paragraph 3(e) introduces a new requirement upon the information licensee to provide the licensee s best view of the capacity, about the



Similar documents
Duncan Burt Head of Commercial Operation National Grid. The Office of Gas and Electricity Markets 9 Millbank London SW1P 3GE

Cross-Border Cost Allocation application submitted by Gaslink Independent System Operator Ltd: Final decision

Joint European Standing Group (JESG) This note sets out the headlines of the most recent meeting of the Joint European Standing Group (JESG).

SCOPING TOWARDS POTENTIAL HARMONISATION OF ELECTRICITY

Strengthening APRA s Crisis Management Powers. ASX Submission

Cost Benefit Analysis for Electricity Balancing general methodology

BETTA open letter on likely late issuance of offers under standard licence condition C18 of the electricity transmission licence

Customers and Other Interested Parties Direct Dial:

Network Code on Harmonised Transmission Tariff Structures for Gas

June Position Paper Contribution to the debate on electricity market design and capacity markets

DTI Consultation on Proposals for a Special Administrator Regime for Energy Network Companies Ofgem s Response

Network Code on Forward Capacity Allocation Explanatory Document of Changes in the Resubmitted Version 2 April 2014

January Eurogas Views on the Energy Union and Enhancing Supply Security

European Distribution System Operators for Smart Grids

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Opening the CfD support scheme to non-uk renewables projects

Completion of the Internal Energy Market. Transport, Telecommunications and ENERGY Council meeting Brussels, 9 December 2014

ACER. oj L 211, , p J L 211, , p RECOMMENDATION Of THE AGENCY FOR THE COOPERATION OF ENERGY REGULATORS No 02/2014

Data Communications Company (DCC) price control guidance: process and procedures

United Kingdom Competition Network (UKCN) Statement of Intent

What can be learned from PCIs for a European Energy Governance? Berlin, 01. Juli 2014 Antina Sander

A new electricity market for Northern Ireland and Ireland from Integrated Single Electricity Market (I-SEM)

EURELECTRIC presentation. EURELECTRIC contribution to a reference model for European capacity markets. DG COMP workshop 30 June 2015

Ofgem s Consultation Gas transmission charging review: Part II our assessment of potential impact

ACER call for comments on the Network Code on Emergency and Restoration

Electricity market reform: policy overview

Memorandum of understanding on a. Joint approach to address the natural gas diversification and security of supply challenges

EMR: Consultation on industry code and licence modifications

Final Draft Framework Guidelines on Capacity Allocation and Congestion Management for Electricity Ref: E10-ENM February 2011

Standard conditions of the Electricity Distribution Licence

CAPACITY MECHANISMS IN EU POWER MARKETS

Getting more connected

Future Trading Arrangements 3 rd Forum. Giuseppina Squicciarini 18/11/13

ESRI Research Note. The Irish Electricity Market: New Regulation to Preserve Competition Valeria di Cosmo and Muireann Á. Lynch

The Levy Control Framework

Wholesale Leased Lines: Review of Price Controls. Initial Notice Proposed directions to JT (Jersey) Limited

Pilot Framework Guidelines on Electricity Grid Connection Ref: E10-ENM December 2010

How To Mitigate Market Power

An Implementation Date for Alternative Modification P169 of 10 Working Days after the Authority s decision;

Government response: EMR consultation on industry code and licence modifications

Cost Benefit Analysis for Electricity Balancing ISP harmonisation scoping paper

Annex 1 Tool for the demonstration and assessment of additionality

How To Create A Power Market In European Power Markets

Implementation Date: 5 working days after Authority Decision. Background to the modification proposal

1. What are your views on Ofcom s proposed priorities for 2007/2008?

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

Below are our responses to the questions included in Appendix 4 of the consultation document.

IMPACT OF GB S ELECTRICITY MARKET REFORM ON INTERCONNECTIONS, CONSEQUENCES ON NORDIC MARKET Michel Martin, 3 April 2014

ELECTRICITY DISTRIBUTION LICENCE: STANDARD CONDITIONS

Structuring Green Electricity Investment in Europe: Development Scenarios and Application to the North and Baltic Sea Grid

Regulatory Financial Reporting. Final Statement

1. The Modification Proposal

Governance of electrical standards Final proposals

Electricity settlement reform moving to halfhourly

We appreciate your feedback

Study to support the definition of a CBA methodology for gas

Viking Link Interconnector

European Wind Integration Study (EWIS) Towards a Successful Integration of Wind Power into European Electricity Grids

European best practice regarding to the licensing in the energy sector

Consultation Paper. ESMA Guidelines on Alternative Performance Measures. 13 February 2014 ESMA/2014/175

DISCLOSURE NOTES. How the accounts are presented. Generation

Single Electricity Market. Acquisition of NIE plc, NIE Powerteam and allied businesses by ESBNI Ltd

Case No COMP/M CENTRICA/ BORD GAIS ENERGY

Electricity Balancing Services

CER Response to Government Consultation on Green Paper on Energy Policy in Ireland

ESB NATIONAL GRID RESPONSE TO CER/03/266 INTERCONNECTOR TRADING PRINCIPLES IN THE MAE

Standard conditions of the Electricity Distribution Licence

Operational Security Network Code

Energy Union and 2030 Energy & Climate Governance. A EURELECTRIC position paper

UK renewable energy an update

Ownership of Transmission Assets in Scotland

Date and time of 12 February 2014 at 14:15pm Location Ofgem s offices, 9 Millbank, London SW1P 3GE

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

Part B1: Business case developing the business case

Anthony Price Swanbarton Limited, Dairy Farm, Pinkney, Malmesbury, Wiltshire, SN16 0NX Telephone

E-MEX Panel Update March 2014

4. Comparison with DECC (2014) Estimated impacts of energy and climate change policies on energy prices and bills

Tackling Bad Debt in the Water Industry

FSR Annual Conference: Future Trends in Energy Market Design. The regulatory dimension: a roundtable of senior regulators

Network Capability Proposal

Harmonisation of electricity generation transmission tariffs. A EURELECTRIC contribution to ACER s scoping exercise

Clean Energy Council submission to Queensland Competition Authority Regulated Retail Electricity Prices for Interim Consultation Paper

ENTSO-E Network Code on Emergency and Restoration

Caithness-Moray Needs Case Consultation

Clarity of fund charges

Non Traditional Business Models: Supporting transformative change in the energy market

COMMISSION STAFF WORKING DOCUMENT SUMMARY OF THE IMPACT ASSESSMENT. Accompanying the document

Rule change request. 18 September 2013

Public Consultation Paper: Payment Accounts Directive. Department of Finance. July 2015

EBA final draft Regulatory Technical Standards

of2o July of Transmission System Operators for Electricity

CCS Roadmap. The regulatory framework

Annex 2: Supplementary response to CAA Final Proposals

NIRIG response to EMR: Consultation on Proposals for Implementation

APHA Response to the Draft Report (Sept 2014) The Competition Policy Review Australian Private Hospitals Association ABN

BERMUDA MONETARY AUTHORITY

Debt in depth: the cost of debt in regulatory determinations

Ministerial Council on Energy. Reform of Energy Markets

Ref. Ares(2014) /05/2014. l(5)vodafone.com>

BRIEF POLICY. Cost-benefit analysis for gasinfrastructure. Authors: Nico Keyaerts, Jean-Michel Glachant. Issue 2014/03 February 2014.

Transcription:

Respondent details: Jonny Hosford, National Grid European Business Development Telephone: 07776 448231 email: jonny.hosford@nationalgrid.com No. Condition number Condition name Page/Paragraph Ref Comments 1 C11 Production Page 19, Paragraph Comment 1. The proposed standard licence condition C11, of 3(e) paragraph 3(e) introduces a new requirement upon the information licensee to provide the licensee s best view of the capacity, about the location and timing of the connection of new national interconnectors that could provide value for GB consumers. electricity We believe the test value to GB consumers is too narrow transmission and instead the test should be consistent with the licensee s system prevailing obligations to promote the development of an efficient, co-ordinated and economical system of electricity transmission. This change is necessary because: (i) GB consumer welfare is just one element of the correct total surplus approach which should be used to properly consider the economic benefit of interconnection. The total surplus approach requires the consideration of producer and consumer surplus (at both ends of the link) together with interconnector congestion rent. Therefore a narrow focus on GB consumer surplus will not lead to the identification of the desired efficient level of interconnection; Suggested alternative drafting the licensee s best view of the capacity, location and timing of the connection of new interconnectors that could provide value for GB consumersto promote the development of an efficient, co-ordinated and economical system of electricity transmission. This should take into account the impact on GB wholesale prices, security of supply, the provision of ancillary services, constraint management and other operational considerations (ii) As proposed the licence condition would enshrine a fundamental inconsistency between the GB regulatory regime and undertakings that the UK Member State has made in support of European Energy policy objectives such as the Single Electricity Market, and the 20% interconnection target by 2020; 1

(iii) (iv) It should be recognised that most interconnector projects either already are denoted as Projects of Common Interest (PCI) or are likely to become designated as such pursuant to regulation 347/2013 EC. The tests for PCI candidacy are based on the results of ENTSO-E harmonised energy system-wide costbenefit analysis at Union level (ref Article 11) and to the extent PCI project promoters incur higher risks in relation to these projects then the Member States and national regulatory authorities shall ensure that appropriate incentives are granted (ref Article 13). It would be highly inappropriate to instigate any elements of domestic regulation that create GB misalignment with the pan-european business drivers for interconnector development; A narrow focus on value for GB consumers would be incompatible with pan-european transmission system development practices as co-ordinated through ENTSO-E s Ten Year Network Development Plan (TYNDP) process (a process which itself has the endorsement of ACER and OFGEM). The whole point of the TYNDP is to promote the identification of an economic level of European transmission capacity anchored on principles (and detailed methodologies) of pan-european socioeconomic cost benefit analysis. The SO would be placed in the awkward position of preparing analysis on one basis for OFGEM (ETYS) and 2

another basis for ENTSOE (TYNDP); (v) Adopting our suggested change will improve consistency with other new conditions elsewhere in the suite of licence modifications which already point to language of efficient, coordinated and economical system of electricity transmission. See for example C27, Paras 1, 4, 8, 14, 15 & 16. 2 C11 Production of information about the national electricity transmission system 3 C27 The Network Options Assessment process and reporting Page 21, Paragraph 13(aa) Part A, Paragraph 8, Page 32 Comment 2. The benefits of increased levels of interconnection upon Security of Supply have been recognised by OFGEM and DECC through recent developments in relation to cap and floor and the participation of interconnectors in the capacity mechanism. It is therefore reasonable to add a reference to security of supply in the (non-exhaustive) list of factors that should be taken into account in considering what constitutes an efficient level of interconnection capacity. Comment 3. The rationale for our proposed changes is the same as described in our Comment 1. Comment 4. In the context of (c)(ii) the word inputs is too narrow a term so we suggest it is widened by adoption of the word impacts. When interconnectors are modelled inputs such as the power transfer capability of the interconnector in question will be relevant but so will the capacity, location and timing of the connection of new interconnectors, having regard to the efficient level of interconnection between the national electricity transmission system and transmission systems in other jurisdictions that could provide value for GB consumers. (c)(ii) the approach used for modelling boundary capacity, offshore transmission capacity and interconnection inputs impacts along with assumptions 3

requirements outputs which can be much more far reaching than just the advent of additional transmission capacity. This is because the interconnector also behaves like an additional source of generation or demand. Unlike transmission-only reinforcement schemes, the effect of additional interconnection may include for example the security of supply benefits of access to new & diverse sources of generation to meet demand, and new opportunities for sharing ancillary services across borders. Comment 5. In the context of (d) we suggest the addition of the reference to benefits because the benefit modelling is equally important to the cost modelling. In the interests of transparency it is important that data sources and assumptions are also clearly identified. This should allow independent transmission developers to fully understand the basis of the modelling, reproduce similar results and undertake their own analysis against alternative assumptions. Comment 6. Running throughout the suite of proposed licence modifications there is a general lack of clear intent to harmonise and streamline GB and European processes. Lack of continuity should be avoided because it acts as a barrier to the developer led regulatory model for interconnector development. For example developers attempts to identify the need for future interconnection are not assisted if GB planning assumptions such as Future Energy Scenarios are not consistent with European planning assumptions such as ENTSO-E Visions. We have therefore proposed certain chances / additions such as this para 8(g) to strengthen the vision for closer alignment between European and GB processes. and assessment criteria used; (d) The basis for the cost and benefit estimates provided for each option and the identification of data sources and assumptions (g) how the NOA process will have regard to the need case for interconnection in the most recent ten year network development plan 4

4 C27 The Network Options Assessment process and reporting requirements Page 34, Part B, Paragraphs 14(a)(i) & 14(b) and Part C, Paragraph 15(a) Comment 7. These additional references to TYNDP (as with comment 6) help to ensure the relevance of the NOA report in the context of pan-european co-ordinated electricity network development. 14 (a) (i) The licensee s best view of the options for Major National Electricity Transmission System Reinforcements (including any Non Developer-Associated Offshore Wider Works that the licensee is undertaking early development work for under Part D), and additional interconnector capacity that could meet the needs identified in both the ten year network development plan and the electricity ten year statement (ETYS) and facilitate the development of an efficient, co-ordinated and economical system of electricity transmission. 14 (b) be consistent with both the ten year network development plan and the ETYS; 5 C27 The Network Options Assessment Page 37, Part C, Paragraph 17(b) Comment 8. The additional reference to security of supply is for the same reasons as cited in Comment 2. 15 (a) with information and analysis to support them in their decision-making and development of options to meet system needs as identified in both the ten year network development plan and the ETYS. This must include the licensee s assessment of the impact of new interconnectors on system operation. This should 5

process and reporting requirements Comment 9. The additional reference to producers and interconnector operators is intended because of the need to consider the total surplus approach to economic modelling as described more fully in our Comment 1. include costs and benefits relating to security of supply, provision of ancillary services, constraint management and other operational factors which may accrue to the licensee and to, producers, consumers and interconnector operators; and Response template for consultation on licence modifications to enhance the role of the System Operator 6