Concrete Pavement Rehabilitation: Repairing Florida One Slab At A Time



Similar documents
September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

Section 500 Rigid Pavement

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

C. Section TESTING LABORATORY SERVICE.

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

High-Speed Nondestructive Testing and Intelligent Construction Systems

State Aid Concrete Pavement Rehabilitation Best Practices Manual 2006

BRIDGE REHABILITATION. Maintaining and Repairing Existing Structures

Case Studies - Concrete Overlays

Bonding Agents: The Good, the Bad, and What Works. Bond with Your Concrete

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

Jointed Plain Concrete Pavement (JPCP) Preservation and Rehabilitation Design Guide

OHIO ASPHALT PAVING CONFERENCE

Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson

CONSTRUCTION PERMIT REQUIREMENTS

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

Guide for Design and Construction of New Jointed Plain Concrete Pavements (JPCPs)

I-66 Pavement Rehabilitation

CHAPTER 2 LCCA APPROACHES

SECTION STORM DRAIN SYSTEM

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

Fly Ash Slurry Injection (FASI) of Bituminous Thermal Cracks

QUALITY ASSURANCE FOR MOBILE RETROREFLECTIVITY UNITS

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

MINIMUM QUALITY CONTROL PLAN FOR FIELD PLACEMENT OF LATEX MODIFIED MORTAR OR CONCRETE WEARING SURFACE

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

Waterproofing System for Wastewater Tanks in Petrochemical Industries and Refineries

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

Inspection, Maintenance, and Repair of PaCT Canadian Pacific Rogers Pass Tunnels British Columbia, Canada

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

GUIDELINES FOR POLISHED CONCRETE FLOORS A Guide for Integrally Colored, Dyed and Stained Polished Floors

Moving Small Mountains Vesuvius Dam Rehab

Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Virginia Approach Spans

Moisture and Resilient Floor Covering

Embedded Parts Introduction - Anchors

LIFE-CYCLE COST ANALYSIS PROCEDURES MANUAL

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

Concrete Pavement Rehabilitation Techniques and Canadian Based Case Studies

CA-48 TECHNICAL SPECIFICATION

Chapter. Restoration of Damaged Structures

Rehabilitation of an Aging Concrete Reservoir Adit Tower

INSTALLATION RECOMMENDATIONS. Outdoor Rubber Tiles

John Hoang P.E. ADOT Traffic Engineering Group Phoenix Design Section

DESCRIPTION OF WORK:

Dowel-Bar Retrofit Using Polyester Polymer Concrete

Section 300 Base Courses

Concrete Repair. Applications and Procedures

DMS REINFORCED CONCRETE PIPE AND MACHINE-MADE PRECAST CONCRETE BOX CULVERT FABRICATION AND PLANT QUALIFICATION

Nevada DOT Cold In-Place Recycling Federal Highway Administration National Review Close out meeting, August 25, 2005

Grinding equipment that causes raveling, aggregate fractures or disturbance to the joints shall not be permitted.

Concrete Waste Management

Technical Services. Product MM INCH Installation direction Seams treatment GTI CONNECT (interlocking)

BENTLEY ELEMENTS COLLECTION LVT

Quality Assurance Concepts. Outline

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

MEMORANDUM West Swann Avenue, Suite 225 Tampa, Florida Phone (813) Fax (813)

KENTUCKY TRANSPORTATION CABINET POLICY FOR FEDERALLY FUNDED PAVEMENT REHABILITATION AND PREVENTATIVE MAINTENANCE PROJECTS

Lesson 3. Portland Cement and Concrete

4-02 Gravel Base Ballast and Crushed Surfacing

PRE INSTALLATION MANUAL

Concrete Specification for Cooling Tower and Basin

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

Construction Specifications for Keyhole Pavement Coring and Reinstatement

The Concrete Life Cycle: Maintain to Sustain. Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH

A strong team for economical concrete paving. Slipform Paver SP 1500

Cold Weather Concrete Practices

GUIDE SPECIFICATION COMBINATION SURFACE SYSTEM FOR NEW HOT MIX ASPHALT TENNIS COURTS I. PART 1 - GENERAL

Asphaltic Wedge Paving

Advancements in Permeable Pavements

CHAPTERS PAVEMENT ENGINEERING CHAPTER 600 GENERAL ASPECTS

Pipe Repair Strategies on I-29

WATERPROOFING FOR CONCRETE STRUCTURES

RANDOM/GRID BLOCK CRACKING EXTREME SEVERITY. Transverse Cracking- Extreme Severity. Alligator Cracking- High. Severity

2015 ODOT Bridge Design Conference May 12, DeJong Rd Bridge High- Seismic Zone Case Study: Bridge Rehab vs. Replacement.

CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN

Resurfacing Concrete. Page 1 of 5

Construction Specification for Concrete Curb and Concrete Curb and Gutter

SECTION PRECAST CONCRETE STRUCTURES

Precast Concrete Parking Structures

CID STREET INFRASTRUCTURE ASSESSMENT

Sikaflex Sealant Installation. Sika Corporation

SECTION CAST-IN-PLACE CONCRETE

La Nueva AASHTO Guia de Diseno de Pavimentos Hormigon

Guide Specification Precast Concrete Products

Division 9. SignaFlor Pad and Pour Flooring System

Evaluation of In-Place Strength of Concrete By The Break-Off Method. Tarun Naik Ziad Salameh Amr Hassaballah

Transcription:

: Repairing Florida One Slab At A Time 2012 FTBA Conference Andre Sutherland, P.E. FDOT District 2 Jacksonville Construction

Contents Describe Scope Characteristics Sequence of operation for slab removal and replacement Characteristics of high early concrete and monitoring performance FDOT

-Typically involves night work for an extended period of time -Work occurs beside live traffic, buffer available where roadway geometry allows

Existing Designs Keyed Joints Skewed Joints Transverse joint spacing; existing joint spacing vs. current 15 ft maximum joint spacing for new concrete pavement. Longitudinal joint spacing may differ from current 12 ft maximum spacing

Identifying Damaged Slabs Typically jointed plain concrete pavement (JPCP) Slabs identified during design then verified nightly during construction Additional guidance through the Designer and FDOT Design Standard Index 308 Approx. 2 to 1 length/width ratio must be maintained Previous spall repairs failing

FDOT Design Standards Index 308 Bond Breaker around entire perimeter (2012 Design Standards)

Saw-cutting Operation Minimize /repair saw overcuts

: Preparation For Removal Slabs saw-cut and lift holes Restrictions on advance saw-cuts

Slab Removal

Removal involves lifting pins/cables Potential for spalling adjacent slabs Preparation of the existing base Base type may differ project to project depending on original design; possible impact to removal method

Dowel Bar Installation Use of a gang drill for dowel holes High pressure air to clean holes Insertion of dowels into epoxy filled holes; grease dowels

Tie Bars or No Tie Bars Tie bars used in new JPCP design Typically omitted from concrete rehabilitation projects Unique circumstances involving rehabilitation of continuous consecutive slabs Check with Designer

: Double Jeopardy Question Replacing slabs on a busy interstate 40 cubic yards to be poured; 3 hours lane closure remain; need 4 hours cure time What do you do? Too Late! You ll Be on the Morning News, In the Newspaper Pre-activity Contingency Plan Allow enough time nightly to complete work and slab to cure

Contractor s Nightly Supply Chain Management Plays A Key Part In Successful Nightly Completion Massive traffic jam on 10 Freeway becomes Caltrans scandal ~ February 17, 2012; LA Times Article I-10 Freeway west of Palm Springs concrete plant in Cabazon had idled workers tore up more of the road than they could replace on time backing up traffic about 25 miles and forcing drivers to endure delays of five hours or longer Instead of opening the road at 7 a.m. Sunday, all westbound lanes opened at 9:30 p.m.

: Placing Concrete Concrete mix design Addition of accelerator and supplier s dosage rate Typically workable for approximately 20 minutes once accelerator added Test plastic properties first, add accelerator after

: Finishing

Finishing

Finishing Rehabilitated slabs open to the traveling public daily Grinding process, if in contract comes at a later stage Nightly finish must meet longitudinal/transverse tolerance ; hand grind if necessary

Curing High cement content/heat of hydration; low w/c ratio Application of curing compound Use of insulation blankets vs. burlap Adjust for environmental/seasonal conditions

Opening To Traffic Compressive strength test or maturity method; both available If using compressive strength tests, cure cylinders in similar fashion as slabs Maturity method involves establishing time-temperature vs. strength correlation for EACH mix design

Grinding Usually grind entire roadway surface California Type Profilograph for Acceptance Testing

Sealing Grinding process damages existing joints Seal all longitudinal and transverse joints, new and existing joints

Pavement Markings Permanent tape for pavement markings/stripes on concrete surfaces (some exceptions) Placement over longitudinal/transverse joints Adhesive backing; temperature and moisture sensitive, needs clean surface Plan grinding/sealing/permanent markings sequence

Summary Balanced nightly production rate Minor adjustments in w/c ratio/accelerator coordinated between contractor/supplier Allow enough time between placement and roadway opening Supplier/contractor co-ordination concerning concrete mix parameters

Conclusion Thanks for attending! Andre Sutherland, PE Jacksonville Construction andre.sutherland@dot.state.fl.us