENERATED DUST

WERRIS CREEK COAL PRP U1: MONITORING RESULTS WHEEL GENERATED DUST Report WERRIS CREEK COAL PRP U1: MONITORING RESULTS WHEEL GENERATED DUST WERRIS CREEK COAL PTY LTD Job ID. 07487c 29 July 2014 PROJECT NAME: Werris Creek Coal PRP U1: Monitoring Results Wheel Generated

More information

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review

Wellington Inner City Improvements National War Memorial Park (Pukeahu) Certification Review Wellington Inner City Improvements National War Memorial Park (Pukeahu) Air Quality (Dust) Certification Review 22 November 2012 [CAQMP1 TR] Prepared in association with: Document produced by: Apecx PO

More information

Section 2 Description of the Existing Mt Arthur Coal Mine

Section 2 Description of the Existing Mt Arthur Coal Mine Section 2 Description of the Existing Mt Arthur Coal Mine TABLE OF CONTENTS 2 DESCRIPTION OF THE EXISTING MT ARTHUR COAL MINE 2-1 2.1 MINING 2-1 2.2 COAL PREPARATION PLANT AND RAIL LOADING FACILITIES 2-3

More information

13.2.4 Aggregate Handling And Storage Piles. 13.2.4.1 General

13.2.4 Aggregate Handling And Storage Piles. 13.2.4.1 General 13.2.4 Aggregate Handling And Storage Piles 13.2.4.1 General Inherent in operations that use minerals in aggregate form is the maintenance of outdoor storage piles. Storage piles are usually left uncovered,

More information

Final. Office of Environment and Heritage. June 2011

Final. Office of Environment and Heritage. June 2011 NSW Coal Mining Benchmarking Study: International Best Practice Measures to Prevent and/or Minimise Emissions of Particulate Matter from Coal Mining Prepared for Office of Environment and Heritage KE1006953

More information

Types of Mining - Expert Table

Types of Mining - Expert Table See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

Rasp Mine. Zinc Lead Silver Project Project Approval No. 07-0018 January 2011. Community Lead Management Plan

Rasp Mine. Zinc Lead Silver Project Project Approval No. 07-0018 January 2011. Community Lead Management Plan Rasp Mine Zinc Lead Silver Project Project Approval No. 07-0018 January 2011 February 2012 This page has been left blank intentionally. Approved By: Operations Manager Issue Date: February 2012 Revision

More information

MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15

MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15 MT ARTHUR COAL ANNUAL ENVIRONMENTAL MANAGEMENT REPORT FY15 Page 2 of 165 Table of Contents 1 Introduction... 6 1.1 Approvals, Leases and Licences... 9 1.2 Mine Contacts... 12 1.3 Actions Required at Previous

More information

Mine Water Truck Tracking Rio Tinto Kennecott Copper TERESA COCKAYNE ENVIRONMENTAL, LAND, & WATER RTKC JULY 23, 2015

Mine Water Truck Tracking Rio Tinto Kennecott Copper TERESA COCKAYNE ENVIRONMENTAL, LAND, & WATER RTKC JULY 23, 2015 Mine Water Truck Tracking Rio Tinto Kennecott Copper TERESA COCKAYNE ENVIRONMENTAL, LAND, & WATER RTKC JULY 23, 2015 Purpose Dust suppression is a key component for safety and air quality compliance within

More information

Pollution & Noise from Demolition & Construction Sites

Pollution & Noise from Demolition & Construction Sites CONTROL OF Pollution & Noise from Demolition & Construction Sites N oi se Co ns tru ct io n MAY 2008 THE LONDON BOROUGH 3 CONTENTS Part 1 Introduction Page 1. Background 4 2. Purpose of the code 5 3.

More information

MAC-ENC-MTP-041 ENVIRONMENTAL MANAGEMENT STRATEGY

MAC-ENC-MTP-041 ENVIRONMENTAL MANAGEMENT STRATEGY ENVIRONMENTAL MANAGEMENT STRATEGY Document Owner Mike Gale, Environmental Superintendent Document Approver Rob Hayes, Environment Manager Revision History Version No Date Published Details 1.1 30 June

More information

www.epa.nsw.gov.au August 2014

www.epa.nsw.gov.au August 2014 Report on the Findings of the NSW Environment Protection Authority s Review of Snowy Hydro Limited Cloud Seeding Program: 2013 Annual Compliance Report August 2014 www.epa.nsw.gov.au State of NSW, Environment

More information

Fugitive Dust Control Plan Waste Management; La Grange, TX October 2015

Fugitive Dust Control Plan Waste Management; La Grange, TX October 2015 Waste Management; La Grange, TX October 2015 FUGITIVE DUST CONTROL PLAN Prepared for: 1634 Highway 531 Minden, Louisiana 71055 and LCRA Fayette Power Project 6549 Power Plant Road La Grange, TX 78945 Prepared

More information

Pollution Incident Response Management Plan

Pollution Incident Response Management Plan Pollution Incident Response Management Plan POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN 1. Introduction This Pollution Incident Response Management Plan (PIRMP) has been prepared to describe the processes

More information

Temporary Batch Plants

Temporary Batch Plants Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012

PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 Division(s): Sutton Courtenay & Harwell Contact Officer: John Duncalfe (john.duncalfe@oxfordshire.gov.uk) Tel: 01865 815356 PLANNING & REGULATION COMMITTEE 16 JANUARY 2012 TO CRUSH, SCREEN, BLEND AND STOCK

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT

LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government

More information

Pollution Incident Response Plan

Pollution Incident Response Plan Pollution Incident Response Plan Introduction Schmidt Quarries is committed to ensuring all aspects of our quarrying activities comply with the environmental legislative requirements in NSW. This Pollution

More information

Pollution Incident Response Management

Pollution Incident Response Management For Notification Procedure, please turn to Section 5 for Pollution Incident Response Management Document Table of Contents 1 Introduction... 3 1.1 Background and Scope... 3 1.2 Regulatory Requirements...

More information

Sustainable Resource Management Ltd

Sustainable Resource Management Ltd 6.0 Predicted nvironmental Impacts 6. Stages and Impacts Considered An nvironmental Impact Analysis has been carried out whereby all the possible environmental, socio economic and health & safety aspects

More information

Section 75J of the Environmental Planning & Assessment Act 1979

Section 75J of the Environmental Planning & Assessment Act 1979 Project Approval Section 75J of the Environmental Planning & Assessment Act 1979 As delegate of the Minister for Planning and Infrastructure under delegation executed on 14 September 2011, the Planning

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

Ingredion ANZ Pty Ltd

Ingredion ANZ Pty Ltd Ingredion ANZ Pty Ltd 170 Epping Road, Lane Cove, NSW 2066 EPL: 518 Page 1 of 8 1. Purpose and Background POLLUTION INCIDENT RESPONSE The purpose of this Pollution Incident Response Management Plan (PIRMP)

More information

Traffic Management Issue 1.0 Revision: v2 October 2014

Traffic Management Issue 1.0 Revision: v2 October 2014 Disclaimer IMPORTANT: The information in this guide is of a general nature, and should not be relied upon as individual professional advice. If necessary, legal advice should be obtained from a legal practitioner

More information

ENVIRONMENTAL MANAGEMENT PLAN :-

ENVIRONMENTAL MANAGEMENT PLAN :- ENVIRONMENTAL MANAGEMENT PLAN :- The Environment Management Plan (EMP) is required to ensure sustainable development in the area of the proposed project. Hence it needs to be all encompassive plan for

More information

STATE OF MISSOURI DEPARTMENT OF NATURAL RESOURCES MISSOURI AIR CONSERVATION COMMISSION PERMIT TO CONSTRUCT

STATE OF MISSOURI DEPARTMENT OF NATURAL RESOURCES MISSOURI AIR CONSERVATION COMMISSION PERMIT TO CONSTRUCT STATE OF MISSOURI flle COPl DEPARTMENT OF NATURAL RESOURCES MISSOURI AIR CONSERVATION COMMISSION PERMIT TO CONSTRUCT Under the authority of RSMo 643 and the Federal Clean Air Act the applicant is authorized

More information

APPENDIX 4. Risk Tables

APPENDIX 4. Risk Tables APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The

More information

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy

Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Expectations and Future Direction of MOP Guidelines Matthew Newton, Principal Officer Rehabilitation Standards Division of Resources & Energy Mine Rehab Conference 2014 Best Practice Ecological Rehabilitation

More information

Management Plan. Contractor Management

Management Plan. Contractor Management Management Plan Contractor Management Doc ID No. Version No. Owner Next Review Date Management Plan Contractor Management Risk Statement: High This document will be reviewed on a one yearly basis, unless

More information

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA

ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED PHASE 2 EXPANSION OF THE TRANSNET IRON ORE HANDLING FACILITY, SALDANHA BACKGROUND INFORMATION DOCUMENT 1 BACKGROUND Transnet Limited s (Transnet) existing

More information

Exploration for natural gas

Exploration for natural gas FACT SHEET NO. 42 Exploration for natural gas Quick facts QGC holds licences from the Queensland Government called Authorities to Prospect that allow us to explore in areas known as tenements We work with

More information

Permit Number: 3.1/062712/CP

Permit Number: 3.1/062712/CP POLLUTION PREVENTION AND CONTROL ACT 1999 ENVIRONMENTAL PERMITTING (ENGLAND AND WALES) REGULATIONS 2010 (amended) Permit Number: 3.1/062712/CP Installation Address: Bardon Concrete Warren Street Attercliffe

More information

Introduction to Waste Treatment Technologies. Contents. Household waste

Introduction to Waste Treatment Technologies. Contents. Household waste Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

Project Details-Minor Minerals (Other Than Sand)

Project Details-Minor Minerals (Other Than Sand) Project Details-Minor Minerals (Other Than Sand) Sr. No. Details Particulars ABOUT THE PROPOSAL 1. Name Of lease Holder M/s. Kirtikumar Samji Sengani 23 0'27.43"N 69 24'10.21"E 2. Location address Survey

More information

Appendix 14 Traffic Management Plan

Appendix 14 Traffic Management Plan Appendix 14 Traffic Management Plan Toms Gully Underground Project Table of Contents 1 Purpose... 3 2 Location & Production Overview... 3 3 Operations History... 3 4 Current Traffic Management & Traffic

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

Leica Jigsaw Jfleet Fleet Management System

Leica Jigsaw Jfleet Fleet Management System Leica Jigsaw Jfleet Fleet Management System You can t improve what you can t measure. You can t measure what you can t see. Unrivaled in their field Complete scalability Increased production & productivity

More information

Beseck Switching Station Inspection

Beseck Switching Station Inspection Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV

More information

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions

PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY. Introduction and Assumptions PROPOSAL FOR HOUSTON COUNTY BAN ON SILICA SAND MINING / PROCESSING ACTIVITY Introduction and Assumptions 1. The existing section 27 Mineral Extraction of the Zoning Ordinance would remain and continue

More information

The key points of the 2013 Annual Compliance Report are described fully in the following sections of this report:

The key points of the 2013 Annual Compliance Report are described fully in the following sections of this report: Introduction Snowy Hydro Limited (Snowy Hydro) relies on precipitation falling over the catchments of the Snowy Mountains to supply water for the production of hydro-electricity. Cloud seeding over this

More information

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT

EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING NAVFAC MIDLANT EQUIPMENT SAFETY EARTHMOVING MATERIAL HANDLING COMMON EARTHMOVING EQUIPMENT SKID LOADERS BACKHOE FRONT END LOADER GRADERS SCRAPERS BULL DOZERS Lots of stuff Here! COMMON MATERIAL HAULING TRUCKS ALL TYPES

More information

Environmental Management Plan

Environmental Management Plan Environmental Management Plan ENVIRONMENTAL MANAGEMENT PLAN An Environmental Management Plan is prepared for construction phase, post construction phase (commissioning & operation) and for post project

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. KARMANBHAI JODHABHAI RABARI (Partner) 2. Location address Mr. Karmanbhai Jodhabhai Rabari Survey No- 194 Paikee,

More information

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES

Final Environmental Impact Assessment of Smt. Singam Bhavani Laterite Mining ADDITIONAL STUDIES ADDITIONAL STUDIES 7.0 DISASTER MANAGEMENT PLAN It is presumed that the proposed mining process would be designed and engineered with all possible safety measures and standard code of practices. In spite

More information

Pollution Incident Response Management Plan (PIRMP)

Pollution Incident Response Management Plan (PIRMP) Pollution Incident Response Management Plan (PIRMP) For NSW Ports For Construction of Berth 103 Stage 2 Extension WATERWAY CONSTRUCTIONS PTY LTD ABN 74 061 311 395 Po Box 290, Annandale NSW 2038 TELEPHONE:

More information

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION

COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project

More information

Sydney Port Botany Terminal 3 Project Water Resource Management Plan

Sydney Port Botany Terminal 3 Project Water Resource Management Plan Civil Works Construction Contract Phase 1 1/8 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP

More information

CHAPTER 10 AIR QUALITY

CHAPTER 10 AIR QUALITY Central Eyre Iron Project Environmental Impact Statement CHAPTER 10: AIR QUALITY CHAPTER 10 AIR QUALITY COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document and any related documentation

More information

CCR Fugitive Dust Control Plan CPS Energy Calaveras Power Station San Antonio, Texas

CCR Fugitive Dust Control Plan CPS Energy Calaveras Power Station San Antonio, Texas CCR Fugitive Dust Control Plan CPS Energy Calaveras Power Station San Antonio, Texas October 15, 2015 The world's leading sustainability consultancy CPS Energy CCR Fugitive Dust Control Plan Calaveras

More information

Engineering Policy 146. Severe Weather Management Plans

Engineering Policy 146. Severe Weather Management Plans Engineering Policy 146 Severe Weather Management Plans January 2014 Contents Engineering Policy... 1 1 Policy statement... 1 2 Applicability... 1 3 Context... 1 4 Objectives and benefits... 1 5 Consultation...

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

SOUTH COOGEE TRANSPORT MANAGEMENT PLAN

SOUTH COOGEE TRANSPORT MANAGEMENT PLAN SOUTH COOGEE TRANSPORT MANAGEMENT PLAN On behalf of : DEPARTMENT FOR PLANNING & INFRASTRUCTURE Prepared by: ENV Australia A.C.N. 091 839 520 Mezzanine Level, Central Park 152-158 St Georges Terrace Perth

More information

Appendix A1. Register of legal and other requirements

Appendix A1. Register of legal and other requirements Appendix A1 Register of legal and other requirements 1 Table 1 Legal register Act Activity / General Environmental Planning and Assessment Act 1979 All Comply with the terms Minister for Planning and Infrastructure

More information

RISK ASSESSMENT. STONE QUARRY (2.40 Ha)

RISK ASSESSMENT. STONE QUARRY (2.40 Ha) RISK ASSESSMENT FOR STONE QUARRY (2.40 Ha) Gat no. 85, A/p Karanjvihire, Tahsil Khed, District Pune, Maharashtra OF M/s Shankar Ramchandra Earthmovers Pvt. Ltd. Risk Assessment for Stone Quarry Mining

More information

Activity Yes No N/A Notes

Activity Yes No N/A Notes CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3

More information

Appendix C. Re-vegetation and Rehabilitation Sub-Plan

Appendix C. Re-vegetation and Rehabilitation Sub-Plan Appendix C Re-vegetation and Rehabilitation Sub-Plan DRENNAN SOLAR ENERGY FACILITY REVEGETATION & REHABILITATION PLAN PRODUCED FOR ERM ON BEHALF OF SOLAIREDIRECT BY Simon.Todd@3foxes.co.za JUNE 2013 BACKGROUND

More information

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011

KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 KAWERAU DISTRICT COUNCIL BUSINESS DISASTER RECOVERY PLAN 2011 Kawerau District Council Private Bag 1004 Ranfurly Court KAWERAU 3169 Tel (07) 306 9009 Fax (07) 323 8072 Email kaweraudc@kaweraudc.govt.nz

More information

Project Details- Minor Minerals (Other Than Sand)

Project Details- Minor Minerals (Other Than Sand) Project - Minor Minerals (Other Than Sand) Sr. ABOUT THE PROPOSAL 1. Name of Lease Holder M/s. ABDUL MUNAF MOHAMMEDMIYA MALEK Mr.Abdul Munaf Mohammedmiya malek (Proprietor) 2. Location address OPP Block

More information

Management of mobile equipment maintenance audit. guide

Management of mobile equipment maintenance audit. guide Management of mobile equipment maintenance audit guide November 2015 1 Adelaide Terrace, East Perth WA 6004 Postal address: Mineral House, 100 Plain Street, East Perth WA 6004 Telephone: (08) 9358 8002

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

Blast Management Plan

Blast Management Plan Boggabri Coal Pty Ltd Blast Management Plan June 2013 Revision Control Chart Rev No Original 1 2 3 Revision Date Prepared by November 2012 B Dillon/J McDonough June 2013 B Bird Reviewed by B Bird J Green

More information

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history:

ANNUAL COMPLIANCE ASSESSMENT REPORT. Brockman Railway Infrastructure Project (Ministerial Statement 923) Revision history: ANNUAL COMPLIANCE ASSESSMENT REPORT Brockman Railway Infrastructure Project (Ministerial Statement 923) 2014 2015 Revision history: Revision Prepared Reviewed Approved Dated Issued Description A G. Firth

More information

MACHINE VISION ORIENTATION SENSOR THERMAL IMAGING 3D VISION DEEP LEARNING THERMAL IMAGING. www.motionmetrics.com

MACHINE VISION ORIENTATION SENSOR THERMAL IMAGING 3D VISION DEEP LEARNING THERMAL IMAGING. www.motionmetrics.com MACHINE VISION ORIENTATION SENSOR THERMAL IMAGING 3D VISION DEEP LEARNING THERMAL IMAGING www.motionmetrics.com EXTENDING MACHINE SENSES Trusted by the biggest names in mining... ABOUT US OUR CUSTOMERS

More information

WORKING IN CONFINED SPACES GUIDELINES

WORKING IN CONFINED SPACES GUIDELINES WORKING IN CONFINED SPACES GUIDELINES Contents 1 Introduction... 2 2 Scope... 2 3 Definitions... 2 4 Responsibilities... 3 4.1 Permit Authoriser... 3 4.2 Permit Receiver... 3 4.3 Responsible UOW Officer...

More information

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction

Devonport EfW CHP Facility. CEMP Proposal for Non Destructive Testing Activities. 1. Introduction Devonport EfW CHP Facility CEMP Proposal for Non Destructive Testing Activities. 1. Introduction This application is issued in compliance with the principles of the approved Construction Environmental

More information

All construction activities and post facility activity. All construction activities. A total of 12 piles are to be installed.

All construction activities and post facility activity. All construction activities. A total of 12 piles are to be installed. Construction on the Facility (a) Dust Prior to the start of construction, a baseline level particulate matter, dust fall and nitrogen dioxide monitoring program will be implemented to quantify the pre-project

More information

Waste Handling & Disposal

Waste Handling & Disposal Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended

More information

GENERAL SPECIFICATION

GENERAL SPECIFICATION R64 - PAVEMENT MARKING August 1996 GENERAL SPECIFICATION G10 CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN Date JUNE 2012 Department 1 DOT Spec R64 of Infrastructure, Energy and Resources Index DEPARTMENT

More information

Environmental Site Inspection Checklist

Environmental Site Inspection Checklist Note : This form is designed for general use and may not be exhaustive. Modifications and additions may be necessary to suit individual projects and to address specific environmental issues and associated

More information

Various Environmental Projects at Vanderbijlpark Works. December 2014

Various Environmental Projects at Vanderbijlpark Works. December 2014 Various Environmental Projects at Vanderbijlpark Works December 2014 1 1 Several Air Quality Projects 2 Emission reduction projects FMB DUST CONTROL INSTALLED SYSTEM The dust control system at the FMB

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Lower Hunter Ambient Air Quality Review of Available Data

Lower Hunter Ambient Air Quality Review of Available Data Lower Hunter Ambient Air Quality Review of Available Data 2012 ACKNOWLEDGEMENTS The Australian Nuclear Science and Technology Organisation, ConPorts, GrainCorp, Newcastle City Council, BHP Billiton, Hunter

More information

Focus on learning key. 1 NIHL impacts. Exercise. Discuss. Introduction

Focus on learning key. 1 NIHL impacts. Exercise. Discuss. Introduction Focus on learning key Exercise Analyse the information in your work group Date: Shift: Discussion led by: Attendees names: Discuss Go through questions in your workgroup Introduction Being exposed to excessive

More information

Bengalla Mine Chapter 3 Environmental Management and Performance. Figure 3-23 Hunter River ph 2008

Bengalla Mine Chapter 3 Environmental Management and Performance. Figure 3-23 Hunter River ph 2008 Bengalla Mine Chapter 3 Environmental Management and Performance Figure 3-23 Hunter River ph 2008 9 Hunter River ph Kayuga Rd Bridge (W01) to Downstream of Bengalla Mine W04) January 2008 to December 2008

More information

Blast management plan template

Blast management plan template Guidance note Blast management plan template Information for shotfirers on what a blast management plan may look like. April 2012 Background A blast management plan (BMP) is a risk control plan used in

More information

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE

WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.

More information

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP)

CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) CONSTRUCTION TRAFFIC MANAGEMENT PLAN (CTMP) [Colston Budd Hunt & Kafes Pty Ltd AS AMENDED BY City of Sydney] 23 March 2010 1. PREAMBLE 1.1 This document constitutes the Demolition and Traffic Management

More information

Management of Environmental Risks and Emergencies. Compliance Audit Program

Management of Environmental Risks and Emergencies. Compliance Audit Program Management of Environmental Risks and Emergencies Compliance Audit Program 2012 State of NSW and Environment Protection Authority The State of NSW and the Environment Protection Authority (EPA) are pleased

More information

Compliance Noise Monitoring

Compliance Noise Monitoring Monitoring Byron Centre The Manse Road Myocum HEALTH SCIENCE ENVIROMENTAL EDUCATION ENVIRONMENTAL AUDITOR Monitoring Byron Centre The Manse Road Myocum Prepared for: Byron Shire Council Version 1.0 Date:

More information

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY

2015 AVAGO 2D SEISMIC SURVEY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY ENVIRONMENTAL MANAGEMENT PLAN SUMMARY TABLE OF CONTENTS 1. INTRODUCTION... 3 2. DESCRIPTION OF ACTIVITY... 4 3. DESCRIPTION OF THE ENVIRONMENT... 4 4. DESCRIPTION OF THE ACTIVITY IN RELATION TO THE ENVIRONMENT...

More information

How To Conduct An Environmental Impact Assessment

How To Conduct An Environmental Impact Assessment Proposed Terms of Reference for EIA studies 1. Introduction The proposed expansion of Bulk Drugs & Intermediates manufacturing unit by M/s. Sri Krishna Pharmaceuticals Limited (Unit V). is located at Plot

More information

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa

Environmental Law Enforcement in Zimbabwe. Farai Michael Nyahwa Environmental Law Enforcement in Zimbabwe By Farai Michael Nyahwa Presentation Breakdown Institutional Arrangement for Environmental Law Enforcement in Zimbabwe Major Environmental Issues of Concern In

More information

Estimated emissions and CO2 savings deriving from adoption of in-place recycling techniques for road pavements

Estimated emissions and CO2 savings deriving from adoption of in-place recycling techniques for road pavements Estimated emissions and CO2 savings deriving from adoption of in-place recycling techniques for road pavements Introduction Objective: to estimate the CO2 emissions produced by road surface construction

More information

INDEPENDENT ENVIRONMENTAL AUDIT REPORT. Bulga Surface Operations

INDEPENDENT ENVIRONMENTAL AUDIT REPORT. Bulga Surface Operations INDEPENDENT ENVIRONMENTAL AUDIT REPORT May 2013 Bulga Surface Operations Report REPORT TITLE: Report CLIENT: Bulga Surface Operations Revision Number Report Date Report Author Reviewer Draft 23 January

More information

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY

TERMS OF REFERENCE FOR SCOPING OF EIA STUDY TERMS OF REFERENCE FOR SCOPING OF EIA STUDY Ours project is a proposed large scale unit and categorized as 5(h)-B as per the EIA notification 2006 of MoEFCC, New Delhi and subsequent amendments. Looking

More information

Port and Rail Operations Noise Environmental Management Plan

Port and Rail Operations Noise Environmental Management Plan Port and Rail Operations Noise Environmental Management Plan 18 May 2011 45-PL-EN-0021 Document Title: Document No: Document Type: Port and Rail Operations Noise Environmental Management Plan 45-PL-EN-0021

More information

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy.

This document must be read in conjunction with the Permit to Work and Service Interruption Notice policy. UNIVERSITY OF HERTFORDSHIRE HIGHER EDUCATION CORPORATION SITE RULES FOR CONTRACTORS The University s Site Rules for Contractors are issued on the authority of the Director of Estates, Hospitality and Contract

More information

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024

Environmental Incident Response Procedure. Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Newcastle Gas Storage Facility Document Number: NGSF-PSV-NAS-EN-PLN-0024 Environmental Incident Response Procedure Document Number: NGSF-PSV-NAS-EN-PLN-0024 Version:

More information

PROPOSED TERMS OF REFERENCE

PROPOSED TERMS OF REFERENCE PROPOSED TERMS OF REFERENCE ABOUT THE PROJECT: Rampura Marble Mine (ML No.- 420/91) is proposed by M/s Continental Minerals Pvt. Ltd. The Mine Lease area consists of 3.0 ha, which is located at Khasra

More information

CONTRACTOR SAFETY MANAGEMENT PROCEDURE

CONTRACTOR SAFETY MANAGEMENT PROCEDURE CONTRACTOR SAFETY MANAGEMENT PROCEDURE Version 1.0 TRIM file number Short description Relevant to Authority Responsible officer Responsible office Date introduced July 20, 2015 Date(s) modified June 11,

More information

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.)

THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT ORDINANCE (CAP. 84 - LAWS OF SARAWAK, 1958 Ed.) THE NATURAL RESOURCES AND ENVIRONMENT (PRESCRIBED ACTIVITIES) ORDER, 1994 (Made under section 11A(1)) (Incorporating

More information

BLAST MANAGEMENT PLAN

BLAST MANAGEMENT PLAN Environmental Management System Integra Coal Operations Pty Ltd BLAST MANAGEMENT PLAN 2012 2015 Doc No: Doc Owner: Blast Management Plan Environmental Advisor Integra Coal Operations Approval: Manager

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

Excavation & Trenching Procedure

Excavation & Trenching Procedure Excavation & Trenching 1. Overview The will ensure, as far as is reasonably practicable, that the conduct of work relating to excavation and trenching will not be harmful to the health and safety of employees

More information