METHOD STATEMENT FOR INSTALLATION & STRESSING OF PERMANENT GROUND ANCHOR

Similar documents
METHOD OF STATEMENT FOR STATIC LOADING TEST

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

Dr. Jesús Gómez, P.E. 36th Annual Conference on Deep Foundations, Boston, MA

Pro-Lift Steel Pile Foundation Repair

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

HUS-V Screw anchor. HUS-V Screw anchor. Basic loading data (for a single anchor) Mean ultimate resistance

PILE TESTING SPECIFICATION

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Guidelines For Sealing Groundwater Wells

COMPETENCY ANALYSIS PROFILE. Rodworker 452A. (All unshaded skill sets must be demonstrated/ completed) Lift equipment and materials

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

TZ WEDGE ANCHOR FOR CRACKED AND UNCRACKED CONCRETE

Hilti HIT-HY 200 with rebar

The International Workshop on Micropiles, 2007

Chapter. Restoration of Damaged Structures

Post Grouted Single Bore Multiple Anchors at Hodenpyl Dam, Michigan

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

Design and Construction of Cantilevered Reinforced Concrete Structures

Operations and Instruction Manual Might Swivel - Part # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn

Section SEWER PIPE INSTALLATION AND TESTING

GLOSSARY OF TERMINOLOGY

PERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.

KWANG SING ENGINEERING PTE LTD

Article 10 - ADMINISTRATIVE SECTION

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

Hilti HIT-HY 150 MAX with rebar

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Embedded Parts Introduction - Anchors

SECTION GUARDRAILS

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

DESIGNING STRUCTURES IN EXPANSIVE CLAY

Technical Information

VOYAGER 570G. 744A Sprayer Control

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SERIES NG 1800 STRUCTURAL STEELWORK

HUS-A 6 / HUS-H 6 / HUS-I 6 / HUS-P 6 Screw anchor in precast prestressed hollow core slabs

RAUFOSS EXPLOSIVE COMPRESSION FITTINGS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

Standard Test Procedures Manual

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Geotechnical Investigation Test Report

Paper The relation of Micropile Diameters in case of Pressure casting and non-pressure casting (30)

Method Statement for Static Load Testing (Compression) for Micropiles

SECTION SUPPORT OF EXCAVATION

Flow Measurement Options for Pipeline and Open Channel Flow

Fiberstars Mini Lighted Laminar Flow Fountains

SELECTION, APPLICATION & MAINTENANCE

SECTION 1 GENERAL REQUIREMENTS

FAG Hydraulic nuts. Technical Product Information

Dead load (kentledge) A structure over the test pile. Ground anchorage either by tension piles or ground anchors. Bi-directional (Osterberg-cell)

How To Retaining Wall Guide

Meter Technician Certification Exam

Elo Touch Solutions Wall-mounting Kit for the 5501L IDS Touchmonitors

PART E SPECIFICATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

Building Pit Roche Building 1 Basel, Switzerland

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Operating Instructions Drill rig DRU160

DESCRIPTION OF WORK:

Standard terms and conditions

European Technical Approval ETA-07/0046

INSTALLATION INSTRUCTIONS

WiMo Antennen und Elektronik GmbH Am Gäxwald 14, D Herxheim Tel. (07276) FAX

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

E-Line and Braided Line. E-Line Open Hole wireline

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

1.2 Advantages and Types of Prestressing

Time- Cost Benefit Analysis for Anchor Type Foundation in Transmission Towers

DYNAMIC TESTING OF MICROPILES. COMPARISON OF STATIC AND DYNAMIC TEST RESULTS

CONTENTS 1. INTRODUCTION METHODOLOGY RESULTS & FINDINGS...9 APPENDIX

How to build a Pizza Oven in 4 days

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

HVU with HAS/HAS-E rod adhesive anchor

High Strain Dynamic Load Testing of Drilled Shafts

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON SOIL TEST FOR PAVEMENT DESIGN

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

How To Safely Dig For Natural Gas

Submittal Information

Acceptance Codes APPENDIX - A. Acceptance Criteria

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Hilti KWIK HUS-EZ I (KH-EZ I) Internally Threaded Carbon Steel Screw Anchor

Product catalogue, abrasive cutting

The Work at Height Safety Association. Guidance on inspecting eyebolts used for personal fall protection purposes

number 2) proposed well's type, location, elevation, total depth, etc. 3) site inspection, 2) assess the adequacy of the proposed engineering

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Policy on Water Heater Installations Policy No. UPC Effective: September 1, 1995 Revised: February 10, 1996

LAYING BLOCK AND BRICK

Transcription:

METHOD STATEMENT FOR INSTALLATION & STRESSING OF PERMANENT GROUND ANCHOR A. DEFINITIONS a) Ground Anchors An installation consisting basically of a stressing anchorage, a tendon and fixed anchor, which is capable of transmitting an applied tensile load to a load bearing stratum, for the specified duration of the structure in which it is required to withstand the design load. b) Anchor Head Anchor head is that part of the ground anchor which transmits the thrust against the face of the structure to be supported through steel anchor plates or other approved materials. c) Tendon This is part of the ground anchor connecting the anchor head and anchor bond length which comprises of dia 15.2mm strands with breaking load not less than 260 KN. d) Fixed Anchor Length This is the length of anchorage over which the tensile load is transferred to the surrounding ground. It shall be constructed outside the zones of active soil failure. e) Free Anchor Length This is that length of tendon which transmits no load to the surrounding strata. f) Tendon Bond Length This shall be the length of the tendon which is effectively bonded directly to the Grout. g) Design Load This is the working load (WL) in the line of the anchor.

B. INSTALLATION METHOD 1. Drilling & Cleaning of Hole Boreholes are to be drilled with wash boring drilling method to the required lengths. Temporary casing is to be used where the ground is likely to collapse. A drag bit or casing drill can be used to drill the hole according to the specified diameter, Holes are to be flushed with water/air after drilling to a reasonable cleanliness. 2. Installation of Cables The strands used shall be 0.6 nominal diameter strand. All strands are to be cut to length and tied together with tie wire at approximately 2.0 meters centres. Plastic centralisers are to be fixed to the cable 3.0 metres centre to centre over the entire length of the cable. Free tendon length or strand free length shall be sheathed with a suitable plastic hose. This bond length shall be loosened (unwire) and cleaned before insertion of anchor into drilled hole. The fixed tendon length shall also have centralisers at 3 metres centres. If for any reason the cable cannot be installed to the correct depth and blowing air and water through the primary grout pipe does not free the cable, it should be withdrawn and the hole re-drilled. When the cable is installed, the hole is to be cleaned again by flushing clean water through the primary grout pipe until reasonably clean water flows out from the top of the hole. 3. Grouting of cables. Primary grouting must be carried out on the same day as cable installation (See Appendix A for mix proportion)

A primary grout pipe is to be tied to the cable and should reach within 0.5m to the bottom of the hole. This grout pipe is withdrawn progressively during primary grouting. The Grout is to be mixed for approximately two minutes in a mechanical mixer and pumped into the hole through the primary grout tube. Pumping shall continue until the flushing water is displaced with grout of even consistency flowing out of the drill hole. Six grout test cubes (100x100 mm) shall be taken for each day of grouting. Three cubes shall be tested on the 7 th day after grouting. Stressing may be permitted if the cube strength reaches 18 N/mm 2. The second set of three cubes shall be tested on the 28 th day after grouting. NOTES a) Anchors shall be formed in such a manner as to ensure that no damage will be sustained by previously formed anchors in adjacent positions. The minimum spacing between ground anchors shall be 3 time anchor diameter. b) The anchors shall be handled on site and inserted into the boreholes without being damaged. c) Holes for the anchors will be drilled to the required depth and diameter in the type of anchorage zone specified. d) Contractor shall ensure that casings for drilling are readily available for use when needed. e) The assembled tendon will be inserted into the hole. f) Grouting will be by tremie system through a Grout tube and the bore hole shall be filled up to the top. g) Anchors shall not be loaded until 7 days after grouting. h) After the Grout strength has reached its required design strength (normally after 7 days), the stressing anchorage is placed is then proof loaded to 1.25 time working load.

The anchor will be locked off at 1.1 times working load to allow for setting in of wedges and for time dependent load losses to take place without adversely affecting the capacity of the anchor. C. TESTING PROCEDURES i) Proof Tests 2 anchors shall be subjected to routine acceptance test, test load shall be 1.50 of WL and carried out in stages as follows: 1st stage - stress to 0.50 WL 2nd stage - stress to 1.00 WL 3rd stage - stress to 1.50 WL and lock off at 1.1 WL At each state the load shall be held for 5 minutes. j) Failure Criteria An anchor is deemed to have failed if: * The anchor fails to hold the load. * During any part of the load procedure the applied load produces a constant rate of anchor movement. All anchors that have failed shall either be: Down graded to a load and additional anchors to be installed to restore the affected anchoring system to original design requirements. k) Accuracy of Measurement The whole load shall be measures on a single pressure gauge calibrated in divisions not more than 10% of the minimum applied load on the constructed anchors. Extension shall be measured to an accuracy of 1 mm.

APPENDIX A MIX PROPORTION FOR GROUTING PERMANENT ANCHORS Water : Cement ratio is 0.45 1. Primary Grout Mix Proportions Grout Mix The proportions of Grout and the minimum strength of work cubes shall comply with the following requirements: Range of water/cement ratio : 0.40 to 0.45 Cube crushing strength at 7 days after mixing : 20 N/mm 2 Cube crushing strength at 28 days after mixing : 30 N/mm 2 minimum Site Mix workers shall take these parameters : Water Cement - 22.5 Litres - 1 bag (50 kg)