EXTERNAL REPORT. Smart Metering Entity (SME) MDM/R Report 3 rd Quarter 2014. July to September. Issue 5.0 - October 29, 2014



Similar documents
FOUNDATION WORKING GROUP SESSION #1

Ontario Smart Metering System Implementation Program (SMSIP) Panel Discussion: Smart Metering the road ahead

We are working hard to help Ontario businesses manage their electricity costs.

Foundation Working Group Meeting #3 Structures and Standards for the MDM/R Information

IESO Information & Technology Services Group Roles, Responsibilities, and Project Management. Doug Thomas: VP- I&TS and CIO May 28, 2015

Ontario Smart Metering System Implementation Program (SMSIP) Bill Limbrick Vice President, IT&I Independent Electricity System Operator (IESO)

Re: New Reporting Requirements Related to Smart Meter Deployment and the Application of Time-of-Use Pricing

NOTICE OF AMENDMENT TO A CODE AMENDMENTS TO THE DISTRIBUTION SYSTEM CODE BOARD FILE NO.: EB

Scorecard - Oakville Hydro Electricity Distribution Inc.

IN THE MATTER OF subsections 78(2.1), (3.0.1), (3.0.2) and (3.0.3) of the Ontario Energy Board Act, 1998;

APPLICATION AND PRE-FILED EVIDENCE

Migration To MDM/R Production Mode. P.D Ferguson, P.Eng President Newmarket Tay Power Distribution Ltd.

Your guide to electricity pricing in Ontario

FUNCTIONAL SPECIFICATION FOR AN ADVANCED METERING INFRASTRUCTURE VERSION 2

Scorecard MD&A - General Overview

Electricity Supply. Monthly Energy Output by Fuel Type (MWh)

The Path Forward: Integrated Transition Plan October 2015

Local Distribution Companies 25% of the Customer Bill

ELECTRICITY PRICING INFORMATION. This list shows the terms that appear on electricity bills and what they mean:

Global Trends in Smart Metering

Scorecard - Tillsonburg Hydro Inc.

Retail Market IT Services Service Level Agreement

Overview of the IESO-Administered Markets. IESO Training. Updated: January, Public

making a difference where health matters Canadian Primary Care Sentinel Surveillance Network

Addressing IT Challenges in Smart Metering and MDM/R Integration

May, Initiative Overview

AIMS Project (UNDP) Training Report. Introduction to Database (MS Access) Kabul January United Nations Development Program (UNDP)

RFP Attachment C Classifications

Getting Outage Management Systems Ready for Outage Events

OEB Smart Grid Advisory Committee

What s going on with LDC Consolidation? Four Directions and an Election

Ontario Energy Board Business Plan

The Ontario Energy Board's ( Board ) Decision and Order in the OPA's 2011 revenue requirement submission (EB ) directed the OPA:

Application Maintenance and Development Attachment C for RFP#

San Francisco Chapter. Information Systems Operations

Project title (in Chinese) 項 目

Part 2.13: Change and Baseline Management

A. General Information

for the reporting interval ending February 28, 2015 INdigital

DATA INTEGRATION APPROACH TO OIL &GAS LEGACY SYSTEMS WITH THE PPDM MODEL. Compete like never before. Consulting Technology Performance

A Big Data Pilot Project with Smart Meter Data (abridged version)

PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:

BUSINESS PLAN

Project Management Plan

Client Services Service Level Agreement

State of California Department of Transportation. Transportation System Data Business Plan

Defining Ontario s Typical Electricity Customer

Horizon Utilities Corporation

IT Outsourced Services. Preliminary Survey

Vidian Connections - Ontario Electricity

Electricity Prices Panel

The management of print is easier with the right tools.

COST OF CAPITAL, COST OF EQUITY, DEBT FINANCING AND DIVIDEND POLICY

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

Service Level Agreement Between: Computing and Informational Technology And The Finance and Business Operations Division

Business Intelligence is a system that collects, integrates, analyses and presents business information to support better business decision making.

CONSERVATION AND DEMAND MANAGEMENT REQUIREMENT GUIDELINES FOR ELECTRICITY DISTRIBUTORS

Purchasing and Supply Chain Analysis: Tools and Techniques

Bold Changes Big Opportunities: The Changing Face of Electricity Conservation in Ontario

ATTACHMENT V2. Transnet

Presented By: Leah R. Smith, PMP. Ju ly, 2 011

ALPINE NEWSLETTER. INSIDE CitySUMs INDICATE CI-NERGY FASUDIR FORTISSIMO iurban MIRIAM Glasgow TSB Future Cities

REQUEST FOR PROPOSALS UTILITY WATER, WASTE WATER, RENTAL BILLING SOFTWARE SOLUTION. ADDENDUM No. 1 Page 1 of 11

INTRODUCTION AND SUMMARY OF O&M COSTS

Ontario Energy Board

The Cost Allocation Working Group. First Report. Load Data Collection

SEP 2014 OCT 2014 DEC 2014 NOV 2014 HOEP*

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15 (Schedule B);

OFFICE OF THE PRIVACY COMMISSIONER OF CANADA. Audit of Human Resource Management

REQUEST FOR PROPOSALS METER DATA MANAGEMENT SYSTEM (MDMS) RFP # 546

3.11. Smart Metering Initiative. Chapter 3 Section. Background. Ministry of Energy

TRANSMISSION BUSINESS PERFORMANCE

GISTEC Standard Technical Support Policy

Progress Report Template -

NOS for Data Analysis (802) September 2014 V1.3

The Key Performance Indicator Evaluation Process (KPI Process)

Symmetry Networks. Corporate Managed Services Schedule

SE-113 Updates to Meter Data Distribution. December 8, 2014

dxhub Denologix MDM Solution Page 1

LafargeHolcim Ltd. Finance & Audit Committee Charter Review date: July 28, 2015

BUSINESS PLAN. 2012/13 to 2014/15 LAND TITLE AND SURVEY AUTHORITY OF BC

Benjamin A. Stafford. February 12, 2010

INDRA IN THE CZECH REPUBLIC

PE9.4 Corrected Report

REPORT On the work of the Croatian Energy Regulatory Agency For the year 2005

Online Channel Office Project Alliance Management Office Report August 2011

Roles within ITIL V3. Contents

CDX Vendor Conformance Process Version 1.0

4.07 Provincial Personal Income Tax Revenue and Related Credits and Reductions

1 Beyond Network CRM (Quotation)

TSE-Listed Companies White Paper on Corporate Governance TSE-Listed Companies White Paper on Corporate Governance 2015

Department of Administration Portfolio Management System 1.3 June 30, 2010

How To Get A Power Control Device From The Power Station

Best Practices in the Formation and Implementation Of Strategic Alliances

Company A Project Plan

ACESS A Comprehensive Enterprise Social Services System

Blackboard Collaborate Web Conferencing Hosted Environment Technical Infrastructure and Security

Payroll Operations and Information Management and Payroll Services Alliance Management Office Annual Report. November 2007

ONTARIO ENERGY BOARD AFFIDAVIT OF TODD WILLIAMS

A McKnight Associates, Inc. White Paper: Effective Data Warehouse Organizational Roles and Responsibilities

Transcription:

REPORT EXTERNAL, Smart Metering Entity (SME) MDM/R Report 3 rd Quarter 2014 July to September Issue 5.0 - October 29, 2014

Table of Contents 1. Introduction... 2 1.1 Purpose... 2 1.2 How to Use this Document... 2 2. MDM/R Operation and Processing Performance... 3 2.1 Performance... 3 2.2 Training... 3 2.3 Other Activities... 3 3. MDM/R Service Levels... 4 4. Initiatives and Software Testing... 6 5. Additional Risks and Issues... 7 Issue 5.0 10/29/2014 Page 1 of 7

1. Introduction 1.1 Purpose The purpose of this report is to provide a quarterly update to the Ontario Energy Board on the ongoing operations of the Meter Data Management and Repository (MDM/R). This report includes the following updates: MDM/R Operation and Processing Performance; MDM/R Service Levels for both Critical and Non-Critical Services as set out in Appendix A of the MDM/R Terms of Service ; Initiatives and Software Testing; Additional Risks and Issues; and, Roles and Responsibilities of the SME as set out in Article 2.2 of the Smart Metering Agreement for Distributors 1.2 How to Use this Document This report presents information and status updates on MDM/R operation and processing performance (in Section 2), MDM/R Service Levels (in Section 3), and Initiatives and Software Testing (in Section 4). The report focuses on quarterly updates for the MDM/R including updates on the Roles and Responsibilities of the SME through the end of the indicated month. More information about the provincial Smart Metering Initiative and the MDM/R is available on the websites of the Ministry of Energy (http://www.mei.gov.on.ca/), the Ontario Energy Board (http://www.oeb.gov.on.ca/oeb/industry) and the IESO/SME website (http://www.smi-ieso.ca/). Each section provides updates as required by the Ontario Energy Board in connection with MDM/R operations and performance, service level attainment, initiatives and software testing, as well as risks and issues. Issue 5.0 10/29/2014 Page 2 of 7

2. MDM/R Operation and Processing Performance 2.1 Performance The MDM/R production environment remains stable and reliable, processing reads from over 4 million meters for 72 LDCs on a daily basis. The SME continues to respond to and address LDC support, service requests, and issues in a timely manner. For the reporting period July 1 to September 30, 2014, the MDM/R operated well, meeting or exceeding service levels for 100.00% of meter reads, 100.00% of billing quantity requests, and 100.00% of master data updates. Where there were processing delays, service was restored in a timely manner. The SME published LDC-specific performance metrics reports for the months of June, July and August 2014. These reports provide each LDC with information related to their organization s meter read, synchronization, and billing performance. This information assists LDCs in improving the quality and timing of their data submissions to the MDM/R. As part of the SME s outreach plan, two on-site LDC visits were conducted during the third quarter. These meetings continue to have positive outcomes, so the SME plans to continue this outreach program for the remainder of 2014. A Smart Metering Steering Committee meeting was held on September 9, 2014. The SME encourages all LDCs to participate during these pre-scheduled SME Steering Committee meeting open calls. During these calls LDCs are given the opportunity to provide feedback and suggestions to the SME. The next call is currently scheduled for November 25, 2014. As part of the SME s commitment to continual service improvement, the SME continues to encourage LDCs to propose and submit opportunities for change or improvements; this can be done through their Service Desk agent and the MDM/R Change Management process. 2.2 Training During the third quarter, the SME delivered one Basic Graphical User Interface (GUI) training session, and one advanced Graphical User Interface (GUI) training session. Feedback from participants continues to be very positive. For the complete training schedule, please visit the SME website. 2.3 Other Activities Larry Herod (Newmarket-Tay Hydro), the Chairperson of the SME Steering Committee, resigned from the committee. During the September meeting, the Committee nominated and appointed John McClean (PowerStream) as the new Chairperson. Issue 5.0 10/29/2014 Page 3 of 7

3. MDM/R Service Levels The Service Level Performance Chart splits Service Level summaries into two parts: Critical Service Level Summary, and; Non-Critical Service Level Summary The Critical Service Level Summary section includes processing metrics for Automatic Meter Read Processing, Billing Quantity Response Processing, Automatic MMD Incremental Synchronization Processing, MDM/R Graphical User Interface, Meter Read Retrieval Web Services, Reporting, Vendor Service Desk Incident Response, and Vendor Service Desk Service Requests. The Non-Critical Service Level Summary section includes processing metrics for Meter Read Retrieval Web Services, MDM/R Availability, and Service Requests. The table also includes a Service Level breakdown for each month along with a quarterly summary 1. Critical Service Level Summary Jul-2014 Aug-2014 Sep-2014 3 rd Quarter Automatic Meter Read Processing Intervals Loaded 3,135,534,759 3,159,853,914 3,043,280,475 9,338,669,148 Intervals Loaded on Time 3,135,534,759 3,159,853,914 3,043,004,633 9,338,393,306 % Intervals Loaded on Time 100.00% 100.00% 99.99% 100.00% 0 0 2 2 accumulated delay >240 minutes 1 Automatic Billing Quantity Processing BQ Requests 4,699,215 4,113,060 3,979,503 12,791,778 BQ Requests Fulfilled on Time 4,699,215 4,113,060 3,979,503 12,791,778 % Requests Fulfilled on Time 100.00% 100.00% 100.00% 100.00% accumulated delay >240 minutes 1 Automatic MMD Incremental Synchronization Processing MDM/R Graphical User Interface Meter Read Retrieval Web Services Reporting Vendor Service Desk Incident Response Vendor Service Desk Service Requests Data Elements Requested 1,678,472 1,575,048 1,468,466 4,721,986 Data Elements Loaded on Time 1,678,472 1,575,048 1,468,466 4,721,986 % Data Elements Loaded on Time 100.00% 100.00% 100.00% 100.00% Data Elements loaded outside of agreed Availability 100.00% 100.00% 99.98% 99.99% MDM/R Graphical User Interface availability outside of agreed Service Level target 1 Availability 100.00% 100.00% 100.00% 100.00% Meter Read Retrieval Web Services availability outside of agreed Service Level target 1 Percentage completion 93.30% 95.03% 95.26% 94.53% Reporting percentage completion outside of agreed Service Level target 1 Response Time 75.00% 75.00% 100.00% 83.33% 2 1 1 4 Vendor Service Desk Incident Response Time outside of agreed Resolution Time 97.98% 94.51% 100.00% 97.50% Vendor Service Desk Request resolution time outside of agreed 1 Percentages are rounded to the second decimal place for each metric. Issue 5.0 10/29/2014 Page 4 of 7

Non-Critical Service Level Summary Jul-2014 Aug-2014 Sep-2014 3 rd Quarter Meter Read Retrieval Web Services MDM/R Availability Response Time 99.96% 99.96% 99.96% 99.96% Meter Read Retrieval Web Services response time outside of agreed Availability 100.00% 100.00% 99.99% 100.00% MDM/R Availability outside of agreed Service Requests Resolution Time 100.00% 100.00% 100.00% 100.00% Service Requests resolution time outside of agreed Service Level target 1 Issue 5.0 10/29/2014 Page 5 of 7

4. Initiatives and Software Testing MDM/R Release 7 (EnergyIP Version 7.6 Upgrade and Measurement Canada 2012 Phase 2) This project will upgrade the MDM/R software to a more current version keeping it maintainable and supportable, and will be combined with the delivery of the Measurement Canada 2012 Phase 2 solution functionality 2. We are currently targeting to complete this project by the end of 1Q 2015. The SME s extensive testing has uncovered defects that need to be addressed by the vendor prior to allowing LDCs to conduct their own tests. The vendor has analyzed the defects and a new release will be delivered to the IESO by October 31, 2014. As tentative dates change, we will continue to update LDCs and provide revised dates. MDM/R Data Access The MDM/R Data Access Platform ( MDAP ) concept emerged as a possible way of addressing the new and emerging needs for data access and analytics of electricity consumption data and pursuing the Ministry of Energy s (the Ministry ) objectives for deriving greater value for consumers, energy stakeholders and the province from MDM/R data. Specifically, high level objectives for MDAP would include: Enhancing the value of the electricity consumption data by adding attributes to existing data (e.g. meter location), as well as new data sources (e.g. weather), Providing new interfaces and functionality for data access by current users of the MDM/R, Supporting access for authorized new classes of users such as researchers, commercial enterprises and other third parties, Supporting authorized access to anonymized data for research purposes and analysis. In late September, The Ministry, the Advanced Energy Center and the IESO ratified the Project Definition Document to develop a business case for an MDM/R Data Access Platform (MDAP). This project is currently underway and is expected to be completed by Q4 2015 In order to protect the operational stability of the MDM/R and support the increasing volumes of data retrieval requests, the SME is in the process of implementing infrastructure reinforcements, including an MDM/R Data Mart. The Data Mart is a purpose-designed synchronized copy of the MDM/R production database that will be used for fulfilling web service requests, data extract requests, and other ad-hoc queries without impacting the operation of the MDM/R. Significant progress has been made on the project with development substantially completed. Internal testing is currently underway, with a follow on testing phase that involves a select number of LDCs targeted by the end of 1Q 2015. The MDM/R Data Mart has been architected such that it could, if deemed appropriate, be expanded in the future to support new and evolving requirements for the MDM/R Data Access Platform without stranding investments. 2 An overview of the Measurement Canada 2012 Phase 2 solution is provided in the SME MDM/R Report Issue 1.0 dated October 28, 2013. Issue 5.0 10/29/2014 Page 6 of 7

MDM/R LDC Merger Utility In order to support the merger of LDCs, the SME was requested to provide a facility for the reassignment of historical electricity consumption data in the MDM/R from one utility to another. This approach enables LDCs and their electricity consumers to be able to retrieve their historical consumption data from the consolidated utility. Preliminary testing has been completed and functional testing will begin in Q4 of 2014. 5. Additional Risks and Issues There are no additional risks or issues to report. Issue 5.0 10/29/2014 Page 7 of 7