Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee



Similar documents
The FIDIC Suite of Contracts

A Contract for Just Digging a Hole

MDB Harmonised Particular Conditions

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

(1) risks should be allocated to the party that is in the position to control them and

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill

The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni

Contractor s Claims Under The FIDIC Contracts For Major Works

The Role of Construction Managers. FIDIC offers two contributions on the question of the role of a construction manager in a construction contract:

GUIDANCE NOTE Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

Bills of Quantity. D. Atkinson December Nature of Bills

A. UK, EUROPEAN AND INTERNATIONAL CONTRACT FORMS. I. Fédération Internationale des Ingénieurs-Conseils (FIDIC)

CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Appendix 18 NEC3 Options

Contract Administration

Information event for consulting companies on 27 September 2010 at GTZ (now GIZ) Open questions Notes Suggestions

CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS

1.1 The contract shall be deemed to have been entered into upon receipt of supplier s written acknowledgement stating its acceptance of the order.

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

The New Standard Construction Contracts: NZS3910, 3916 and 3917

A Guidance Note to. Conditions of Contract for Consultancy Services (2005)

LUONNOS. Client s representatives In contract matters In matters related to project execution

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011

Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program

Code of Practice for Agents Undertaking Renovation Grants

FIDIC S GREEN BOOK CLAUSES 6, 13 & 14

Explaining an architect s services. General information on the usual tasks undertaken by an architect

Conditions of Contract for CONSTRUCTION

Giovanni Di Folco Letters of Intent, Bonds & Guarantees, Defects Liability Periods

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS

How To Write New Government Construction Contracts

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

INSURANCE PROVISIONS

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices

PREQUALIFICATION DOCUMENT FOR CONSULTANTS FOR CIVIL WORKS. (Ref No. Secy/PPC/CVL/01)

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review

Contracting Practices in Mega Projects

CLIENT / PROJECT MANAGER AGREEMENT

The South African Council for the Project and Construction Management Professions (SACPCMP)

Texas Department of Transportation

CODE OF CONDUCT for Court Experts in civil law and administrative law cases

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

TENDER DOCUMENTS. Procurement of Works. Small Contracts (Small Value, Short Duration and Low Risk) Public Procurement Board.

SPECIMEN INSURANCE PROVISIONS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

How To Write A Contract

Schedule of Prices. Project Name Contract No. Contract Number

TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG

Article. Turnkey contracting under the FIDIC Silver Book:What do owners want? What do they get?

Memorandum Potentially Affected AIA Contract Documents AIA Document A AIA Document B Important Information

CHAPTER 2 CONTRACT STRATEGY

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

General Conditions Of Contract for Use in the Procurement and Erection of Plant at Site in the United Kingdom

Engineering Council of South Africa

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

FIDIC's New Suite of Contracts - Clauses 17 to 19 Risk, Responsibility, Liability, Indemnity, Insurance and Force Majeure

How To Write A Contract

ICE Legal Notes Series

ENHANCEMENT CONTRACTS - AVAILABILITY OF INSURANCE TO NETWORK RAIL

Chartered Architectural Technologists: Client information for domestic projects

Managing construction procurement risks

GUIDELINES FOR AUGUST 1995

Construction Claims in

Procurement Strategy and Contract Selection

OFFER BY WPP GROUP PLC ("WPP")

Recommended Good Practice for. contractor SAFETY CSI. World Business Council for Sustainable Development

New Build Problems the Professional Consultant s Certificate

North American Development Bank. Model Prequalification Document: Prequalification of Contractors

FIDIC CONDITIONS OF CONTRACT AS A MODEL FOR AN INTERNATIONAL CONSTRUCTION CONTRACT

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

unidentified motor vehicle, by the Association of Traffic Insurance Companies.

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

NEC3 Engineering & Construction Contract An Overview

Guidance on the template contract for social impact bonds and payment by results

Public Lecture at Engineers Ireland. How the Public Works Contracts might be used in the Private Sector

How To Design A Project

Guidance Notes for the NEC Engineering and Construction Contract

UNITED STATES DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

NEC3: Early Warning and Compensation Events

Introduction Building project management

Shtokman Development AG

Mandatory Addendum to the Owner/Architect Contract For Projects Funded in Whole or in Part with State Capital Outlay Funds

The matter before FDR relates to a complaint regarding online Forex trading activity between the Complainant and the Scheme Member.

GETTING STARTED WITH THE NEC3

Article. Worlds Apart: EPC and EPCM Contracts: Risk issues and allocation

NEC3: The Engineering and Construction Contract An overview

USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE

COMPLIANCE WITH LAWS, CODES, AND STANDARDS

EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS

SPECIAL CONDITIONS OF EMPLOYMENT/CONTRACT AND NOTE TO TENDERERS/CONSULTANTS

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.

Design Responsibility: What Difference Does It Make? A CostE NW Inaugural Lecture 23 January 2013 Paul Tracey

THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $ EDITION

Transcription:

FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee 1. Introduction FIDIC - the International Federation of Consulting Engineers - published late in 1999 a suite of four new Standard Forms of Contract 2. This new suite comprises 3 Books for major works and 1 for minor: Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer : The Construction Contract Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant, and for Building and Engineering Works, Designed by the Contractor : The Plant and Design/Build Contract Conditions of Contract for EPC/Turnkey Projects : The EPC/Turnkey Contract Short form of Contract : The Short Form. The Books in the new suite are all marked First Edition 1999, and the reason is that they can not be regarded as direct updates of FIDIC's very well-known and widely used Red Book, Yellow Book and Orange Book 3, i.e. respectively: Conditions of Contract for Works of Civil Engineering Construction (1987) Conditions of Contract for Electrical and Mechanical Works including Erection on Site (1987) Conditions of Contract for Design-Build and Turnkey (1995). The suite has now been complemented by the Contracts Guide for the three major New Books. 2. Purpose and Drafting Principles

When drafting these new standard Conditions, the following principles were followed: for engineering construction contracts, between `the Employer' and `the Contractor' primarily for international projects (adjustment for national projects possible) manuals of good engineering practice prepared by engineers for practical use balance between legal precision and practicability, i.e. correct level of detail to cover projects of all sizes and complexity to be equitable to employer and contractor (any imbalance of risks to be clearly stated) provide flexibility for individual contracts 2 parts - General Conditions and Particular Conditions 3. Standardisation and User Friendliness The old Books were not standardised. The New Books should be standardised as far as possible and as user friendly as possible. The `users' will be those preparing documents for a project, and those using them during construction. definitions and terminology are the same in all 3 Books (except for intentional differences) 20 Clause layout and titles are the same (except for intentional differences) wording identical (except for intentional differences) diagrams of typical sequence of events included alphabetical list of definitions clauses included applicable to most (but not all) contracts alternative clauses in Guidance for Preparation of Particular Conditions clauses often interchangeable, i.e. import from another Book data required by General Conditions included in Appendix to Tender (EPCT Part. Conds) simple to delete or not invoke clauses which are not required forms for guarantees, Letter of Tender, Contract and DAB Agreements, etc, included index of Sub-Clauses included But remember: preparation to be done by experienced personnel - not `blind' acceptance! clauses must always be checked for appropriateness, and adjusted where necessary adjustments/modifications to be made in Particular Conditions use Guidance for Preparation of Particular Conditions

4. Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer The New Red Book is similar to - and an update of - the Old Red Book, but with new features: Old Red Book dealt only with civil construction work - the New Red Book covers all types of work designed by the Employer. suitable for all projects where main responsibility for design lies with Employer (or his Engineer) some design may, of course, be carried out by Contractor basically an update of Old Red Book administration of Contract and supervision by Engineer approval of work, payment, etc. certified by Engineer work done is measured, payment according to Bill of Quantities option for payment on Lump Sum basis 5. Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant, and for Building and Engineering Works, Designed by Contractor The New Yellow Book replaces both the Old Yellow Book and the Orange Book: Old `Yellow Book' dealt only with electrical and mechanical construction works (most design being done by Contractor) the Orange Book from 1995 dealt with Design-Build and Turnkey for civil and other construction where majority of design done by Contractor the New Yellow Book covers all types of work designed by the Contractor it therefore updates and replaces both the Old Yellow and the Orange Books (layout of all the New Books follows closely that of the Orange Book) New Yellow Book is thus suitable for all types of projects where main responsibility for design lies with Contractor recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works (the majority of such projects may well be electrical and mechanical works. Many will be a combination of civil, e & m, and/or building) some design may, of course, be carried out by Employer or his Engineer Employer provides `Employer's Requirements' to which Contractor designs

administration of Contract and supervision by Engineer approval of work, payment, etc. certified by Engineer payment on Lump Sum basis, usually against a Schedule of Payments testing procedures usually more complicated than for New Red Book 6. Some Features of the Construction Book and the Plant and. Design-Build Book Identical or similar provisions are included in both Books for many matters: traditional competitive tendering procedures are envisaged and Contract becomes legally effective when Employer issues the Letter of Acceptance in response to the successful Tender alternatively, if no LOA, then on signing of Contract Agreement risk sharing is balanced between Parties, as in Old Red and Yellow Books, e.g. Employer takes risk of `adverse physical conditions' - C14.12 and unforeseeable `operation of the forces of nature' - Cl 17.3(h) and design by Employer - Cl 17.3(g) in addition to war (anywhere), terrorism, riot, & similar (within the country), etc all claims, from either Party, have to follow a strict procedure - Cl 2.5 & 20.1 (see later) Engineer must consult both parties and try to reach agreement if no agreement, Engineer makes fair determination in accordance with the Contract, taking due regard to all relevant circumstances' if not accepted, then Dispute Adjudication Board takes over there is no longer the `Engineer's Decision', it is now the DAB's (except that option still remains for Engineer also to be the DAB) (see later) Engineer is no longer stated to be `impartial' as old Red & Yellow Books he `shall be deemed to act for the Employer', except as otherwise stated - C13.1 however, when he has `to agree or determine' any matter he shall `make a fair determination in accordance with the Contract...' as above-said - Cl 3.5 if Contractor is awarded extra time or Cost for Unforeseeable physical conditions - C14.12 Engineer may review `whether other physical conditions in similar parts of the Works' were more favourable than could reasonably have been foreseen, and these may entitle deduction but, all such deduction shall not result in net reduction of Contract Price Employer must submit - when requested - evidence that he has the finances to pay the

current Contract Price - Cl 2.4 (Applies to all 3 Books) if Employer does not provide evidence Contractor can suspend (or reduce rate of) work - Cl 16.1 - or, if evidence is not received within 42 days, terminate - Cl 16.2 7. Need for a New Book where Final Price is More Certain The Old Books only covered part of the international need. Old Red and Yellow Books recognised for balanced risk-sharing, meaning that: Employer only pays extra when specific risks actually occur Contractor does not have to estimate for unlikely hard-to-value risks BUT final price and time is uncertain market has shown requirement for more certain final price and time in two ways: some Employers have - for many years - changed FIDIC Books balance to place more responsibility on Contractor development of privately financed projects (BOT etc) where lenders want definition of final price and time for such projects Contractor is asked to cover a wider range of risks of final cost and time including often ground conditions, guaranteed result, etc Employers must, however, realise that: essential that Contractors are given adequate time and opportunity to consider and evaluate all information and risks the price for the project will be higher to cover the extra risk-taking Employers will anyway have some risks FIDIC therefore produced this completely New Book for: those projects where Employers want traditional projects with a more certain final price and less Employer-risk BUT as a Book where Parties enter the Contract with full understanding, andacceptance, of the risks (instead of trying to adapt another risk-sharing arrangement) as a common starting point for EPC 4 /Turnkey type projects, usually with private financing, in a BOT or similar environment the EPCT Book is thus intended to be suitable for the many projects, both larger and smaller: particularly E & M and other process plant projects all types of employers

often civil law countries where government employer or private developer wants his project on a fixed price turnkey basis and with strictly two-party approach (i.e. no Engineer) EPCT Book includes an `Introductory Note' where these matters are discussed. 8. Conditions of Contract for EPC/Turnkey Projects (Silver Book) EPCT is a completely new Book responsibility for design lies solely with Contractor Employer provides `Employer's Requirements' to which Contractor designs Employer's Requirements usually `performance specification' type Contractor carries out all engineering, procurement, construction providing a fully-equipped facility, ready for operation at `the turn of a key' no Engineer - instead it is the Employer Employer may appoint an Employer's Representative lump sum Contract Price (but adjustments in limited specified cases) interim payments as work proceeds, usually against a Schedule testing procedures including Tests after Completion all claims, from either Party, have to follow a strict procedure Employer must consult with Contractor to try to reach agreement if no agreement, Employer makes fair determination in accordance with the Contract, taking due regard to all relevant circumstances' if not accepted, then Dispute Adjudication Board takes over Contractor takes majority of risks, Employer pays more to cover such risks final price and time of completion should be more certain 9. Circumstances Governing Use of EPCT Book Circumstances for use of the Silver Book are somewhat different from traditional projects: Employer's Requirements should describe principle and basic design of the plant on a functional basis (i.e. performance specification) procurement procedures are different: tenderers permitted and required to verify all information and data and make other

investigations, which may require considerable time tenderer may also have to carry out preliminary design, also time and money therefore often an early reduction to a small number of tenderers tendering period has to permit discussions, at least with `preferred tenderer(s)', about technical matters and commercial conditions Contractor should be given freedom to carry out Works in his chosen manner as long as end results meet specified performance criteria Employer should exercise limited control and not interfere however Employer will want to know that progress is following time programme, work is up to quality, third parties are not disturbed, performance tests are met with, and other Employer's Requirements are adhered to Contractor has to prove reliability and performance of completed project, therefore emphasis on testing, often over considerable period privately-financed projects subject to more negotiation than public and therefore more likely to change standard conditions - but a standard form is necessary anyway as a starting point. These Conditions are not suitable in following circumstances: if time or information is insufficient before Contract signature if considerable work underground or difficult to inspect if Employer intends to supervise closely or control or review if an intermediary determines interim payments where part of Works is designed by Employer for public bidding without negotiations for such circumstances P&DB should be used instead EPCT Book has come because of market demand - given free choice FIDIC would recommend use of P&DB with its balanced risk sharing 10. Comparison of Salient Features of Plant and Design-Build and EPC/Turnkey Books For EPCT the intention is that all matters that could cause a price change (incl. time change) should - as far as possible - be sorted out and agreed before Contract signature to ensure firm final price. Notable differences between these two Books - apart from the extra risks allocated to the Contractor - include (inter alia) the following: for P&DB usually the best tender is accepted by a LOA. For EPCT typically becomes

legally effective on signing the Contract Agreement Employer administers the Contract - unless he appoints an Employer's Representative interim and final payments are made without certification, usually Schedule of Payments under P&DB the Engineer may issue necessary instructions - Cl 3.3. Under EPCT the Employer may only issue an instruction if he can state the obligations in the Contract to which it relates C1 3.4 both Books require the Contractor to design the Works to `befit for purpose' - Cl 4.1 to enable the Contractor to accept this requirement he has to have complete information and sufficient time to scrutinize, verify and evaluate all relevant data. This is allowed for as follows: In P&DB Employer is ultimately responsible for his Employer's Requirements Cl 1.9. However Cl 4.10 requires the Tenderer to obtain all information etc `to the extent which was practicable (taking account of cost and time)' before submitting the Tender Then, after Contract signature, he has a scrutiny period within which to find out any errors, faults or defects in Employer's Requirements (as an experienced contractor exercising due care would have discovered). Cl 5.1 Any such error entitles a variation. In EPCT 5, the Contractor-to-be is expected - before Contract signature - to have verified and interpreted all data from the Employer - C14.10 - and obtained all other necessary information - Cl 4.12 - and thus - on Contract signature - takes over all responsibility both for the design as well as for the accuracy of the Employer's Requirements (including design criteria and calculations) - Cl 5.1 Except that the Employer remains responsible for the matters under (a)-(d) of Cl 5.1, i.e. basically matters which Contractor cannot verify. EPCT does not allow for `Unforeseeable Physical Conditions' - Cl 4.12, but the Book is not suitable when such unforeseeable matters constitute an appreciable risk 6. both Books require final operation and maintenance manuals before taking-over - Cl 5.7 EPCT does not allow for time extension for exceptionally adverse climatic conditions or unforeseeable shortages of personnel or Goods due to epidemic or governmental actions -Cl 8.4 both Books allow for time extension for unforeseen delay by authorities - Cl 8.5

EPCT does not allow partial taking-over or early use by Employer - Cl 10.2 EPCT does not anticipate price adjustment for rise in costs - Cl 13.8 11. Conclusion By the introduction of this suite of 3 matching new standard forms for major contracts, together with the `Green Book' for minor works contracts (and, indeed, the Dredging Form), FIDIC has updated and widened the scope of its standard forms. It is believed and hoped that one or other of the suite will be suitable for use on virtually every international engineering construction project, from minor projects, through the whole range of traditional civil, electrical, mechanical and other plant contracts, to the large complex multi-disciplinary projects, including those of BOT or similar type. As regards which Book to select for any particular project, guidance is given in the Introduction to the FIDIC Contracts Guide. 7 1 SWECO International, Box 34044, SE 100 26 Stockholm, Sweden. (Tel.: +468 695 6059 E-mail: christopher.wade@sweco.se) 2 Available from FIDIC Bookshop, POBox 86, CH-1000 Lausanne 12, Switzerland. http://www.fidic.org 3 Also available from FIDIC 4EPC= engineering, procurement, construction (US) which is approx same as Turnkey (European) 5 where traditional competitive bidding procedures between more than a few tenderers are normally not appropriate, and where some negotiation is necessary and permitted 6 Introductory Note to EPCT, last para. 7 The FIDIC Contracts Guide, 2000, with detailed guidance on using the First Editions of FIDIC's 3 major New Books C.Wade - Overview FIDIC Conditions SWECO International 2003-11-27