District of Columbia Water and Sewer Authority George S. Hawkins, General Manager



Similar documents
9 Recommended Plan. 9.1 Introduction. 9.2 Recommended Plan

3 Analysis of July and September 2012 Flood Events

CLIMATE ADAPTATION AND MITIGATION AT DC WATER

DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY. a guide to PREVENTING SEWER BACKUPS AND FLOODING

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

AN ACT IN THE COUNCIL OF THE DISTRICT OF COLUMBIA

The Clean Water Project What Is The Stormwater Impact?

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

AN UPDATE ON LOUISVILLE MSD s BASEMENT BACKFLOW PREVENTION PROGRAM 10 YEARS AND 6,700 INSTALLATIONS LATER

Executive Summary Consent Decree

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000

Kansas City s Overflow Control Program

Basement Flood Risk Reduction City of Winnipeg. Charles Boulet

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary

SANITARY SEWER BACKUP. Causes & Prevention

a guide to PREVENTING HOME FLOODING DURING STORMS

CITY OF HIGHLAND PARK, ILLINOIS Stormwater Management Fact Sheet

City and County of San Francisco 2030 Sewer System Master Plan TASK 400 TECHNICAL MEMORANDUM NO. 405

Beechmont Park Project

Update on the Metro Nashville Consent Decree Program. Scott Potter Ron Taylor

Understanding Your An Introduction to the Chicago Area s Combined Sewer Systems

PREVENTING WET OR FLO ODED BASEMENTS

Lansdowne Stormwater UPDATE

First in Service First in Safety

Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No.

Review of Footing Drain Disconnection Projects

How To Build A Backwater Valve

Integrated Water Management in Maryland. Anwer Hasan, Senior Vice President

Home Drainage & Causes of Basement Flooding. Water

Flood Protection Tips

ELIMINATE STORM WATER FROM ENTERING SANITARY SEWER SYSTEMS

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

M I D W E S T S O C I E T Y F O R T R E N C H L E S S T E C H N O L O G Y. Kansas City, Missouri s Trenchless Program

Micromanagement of Stormwater in a Combined Sewer Community for Wet Weather Control The Skokie Experience

Impact of July 8, 2013 storm on the City's Sewer and Stormwater Systems

ORDINANCE NO. 511 ORDINANCE ESTABLISHING A COST REIMBURSEMENT PROGRAM FOR THE INSTALLATION OF OVERHEAD SEWERS OR BACKFLOW PREVENTION DEVICES

BASEMENT FLOODING. Prevention Guide for. Homeowners

Omaha Combined Sewer Overflow (CSO) Control Program

Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1

FY 2016 Proposed Capital Improvement Program

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

Thanks to its newly issued federal stormwater permit, Washington,

Sewer Flooding Alleviation in the Counters Creek Catchment

Sanitary Sewer Master Plan

CHELTENHAM TOWNSHIP. SANITARY SEWER UPDATE Public Works Committee Meeting September 7, 2010 Curtis Hall

Sanitary Sewer Overflow Annual Report

Implementation of the New York City Wastewater Resiliency Plan: Opportunities And Lessons Learned

Toronto s Wet Weather Flow Master Plan

Summary of Potential Storm Drain Projects and Programs

foundation designed to keep water out of the basement.

SUMP PUMP. City of Ann Arbor & C O L L E C T I O N S Y S T E M G L O S S A R Y

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

Flood Emergency Response Planning: How to Protect Your Business from a Natural Disaster RIC005

Green Infrastructure in Action: Examples, Lessons Learned, and Strategies for the Future

JULY 24, 2009 WEST-END FLOODING INVESTIGATION ACTION PLAN. Presentation to Insurance Companies 19 January 2012

minimum deductible may be increased significantly.

Appendix B. Property Owner Questionnaire

Stormwater Control Measures for Tokyo

City of Hillsboro Inflow and Infiltration Elimination Program

Standard Operating Procedures for Flood Preparation and Response

BEFORE THE PHILADELPHIA WATER, SEWER AND STORMWATER RATE BOARD DIRECT TESTIMONY OF STEPHEN J. FURTEK

OVER-HEAD SEWER ASSISTANCE GRANT

INTRODUCTION AND BACKGROUND

PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET

VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES

Protect Your Home From Flooding. A guide for Lethbridge Residents

SAWS SSO Reduction Program

The City has requested that the boundaries of the study area be expanded to include additional areas in the floodplain impacted by the recent storm.

The Metropolitan St. Louis Sewer District. Sewer Overflows In Our Community

Extreme Wet Weather in Brookfield. How to Keep Your Basement Dry During Heavy Rains and Floods

REPORT TITLE: TERM OF COUNCIL PRIORITY NO. 6 - ENHANCE INTEGRITY OF WASTEWATER COLLECTION SYSTEM INCLUDING FLOOD REMEDIATION PROGRAM

Beacon Hill Sewer District Standard Specifications

Flooding and Stormwater in

At the end of today s seminar you should be better. Recognize the causes of Sewer Lateral backup. Identify techniques to protect your home from

LAKES REGION SANITARY DISTRICT COST REIMBURSEMENT PROGRAM FOR THE INSTALLATION OF OVERHEAD SEWERS OR BACKFLOW PREVENT DEVICES

Communicating the Flood Risk

HERE COMES THE RAIN AGAIN Stormwater Management in a Changing Climate at the City of Toronto

What is a CSO / SSO? Sewer Overflows. Prevalence of CSOs in the US. Magnitude of Problem (Local)

Rainwater is directed away from walls at surface. Any water infiltrating is captured in drains below foundation

Lower Raritan Watershed Management Area Stormwater & Flooding Subcommittee Strategy Worksheet LRSW-S3C1

WEST-END FLOODING INVESTIGATION 24 JULY 2009 RAINSTORM EVENT CONSOLIDATED REPORT AND ACTION PLAN

Downspout to storm sewer. Leaky laterals

Protect your home from basement flooding

Chair and Members of the Planning and Public Works Committee. Peter M. Crockett, P. Eng., Commissioner of Planning and Public Works

Sewer and Stormwater Back-ups Policy Adopted by Council October 4, 2010

CHAPTER 3 STORM DRAINAGE SYSTEMS

Purpose and Approach. Introduction

Community of Tavistock July 16, 2005 Flooding Event Questionnaire

How To Install An Overhead Sewer

A Century of Progress with Pride

Protect your. home from. basement. have you done everything you can?

GOVERNMENT OF THE DISTRICT OF COLUMBIA District Department of the Environment *** MS4 LETTER AGREEMENT

EXHIBIT 6 WATER IN BASEMENT PREVENTION PROGRAM PLAN

Summary of Key Changes to Metro Water Services (MWS) Spill and Overflow Response Plan (2007 comparison to 2009)

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.

Downspout Disconnection Program FAQs

5.14 Floodplains and Drainage/Hydrology

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Implementing Green Infrastructure in Atlanta

Transcription:

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager FLOODING ISSUES IN BLOOMINGDALE AND LeDROIT PARK A DC Water Presentation Given to the Mayor s Task Force on the Prevention of Flooding in the Bloomingdale and LeDroit Park Areas August 28, 2012 1

CSO = Combined Sewer Overflow Background What is a CSO? 100% of Suburbs 0% of suburbs 67% of DC 33% of DC 2

Background DC Combined Sewer System Bloomingdale 1/3 of the District is served by combined sewers (12,478 acres) 53 CSO outfalls 15 to Anacostia 10 to Potomac 28 to Rock Creek Three receiving waters Anacostia River Potomac River Rock Creek 3

Background NEB Drainage Area Northeast Boundary Drainage Area (NEB) serves the Bloomingdale l neighborhood h Part of the District s Combined Sewer System One (1) pipe in street serves both sanitary collection and storm water runoff Built-out in the early 1900s Bloomingdale Northeast Boundary Trunk (NEBT) Sewer Major sewer serving the NEB Drainage area Constructed circa 1870-1880 4

Background History of Flooding Flooding occurred soon after NEBT Sewer construction Recognition that sewer capacity was too low Many studies have identified longstanding flooding issues in Northeast Boundary 1955 Sewer Investigation 1957 Board of Engineers 1968 Burns & MacDonald 1997 Alignment Study 1999 NEB Flooding Study 2002 CSO Long Term Control Plan 2006 Bloomingdale Flood Study Bloomingdale (Thomas & Flagler) l is the old stream valley 1860s Map of DC 5

Background Why was Flooding not Addressed in the Past? Bloomingdale Massive scale of project Not constructible without large disruption to neighborhoods and existing infrastructure without tunneling New tunneling technologies have made soft ground tunneling practical Existing NEBT Sewer Section (10-0 Diameter) Existing NEBT Sewer Section (22-0 23-6 ) 6

Background What is Storm Frequency? Long-term average = 10 storms 1,000 years = 1 % chance of 100 year storm Probability of occurrence is 1% in any year, not one storm every 100 years 7

Background Flood Areas Known Chronic Flood Areas W. Virginia & Mt Olivet Rhode Island Metro 1 st & P St, 6 th & R St NW Capacity of Current System (Storm Frequency) Less than 2 yr Less than 2yr Less than 5 yr Character- istic Bowl Bowl Bowl Bloomingdale Less than 5 yr Bowl Harvard & Sherman NW NEBT Sewer ~ 2 yr Hillside Most 2 yr, upper reach <2 yr Existing conditions 15-year 6-hour storm Bloomingdale W. Virginia & Mt. Olivet 8

June/July 2012 Storm Events Intensity Analysis Peak Intensity of June/July 2012 Storms Date 6/29/12 Derecho Duration Rainfall (inches)* NOAA Point Precipitation Frequency (Nearly) 30-min 0.50 < 1 year storm 7/10/2012 0 1-hour 1.96 10 year storm 7/18/2012 30-minute 1.35 5 year storm 7/19/2012 15-min 0.94 5 year storm NOTES: *Bryant Street Station Rain Gauge 9

General Focus Area 10

July 2012 Storm Events Modeling Results July 18th 11

July 2012 Storm Events Modeling Results July 19th 12

July 2012 Storm Events Conclusions Sewers constructed in late 1800s were too small to accommodate development of District The amount of rainfall overwhelmed the sewer system, which resulted in flooding Continuing our detailed assessment and analysis of local sewers (sewer inspection by closed-circuit television camera and walkthrough of sewers) to determine whether present condition of the sewers has measurable impact on flooding 13

DC Water Catch Basin Cleaning Program Approximately 25,000 catch basins in the District Predetermined schedule for cleaning District is divided into 10 Catch Basin Cleaning areas Cleaning done in repetitive numerical order 14

Bloomingdale Catch Basin Cleaning April 2010-Annual Catch Basin Cleaning g( (274 catch basins cleaned) August 2010-Service request (97 catch basins cleaned) April/ May 2011-Annual Catch Basin Cleaning (355 catch basins cleaned) August 2011-Hurricane Irene (191 catch basins inspected and cleaned ) April/ May 2012-Annual Catch Basin Cleaning (371 catch basins cleaned) July 2012-Service request (225 catch basins inspected and cleaned) 15

Bloomingdale/LeDroit Park Action Agenda Information And Communications Launch of Bloomingdale/LeDroit Park specific web page Customer surveys (results next page) Implementation of Bloomingdale/LeDroit email and hotline for customer inquiries Preparatory Assistance Coordination with the DC Department of Public Works (DPW) in sandbag distribution to community prior to anticipated heavy storms Backflow Preventer Rebate Program Engineering Consulting Services Sewer inspection About 30,000 linear feet (1/3 of total) have been inspected by closed-circuit television camera. Remainder by end of Oct. Flood Insurance Program According to the DC Department of the Environment (DDOE) and DC Homeland Security and Emergency Management Agency (HSEMA), Bloomingdale is categorized as a low-risk flood zone area. Reasonable flood insurance is made available through the Federal Emergency Management Agency (FEMA) and its National Flood Insurance Program. 16

Bloomingdale/LeDroit Park Action Agenda 17

Backflow Prevention Device Backflow prevention device protects against basement backups Without Backflow Prevention With Backflow Prevention Manhole Manhole Combined Sewer Basement flooded House Lateral Combined Sewer Basement not flooded House Lateral Backflow Preventer Rainfall overloads sewers backs-up into basement Backflow preventer stops flow from sewer from entering basement DC Water rebate: 90 percent of purchase and installation cost, up to $3,000. Retroactive to July 1. Community workshops: September 6 and 8. 18

Other Floodproofing Measures Basement steps and door barriers protect against flooding from surface overflows 19

Design New Development to Prevent Sewer Backups Other cities have required: New construction to have lowest floor with gravity service be above manhole rim Backflow preventers Basements disconnected from gravity service and equipped with sewage ejector pumps Potential for implementing similar plan in the District 20

Exploring Medium-Term Engineering Solutions 1. Capture and temporary storage of stormwater upstream of the Bloomingdale area at available ailable facilities 2. Installation of a relief sewer at designated portions along NEBT as a way to prevent backups 3. Disconnect connector lines from the main sewer and take flow directly to trunk sewers 4. Convey some flow to another major trunk sewer aside from NEBT 21

Medium-Term: For Discussion with Other Agencies on the Task Force HSEMA Work with DC Water to provide federal disaster relief funding for backflow preventer rebates. DISB Require insurers to identify sewer-backup insurance as an option for homeowner and renter policies? DDOE Consider expanding RiverSmart program to provide rain barrels or other green infrastructure to homeowners in the NEBT sewershed? DDOT Work with DC Water to investigate drainage conditions and number of catch basins along Florida Avenue NW in LeDroit. Possibly improve. Consider alternative traffic plans, including closing Rhode Island Avenue, during flooding events. Investigate some type of inflatable or movable flood wall solution for Rhode Island Avenue? DCRA Work with DC Water to ratify backflow unpermitted preventer installations between July 1 and August 10. Changes to plumbing code? Building code? DMPED Work with DC Water to ensure additional planned development in the NEBT sewershed does not further overload the sewer system with stormwater runoff or residential/commercial wastewater. 22

Long-Term Solution Clean Rivers Project will Provide Flood Relief ANACOSTIA RIVER PROJECTS System of deep tunnels 98% CSO Reduction Tunnels reach into NE DC and Bloomingdale to provide flood relief CSO portion in-service by 3/2018, flood relief by 3/2025 per Consent Decree POTOMAC & ROCK CREEK PROJECTS System of deep tunnels Green infrastructure is being evaluated 93% CSO Reduction In-service by 3/2025 23

Long-Term Solution Anacostia River Projects Northeast Boundary Branch Tunnel (Preliminary Engineering) Northeast Boundary Tunnel (Preliminary Engineering) Schedule specified by Consent Decree with EPA Schedule influenced by affordability concerns (rate impacts) Stipulated penalties for failure to meet specified schedules Construction of tunnels in the NEB area to alleviate flooding Tunnels act as relief sewer that controls flooding in the NEB area DC Water performing preliminary engineering for NEB area now Place facilities south of RFK stadium in operation by 2018, remainder by 2025 Blue Plains Tunnel (Construction) Tingey St Diversions (Procurement) Main PS Diversions (Design) Poplar Point PS (Design) M St Div. Sewer (Construction) CSO 007 (Construction) Anacostia River Tun. (Procurement) CSO 019 (Construction) A Blue Plains Tunnel C CSO 019 Overflow and Diversion Structures D JBAB Overflow and Potomac Outfall Sewer Diversion E M Street Diversion Sewer (CSOs 015, 016 and 017) G CSO 007 Diversion Structure and Diversion Sewer H Anacostia River Tunnel I Main Pumping Station and Tingey Street Diversions J Northeast Boundary Tunnel K Northeast Boundary Branch Tunnels L Northeast Boundary Diversions M Mt. Olivet Road Diversions 24 Y Blue Plains Dewatering Pumping Station and ECF 24 Z Poplar Point Pumping Station Replacement

Long Term-Solution Magnitude of Clean Rivers Project Tunnel Boring Machine is 26-ft in diameter to construct a 23-ft diameter tunnel Tunnel length: Blue Plains to NEB = 13miles l Tunnel is slightly larger g than existingg NEBT Sewer 25

Long-Term Solution NEB Tunnels Address Flooding Areas Flooding Areas NEB Tunnels Existing Sewers Howard University McMillan Reservoir Bryant Street PS Glenwood Cemetery USPS Facility Home Depot McKinley Tech Gallaudet University 26

NEB Tunnel Design and Construction Long-Term Solution Cost and Schedule Dates Preliminary Engineering and Procurement 2012 2017 Construction 2018 2025 Place into Operation 2025 DC Water is looking into the potential to accelerate, but the current schedule is ambitious. Support and collaboration from entire District Government is key to meeting deadlines. 27

Questions? 28