RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD. (Regd. Office: Vidyut Bhavan, Janpath, Jyoti Nagar, Jaipur ) CONSTRUCTION MANUAL FOR SUB STATIONS

Size: px
Start display at page:

Download "RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD. (Regd. Office: Vidyut Bhavan, Janpath, Jyoti Nagar, Jaipur 302005) CONSTRUCTION MANUAL FOR SUB STATIONS"

Transcription

1 RAJASTHAN RAJYA VIDYUT PRASARAN NIGAM LTD. (Regd. Office: Vidyut Bhavan, Janpath, Jyoti Nagar, Jaipur ) CONSTRUCTION MANUAL FOR SUB STATIONS

2 F O R E W O R D The Engineers experienced in the field of Transmission have made this effort to compile the experience gained over the past 40 years in the form of a Manual and make it available to the Engineers and Technical Supervisors of the Company. This is a step forward to disseminate knowledge so that uniform practices and procedures are followed in the construction activities in the Company. This Manual covers all the activities related to the construction of Sub Stations. I appreciate the work done by the members of the Committee in preparing and bringing out this Construction Manual for Sub Stations. I hope that the Manual will be of immense use and reference to the Engineers of the Transmission & Construction Wing. April, 2007 Jaipur Shreemat Pandey Chairman & Managing Director Rajasthan Rajya Vidyut Prasaran Nigam Ltd.

3 P R E F A C E The construction practices in the transmission wing of RVPN have been built over the past 40 years and passed on from seniors to juniors. The new generation of Engineers, skilled Technical Supervisors and Workmen has, from time to time, constantly updated the construction practices according to the latest developments in the field of Transmission Engineering. It was felt that the construction practices built over the years be compiled in the form of a Manual and made available to Engineers and Technical Supervisors engaged in the construction activities so that uniform practices and procedures are followed in the Company. A Committee of the following Engineers experienced in the field of Transmission was assigned the task of preparing the Construction Manual: Shri S. Dhawan, Chief Engineer (MM) Shri B. N. Saini, Superintending Engineer (400 KV Design) Shri Raghuvendra Singh, Executive Engineer (Prot. II) Shri Mohan Singh Ruhela, Executive Engineer (C&M 400 KV GSS), Heerapura Shri A. D. Sharma, Assistant Engineer (Civil 400 KV Design) Shri Atul Sharma, Assistant Engineer (TLPC) I appreciate the work done by the members of the Committee in preparing and bringing out this Construction Manual for Sub Stations. I am confident that the Manual will be of great help to the Engineers posted in the Transmission & Construction Wing in discharging their duties. April, 2007 Jaipur Y. K. Raizada Director (Technical) Rajasthan Rajya Vidyut Prasaran Nigam Ltd.

4 CONTENTS Section I: SITE SELECTION & SUB STATION DESIGN Selection of Land Layout Design Safety Clearances Earth Mat Design Section II: ERECTION, TESTING AND COMMISSIONING General Instructions Structures Bus Bar and Earth Wire Aluminium Pipe Bus Bar and Joints Power Transformers Circuit Breakers Isolators Current Transformers Capacitor Voltage Transformers (CVT) / Potential Transformers (PT) Lightning Arresters Post / Polycone Insulators Wave Traps Line Matching Unit (LMU) / Line Matching Distribution Unit (LMDU) Capacitor Banks Earthing Cable Laying and Wiring Battery Sets (Valve Regulated Lead Acid / VRLA) DC Panels Battery Chargers Control & Relay Panels LT Panels PLCC Carrier Sets Carrier Protection Couplers PLCC Exchange Commissioning of Sub Station Bibliography

5 SECTION I SITE SELECTION & SUB STATION DESIGN

6 CHAPTER 1 SELECTION OF LAND 1.0 SELECTION OF SITE: 1.1 Selection of site for construction of a Grid Sub Station is the first and important activity. This needs meticulous planning, fore-sight, skillful observation and handling so that the selected site is technically, environmentally, economically and socially optimal and is the best suited to the requirements. 1.2 The main points to be considered in the selection of site for construction of a Grid Sub Station are given below. 1.3 The site should be: a) As near the load centre as possible. b) As far as possible rectangular or square in shape for ease of proper orientation of bus bars and feeders. c) Far away from obstructions, to permit easy and safe approach / termination of high voltage overhead transmission lines. d) Free from master plans / layouts or future development activities to have free line corridors for the present and in future. e) Easily accessible to the public road to facilitate transport of material. f) As far as possible near a town and away from municipal dumping grounds, burial grounds, tanneries and other obnoxious areas. g) Preferably fairly leveled ground. This facilitates reduction in leveling expenditure. h) Above highest flood level (HFL) so that there is no water logging. i) Sufficiently away from areas where police and military rifle practices are held. 1.4 The site should have as far as possible good drinking water supply for the station staff. 1.5 The site of the proposed Sub Station should not be in the vicinity of an aerodrome. The distance of a Sub Station from an aerodrome should be maintained as per regulations of the aerodrome authority. Approval in writing should be obtained from the aerodrome authority in case the Sub Station is proposed to be located near an aerodrome. 2.0 REQUIREMENT OF LAND / AREA: 2.1 The site should have sufficient area to properly accommodate the Sub Station buildings, structures, equipments, etc. and should have the sufficient area for future extension of the buildings and / or switchyard.

7 6 Construction Manual for Sub Stations 2.2 The requirement of land for construction of Sub Station including staff colony is as under: S.No. Voltage Class of GSS Required Area kv 20.0 Hectare kv 6.0 Hectare kv 3.5 Hectare 2.3 While preparing proposals for acquisition of private land and allotment of Government land, the area of land for respective Grid Sub Stations shall be taken into consideration as mentioned in para 2.2 above. While selecting Government land, the requirement may be made liberally but in other cases, where payment is to be made for the land acquisition, the requirement should be restricted to the limit mentioned in para 2.2.

8 CHAPTER 2 LAYOUT DESIGN 1.0 BUS BAR SCHEMES: The commonly used bus bar schemes at Sub Stations are: a) Single bus bar. b) Main and Auxiliary bus bar. c) Double bus bar. d) Double Main and Auxiliary bus bar e) One and a half breaker scheme. 1.1 SINGLE BUS BAR ARRANGEMENT: This is the simplest switching scheme in which each circuit is provided with one circuit breaker. This arrangement offers little security against bus bar faults and no switching flexibility resulting into quite extensive outages of bus bar and frequent maintenance of bus bar isolator(s). The entire Sub Station is lost in case of a fault on the bus bar or on any bus bar isolator and also in case of maintenance of the bus bar. Another disadvantage of this switching scheme is that in case of maintenance of circuit breaker, the associated feeder has also to be shutdown Typical Single Bus Bar arrangement is shown in Annexure MAIN AND AUXILIARY BUS ARRANGEMENT: This is technically a single bus bar arrangement with an additional bus bar called Auxiliary bus energized from main bus bars through a bus coupler circuit, i.e., for n number of circuits, it employs n + 1 circuit breakers. Each circuit is connected to the main bus bar through a circuit breaker with isolators on both sides and can be connected to the auxiliary bus bar through an isolator. The additional provision of bus coupler circuit (Auxiliary bus) facilitates taking out one circuit breaker at a time for routine overhaul and maintenance without de energizing the circuit controlled by that breaker as that circuit then gets energized through bus coupler breaker As in the case of single bus arrangement, this scheme also suffers from the disadvantages that in the event of a fault on the main bus bar or the associated isolator, the entire substation is lost. This bus arrangement has been extensively used in 132 kv Sub Stations Typical Main and Auxiliary Bus Bar arrangement is shown in Annexure DOUBLE BUS BAR ARRANGEMENT: In this scheme, a double bus bar arrangement is provided. Each circuit can be connected to either one of these bus bars through respective bus bar isolator. Bus coupler breaker is also provided so that the circuits can be switched on from one bus to the other on load. This scheme suffers from the disadvantage that when any circuit breaker is taken out for maintenance, the associated feeder has to be shutdown This Bus bar arrangement was generally used in earlier 220 kv sub stations Typical Double Bus Bar arrangement is shown in Annexure DOUBLE MAIN AND AUXILIARY BUS BAR ARRANGEMENT: The limitation of double bus bar scheme can be overcome by using additional Auxiliary bus, bus coupler breaker and Auxiliary bus isolators. The feeder is transferred to the

9 8 Construction Manual for Sub Stations Auxiliary bus during maintenance of its controlling circuit breaker without affecting the other circuits This Bus bar arrangement is generally used nowadays in 220 kv sub stations Typical Double Main and Auxiliary Bus Bar arrangement is shown in Annexure ONE AND A HALF BREAKER ARRANGEMENT: In this scheme, three circuit breakers are used for controlling two circuits which are connected between two bus bars. Normally, both the bus bars are in service A fault on any one of the bus bars is cleared by opening of the associated circuit breakers connected to the faulty bus bar without affecting continuity of supply. Similarly, any circuit breaker can be taken out for maintenance without causing interruption. Load transfer is achieved through the breakers and, therefore, the operation is simple. However, protective relaying is somewhat more involved as the central (tie) breaker has to be responsive to troubles on either feeder in the correct sequence. Besides, each element of the bay has to be rated for carrying the currents of two feeders to meet the requirement of various switching operations which increases the cost. The breaker and a half scheme is best for those substations which handle large quantities of power and where the orientation of out going feeders is in opposite directions. This scheme has been used in the 400 kv substations Typical One and a Half Breaker arrangement is shown in Annexure ELECTRICAL LAYOUT DRAWING: 2.1 Typical electrical layout drawings and sectional drawings of 400 kv, 220 kv and 132 kv sub stations with different bus bar arrangements generally adopted in RVPN are shown in Annexure 6 to Annexure BILL OF MATERIAL: 3.1 Lists of material showing the particulars of the material generally required for construction of 132 kv, 220 kv and 400 kv sub stations are given at Annexure 15 to Annexure 17 respectively. 3.2 The lists of material are only typical and cover the general requirement. Any other equipment / structure / material which may be required for construction of Sub Station as per layout and other requirements and not included in the above typical lists of material are also to be added.

10 Layout Design 9 ANNEXURE 1

11 10 Construction Manual for Sub Stations ANNEXURE 2

12 Layout Design 11 ANNEXURE 3

13 12 Construction Manual for Sub Stations ANNEXURE 4

14 Layout Design 13 ANNEXURE 5

15 14 Construction Manual for Sub Stations ANNEXURE 6

16 Layout Design 15 ANNEXURE 7

17 16 Construction Manual for Sub Stations ANNEXURE 8

18 Layout Design 17 ANNEXURE 9

19 18 Construction Manual for Sub Stations ANNEXURE 10

20 Layout Design 19 ANNEXURE 11

21 20 Construction Manual for Sub Stations ANNEXURE 12

22 Layout Design 21 ANNEXURE 13

23 22 Construction Manual for Sub Stations ANNEXURE 14

24 Layout Design 23 LIST OF MATERIAL (TYPICAL) FOR CONSTRUCTION OF 132 kv GRID SUB-STATION Annexure 15 S. No. Particulars A. Structures / Beams with nuts, bolts, washers, etc. complete. 1. BT 1 type Column 2. BT 4 type Column 3. BT 6 type Column 4. BT 7 type Column 5. BB 1 type Beam 6. P type Column 7. Q type Column (with stub) 8. Q type Column (without stub) 9. R type Column (with stub) 10. GD type (10.0 Meters) Beam 11. X type Column 12. Y type Column (with stub) 13. Y type Column (without stub) 14. Z type Column (with stub) 15. GF type Beam (5.4 Meters for 33 kv) 16. BO 1 type for 132 kv Isolators 17. BO 1 (T) type for 132 kv Tandem Isolators 18. AO 5 type for LA s / CT s / Bus CVT s 19. PIS type for 132 kv PIs 20. X 15 type for 33 kv Isolators kv CT type B. Outdoor Equipment / 33 kv Power Transformer kv Isolator without Earth Blade kv Isolator with Earth Blade kv Tandem Isolator kv Circuit Breaker with structure (110 V DC) kv Current Transformer for transformer ( / 1A, 3C) kv Current Transformer for feeder ( / 1A, 3C) kv Capacitor Voltage Transformer (110/ 3, 110/ 3) kv Lightning Arrester kv Wave Trap kv Post Insulators kv Marshalling Kiosk kv Isolator without Earth Blade kv Isolator with Earth Blade kv Circuit Breaker with structure (110 V DC) kv Current Transformer for transformer ( / 1A, 5C) kv Current Transformer for feeder ( / 1A, 2C) kv Potential Transformer (110/ 3, 110/ 3, 110/ 3) kv Lightning Arrester kv Post Insulators / kv, 250 KVA Station Transformer kv Horn Gap Fuse Set kv Marshalling Kiosk (one for 2 nos. bays)

25 24 Construction Manual for Sub Stations S. No. Particulars C. Control Room Equipment kv side of Transformer Control & Relay Panel (110 V, 1A) kv Feeder Control & Relay Panel (110 V, 1A) kv Bus Coupler Control & Relay Panel (110V, 1A) kv side Control & Relay Panel for Transformer & Bus Coupler (110V, 1A) kv Feeder Control & Relay Panel for two nos. feeders (110V, 1A) Volts, 200 AH Battery Set Volts, 200 AH Battery Charger Volts D. C. Distribution Board 9. L. T. Distribution Board (110 V DC) D. Bus Bar Material 1. Single Tension Hardware for Single Zebra (Bolted type) 2. Single Tension Hardware for Panther (Bolted type) 3. Single Suspension Hardware for Single Zebra 4. Single Suspension Hardware for Panther KV Disc Insulators, 120 KN KV Disc Insulators, 45 KN 7. ACSR Zebra Conductor 8. ACSR Panther Conductor 9. T Clamps for Zebra to Zebra 10. T Clamps for Zebra to Panther 11. T Clamps for Panther to Panther 12. P. G. Clamps for Zebra to Zebra 13. P. G. Clamps for Zebra to Panther 14. P. G. Clamps for Panther to Panther 15. P. I.Clamps for Zebra 16. P. I.Clamps for Panther 17. Tension Hardware for 7 / 3.15 mm GSS Earth wire / 3.15 mm. GSS Earth wire 19. P. G. Clamps for 7 / 3.15 mm. Earth wire E. Copper Control Cables / 16 core 2.5 sq. mm / 10 core 2.5 sq. mm core 2.5 sq. mm core 4 sq. mm core 2.5 sq. mm core 2.5 sq. mm. F. LT Power Cable (Aluminium) 1. 3½ core 300 sq. mm. G. Earthing Material 1. M. S. Round 25 mm. dia. 2. M. S. Flat mm. 3. M. S. Flat 50 6 mm. H. Others / Miscellaneous 1. M. S. Channel mm. 2. Copper Earth Bond I. Fire Fighting Equipment 1. D. C. P. type. 2. CO2 type.

26 Layout Design 25 LIST OF MATERIAL (TYPICAL) FOR CONSTRUCTION OF 220 kv GRID SUB-STATION Annexure 16 S. No. Particulars A. Structures / Beams with nuts, bolts, washers, etc. complete. 1. AT 1 type Column 2. AT 3 type Column 3. AT 4 type Column 4. AT 6 type Column 5. AT 8 type Column 6. AB 1 type Beam 7. BT 1 type Column 8. BT 4 type Column 9. BT 6 type Column 10. BT 7 type Column 11. BB 1 type Beam 12. AO 1 type for 220 kv Isolators 13. AO 1 (T) type for 220 kv Tandem Isolators 14. AO 3 type for 220 kv CT s 15. AO 4 type for 220 kv CVT s 16. AO 5 type for 220 kv LA s & for 132 kv CT s, CVT s / PT s, LA s 17. BO 1 type for 132 kv Isolators 18. BO 1 (T) type for 132 kv Tandem Isolators 19. PIS type for 220 kv & 132 kv PI s B. Outdoor Equipment / 132 kv Power Transformer kv Isolator without Earth Blade kv Isolator with Earth Blade kv Isolator with Double Earth Blade kv Tandem Isolator kv Circuit Breaker with structure (220 V DC) kv Current Transformer ( / 1A, 5C) kv Capacitor Voltage Transformer (110/ 3, 110/ 3) kv Lightning Arrester kv Wave Trap kv Post Insulators kv Marshalling Kiosk kv Isolator without Earth Blade kv Isolator with Earth Blade kv Tandem Isolator kv Circuit Breaker with structure (220 V DC) kv Current Transformer ( / 1A, 4C) kv Capacitor Voltage Transformer (110/ 3, 110/ 3) kv Lightning Arrester kv Wave Trap kv Post Insulators kv Marshalling Kiosk / kv, 250 KVA Station Transformer

27 26 Construction Manual for Sub Stations S. No. Particulars C. Control Room Equipment kv side of Transformer Control & Relay Panel (220 V DC, 1A) kv Feeder Control & Relay Panel (220 V DC, 1A) kv Bus Coupler Control & Relay Panel (220 V DC, 1A) kv side of Transformer Control & Relay Panel (220 V DC, 1A) kv Feeder Control & Relay Panel (220 V DC, 1A) kv Bus Coupler Control & Relay Panel (220 V DC, 1A) Volts, 400 AH Battery Set Volts, 400 AH Battery Charger Volts D. C. Distribution Board 10. L. T. Distribution Board (220 V DC) D. Bus Bar Material 1. Single Tension Hardware for Double Zebra (Bolted type) 2. Single Tension Hardware for Single Zebra (Bolted type) 3. Single Tension Hardware for Panther (Bolted type) 4. Single Suspension Hardware for Double Zebra 5. Single Suspension Hardware for Single Zebra 6. Single Suspension Hardware for Panther kv Disc Insulators, 120 KN kv Disc Insulators, 70 KN 9. ACSR Zebra Conductor 10. ACSR Panther Conductor 11. Spacer T Clamps for Double Zebra to Zebra (ZZ Z) 12. Spacer T Clamps for Double Zebra to Panther (ZZ P) 13. T Clamps for Zebra to Zebra (Z Z) 14. T Clamps for Zebra to Panther (Z P) 15. T Clamps for Panther to Panther (P P) 16. P. G. Clamps for Zebra to Zebra (Z Z) 17. P. G. Clamps for Zebra to Panther (Z P) 18. P. G. Clamps for Panther to Panther (P P) 19. P. I.Clamps for Zebra 20. P. I.Clamps for Panther 21. Tension Hardware for 7 / 4.00 mm GSS Earth wire / 4.00 mm. GSS Earth wire 23. P. G. Clamps for 7 / 4.00 mm. Earth wire E. Copper Control Cables / 16 core 2.5 sq. mm / 10 core 2.5 sq. mm core 6 sq. mm core 2.5 sq. mm core 4 sq. mm core 2.5 sq. mm core 2.5 sq. mm. F. LT Power Cable (Aluminium) 1. 3½ core 300 sq. mm. G. Earthing Material 1. M. S. Round 28 mm. dia. 2. M. S. Flat mm. 3. M. S. Flat 50 6 mm.

28 Layout Design 27 S. No. Particulars H. Others / Miscellaneous 1. M. S. Channel mm. 2. Copper Earth Bond I. Fire Fighting Equipment 1. D. C. P. type 2. CO2 type

29 28 Construction Manual for Sub Stations LIST OF MATERIAL (TYPICAL) FOR CONSTRUCTION OF 400 kv GRID SUB-STATION Annexure 17 S. No. Particulars A. Structures / Beams with nuts, bolts, washers, etc. complete. 1. EhT 1 type Column 2. EhB 1 type Beam 3. AT 1 type Column 4. AT 3 type Column 5. AT 4 type Column 6. AT 6 type Column 7. AT 8 type Column 8. AB 1 type Beam kv Isolator Structure kv CT Structure kv CVT Structure kv LA Structure kv PI Structure (8.0 Meter Bus Height) kv PI Structure (10.0 Meter Bus Height) kv PI Structure (13.0 Meter Bus Height) kv Wave Trap Structure 17. AO 1 type for 220 kv Isolators 18. AO 1 (T) type for 220 kv Tandem Isolators 19. AO 3 type for 220 kv CT s 20. AO 4 type for 220 kv CVT s 21. AO 5 type for 220 kv LA s 22. PIS type for 220 kv PI s kv PT structure kv PI structure for PI and Horn Gap Fuse B. Outdoor Equipment / 220 kv Power Transformer kv Isolator with Earth Blade kv Isolator with Double Earth Blade kv Isolator with Double Earth Blade (Individual Pole Operated) kv Circuit Breaker with structure (220 V DC) kv Current Transformer ( / 1A, 5C) kv Capacitor Voltage Transformer (110/ 3 V, 110/ 3 V, 110/ 3V) kv Lightning Arrester kv Polycone Insulators with corona ring kv Wave Trap (Pedestal Type) kv Marshalling Kiosk kv Isolator without Earth Blade kv Isolator with Earth Blade kv Isolator with Double Earth Blade kv Tandem Isolator kv Circuit Breaker with structure (220 V DC) kv Current Transformer ( / 1A, 5C) kv Capacitor Voltage Transformer (110/ 3 V, 110/ 3V)

30 Layout Design 29 S. No. Particulars kv Lightning Arrester kv Wave Trap kv Polycone Insulators kv Marshalling Kiosk kv Potential Transformer (110/ 3 V, 110/ 3V) for tertiary winding of Transformer / kv, 630 kva Station Transformer kv Post Insulators kv Horn gap Fuse 27. Junction Box 28. WCSM 90 / 30 mm insulation for 33 kv pipe bus with tube roll C. Control Room Equipment (220 V DC, 1 Amp.) kv Control Panel for line, Tie CB and Transformer (One and a Half Breaker Scheme) kv Relay Panel for 400 kv line kv Relay Panel for 400 kv Tie CB kv Relay Panel for 400 kv side of transformer kv Bus Bar Protection Relay Panel kv Control Panel for 220 kv side of transformer kv Control Panel for 220 kv feeders kv Control Panel for 220 kv Bus Coupler kv Relay Panel for 220 kv side of transformer kv Relay Panel for 220 kv feeders kv Relay Panel for 220 kv Bus Coupler kv Bus Bar Protection Relay Panel 13. Disturbance Recorder 14. Event Logger Panel Volts, 600 AH Battery Set Volts, 600 AH Battery Charger Volts D. C. Distribution Boards 18. L. T. Distribution Boards V DC / 240 V AC Inverter (2.5 kva) 20. Master and Slave Clock System (1 No. Master and 6 Nos. Slave) 21. Air Conditioning system 22. Mulsifier Fire fighting System 23. Synchronizing Panel / Trolley D. Bus Bar Material a) 400 kv Side: 1. Double Tension Hardware for double Moose 2. Single suspension Hardware for double Moose (Dropper Type) 3. Single suspension Hardware for double Moose (Jumper Type) KN Disc Insulators (Antifog type) 5. Spacer for Double Moose (Rigid type) 6. Spacer for Double Moose (Flexible type) 7. T Clamp for Moose 8. Double Moose to mm dia. Aluminium pipe clamp (Vertical & Horizontal take off) kv Isolator clamp for Double Moose

31 30 Construction Manual for Sub Stations S. No. Particulars kv Isolator clamp for mm dia. Aluminium pipe (Expansion type) kv CT clamp for mm dia. Aluminium pipe (Expansion type) kv CB clamp for mm dia. Aluminium pipe (Expansion type) kv PI clamp for mm dia. Aluminium pipe (Expansion type) kv PI clamp for mm dia. Aluminium pipe (Rigid type) kv PI clamp for 114.2mm dia. Aluminium pipe (Sliding type) kv LA clamp for Double Moose kv CVT clamp for Double Moose kv Wave Trap clamp for Double Moose mm dia. Aluminium pipe 20. Corona End Shield for mm dia. Aluminium pipe 21. Angular Connector for mm dia. Aluminium pipe, 20 Deg. 22. Angular Connector for mm dia. Aluminium pipe, 80 Deg. 23. Angular Connector for mm dia. Aluminium pipe, 90 Deg. 24. Angular bend Coupler for mm dia. Aluminium pipe, 110 Deg. 25. Angular bend Coupler for mm dia. Aluminium pipe, 135 Deg. 26. Straight Run Coupler for mm dia. Aluminium pipe 27. Transformer clamp for 400 kv Bushing for Double Moose b) 220 kv Side: 1. Double Tension Hardware for Quadruple Zebra 2. Double Tension Hardware for Double Zebra 3. Single Tension Hardware for Zebra 4. Single Suspension Hardware for Quadruple Zebra (Jumper type) 5. Single Suspension Hardware for Double Zebra (Dropper type) 6. Single Suspension Hardware for Double Zebra (Jumper type) 7. Single Suspension Hardware for Single Zebra KN Disc Insulators (Antifog type) 9. Spacer for Quadruple Zebra 10. Spacer for Double Zebra 11. P. I.Clamps for Double Zebra 12. T Connector; Quadruple Zebra to Quadruple Zebra 13. T Connector; Quadruple Zebra to Double Zebra 14. Spacer T Clamps for Double Zebra to Zebra (ZZ Z) 15. T Clamp; Zebra to Zebra 16. P. G. Clamps for Zebra to Zebra (Z Z) 17. Transformer clamp for 220 kv Bushing for Double Zebra 18. LA Clamp for Double Zebra 19. LA Clamp for Single Zebra 20. CVT Clamp for Single Zebra 21. CT Clamp for Double Zebra 22. CT Clamp for Single Zebra 23. CB Clamp for Double Zebra 24. Isolator Clamp for Double Zebra

32 Layout Design 31 S. No. Particulars 25. ACSR Conductor ZEBRA 26. Tension Hardware for 7 / 4.00 mm GSS Earth wire / 4.00 mm. GSS Earth wire 28. P. G. Clamps for 7 / 4.00 mm. Earth wire c) 33 kv Side: 1. Transformer clamp for 52 kv Bushing for mm dia. Aluminium pipe (Expansion type) kv PT Clamp for mm dia. Aluminium pipe (Expansion type) kv PI Clamp for mm dia. Aluminium pipe (Expansion type) kv PI Clamp for mm dia. Aluminium pipe (Rigid type) E. Copper Control Cables (FRLS) / 16 core 2.5 sq. mm / 10 core 2.5 sq. mm core 6 sq. mm core 2.5 sq. mm core 4 sq. mm core 2.5 sq. mm core 2.5 sq. mm. F. LT Power Cable (Aluminium) 1. 3½ core 300 sq. mm. 2. 3½ core 95 sq. mm. G. Earthing Material 1. M. S. Round 40 mm. dia. 2. M. S. Flat mm. 3. G. I. Flat mm 4. M. S. Flat mm. 5. M. S. Flat 50 6 mm. H. Others / Miscellaneous 1. M. S. Channel mm. 2. Copper Earth Bond I. Fire Fighting Equipment 1. D. C. P. type 2. CO2 type

33 32 Construction Manual for Sub Stations

34 CHAPTER 3 SAFETY CLEARANCES 1.0 SAFETY CLEARANCES: 1.1 The various equipments and associated / required facilities have to be so arranged within the substation that specified minimum clearances are always available from the point of view of the system reliability and safety of operating personnel. These include the minimum clearances from live parts to earth, between live parts of adjacent phases and sectional clearance between live parts of adjacent circuits / bays. It must be ensured that sufficient clearance to ground is also available within the Sub Station so as to ensure safety of the personnel moving about within the switchyard. 1.2 The Table below gives the minimum values of clearances required for Sub Stations up to 765 kv: Nominal System Voltage (kv) Highest System Voltage (kv) Table for Minimum Clearance Lightning Impulse level (kvp) Switching Impulse Voltage (kvp) Minimum clearances $ (mm) Between Phase and Earth Between Phases Safety Clearances (mm) Ground Clearance* (mm) (Ph E) (Ph Ph) (Ph E) 2550 (Ph Ph) $ These values of air clearances are the minimum values dictated by electrical consideration and do not include any addition for construction tolerances, effect of short circuits, wind effects and safety of personnel, etc. * For safety of personnel moving in the switchyard with tools & plant. Notes: 1) The values in the Table above refer to an altitude not exceeding 1000 Meters and take into account the most unfavourable conditions which may result from the atmospheric pressure variation, temperature and moisture. A correction factor of 1.25 percent per 100 Meters is to be applied for increasing the air clearance for altitudes more than 1000 Meters and up to 3000 Meters. 2) Safety Clearance is the minimum clearance to be maintained in air between the live part of the equipment on one hand and earth or another piece of equipment or conductor (on which it is necessary to carry out the work) on the other.

35 34 Construction Manual for Sub Stations 1.3 As per Rule 64 (2) of the Indian Electricity Rules, 1956, the following safety working clearances shall be maintained for the bare conductors and live parts of any apparatus in any Sub Stations, excluding over head lines of HV and EHV installations: Table for Safety Working Clearance Sl. No. Nominal System Voltage (kv) Highest System Voltage (kv) Safety Working Clearance (mm) Notes: i) The above values are valid for altitudes not exceeding 1000 Meters. A correction factor of 1.25 percent per 100 Meters is to be applied for increasing the clearance for altitudes more than 1000 Meters and up to 3000 Meters. ii) The above safety working clearances are based on an insulator height of 2440 mm, which is the height of lowest point on the insulator (where it meets the earthed metals) from the ground. iii) Safety Working Clearance is the minimum clearance to be maintained in air between the live part of the equipment on one hand and earth or another piece of equipment or conductor (on which it is necessary to carry out the work) on the other.

36 CHAPTER - 4 EARTH MAT DESIGN 1.0 BASIC REQUIREMENT: 1.1 Provision of adequate earthing system in a Sub Station is extremely important for the safety of the operating personnel as well as for proper system operation and performance of the protective devices. The primary requirements of a good earthing system in a Sub Station are: a) The impedance to ground should be as low as possible but it should not exceed 1.0 (ONE) Ohm. b) The Step Potential, which is the maximum value of the potential difference possible of being shunted by a human body between two accessible points on the ground separated by the distance of one pace (which may be assumed to be one metre), should be within safe limits. c) Touch Potential, which is the maximum value of potential difference between a point on the ground and a point on an object likely to carry fault current such that the points can be touched by a person, should also be within safe limits. 1.2 To meet these requirements, an earthed system comprising of an earthing mat buried at a suitable depth below ground and supplemented with ground rods at suitable points is provided in the Sub Stations. 1.3 All the structures & equipments in the Sub Station are connected to the earthing mat so as to ensure that under fault conditions, none of these parts is at a potential higher than that of the earthing mat. 1.4 The neutral points of different voltage levels of transformers & reactors are separately earthed at two different points. Each of these earthed points should be interconnected with the station earthing mat. 2.0 MEASUREMENT OF EARTH RESISTIVITY: 2.1 Weather Conditions: The resistivity of earth varies over a wide range depending on its moisture content. It is, therefore, advisable to conduct earth resistivity tests during the dry season in order to get conservative results. 2.2 Test Procedure: Four electrodes are driven in to the earth at equal intervals s along a straight line in the chosen direction. The depth of the electrodes in the ground shall be of the order of 30 to 50 cm. The earth resistance Megger is placed on a steady and approximately level base, the link between terminals P1 and C1 is opened and the four electrodes are connected to the instrument terminals as shown in the figure. An appropriate range on the instrument, avoiding the two ends of the scale as far as possible, is then selected to obtain clear readings.

37 36 Construction Manual for Sub Stations The resistivity is calculated from the equation given below: ρ = 2 π sr where ρ = resistivity of soil in ohm metre, s = distance between two successive electrodes in metres, and R = Megger reading in ohms. 2.3 Testing Soil Uniformity It is desirable to get information about the horizontal and vertical variations in earth resistivity over the site under consideration. The horizontal and vertical variation may be detected by repeating the tests at atleast 6 (Six) different location with a number of different electrode spacings, increasing from 1 metre to 50 metres in the steps of 1, 5, 10, 15, 25 and 50 metres. A diagram showing the typical layout for earth resistivity measurement in 6 directions is enclosed These readings, along with a sketch showing the directions in which earth resistivity readings have been taken, shall be submitted to the Superintending Engineer (400 KV Design) for designing the earth mat.

38 Earth Mat Design An example of the format in which the earth resistivity readings are to be recorded is given below. Sl. No. Electrode Spacing Megger Reading in Ohms Direction M 2. 2 M 3. 5 M M M M M Direction M 2. 2 M 3. 5 M M M M M Similarly for Direction 3 to Direction 6. Earth Resistivity in Ohm metres Remarks

39 38 Construction Manual for Sub Stations

40 SECTION II ERECTION, TESTING & COMMISSIONING

41

42 CHAPTER - 1 GENERAL INSTRUCTIONS 1.0 Transportation and unloading of the sub station material and equipment at the location shall be done in a safe manner so that they are not damaged or misplaced. 2.0 All the material and equipment shall be checked as per Bill of Material (BOM). 3.0 All support insulators, circuit breaker poles, Transformer bushings and other fragile equipment shall preferably be handled carefully with cranes having suitable boom length and handling capacity. 4.0 Sling ropes, etc. should of sufficient strength to take the load of the equipment to be erected. They should be checked for breakages of strands before being used for the erection of equipments. 5.0 The slings should be of sufficient length to avoid any damage to insulator or other fragile equipments due to excessive swing, scratching by sling ropes, etc. 6.0 Mulmul cloth shall be used for cleaning the inside and outside of hollow insulators. 7.0 Erection of equipment shall be carried out as per and in the manner prescribed in the erection, testing and commissioning manual / instructions procedures of the manufacturer. 8.0 The services of the manufacturer s Engineer, wherever necessary, may be utilized for erection, testing and commissioning of sub station equipment. 9.0 Whenever the work is required to be got done at the existing GSS where the adjacent portions may be charged, effective earthing must be ensured for safety against induced voltages so that work can be carried out without any danger / hazard to the workmen Wherever it is necessary to avail shutdowns of energized circuits for carrying out any work, the Work In - Charge shall submit a requisition to the Engineer In - charge of the GSS stating the date, time and duration of the shutdown and the section / portion which is to be kept out of circuit during the shutdown The Work In Charge shall ensure that the portion of the switchyard under shutdown has been isolated and that effective earthing of the equipment / bus bar, on which work is to be carried out, has been done The Work In Charge shall ensure that the work is completed within the requisitioned time After completion of the erection work, all surplus material including bolts and nuts, templates, etc. shall be returned to the store. All unusable cut lengths of material such as conductor, earth wire, aluminium pipes, etc. shall not be treated as wastage and shall also be deposited in the store.

43 42 Construction Manual for Sub Stations

44 CHAPTER - 2 STRUCTURES 1.0 GENERAL INSTRUCTIONS: 1.1 The structure material shall be stacked member / item wise. 1.2 The following are required to be made available to the workmen for erection of sub station structures / beams and equipment structures: i) Drawings and bills of material of structures / beams / equipment structures. ii) Templates of structures. iii) T & P such as levelling instruments, tackles, spanners, jacks, winches, ropes, derrick, etc. 2.0 TYPE OF STRUCTURES: 2.1 The types of structures generally used at sub stations are given below: Sl. No. Name of Structure Type of Structure Height of Column / Height of Conductor (Meters) A. 400 kv Structures: 1. EHT1 Column with Peak 27.0 / EHB Beam 25.3 (Width) B. 220 kv Structures: 1. AT1 Column with Peak 20.0 / AT3 Column without Peak 15.0 / AT4 Column with Peak and 20.0 / 14.5 and 9.5 Beams at two levels for Bus Bar stringing 4. AT6 Column without Peak 10.0 / AT8 Column with Peak 15.0 / AB Beam 16.6 (Width) C. 132 kv Structures: 1. BT1 Column with Peak 16.0 / BT3 Column without Peak 12.0 / BT4 Column with Peak and 16.0 / 11.5 and 7.5 Beams at two levels for Bus Bar stringing 4. BT6 Column without Peak 8.0 / BT7 Column with Peak 12.0 / BB Beam 12.2 (Width) 7. P Peak Q Column 7.5 / R Extension GD Beam 10.0 (Width)

45 44 Construction Manual for Sub Stations Sl. No. Name of Structure Type of Structure Height of Column / Height of Conductor (Meters) D. 33 kv and 11 kv Structures: 1. X Peak Y Column 5.5 / Z Extension GF 5.4 Beam for 33 kv 5.4 (Width) 5. GF 4.6 Beam for 11 kv 4.6 (Width) E. Equipment Structures: 1. AO1 220 kv Isolators AO1 (T) 220 kv Tandem -- Isolators 3. AO3 220 kv CT AO4 220 kv CVT AO5 220 kv LA & 132 kv -- CT, CVT / PT, LA 6. BO1 132 kv Isolator BO1 (T) 132 kv Tandem -- Isolator 8. X kv & 11kV -- Isolators 9. X 15 (T) 33 kv & 11kV Tandem -- Isolators 10. CT Structure 33 kv & 11kV CT, PT PI Structure 220 kv, 132kV, 33 kv & 11 kv PI SETTING OF STUB / FOUNDATION BOLTS, LEVELLING AND GROUTING: 3.1 In case of structures with foundation bolts, the template, along with the foundation bolts tightened on it with nuts on both sides, shall be placed on the foundation. The length of the foundation bolts above the template shall be sufficient so that all parts of the base plate assembly of the structure, washers, nuts and lock nuts can be tightened fully and 2 3 threads are left above the lock nut. 3.2 The template is levelled & centered with reference to its location on the foundation. The foundation bolts shall thereafter be grouted ensuring that there is no displacement during the placing of the concrete and use of vibrator. 3.3 In case of structures with stubs, the template with stubs shall be placed on the foundation. In case of structures in which the lowest member is used as a stub, the assembled lower part of the structure is placed on the foundation. This is levelled & centered with reference to its location on the foundation. The stubs / lowest member shall thereafter be grouted ensuring that there is no displacement during the placing of the concrete and use of vibrator. 3.4 While levelling and centering the structure / template, the following points should be checked:

46 Structures 45 a) Level of structure / template with reference to the finished foundation level or the ground level. b) The level of the structure / template with reference to level of other similar structures. c) Distance of centre line of the structure from the center line of other structures or from a reference point. d) Centre to centre distance between structures, particularly structures which are to be connected together, for example, by a common beam. 4.0 ERECTION OF STRUCTURES: 4.1 Method of Erection: There are mainly three methods of erection of structures, which are as below: i) Ground assembly method. ii) Section method. iii) Built up method or Piecemeal method. 4.2 Ground Assembly Method: This method is used for erection of equipment structures and is the preferred method for erection of sub station structures when crane facility is available This method consists of assembling the structure on the ground and erecting it as a complete unit The complete structure is assembled in a horizontal position near its location. On sloping or uneven ground, suitable packing is provided in the lower level area before or during assembly, as required, to eliminate / minimize stress on the structure members After the assembly is complete, the structure is picked up from the ground with the help of a crane and set on its foundation. 4.3 Section Method: This method is used for large and heavy structures when crane facility is available A mobile crane is used for erecting the structures The two faces / sides of the complete structure are assembled on the ground and then erected. Alternatively, the two faces / sides of the major sections of the structure are assembled on the ground and the same are erected as units Each assembled side is then lifted clear of the ground with the crane and is lowered into position on its foundation or fitted on to stubs or foundation bolts which are already grouted. One side is held in place with props or rope guys while the other side is being erected. The two opposite sides are then connected together with cross members In case where the major sections of the structure have been assembled, the first face of the second section is erected. After the two opposite faces have been erected, the bracings on the other two sides are bolted up. The last lift raises the top of the structure. After the structure top is erected and all side bracings have been bolted up, all the guys are thrown off. 4.4 Built up method or Piecemeal method: This method is used for large and heavy structures when crane facility is not available This method consists of erecting the structure member by member. The structure members are kept on ground serially according to erection sequence so that they can be sent up conveniently.

47 46 Construction Manual for Sub Stations The erection progresses from the bottom upwards. The four main corner leg members of the first section of the structure are first erected The cross bracings of the first section are raised one by one and bolted to the already erected corner leg angles. If these have been assembled on the ground, then they are lifted up as a unit For assembling the second section of the structure, a derrick is placed on one of the corner legs. This derrick is used for raising parts of second section. The leg members and bracings of this section are then hoisted and assembled The derrick is then shifted to the corner leg members on the top of second section to raise the parts of third section of the structure in position for assembly. The derrick is thus moved up as the structure grows. This process is continued till the complete structure is erected. 5.0 ERECTION OF BEAMS: 5.1 The two faces of the beam are assembled on the ground. 5.2 Each face of the beam is raised with the help of crane or using derricks which are placed on the top of the already erected structures on both the sides of the beam. Single or multi way pulleys with polypropylene / steel ropes are used as per load requirement. The ends of the beam are connected to the column as per fixing arrangement provided on the columns. 5.3 The bracings of the upper and lower faces of the beam are then raised up and fitted. 6.0 The columns shall be truly vertical and the beams truly horizontal after erection. Measures taken to bring the column to verticality and beam to horizontality should not result in strain on the structure members so as to cause distortion / bending of the members. 7.0 The work of erection of beams on erected columns and erection of equipment on erected structures shall not be taken up until these have been checked for tightening of the bolts & nuts. 8.0 All bolted connections shall be well tightened using spring washers & then punched at three points on the circumference of the bolt.

48 CHAPTER - 3 BUS BAR & EARTH WIRE 1.0 GENERAL INSTRUCTIONS: 1.1 Care shall be taken during sagging operations so that no damage or deformation is caused to the structures. 1.2 The ends of the cut piece of conductor / earth wire shall be tied with at least two rounds of binding wire so that the strands do not open out. The tying of the binding wire shall be done such that the binding wire does not get tightened in the groove of the T Clamps or the PG (Parallel Groove) Clamps or the terminal connectors of the equipment. 1.3 Cut lengths of conductor and earth wire which are available as surplus / left over material from line works should preferably be used for stringing of bus bars & earth wire. Cut lengths of conductor and earth wire left after stringing of bus bars and earth wire can be used for jumpering work. 2.0 BUS BAR MATERIAL: 2.1 The bus bar material generally used in 400 kv, 220 kv & 132 kv substations is given below: Sl. No. Description Bus Bar and Jumper Material kv Main Bus mm dia. Aluminium pipe kv equipment interconnection mm dia. Aluminium pipe kv overhead bus & droppers in all bays. Twin ACSR Moose kv Main Bus Quadruple / Twin ACSR Zebra / Twin AAC Tarantulla kv Auxiliary Bus ACSR Zebra kv equipment interconnection Twin ACSR Zebra / Single ACSR Zebra kv overhead bus & droppers in all Twin ACSR Zebra / Single ACSR Zebra bays kv Main Bus ACSR Zebra kv Auxiliary Bus ACSR Panther kv equipment interconnection ACSR Zebra / ACSR Panther kv overhead bus & droppers in all bays. ACSR Panther kv Main Bus ACSR Zebra kv Auxiliary Bus ACSR Zebra kv equipment interconnection, overhead bus and droppers: (i) Bus coupler & transformer bay ACSR Zebra (ii) Feeder bay. ACSR Panther kv Main Bus Twin ACSR Zebra kv Auxiliary Bus ACSR Zebra kv equipment interconnection, overhead bus and droppers: (i) Transformer bay Twin ACSR Zebra / Single ACSR Zebra (ii) Bus coupler ACSR Zebra (iii) Feeder bay. ACSR Panther

49 48 Construction Manual for Sub Stations 3.0 STRINGING OF CONDUCTOR BUS BARS: 3.1 The conductor shall be handled with care to prevent scratches on it or damage to the strands of the conductor. When the conductor is to be taken from drums, small lengths can be unwound from the drum. For longer lengths, the conductor drum shall be placed on a turn table or jacked up on a suitable size of steel shaft. The conductor shall be paid out in a manner so that there are no scratches or damages caused to the conductor due to rubbing on the sides of the drum. 3.2 Disc insulators shall be cleaned and examined for any cracks / chipping, etc. Disc insulators having any hair cracks or chipping or defective glazing or any other defect shall not be used. The limits of the area of defective glazing are given by the following formulas. D F a) Single Glaze Defect = 0.5+ Sq. cm D F b) Total Glaze Defect = 1.0+ Sq. cm where, D = Diameter of the disc in cm. F = Creepage distance in cm. 3.3 The disc insulators shall be assembled on the ground to form the suspension and tension strings as given below. Suspension String Tension String System Voltage E & M Nos. Strength (kn) Nos kv (Anti fog type) kv at 400 kv GSS (Anti fog type) kv kv kv kv Sl. No. E & M Strength (kn) 3.4 After assembly of the strings, the mouth of the W clips / R clips shall be widened to prevent any inadvertent removal during service. 3.5 The suspension and tension hardware shall be assembled as per their respective drawings and the disc insulator string shall be fitted in the requisite portion of the hardware assembly. 3.6 For stringing of bus bars, the conductor shall be fixed and tightened in the clamp of the tension hardware on one side of the bus. Thereafter, the complete hardware assembly with the conductor shall be hoisted up and fixed on the beam at this end. Sagging arrangement shall be made on the other end of the bus and the conductor shall be tensioned. 3.7 Measurement of length of conductor required for the bus shall be made thereafter and the conductor shall be released so that it returns to the ground. The conductor shall be cut to the marked length after deducting the length of the tension hardware with insulators and fixed on the clamps of the tension hardware. The conductor along with tension hardware set shall then be again pulled up and connected to the beam.

50 Bus Bar & Earth Wire Equalizing of tension in the different sub conductors of the same phase and in the different phases shall be done, if required, to ensure equal sag of all the sub conductors or between phases of the bus section as well as that of adjacent or parallel sections. 3.9 The spacers shall be fitted on the twin and quadruple conductor bus bars at the spacing shown in the drawing. The spacers shall also be provided at points where jumpers are taken from the bus bar using T clamps and / or P. G. clamps. Spacers are not used at jumper points in case T Spacers are used for taking jumpers from multi conductor bus bars. 4.0 JUMPERING OF CONDUCTORS: The jumpers connecting different sections of the bus bars as well as those connecting equipment to bus bars shall be of Y type A typical diagram of Y type jumpering is given below For making Y type jumpers, the jumper conductor(s) shall be first connected to the bus bar conductor(s) using T Clamp / Spacer T Clamp which is suitable for clamping the respective conductors, i.e., bus bar conductor(s) and the jumper conductor(s). Thereafter, the bus bar conductor(s) shall be again connected with the jumper conductor(s) using properly curved & shaped Y conductor(s) and 2 nos. PG clamps as shown in the diagram above. 4.2 The jumpering between equipment shall be done with single / twin / quadruple conductors as per the terminal connectors provided on the equipment. 4.3 In case of jumpers for twin and quadruple conductors, the spacers shall also be fitted at a suitable spacing on the jumpers in order to maintain their shape. 4.4 JUMPERING OF BUS BARS: For jumpering of different sections of bus bars on the beam, the suspension hardware set along with disc insulators shall first be hoisted and fitted on the beam Conductor of approximately the length required for the jumper shall be cut and straightened so that kinks are removed. This shall be connected to the bus bar conductor on one side of the beam after taking into consideration the natural curve of the conductor.

CLAMPS CONNECTORS & EQUIPOTENTIAL RING

CLAMPS CONNECTORS & EQUIPOTENTIAL RING CLAMPS CONNECTORS & EQUIPOTENTIAL RING March 2015 Engineering Department WEST BENGAL STATE ELECTRICITY TRANSMISSION COMPANY LIMITED Regd. Office: VidyutBhawan, Block DJ, Sector-II, Bidhannagar, Kolkata

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values a) For 33/11 KV Power Transformer 2500 V megger is to be need. b) Power Transformer neutral Earthing is

More information

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables

GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables Engineering Department SEPTEMBER, 2007 GUIDELINES FOR UTILITY INSTALLATIONS Part 1 - Wire Lines and Communications Cables General Requirements This section applies to all public and private utilities,

More information

Schedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address

Schedule-4(A3) Page 1 of 5. Specification No.: JPL/KWTL/A3 (Package-A3) To: Bidder's Name & Address Specification : JPL/KWTL/A3 (Package-A3) Page 1 of 5 Tower Package (Package-A3) for 400 kv D/C (Quad Bundle) Karcham Wangtoo Abdullapur Line Part III associated with Karcham Wangtoo HEP Transmission System

More information

OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd

OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd OUTDOOR DISCONNECTORS A division of ACTOM (Pty) Ltd ACTOM OUTDOOR DISCONNECTORS Single Side Break (SSB) Disconnector 22-132 kv, 800-1 A, 25 ka - 3s Typical bearing assembly. Voltage range 11 kv to 132

More information

Requirements for the Attachment of Communication Cable Facilities on PPL Poles

Requirements for the Attachment of Communication Cable Facilities on PPL Poles Page 99 of 137 Requirements for the Attachment of Communication Cable Facilities on Replaces: URS-3002 URS-3004 URS-101C-304 A-157649 Page 100 of 137 Reference Notes for Drawings: General 1. The term communication

More information

SF 6 Gas Insulated Switchgear Type SDF for 170 kv

SF 6 Gas Insulated Switchgear Type SDF for 170 kv Three Phase Encapsulated Type SF 6 Gas Insulated Switchgear Type SDF for 170 kv 06B1-E-0001 With Trustworthy Technology, Structure Fuji Electric as a manufacturer of comprehensive substation equipment

More information

INSTRUCTIONS FOR CHAIN LINK INSTALLATION Chain Link fence & Posts Meshdirect.co.uk

INSTRUCTIONS FOR CHAIN LINK INSTALLATION Chain Link fence & Posts Meshdirect.co.uk INSTRUCTIONS FOR CHAIN LINK INSTALLATION Chain Link fence & Posts Meshdirect.co.uk This guide explains how to correctly install our chain link fencing and post system. The guide provides details of the

More information

Power Plant Electrical Distribution Systems

Power Plant Electrical Distribution Systems PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com

More information

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE

CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE CHAPTER VIII LINE PLANT SYSTEM COMMUNICATION THROUGH RE CABLE 8.1 SYSTEM 8.1.1 Armoured, screened underground cables are used for control communication in electrified areas to limit induction effect. 8.2

More information

ELECTRIC METERING COMMERCIAL & INDUSTRIAL

ELECTRIC METERING COMMERCIAL & INDUSTRIAL ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS

More information

I BEAM TRACK INSTALLATION

I BEAM TRACK INSTALLATION PDQ 0/700 FESTOON SYSTEM INSTALLATION AND MAINTENANCE INSTRUCTIONS INTRODUCTION The PDQ Festoon System was designed to run on one of three sizes of I-beams: S x., S8 x 8. and S x.. System trolleys must

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

SPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST

SPECIFICATIONS FOR TENDER NO: PSNR/SCP/VKS/E 1635 ANNEXURE I TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST TECHNICAL SPECIFICATIONS FOR LIGHTING HIGH MAST ANNEXURE I Sl.No. Description for BHEL Requirement Offered Deviation Scope of supply, erection and commissioning: 1 The scope of this specification covers

More information

TECHNICAL SPECIFICATION FOR HIGH TENSION LINE HARDWARE AND ACCESSORIES FOR ACSR PANTHER & WOLF CONDUCTOR

TECHNICAL SPECIFICATION FOR HIGH TENSION LINE HARDWARE AND ACCESSORIES FOR ACSR PANTHER & WOLF CONDUCTOR TECHNICAL SPECIFICATION FOR HIGH TENSION LINE HARDWARE AND ACCESSORIES FOR ACSR PANTHER & WOLF CONDUCTOR 1.1.0 SCOPE : This specification covers design, manufacture, testing at manufacture s works before

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet

ABB ! CAUTION. Type COQ Negative Sequence Generator Relay. (50/60 Hertz) 41-161J. Instruction Leaflet ABB Instruction Leaflet 41-161J Effective: May 1997 Supersedes I.L. 41-161H Dated July 1984 ( ) Denotes Change Since Previous Issue Type COQ Negative Sequence Generator Relay (50/60 Hertz)! CAUTION Before

More information

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS MIOSHA-STD-1313 (10/15) 6 Pages For further information Ph: 517-284-7740 www.michigan.gov/mioshastandards DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

More information

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

What are the basic electrical safety issues and remedies in solar photovoltaic installations? What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE By H P Gupta & D K Gupta DIFFERENT TYPES OF DAMAGES 1.Minor cracks 0.5 to 5 mm wide in load or non-load bearing walls 2.Major

More information

www.klmtechgroup.com TABLE OF CONTENT

www.klmtechgroup.com TABLE OF CONTENT Page : 1 of 13 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia ELECTIRAL GROUNDING TABLE OF CONTENT

More information

VCE VET ENGINEERING STUDIES

VCE VET ENGINEERING STUDIES Victorian Certificate of Education 2013 SUPERVISOR TO ATTACH PROCESSING LABEL HERE STUDENT NUMBER Letter Figures Words VCE VET ENGINEERING STUDIES Written examination Section Wednesday 20 November 2013

More information

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION

CONSTRUCTION STANDARD ELECTRIC OPERATIONS ORGANIZATION Page 1 of 11 ****This Standard Supercedes BECo CS2.13-2.3 & ComElectric OH Construction Manual, System Grounding Section, drawings CGND, GRDSUM, and C2**** 1.0 Bill of Materials GROUNDING AND BONDING POLE-MOUNTED

More information

About our Chairman cum- Managing Director

About our Chairman cum- Managing Director INTEGRATED GROUP Complete Range of Power Transmission and Distribution Equipments & Head office- SO 2-5, Second Floor, Amarjyoti Palace, Lokmat Square, Wardha Road, Nagpur-440012 Group E-mail ID : enquiry@integratedgroup.asia

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Owner s Manual Gantry Cranes

Owner s Manual Gantry Cranes Owner s Manual Gantry Cranes Fixed Height Gantry Crane MODEL NUMBER: SERIAL NUMBER: CAPACITY IN TONS: Telescoping Gantry Crane Bushman AvonTec 262-790-4200, 800338-7810, Fax 262-790-4200 www.bushmanavontec.com

More information

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance SPECIFICATION FOR LOW VOLTAGE SWITCHBOARD SEN I N D E X Description 10 STANDARD TECHNICAL REQUIREMENTS 11 Standards 12 General Operating Conditions 13 General Description Of Switchboard 131 Structure 132

More information

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act.

(2) Words and expressions used and not defined in these regulations but defined in the Act shall have the meaning assigned to them in the Act. (e) condition based maintenance means a set of maintenance actions based on continuous or frequent assessment of equipment condition, which is obtained from either of or a combination of embedded sensors,

More information

Aerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW

Aerial Fibre Optics. Complete One Stop Solution for Aerial Fibre Optics. OPGW Cable and Fittings for OPGW Complete One Stop Solution for OPGW Cable and Fittings for OPGW 53, Justice Chandra Madhav Road, Kolkata - 700020. India. Phone: 91-33-24748575 / 7565 Fax: 91-33-2476-1955 Email: sales@supremeco.com Website:

More information

GroundRod AC Substation Earthing Tutorial

GroundRod AC Substation Earthing Tutorial 1 GroundRod AC Substation Earthing Tutorial 1. Functions of an earthing system The two primary functions of a safe earthing system are: To ensure that a person who is in the vicinity of earthed facilities

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

Network Standard Advice No. 1420C 9/6/2011

Network Standard Advice No. 1420C 9/6/2011 Network Standard Advice No. 1420C 9/6/2011 TO: Customers, Service Providers and Ausgrid Staff. Advisory Note on Changes to the Use of 11kV Cable Types. Introduction This Network Standard Advice (NSA) provides

More information

Installation Manual. BYD Wall-mounted AC Charging Box

Installation Manual. BYD Wall-mounted AC Charging Box Installation Manual BYD Wall-mounted AC Charging Box BYD Wall-mounted AC Charging Box Installation Manual Version/Revision: A/0 Dedicated Service Commitment from BYD Auto Dear valuable customers: We are

More information

Fault location on power cables. Fault location on power cables

Fault location on power cables. Fault location on power cables Fault location on power cables Fault location on power cables Contents: 1. Introduction 2. Construction of power cables 3. Cable faults 01. Introduction Fault location on communication and power cables

More information

ATS Overhead Table Shelf System INSTRUCTION MANUAL

ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System INSTRUCTION MANUAL ATS Overhead Table Shelf System Instruction Manual Warranty Newport Corporation warrants this product to be free of defects in material and workmanship

More information

DELHI METRO RAIL CORPORATION LIMITED. (A Joint Venture of Govt. of India & GNCTD) MASS RAPID TRANSPORT SYSTEM PHASE III. Contract: - CE -16 VOLUME-6

DELHI METRO RAIL CORPORATION LIMITED. (A Joint Venture of Govt. of India & GNCTD) MASS RAPID TRANSPORT SYSTEM PHASE III. Contract: - CE -16 VOLUME-6 DELHI METRO RAIL CORPORATION LIMITED (A Joint Venture of Govt. of India & GNCTD) MASS RAPID TRANSPORT SYSTEM PHASE III TURNKEY PROJECT OF DESIGN, SUPPLY, LAYING, JOINTING, TESTING AND COMMISSIONING OF

More information

Uninterruptible Power Supply. 500 kva - 750 kva

Uninterruptible Power Supply. 500 kva - 750 kva 9 315 Uninterruptible Power Supply 500 kva - 750 kva T1 and T3 Installation Addendum 164201244-001 Rev. A ------------------------------------------------------------------------ ------------------------------------------------------------------------

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Transformer Deluge Systems

Transformer Deluge Systems Transformer Deluge Systems How Do Transformer Fires Ignite? Common causes of transformer failure: Weather-related events such as lightning Short circuits in electrical equipment The most common cause is

More information

INTER PLANT STANDARD STEEL INDUSTRY

INTER PLANT STANDARD STEEL INDUSTRY INTER PLANT STANDARD STEEL INDUSTRY CODE OF PRACTICE FOR REVAMPING OF EOT CRANES IPSS:3-02-014-03 IPSS Corresponding IS does not exist 0. FOREWORD 0.1 This Inter Plant Standard has been prepared by the

More information

AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System

AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System AJ s Technical Tips: Designing a Small Solar PV System Part IV; Selecting Wires for the System A little while back Simon Nyukuri of Kitale wrote to ask me about sizing wires and cables for solar PV systems.

More information

800 Communications Circuits

800 Communications Circuits ARTICLE 800 Communications Circuits INTRODUCTION TO ARTICLE 800 COMMUNICATIONS CIRCUITS This article has its roots in telephone technology. Consequently, it addresses telephone and related systems that

More information

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION COST DATA BOOK FOR RECOVERY OF EXPENSES & OTHER CHARGES FROM PROSPECTIVE CONSUMERS FOR TAKING ELECTRIC SUPPLY (APPLICABLE TO ALL DISTRIBUTION LICENSEES IN

More information

39HQ Airovision Air Handling Units

39HQ Airovision Air Handling Units 39HQ Airovision Air Handling Units Mounting instructions CONTENTS 1 - TRANSPORT AND LIFTING INSTRUCTIONS... 3 1.1 - General... 3 1.2 - Transport and storage... 3 1.3 - Roof edge protection during transport

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

Gulf Cable & Electrical Ind. Co.

Gulf Cable & Electrical Ind. Co. CONTENTS INTRODUCTION PRODUCT RANGE I PRODUCT DATA TABLES XLPE INSULATED 600/1000V CABLES Two Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 1 Three Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC 2 Four Core Cables CU/XLPE/PVC/LC/PVC/SWA/PVC

More information

Electrical Grounding. Appendix C

Electrical Grounding. Appendix C Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment

More information

POWER WAVE 455M/STT & (CE)

POWER WAVE 455M/STT & (CE) Illustration of Sub Assemblies Illustration of Sub Assemblies Illustration of Sub Assemblies Illustration of Sub Assemblies P-450 P-450 PARTS LIST FOR POWER WAVE 455M/STT & (CE) P-450-A P-450-A ILLUSTRATION

More information

INSTALLATION. General. Important Note. Design. Transport

INSTALLATION. General. Important Note. Design. Transport General The roof trusses you are about to install have been manufactured to precise engineering standards. To ensure that the trusses perform as designed, it is essential that they be handled, erected

More information

A product made in Australia. Insulated Conductor Rail ACTIV-8 PLUS

A product made in Australia. Insulated Conductor Rail ACTIV-8 PLUS A product made in Australia Insulated Conductor Rail ACTIV-8 PLUS ACTIV-8 PLUS The Industry Standard in Conductor Rails ACTIV-8 is the most widely used and stocked conductor rail in use in Australia. It

More information

UGVCL/SP/591/11KV HT AB CABLE

UGVCL/SP/591/11KV HT AB CABLE TECHNICAL SPECIFICATION FOR 11KV AERIAL BUNCHED CABLES FOR OVERHEAD LINES (CROSSED LINKED POLYTHENE DRY GAS CURED) 1. SCOPE This specification covers requirements of XLPE insulated, 11 KV Aerial Bunched

More information

Technical Guidance Note 287. Third-party guidance for working near National Grid Electricity Transmission equipment

Technical Guidance Note 287. Third-party guidance for working near National Grid Electricity Transmission equipment Technical Guidance Note 287 Third-party guidance for working near National Grid Electricity Transmission equipment 02 Purpose and scope... 3 Part 1 Electricity Transmission infrastructure... 4 Overhead

More information

Inverter / Charger Installation General Operations and AC and DC Connections

Inverter / Charger Installation General Operations and AC and DC Connections Inverter / Charger Installation General Operations and AC and DC Connections The Inverter is just one piece. Sometimes, a tendency is to mount the inverter and batteries, and make it work It is better

More information

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING

MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Title MV, HV AND EHV SWITCHGEAR TESTING & COMMISSIONING Training Duration 5 days Training Date MV, HV and EHV Switchgear Testing & Commissioning 5 20 24 Apr $3,750 Dubai, UAE In any of the 5 star

More information

Contractors Guide Central Inverter System Installation

Contractors Guide Central Inverter System Installation Contractors Guide Central Inverter System Installation Step By Step Procedures 2,200 Watt/VA 6 Step Installation 1. Mount Bottom Cabinet 2. Mount Top Cabinet 3. Install Batteries 4. Install Conduit 5.

More information

Guidelines for Earthquake Bracing of Residential Water Heaters

Guidelines for Earthquake Bracing of Residential Water Heaters Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)

More information

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK

Pressure monitoring equipment for oil-sf 6. bushings, type GOEK Pressure monitoring equipment for oil-sf 6 bushings, type GOEK Installation and maintenance guide 5693 827-6 en, Rev. 3, 2002-01-30 This document must not be copied without our written permission, and

More information

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

INSTALLATION AND OPERATING INSTRUCTIONS For Model GL1 Gate Locks

INSTALLATION AND OPERATING INSTRUCTIONS For Model GL1 Gate Locks Securitron Magnalock Corp. www.securitron.com ASSA ABLOY, the global leader Tel 800.624.5625 techsupport@securitron.com in door opening solutions INSTALLATION AND OPERATING INSTRUCTIONS For Model GL1 Gate

More information

INSTRUCTIONS THOROUGHLY BEFORE BEGINNING***************

INSTRUCTIONS THOROUGHLY BEFORE BEGINNING*************** Bill of Materials: RAC0012 Green Wing Aerodynamic Skirt Kit Item Part Number Description Quantity 1 RMC0218 Gen 2 Trailer Skirt Roadside 1 2 RMC0219 Gen 2 Trailer Skirt Curbside 1 3 RMC0041 Trailer Skirt

More information

Grounding of Electrical Systems NEW CODE: Grounding and Bonding

Grounding of Electrical Systems NEW CODE: Grounding and Bonding Grounding of Electrical Systems NEW CODE: Grounding and Bonding Presented By Scott Peele PE Grounding of Electrical Systems Outline Defining the Terms Why should I Ground? Types of Grounding Systems Separately

More information

ACTIV-8 PLUS Insulated Conductor Bar

ACTIV-8 PLUS Insulated Conductor Bar ACTIV-8 PLUS Insulated Conductor Bar A product made in Australia www.conductix.com.au ACTIV-8 PLUS ACTIV-8 is the most widely used and stocked conductor rail in use in Australia. It was designed by Conductix

More information

Front axle components, overview

Front axle components, overview just a test. Front axle components, overview 40-1 General Information Load bearing components and parts of the suspension must not be welded or straightened. Vehicles without drive axle must not be moved,

More information

1. The diagram below represents magnetic lines of force within a region of space.

1. The diagram below represents magnetic lines of force within a region of space. 1. The diagram below represents magnetic lines of force within a region of space. 4. In which diagram below is the magnetic flux density at point P greatest? (1) (3) (2) (4) The magnetic field is strongest

More information

SPECIFICATIONS FOR 220KV CAPACITOR VOLTAGE TRANSFORMER. The equipment is required for 220KV system. The system data is given as under:

SPECIFICATIONS FOR 220KV CAPACITOR VOLTAGE TRANSFORMER. The equipment is required for 220KV system. The system data is given as under: REQUIREMENT : The equipment offered shall be highly reliable suitable to operate satisfactorily in hot humid and polluted climate. The equipments offered shall work satisfactorily within temperature range

More information

Electrical Practices for Construction Work

Electrical Practices for Construction Work 1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in

More information

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING

TS 813 GROUNDING AND BONDING TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET GROUNDING TORONTO TRANSPORTATION January 2012 TS 813 GROUNDING AND BONDING TABLE OF CONTENTS 1. DRAWINGS TTD 813.001 TRAFFIC SIGNAL INSTALLATION AND CONTROLLER CABINET GROUNDING SYSTEM TTD 813.005 CONTROLLER CABINET

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

The electrical energy produced at the gen

The electrical energy produced at the gen 300 300 Principles of Power System CHAPTER CHAPTER 12 Distribution Systems General 12.1 Distribution System 12.2 Classification of Distribution Systems 12.3 A.C. Distribution 12.4 D.C. Distribution 12.5

More information

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13

STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 STEADYfast Stabilizer Installation Notes Fifth Wheel and Travel Trailers 11/23/13 (See Supplemental Instructions for trailers with heavy duty round footplates and/or Power Leveling Systems) PHONE SUPPORT

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Customer Substation Manual 08/05/02

Customer Substation Manual 08/05/02 Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

How To Plan Out An Array Of Solar Panels

How To Plan Out An Array Of Solar Panels CITY OF DOWNEY COMMUNITY DEVELOPMENT, BUILDING AND SAFETY 11111 Brookshire Avenue Downey, CA 90241 562.904.7142 (www.downeyca.org) B SECTION 01/01/2011 EFFECTIVE DATE PHOTOVOLTAIC 032 FORM NUMBER 2013

More information

EARTHING SYSTEM CALCULATION

EARTHING SYSTEM CALCULATION BAZIAN STEAL FACTORY S/S 132/11kV, 1x30/40MVA EARTHING SYSTEM CALCULATION Kurdistan Region Sulaimani May 2011 Bazian Steal Factory S/S 132/11kV, 1x30/40 MVA Contents: 1. Introduction... 3 2. List of references

More information

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN

CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN CHAPTER 5 PHOTOVOLTAIC SYSTEM DESIGN 5.1 Introduction So far in the development of this research, the focus has been to estimate the available insolation at a particular location on the earth s surface

More information

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1

City Of Ottawa High Voltage Substation Inspection, Maintenance Rev 00 2015 July 17 and Testing, ROPEC Page 1 2015 July 17 and Testing, ROPEC Page 1 PART 1 GENERAL 1.1. Scope.1 Equipment replacement and testing for a 44 kv 4.16kV/600V substation: a. Replacement of Insulators as indicated on the drawings in Appendix

More information

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc.

Grounding Practice at Data and Communications Centers. David Brender, P.E., CPQ National Program Manager Copper Development Association Inc. Grounding Practice at Data and Communications Centers David Brender, P.E., CPQ National Program Manager Copper Development Association Inc. Overview of This Presentation Elements of building wiring and

More information

Comparative study for cables and busbars

Comparative study for cables and busbars Comparative study for cables and busbars Preliminary considerations To compare the prices of two categories of product as different as traditional cables and busbars, it is necessary to make some preliminary

More information

GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT

GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT GUIDELINES TO INSTALL, OPERATE AND MAINTAIN HT CAPACITORS & IT S ASSOCIATED EQUIPMENT GENERAL: 1. The selection of switchgear for switching the capacitors should be done carefully. The circuit breaker

More information

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents

Federal Wage System Job Grading Standards for Electric Power Controlling, 5407. Table of Contents Federal Wage System Job Grading Standards for Electric Power Controlling, 5407 Table of Contents WORK COVERED... 2 WORK NOT COVERED...2 TITLES... 2 GRADE LEVELS... 2 SPECIAL ADDITIONAL RESPONSIBILITIES...

More information

Asset Management Plans

Asset Management Plans November 213 Introduction Table of Contents Page # ACS Buildings & Grounds 2 Purpose and Scope ACS Buildings & Seismic 3 The purpose of these ( Plans ) is to demonstrate how we intend to deliver on the

More information

Co-location Interconnect Power Panel (CIPP) Installation Guide

Co-location Interconnect Power Panel (CIPP) Installation Guide Co-location Interconnect Power Panel (CIPP) Installation Guide Document INS-97xxxxxxx This guide covers the following part numbers- Trimm 97xxxxxxx Series Table of Contents Section 1 - General Information...

More information

Earthing Guidance Notes

Earthing Guidance Notes Central Networks Earthing Manual Section E2 Earthing Guidance Notes Version: 2 Date of Issue: September 2007 Author: Nigel Johnson Job Title: Earthing Specialist Approver: John Simpson Job Title: Head

More information

Electrical Safety Tips. Help us keep you safe

Electrical Safety Tips. Help us keep you safe Electrical Safety Tips Help us keep you safe To help you stay safe when using electricity, ActewAGL has compiled these electrical safety tips. For natural gas safety tips please see ActewAGL s natural

More information

2100 AD 015 0009 Mirror Elevator Ball Nut Replacement Procedure

2100 AD 015 0009 Mirror Elevator Ball Nut Replacement Procedure 2100 AD 015 0009 Mirror Elevator Ball Nut Replacement Procedure Derek Guenther 1/28/2015 Rev. Purpose The purpose of this document is to describe the procedure necessary to replace one of the ball nuts

More information

Complete Solar Photovoltaics Steven Magee. Health and Safety

Complete Solar Photovoltaics Steven Magee. Health and Safety Health and Safety Health and safety around solar photovoltaic systems is very important. In the DC circuit you will find up to 600 volts in residential and commercial systems. In utility systems you may

More information

Cable/Conduit Conversion

Cable/Conduit Conversion Cable/Conduit Conversion Busway can be used in many applications where cable and conduit are more commonly used. The question arises, Why use busway instead of conventional cable and conduit? Benefits

More information

Switchgear and Metal-Enclosed Bus

Switchgear and Metal-Enclosed Bus Section 18 Switchgear and Metal-Enclosed Bus 180. SWITCHGEAR ASSEMBLIES 180A. General Requirements for All Switchgear. This rule covers general requirements for all switchgear. Examples of switchgear found

More information

Video Camera Installation Guide

Video Camera Installation Guide Video Camera Installation Guide The intent of this guide is to provide the information needed to complete or modify a video camera installation to avoid lightning and induced power surge damage. This guide

More information

WOLFFKRAN. 1 Schedule drawing. 1.1 Schedule drawing, WOLFF 6023.6clear. max. hook height above ground. Data WOLFF 6023.6clear

WOLFFKRAN. 1 Schedule drawing. 1.1 Schedule drawing, WOLFF 6023.6clear. max. hook height above ground. Data WOLFF 6023.6clear 1 Schedule drawing 1.1 Schedule drawing, WOLFF 6023.6clear [X] max. hook height above ground Data WOLFF 6023.6clear Item Crane type Design Type of setup Basis of calculation Payload torque Hoist winch

More information

HORIZONTAL INSTALLATION

HORIZONTAL INSTALLATION THERMO/SOLAR Žiar s.r.o. MANUAL FOR INSTALLATION PV SUPPORTING FRAMES HORIZONTAL INSTALLATION Technical alternation reserved A1410 1 12/2014 CONTENT ORD.NO. PAGE Mounting information 3 Mounting, flat roof

More information

RAY-MAX Integrated Solar Power Strip

RAY-MAX Integrated Solar Power Strip RAY-MAX Integrated Solar Power Strip 600008, 600009, 600010, 600208, 600209, 600210 Owner s Manual NEXTRONEX, INC. Revision Date: 10/27/14 Contents 1. Safety Instructions... 3 2. General Equipment Warnings...

More information