Optimised Design for Soil Nailed Walls 1



Similar documents
SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

How To Design A Foundation

System. Stability. Security. Integrity. 150 Helical Anchor

Numerical modelling of shear connection between concrete slab and sheeting deck

Designed and Engineered to Perform

8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS

PART TWO GEOSYNTHETIC SOIL REINFORCEMENT. Martin Street Improvements, Fredonia, Wisconsin; Keystone Compac Hewnstone

Numerical Simulation of CPT Tip Resistance in Layered Soil

Detailing of Reinforcment in Concrete Structures

6 RETROFITTING POST & PIER HOUSES

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Glass Fibers Reinforced Composits (GFRP) for TUNNELLING

METHOD OF STATEMENT FOR STATIC LOADING TEST

Interpretation of clogging effects on the hydraulic behavior of ion treated geotextiles

BEARING CAPACITY AND SETTLEMENT RESPONSE OF RAFT FOUNDATION ON SAND USING STANDARD PENETRATION TEST METHOD

THE EFFECT OF STIRRUPS AND HOOKED STEEL FIBERS INSTEAD ON MOMENT-ROTATION CAPACITY OF BEAM-COLUMN CONNECTIONS

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

c. Borehole Shear Test (BST): BST is performed according to the instructions published by Handy Geotechnical Instruments, Inc.

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Design of pile foundations following Eurocode 7-Section 7

Technical Notes 3B - Brick Masonry Section Properties May 1993

Soil Screw Design Manual Edition 2

KWANG SING ENGINEERING PTE LTD

Soil Classification Through Penetration Tests

SEISMIC RETROFITTING TECHNIQUE USING CARBON FIBERS FOR REINFORCED CONCRETE BUILDINGS

Mechanically stabilized layers in road construction

Geotechnical Investigation Test Report

Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

GUIDELINE FOR HAND HELD SHEAR VANE TEST

Site Investigation. Some unsung heroes of Civil Engineering. buried right under your feet. 4. Need good knowledge of the soil conditions

Current opportunities of sprayed waterproofing membrane. Frank Clement Technical Manager Sprayable Membranes MEYCO Global Underground Construction

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

THE DEVELOPMENT OF DESIGN METHODS FOR REINFORCED AND UNREINFORCED MASONRY BASEMENT WALLS J.J. ROBERTS

Rehabilitation of Existing Foundation Building to Resist Lateral and Vertical Loads

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

ENCE 4610 Foundation Analysis and Design

Tests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill

What is QuickBase? Traditional foundations (left) compared with QuickBase (right)

A CASE STUDY ON THE USE OF FLEXIBLE EARTH RETAINING STRUCTURE IN UNSTABLE SLOPES

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Paper The relation of Micropile Diameters in case of Pressure casting and non-pressure casting (30)

product manual HS-4210 HS-4210_MAN_09.08 Digital Static Cone Penetrometer

Stability. Security. Integrity.

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes

SPECIAL COMPOUND FOR RHEOPLASTIC AND ANTI-CORROSION SUPERCONCRETE WITH VERY HIGH DURABILITY

Reliability of Estimated Anchor Pullout Resistance. Yasser A. Hegazy, M. ASCE 1

The Original Carbon Fiber Reinforced Polymer System

Program COLANY Stone Columns Settlement Analysis. User Manual

Anirudhan I.V. Geotechnical Solutions, Chennai

A study on the Effect of Distorted Sampler Shoe on Standard Penetration Test Result in Cohesionless soil

RMS Guide for design of concrete pavements in areas of settlement. Version 1.0. Roads and Maritime Services

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

SEISMIC DESIGN. Various building codes consider the following categories for the analysis and design for earthquake loading:

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

ATLAS RESISTANCE Pier Foundation Systems

FLOORS REINFORCEMENT Shear Stud Connector for steel- concrete composite structures cold applied by pins

Measurement of Soil Parameters by Using Penetrometer Needle Apparatus

NUMERICAL MODELLING OF PIEZOCONE PENETRATION IN CLAY

16. Beam-and-Slab Design

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

An Automatic Kunzelstab Penetration Test

SEISMIC RETROFITTING OF STRUCTURES

Structural Integrity Analysis

Geotechnical Testing Methods II

CIVL451. Soil Exploration and Characterization

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

How To Model A Shallow Foundation

Strength Determination of "Tooth-Paste" Like Sand and Gravel Washing Fines Using DMT

EXAMPLE 1 DESIGN OF CANTILEVERED WALL, GRANULAR SOIL

DEVELOPMENT OF A NEW TEST FOR DETERMINATION OF TENSILE STRENGTH OF CONCRETE BLOCKS

SKER HUESKER HUESKER geogrid HUESKER HUESKER for HUESKERHUES SKER HUESKER HUESKER HUESKERHUES SKER HUESKER HUESKER HUESKER HUESKER HUESKERHUES

Ingeniería y Georiesgos Ingeniería Geotécnica Car 19 a Nº of 204 ; TEL : igr@ingeoriesgos.com

STRUCTURAL DAMAGE OF A 5-STOREY BUILDING: DIFFERENTIAL SETTLEMENT DUE TO CONSTRUCTION OF AN ADJACENT BUILDING OR BECAUSE OF CONSTRUCTION DEFECTS?

DESIGN OF BLAST RESISTANT BUILDINGS IN AN LNG PROCESSING PLANT

List of Graduate Level Courses in Civil Engineering

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

ENGINEERING SPECIFICATION PULTRUDED DYNARAIL FIBERGLASS LADDER & LADDER CAGES

IS THAT LINER THICK ENOUGH?

Basic principles of steel structures. Dr. Xianzhong ZHAO

Module 7 (Lecture 24 to 28) RETAINING WALLS

Concrete Design Manual

Hardened Concrete. Lecture No. 14

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

Transcription:

Optimised Design for Soil Nailed Walls 1 J A R Ortigao 1 and E M Palmeira 2 1 Federal University of Rio de Janeiro, Rio de Janeiro, Brazil 2 University of Brasília, Brasília, Brazil INTRODUCTION The first application of soil nailing for slope stabilisation in Brazil dates back to 1970 for a tunnel portal, carried out by tunnel engineers (Ortigao et al, 1995). Unfortunately, almost no publicity was given to this development. On the other hand, a lot was publicised on the effectiveness of tieback walls in Brazil and thousands of them were used throughout the country. In mid 80 s, geotechnical engineers in Brazil started to become aware of a costeffective alternative to tiebacks and interest on soil nailing increased. Several walls have been constructed since then, many without proper analysis of the effect of the reinforcement, and the design has been carried out based on previous experience and engineering judgement. The next decade brought a new era for soil nailing in Brazil: the trend now is towards optimised design in which nail length and facing design are optimised, but nail corrosion still needs further considerations. The following aspects will be discussed in this paper: soil-nail interaction and nail length and stability analysis, facing design and corrosion. SOIL-NAIL INTERACTION The authors take only nail tension into account, since in their experience, for the dimensions of nails usually employed, bending effect has only a very small effect and can be disregarded (Ortigao et al 1995 a & b). Nail tension depends on so many aspects that only site specific testing can give reliable values of the soil-nail unit friction q s. However, pull-out testing before construction never occurred in the author s experience, and the evaluation of an a priori value for q s has been necessary in most walls. Testing always come afterwards to confirm, or not, pre-construction values and today pre-estimation of q s are carried by the authors from the data in Figure 1. This figure relates unit friction with N values from Standard Penetration Tests (SPT). Despite being a very crude test the SPT is the sole site investigation in most small and medium projects in Brazil, therefore data in Figure 1 can be very useful for preliminary design stage. 1 Ortigao J A R & Palmeira E M (1997) Optimised design for soil nailed walls, Proc. 3 rd Int Conf on. Ground Improvement Geosystems, London, T Telford, pp 368-374 1

q s (kpa) 400 300 200 q s = 67 + 60 ln N (r 2 = 0.624) 100 90% lower confidence limit Suggested lower limit 0 1 2 3 4 5 6 7 8 910 20 30 40 50 N (blows/30 cm) Sandy silt, São Paulo Sandy clays, Rio Porous clay, Brasília Silts (weathered slates) Brasília Sandy silt, São Paulo Figure 1 Pull -out tests results NAIL LENGTH AND STABILITY ANALYSES Existing slopes to be stabilised deserve in general little deformation concern. The problem is to ensure stability and an adequate factor of safety for the reinforced slope. This is the case of the example in Figure 2. This slope required very little excavation to reach the final geometry. However, since a building nearby was going to be constructed, the slope had to be stabilised to increased its safety. The site is close to the Congonhas Airport in São Paulo, where a there is a porous clay deposit, found in many locations in Brazil (Ortigao et al, 1996a) The distributed surcharge on the slope was 40 kpa. For a preliminary analysis, soil parameters were evaluated from previous experience with these clays: c taken equal to 10 kpa, φ was 26 degrees and the unit weight γ was 15 kn/m 3. The water table was found very low and the analysis has shown it had little effect on the results. This yielded a factor of safety for the unreinforced slope of 1.080 using Bishop s method of analysis. The analysis of the reinforced slope was carried out with Rstabl (Ortigao et al, 1995b) employing Bishop s and Janbu s method. Nails were 32 mm steel bars in 100 mm grouted boreholes. The soil-nail friction was estimated using the chart in Figure 1 as 120 kpa. The analysis started by introducing nails from the bottom of the slope upwards and carrying out global stability analyses until the required factor of safety was obtained. It was found that the minimum length of the bottom nail layer was 21 m. The other nail layers with 18 and 15 m long were assigned in the next step leading to a factor of safety (FS) close to 1.5. In the upper part of the slope there was a 6 m high vertical cut to be carried out. Since it was very close to the top where the 40 kpa surcharge was to be applied, deformation became of concern and three layers of 9 m long nails were designed. The FS for this part of the slope is close to 1.6. 2

In summary, the technique adopted by the authors is to carry out successive analysis starting from a global analysis and following the slope upwards. This certainly minimises nail length and ensure stability. Later during construction, it is of utmost importance that pull out tests on sacrificial nails are carried out. These data will enable the designer to adapt his design to actual measured conditions. An opposite situation occurs when deformation is of major concern, as it is the case shown in Figure 3. This wall was proposed to be excavated very close to an existing road on the top. Local soil was a silty sand with N values around 8, too low. Wall deformation could lead to cracks on the pavement, which was undesired. Therefore, a mixed soil nailed structure employing nails and soil anchors was designed to 50 40 Elevation (m) 30 20 1.599 1.496 1.471 10 0 0 10 20 30 40 50 60 70 80 Distance (m) Figure 2 Example of wall close to Congonhas Airport, São Paulo increase stiffness and, consequently, to reduce deformation (Ortigao et al, 1995b). Soil parameters were estimated as: unit weight 18 kn/m 3, cohesion was taken as 10 kpa and friction angle equal to 26 degrees. Table 1 Stability analyses of mixed soil nailed wall Condition Calculated FS Rstabl Prosper Bishop Janbu FS δ (mm) No reinforcement 0.480 0.498 0.69 0 Nails only 1.481 1.478 1.50 16 Nails and soil anchors 1.499 1.483 1.50 11 3

Rstabl results in Table 1 were compared with a different method of analysis developed at the Laboratoire des Ponts et Chaussées and described by Delmas et al (1986) incorporated into the Prosper program. In Prosper nails are treated according to the Winkler model, as a beam supported by non-linear springs. Tension, bending and shear are considered. The FS calculation iterates until the necessary nail deformation δ is calculated to give a specified FS equal to 1.50. The resulting δ values in Table 1 are small, indicating that the proposed wall is acceptable. The calculated slip surface is different from the one obtained by Rstabl. Computed FS values with Bishop and Janbu s methods are close. STEEL FIBRE REINFORCED SHOTCRETE Vertical or nearly vertical walls require a flexible facing and in most cases shotcrete has been used. In the last years there has been a considerable progress in the use of steel fibre reinforced shotcrete (SFRS) (Vandewalle, 1993) which presents advantages in relation to the use of mesh reinforcement. Fibres are high tensile strength steel elements having 30-50 mm in length and 0.5 mm in diameter with hooked ends, that are mixed in the concrete as an aggregate with a dosage in the range of 35 to 60 kg/m 3. It can be used in either dry or wet sprayed concrete mix. The fibres have no effect in the compressive strength of the concrete, but increase ductility, enabling to take into account flexure tensile strength. The market offers a variety of fibre types, but only some with a very high length to diameter ratio achieve high performance. Some are glued forming small clusters with 30 to 40 fibre pieces stuck side by side. These bundles are mixed in the concrete and are separated in contact with water after one or two minutes of mixing. This leads to a better fibre random distribution and better concrete workability. The final SFRS product is a homogeneous material with increased crack and corrosion resistance. SFRS saves the labour for the mesh placement and saves total concrete volume in Figure 3 Mixed soil nailing structure proposed for an excavation in medium sandy-silt 4

relation to mesh reinforced shotcrete. SFRS complies with soil or rock surface irregularities, saving total concrete volume, as compared to the use of a steel mesh. SFRS is being applied with considerable success at the portals and at the lining of a 2.2 km long Covanca Tunnel in Rio de Janeiro. A series of preliminary laboratory tests conducted on SFRS samples confirmed the properties of the concrete mix and additional testing and evaluation are underway. It is expected that SFRS will replace most of the steel meshes today still employed for slope stabilisation and soil nailing. NAIL CORROSION AND FRP The first tieback wall in Brazil was constructed in 1957 and since then, Brazilian experience can be summarised as follows. Yassuda (1994) presented several cases in which corrosion took place in multi-strand anchors close to the anchor head and caused failure of the structure. These and other evidence led the Geo-Rio, the Rio de Janeiro Geotechnical Office, to ban this type of soil or rock anchor in this City. However, there had been no evidence of corrosion in a 25 (or more) mm diameter steel bar used for tiebacks, although there had been cases of deterioration of the anchor head protection leading to corrosion of the nut and supporting steel plate. Double protection, in which the steel bar is sheathed in corrugated plastic and grouted, has not been common in this country. The ultimate solution for corrosion certainly is the use of fibre reinforced plastic (FRP) nails, as described by Ortigao (1996). FRP s are a composite material obtained by an industrial process called pultrusion that combines the fibre reinforced elements, usually glass fibres, with different types of resins. The final product can be of any shape with very high tensile strength, usually three times steel strength, low modulus and low unit weight. Bars and tubes are produced for geotechnical applications. FRP s have a very high corrosion resistance, easy cuttability, but its cost is still high as compared to steel. FRP s have already found some applications in tunnelling in Brazil (Ortigao, 1996) but, none to the authors' knowledge, in soil nailing. However, since the cost of the nail bar alone may have little effect on the overall cost of the stabilisation project, FRP s will find their way in slope stabilisation works, leading to long-term corrosion-free and safer walls. CONCLUSIONS This paper discussed soil nailing design optimisation according to three different aspects. The first, concerns stability analysis and deformation compatibility of a soil nailed wall. The soil friction data in Figure 1 enable the selection of a priori friction value based on the N value from the SPT for a particular soil, but its value has to be confirmed a posteriori through pull-out tests. Stability analyses should be carried out in several levels of the structure from the bottom upwards, ensuring safety and adequacy of the FS value at each level. Existing slopes or those subjected to little excavation have little deformation concern. Vertical excavations close to sensitive structures should be more rigid and avoid excessive deformation. The authors have combined nails and anchors at the top to limit deformation. Steel fibre reinforced shotcrete has been used in Rio de Janeiro with considerable cost and time saving. SFRS should be considered in most projects where a concrete facing is necessary. 5

Finally, long term corrosion should receive additional consideration. Reinforced plastic technology seems to be the ultimate solution but, since the cost is higher than steel, it is likely to find applications in aggressive environments or by the imposition industry standards. Some aspects of FRP long term behaviour, such as creep and interaction with grout, seem to deserve further investigation ACKNOWLEDGEMENTS Prosper was provided by Dr R Frank from Cermes l ENPC (formerly at the Laboratoire des Ponts et Chaussées, Paris). REFERENCES Delmas P, Berche J C, Cartier G & Abdelhedi A (1986) Une nouvelle méthode de dimensionnement du clouage des pentes: programme Prosper, Bulletin de Liaison des Laboratoires des Ponts et Chaussées, no. 141, pp 57-65 Ortigao J A R, Palmeira E M & Zirlis A (1995a) Experience with soil nailing in Brazil: 1970-1994, Proceedings of The Institution of Civil Engineers, Geotechnical Engineering, London, vol 113, April 1995, paper no. 10584, pp 93-106 Ortigao J A R, Alves L S, Brandi V R & Far J (1995b) Rstabl: a program for stability analysis of reinforced soil slopes, Proc. Symp. on Geosynthetics, Geossintéticos 95, São Paulo, pp 363-371 Ortigao J A R, Cunha R P & Alves L S (1996a) In situ tests in Brasília porous clay, Canadian Geotechnical Journal, February 1996, vol 33, pp 189-198 Ortigao J A R, Palmeira E M & Zirlis A (1996b) Discussion on Experience with soil nailing in Brazil: 1970-1994, Proceedings of The Institution of Civil Engineers, Geotechnical Engineering, London, vol 119, Oct 1996, paper no. 10584, pp 238-241 Ortigao J A R (1996) FRP applications in geotechnical engineering, Proc. ASCE 4 th Materials Conference, Washington DC, Nov 1996 Vandewalle M (1993) Tunnelling: the world, N.V. Bekaert SA, Belgium, 229 p Yassuda C (1994) Panel presentation on Accidents in slope stabilisation works (in Portuguese), Brazilian Conference on Soil Mechanics and Foundation Engineering, Iguassu Falls, Nov, 1994 6