HTC Sweden AB. Concrete and Pouring Techniques. Betong och gjutteknik. Case study HTC Sweden AB. Professional Floor Grinding Systems

Similar documents
Guidelines for Durable Driveways, Carports Patios, Walks, Garage Floors

LAYING BLOCK AND BRICK

CORROSION ENGINEERING RESIN-BASED POLYMER CONCRETES AND GROUTS

Construction Specification for Concrete Curb and Concrete Curb and Gutter

PROPERTIES AND MIX DESIGNATIONS

:: ARTIFICIAL SAND :: Zone One Sand : Zone Two Sand :

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

These recommendations generally follow the Construction Specifications Institute (CSI) Master Format.

Lab 1 Concrete Proportioning, Mixing, and Testing

kalox-pool draft 231 repairing refurbishing and finishing KALOX-POOL Waterproof cement-based mortar for protecting and finishing concrete.

Lay blocks with mortar

Concrete for industrial floors

PROJECT PROFILE ON CEMENT CONCRETE HOLLOW BLOCKS

Monocouche Best Practice Guide. New-Build Housing Managing movement to avoid cracking

International Greenhouse Company

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Chapter 2 Basis of design and materials

ELASTOCEM. Technical features. Applications. Two-component flexible, waterproofing and protective cementitious grout.

Installation PowerPoint for Grasscrete Formers

NOTE: FOR PROJECTS REQUIRING CONTRACTOR MIX DESIGN, THE DESIGN PROCEDURES ARE SPECIFIED IN THE SPECIAL PROVISIONS OF THE CONTRACT.

Mineral waterproof coating PCI Dichtschlämme

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

INDEX DESCRIPTION MATERIALS APPROVAL OF SUBBASE COURSE CONSTRUCTION MEASUREMENT PAYMENT 6

Resurfacing Concrete. Page 1 of 5

Quick Guide to Floor Grinding

Free-Form Concrete Pool

Ultracolor CG2. Fast setting and drying grout for 2 to 20 mm joints, available in 26 colours; does not produce efflorescence

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

Otta Seal BACKGROUND GENERAL DESCRIPTION DESIGN ASPECTS. Category : Technical Information/On-carriageway/

Herringbone Pattern Flooring

ARDEX GUIDE SPECIFICATION ARDEX Exterior Concrete Repair & Resurfacing Polymer-Modified, Cement-Based, Patch & Horizontal Overlay Materials

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

The minimum reinforcement for the stem wall is the placement of:

MASONRY RESTORATION Lime Putty Mortar Repointing Guide

Seven. Easy Steps. Your Own Walkway, Without Mortar. or Concrete. to Installing. Driveway and Patio

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

1.5 Concrete (Part I)

AGREGADOS RECICLADOS MITOS Y REALIDADES

SECTION RESURFACING CAST IN PLACE CONCRETE

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

Minor Cracks in Horizontal Surfaces

Saint Gobain Gyproc India Ltd. (Formerly India Gypsum Ltd.)

Construction. Pre-Bagged Structural Waterproofing System. Product Description. Product Data. Tests. Form

Vanishing Lid Trays Construction Methods with Tile or Masonry

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

weber.floor 4660 Marine Elastic (EN)

Chimney systems ICOPAL WULKAN C/CI/C-eko/CI-eko

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER

Strength and Workability Characteristics of Concrete by Using Different Super Plasticizers

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

C. Section TESTING LABORATORY SERVICE.

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

Lesson 3. Portland Cement and Concrete

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

DIY GUIDE 10 EASY STEPS FOR TREATMENT OF RISING DAMP

M10. Cement based levelling/ wearing screeds. Scope. Contents. Reference documents. General guidance 2

Site sampling and testing of concrete

Ron Miedema Cement Contractor 1865 Pine Ridge ~ Jenison, MI 49428

TECHNICAL DATA SHEET. TOPECA, Lda Rua do Mosqueiro Cercal Ourém PORTUGAL. Tel.: Fax.:

RAW INSTALLATION GUIDE

MINIMUM QUALITY CONTROL PLAN FOR FIELD PLACEMENT OF LATEX MODIFIED MORTAR OR CONCRETE WEARING SURFACE

How to build a Pizza Oven in 4 days

A Study on the Flexural and Split Tensile Strengths of Steel Fibre Reinforced Concrete at High Temperatures

Shotcrete Quality Control and Testing for an Underground Mine in Canada

Proper use of the Rebound Hammer Updated to reflect the changes to ASTM C805

Sika Membran System For Sealing and Waterproofing Construction Gaps in Building Façades

Soils, Foundations & Moisture Control

FIXIT.CH. Aerogel Insulating Plaster System. Handling Guidelines. Easy to use. Mineral based W/mK BAUSTOFFE MIT SYSTEM

Section 300 Base Courses

G4 is browny translucent in colour and is effected by UV light. Therefore it is for internal use unless top coated to protect it from UV light

SECTION PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

Appendices. Appendices. A: Surfaces paved with stone paving slabs or precast concrete paving slabs. B: Cobbles. C: Stone Setts. D: Insitu Concrete

(T indicates a Tropicalised version with extended workability. No change has been made to the formulation)

SEE HOW TO MAKE LIME PLASTER WHY USE LIME? PATTI STOUTER, BUILD SIMPLE INC. FEBRUARY 2013

Sonotube Instructions for PreFab Sheds

CHAPTER 8 ROAD SURFACE PROPERTIES

SafetyBuletin. Concrete101 Aguidetounderstandingthequalitiesofconcrete andhowtheyaffectpumping

GUIDELINE FOR EXPOSED AGGREGATE FINISHES

Tecnoepo Flooring System 185

Technical Advice Note

EXPERIMENTAL INVESTIGATION ON BEHAVIOUR OF NANO CONCRETE

EXPERIMENT NO.1. : Vicat s apparatus, plunger

METHOD A10 (a) THE DETERMINATION OF THE IN-PLACE DRY DENSITY OF SOIL OR GRAVEL BY THE SAND REPLACEMENT METHOD

CHAPTER 12 C O N C R E T E W O R K S

MeltonStone Cast Stone Product Specifications

Guidelines For Sealing Groundwater Wells

Advancements in Permeable Pavements

September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

Epoxy Floor Coating Problem Solving Guide

Quality control: Annex-A.

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

DryWeight BulkVolume

BENTLEY ELEMENTS COLLECTION LVT

Elektra. Elektra. training. manual. manual. Coffee Grinder. Coffee Grinder SHARING THE PASSION

CAUSES, EVALUATION AND REPAIR OF CRACKS IN CONCRETE

CA-48 TECHNICAL SPECIFICATION

GUIDELINES FOR POLISHED CONCRETE FLOORS A Guide for Integrally Colored, Dyed and Stained Polished Floors

Surface Engineering Solutions Rebuild, Repair and Protect Industrial Equipment

Transcription:

Concrete and Pouring Techniques Case study HTC Sweden AB

General Concrete floors should be designed according to general requirements based on the activity and stress that the floor will be exposed to. The designer always has the responsibility for maintaining the calculations of the requirements for reinforcement and the choice of concrete quality.

General In order for the floor to obtain the optimal aesthetical appearance, the pouring and treatment of the concrete during laying is extremely important. When grinding, the external surface of the concrete is exposed and any defects or cracks and pores that occurred during pouring can be both time-consuming and difficult to correct.

General In connection with our addition, we wanted to plan already from the project stage for good pouring, and in the end as good a floor both functionally and aesthetically as possible. Therefore we collected knowledge both from the concrete supplier and the contractor to optimise the prerequisites.

General Below, in addition to reference pictures of our HTC Superfloor, you will also find a case study for the entire pouring process that can hopefully also be applied to other situations.

Preparatory work: The isolated subgrade with coarse gravel was topped with macadam (gravel 4-8 mm) which was carefully compacted. The surfaces were floated with a bullfloat to further level and compact the surface to avoid the risk of settling. Picture: Meticulous preparatory work beginning from the subgrade.

The reinforcing netting was fingerjointed and checked that it was placed at the correct level, 25-30 mm under the pouring level.

The floor was designed to be poured in two layers, the lower layer in standard concrete, 110 mm, with a top pouring, 70 mm, wet-on-wet with finer ballast aggregate to obtain as stone-rich an upper surface as possible.

The choice of two-layer construction was guided only by the design wishes of HTC Sweden AB. In the office section, the concrete was coloured with a red colouring pigment while the workshop section remained the standard grey.

The pouring was performed in stages of 300 500 sq. m. / day. The screed guides between the pouring zones were created with concrete screed guides, of the type BBK ban, with a steel top with a 7 mm plastic rim that was removed before the next pouring zone was begun. A concrete net was placed under the screed guide to prevent the concrete from flowing off. This type of screed guide has prepared holes for bolts of cc 150 mm.

The concrete mixer truck/pump should be placed in an appropriate location so that all or as large portions of the work area as possible can be reached. Before pouring from the truck, the concrete should be rotated for 7-10 minutes to obtain as even quality as possible and to avoid separation. The mixer should also be started during longer pouring pauses.

The first poured layer is pumped out and vibrated with a poker vibrator. Pouring thickness 110 mm with standard concrete of quality C28/35. (see separate preparation instructions with the concrete) Keep in mind: Internal vibration should always be performed on concrete with compression reinforcement located on the ground, as in this case. Always vibrate carefully close to guides, screed guides and forms.

Remember: Never transport the concrete with the vibrator, as this involves a risk for over vibration and separation.

The external surface was poured with laser assistance approx. 1 hr after the foundation. Pouring thickness approx. 70 mm. Concrete of a quality equivalent to C28/35 was used here, but with an aggregate of crushed material of max. 8 mm. We ensured that the crushed material was free from impurities and slate to obtain a good upper surface when grinding later. To minimize the plastic cracking (microcracks), polypropylene fibres were added to the concrete mixture (0.8 kg / c3).

Plastic fibres also have aesthetic benefits when the floor is ground and polished since the aggregate material remains more even in the concrete s upper surface. The fibres are however completely invisible in the polished surface.

When the concrete topping is vibrated with the poker vibrator, it is important to remember not to pull up the vibrator so quickly that larger cobble fractions from the base course are pulled up into the concrete topping.

A vibrating bullfloat is used to obtain the best surface evenness after pouring. To obtain the greatest possible evenness, floating should be performed in two directions perpendicular to each other. Remember: Do not walk in the concrete more than necessary. This minimises the risk that the ballast material is pressed down, which can create sections in the floor where only the cement paste is visible.

When the concrete has reached the correct bearing capacity, surface work is begun with a power trowel equipped with a floating disc. The procedure was performed carefully 2 times over the surface of the floor. Surfaces which are not accessible with the machine such as corners, joints, etc are floated by hand. Careful power floating is an important element that strengthens the concrete s upper layer through fibrillation and mixing of cement and sand particles, as well as making it more compact and vibrating the surface to make it as porous as possible.

After floating is completed, the surface is machine trowelled slightly to further strengthen the external surface. Remember: A surface which has been trowelled too hard will be more costly to grind.

We chose to finish trowelling with a wide blade that was pulled across the concrete to obtain the most porous upper surface possible. This treatment facilitates grinding since the surface is not hard-trowelled but still compact and pore-free.

When the concrete hydrates and begins to harden, internal strains in the concrete occur which will create shrinkage cracks.

To control the shrinkage, it is important to cut control joints in the floor as early as possible. Cutting should be performed in square boxes with a depth of approx. 20-25 mm or up to 30% of the pouring thickness, but it is important to never cut into the lower reinforcement. We used a machine named Soff-Cut. This is a dry-cutting method that can be begun already 1-2 hours after finishing. The joints are shallow and the early cutting minimises the risk for shrinkage cracks.

After the cutting, a plastic strip is placed into the cut joints to avoid chipping in the joints when grinding of the floor is begun. This plastic strip is removed from the joint later and is replaced with real jointing material.

Other things to consider: All too rapid and early drying of the concrete would cause shrinkage cracks, so to avoid this the surface is coated with water and covered with plastic sheeting. It is advisable to allow the surface to harden under water at least 3-4 days. The concrete should have reached more than 70% of its final strength before grinding begins. Depending on weather and temperature, we generally recommend that grinding begins at the earliest 5-7 days after pouring if the choice of concrete was a standard product such as the one we used. With material that hardens more quickly, grinding can begin even earlier.

As a result of rain and snow, such early grinding was not possible in our case and we were forced to wait until the building had a roof.