Wauwatosa Lateral Rehabilitation Pilot Project. Prepared for City of Wauwatosa Wauwatosa, WI January 18, 2013

Size: px
Start display at page:

Download "Wauwatosa Lateral Rehabilitation Pilot Project. Prepared for City of Wauwatosa Wauwatosa, WI January 18, 2013"

Transcription

1 Wauwatosa Lateral Rehabilitation Pilot Project Prepared for City of Wauwatosa Wauwatosa, WI January 18, 2013

2

3 Wauwatosa Lateral Rehabilitation Pilot Project Prepared for City of Wauwatosa, Wauwatosa, WI January 18, 2013 Job: Milwaukee Metropolitan Sewerage District Private Property Infiltration and Inflow Reduction Program Wauwatosa Technical Assistance 250 East Wisconsin Ave, Suite 1525 Milwaukee, Wisconsin 53202

4

5 Table of Contents List of Figures... v List of Tables... vi List of Abbreviations... vii Executive Summary... ES-1 1. Background and Objectives Background Sources of I/I Objectives Focus Areas Implementation Approach Summary of Work Completed N. 65 th St Eagle St Investigation Rainfall Simulation Soaker Hose Testing Soaker Hose and Dye Water Testing Flow Monitoring Direct observation V-notch Weir Sanitary Sewer Flow Estimation Downstream metering at FM6 on North Avenue Passive Monitoring Evaluation and Results N. 65 th St. Results Soaker Hose Testing Soaker Hose and Dye Water Testing Flow Monitoring Eagle St. Results Soaker Hose Testing Soaker Hose and Dye Water Testing Flow Monitoring Conclusions Pilot Project Flow Reduction Effectiveness Summary of Results by Objective Application of Results to Metershed iii

6 Table of Contents Wauwatosa Lateral Rehabilitation Pilot Project 5.4 Construction Costs Lessons Learned Construction Testing References... REF-1 Appendix A: Lateral Flow Rates... A iv

7 Wauwatosa Lateral Rehabilitation Pilot Project Table of Contents List of Figures Figure ES-1. I/I Effectiveness Evaluation Approach.... ES-3 Figure ES-2. Cumulative Lateral Flows, N 65 th St., Soaker Hose and Dye Water Test... ES-4 Figure ES-3. Cumulative Lateral Flows, Eagle St., Soaker Hose and Dye Water Test... ES-4 Figure ES-4. Comparison of MMSD Performance Standard to Pre- and Post-Rehabilitation Flows... ES-5 Figure 1-1. Project Location Figure 1-2. Public and Private Sources of I/I Figure Dye Water Testing Results: N. 65 th St. Project Area Figure Dye Water Testing Results: Eagle St. Project Area Figure 2-1. I/I Effectiveness Evaluation Approach Figure 2-2. Project Implementation Sequence: N. 65 th St Figure 2-3. Project Implementation - Eagle St Figure 3-1. Soaker Hose Test Schematic Figure 3-2. Soaker Hose and Dye Water Test Schematic Figure 3-3. Lateral Flow Entering Sanitary Sewer Main During Dye Water Testing, N. 65 th St., Round Figure 4-1. Cumulative Lateral Flows, N 65 th St., Soaker Hose Test Figure 4-2. Example of Lateral Flow Rate Reduction from Rounds 0 to 3 of Testing Figure 4-3. Cumulative Lateral Flows, N 65 th St., Soaker Hose and Dye Water Test Figure 4-4. V-notch Weir Flow Measurement, Round 1 Testing on the 2400 Block of N. 65 th St Figure 4-5. Cumulative Lateral Flows, Eagle St., Soaker Hose Test Figure 4-6. Cumulative Lateral Flows, Eagle St., Soaker Hose and Dye Water Test Figure 4-7. V-notch Weir Flow Measurement, Round A Testing on the 7800 to 7900 Block of Eagle St.4-11 Figure 5-1. Conceptual I/I components of a rehabilitated system Figure 5-2. MMSD Performance Standard Figure 5-3. Estimated Pre and Post Rehabilitation Components of Flow Figure 5-4. Pre-rehabilitation Metershed Average I/I Components Figure 5-5. Post-rehabilitation Metershed Average I/I Components (Estimated) Figure 5-6. Comparison of MMSD Performance Standard to Pre- and Post-Rehabilitation Flows v

8 Table of Contents Wauwatosa Lateral Rehabilitation Pilot Project List of Tables Table 2-1. Sequencing of Wauwatosa Lateral Rehabilitation Project Table 5-1. N. 65 th St. Average Lateral I/I Rate (gpm) by Phase Table 5-2. Eagle St. Average Lateral I/I Rate (gpm) by Phase vi

9 Wauwatosa Lateral Rehabilitation Pilot Project Table of Contents List of Abbreviations A-V CCTV cfs CIPP gpad gpm I/I MMSD PPIIR PVC ROW VCP Area-Velocity Closed Circuit Television cubic feet per second Cured-in-Place Pipe gallons per acre per day gallons per minute Infiltration and Inflow Milwaukee Metropolitan Sewerage District Private Property Infiltration and Inflow Reduction Polyvinyl Chloride (pipe material) Right-of-way Vitreous Clay Pipe vii

10

11 Executive Summary The City of Wauwatosa implemented a pilot project to determine the effectiveness of different lateral rehabilitation strategies to reduce the contribution of infiltration and inflow (I/I) from laterals. Specifically, the pilot project was undertaken to answer the following questions: 1. How effective is it to rehabilitate the leakiest laterals, rather than all of the laterals in a given focus area? 2. Can significant I/I reduction be achieved by rehabilitating only the portion of a lateral in the public right-of-way (ROW), rather than the entire lateral up to the house? 3. What amount of residual I/I will remain after lateral rehabilitation if foundation drains remain connected to the sanitary sewer system? These questions will help Wauwatosa to identify the best strategy for addressing I/I on private property and for utilizing funding assistance from MMSD for private property I/I reduction. The pilot project was conducted in two focus areas: N. 65 th St. between North Ave. and Clarke St., and Eagle St. between Wauwatosa Ave. and N. 80 th St. These areas were selected based on the results of the report Investigation and Analysis of Sanitary Sewersheds WA4001, WA4002, WA4035 [1], which indicated that these focus areas have some of the highest I/I rates in Wauwatosa. Rehabilitation was conducted in different phases for each of the focus areas. As seen in Figure ES-1, testing followed each rehabilitation phase to identify the effectiveness of each phase for reducing I/I. Testing consisted of flow monitoring and rainfall simulation. The rainfall simulation consisted of applying water to the ground surface over the lateral for each property for a period of two to eight hours using soaker hoses to simulate the effects of rainfall, as well as flooding the storm sewer with water that was dyed green. Figures ES-2 and ES-3, respectively, show the effectiveness of each phase of rehabilitation for N. 65 th St. and for Eagle St. for reducing I/I. After all of the phases of rehabilitation, the contribution of I/I from laterals was reduced by 75% from pre-rehabilitation conditions. I/I from the laterals was reduced from an average of 3 or 4 gpm per property to a residual amount of about 1 gpm per property. The results of the pilot project are site-specific and represent the 118 homes that were included in the pilot project; however, Wauwatosa conducted this pilot project in an attempt to identify a City-wide strategy for addressing I/I. As a result, the findings of the pilot project were put in perspective of the larger metershed area, which includes approximately 3200 homes in Wauwatosa. Flows were estimated for the metershed for pre-rehabilitation conditions as well as if all of the laterals and all of the public sanitary sewer mains and manholes in the entire metershed were rehabilitated (as in the pilot project). This estimate assumes that foundations drains remain connected to the sanitary system. Figure ES-4 shows the changes in flows, on a metershed basis, from the pre- to post-rehabilitation condition relative to the MMSD performance standard for peak flow. As seen in this figure, the rehabilitation provided a reduction in flows but additional reduction is needed to bring the flows down to what is required for the MMSD performance standard. The remaining flows consist of residual I/I from the laterals, the sanitary sewer mains, and the sanitary sewer manholes, as well as I/I from the foundation drains that are on most properties that were built before Foundation drains are a major contributor of I/I. ES-1

12 Executive Summary Wauwatosa Lateral Rehabilitation Pilot Project Answers to the pilot project objectives are as follows: 1. How effective is it to rehabilitate the leakiest laterals, rather than all of the laterals in a given focus area? Targeting the leakiest laterals provided an incremental reduction in I/I, but all laterals needed to be lined to achieve the greatest degree of reduction possible. 2. Can significant I/I reduction be achieved by rehabilitating only the portion of a lateral in the public ROW, rather than the entire lateral up to the house? Rehabilitating the lower section of all laterals in the public ROW appears to be effective at reducing the majority of the I/I from the laterals. Subsequent rehabilitation by extending the lining to the upper sections of laterals did not significantly reduce the average I/I into the laterals beyond approximately 1 gpm. This may be because the lateral lining in the ROW rehabilitates the lateral where it crosses under the storm sewer. 3. What amount of residual I/I will remain after lateral rehabilitation if foundation drains remain connected to the sanitary sewer system? Neither of the pilot projects evaluated the contribution of foundation drains to the total I/I. Therefore the significance of the remaining I/I from foundation drains is unknown; however, an analysis of flow monitoring data and other sources of information suggest that the I/I contribution from foundation drains is in the range of 2 to 3 gpm. If the average residual lateral I/I rates after rehabilitation are approximately 1 gpm, then the sum of private property sources (laterals and foundation drains) is approximately 3 to 4 gpm. Aside from the replacement of the sanitary sewer main and lateral connections on N. 65 th St., which occurred in 2011, the rest of the rehabilitation work was completed from May through October Excluding testing, the cost for a 60-foot long lateral lining ranged from $5,300 to $7,100, depending on the approach implemented. It is anticipated that the costs for future work will be less because the work will not be completed in increments. Future costs are estimated to be $4,700 to line the lateral just to the property line and $6,000 to line the lateral to the house. ES-2

13 Wauwatosa Lateral Rehabilitation Pilot Project Executive Summary North 65 th Street Eagle Street Initial Testing Initial Testing Public ROW Sewer Replacement + 4 lateral replacement Public ROW Sewer Main Lining + All Laterals Lined to Sidewalk Testing Testing Private Property Targeted Laterals Lined (from 4 replacement to house) Private Property Targeted Laterals Lined (from sidewalk to house) Testing Testing Private Property Remaining Laterals Lined (from 4 replacement to house) Private Property Remaining Laterals Lined (from sidewalk to house) Testing Testing Figure ES-1. I/I Effectiveness Evaluation Approach. ES-3

14 Executive Summary Wauwatosa Lateral Rehabilitation Pilot Project Cumulative Lateral Flow Rates (gallons per minute) Cumulative Lateral Flow Rates Soaker Hose and Dye Water Test Round 0 = pre rehabilitation Round 1 = new PVC main and lateral stubs Round 2 = targeted lateral liners from stubs to cleanouts Round 3 = remaining lateral liners Round 0 Round 1 Round 2 Round 3 Round 0 dye test revised Round 1 Round 2 Round 3 0 Clarke St MH 332 MH 499 MH 327 MH 325 MH 322 MH 320 MH 318 Wright St Addresses on N 65th St Figure ES-2. Cumulative Lateral Flows, N 65 th St., Soaker Hose and Dye Water Test Meinecke North Ave Round 0 Round A Round B Round C Cumulative Lateral Flow Rates Soaker Hose and Dye Water Test Cumulative Lateral Flow Rates (gallons per minute) Round 0 = Pre rehabilitation Round A = all laterals in lined in ROW and sanitary main lined Round B = targeted lateral liners from sidewalk to cleanouts Round C = remaining lateral liners from sidewalk to cleanouts No stormwater pipe in front of these properties Not tested in Round 0 Round 0 dye test revised Round A Round C Round B 0 N 80th St MH218 MH217 MH216 N 78th St MH214 Addresses on Eagle St, Wauwatosa MH212 MH211 MH210 Wauwatosa Ave Figure ES-3. Cumulative Lateral Flows, Eagle St., Soaker Hose and Dye Water Test ES-4

15 Wauwatosa Lateral Rehabilitation Pilot Project Executive Summary 7 Typical Flow per Property (gpm per property) MS0411 measured total 5.4 gpm Approx 4 gpm 5 year Recurrence Interval Peak Hourly Flow 2.8 gpm 1 0 Pre Rehab Estimated Post Rehab MMSD Perf Std Figure ES-4. Comparison of MMSD Performance Standard to Pre- and Post-Rehabilitation Flows ES-5

16

17 Section 1 Background and Objectives 1.1 Background In 2011, the City of Wauwatosa (Wauwatosa) conducted a study to identify system improvements to reduce basement backups in three sewersheds on the east side of Wauwatosa (Investigation and Analysis of Sanitary Sewersheds WA4001, WA4002, WA4035 [1]). These sewersheds, which are indicated in Figure 1-1, were identified by the Milwaukee Metropolitan Sewerage District (MMSD) as having excessive wet weather peak flows. The study included flow monitoring, hydraulic modeling, evaluation of condition assessment data, evaluation of infiltration and inflow (I/I) reduction, and the development of a sewer system improvement plan. A major conclusion of the study was that private sanitary sewer laterals and foundation drains connected to the sanitary laterals contribute a substantial portion of I/I in these basins. As a result, Wauwatosa elected to perform a pilot project to determine the effectiveness of different lateral rehabilitation strategies for reducing I/I. Wauwatosa received funding assistance from MMSD s Private Property Infiltration/Inflow Reduction (PPIIR) program to assist with the development, design, public involvement, investigations, and implementation of private property rehabilitation for this pilot program. 1-1

18 Section 1 Wauwatosa Lateral Rehabilitation Pilot Project Figure 1-1. Project Location 1-2

19 Wauwatosa Lateral Rehabilitation Pilot Project Section Sources of I/I Infiltration and Inflow (I/I) is flow that enters the sanitary sewer system that should not be there (e.g. groundwater infiltration, stormwater runoff). For the metershed as a whole, I/I that enters the sanitary sewer system is the cause of excessive flows. The sanitary sewer mains and manholes are public sources of I/I. Laterals, foundation drains, and direct inflow from roof drains if incorrectly connected to the sanitary system are private sources of I/I. (The pilot project areas did not have any connected roof drains.) Figure 1-2 shows the various sources of I/I that may be found on a single residential property and from a single sanitary sewer and manhole to which the residential property is tributary. (The sanitary sewage component of the flows is a small portion of the total flows and therefore the total flows are nearly entirely I/I.) Estimated I/I rates are given in terms of gallons per minute (gpm) for both public and private sources and are meant to show the relative contribution of each source to the overall total I/I of a large metershed area. Individual components for any one property may vary greatly. The I/I values were obtained by dividing the total flow of the metershed by the number of properties in the metershed so that the I/I can be expressed as gpm per property, even for the public sources of I/I. In Figure 1-2, the I/I is 5.4 gpm per property, which corresponds to a 5-year recurrence interval flow for metershed MS0411 averaged over all of the properties in the metershed. Foundation drains may be the single largest source of I/I, contributing almost half of the total I/I. Lateral I/I may be another large source of I/I, contributing perhaps a third of the total. Public sources of I/I may account for approximately 20% of the total. The percentages in the figure should be taken as conceptual estimates to help understand the general nature of the problem, rather than a fixed rule. Figure 1-2. Public and Private Sources of I/I 1-3

20 Section 1 Wauwatosa Lateral Rehabilitation Pilot Project 1.3 Objectives The focus of the pilot project was on the rehabilitation of laterals to reduce I/I. Foundation drains remained connected to the laterals. Therefore, one of the key objectives of this investigation was to determine how much I/I reduction could be achieved by lateral rehabilitation while the foundation drains remain connected. Other objectives of this study were related to the degree of lateral rehabilitation. Extensive dye water testing was conducted in the study area in 2010 and 2011 and this testing indicated that approximately one third of the laterals are the source of most of the leakage. In the dye water test, a number of properties showed no leakage and others had relatively small rates of leakage. Therefore, one of the objectives of this study was to investigate whether rehabilitation of targeted laterals with the highest I/I rates could achieve a significant overall reduction in leakage or if all laterals must be rehabilitated to avoid migration of clear water to the remaining, un-rehabilitated laterals. Another objective of this study was to investigate whether rehabilitation of the lateral in the public rightof-way (ROW) could achieve a significant reduction in leakage. The evaluation of this objective compared the leakage reduction for liners installed in the lower sections of laterals in the public ROW (from the sanitary sewer main to the sidewalk) to liners installed in the full length of the laterals (from the sanitary sewer main to the house). In summary, Wauwatosa used the pilot project to determine the effectiveness of different rehabilitation strategies to answer the following questions: 1. How effective is it to rehabilitate the leakiest laterals, rather than all of the laterals in a given focus area? 2. Can significant I/I reduction be achieved by rehabilitating only the portion of a lateral in the public ROW, rather than the entire lateral up to the house? 3. What amount of residual I/I will remain after lateral rehabilitation if foundation drains remain connected to the sanitary sewer system? 1.4 Focus Areas Two focus areas were included in the pilot project: N. 65 th St. and Eagle St. Three blocks on N. 65 th St. were selected as a focus area because, as seen in Figure 1-3, the dye water testing that was conducted in 2010 indicated that this area had high leakage rates and a storm sewer. In addition, Wauwatosa replaced the public sanitary sewer main and the connections of the laterals to the sanitary sewer main during the summer of The lateral connections were replaced with approximately 4 feet of polyvinyl chloride (PVC) pipe. Because of this recent work on the public system, the pilot project could begin immediately since all possible work had already been completed on the public system. In addition, because the first four feet of the laterals had been replaced, the first phase could evaluate the change in leakage response due to this recent work. Two blocks on Eagle Street were selected as a focus area because the dye water testing that occurred in 2011 indicated high leakage rates, the street had a storm sewer, and its sanitary sewer main was recommended for lining in the 2011 Sewer System Improvement Plan. Both project sites are near the upstream end of their respective collection system service areas. As a result, monitoring flow in the sanitary sewer mains immediately downstream of the project area would result in a relatively direct measure of the flow condition changes resulting from the project. 1-4

21 Wauwatosa Lateral Rehabilitation Pilot Project Section 1 Figure Dye Water Testing Results: N. 65 th St. Project Area 1-5

22 Section 1 Wauwatosa Lateral Rehabilitation Pilot Project Figure Dye Water Testing Results: Eagle St. Project Area 1-6

23 Section 2 Implementation 2.1 Approach The approach for implementing the pilot project was to first rehabilitate the sanitary sewer main and a portion of the lateral that was within the public ROW. Next, a targeted sub-group of private laterals was rehabilitated. This targeted sub-group (also referred to as the Priority 1 laterals) was selected based on observed leakage rate estimates from the dye water testing that was performed in 2010 in the N. 65 th St. focus area and in 2011 in the Eagle St. focus area. Those laterals that had an estimated leakage rate of 5 gallons per minute (gpm) or more were placed into the targeted laterals category. The last step was to rehabilitate the remaining laterals (Priority 2 laterals) within the focus areas. Each phase of rehabilitation was followed by testing, which included dye water testing and soaker hose testing. Figure 2-1 shows the overall sequencing of the project. North 65 th Street Eagle Street Initial Testing Initial Testing Public ROW Sewer Replacement + 4 lateral replacement Public ROW Sewer Main Lining + All Laterals Lined to Sidewalk Testing Testing Private Property Targeted Laterals Lined (from 4 replacement to house) Private Property Targeted Laterals Lined (from sidewalk to house) Testing Testing Private Property Remaining Laterals Lined (from 4 replacement to house) Private Property Remaining Laterals Lined (from sidewalk to house) Testing Testing Figure 2-1. I/I Effectiveness Evaluation Approach. 2-1

24 Section 2 Wauwatosa Lateral Rehabilitation Pilot Project 2.2 Summary of Work Completed Table 2-1 provides a summary of the construction and testing that was completed and the dates that it was completed. The lateral rehabilitation work for N. 65 th St. and Eagle St., which was covered under Wauwatosa Contract 12-99, occurred from June 2012 through October Laterals were lined with cured-in-place-pipe (CIPP) liners, with hydrophilic seals at each end of the liner to reduce leakage. Cleanouts were also installed under Contract All cleanouts were installed using VAC-A-TEE by LMK Enterprises. For this system, a 1- to 2-foot hole was hydro-excavated above the lateral for the cleanout. Next, a PVC connector (saddle) and riser pipe was bonded to the lateral. Finally a hole was cut into the lateral to establish a cleanout access point. The location of the cleanout was to be as close to the house as possible but in many cases the lateral could not be located because: 1. The lateral could not be televised fully because of roots, deposits, configuration, or conditions; 2. Landscaping and/or the placement of porches, sidewalks and driveways prevented a cleanout close to the house; 3. The homeowner requested a cleanout in a different location. Staff from Wauwatosa, BC, MMSD, and the contractor (Musson Bros.) reviewed and agreed upon the locations of the cleanouts prior to their installation. All but one of the homeowners within the Eagle St. focus area and all but five homeowners within the N. 65 th St. focus area (including one with a targeted lateral) agreed to participate in the program. In addition, one lateral for N. 65 th St. and one lateral for Eagle St. were not rehabilitated. The lateral at 2374 N. 65 th St. was replaced by the homeowner about three years ago and was not lined under Contract since it was deemed to be in good condition. The lateral for 7715 Eagle St. was not lined because a dye water test, performed by the City of Wauwatosa, confirmed that this lateral connects to the lateral from 7717 Eagle St., which then connects to the sanitary sewer main. The exact location of this connection is unknown and as a result, 7715 Eagle St. was not lined under Contract Table 2-1. Sequencing of Wauwatosa Lateral Rehabilitation Project Phase Focus Area N. 65th St. Eagle St. Total Number of Laterals in Focus Area Total Number of Laterals Rehabilitated Pre-Rehabilitation Testing Round 0: August/September 2010 Round 0: April 2011 Type of Sanitary Sewer Main and Manhole Rehabilitation Replacement CIPP Lining Dates of Sanitary Sewer Main Rehabilitation June 2010 May 2012 Type of Lateral Rehabilitation within ROW Replace first 1 to 4 feet with PVC CIPP Lining of first approx. 30 feet (to public ROW line) Dates of ROW Lateral Rehabilitation June 2010 July 23 to Aug. 2, 2012 Dates of Cleanout Installation June 25 to Aug.18, 2012 June 15 to July 13, 2012 Public Property Rehabilitation Effectiveness Testing Round 1: June 25-27, 2012 Round A: Aug. 8-9, 2012 Number of Targeted (Priority 1) Laterals Rehabilitated

25 Wauwatosa Lateral Rehabilitation Pilot Project Section 2 Table 2-1. Sequencing of Wauwatosa Lateral Rehabilitation Project Phase Focus Area N. 65th St. Eagle St. Percentage of Targeted Laterals out of Total Number of Focus Area Laterals 32% 43% Type of Targeted Laterals Rehabilitation CIPP Lining from PVC connection stub to house (approx.) CIPP Lining from ROW to house (approx) Dates of Targeted Laterals Rehabilitation Aug. 20 to Sept. 5, 2012 Aug. 9 to Aug. 31, 2012 Targeted Laterals Rehabilitation Effectiveness Testing Round 2: Sept. 6-10, 2012 Round B: Sept. 4-5, 2012 Number of Remaining (Priority 2) Laterals Rehabilitated Percentage of Remaining Laterals out of Total Number of Focus Area Laterals 61% 52% Type of Remaining (Priority 2) Laterals Rehabilitation CIPP Lining from PVC connection to house (approx) CIPP Lining from ROW to house (approx) Dates of Remaining Laterals Rehabilitation Sept. 11 to Oct. 12, 2012 Sept. 6 to Sept.27, Remaining Laterals Rehabilitation Effectiveness Testing Round 3: Oct , 2012 Round C: Sept , One property (7835 Eagle St.) was lined after the last round of soaker hose and dye water testing for that focus area. The lateral for this property had another pipe connected to the lateral and it took additional time to investigate whether this pipe was active and to work with the homeowner to decide on an appropriate lining approach. Ultimately the homeowner decided to have the lateral lined completely through, therefore closing off the connection of the second pipe to the lateral N. 65 th St. Figure 2-2 provides a visual of the work and testing that was completed for N. 65 th St. and the order in which it was completed. The process was as follows: In 2011, the old clay sanitary sewer main was replaced with a new PVC pipe. Connections of the laterals to the sanitary sewer main were also replaced with PVC. The new lateral connections were generally about 4-feet long; however, some of the PVC pipes were only 1- to 2-feet long. The segments of new lateral were not sufficiently long to cross under the storm sewer. New manholes were also constructed at this time. All of the rehabilitation was within the public ROW and work was completed on all of the laterals within the N. 65 th St. focus area. Round 1 of soaker hose and dye water testing was conducted in June 2012 to test the effectiveness of rehabilitating public property infrastructure for reducing I/I. Following Round 1 testing, targeted laterals were CIPP-lined from the PVC lateral connection pipe to the cleanout or house, depending on the cleanout s location. Hydrophilic seals were installed at both the upstream and downstream ends of the liner to reduce the chance of leakage at these connections. Round 2 of soaker hose and dye water testing occurred in late September 2012 and observed the effectiveness of rehabilitating the targeted laterals. Following Round 2 testing, the remaining laterals within the focus area were CIPP-lined from the PVC lateral connection pipe to the cleanout or house. Round 3 of soaker hose and dye water testing occurred in mid-october 2012 and observed the effectiveness of rehabilitating all of the remaining laterals within the N. 65 th St. focus area that were included in the program. In most cases where the cleanout was not sufficiently close to the house (as determined by Wauwatosa, BC, and MMSD staff), the contractor installed the liner from the sanitary sewer main to the house, lining 2-3

26 Section 2 Wauwatosa Lateral Rehabilitation Pilot Project through the cleanout. Lining from the sewer main was not anticipated for N. 65 th St. so the contractor used a brim connection liner to stabilize the liner at the sanitary sewer main and to keep the pressures down during liner installation. Laterals with cleanouts sufficiently close to the house were lined from the cleanouts to the sanitary sewer main. All lined laterals had hydrophilic seals installed at each end of the lateral liners, to help prevent leaking at the connection points between the existing laterals and the new liners. The PVC lateral connection for the sanitary sewer main was shorter than anticipated in some cases. This, combined with numerous bends in the lateral connection pipes, contributed to the following laterals having liners that were short of the PVC lateral connection pipe and therefore not meeting specifications: 2329 N. 65th (missed PVC overlap by 6-inches) 2434 N. 65 th (missed PVC overlap by 6-inches) 2446 N. 65th (missed PVC overlap by 1-inch) 2503/2505 N. 65 th (missed PVC overlap by 6-inches) 2523 N. 65 th (missed PVC overlap by 6-inches) BC reviewed videos of these laterals from when they were televised during the last round of soaker hose and dye water testing, to determine whether the laterals were leaking. There appeared to be no issues with 2446, 2503/2505, and 2523 N. 65 th St., but the review of 2329 and 2434 N. 65 th St. was inconclusive. Wauwatosa plans to have all five of the laterals with short liners air pressure tested; if the lateral fails the air pressure test, then the first five feet of the lateral and the lateral connection to the sanitary sewer main will be grouted. Figure 2-2. Project Implementation Sequence: N. 65 th St. Note: cleanout locations varied by property. 2-4

Wauwatosa Lateral Rehabilitation Pilot Project. CSWEA Annual Meeting Madison, WI May 15, 2013

Wauwatosa Lateral Rehabilitation Pilot Project. CSWEA Annual Meeting Madison, WI May 15, 2013 Wauwatosa Lateral Rehabilitation Pilot Project CSWEA Annual Meeting Madison, WI May 15, 2013 Overview Background Objectives Work Completed Testing Evaluation Conclusions 2 Milwaukee Metropolitan Sewerage

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

Quantifying Inflow and Infiltration via Dyed Water Flooding

Quantifying Inflow and Infiltration via Dyed Water Flooding Quantifying Inflow and Infiltration via Dyed Water Flooding Prepared by Anna Kesler, E.I.T. Catherine Morley, P.E. Overview Historical background to City of Elmhurst I/I issues What Is Dye Flooding? What

More information

Review of Footing Drain Disconnection Projects

Review of Footing Drain Disconnection Projects Wastewater Master Plan DWSD Project No. CS-1314 Review of Footing Drain Disconnection Projects Technical Memorandum Original Date: August 8 2002 Revision Date: September 2003 Author: CDM Table of Contents

More information

A CASE STUDY IN INFILTRATION REDUCTION THROUGH TRENCHLESS TECHNOLOGY

A CASE STUDY IN INFILTRATION REDUCTION THROUGH TRENCHLESS TECHNOLOGY A CASE STUDY IN INFILTRATION REDUCTION THROUGH TRENCHLESS TECHNOLOGY SOUTH PALOS TOWNSHIP SANITARY DISTRICT COOK COUNTY, ILLINOIS March 1999 By: Aaron E. Fundich, P.E. Robinson Engineering, Ltd. and Larry

More information

SANITARY SEWER BACKUP. Causes & Prevention

SANITARY SEWER BACKUP. Causes & Prevention SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides

More information

Presented by: Scott E. Belz Project Manager- URS Corporation Robert P. Kelly, P.E. Director of Engineering-City of Westlake James J. Smolik, P.E.

Presented by: Scott E. Belz Project Manager- URS Corporation Robert P. Kelly, P.E. Director of Engineering-City of Westlake James J. Smolik, P.E. Presented by: Scott E. Belz Project Manager- URS Corporation Robert P. Kelly, P.E. Director of Engineering-City of Westlake James J. Smolik, P.E. Engineer-City of Westlake City of Westlake Facts Founded

More information

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance

More information

PPII Public Outreach Lessons Learned Private Property Infiltration and Inflow Reduction Program. Thomas M. Grisa, P.E.

PPII Public Outreach Lessons Learned Private Property Infiltration and Inflow Reduction Program. Thomas M. Grisa, P.E. PPII Public Outreach Lessons Learned Private Property Infiltration and Inflow Reduction Program Thomas M. Grisa, P.E. Meeting Overview Welcome and Introductions Tom Grisa, Director of Public Works Overview

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

Sanitary Sewer Smoke Testing

Sanitary Sewer Smoke Testing Sanitary Sewer Smoke Testing Beginning March 31, 2014 The City of Brunswick will be conducting smoke testing on the City s sanitary sewer system beginning March 31, 2014. Smoke testing will occur over

More information

Kansas City s Overflow Control Program

Kansas City s Overflow Control Program Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater

More information

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short

More information

FY15 Gravity Sewer and Manhole Rehabilitation

FY15 Gravity Sewer and Manhole Rehabilitation Contract Drawings For FY15 Gravity Sewer and Manhole Rehabilitation TRAVELERS REST TAYLORS Frazier Project No. -030 BASIN 850 Greenville, South Carolina April 2015 BASIN 700A GREENVILLE BASIN 700B FIVE

More information

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Village of Shorewood, Wisconsin SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER Prepared By: Thomas A. Zoulek, P.E., LEED A.P. Vice President Mid City Plumbing & Heating

More information

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems Please see the DEFINITIONS of terms at the end of this section. If you have any questions about these definitions, do not understand a question,

More information

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience Robert W. Carr 1 * and Stuart G. Walesh 2 1 Water Resources Modeling, LLC, 4144 S. Lipton Ave,

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

Beechmont Park Project

Beechmont Park Project Beechmont Park Project Foundation Drain Project Why pre -1972 homes are chosen in your neighborhood? Results of pilot study in your area showed the majority of homes built prior to 1972 within your neighborhood

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods Extreme Wet Weather in Brookfield How to Keep Your Basement Dry During Heavy Rains and Floods Relating Stormwater Drainage to Sewer Backups Brookfield has two separate sewer systems Storm sewer system

More information

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS

CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS CITY OF COLFAX REQUIREMENTS AND STANDARDS FOR CLOSED CIRCUIT TELEVISION SEWER LATERAL INSPECTIONS PURPOSE AND SCOPE This document provides information and sets forth standards for sewer lateral closed

More information

Sewer Rehabilitation Design Requirements

Sewer Rehabilitation Design Requirements Sanitary Sewer Overflow (SSO) Control and Wastewater Facilities Program Sewer Rehabilitation Design Requirements City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared

More information

OVER-HEAD SEWER ASSISTANCE GRANT

OVER-HEAD SEWER ASSISTANCE GRANT OVER-HEAD SEWER ASSISTANCE GRANT The Village of North Aurora has a vested interest in the proper operation of the North Aurora sanitary system. Understanding that some residential users of the sanitary

More information

Guidelines for Performing Infiltration/Inflow Analyses And Sewer System Evaluation Survey

Guidelines for Performing Infiltration/Inflow Analyses And Sewer System Evaluation Survey COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF ENVIRONMENTAL AFFAIRS DEPARTMENT OF ENVIRONMENTAL PROTECTION ONE WINTER STREET, BOSTON, MA 02108 617-292-5500 Guidelines for Performing Infiltration/Inflow

More information

ORDINANCE NO. 15 BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

ORDINANCE NO. 15 BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY: ORDINANCE NO. 15 Amending Chapter 60 of the Code of Ordinances of Kansas City, Missouri, entitled Sewers and Sewage Disposal by adding Sections 60-349 through 60-360; and establishing an effective date.

More information

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E.

MIAMI-DADE LATERAL PILOT PROGRAM. James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. MIAMI-DADE LATERAL PILOT PROGRAM James T. Cowgill, P.E. Rodney J. Lovett Franklin Torrealba, P.E. Hazen and Sawyer, P.C. 4000 Hollywood Boulevard Hollywood, FL 33021 ABSTRACT Since 1994 the Miami-Dade

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

Lansdowne Stormwater UPDATE

Lansdowne Stormwater UPDATE Lansdowne Stormwater UPDATE August 22, 2012 Ann Arbor Footing Drain Disconnection Stormwater Review Presentation Agenda Welcome and introductions Background on stormwater and sanitary sewer issues Footing

More information

CITY OF DULUTH PRIVATE SEWER SERVICE GRANT PROGRAM PROGRAM GUIDELINES

CITY OF DULUTH PRIVATE SEWER SERVICE GRANT PROGRAM PROGRAM GUIDELINES CITY OF DULUTH PRIVATE SEWER SERVICE GRANT PROGRAM PROGRAM GUIDELINES Policy and Statement of Purpose The City of Duluth has existed as a city on the shoreline of Lake Superior for more than 100 years

More information

VERIFICATION TESTING GUIDELINES FOR CONTRACTORS

VERIFICATION TESTING GUIDELINES FOR CONTRACTORS Public Works Department Engineering Division VERIFICATION TESTING GUIDELINES FOR CONTRACTORS CITY OF BERKELEY PRIVATE SEWER LATERAL ORDINANCE BMC Chapter 17.24 Effective November 3, 2014 A consent decree

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

Working together to improve beach water quality. Fixing our. public and private. sewers

Working together to improve beach water quality. Fixing our. public and private. sewers Working together to improve beach water quality Fixing our public and private sewers May 2004 FIND FIX DECIDE Narrow Neck Beach on a summer day As part of Project CARE, our long-term project to improve

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

Weeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario

Weeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario Weeping Tile Disconnection to Reduce the Impact of Basement Flooding London, Ontario September 19, 2013 Kyle Chambers, P.Eng. City of London Environmental and Engineering Services Department Today s presentation

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

BASEMENT FLOODING. Prevention Guide for. Homeowners

BASEMENT FLOODING. Prevention Guide for. Homeowners BASEMENT FLOODING Prevention Guide for Homeowners 1 Did You Know? Floods are the most common hazards in Canada. Water damage is a common cause of loss for homeowner insurance. A heavy rainfall can result

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing

CCTV INSPECTION OF SEWER LINES. A. Section 02730 Sanitary Gravity Sewer Lines. B. Section 02731 Sanitary Gravity Sewer Line Testing CCTV INSPECTION OF SEWER LINES PART 1 GENERAL 1.1 SECTION INCLUDES A. CCTV Inspections 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02731 Sanitary Gravity Sewer Line Testing

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

89 Avenue Road GP Ltd. Functional Servicing and Stormwater Management Report for 89 Avenue Road Re-Development City of Toronto

89 Avenue Road GP Ltd. Functional Servicing and Stormwater Management Report for 89 Avenue Road Re-Development City of Toronto 89 Avenue Road GP Ltd. Functional Servicing and Stormwater Management Report for 89 Avenue Road Re-Development City of Toronto Prepared By: R.J. Burnside & Associates Limited 6990 Creditview Road, Unit

More information

See Appendix A for additional information, or contact ASTM directly.

See Appendix A for additional information, or contact ASTM directly. DEFINITIONS Wherever used in these specification guidelines, the following words and terms have the meanings indicated. AREAWAY: A paved surface, serving as an entry area to a basement or subsurface portion

More information

JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012

JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012 JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN Presentation to Insurance Companies 19 January 2012 Topics of Discussion Investigation Levels of Service Cause of Flooding Analysis Undertaken

More information

Sanitary Sewer Overflow (SSO) Incident Report Form

Sanitary Sewer Overflow (SSO) Incident Report Form Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category

More information

Section 2651 Television Inspection

Section 2651 Television Inspection Section 2651 Television Inspection PART 1: General 1.1 Description Provide all labor, materials, tools, equipment and incidentals as shown, specified, and required to perform television (TV) inspection

More information

Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No.

Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No. Town of Essex Basement Flooding Study Town of Essex NE Lagoon Service Area Pumping Station No. 4 Essex Plant Service Area Wastewater Pumped To NE Lagoons (Treatment Plant No. 2) Essex Treatment Plant (Treatment

More information

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans

More information

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1001 SOUTH LEECHBURG HILL LEECHBURG, PA 15656 Phone: 724-845-9355 Fax: 724-845-1186 SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS 1. General

More information

ELIMINATE STORM WATER FROM ENTERING SANITARY SEWER SYSTEMS

ELIMINATE STORM WATER FROM ENTERING SANITARY SEWER SYSTEMS (408) 761 5882 http://www.sewerlock.net ELIMINATE STORM WATER FROM ENTERING SANITARY SEWER SYSTEMS 1. `The United States and various State Environmental Protection Agency regulations require elimination

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

SANITARY GRAVITY SEWER LINE TESTING. B. Section 02732 CCTV Inspection of Gravity Sewer Lines

SANITARY GRAVITY SEWER LINE TESTING. B. Section 02732 CCTV Inspection of Gravity Sewer Lines PART 1 GENERAL 1.1 SECTION INCLUDES A. Low Pressure Air Test B. Deflection Test 1.2 RELATED SECTIONS A. Section 02730 Sanitary Gravity Sewer Lines B. Section 02732 CCTV Inspection of Gravity Sewer Lines

More information

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect

More information

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES

2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 2016 - SECTION 25 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER LINES 25.1 GENERAL This section of the specifications shall form a part of the contract documents and should be read in conjunction with

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

1. General...1. 1.1 General Requirements... 1. 2. Gravity Sanitary Sewer Testing Requirements...3

1. General...1. 1.1 General Requirements... 1. 2. Gravity Sanitary Sewer Testing Requirements...3 Table of Contents 1. General...1 1.1 General Requirements... 1 2. Gravity Sanitary Sewer Testing Requirements...3 2.1 General Requirements... 3 2.2 Test Method & Sequence... 3 2.3 Exfiltration Test - Low

More information

REPORT TITLE: TERM OF COUNCIL PRIORITY NO. 6 - ENHANCE INTEGRITY OF WASTEWATER COLLECTION SYSTEM INCLUDING FLOOD REMEDIATION PROGRAM

REPORT TITLE: TERM OF COUNCIL PRIORITY NO. 6 - ENHANCE INTEGRITY OF WASTEWATER COLLECTION SYSTEM INCLUDING FLOOD REMEDIATION PROGRAM J Wokking foh y or REPORT Meeting Date: November 28,2013 Regional Council DATE: October 22,201 3 REPORT TITLE: TERM OF COUNCIL PRIORITY NO. 6 - ENHANCE INTEGRITY OF WASTEWATER COLLECTION SYSTEM INCLUDING

More information

VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES

VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES SEWER BACK-UP POLICY General Sewer back-ups are an unfortunate, but common problem in older communities. A sewer back-up can create a health or

More information

Downspout to storm sewer. Leaky laterals

Downspout to storm sewer. Leaky laterals Flooded street Surface water through MH top Blocked street catch basin Cracked MH or sewer Property line Downspout to storm sewer BREATHERS Leaky laterals Weeping Tile to sanitary or storm sewer BASEMENT

More information

City of Largo Environmental Services Department Environmental Control Program 5100 150 th Avenue North Clearwater, FL 33760 Phone: (727) 518-3076

City of Largo Environmental Services Department Environmental Control Program 5100 150 th Avenue North Clearwater, FL 33760 Phone: (727) 518-3076 POCTS # (To be assigned by City of Largo Environmental Control.) City of Largo Environmental Services Department Environmental Control Program 5100 150 th Avenue rth Clearwater, FL 33760 Phone: (727) 518-3076

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1

CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1 CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm

More information

Module 9: Basics of Pumps and Hydraulics Instructor Guide

Module 9: Basics of Pumps and Hydraulics Instructor Guide Module 9: Basics of Pumps and Hydraulics Instructor Guide Activities for Unit 1 Basic Hydraulics Activity 1.1: Convert 45 psi to feet of head. 45 psis x 1 ft. = 103.8 ft 0.433 psi Activity 1.2: Determine

More information

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority

More information

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area. 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall CHELTENHAM TOWNSHIP SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall 1 SANITARY SEWER UPDATE 1. Overview a. The Problem b. Pennsylvania Department of Environmental Protection

More information

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING 812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,

More information

Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010

Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010 Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010 A. Purpose The purpose of this policy is to explain how and why sewer or stormwater backups occur, what to do in the event a homeowner

More information

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS Article I General Provisions Section 22-101 Definitions Section 22-102 Supervision of Sewer System Section 22-103 Inspections Section 22-104 Use of Public

More information

Corporate Report. Report from Transportation and Environmental Services, Environmental Services

Corporate Report. Report from Transportation and Environmental Services, Environmental Services Corporate Report Report from Transportation and Environmental Services, Environmental Services Date of Report: January 9, 2015 Date of Meeting: January 26, 2015 Report Number: TES-020-2015 File: 68.81.4

More information

Dry Weather Flow from Footing Drains and Service Connections

Dry Weather Flow from Footing Drains and Service Connections Wastewater Master Plan DWSD Project No. CS-1314 Dry Weather Flow from Footing Drains and Service Connections Technical Memorandum Original Date: May 2, 2002 Revision Date: September 2003 Author: CDM Table

More information

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM Stadium Reconstruction EIR Appendices \ AECOM Technical Services, Inc 401 West A Street Suite 1200 San Diego, CA 92101 www.aecom.com 619-610-7600 tel 619-610-7601

More information

City of Hillsboro Inflow and Infiltration Elimination Program

City of Hillsboro Inflow and Infiltration Elimination Program City of Hillsboro Inflow and Infiltration Elimination Program Because of continuing problems with overloaded sanitary sewers, the City of Hillsboro is inspecting the sewer system in your neighborhood.

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD 21.01 SCOPE: It is the intent of the Specification to define the approved methods and materials

More information

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R

CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R CCTV PIPE INSPECTION AND EVALUATION For RUNWAY 17L-35R At ST. PETERSBURG CLEARWATER INTERNATIONAL AIRPORT February 2011 CCTV PIPE INSPECTION AND EVALUATION RUNWAY 17L-35R ST. PETERSBURG CLEARWATER INTERNATIONAL

More information

Mitigating Basement Backups

Mitigating Basement Backups Mitigating Basement Backups Avon Lake Municipal Utilities 201 Miller Road Avon Lake, OH 44012 Tel: 440-933-6226 Emergency: 440-933-3229 www.avonlakewater.org April 28, 2011 This document was originally

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

BMP #: Dry Wells / French Drains

BMP #: Dry Wells / French Drains Structural BMP Criteria BMP #: Dry Wells / French Drains A Dry Well, or French Drain, is a variation on an Infiltration Trench that is designed to temporarily stores and infiltrate rooftop runoff. Key

More information

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan

Monterey Regional Water Pollution Control Agency. Sewer System Management Plan Monterey Regional Water Pollution Control Agency Sewer System Management Plan March 31, 2013 Sewer System Management Plan Introduction I. Goals II. Organization III. Legal Authority IV. Operation and Maintenance

More information

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion

TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion TOWN OF SURFSIDE UTILITY UPGRADE PROJECT Project Completion Project Overview Sanitary Sewer System 2 Town of Surfside Project Overview Potable Water System 3 Town of Surfside Project Overview Storm Water

More information

4.3 Cisterns and Rain Barrels

4.3 Cisterns and Rain Barrels 4.3 Cisterns and Rain Barrels Rain barrels, cisterns, and tanks are structures designed to intercept and store runoff from rooftops. Rain barrels are used on a small scale while cisterns and tanks may

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

Sanitary Sewer Overflows Leave Telltale Signs in Depth-Velocity Scattergraphs

Sanitary Sewer Overflows Leave Telltale Signs in Depth-Velocity Scattergraphs Sanitary Sewer Overflows Leave Telltale Signs in Depth-Velocity Scattergraphs Patrick L. Stevens and Heather M. Sands ADS Environmental Services, Inc., Indianapolis, Indiana Sanitary sewer overflows (SSOs)

More information

PREVENTING WET OR FLO ODED BASEMENTS

PREVENTING WET OR FLO ODED BASEMENTS PREVENTING WET OR FLO ODED BASEMENTS TABLE OF CONTENTS Prevention Tips...Page 1 Why is there Water in my Basement?...Page 2 City of Saskatoon Sewer Systems...Page 3 Why Does Saskatoon Have Two Separate

More information

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet WHAT IS STORMWATER MANAGEMENT? Stormwater management is the method for channeling rainfall through pipes and sewers away from property to

More information

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana

More information

5O. Consideration of adopting a Sanitary Sewer Maintenance Policy for the City of Monticello (MT)

5O. Consideration of adopting a Sanitary Sewer Maintenance Policy for the City of Monticello (MT) City Council Agenda: 10/13/14 5O. Consideration of adopting a Sanitary Sewer Maintenance Policy for the City of Monticello (MT) A. REFERENCE AND BACKGROUND: City Council is asked to approve the City of

More information

Protect Your Home From Flooding. A guide for Lethbridge Residents

Protect Your Home From Flooding. A guide for Lethbridge Residents Protect Your Home From Flooding A guide for Lethbridge Residents Every year, millions of litres of water flow into the City of Lethbridge s stormwater and wastewater collection systems from residential

More information

INSTALLATION OF INSITUFORM LINER

INSTALLATION OF INSITUFORM LINER PART 1 GENERAL 1.1 SCOPE: A. This item shall include all work and materials to install, insert a flexible polyester felt liner saturated with a thermo-setting resin into the existing sewer line for rehabilitation

More information